Asbestos Management Plan for Tunsgate Square, Guildford March 2012
|
|
- Willis French
- 5 years ago
- Views:
Transcription
1 Asbestos Management Plan for Tunsgate Square, Guildford March 2012 Scope of plan and responsibilities 1. This plan is for the management of asbestos containing materials (ACM) at Tunsgate Square in accordance with the requirements of the Control of Asbestos Regulations 2006 and the Approved Code of Practice and Guidance (L127 second edition) The management of asbestos in non-domestic properties. 2. As managing agents, CBRE, are responsible for the management of asbestos in those areas of the property for which CBRE has the responsibility for maintenance, namely the common and landlord areas. This plan primarily covers these areas and the duties of CBRE to manage ACM in these areas. The CBRE nominated responsible person for asbestos management at the premises is Nicola Mendelssohn. 3. Other parts of the premises (that is tenanted areas) have been included in the asbestos risk assessment that has been undertaken by CBRE. Information on the location and condition of ACM or suspected ACM has been given to the tenants to form the basis for their own management plans. Tenants are responsible for complying with legislative requirements and for the safe management of ACM within their demise. On no account should tenants, or their contractors, damage or disturb ACM in any way. 4. All contractors who work on the premises have a responsibility to do so according to safe working practices. They must acquaint themselves with the location and condition of ACM and consider the implications of their proposed work activity. On no account should contractors work on, or in the vicinity of, ACM in a manner that could damage or disturb the material and cause asbestos fibre release. 5. This plan has been prepared in the context of the overall CBRE Asbestos Management Policy and Management Plan, and forms part of CBRE integrated management of Health and Safety at the premises. Asbestos Surveys and Risk assessments 6. CBRE have delegated the task of carrying out an asbestos survey and risk assessment to a competent organisation accredited for the purpose by the United Kingdom Accreditation Service (UKAS).
2 7. The survey was last done by SM&MS Consulting. Previous surveys were done by BES Consulting in 2009 and by Kitsons Environmental Europe Ltd in 2001 and The results of the asbestos survey and risk assessment are held on an electronic database called Meridian. This database is updated to reflect any changes to the condition of ACM, or if work has been done to remove or treat ACM. Location and condition of ACM 9. The survey has located ACM within the premises. The position, type, extent, condition and material risk assessment of ACM is recorded on the Asbestos Register attached to this management plan. 10. On the basis of the material risk assessment, and in consideration of the potential for fibre release and likelihood of disturbance, actions to manage the ACM have been recommended and listed at the end of this document. Contacts in an emergency or on discovery of suspect material 11. In the event of an emergency involving ACM or suspected ACM, or on discovery of suspected ACM not listed on the register, the following should be contacted in the first instance: Nicola Mendelssohn The CBRE responsible person will contact a competent organisation accredited by UKAS. Management plan - management actions 13. The CBRE responsible person for asbestos management at the premises will implement the following management actions in compliance with the requirements of the ACOP and overall CBRE Asbestos Policy and Management Plan: Item Updating records Labelling asbestos materials Informing contractors Management action Keep all asbestos records and drawings (hard copy and electronic) updated and current. Fix hazard warning labels to ACM, and check their condition and replace as necessary. Labels should be checked as part of the regular inspection of ACM. Inform all contractors as to the location of ACM by issuing copies of the Register as part of and in conjunction with the established permit and permissions to work system. Contractors will be instructed that on no account are they to work on ACM or do anything to disturb it.
3 Informing staff Informing tenants Informing the fire services Dealing with areas not accessed during the survey Keeping ACM in good condition Reviewing the plan Inform CBRE staff, including new starters, as to where information on ACM can be found, and any locations of ACM that staff might disturb either accidentally or during their work. Give copies of the management plan including the current asbestos register to tenants. Give new tenants these documents as part of the tenant s information pack. Ensure the asbestos plan is available in the event of an emergency. Treat any no-access areas as containing ACM until there is strong evidence that they do not. Arrange annual inspections of all ACM listed in the Register, to check that its condition has not deteriorated and update the risk assessments and records. If ACM has been damaged or disturbed review if any further actions are required to repair or remove it, or to prevent further damage. Audit and review this plan and the arrangements for managing asbestos, and revise as necessary. Management Plan Control Actions 14. The CBRE nominated responsible person will liaise with an UKAS accredited asbestos analysts for the supervision of asbestos abatement works, to manage the actions identified to repair or remove ACM. Only approved contractors licensed by the HSE for asbestos removal will be appointed, and all works will be in accordance with the Control of Asbestos Regulations 2006.
