1 Clean and Redline Tariffs Schedule 18 Only Attachment 2 to Appendix IX of SCE Transmission Owner Tariff January 1, 2015 and January 1, 2016 Effective Dates
2 Clean Tariff Schedule 18 Only Attachment 2 to Appendix IX of SCE Transmission Owner Tariff January 1, 2015 Effective Date
3 1) Transmission Plant - ISO Plant Line Fee Land Easements 1.66% 1.66% Structures and Improvements 1.80% 0.77% 2.57% Station Equipment 2.20% 0.27% 2.47% Towers and Fixtures 1.35% 1.09% 2.44% Poles and Fixtures 2.00% 1.67% 3.67% Overhead Conductors and Devices 2.00% 1.05% 3.05% Underground Conduit 1.65% 1.65% Underground Conductors and Devices 3.26% 0.61% 3.87% Roads and Trails 1.56% 1.56% 11 2) Distribution Plant - ISO Plant Land and Land Rights 1.67% 1.67% Structures and Improvements 2.33% 0.71% 3.04% Station Equipment 2.17% 0.96% 3.13% 3) General Plant Plant Land and Land Rights 1.67% 1.67% Structures and Improvements 2.41% 0.33% 2.74% Office Furniture 5.00% 5.00% Office Equipment Duplicating Equipment Personal Computers Mainframe Computers PC Software DDSMS - CPU & Processing 14.29% 14.29% DDSMS - Controllers, Receivers, Comm DDSMS - Telemetering & System 6.67% 6.67% DDSMS - Miscellaneous 5.00% 5.00% DDSMS - Map Board 4.00% 4.00% Stores Equipment 5.00% 5.00% Laboratory Equipment 6.67% 6.67% Misc Power Plant Equipment 5.00% 5.00% Data Network Systems Telecom System Equipment 14.29% 14.29% Netcomm Radio Assembly Microwave Equip. & Antenna Assembly 6.67% 6.67% Telecom Power Systems 5.00% 5.00% Fiber Optic Communication Cables 5.94% 0.12% 6.06% Telecom Infrastructure 3.65% 0.10% 3.75% Transportation Equip % 14.29% Garage & Shop -- Equip Tools & Work Equip. -- Shop Power Oper Equip 6.67% 6.67% 4) Intangible Plant Plant Hydro Relicensing 2.52% 2.52% Radio Frequency 2.50% 2.50% Other Intangibles 5.00% 5.00% Cap Soft 5yr 20.58% 20.58% Cap Soft 7yr 14.93% 14.93% Cap Soft 10yr 12.45% 12.45% Cap Soft 15yr 6.78% 6.78% Notes: 1) Depreciation rates may only be revised as approved by the Commission pursuant to a Section 205 or 206 filing.
4 Redline Tariff Schedule 18 Only Attachment 2 to Appendix IX of SCE Transmission Owner Tariff January 1, 2015 Effective Date
5 1) Transmission Plant - ISO Plant Line Fee Land Easements 1.66% 1.66% Structures and Improvements 1.80% 0.77% 2.57% Station Equipment 2.20% 0.27% 2.47% Towers and Fixtures 1.35% 1.09% 2.44% Poles and Fixtures 2.00% 1.67% 3.67% Overhead Conductors and Devices 2.00% 1.05% 3.05% Underground Conduit 1.65% 1.65% Underground Conductors and Devices 3.26% 0.61% 3.87% Roads and Trails 1.56% 1.56% 11 2) Distribution Plant - ISO Plant Land and Land Rights 1.67% 1.67% Structures and Improvements Station Equipment 2.43% 2.33% 2.29% 2.17% 0.77% 0.71% 0.84% 0.96% 3.20% 3.04% 3.13% 3) General Plant Plant Land and Land Rights 1.67% 1.67% 1.69% 2.41% 0.11% 0.33% 1.80% 2.74% Structures and Improvements Office Furniture 5.00% 5.00% Office Equipment Duplicating Equipment Personal Computers Mainframe Computers PC Software DDSMS - CPU & Processing 14.29% 14.29% DDSMS - Controllers, Receivers, Comm DDSMS - Telemetering & System 6.67% 6.67% DDSMS - Miscellaneous 5.00% 5.00% DDSMS - Map Board 4.00% 4.00% Stores Equipment 5.00% 5.00% Laboratory Equipment 6.67% 6.67% Misc Power Plant Equipment 5.00% 5.00% Data Network Systems Telecom System Equipment 14.29% 14.29% Netcomm Radio Assembly Microwave Equip. & Antenna Assembly 6.67% 6.67% Telecom Power Systems 5.00% 5.00% Fiber Optic Communication Cables 6.06% 5.94% 3.75% 3.65% 0.12% 0.10% 6.06% 3.75% Telecom Infrastructure Transportation Equip % 14.29% Garage & Shop -- Equip Tools & Work Equip. -- Shop Power Oper Equip 6.67% 6.67% 4) Intangible Plant Plant 2.64% 2.52% 2.64% 2.52% Hydro Relicensing Radio Frequency 2.50% 2.50% Other Intangibles 5.00% 5.00%
6 Cap Soft 5yr Cap Soft 7yr Cap Soft 10yr 21.41% 20.58% 14.71% 14.93% 10% 12.45% Cap Soft 15yr 6.67% 6.78% Notes: 1) Depreciation rates may only be revised as approved by the Commission pursuant to a Section 205 or 206 filing % 20.58% 14.71% 14.93% 10% 12.45% 6.67% 6.78%
7 Clean Tariff Schedule 18 Only Attachment 2 to Appendix IX of SCE Transmission Owner Tariff January 1, 2016 Effective Date
8 1) Transmission Plant - ISO Plant Line Fee Land Easements 1.66% 1.66% Structures and Improvements 1.80% 0.77% 2.57% Station Equipment 2.20% 0.27% 2.47% Towers and Fixtures 1.35% 1.09% 2.44% Poles and Fixtures 2.00% 1.67% 3.67% Overhead Conductors and Devices 2.00% 1.05% 3.05% Underground Conduit 1.65% 1.65% Underground Conductors and Devices 3.26% 0.61% 3.87% Roads and Trails 1.56% 1.56% 11 2) Distribution Plant - ISO Plant Land and Land Rights 1.67% 1.67% Structures and Improvements 2.33% 0.71% 3.04% Station Equipment 2.17% 0.96% 3.13% 3) General Plant Plant Land and Land Rights 1.67% 1.67% Structures and Improvements 2.41% 0.33% 2.74% Office Furniture 5.00% 5.00% Office Equipment Duplicating Equipment Personal Computers Mainframe Computers PC Software DDSMS - CPU & Processing 14.29% 14.29% DDSMS - Controllers, Receivers, Comm DDSMS - Telemetering & System 6.67% 6.67% DDSMS - Miscellaneous 5.00% 5.00% DDSMS - Map Board 4.00% 4.00% Stores Equipment 5.00% 5.00% Laboratory Equipment 6.67% 6.67% Misc Power Plant Equipment 5.00% 5.00% Data Network Systems Telecom System Equipment 14.29% 14.29% Netcomm Radio Assembly Microwave Equip. & Antenna Assembly 6.67% 6.67% Telecom Power Systems 5.00% 5.00% Fiber Optic Communication Cables 5.94% 0.12% 6.06% Telecom Infrastructure 3.65% 0.10% 3.75% Transportation Equip % 14.29% Garage & Shop -- Equip Tools & Work Equip. -- Shop Power Oper Equip 6.67% 6.67% 4) Intangible Plant Plant Hydro Relicensing 2.52% 2.52% Radio Frequency 2.50% 2.50% Other Intangibles 5.00% 5.00% Cap Soft 5yr 20.58% 20.58% Cap Soft 7yr 14.93% 14.93% Cap Soft 10yr 12.45% 12.45% Cap Soft 15yr 6.78% 6.78% Notes: 1) Depreciation rates may only be revised as approved by the Commission pursuant to a Section 205 or 206 filing.
9 Redline Tariff Schedule 18 Only Attachment 2 to Appendix IX of SCE Transmission Owner Tariff January 1, 2016 Effective Date
10 1) Transmission Plant - ISO Plant Line Fee Land Easements 1.66% 1.66% Structures and Improvements 1.80% 0.77% 2.57% Station Equipment 2.20% 0.27% 2.47% Towers and Fixtures 1.35% 1.09% 2.44% Poles and Fixtures 2.00% 1.67% 3.67% Overhead Conductors and Devices 2.00% 1.05% 3.05% Underground Conduit 1.65% 1.65% Underground Conductors and Devices 3.26% 0.61% 3.87% Roads and Trails 1.56% 1.56% 11 2) Distribution Plant - ISO Plant Land and Land Rights 1.67% 1.67% Structures and Improvements Station Equipment 2.43% 2.33% 2.29% 2.17% 0.77% 0.71% 0.84% 0.96% 3.20% 3.04% 3.13% 3) General Plant Plant Land and Land Rights 1.67% 1.67% 1.69% 2.41% 0.11% 0.33% 1.80% 2.74% Structures and Improvements Office Furniture 5.00% 5.00% Office Equipment Duplicating Equipment Personal Computers Mainframe Computers PC Software DDSMS - CPU & Processing 14.29% 14.29% DDSMS - Controllers, Receivers, Comm DDSMS - Telemetering & System 6.67% 6.67% DDSMS - Miscellaneous 5.00% 5.00% DDSMS - Map Board 4.00% 4.00% Stores Equipment 5.00% 5.00% Laboratory Equipment 6.67% 6.67% Misc Power Plant Equipment 5.00% 5.00% Data Network Systems Telecom System Equipment 14.29% 14.29% Netcomm Radio Assembly Microwave Equip. & Antenna Assembly 6.67% 6.67% Telecom Power Systems 5.00% 5.00% Fiber Optic Communication Cables 6.06% 5.94% 3.75% 3.65% 0.12% 0.10% 6.06% 3.75% Telecom Infrastructure Transportation Equip % 14.29% Garage & Shop -- Equip Tools & Work Equip. -- Shop Power Oper Equip 6.67% 6.67% 4) Intangible Plant Plant 2.64% 2.52% 2.64% 2.52% Hydro Relicensing Radio Frequency 2.50% 2.50% Other Intangibles 5.00% 5.00%
11 Cap Soft 5yr Cap Soft 7yr Cap Soft 10yr 21.41% 20.58% 14.71% 14.93% 10% 12.45% Cap Soft 15yr 6.67% 6.78% Notes: 1) Depreciation rates may only be revised as approved by the Commission pursuant to a Section 205 or 206 filing % 20.58% 14.71% 14.93% 10% 12.45% 6.67% 6.78%
UNIFORM SYSTEM OF ACCOUNTS ACCOUNT LISTING BALANCE SHEET CHART OF ACCOUNTS ASSETS AND OTHER DEBITS
BALANCE SHEET CHART OF ACCOUNTS ASSETS AND OTHER DEBITS 1. UTILITY PLANT 101 Electric plant in service (Major only). 101.1 Property under capital leases. 102 Electric plant purchased or sold. 103 Experimental
More informationExhibit A Affidavit of Alan Varvis
Affidavit of Alan Varvis Page 1 of 9 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southern California Edison Company ) Docket No. ER16- -000 AFFIDAVIT OF ALAN VARVIS FOR SOUTHERN
More informationMonthly Financial Report
AGENDA ITEM NO: 4.C.1 Monthly Financial Report with data through February 2019 (Unaudited) The data contained in this report has not been independently audited. Alameda Municipal Power Financial Report
More information2011 PILS / CORPORATE TAX FILING
Page 1 of 33 2011 PILS / CORPORATE TAX FILING Sheet Index: Title Page Input Information Summary Tax Rates & Exemptions Test Year Sch 8 and 10 UCC&CEC Test Year UCC and CEC Additions & Disposals Test Year
More informationMonthly Financial Report
AGENDA ITEM NO: 4.C.1 Monthly Financial Report with data through October 2017 (Unaudited) The data contained in this report has not been independently audited. Alameda Municipal Power Financial Report
More information2009 PILS / CORPORATE TAX FILING
Page 1 of 44 29 PILS / CORPORATE TAX FILING Sheet Index: Title Page Input Information Summary Tax Rates & Exemptions 28 Adjusted Taxable Income 28 Taxable Income Additions 28 Taxable Income Deductions
More information2007 PILS / CORPORATE TAX FILING
Page 1 of 44 27 PILS / CORPORATE TAX FILING Sheet Index: Title Page Input Information Summary Tax Rates & Exemptions 26 Adjusted Taxable Income 26 Taxable Income Additions 26 Taxable Income Deductions
More informationSUMMARY EXPLANATION OF STATEMENTS AND SCHEDULES. The following summary explanations of Statements and Schedules are intended as a general guide.
