FINANCIAL ANALYSIS A. Introduction

Size: px
Start display at page:

Download "FINANCIAL ANALYSIS A. Introduction"

Transcription

1 Green Energy Corridor and Grid Strengthening Project (RRP IND 44426) FINANCIAL ANALYSIS A. Introduction 1. The proposed Green Energy Corridor and Grid Strengthening Project funds (i) a portion of India s Green Energy Corridor initiative to facilitate the transfer of renewable energy, and (ii) four high-voltage direct current terminals as part of increased interregional connectivity between India s western and southern regional grids. Asian Development Bank (ADB) funding consists of a $500 million sovereign-guaranteed loan to Power Grid Corporation of India Limited (POWERGRID). B. Methodology and Major Assumptions 2. Financial models. The project s financial analysis includes a project-level model and a corporate-level model. The project-level model takes detailed cost estimates for the specific project-funded assets, including the funding sources, and projects financial revenues generated from, and costs incurred related to, these assets. The corporate-level model evaluates POWERGRID s 3 year historical performance and projects results for 15 years. 3. Tariff-based revenue. POWERGRID comprises a portfolio of primarily regulated transmission assets, with each capitalized asset earning a tariff as defined by India s Central Electricity Regulatory Commission (CERC), the regulator. As a regulated asset, the project therefore benefits from both predictable revenue streams commonly found in project finance transactions, as well as from the strength of POWERGRID s overall balance sheet. POWERGRID may, in future years, undertake transmission projects that require bidding on a competitive basis. However, these projects would be implemented via subsidiaries and/or joint-venture companies (and this analysis makes no assumptions in respect to future POWERGRID activities). C. Project-Level Analysis and Risk Assessment 4. Project costs. The project s required capital investment is estimated in Indian rupees using mid-2015 price levels. Capital costs were estimated based on recent procurement data and market sources. Costs include civil works, equipment, land development, environment and social mitigation costs, project management cost, and taxes. Incremental operation and maintenance (O&M) costs are computed based on regulatory norms. 5. Financial internal rate of return. The project s financial viability was examined by comparing the incremental costs and benefits. The financial internal rate of return (FIRR) is calculated at 5.76% in real terms (10.72% on a nominal basis), which compares favorably with the estimated weighted average of cost of capital (WACC) value of 3.66% in real terms (7.78% on a nominal basis), thus substantiating the project s financial viability Project risk assessment. POWERGRID s project-level returns are based on the return on equity (ROE) and capital cost allowed by CERC regulations, therefore a reduction of the ROE in the CERC tariff guidelines or disallowance of any project cost component could negatively affect returns. However, the risk is considered limited due to National Tariff Policy provisions that specify a full cost pass-through, as well as the regulator s past record. 2 1 The WACC is computed based on a pretax cost of capital of the ADB sovereign loan of 3.5%, applicable rates for other corporate loans, local bonds at 8.5%, and a cost of equity at 15.5%. 2 National Tariff Policy provision 5.3 (a) to (h) stipulates performance-based cost of service regulation that assures adequate return on investment and complete pass-through of costs.

2 2 7. Sensitivity analysis. Variables considered for the sensitivity analysis are (i) 20% increase in capital costs, (ii) 20% increase in O&M costs, (iii) 1-year completion delay and withdrawal of the 0.5% incentive for timely completion, and (iv) 1% reduction in ROE. Increases in capital and O&M costs and completion delays have a marginal impact on the FIRR, as these are passed through in tariffs, though they would have minor cash flow implications, since tariff adjustments are made post facto. The FIRR is sensitive to changes in the ROE or incentive elements that directly affect profitability. Even in a worst-case scenario, the lowest FIRR remains 5.21% and compares favorably with the estimated WACC of 3.66%, further substantiating the project s financial viability (Table 1). Table 1: Project-Level Sensitivity Analysis Item FIRR a (%) FNPV a (Rs million) Base case ,722.4 Scenario A: Base case plus 20% increase in capital cost ,239.7 Scenario B: Scenario A plus 20% increase O&M costs ,585.9 Scenario C: Scenario B plus 1-year completion delay, no incentive for timely completion ,786.7 Scenario D: Scenario C plus 1% reduction in return on equity ,743.2 FIRR = financial rate of return, FNPV = financial net present value, O&M = operation and maintenance. a Calculated in real terms. Source: Asian Development Bank estimates. D. Corporate-Level Financial Analysis and Risk Assessment 8. Historical corporate performance. POWERGRID s revenues increased at a compound annual growth rate of 15.5% from Rs133 billion in 2013 to Rs178 billion in 2015, while total assets increased from Rs1,111 billion in 2013 to Rs1,583 billion in POWERGRID is implementing several large projects, and revenues will increase as projects are completed. Since POWERGRID receives both full recovery of allowed project costs and a defined ROE, its earnings before interest, tax, depreciation, and amortization margin has remained above 85%, and the net profit margin has been about 30% in each of the past three financial years. Table 2: Historical Audited Corporate Financial Indicators (Rs billion) Item (Year Ended 31 March) Total Assets 1, , ,583.0 Total Liabilities (without Shareholder's Equity) , ,201.3 Total Shareholder s Equity Total Revenue EBITDA FCF a Year Average EBITDA Margin (%) DSCR b 1.7x 1.6x 2.0x 1.8x Percent of Cash from Internal Sources (%) Current FCF to DSR c 1.6x 1.6x 1.5x 1.6x Average FCF to DSR 1.7x 1.4x 1.6x 1.6x Debt-to-Equity Ratio 2.4:1 2.2:1 2.3:1 2.3:1 ADB = Asian Development Bank, DSCR = debt service coverage ratio, DSR = debt service requirement, EBITDA = earnings before interest, taxes, depreciation, and amortization, FCF = free cash flows. a FCF = the sum of all revenues less the sum of all operating expenses including finance charges. b DSCR = earnings before interest, tax, and depreciation divided by the sum of (i) principal repayments and (ii) interest and finance charges, net of amounts charged during construction. c DSR = aggregate of all repayments and interest on debt, net of capitalized interest. Source: POWERGRID; ADB analysis. 9. POWERGRID maintains a corporate debt-to-equity ratio of approximately 70:30, or 2.3