4
5
ASBESTOS POLICY. November 2015 November 2018 Chair Person/Office Bearers Signature:
ASBESTOS POLICY Date Approved Proposed Review Date November 2015 November 2018 Chair Person/Office Bearers Signature: CASSILTOUN HOUSING ASSOCIATION LIMITED CASTLEMILK STABLES, 59 MACHRIE ROAD, GLASGOW
More informationASBESTOS POLICY (2017)
ASBESTOS POLICY (2017) 1.0 INTRODUCTION The Association has stated its commitment, through its Health & Safety Policy Statement, to take all reasonable steps to ensure the health, safety and welfare at
More informationGuideline Leaflet L11: Control of Asbestos at Work Regulations 2012
Guideline Leaflet L11: Control of Asbestos at Work Regulations 2012 New regulations about managing the risk of asbestos were introduced in 2012. This leaflet explains what is required by these regulations
More informationAsbestos Management Policy and Plan
Asbestos Management Policy and Plan Trust Board Approval Date 29 January 2018 Effective Date 29 January 2018 Planned Review Date September 2018 Web Access Internet Issue 2 Prepared by: Verified by: Date:
More informationASBESTOS CONTAINING MATERIALS POLICY
ASBESTOS CONTAINING MATERIALS POLICY 1.0 INTRODUCTION 1.1 Almond Housing Association Limited (AHA Ltd.) recognises the risks to the health of those who have to work with materials containing asbestos (ACM
More informationAsbestos Management. Date of Approval: Date for Next Scheduled Review: Review Body: Equality Impact Assessment Complete: Policy Published on Web:
Asbestos Management Policy Title: Policy Author: Date of Approval: Date for Next Scheduled Review: Review Body: Asbestos Management Diane Hendry MC Equality Impact Assessment Complete: Policy Published
More informationPolicy & Procedures for the management of Asbestos Containing Materials
Limited Policy & Procedures for the management of Asbestos Containing Materials Housing Management/Maintenance Sub- Committee submission: 20 February 2018 Approved: 20 February 2018 Review date: February
More informationAsbestos Management Policy
Asbestos Management Policy Reviews and Revisions Date Reason Reviewer Next review date Approved by 28/07/2015 New members of working group L Salkeld 28/07/16 L Salkeld 10/02/2016 Following an incident
More informationAsbestos Management Policy
Asbestos Management Policy Originator: Executive Management Team Approval Date: Policy and Strategy Policy 18 July 2017 Review date: July 2018 1 Introduction 1.1 1.2 1.3 1.4 The scope of this Policy sets
More informationHealth & Safety Guidance
St Bartholomew & All Saints Parochial Church Council Health & Safety Guidance Section C.07 Control of Asbestos at Work Regulations Guidance No: SBC.09 Issue No: 03 Issue Date: Mar 2017 Review Date: n/a
More informationRisk Management Guidelines
Management of Asbestos in Buildings - Occupiers General Guidance Introduction Asbestos continues to be a major occupational health issue in the UK. It currently causes about 3,000 fatalities a year and
More informationHealth & Safety Policy HSP 06 Asbestos Management Version Status Date Title of Reviewer Purpose/Outcome
Health & Safety Policy HSP 06 Asbestos Management Version Status Date Title of Reviewer Purpose/Outcome 1.0 Draft 07.03.2016 David Maine 1 st Draft for consultation/review 1.1 Approved 22.12.2016 David
More informationControl of Asbestos at Work Regulations 2002
If telephoning please ask for: Mrs. Wilson. Our ref: JSW/MW/LD1152 Your ref: 26th November, 2002 Direct Dial: 0131 240 2213 Email jwilson@cofscotland.org.uk TO: PROPERTY CONVENERS OF CHURCH OF SCOTLAND
More informationPROJECT NAME. Risk Management Log
Risk Management Log Document Number:JobNo/001 Revision:0 Revision date:dd/mm/yyyy Document Owner: Levitt Bernstein QMS/SF/3-07-04/08.06.11 PAGE 1 OF 9 Purpose: The Risk Management Log is a record of each
More informationPolicy A6 Health & Safety Appendix 4 - Control of Asbestos
Policy A6 Health & Safety Appendix 4 - Control of Asbestos Contents 1. Policy Statement 2. Introduction 3. Objectives 4. Statutory Requirements 5. Roles and Responsibilities 5.1 The Trust 5.2 Local Governing
More informationDIOCESE OF LINCOLN GUIDANCE ASBESTOS Diocesan Advisory Committee for the Care of Churches
DIOCESE OF LINCOLN GUIDANCE ON ASBESTOS Diocesan Advisory Committee for the Care of Churches July 2004 The legal position of PCCs regarding Asbestos From 21 st May 2004 each PCC has had an additional responsibility.