Black Hills Power, Inc. South Dakota Revenue Requirement Model Description SUMMARY EXPLANATION OF STATEMENTS AND SCHEDULES The following summary explanations of Statements and Schedules are intended as
More information2010 PILS / CORPORATE TAX FILING
Page 1 of 39 21 PILS / CORPORATE TAX FILING Sheet Index: Title Page Input Information Summary Tax Rates & Exemptions 29 Adjusted Taxable Income 29 Taxable Income Additions 29 Taxable Income Deductions
More informationThunder Bay Hydro Electricity Distribution Inc. 1-1 GENERAL (Input) Enter general information related to the Application. EDR 2006 MODEL (ver. 2.
Thunder Bay Hydro Electricity Inc. 1-1 GENERAL (Input) Enter general information related to the Application Version: 2.1 Name of Applicant Thunder Bay Hydro Electricity Inc. License EB -0259 File (s) RP
More informationDuquesne Light Company Distribution Rate Case Docket No. R Filing Index
Duquesne Light Company Distribution Rate Case Docket No. R-2013-2372129 Filing Index Exhibit 1 Summary of Filing Part I General Information Part II Primary Statements of Rate Base & Operating Income Part
More information1.0 Overview Reduction in Depreciation Under Canadian GAAP (2014/15) Reduction in Depreciation Under IFRS (2015/16 & 2016/17)...
Appendix 5.6 January 23, 2015 1 2 3 4 5 6 7 8 9 10 11 MANITOBA HYDRO 2015/16 & 2016/17 GENERAL RATE APPLICATION DEPRECIATION RATES & DEPRECIATION STUDY 1.0 Overview... 2 2.0 Reduction in Depreciation Under
More informationElectric Utility System of Accounts
National Association of Regulatory Utility Commissioners 3rd Partnership Activity of the Energy Regulation Board of Zambia & Pennsylvania Public Utility Commission March 20-23, 2006 Electric Utility System
More informationCOST ALLOCATION. Cost Allocation Informational Filing Guidelines for Electricity Distributors dated November 15, 2006.
Filed: October 10, 2008 Schedule 1 Page 1 of 2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 COST ALLOCATION PowerStream submitted a cost allocation informational filing with the Board
More information(1) (2) (3) (4) (5) 1 GROSS REVENUE REQUIREMENT (page 3, line 47) $
page 1 of 5 Attachment H Formula Rate NonLevelized Rate Formula Template For the 12 months ended 12/31/2018 Utilizing FERC Form 1 Data (1) (2) (3) (4) (5) Line Allocated No. Amount 1 GROSS REVENUE REQUIREMENT
More informationUNITIL ENERGY SYSTEMS, INC NEW HAMPSHIRE FILING REQUIREMENT SCHEDULES TABLE OF CONTENTS
Unitil Energy Systems, Inc. DE 16-384 Filing Requirement Schedules UNITIL ENERGY SYSTEMS, INC NEW HAMPSHIRE FILING REQUIREMENT SCHEDULES TABLE OF CONTENTS Page Filing Requirement Schedule 1 Schedule -
More informationMay 15, Duke Energy Ohio, Inc., and Duke Energy Kentucky, Inc. Formula Rate Annual Update Docket No. ER
Gary A. Morgans 202 429 6234 gmorgans@steptoe.com 1330 Connecticut Avenue, NW Washington, DC 20036-1795 202 429 3000 main www.steptoe.com The Hon. Kimberly D. Bose Secretary Federal Energy Regulatory Commission
More informationAPPENDIX X FORMULA FOR CALCULATING THE ALLOCATED COSTS TO THE CITIZENS BORDER EAST LINE RATE UNDER SDG&E S TRANSMISSION OWNER TARIFF
APPENDIX X FORMULA FOR CALCULATING THE ALLOCATED COSTS TO THE CITIZENS BORDER EAST LINE RATE UNDER SDG&E S TRANSMISSION OWNER TARIFF Appendix X sets forth the formula for calculating the Citizens Border
More information2017 Budget. Final. v.2. Passed by Resolution No December 6, 2016
Budget Final v.2 Passed by Resolution No. 2757 December 6, 2016 Blank Page Inserted Intentionally Public Utility District #1 of Lewis County Electric System Budget Final Budget Overview Electric System
More informationConsolidated Financial Statements. Lakeland Holding Ltd. December 31, 2013
Consolidated Financial Statements Lakeland Holding Ltd. Contents Page Independent Auditor s Report 1-2 Consolidated Statements of Earnings and Comprehensive Loss 3 Consolidated Statement of Shareholders
More informationExcerpt From FCC USOA Part-32