3 3 times, since CERC regulations allow POWERGRID to earn the ROE on a maximum 30% of capital costs. Projects are financed under a similar debt-to-equity ratio. POWERGRID has been able to finance at least 20% of capital expenditure from internal sources, and the debt service coverage ratio (DSCR) has remained above 1.5 times in the past three years. Free cash flow to debt service requirement has been 1.6 times on average for the past three years. 10. Projected corporate performance. POWERGRID s projected financial indicators from are in Table 3. Extended forecasts through 2030 are in Table 5. Its capital investment plans are forecast to increase total revenue from Rs177.8 billion in 2015 to Rs422.1 billion by Table 3: Projected Corporate Financial Indicators (Rs billion) Item (Year Ended 31 March) to 2030 Total Assets 1, , , , ,543.1 See Table 5 Total Liabilities 1, , , , ,807.9 Total Shareholder s Equity Total Revenue EBITDA FCF year Average EBITDA Margin (%) DSCR 2.4x 2.2x 2.2x 2.1x 2.3x 2.4x Percent of Cash from Internal Sources (%) Current FCF to DSR 1.5x 1.3x 1.7x 1.6x 1.5x 1.7x Average FCF to DSR 1.4x 1.5x 1.6x 1.6x 1.5x 1.7x Debt-to-Equity Ratio 2.3:1 2.3:1 2.2:1 2.1:1 1.9:1 1.3:1 ADB = Asian Development Bank, DSCR = debt service coverage ratio, DSR = debt service requirement, EBITDA = earnings before interest, taxes, depreciation, and amortization, FCF = free cash flows. Source: ADB estimates. 11. Based on POWERGRID s plans, capital expenditure is expected to reach a maximum annual amount of Rs291 billion in 2019, financed by a combination of debt and equity in a debt-to-equity ratio of about 70:30, or 2.3 times. Cumulative capital expenditure from 2016 to 2020 is Rs1,016.6 billion, after which projects are completed and no major expenditures are planned; liabilities also start reducing after reaching a maximum of Rs1,807.9 billion in During the loan term, POWERGRID s average DSCR is calculated to be 2.4 times, and the minimum is 2.0 times. POWERGRID is able to finance at least 20% and on average 51% of capital expenditure from internal sources from 2016 to These projections indicate that POWERGRID s financial position will remain strong during peak capital expenditure and with maximum long-term liabilities. 13. Sources of financing. POWERGRID is expected to have continued access to several financing sources, including domestic and international banks, capital markets, and multilateral and other development financial institutions. In the financial projections, it is assumed that POWERGRID will maintain a debt-to-equity ratio of about 70:30 and that foreign currency debt will represent a maximum 33% of debt financing and 23% of total financing. 14. Foreign currency debt. CERC regulations allow POWERGRID to hedge foreign exchange exposure based on its own approved hedging policy or recover foreign exchange rate variations from its customers without further regulatory approval. These variations are calculated and collected from customers on a quarterly basis after projects are completed. 15. Corporate-level risk assessment. Risk factors that may impact future corporate-level

4 4 financial performance, and corresponding risk mitigators, are described and assessed in the Risk Assessment and Risk Management Plan (accessible in the Linked Documents in Appendix 2). E. Sensitivity Analysis 16. Sensitivity analyses determined the impact on compliance with financial covenants under certain scenarios that represent potential risks, such as delays that could prevent POWERGRID from achieving the incentive ROE for timely completion, or cost overruns that are not ultimately regulator-approved. Other scenarios include a reduction in the tariff-defined ROE rate, non-payment of receivables, and foreign exchange and interest rate variations. 17. The sensitivity analysis shows that even in a worst-case scenario, with a combination of delays, currency depreciation and regulatory changes, the DSCR remains above 1.0. Moreover, given the tariff s cost-recovery nature, scenarios such as currency depreciation, interest rate increases, operating cost increases, and approved cost overruns have a minimal impact on key financial ratios and covenants. POWERGRID s collection record with customers has been robust, with average accounts receivable representing less than 11% of annual revenue and overdue accounts representing less than 2% in the past three years. While this is expected to continue, scenarios were considered where the average accounts receivable increases to 90 days, or a customer with 10% of revenue defaults on 50% of amounts due (and POWERGRID is unable to recover this amount). In this case, the DSCR remains above 1.0. A summary of the analyses performed on key financial covenants is in Table 4. Scenarios Table 4: Financial Ratios Sensitivities Minimum DSCR Key Financial Ratios Average DSCR Maximum Debt-to- EBITDA Cash from Internal Sources (%) (Minimum) Current FCF:DSR a (Minimum) Average FCF:DSR b Maximum Debt:Equity Ratio Base case scenario 2.1x 2.4x 4.6x x 1.4x 2.3:1 Delays and no incentive ROE c 2.1x 2.4x 4.8x x 1.4x 2.4:1 20% project cost overrun d 2.0x 2.4x 4.7x x 1.4x 2.3:1 1% reduction in tariff ROE starting x 2.4x 4.6x x 1.4x 2.3:1 Tariff O&M escalation lowered to 1% in 2.1x 2.4x 4.6x x 1.4x 2.3: e 5% (net) annual currency depreciation 2.1x 2.4x 4.6x x 1.4x 2.3:1 1% increase in LIBOR throughout 2.1x 2.4x 4.6x x 1.4x 2.3:1 1% increase in Indian rupee rates 2.0x 2.4x 4.5x x 1.3x 2.3:1 throughout Increase of receivables (from 45 to x 2.3x 4.6x x 1.3x 2.3:1 days) Default of largest customer f 1.9x 2.2x 5.2x x 1.2x 2.4:1 Worst case scenario g 2.0x 2.3x 4.8x x 1.3x 2.4:1 ADB = Asian Development Bank, DSCR = debt service coverage ratio, DSR = debt service requirements, EBITDA = earnings before interest, taxes, depreciation, and amortization, FCF = free cash flows, LIBOR = London interbank offered rate, O&M = operation and maintenance, ROE = return on equity. a Ratio of FCF to DSR for the current financial year. b Ratio of FCF to DSR, in the case of an average of the previous, current, and following financial year. c Assumes the unlikely scenario where all future projects are delayed, and while costs overruns are approved by Central Electricity Regulatory Commission (CERC), all future revenues are delayed and ROE of 0.5% is not received. d Assumes the unlikely scenario where all future projects are delayed and CERC approves only 50% of cost overruns, while the remainder is not allowed for recovery via the tariff. e Current tariff regulations permit annual inflation rate of 3.32%. f Assumes largest customer currently represents approximately 10% of annual revenues. g One year delay in project completion, 5% (net) annual rupee depreciation and tariff ROE reduced by 1% from Source: ADB estimates.