More informationContractor Management Procedure
Contractor Management Procedure Purpose Skillset Limited ( Skillset ) has a duty under the NSW Work Health and Safety Act and Regulations 2011 (the Legislation ) to prevent and/or to minimise risk in the
More informationThe Community Housing Group & all subsidiaries. Executive Business Manager (Repairs & Voids)
Business Units: The Community Housing Group & all subsidiaries Date of Document: March 2015 Date for Next Review: March 2018 Authors: Executive Business Manager (Repairs & Voids) Introduction This document
More informationJOB DESCRIPTION. Supported Housing Services Manager
JOB DESCRIPTION Job Title: Responsible To: Responsible for: Scheme Manager Supported Housing Services Manager Cleaners Main Purpose of Job To provide an effective intensive housing management service to
More informationAsbestos. When it feels irreplaceable, trust
Asbestos Asbestos is a naturally occurring, fibrous material which if inhaled can cause serious diseases. These include cancers of the lungs and chest linings which can take many years to develop following
More informationControl of Asbestos Regulations 2012 (SI 2012 No. 632)
Control of Asbestos Regulations 2012 (SI 2012 No. 632) Part 1: Preliminary Part 1 covers commencement, interpretation and application. 2: Interpretation This contains a number of definitions. Of particular
More informationLightning Protection Policy
Lightning Protection Policy Estates Policy EM&I C031 Version 2.0 28 th May 2015 Section Contents Page 1.0 Introduction... 4 2.0 Purpose... 5 3.0 Scope... 5 4.0 Roles and Responsibilities... 7 4.1.1 UCL
More informationRisk Assessment Policy
Risk Assessment Policy Introduction All independent schools are legally required to have risk assessments in place that cover a great many school activities, including all the many educational visits,
More informationHealth & Safety Policy
Health & Safety Policy K4S Security Ltd Imperial Office 2a Heigham Road East Ham London E6 2JG Registered Company Number: 09646212 Policy Date: 12 April 2018 1/14 Contents Page 1.0 General Statement of
More informationSub-Contractor Pre-Qualification Questionnaire
Sub-Contractor Pre-Qualification Questionnaire ACES Pre-Qualification Questionnaire (PQQ) To become an ACES Approved Supplier requires the completion and approval of this Pre-Qualification Questionnaire
More informationReactive maintenance repairs policy. August 2013 August If you require this policy in a different format please ask a member of staff
1 M 4 Reactive maintenance repairs policy Date of approval Review date August 2013 August 2016 If you require this policy in a different format please ask a member of staff Foreword 2 Elderpark Housing
More informationPolicy for Occupational Health, Safety and Environment Requirements for Contracted Construction and Maintenance Work
Policy for Occupational Health, Safety and Environment Requirements for Contracted Construction and Maintenance Work Policy Statement Rationale Construction and Maintenance work undertaken by contracted
More informationRisk Assessment Policy
Risk Assessment Policy To be accepted if agreed December 2016 Review Date December 2018 Overview This policy is designed to assist the school in fulfilling their legal duties in assessing risks. Risk management
More informationGAS SAFETY POLICY & PROCEDURE
GAS SAFETY POLICY & PROCEDURE Date Approved Proposed Review Date January 2016 January 2019 Chair Person/Office Bearers Signature: CASSILTOUN HOUSING ASSOCIATION LIMITED 59 Machrie Road, Castlemilk, Glasgow
More informationSubcontractor Approval Form