Page 1 of 11 Plant Accounts to be Maintained by Class A and Class B telephone companies as indicated: Account title Class A Class B account account REGULATED PLANT Property, plant and equipment: Telecommunications
More informationJune 20, Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C
McGuireWoods LLP 2001 K Street N.W. Suite 400 Washington, DC 20006-1040 Phone: 202.857.1700 Fax: 202.857.1737 www.mcguirewoods.com Julia Dryden English Direct: 202.857.1706 jenglish@mcguirewoods.com Fax:
More informationBANDERA ELECTRIC COOPERATIVE, INC. BANDERA, TEXAS FINANCIAL STATEMENTS WITH ACCOMPANYING INFORMATION FOR THE YEARS ENDED DECEMBER 31, 2012 AND 2011
BANDERA, TEXAS FINANCIAL STATEMENTS WITH ACCOMPANYING INFORMATION FOR THE YEARS ENDED DECEMBER 31, 2012 AND 2011 AND REPORT OF BOLINGER, SEGARS, GILBERT & MOSS, L.L.P. LUBBOCK, TEXAS BANDERA, TEXAS FINANCIAL
More informationWorkpapers General Rate Case APPLICATION
An E D ISO N INTERNATIONAL Company (U 338-E) 2015 General Rate Case APPLICATION Workpapers Results of Operations (RO) Plant, Taxes, Depreciation Expense and Reserve, Rate Base, and Productivity SCE-10
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Southern California Gas Company (U 904 G) and San Diego Gas & Electric Company (U 902 G) for Low Operational Flow Order
More informationBANDERA ELECTRIC COOPERATIVE, INC. BANDERA, TEXAS FINANCIAL STATEMENTS WITH ACCOMPANYING INFORMATION FOR THE YEARS ENDED DECEMBER 31, 2014 AND 2013
BANDERA, TEXAS FINANCIAL STATEMENTS WITH ACCOMPANYING INFORMATION FOR THE YEARS ENDED DECEMBER 31, 2014 AND 2013 AND REPORT OF BOLINGER, SEGARS, GILBERT & MOSS, L.L.P. LUBBOCK, TEXAS BANDERA, TEXAS FINANCIAL
More informationENMAX POWER CORPORATION Distribution AUC Rule 005: ANNUAL OPERATIONS FINANCIAL AND OPERATING REPORTING For the Year Ended December 31, 2017 $M
ENMAX POWER CORPORATION Distribution AUC Rule 005: ANNUAL OPERATIONS FINANCIAL AND OPERATING REPORTING For the Year Ended December 31, 2017 $M TABLE OF CONTENTS Schedule Schedule Name Page Sch 1 Summary
More informationResidential General Service Less Than 50 kw General Service - 50 to 999,000 kw 1,000 to 4,999 kw Large Use Standby - General Service kw
Page 1 of 65 Residential This classification refers to an account where the electricity is used exclusively in a separately metered living accommodation. Customers shall be residing in singledwelling units
More informationRepublic of the Philippines ENERGY REGULATORY COMMISSION San Miguel Avenue, Pasig City
Republic of the Philippines ENERGY REGULATORY COMMISSION San Miguel Avenue, Pasig City IN THE MATTER OF THE APPLICATION FOR APPROVAL OF THE ANNUAL REVENUE REQUIREMENT AND PERFORMANCE INCENTIVE SCHEME IN
More informationBOLINGER, SEGARS, GILBERT & MOSS, L.L.P.
BOLINGER, SEGARS, GILBERT & MOSS, L.L.P. certified public accountants PHONE: (806) 747-3806 FAX: (806) 747-3815 8215 Nashville Avenue LUBBOCK, TEXAS 79423-1954 March 6, 2014 Board of Directors Bandera
More informationSOUTH AFRICAN TELECOMMUNICATIONS REGULATORY AUTHORITY (SATRA) VOLUME 3 CHART OF ACCOUNTS AND COST ALLOCATION MANUAL (COA/CAM)
Regional Telecommunications Restructuring Program SOUTH AFRICAN TELECOMMUNICATIONS REGULATORY AUTHORITY (SATRA) VOLUME 3 CHART OF ACCOUNTS AND COST ALLOCATION MANUAL (COA/CAM) DETAILED REQUIREMENTS FOR
More informationIn addition to this transmittal letter and associated records for the etariff database, this filing includes:
1050 Thomas Jefferson Street, NW Seventh Floor Washington, DC 20007 (202) 298-1800 Phone (202) 338-2416 Fax SUBMITTED VIA E-TARIFF FILING January 4, 2017 Kimberly D. Bose Secretary Federal Energy Regulatory
More informationFinancial Statements December 31, 2012 and 2011 Rio Grande Electric Cooperative, Inc.
Financial Statements December 31, 2012 and 2011 Rio Grande Electric Cooperative, Inc. www.eidebailly.com Table of Contents December 31, 2012 and 2011 Independent Auditor s Report... 1 Financial Statements...