5 5 Table 5: Historical ( ) and Projected ( ) Corporate-Level Financials Balance Sheet Actual Projected Fixed assets , , , , , , , , , , , , , , , , ,280.4 Other non-current assets Current assets , , , , , ,678.4 Total Assets 1, , , , , , , , , , , , , , , , , ,071.4 Current liabilities Other non-current liabilities Long-term debt (domestic) Long-term debt (foreign) Total long-term debt , , , , , , , , , Total Liabilities , , , , , , , , , , , , , , , , ,344.7 Share capital Reserves and surplus , , , , , , ,674.4 Total Shareholder s Equity , , , , , , , ,726.7 Income Statement Actual Projected Transmission sales Other income Revenue Total operating expenses EBITDA Finance costs Depreciation & amortization Taxes Net profit Transmission sales Cash Flow Statement Actual Projected Profit before tax Cash from operations Cash from investments (219.5) (263.8) (238.4) (201.3) (180.1) (276.3) (291.0) (67.9) 21.2 (15.1) 0.4 (14.8) (10.1) (29.1) (29.1) (24.8) (24.7) (24.6) Cash from financing (15.4) (102.3) (224.1) (176.0) (205.5) (207.2) (216.1) (212.5) (191.3) (187.5) (175.7) (168.5) Net change in cash (6.7) 27.6 (23.5) (3.2) Final cash balance , , , , ,548.7 Free cash flows Cash from internal sources Debt service requirement EBITDA = earnings before interest, taxes, depreciation, and amortization. Source: Asian Development Bank estimates.

Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS. A. Introduction

Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS. A. Introduction Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS A. Introduction 1. The financial analysis of the Tanahu Hydropower Project was carried out in accordance with Financial Management and Analysis

More information

FINANCIAL ANALYSIS. A. Background

FINANCIAL ANALYSIS. A. Background SASEC Second Bangladesh India Electrical Grid Interconnection Project (RRP BAN 44192) A. Background FINANCIAL ANALYSIS 1. The South Asia Subregional Economic Cooperation (SASEC) Second Bangladesh India

More information

FINANCIAL ANALYSIS. A. Methodology and Major Assumptions

FINANCIAL ANALYSIS. A. Methodology and Major Assumptions Second Green Power Development Project (RRP BHU 44444) FINANCIAL ANALYSIS 1. The project s financial analysis was carried out in accordance with the Financial Management and Analysis of Project Guidelines

More information

FINANCIAL ANALYSIS OF TRANCHE 1

FINANCIAL ANALYSIS OF TRANCHE 1 Town Electrification Investment Program (RRP PNG 41504) FINANCIAL ANALYSIS OF TRANCHE 1 A. Financial Analysis 1. Introduction 1. The financial analysis of the project covers the first three subprojects

More information

FINANCIAL ANALYSIS. 3. Assumptions. The following assumptions were used in carrying out the financial analysis:

FINANCIAL ANALYSIS. 3. Assumptions. The following assumptions were used in carrying out the financial analysis: Java Bali 500-Kilovolt Power Transmission Crossing Project (RRP INO 42362) FINANCIAL ANALYSIS 1. General Methodology. Financial analysis of the project has been undertaken in accordance with Asian Development

More information

FINANCIAL ANALYSIS: PROJECT 1

FINANCIAL ANALYSIS: PROJECT 1 Green Power Development and Energy Efficiency Improvement Investment Program (RRP SRI 47037) A. Background and Rationale FINANCIAL ANALYSIS: PROJECT 1 1. Project 1 of the Green Power Development and Energy

More information

FINANCIAL ANALYSIS. A. Financial Capacity Assessment of MWSS

FINANCIAL ANALYSIS. A. Financial Capacity Assessment of MWSS Angat Water Transmission Improvement Project (RRP PHI 46362-002) FINANCIAL ANALYSIS 1. The project is estimated to be $134.0 million of which $98.4 million is for the design and build contract, $6.0 million

More information

South Asia Subregional Economic Cooperation Power System Expansion Project (RRP NEP 44219) FINANCIAL ANALYSIS

South Asia Subregional Economic Cooperation Power System Expansion Project (RRP NEP 44219) FINANCIAL ANALYSIS South Asia Subregional Economic Cooperation Power System Expansion Project (RRP NEP 44219) A. Approach FINANCIAL ANALYSIS 1. Financial analysis of the project was carried out in accordance with the Financial

More information

FINANCIAL ANALYSIS. A. Introduction

FINANCIAL ANALYSIS. A. Introduction Solar Power Development Project (RRP SOL 48346) A. Introduction FINANCIAL ANALYSIS 1. The scope of the financial analysis for the Solomon Islands Solar Power Development project includes (i) an estimate

More information

FINANCIAL ANALYSIS. 2. Taking into account the financial costs, the total amount needed to finance the Padma Bridge Project is presented in Table 1.

FINANCIAL ANALYSIS. 2. Taking into account the financial costs, the total amount needed to finance the Padma Bridge Project is presented in Table 1. Padma Multipurpose Bridge Project (RRP BAN 35049) FINANCIAL ANALYSIS A. Introduction 1. A financial analysis assessed the viability of the proposed project investment based on the capacity of Bangladesh

More information

FINANCIAL ANALYSIS. A. Introduction

FINANCIAL ANALYSIS. A. Introduction Urban Water Supply and Wastewater Management Investment Project (RRP FIJ 491-2) A. Introduction FINANCIAL ANALYSIS 1. The Asian Development Bank (ADB) Urban Water Supply and Wastewater Management Investment

More information

FINANCIAL ANALYSIS. A. Introduction

FINANCIAL ANALYSIS. A. Introduction FINANCIAL ANALYSIS Henan Sustainable Livestock Farming and Product Safety Demonstration Project (RRP PRC 46081) A. Introduction 1. A financial analysis was conducted following relevant Asian Development

More information

FINANCIAL ANALYSIS. 1. Introduction and Methodology

FINANCIAL ANALYSIS. 1. Introduction and Methodology Third Urban Governance and Infrastructure Improvement (Sector) Project (RRP BAN 39295) 1. Introduction and Methodology FINANCIAL ANALYSIS 1. The project finances basic urban services improvements and aims