Page 1 of 8 1. General Information Company / Partnership / Individual Name: Address: Telephone: Email: Website: Main Contact Name: Telephone: Email: 2. Financial Information Bank Name: Account Name: Accounts
More informationLEGAL SUPPLEMENT 1269
LEGAL SUPPLEMENT 1269 to the Government Gazette of Mauritius No. 113 of 29 November 2014 Government Notice No. 216 of 2014 THE OCCUPATIONAL SAFETY AND HEALTH ACT Regulations made by the Minister under
More informationAppendix 4 :Contractors Health and Safety Questionnaire (Form CCHSQ1) 1. DETAILS OF CONTRACTOR / SUB-CONTRACTOR Name of Company:
Appendix 4 :Contractors Health and Safety Questionnaire (Form CCHSQ1) 1. DETAILS OF CONTRACTOR / SUB-CONTRACTOR Name of Company: Address: Telephone Number: Contact for Further Information: Email Address:
More informationSite-Specific Health and Safety Agreement
: Company Site Name Complete pre-start This agreement establishes the basis on which businesses (including trades and other organisations) agree to work on a specific construction site. A Site-Specific
More informationSAFETY POLICY PART 1 - GENERAL POLICY
SAFETY POLICY PART 1 - GENERAL POLICY a. The Scope of This Policy This is the Safety Policy of National Game Fair Ltd (the Organiser) as required by Section 2(3) of the Health and Safety at Work Act 1974,
More informationThis document is meant to be a starting point for any company wanting to implement the safety passport scheme for their contractors on site.
Introduction This document is meant to be a starting point for any company wanting to implement the safety passport scheme for their contractors on site. It was put together by members of the Food & Drink
More informationProperty Risk Control Report
Religious Society of Friends (Quakers) NSW Regional Meeting Inc Head Office 119 Devonshire Street, Surry Hills, NSW, 2010 of Survey: 05/06/2018 Contents 1 SUMMARY...4 1.1 OVERALL SUMMARY...4 1.2 RECENT
More informationThe most recently inserted text is shown in bold blue
The most recently inserted text is shown in bold blue FEEDWATER LTD PROCEDURE REF: SP037 STANDARD PROCEDURES ISSUE NO: 008 STATEMENT OF COMPLIANCE WITH CODE OF DATE: 21/04/2010 CONDUCT FOR SERVICE PROVIDERS
More informationHealth and Safety. Version 5. Category: Corporate. Latest Review Date: December Review Frequency: Annual. Owner: Company Secretary
Health and Safety Version 5 Category: Corporate Latest Review Date: December 2016 Review Frequency: Annual Owner: Company Secretary Contributors: H&S Facilitator, Facilities Manager, Customer Service Manager,
More informationSCHOOL. #13 An Overview of Recent Federal Law on Asbestos in Schools an Introduction to AHERA
DRUMMOND WOODSUM & MACMAHON 245 Comm ercial Street Post Office Box 9781 Portland, Maine 04104-5081 (207) 772-1941 FAX (207) 772-3627 SCHOOL Summer 1989 Issue LAW ADVISORY #13 An Overview of Recent Federal
More informationSt George s School Windsor Castle Risk Assessment and Risk Management Policy
St George s School Windsor Castle Risk Assessment and Risk Management Policy The Governors and management of St George s School Windsor Castle are committed to promoting the safety and welfare of all members
More informationManagement of Asbestos Policy and Procedure
Policy and Procedure Reference No. P26:2009 Implementation date 1 July 2010 Version Number V2.3 Reference No: Name. Linked documents P22:2004 Health and Safety Policy and Procedure Policy Section Procedure
More informationAPPROVED CODE OF PRACTICE FOR THE SAFE CONDUCT OF TRACK AND FIELD COMPETITION
APPROVED CODE OF PRACTICE FOR THE SAFE CONDUCT OF TRACK AND FIELD COMPETITION Revised August 2017-1 - P a g e CONTENTS PAGE 2017 Updated Code of Practice 3 UKA Health & Safety Policy 4 Definitions 5 Hazard