More informationRegulatory Accounting Manual Volume 2
Regulatory Accounting Manual Volume 2 Project: Regulatory Accounting Report: (Draft for Discussion) Date Revised: 25 September 2007 1 Table of Contents 1 DEFINITIONS AND INSTRUCTIONS 4 1.1 OVERVIEW 4 1.2
More informationAUDITED FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION MUNICIPAL UTILITIES BOARD OF THE CITY OF ALBERTVILLE ELECTRIC SYSTEM ALBERTVILLE, ALABAMA
AUDITED FINANCIAL STATEMENTS AND SUPPLEMENTARY INFORMATION MUNICIPAL UTILITIES BOARD OF THE CITY OF ALBERTVILLE ELECTRIC SYSTEM ALBERTVILLE, ALABAMA June 30, 2017 and 2016 TABLE OF CONTENTS PAGE INDEPENDENT
More informationEntergy Gulf States Louisiana, LLC 2015 Pole Attachment Formula and Calculation for Public Utilities For the Test Year Ended December 31, 2014
Entergy Gulf States Louisiana, LLC 2015 Pole Attachment Formula and Calculation for Public Utilities For the Test Year Ended December 31, 2014 Ln Data Source Reference [1] USofA [2] Amount 1 Gross Plant
More informationAmerican Electric Power Service Corporation Docket No. ER10- -
American Electric Power 801 Pennsylvania Avenue N.W. Suite 320 Washington, DC 20004 AEP.com May 3, 2010 Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E.
More informationPublic Utility District #1 of Ferry County Budget. December 17, 2018
Public Utility District #1 of Ferry County 2019 Budget December 17, 2018 The Approved Budget for 2019 reflects an overall reduction of approximately 3.2 percent from the 2018 Budget. The District is predicting
More informationPower Workers' Union (PWU) INTERROGATORY #1. Ref (a): Participant Information Package: Exhibit C1-2-1, Page 5 of 6, Table 2 (OM&A Expenditures)
Filed: 0-0- 0-0 Tx Rates Schedule Page of Power Workers' Union (PWU) INTERROGATORY # Ref (a): Participant Information Package: Exhibit C--, Page of, Table (OM&A Expenditures) Table : 0 Board Approved versus
More informationEntergy Louisiana, LLC (5) 2016 Pole Attachment Formula and Calculation for Public Utilities For the Test Year Ended December 31, 2015.
Entergy Louisiana, LLC (5) 2016 Pole Attachment Formula and Calculation for Public Utilities For the Test Year Ended December 31, 2015 Ln Description FF1 Ref. [1] USofA [2] Amount 1 Gross Plant 110.4.c
More informationRIO GRANDE ELECTRIC COOPERATIVE, INC. FINANCIAL STATEMENTS DECEMBER 31, 2013 AND 2012
FINANCIAL STATEMENTS DECEMBER 31, 2013 AND 2012 TABLE OF CONTENTS YEARS ENDED DECEMBER 31, 2013 AND 2012 DIRECTORS AND OFFICERS 1 INDEPENDENT AUDITORS REPORT 2 FINANCIAL STATEMENTS BALANCE SHEETS 4 STATEMENTS
More informationExhibit B SCE General Rate Case Decision CPUC D (Relevant Portions)
Exhibit B SCE General Rate Case Decision CPUC D.15-11-021 (Relevant Portions) statistics justify ASLs up to 69 years. Finally, TURN suggests that aluminum conductor can last far longer than the ASLs considered
More informationEntergy Louisiana, LLC 2017 Pole Attachment Formula and Calculation for Public Utilities For the Test Year Ended December 31, 2016
2017 Pole Attachment Formula and Calculation for Public Utilities For the Test Year Ended December 31, 2016 Ln Description FF1 Ref. [1] USofA [2] Amount 1 Gross Plant 110.4.c 101-106, 114, 107 19,847,012,044
More informationRIO GRANDE ELECTRIC COOPERATIVE, INC. FINANCIAL STATEMENTS YEARS ENDED DECEMBER 31, 2016 AND 2015
FINANCIAL STATEMENTS YEARS ENDED DECEMBER 31, 2016 AND 2015 TABLE OF CONTENTS YEARS ENDED DECEMBER 31, 2016 AND 2015 DIRECTORS AND OFFICERS 1 INDEPENDENT AUDITORS REPORT 2 FINANCIAL STATEMENTS BALANCE
More informationRIO GRANDE ELECTRIC COOPERATIVE, INC. FINANCIAL STATEMENTS YEARS ENDED DECEMBER 31, 2015 AND 2014
FINANCIAL STATEMENTS YEARS ENDED DECEMBER 31, 2015 AND 2014 2015 Audit Report as per SS 4.6.16 TABLE OF CONTENTS YEARS ENDED DECEMBER 31, 2015 AND 2014 DIRECTORS AND OFFICERS 1 INDEPENDENT AUDITORS REPORT
More informationPublic Utility District #1 of Ferry County Budget. December 19, 2016
Public Utility District #1 of Ferry County 2017 Budget December 19, 2016 The Approved Budget for 2017 is $7,688,400 which reflects an overall decrease of 3.86% from the 2016 Budget; this is a reduction
More informationTHE CORPORATION OF THE TOWN OF LINCOLN
THE CORPORATION OF THE TOWN OF LINCOLN BY - LAW NO. 00-17 A BY-LAW TO TRANSFER THE EMPLOYEES, ASSETS, LIABILITIES, RIGHTS AND OBLIGATIONS OF THE LINCOLN HYDRO ELECTRIC COMMISSION AND THE CORPORATION OF
More informationALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC
ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404 202-239-3300 Fax: 202-239-3333 www.alston.com September 1, 2016 To: Re: Parties to FERC Docket No. ER08-386-000 Potomac-Appalachian
More informationSouthern California Edison IEC (Corp ID 6096) Status of Advice Letter 128 As of January 21, Disposition: Effective Date: Accepted
STATE OF CALIFORNIA EDMUND G. BROWN JR., Governor PUBLIC UTILITIES COMMISSION 505 Van Ness Avenue San Francisco CA 94102-3298 Southern California Edison IEC (Corp ID 6096) Status of Advice Letter 128 As