More information

FINANCIAL ANALYSIS. A. Introduction

FINANCIAL ANALYSIS. A. Introduction A. Introduction Air Quality Improvement in the Greater Beijing Tianjin Hebei Region China National Investment and Guaranty Corporation s Green Financing Platform Project (RRP PRC 50096) FINANCIAL ANALYSIS

More information

FINANCIAL ANALYSIS. Table 1: Project Outputs Output Subcomponents Type of Analysis Enshi Wastewater Enshi Hongmiao WWTP Enshi Dashaba WWTP

FINANCIAL ANALYSIS. Table 1: Project Outputs Output Subcomponents Type of Analysis Enshi Wastewater Enshi Hongmiao WWTP Enshi Dashaba WWTP Hubei Enshi Qing River Upstream Environment Rehabilitation Project (RRP PRC 47048) FINANCIAL ANALYSIS A. Introduction 1. The financial analysis of the project was carried out in accordance with the Asian

More information

PROGRAM EXPENDITURE AND FINANCING ASSESSMENT

PROGRAM EXPENDITURE AND FINANCING ASSESSMENT Sustainable Energy Access in Eastern Indonesia Electricity Grid Development Program (RRP INO 50016) PROGRAM EXPENDITURE AND FINANCING ASSESSMENT 1. The program expenditure and financing assessment reviews

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Bihar New Ganga Bridge Project (RRP IND 48373) ECONOMIC AND FINANCIAL ANALYSIS A. Introduction 1. The proposed project is to build a new six-lane bridge across the Ganges River near Patna in the state

More information

FINANCIAL ANALYSIS. A. Introduction

FINANCIAL ANALYSIS. A. Introduction Additional Financing of Agriculture and Rural Development Project (RRP MON 39229) FINANCIAL ANALYSIS A. Introduction 1. The financial analysis of the additional financing of the Agriculture and Rural Development

More information

Wind Project Financing. Targets, Barriers & Challenges, Elements of Financing, Recommendations for Financing

Wind Project Financing. Targets, Barriers & Challenges, Elements of Financing, Recommendations for Financing Wind Project Financing Targets, Barriers & Challenges, Elements of Financing, Recommendations for Financing 1 Coverage Background Debt Financing Elements & Barriers Equity Financing Elements & Barriers

More information

Trung Son Hydropower Project. Financial Analysis

Trung Son Hydropower Project. Financial Analysis Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized The World Bank Trung Son Hydropower Project Financial Analysis Final Report February

More information

FINANCIAL ANALYSIS. A. Kathmandu Upatyaka Khanepani Limited

FINANCIAL ANALYSIS. A. Kathmandu Upatyaka Khanepani Limited Kathmandu Valley Wastewater Management Project (RRP NEP 43524) FINANCIAL ANALYSIS A. Kathmandu Upatyaka Khanepani Limited 1. Kathmandu Upatyaka Khanepani Limited (KUKL) is a public company registered under

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Railway Rolling Stock Project (RRP BAN 49094) ECONOMIC AND FINANCIAL ANALYSIS A. Introduction 1. The project involves procurement of 214 meter gauge (MG) passenger carriages, 50 broad gauge (BG) passenger

More information

LOAN AGREEMENT (Ordinary Operations) (National Grid Improvement Project) between POWER GRID CORPORATION OF INDIA LIMITED. and ASIAN DEVELOPMENT BANK

LOAN AGREEMENT (Ordinary Operations) (National Grid Improvement Project) between POWER GRID CORPORATION OF INDIA LIMITED. and ASIAN DEVELOPMENT BANK LOAN NUMBER 2787-IND LOAN AGREEMENT (Ordinary Operations) (National Grid Improvement Project) between POWER GRID CORPORATION OF INDIA LIMITED and ASIAN DEVELOPMENT BANK DATED 30 MARCH 2012 IND 44426 LOAN

More information

Karnataka Integrated Urban Water Management Investment Program (RRP IND 43253) ECONOMIC ANALYSIS

Karnataka Integrated Urban Water Management Investment Program (RRP IND 43253) ECONOMIC ANALYSIS Karnataka Integrated Urban Water Management Investment Program (RRP IND 43253) A. Introduction ECONOMIC ANALYSIS 1. Karnataka. Karnataka is one of the top ten states in India by gross domestic product

More information

By S K Agrawal ED (Commercial) NHPC Ltd.1

By S K Agrawal ED (Commercial) NHPC Ltd.1 By S K Agrawal ED (Commercial) NHPC Ltd.1 Need for Renovation & Modernisation of HEPs Advantages of R&M of old Power Stations Govt. policies on R&M Regulatory Provisions & Commercial aspects Overview of

More information

RATING METHODOLOGY FOR DEBT ISSUES OF TOLL ROAD PROJECTS

RATING METHODOLOGY FOR DEBT ISSUES OF TOLL ROAD PROJECTS RATING METHODOLOGY FOR DEBT ISSUES OF TOLL ROAD PROJECTS CARE s rating methodology for debt issues of road projects (RPs) is designed to facilitate appropriate credit risk assessment, keeping in view the

More information

Criteria for Rating power transmission projects. October 2016

Criteria for Rating power transmission projects. October 2016 Criteria for Rating power transmission projects October 2016 Criteria contacts Pawan Agrawal Chief Analytical Officer CRISIL Ratings Email: pawan.agrawal@crisil.com Sameer Charania Director Rating Criteria

More information

ADB s Local Currency Loan Product. Responding to Borrowers Evolving Needs

ADB s Local Currency Loan Product. Responding to Borrowers Evolving Needs ADB s Local Currency Loan Product Responding to Borrowers Evolving Needs Contents Introduction v Rationale for the Local Currency Loan Product 1 Eligible Borrowers 4 Main Features of the Local Currency

More information

OUTLINE TERMS OF REFERENCE FOR CONSULTANTS

OUTLINE TERMS OF REFERENCE FOR CONSULTANTS Strengthening Public Financial Resource Management through Information and Communication Systems Technology Systems (TRTA MON 51084) OUTLINE TERMS OF REFERENCE FOR CONSULTANTS 1. The transaction technical

More information

Rating Methodology for Wind Power Producers

Rating Methodology for Wind Power Producers RATING METHODOLOGY April 2017 ICRA Rating Feature ICRA Rating Feature This rating methodology describes ICRA s approach towards assessing credit risk of wind power producers. It aims to help issuers, investors

More information

Guidelines for the Financial Governance and Management of Investment Projects Financed by the Asian Development Bank