More informationEDEN HOUSING ASSOCIATION LIMITED GAS SAFETY POLICY
EDEN HOUSING ASSOCIATION LIMITED GAS SAFETY POLICY Document Reference Number Document Author PROP04. Kevan Guest Date Document Originally Approved 15 September 2009 Revised 05 January 2012 Reviewed by
More informationDated 20 BIRMINGHAM CITY COUNCIL (1) AND THE COMMITTEE OF COURT OAK ROAD AND TENNAL LANE ALLOTMENTS ASSOCIATION (2) ALLOTMENT MANAGEMENT AGREEMENT
Dated 20 BETWEEN : BIRMINGHAM CITY COUNCIL (1) AND THE COMMITTEE OF COURT OAK ROAD AND TENNAL LANE ALLOTMENTS ASSOCIATION (2) ALLOTMENT MANAGEMENT AGREEMENT Legal Services Legal Services s LHT / PP 86679
More informationCode of Practice. The principles, standards of behaviour and service delivery requirements for all FPA Australia Corporate Members
Code of Practice The principles, standards of behaviour and service delivery requirements for all FPA Australia Corporate Members Fire Protection Association Australia Life Property Environment Introduction
More informationHIGH RISK CONSTRUCTION WORK
CONTRACTOR WHS SYSTEM STANDARD HIGH RISK CONSTRUCTION WORK EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION
More informationContractor Safety Management Element November 2018
Contractor Safety Management Element November 2018 Table of Contents 1.0 Purpose... 1 2.0 Scope... 1 3.0 Definitions... 1 4.0 Roles and Responsibilities... 2 4.1 Project Management Team... 2 4.2 Contractors...
More informationLandscape Construction. For Hard & Soft Landscaping. Standard Terms and Conditions of Contract. Artisan Hardscape Solutions Ltd
Landscape Construction For Hard & Soft Landscaping Standard Terms and Conditions of Contract Artisan Hardscape Solutions Ltd 1.0 DEFINITIONS 1.1 Client means the individual or organisation who buys or
More informationReactive Maintenance Policy
Reactive Maintenance Policy If you need this publication in larger print, audio form, Braille, or in another language, please contact our office and we will try to help you. KINGDOM HOUSING ASSOCIATION
More informationPremises Management Policy
Kenmore Park Infant & Nursery School Aims Premises Management Policy This document has been adopted by the Governing Body as the basis for the maintenance and upkeep of Kenmore Park Infant & Nursery School.
More informationRisk Assessment Policy
Risk Assessment Policy Updated: April 2018 Date of next Review: April 2019 Policy Lead: Bursar Checked by: Middle Leadership Team 1. INTRODUCTION Beachborough School will have hazards which if not controlled
More informationAPPLICATION FOR INITIAL REGISTRATION FOR ASBESTOS-RELATED WORK
STATE OF CALIFORNIA DEPARTMENT OF INDUSTRIAL RELATIONS DIVISION OF OCCUPATIONAL SAFETY AND HEALTH APPLICATION FOR INITIAL REGISTRATION FOR ASBESTOS-RELATED WORK TABLE OF CONTENTS APPLICATION INSTRUCTIONS
More informationSUB CONTRACTOR INDUCTION PACK
REQUIREMENTS FOR WORKING ON ROYAL MAIL PREMISES 1. INTRODUCTION AND PURPOSE This document sets out the arrangements that Royal Mail Property & Facilities Solutions Limited and Royal Mail [hereinafter jointly
More informationRisk Assessment Procedure
1. Introduction Risk Assessment Procedure 1.1 The Management of Health and Safety at Work Regulations 1999 set out general duties which apply to employers and are aimed at improving health and safety management.
More informationFire Protection Industry Scheme Reference SP205 Part 2
BAFE Scheme: SP205 Version 3: July 2015 Fire Protection Industry Scheme Reference SP205 Part 2 Accreditation Requirements and Guidance BAFE (British Approvals for Fire Equipment) The Fire Service College,
More information(PSL) Officer. Special Conditions: Essential User Car Allowance. Ability to work outside normal hours to meet service needs.