More informationPublic Accounts of Ontario
Ontario Ministry of Finance Public Accounts of Ontario Financial Statements of Crown Corporations, Boards, Commissions 2000-2001 VOLUME 2 TABLE OF CONTENTS General Guide to Public Accounts...vii Ontario
More informationrequest for approval of Telecommunication leases between SCEC and MCImetro access transmission services LLC pursuant to GO 173 Accepted
STATE OF CALIFORNIA EDMUND G. BROWN JR., Governor PUBLIC UTILITIES COMMISSION 505 Van Ness Avenue San Francisco CA 94102-3298 Southern California Edison IEC (Corp ID 6096) Status of Advice Letter 130 As
More informationTelecommunications Service Agreement (Pursuant to PSC No. 9 Electricity, Rider X)
Consolidated Edison Company of New York, Inc. Telecom Application Management Department Telecommunications Service Agreement (Pursuant to PSC No. 9 Electricity, Rider X) WHEREAS, ( Customer ) has applied
More informationBEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION. PENNSYLVANIA PUBLIC UTILITY COMMISSION v. PECO ENERGY COMPANY ELECTRIC DIVISION
PECO ENERGY COMPANY STATEMENT NO. BEFORE THE PENNSYLVANIA PUBLIC UTILITY COMMISSION PENNSYLVANIA PUBLIC UTILITY COMMISSION v. PECO ENERGY COMPANY ELECTRIC DIVISION DOCKET NO. R-01-0001 DIRECT TESTIMONY
More informationREVISED SDG&E DIRECT TESTIMONY OF MATTHEW C. VANDERBILT (DEPRECIATION) DECEMBER 2017 BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Company: San Diego Gas & Electric Company (U 0 M) Proceeding: 01 General Rate Case Application: A.1--00 Exhibit: SDG&E--R REVISED SDG&E DIRECT TESTIMONY OF MATTHEW C. VANDERBILT (DEPRECIATION) DECEMBER
More informationTown of Holly Springs
Meeting Date: March 20, 2018 Town of Holly Springs Town Council Meeting Agenda Form Town Clerk s Office Use: Agenda Item #: 8h Attachment #: 3h Agenda Placement: Consent Agenda (Special Recognitions (awards,
More informationBoard Finance & Budget Planning Workshop. April 18, 2016
Board Finance & Budget Planning Workshop April 18, 2016 1 Management Introduction (Glenn Steiger) 2 Overview Management Introduction Strategic Plan Cost of Doing Business FY2017 Financial Highlights Division
More informationHYDRO ONE INC. MANAGEMENT S REPORT
MANAGEMENT S REPORT The Consolidated Financial Statements, Management s Discussion and Analysis (MD&A) and related financial information have been prepared by the management of Hydro One Inc. (Hydro One
More informationPUBLIC SERVICE CO. OF COLORADO ANNUAL REPORT CITY OF BOULDER, COLO. FOR THE YEAR ENDED DEC. 31, 2010
ANNUAL REPORT, COLO. FOR THE YEAR ENDED DEC. 31, 2010 METHODOLOGY & DISCLAIMERS THE FOLLOWING CALCULATIONS ARE USED TO DERIVE THE ESTIMATED AMOUNTS IN THIS REPORT: ELECTRIC AND GAS plant INVESTMENT OF
More informationDecember 29, American Electric Power Service Corporation Docket No. ER
American Electric Power 1 Riverside Plaza Columbus, OH 43215 AEP.com Honorable Kimberly D Bose Secretary Federal Energy Regulatory Commission 888 First St., N.E. Washington D.C. 20426 December 29, 2015
More informationTILLAMOOK PEOPLE'S UTILITY DISTRICT
TILLAMOOK PEOPLE'S UTILITY DISTRICT ANNUAL FINANCIAL REPORT Years Ended December 31, 2011, and 2010 KENNETH KUHNS & CO. Certified Public Accountants 570 Liberty Street S.E., Suite 210 Salem, Oregon 97301-3594
More informationMANAGEMENT S REPORT. Financial Statements December 31, 2011
Financial Statements December 31, 2011 MANAGEMENT S REPORT The accompanying financial statements of FortisAlberta Inc. (the Corporation ) have been prepared by management, who are responsible for the integrity
More informationCENTRAL LINCOLN PEOPLE'S UTILITY DISTRICT
AUDIT REPORT Years Ended June 30, 2014, and 2013 KENNETH KUHNS & CO. Certified Public Accountants 570 Liberty Street S.E., Suite 210 Salem, Oregon 97301-3594 Telephone: (503) 585-2550 TABLE OF CONTENTS
More informationRULE H NEW SERVICE ATTACHMENTS AND DISTRIBUTION LINE INSTALLATIONS OR ALTERATIONS (Continued)
IDAHO POWER COMPANY NINTH REVISED SHEET NO. H-5 CANCELS P.U.C. ORE. NO. E-27 EIGHTH REVISED SHEET NO. H-5 2. General Provisions (Continued) RULE H NEW SERVICE ATTACHMENTS AND DISTRIBUTION LINE INSTALLATIONS
More informationCOVER PAGE FOR THE NEW JERSEY ELECTRIC TARIFF SECTION II
COVER PAGE FOR THE NEW JERSEY ELECTRIC TARIFF SECTION II CURRENT UPDATE Date of this Internet update: July 21, 2005 AM Tariff Change Effective: March 20, 2005 Total Pages (including cover): 41; Last Sheet:
More informationFinancial Statements For the years ended December 31, 2015 and 2014
FORTISALBERTA INC. Financial Statements MANAGEMENT S REPORT The accompanying annual financial statements of FortisAlberta Inc. (the Corporation ) have been prepared by management, who are responsible for
More informationFormula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/17 Utilizing FERC Form 1 Data
Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/17 Utilizing FERC Form 1 Data Northern Indiana Public Service Company Line Allocated No. Amount
More informationJuly 30, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC Dear Ms.