Guidelines for the Financial Governance and Management of Investment Projects Financed by the Asian Development Bank Guidelines for the Financial Governance and Management of Investment Projects Financed by the Asian Development Bank Effective January 2002 Foreword Financial analysis of ADB projects has been conducted

More information

India: Power Grid Transmission (Sector) Project

India: Power Grid Transmission (Sector) Project Completion Report Project Number: 38492-013 Loan Number: 2152 July 2017 India: Power Grid Transmission (Sector) Project This document is being disclosed to the public in accordance with ADB s Public Communications

More information

FINANCIAL ANALYSIS. Second Greater Mekong Subregion Tourism Infrastructure for Inclusive Growth Project (RRP REG 49387)

FINANCIAL ANALYSIS. Second Greater Mekong Subregion Tourism Infrastructure for Inclusive Growth Project (RRP REG 49387) Second Greater Mekong Subregion Tourism Infrastructure for Inclusive Growth Project (RRP REG 49387) FINANCIAL ANALYSIS 1. The financial analysis follows Asian Development Bank (ADB) guidelines. 1 Subprojects

More information

Report and Recommendation of the President to the Board of Directors

Report and Recommendation of the President to the Board of Directors Report and Recommendation of the President to the Board of Directors Project Number: 32254-02 September 2008 Proposed Supplementary Loan India: Urban Water Supply and Environmental Improvement in Madhya

More information

Rs Billion Short Term Debt Programme. (Series IX & X)

Rs Billion Short Term Debt Programme. (Series IX & X) CRISIL Limited CRISIL s RatingRationale Power Grid Corporation of India Limited OCTOBER 2005 Rs. 20 Billion Bonds Programme Rs. 6.50 Billion Short Term Debt Programme (Enhanced from Rs. 6 Billion) Rs.

More information

India Infrastructure Debt Fund: A Concept Paper

India Infrastructure Debt Fund: A Concept Paper India Infrastructure Debt Fund: A Concept Paper - Gajendra Haldea Creation of world-class infrastructure has been recognised as a key priority and a necessary condition for sustaining the growth momentum

More information

Project Finance Modelling For Renewable Energy

Project Finance Modelling For Renewable Energy Project Finance Modelling For Renewable Energy A 3-Day Programme This course can be presented in-house for you on a date of your choosing The Banking and Corporate Finance Training Specialist Course Overview

More information

Overview of the framework

Overview of the framework Overview of the framework Need for a framework Economic growth and trade expansion in recent years have enhanced the relevance of port sector as a critical element in globalisation of the Indian economy.

More information

TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Tariff Order No 1 of 2010 dated

TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Tariff Order No 1 of 2010 dated TAMIL NADU ELECTRICITY REGULATORY COMMISSION Tariff Order No 1 of 2010 dated 27.05.2010 Sl.No Description Summary of Regulations 1 Title Tariff order for projects covered by Jawaharlal Nehru National Solar

More information

SUGGESTED SOLUTIONS Strategic Financial Management. CA Professional (Strategic Level II) Examination December 2013

SUGGESTED SOLUTIONS Strategic Financial Management. CA Professional (Strategic Level II) Examination December 2013 SUGGESTED SOLUTIONS 21404 Strategic Financial Management CA Professional (Strategic Level II) Examination December 2013 THE INSTITUTE OF CHARTERED ACCOUNTANTS OF SRI LANKA All Rights Reserved Answer No.

More information

Rating Methodology - Toll Road Projects [In supersession of Rating Methodology - Toll Road Projects issued in June 2017]

Rating Methodology - Toll Road Projects [In supersession of Rating Methodology - Toll Road Projects issued in June 2017] [In supersession of Rating Methodology - Toll Road Projects issued in June 2017] CARE s rating methodology for debt issues of road projects is designed to facilitate appropriate credit risk assessment,

More information

LOAN AGREEMENT (Ordinary Operations) (National Power Grid Development Investment Program Tranche 2) between POWER GRID CORPORATION OF INDIA LIMITED

LOAN AGREEMENT (Ordinary Operations) (National Power Grid Development Investment Program Tranche 2) between POWER GRID CORPORATION OF INDIA LIMITED LOAN NUMBER 2510-IND LOAN AGREEMENT (Ordinary Operations) (National Power Grid Development Investment Program Tranche 2) between POWER GRID CORPORATION OF INDIA LIMITED and ASIAN DEVELOPMENT BANK DATED

More information

COMPONENTS OF REVENUE REQUIREMENT

COMPONENTS OF REVENUE REQUIREMENT COMPONENTS OF REVENUE REQUIREMENT A typical Tariff Application of Discom has to include Demand Forecast Annual Revenue Requireme nt to meet the Cost of Supply to cater to the demand Power Procurement (Self+Purchase)

More information

CASE No. 150 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Vidarbha Industries Power Limited ORDER

CASE No. 150 of Coram. Shri. Azeez M. Khan, Member Shri. Deepak Lad, Member. Vidarbha Industries Power Limited ORDER Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 022-22163964/65/69 Fax: 022-22163976 E-mail: mercindia@merc.gov.in

More information

BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL)

BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL) BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL) REVISED PETITION FOR APPROVAL OF TRUE UP OF FY 2015-16 & FY 2016 17 AND PROVISIONAL TRUE UP of FY 2017-18

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Coral Reef Rehabilitation and Management Program Coral Triangle Initiative Project (RRP INO 46421) A. Approach and Methodology ECONOMIC AND FINANCIAL ANALYSIS 1. The economic and financial analysis of

More information

LONG OPPORTUNITY: LCI (NYSE) LANNETT CORPORATION: STRUCTURAL BENEFITS OF KREMMERS ACQUISITION: 100% UPSIDE

LONG OPPORTUNITY: LCI (NYSE) LANNETT CORPORATION: STRUCTURAL BENEFITS OF KREMMERS ACQUISITION: 100% UPSIDE LONG OPPORTUNITY: LCI (NYSE) LANNETT CORPORATION: STRUCTURAL BENEFITS OF KREMMERS ACQUISITION: 100% UPSIDE Executive Summary Lannett Corporation ( LCI ) shareholders have a unique opportunity to realize

More information

Bhopal: Dated 5 th May 2006

Bhopal: Dated 5 th May 2006 Bhopal: Dated 5 th May 2006 No. 1192/MPERC/2006. In exercise of the powers conferred by section 181 (g) read with section 32(3) of the Electricity Act, 2003 enacted by the parliament, the Madhya Pradesh