Job Description Directorate: Operations Service Area: Leasehold Management Job Title: Private Sector Leasing (PSL) Officer Grade: Scale 6 Special Conditions: Essential User Car Allowance. Ability to work
More informationCyclical & Planned Maintenance Procedure. This procedure relates to the establishment of programmes for cyclical and planned maintenance.
Providing Choice Addressing Inequalities Cyclical & Planned Maintenance Procedure This procedure relates to the establishment of programmes for cyclical and planned maintenance. Improving Life Opportunities
More informationRICS Practice Standards, UK. Asbestos. and its implications for members and their clients. 2nd Edition Guidance Note
RICS Practice Standards, UK Asbestos and its implications for members and their clients 2nd Edition Guidance Note Asbestos and its implications for members and their clients RICS guidance note 2nd edition
More informationPOLICY. Keywords: 1) Hazardous 2) Substances 3) Chemicals
POLICY Policy Title: Hazardous Chemicals Policy Owner: Director Human Resources Service Centre Keywords: 1) Hazardous 2) Substances 3) Chemicals Policy Code: PL158 [hr116] Intent Organisational Scope Definitions
More informationPEST CONTROL POLICY. Page 1 of 5
PEST CONTROL POLICY Page 1 of 5 Policy Owner Document Author(s) Communication & Training Methods Director of Property and New Business Maintenance Manager Circulated to LTT and OMT. The policy will be
More informationStowe School Risk Assessment Policy
Stowe School Risk Assessment Policy Created April 2011 Updated Feb 2012 Version 2 Updated January 2013 Version 3 Annual Reviewed January 2014 version 4.0 Annual Reviewed January 2015 version 5.0 Annual
More informationHealth and Safety Policy Statement
Health and Safety Policy Statement Under the Health and Safety at Work etc Act 1974 (HSW Act) employers must, so far as is reasonably practicable, provide: Safe equipment Safe substances Necessary information,
More informationLegionella Control Policy
Legionella Control Policy Originator: Executive Management Team Approval Date: Policy and Strategy Team July 2018 Review date: July 2019 1 Introduction 1.1 1.2 1.3 1.4 One Vision Housing (OVH) treats the
More informationEnvironmental Insurance
Environmental Insurance May 29, 2017 2017 SPIAO Conference 1 Environmental Insurance Absolute Exclusion under General Liability Policy except Hostile Fire Coverage can be brought back by: Endorsement -
More informationBetween the Parramatta Park Trust (the Trust) (LAND OWNER) and
PERMIT TO ENTER Between the Parramatta Park Trust (the Trust) (LAND OWNER) and (ENTRANT) DEED made the day of, over land at / known as: Address Parramatta Park Certificate of Title LAND OWNER Parramatta
More informationlinked to the Australian National University s Work health and safety policy and is one of the procedures within the WHS Management System.
Purpose This procedure describes how the Australian National University evaluates and monitors contractors work health and safety for all activities performed at the University. This procedure ensures
More informationHealth & Safety Policy& Procedure. Head Office: Marle House Oldham Broadway Business Park Broadgate Chadderton Oldham OL9 9XA
Health & Safety Policy& Procedure Head Office: Marle House Oldham Broadway Business Park Broadgate Chadderton Oldham OL9 9XA HEALTH & SAFETY POLICY CONTENTS Page Date of Last Review 1 Health & Safety Policy
More informationRISK ASSESSMENT POLICY 2018
RISK ASSESSMENT POLICY 2018 INTRODUCTION A risk assessment is an important tool in protecting employees, parents, children and visitors by analysing hazards and identifying risk reduction measures. The
More informationBetween the Western Sydney Parklands Trust (the Trust) (LAND OWNER) and
PERMIT TO ENTER Between the Western Sydney Parklands Trust (the Trust) (LAND OWNER) and (ENTRANT) DEED made the day of, over land at / known as: Address Western Sydney Parklands Certificate of Title LAND
More informationREDDITCH FRIENDS HOUSING ASSOCIATION LIMITED HEALTH AND SAFETY POLICY. 1 Policy Statement The Board of Management The Management Team 4