Regulation James A. Cuillier Director FERC Rates & Regulation July 30, 2014 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose:
More informationNANTUCKET ELECTRIC COMPANY STREET LIGHTING UNDERGROUND DIVISION OF OWNERSHIP S-3 RETAIL DELIVERY SERVICE
Sheet 1 Canceling M.D.P.U. No. 604 AVAILABILITY Service is available under this rate to any municipal city or town, hereinafter referred to as the Customer, only for street lighting installations served
More informationTOWN OF MANSFIELD, MASSACHUSETTS MUNICIPAL ELECTRIC DEPARTMENT REPORT ON EXAMINATION OF BASIC FINANCIAL STATEMENTS YEARS ENDED JUNE 30, 2014 AND 2013
REPORT ON EXAMINATION OF BASIC FINANCIAL STATEMENTS YEARS ENDED REPORT ON EXAMINATION OF BASIC FINANCIAL STATEMENTS YEARS ENDED TABLE OF CONTENTS PAGE Independent Auditor s Report 1-2 Independent Auditor
More informationFormula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2016 Utilizing FERC Form 1 Data
Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2016 Utilizing FERC Form 1 Data Northern Indiana Public Service Company Line Allocated No. Amount
More informationRAMAPO CATSKILL LIBRARY SYSTEM 2017 BUDGET - AUTOMATION 09/26/16
RAMAPO CATSKILL LIBRARY SYSTEM 2017 BUDGET - AUTOMATION 09/26/16 Column 1 Column 2 Column 3 Column 4 Column 5 Column 6 Column 7 Column 8 Column 9 REVENUE 2015 2016 ORGINAL ADJUSTED ACTUAL ORGINAL ADJUSTED
More informationBDR. Submitted to Toronto Hydro-Electric System Limited February 18, 2011
COST OF SERVICE STUDY FOR INDIVIDUALLY METERED SUITES IN MULTI-UNIT RESIDENTIAL BUILDINGS Alternative Scenario Ordered by the Ontario Energy Board Submitted to Toronto Hydro-Electric System Limited 34
More informationDEPARTMENT OF WATER AND POWER WATER REVENUE FUND
DEPARTMENT OF WATER AND POWER This Department, under the City Charter, is responsible for supplying the City its inhabitants with water electric energy by constructing, operating, maintaining for that
More informationTOWN OF LITCHFIELD, MAINE CATV FRANCHISE AGREEMENT
TOWN OF LITCHFIELD, MAINE CATV FRANCHISE AGREEMENT SECTION 1 - SHORT TITLE This franchise agreement shall be known and may be cited as Town of Litchfield, Maine CATV,Franchise. SECTION 2 - DEFINITION8
More information1 GROSS REVENUE REQUIREMENT (page 3, line 31, column 5) $ 121,165,696
Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/14 Utilizing FERC Form 1 Data Line Allocated No. Amount 1 GROSS REVENUE REQUIREMENT (page 3, line
More informationREVENUE AND EXPENDITURE REPORT FOR CANNON TOWNSHIP Page: 1/19 User: bonnies DB: CANNON PERIOD ENDING 09/30/2016
REVENUE AND EXPENDITURE REPORT FOR CANNON TOWNSHIP Page: 1/19 DB: CANNON PERIOD ENDING DIFF Fund 101 - GENERAL FUND Revenues Dept 000 101-000-402.000 CURRENT PROPERTY TAX 101-000-412.000 DELINQUENT PROPERY
More informationALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC
The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404
More informationRESIDENTIAL SERVICE CLASSIFICATION
Niagara-on-the-Lake Hydro Inc. Page 1 of 10 RESIDENTIAL SERVICE CLASSIFICATION This classification applies to an account taking electricity at 750 volts or less where the electricity is used exclusively
More informationBUDGET REPORT FOR CALEDONIA TOWNSHIP Fund: 101 GENERAL FUND
06/12/ 0946 AM DB Caledonia REPORT FOR CALEDONIA TOWNSHIP Fund 101 GENERAL FUND 1/9 101-000-40100000 101-000-40200000 101-000-40500000 101-000-41803000 101-000-42300000 101-000-42700000 101-000-44100000
More informationNorth Carolina State University Administrative Procedures Manual Chart of Accounts - Expenses Accounts
North Carolina State University Administrative Procedures Manual Chart of Accounts - Expenses Accounts 53000-53999 *Restricted codes are restricted for Office of Finance and Business Restricted Department
More informationROCKY MOUNTAIN POWER First Revision of Sheet No. R12-1 Canceling Original Sheet No. R12-1
First Revision of Sheet No. R12-1 Canceling Original Sheet No. R12-1 I. - Conditions and Definitions A. Contracts Before building an Extension, the Company may require the Applicant to sign a contract.