More information

THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA. NOTIFICATION Shimla, the 22 nd November, 2018

THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA. NOTIFICATION Shimla, the 22 nd November, 2018 THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA NOTIFICATION Shimla, the 22 nd November, 2018 No. HPERC-F(1)-1/2018- Whereas section 61 of the Electricity Act, 2003 (36 of 2003), provides

More information

INTEREST RATE SWAP POLICY

INTEREST RATE SWAP POLICY INTEREST RATE SWAP POLICY August 2007 Table of Contents I. Introduction... 1 II. Scope and Authority... 1 III. Conditions for the Use of Interest Rate Swaps... 1 A. General Usage... 1 B. Maximum Notional

More information

Superseding Sheet No. 89 REVISED SHEET NO. 89 Effective April 9, 2012 Effective June 1, 2013 RATE ADJUSTMENT MECHANISM PROVISION

Superseding Sheet No. 89 REVISED SHEET NO. 89 Effective April 9, 2012 Effective June 1, 2013 RATE ADJUSTMENT MECHANISM PROVISION Superseding Sheet No. 89 REVISED SHEET NO. 89 Effective April 9, 2012 Effective June 1, 2013 RATE ADJUSTMENT MECHANISM PROVISION Rate Adjustment Mechanism ( RAM ) Provision Purpose This mechanism is subject

More information

New Development Bank. Policy on Financial Management and Financial Analysis, and Economic Analysis of Projects

New Development Bank. Policy on Financial Management and Financial Analysis, and Economic Analysis of Projects New Development Bank Policy on Financial Management and Financial Analysis, and Economic Analysis of Projects Owner: Operations Division Approved Date: January 21, 2016 Policy on Financial Management and

More information

Perspective on Financing Wind Energy Projects. June 16, 2016

Perspective on Financing Wind Energy Projects. June 16, 2016 Perspective on Financing Wind Energy Projects June 16, 2016 Agenda 2 1 Risk Matrix 3 Context Setting Way Forward KEY SEGMENTS IN THIS PRESENTATION 3 Indian Energy Sector Landscape Bank Lending Sector wise

More information

Tariff based bidding process for transmission: The first Indian experience

Tariff based bidding process for transmission: The first Indian experience Tariff based bidding process for transmission: The first Indian experience Ajay Talegaonkar and Ravinder Abstract There is policy shift towards private investment in the electricity supply industry. In

More information

RATING METHODOLOGY June Rating Methodology for Solar Power Producers. ICRA Rating Feature. Overview

RATING METHODOLOGY June Rating Methodology for Solar Power Producers. ICRA Rating Feature. Overview RATING METHODOLOGY June 2017 ICRA Rating Feature This rating methodology describes ICRA s approach towards assessing credit risk of solar power producers. It aims to help issuers, investors and other interested

More information

Notice of Entering into a Compact with the Federal Democratic Republic of Nepal

Notice of Entering into a Compact with the Federal Democratic Republic of Nepal This document is scheduled to be published in the Federal Register on 09/28/2017 and available online at https://federalregister.gov/d/2017-20847, and on FDsys.gov BILLING CODE 921103 MILLENNIUM CHALLENGE

More information

Cash and cash equivalents 619,525 Trade accounts receivable and others 951,653 Total 1,571,178 Net $ 229,209

Cash and cash equivalents 619,525 Trade accounts receivable and others 951,653 Total 1,571,178 Net $ 229,209 11. Derivative financial instruments The Entity has exposure to market risks, operating risks and financial risks arising from the use of financial instruments that involves interest rates, credit risks,

More information

PEER GROUPS CMP MARKET CAP EPS P/E (X) P/BV(X) DIVIDEND Company Name (Rs.) Rs. in mn. (Rs.) Ratio Ratio (%)

PEER GROUPS CMP MARKET CAP EPS P/E (X) P/BV(X) DIVIDEND Company Name (Rs.) Rs. in mn. (Rs.) Ratio Ratio (%) BUY CMP 244.05 Target Price 280.00 KALPATARU POWER TRANSMISSION LTD. Result Update (PARENT BASIS): Q3 FY15 March 2 nd 2015 ISIN: INE220B01022 Index Details Stock Data Sector Heavy Electrical Equipment

More information

Leading Diversified Renewable Energy Generation Company

Leading Diversified Renewable Energy Generation Company Leading Diversified Renewable Energy Generation Company Disclaimer Certain statements in this presentation concerning our future growth prospects areforward looking statements, which involve a number of

More information

India: Supporting the Second West Bengal Development Finance Program

India: Supporting the Second West Bengal Development Finance Program Second West Bengal Development Finance Program (RRP IND 49209) Technical Assistance Report Project Number: 49209-001 Transaction Technical Assistance (TRTA) August 2017 India: Supporting the Second West

More information

1200kV AC Sub-station at Bina. Delivering Smart Grid/ Distribution Solutions `

1200kV AC Sub-station at Bina. Delivering Smart Grid/ Distribution Solutions ` 1200kV AC Sub-station at Bina Delivering Smart Grid/ Distribution Solutions ` Press Meet 12 th February, 2013 Disclaimer By attending the meeting where this presentation is made, or by reading the presentation

More information

CASE STUDIES: HISTORICAL BACKDROP TO NONSOVEREIGN INTERVENTIONS

CASE STUDIES: HISTORICAL BACKDROP TO NONSOVEREIGN INTERVENTIONS State-Owned Enterprise Engagement and Reform, Linked Document 6 CASE STUDIES: HISTORICAL BACKDROP TO NONSOVEREIGN INTERVENTIONS A. Power Grid Corporation of India Limited (POWERGRID) 1. POWERGRID was established

More information

PROJECT PREPARATION TECHNICAL ASSISTANCE

PROJECT PREPARATION TECHNICAL ASSISTANCE 12 Appendix 4 A. Justification PROJECT PREPARATION TECHNICAL ASSISTANCE 1. A regional project preparatory technical assistance (R-PPTA) is required to prepare the Pacific Renewable Energy Investment Facility

More information

Criteria for rating wind power projects

Criteria for rating wind power projects Criteria for rating wind power projects Executive Summary CRISIL has outstanding ratings on 21 wind power project companies as on June 30, 2015. Wind power projects depend primarily on wind speeds for

More information

Superseding Sheet No. 96 REVISED SHEET NO. 96 Effective May 4, 2012 Effective June 1, 2013

Superseding Sheet No. 96 REVISED SHEET NO. 96 Effective May 4, 2012 Effective June 1, 2013 Superseding Sheet No. 96 REVISED SHEET NO. 96 Effective May 4, 2012 Effective June 1, 2013 RATE ADJUSTMENT MECHANISM PROVISION Rate Adjustment Mechanism ( RAM ) Provision Purpose This mechanism is subject

More information

Distribution Tariff Determination and Rationalization

Distribution Tariff Determination and Rationalization Department of Industrial and Management Engineering Indian Institute of Technology Kanpur 3 rd Capacity Building Programme for Officers of Electricity Regulatory Commissions 23 28 August, 2010 Forum of

More information

OPERATIONAL POLICY ON FINANCING

OPERATIONAL POLICY ON FINANCING OPERATIONAL POLICY ON FINANCING January 2016 (updated March 21, 2017) I. PURPOSE; CONTENTS 1.1. Purpose. The purpose of this Operational Policy on Financing (Policy) is to set out the Bank s policy on

More information

OERC KEEPS RETAIL ELECTRICITY TARIFF UNCHANGED FOR

OERC KEEPS RETAIL ELECTRICITY TARIFF UNCHANGED FOR OERC KEEPS RETAIL ELECTRICITY TARIFF UNCHANGED FOR 2007-08 The Orissa Electricity Regulatory Commission approved the Retail Supply Tariff orders for the four distribution companies of Orissa for 2007-08.

More information

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. Page 1 of 1 OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. A. Introduction FINANCIAL INTERMEDIATION

More information

Texas Public Finance Authority MASTER SWAP POLICY

Texas Public Finance Authority MASTER SWAP POLICY Texas Public Finance Authority MASTER SWAP POLICY 1. Purpose The purpose of this Swap Policy is to provide a policy for the Texas Public Finance Authority s use of swaps, cap, floors, collars, options

More information

World Bank Group - LED Streetlight Financing Tool: User s Manual

World Bank Group - LED Streetlight Financing Tool: User s Manual World Bank Group - LED Streetlight Financing Tool: User s Manual The World Bank Group developed the CityLED Streetlight Financing Tool to allow cities to evaluate the financial implications, as well as

More information

Rating criteria for toll road projects. February 2018

Rating criteria for toll road projects. February 2018 Rating criteria for toll road projects February 2018 Criteria contacts Pawan Agrawal Chief Analytical Officer CRISIL Ratings Email: pawan.agrawal@crisil.com Sameer Charania Director Rating Criteria and

More information

Public-Private Partnership (PPP) Contracts

Public-Private Partnership (PPP) Contracts 25 29 June 2018 London / United Kingdom Introduction A key motivation for governments considering public-private partnerships (PPPs) is the possibility of bringing in new sources of financing for funding

More information

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. OM Section H5/BP Page 1 of 4 BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. A. Introduction ADDITIONAL FINANCING 1. The

More information

HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA. (Date of Order: )

HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA. (Date of Order: ) HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA IN THE MATTER OF:- (Date of Order: 25.07.2018) Petition No.: 26/2018(Suo-Moto) CORAM Sh. S.K.B.S. Negi Chairman Sh. Bhanu Pratap Singh Member

More information

Adani Transmission Limited Q Results Analyst Call. August 10, 2017

Adani Transmission Limited Q Results Analyst Call. August 10, 2017 Adani Transmission Limited Q1 2018 Results Analyst Call MANAGEMENT: MR. KAUSHAL SHAH - CHIEF FINANCIAL OFFICER - ADANI TRANSMISSION LIMITED Page 1 of 5 Adani Transmission Limited Good day ladies and gentlemen

More information

2 nd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes

2 nd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes 2 nd Technical Workshop: Gas Market Design and Natural Gas Transmission Grid Codes Reviewing and Approving TYNDP A Regulatory Perspective Evangelos Penglis Partner, VIS Economic & Energy Consultants 08/12/2017

More information

Cross Border Electricity Trade

Cross Border Electricity Trade Cross Border Electricity Trade Afghanistan Pakistan Nepal Bhutan India First meeting of core team on South Asian Regional Power Exchange (SARPEX) Bangladesh 7 th - 9 th February, 2017 New Delhi, India

More information

Technics of financial assessment of infrastructure projects. Balázs Felsmann REKK

Technics of financial assessment of infrastructure projects. Balázs Felsmann REKK Technics of financial assessment of infrastructure projects Balázs Felsmann REKK 1 Main focuses of the corporate (TSO) level financial assessment Identify the investment costs of the project including

More information

Evolution of Power Exchange. S. C. Saxena National Load Despatch Center Power System Operation Corporation Ltd.

Evolution of Power Exchange. S. C. Saxena National Load Despatch Center Power System Operation Corporation Ltd. Evolution of Power Exchange S. C. Saxena National Load Despatch Center Power System Operation Corporation Ltd. Market Design Four Pillars of Market Design ELECTRICITY MARKET SCHEDULING & DISPATCH CONGESTION

More information

J.P.Morgan 2018 Energy Conference June 20, 2018

J.P.Morgan 2018 Energy Conference June 20, 2018 J.P.Morgan 2018 Energy Conference June 20, 2018 Legal Notice FORWARD LOOKING STATEMENTS Certain statements in this presentation may relate to our future business and financial performance and future events

More information

NTPC LIMITED RESEARCH

NTPC LIMITED RESEARCH RESULTS REVIEW Share Data Market Cap Rs. 1,457.0 bn Price Rs. 176.70 BSE Sensex 9,201.85 Reuters NTPC.BO Bloomberg NATP IN Avg. Volume (52 Week) 2.06 mn 52-Week High/Low Rs. 227 / 113 Shares Outstanding

More information

Project Administration Manual. India: Green Energy Corridor and Grid Strengthening Project. Project Numbers: October 2015

Project Administration Manual. India: Green Energy Corridor and Grid Strengthening Project. Project Numbers: October 2015 Green Energy Corridor and Grid Strengthening Project (RRP IND 44426) Project Administration Manual Project Numbers: 44426-016 October 2015 India: Green Energy Corridor and Grid Strengthening Project Contents

More information

Leveraged Bank Loans. Prudential Investment Management-Fixed Income. Leveraged Loans: Capturing Investor Attention July 2006