More informationNOW THEREFORE, BE IT ORDAINED BY THE BOARD OF COMMISSIONERS OF THE TOWN OF PINE LEVEL, THAT:
AN ORDINANCE TO PROVIDE FOR THE REGULATION OF BASIC SERVICE TIER RATES AND RELATED EQUIPMENT, INSTALLATION AND SERVICE CHARGES OF ANY CABLE TELEVISION SYSTEM OPERATING IN THE TOWN OF PINE LEVEL WHEREAS,
More informationLANCASTER CHOICE ENERGY
LANCASTER CHOICE ENERGY CITY OF LANCASTER FISCAL YEAR 2018 ADOPTED BUDGET 181 CITY OF LANCASTER FISCAL YEAR 2018 ADOPTED BUDGET 182 Lancaster Choice Energy, Lancaster Power Authority & California Choice
More informationFormula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/15 Utilizing FERC Form 1 Data
Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/15 Utilizing FERC Form 1 Data Northern Indiana Public Service Company Line Allocated No. Amount
More informationI L E OG111 APR April 20, 2017 VIA CERTIFIED MAIL
OGE Energy Corp. PO Box 321 Oklahoma City, Oklahoma 73101-0321 405-553-3000 www.oge.com April 20, 2017 VIA CERTIFIED MAIL Commissioner Dana Murphy Commissioner Bob Anthony Commissioner Todd Hiett Oklahoma
More informationIn this Order, the Commission directs Eversource to adopt a cost allocation policy for
ST ATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION IR 14-190 PUBLIC SERVICE COMPANY OF NEW HAMPSHIRE D/B/A EVERSOURCE ENERGY, UNITIL ENERGY SYSTEMS, INC., AND LIBERTY UTILITIES (GRANITE STATE ELECTRIC)
More informationPortland General Electric Company P.U.C. Oregon No. E-18 Original Sheet No. I-1 RULE I LINE EXTENSIONS
P.U.C. Oregon No. E-18 Original Sheet No. I-1 RULE I LINE EXTENSIONS 1. Purpose This rule establishes procedures and defines respective cost responsibilities to provide a Line Extension to a builder, developer,
More informationELECTRIC UTILITY OPERATING BUDGET. Presented by: Eric Livolsi Electric Utility Operations Manager
ELECTRIC UTILITY OPERATING BUDGET Presented by: Eric Livolsi Electric Utility Operations Manager City of Penticton Budget 2012 1 Electric Utility Overview Electrical Distribution System: 4150 power poles
More informationFirst Revised Sheet No. 2758L. Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/10 Utilizing FERC Form 1 Data VECTREN
Midwest ISO FERC Electric Tariff, Fourth Revised Volume No. 1 First Revised Sheet No. 2758L Superseding Original Sheet No. 2758L Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended
More informationARKANSAS PUBLIC SERVICE COMMISSION
2 nd Revised Sheet No. 61.0.1 Schedule Sheet 1 of 18 Replacing: 1 st Revised Sheet No. 61.0.1 61.0. TARIFF GOVERNING THE INSTALLATION OF ELECTRIC UNDERGROUND RESIDENTIAL DISTRIBUTION SYSTEMS AND UNDERGROUND
More informationCHAPTER 1 PRELIMINARY
JAMMU AND KASHMIR STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION No.: JKSERC/12/2011 Dated April 20, 2011. In exercise of powers conferred by Sub-Section (1) of the Section 138 of Jammu & Kashmir
More informationSenate Substitute for HOUSE BILL No. 2131
Senate Substitute for HOUSE BILL No. 2131 AN ACT concerning telecommunications; relating to local exchange carriers; concerning the Kansas universal service fund; concerning wireless communications, siting
More informationExhibit PSE-501 Period II John Story. Statement AA - Period II Puget Sound Energy Balance Sheets
Statement AA - Period II Balance Sheets Page 1 of 4 FERC 2010 Change 2011 Line No. Account Description Amount Amount Utility Plant 1. 101 Plant in Service $9,793,926,043 $478,686,201 $10,272,612,244 2.
More informationTHE NARRAGANSETT ELECTRIC COMPANY POLICY 2 LINE EXTENSION POLICY FOR RESIDENTIAL DEVELOPMENTS
THE NARRAGANSETT ELECTRIC COMPANY POLICY 2 LINE EXTENSION POLICY FOR RESIDENTIAL DEVELOPMENTS When a developer, contractor, builder or other customer ( Developer ) proposing to construct a residential
More informationDepreciable assets 361 Structures. Easements. Depreciable assets 366 Structures. and easements. Mains and TBS. includes services.
Measuring Regulating 356 Purification Other Storage Total Assets and easements 360.1 360 Rights Depreciable 361 Structures 382 Gas Holders 363 Purification 363.1 Liquefaction 363.2 Vaporizing 363.3 Compressor
More informationFormula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2019 Utilizing FERC Form 1 Data
Attachment O Page 1 of 5 Formula Rate - Non-Levelized Rate Formula Template For the 12 months ended 12/31/2019 Utilizing FERC Form 1 Data Northern Indiana Public Service Company LLC Line Allocated No.
More informationTOWN OF MANSFIELD, MASSACHUSETTS MUNICIPAL ELECTRIC DEPARTMENT REPORT ON EXAMINATION OF BASIC FINANCIAL STATEMENTS YEARS ENDED JUNE 30, 2012 AND 2011
REPORT ON EXAMINATION OF BASIC FINANCIAL STATEMENTS YEARS ENDED REPORT ON EXAMINATION OF BASIC FINANCIAL STATEMENTS YEARS ENDED TABLE OF CONTENTS PAGE Independent Auditor s Report 1-2 Report on Internal
More informationIMPORTANT INFORMATION Invitation to Bid No. TS12-S-10 Kindly acknowledge important revisions to the terms and conditions under the bidding documents in details as follows: Volume I of IV 1. TC-SUB-01 Data
More informationCES ORGANIZATIONAL CHART ZATIONAL CHART
ADMINISTRATIVE SERVICES ORGANIZATIONAL CHART C-100 Actual 2013-13 Adopted 2013-14 Year-End Estimated 2013-14 Proposed 2014-15 Proposed 2015-16 PROGRAM EXPENSES/REVENUES Salaries & Benefits $ 1,648,890
More informationUNDERWRITING GUIDELINES FOR TECHNOLOGY MANUFACTURERS SEGMENT
UNDERWRITING GUIDELINES FOR TECHNOLOGY MANUFACTURERS SEGMENT Local exceptions to these underwriting guidelines may apply. Please consult with your underwriter or sales executive for details and to discuss
More information