Leveraged Bank Loans. Prudential Investment Management-Fixed Income. Leveraged Loans: Capturing Investor Attention July 2006 Prudential Investment Management-Fixed Income Leveraged Loans: Capturing Investor Attention July 2006 Timothy Aker Head of US Bank Loan Team Martha Tuttle Portfolio Manager, US Bank Loan Team Brian Juliano

More information

RAVEN RUSSIA LIMITED. Raven Russia Limited Risk Report. Extracted from the 2015 Annual Report

RAVEN RUSSIA LIMITED. Raven Russia Limited Risk Report. Extracted from the 2015 Annual Report RAEN RUSSIA LIMITED Raven Russia Limited Risk Report Extracted from the 2015 Annual Report RISK REPORT Risk Appetite The Board places significant importance on identifying and managing the risks facing

More information

Indian Accounting Standard 36 Impairment of Assets

Indian Accounting Standard 36 Impairment of Assets Indian Accounting Standard 36 Impairment of Assets Contents Paragraphs Objective 1 Scope 2 5 Definitions 6 Identifying an asset that may be impaired 7 17 Measuring recoverable amount 18 57 Measuring the

More information

State of Texas Policies for Interest Rate Management Agreements

State of Texas Policies for Interest Rate Management Agreements State of Texas Policies for Interest Rate Management Agreements Introduction The following policies have been created by the Texas Bond Review Board to standardize and rationalize the use and management

More information

ECONOMIC ANALYSIS. Table 1: Total Cost Estimate (Economic Costs) (CNY million)

ECONOMIC ANALYSIS. Table 1: Total Cost Estimate (Economic Costs) (CNY million) Jiangxi Ji an Sustainable Urban Transport Project (RRP PRC 45022) ECONOMIC ANALYSIS A. Project Costs 1. This chapter outlines the methodology and results of the economic analysis for the project, comprising

More information

India: National Highway Sector II Project

India: National Highway Sector II Project Validation Report October 2017 India: National Highway Sector II Project Reference Number: PVR-517 Project Number: 35335-013 Loan Number: 2154 ABBREVIATIONS ADB Asian Development Bank CSC construction

More information

From CapEx to Cash Capital Markets Day Merkers - November 12th, 2015

From CapEx to Cash Capital Markets Day Merkers - November 12th, 2015 K+S Aktiengesellschaft From CapEx to Cash Capital Markets Day Merkers - November 12th, 2015 Dr. Burkhard Lohr, CFO From Capex to Cash Capex Phase Cash Phase 2020 Net debt: 2.2 billion 1) Leverage: 2.1x

More information

Project Finance An Overview

Project Finance An Overview Project Finance An Overview KAMAL TAK ICAI, Navi Mumbai Chapter December 16, 2012 1 Project Finance An Overview What is Project Financing? How is it different? How are Projects developed? Various Project

More information

ECONOMIC ANALYSIS. A. Introduction and Macroeconomic Context

ECONOMIC ANALYSIS. A. Introduction and Macroeconomic Context Dhaka Water Supply Network Improvement Project (RRP BAN 47254-003) ECONOMIC ANALYSIS A. Introduction and Macroeconomic Context 1. Economic growth in Bangladesh averaged an very healthy 6.1% during FY2006

More information

Leading Renewable Energy Generation Company

Leading Renewable Energy Generation Company Leading Renewable Energy Generation Company Disclaimer Certain statements in this presentation concerning our future growth prospects are forward looking statements, which involve a number of risks and

More information

PJM INTERCONNECTION, L.L.C. FOR THE QUARTER ENDED SEPTEMBER 30, 2017

PJM INTERCONNECTION, L.L.C. FOR THE QUARTER ENDED SEPTEMBER 30, 2017 PJM INTERCONNECTION, L.L.C. FOR THE QUARTER ENDED SEPTEMBER 30, 2017 INDEX PART I FINANCIAL INFORMATION PAGE Item 1. Financial Statements Consolidated Statement of Financial Position 2 Consolidated Statement

More information

Development of Power Markets and Market Monitoring

Development of Power Markets and Market Monitoring Department of Industrial and Management Engineering Indian Institute of Technology Kanpur 3 rd Capacity Building Programme for Officers of Electricity Regulatory Commissions 23 28 August, 2010 Development

More information

Project Finance Modelling For Renewable Energy

Project Finance Modelling For Renewable Energy Project Finance Modelling For Renewable Energy A 3-Day Programme This course can be presented in-house for you on a date of your choosing The Banking and Corporate Finance Training Specialist Course Objectives

More information

PROPOSED NATIONAL POLICY INCOME TRUSTS AND OTHER INDIRECT OFFERINGS

PROPOSED NATIONAL POLICY INCOME TRUSTS AND OTHER INDIRECT OFFERINGS 6.1.2 Proposed National Policy 41-201 Income Trusts and Other Indirect Offerings Part 1 - Introduction 1.1 What is the purpose of the policy? PROPOSED NATIONAL POLICY 41-201 INCOME TRUSTS AND OTHER INDIRECT

More information

CASE 17-M-0178 Draft Discussion Document, November 2017 Session, Publicly Released November 15, 2017 STATE OF NEW YORK PUBLIC SERVICE COMMISSION

CASE 17-M-0178 Draft Discussion Document, November 2017 Session, Publicly Released November 15, 2017 STATE OF NEW YORK PUBLIC SERVICE COMMISSION STATE OF NEW YORK PUBLIC SERVICE COMMISSION At a session of the Public Service Commission held in the City of COMMISSIONERS PRESENT: CASE 17-M-0178 - Petition of Orange and Rockland Utilities, Inc. for

More information

BALANCE SHEET AS AT DECEMBER 31, 2014 (UA thousands Note B)

BALANCE SHEET AS AT DECEMBER 31, 2014 (UA thousands Note B) Chapter 7 African Development Bank BALANCE SHEET AS AT DECEMBER 31, 2014 (UA thousands Note B) ASSETS 2014 2013 CASH 406,709 954,133 DEMAND OBLIGATIONS 3,801 3,801 SECURITIES PURCHASED UNDER RESALE AGREEMENTS

More information

CARE ADVISORY RESEARCH AND TRAINING LTD. Project Finance: Infrastructure and Manufacturing Sectors

CARE ADVISORY RESEARCH AND TRAINING LTD. Project Finance: Infrastructure and Manufacturing Sectors CARE ADVISORY RESEARCH AND TRAINING LTD Project Finance: Infrastructure and Manufacturing Secrs COURSE DESCRIPTION: Project finance involves limited or non-recourse of a new project in which risks must

More information