REDDITCH FRIENDS HOUSING ASSOCIATION LIMITED HEALTH AND SAFETY POLICY Contents Page 1 Policy Statement 3 2 Health and safety organisation 2.1 The Board of Management 4 2.2 The Management Team 4 3 Health
More informationASSET MANAGEMENT POLICY
ASSET MANAGEMENT POLICY Page 1 of 5 FULL REVIEW TRACKING A Full Review refers to a point when a the whole document is reconsidered by appropriate stakeholder to establish if it is still fit for purpose
More informationCarson, CA Inland Star Distribution Centers, Inc. PSM/CalARP
Carson, CA Inland Star Distribution Centers, Inc. PSM/CalARP CONTRACTOR PROGRAM Revision History Rev. # Description of Change Date Revised By 0 Initial Issues July 2016 PSM RMP Solutions Purpose The purpose
More informationThe Langstane Group. Legionella Management Policy
The Langstane Group Legionella Management Policy SMT approval date 24 th August 2017 Committee / sub committee Board of Management Approval date 2 nd October 2017 Implementation date 1 st November 2017
More informationContractor Policy and Procedures. Contractor. Policy and Procedures. Working Together. November Borders College 4/12/ Working Together
Contractor Working Together Policy and Procedures November 2017 Borders College 4/12/2017 1 Working Together History of Changes Version Description of Change Authored by Date 1.1 This document combines
More informationRISK ASSESSMENT POLICY
RISK ASSESSMENT POLICY Scope of the Policy The academy s Governors are committed to promoting the safety and welfare of all members of its community. Governors priority lies in ensuring that all operations
More informationGas Safety Policy
Gas Safety Policy -------------------------------------------------------------- POLICY REFERENCE INFORMATION Policy Reference Number Version Number 1 ETG GSP001 Status Current Author/Lead Peter Lee (Special
More informationProduct Contamination Insurance
Product Contamination Insurance Proposer Details 1. (a) Name of company and all subsidiary companies to be insured under this policy: (b) Company mailing address: (c) Web site: (d) Main contact name: (e)
More informationRULES AND HIRERS AGREEMENT FOR USERS OF THE PARISH FACILITIES
St Teresa of the Child Jesus, Roman Catholic Church 291 Shenley Road Borehamwood WD6 1TG 0208 953 1294 RULES AND HIRERS AGREEMENT FOR USERS OF THE PARISH FACILITIES 1 INTRODUCTION The Parish of St Teresa
More informationTerms and conditions of sale of stairlifts
Terms and conditions of sale of stairlifts These terms and conditions relate to you buying a stairlift direct from us, Stannah Lift Services Ltd. They do not apply to products you bought or are buying
More informationPEOP-048 OCCUPATIONAL HEALTH AND SAFETY MANAGEMENT SYSTEM FOR ENZED FRANCHISES
OCCUPATIONAL HEALTH AND SAFETY MANAGEMENT SYSTEM FOR ENZED FRANCHISES 01 November This Occupational Health & Safety Management System (OHSMS) is a guide only to managing occupational health and safety
More informationNATIONAL BACK EXCHANGE FRAUD POLICY
NATIONAL BACK EXCHANGE FRAUD POLICY National Back Exchange NATIONAL BACK EXCHANGE POLICY ON COUNTERING FRAUD AND CORRUPTION INTRODUCTION 1.2 In National Back Exchange, as in any other public sector organisation,
More informationWoodcote House School. Risk Management and Risk Assessment Policy
Woodcote House School Risk Management and Risk Assessment Policy 1.1 Scope This guidance is applicable to all those with responsibility for developing / implementing risk management strategy and undertaking
More informationAGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC)
AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC) FOR USE IN CONJUNCTION WITH THE FORMS OF MAIN CONTRACT FOR PUBLIC WORKS ISSUED BY THE OFFICE OF GOVERNMENT PROCUREMENT, DEPARTMENT OF PUBLIC EXPENDITURE
More informationSECURITY POLICY April 2011
SECURITY POLICY April 2011 CONTENTS Page No 1.0 Statement of Intent 1 2.0 Security Accountability Structure 2 3.0 Roles and Responsibilities 3 4.0 Reporting and Monitoring of Incidents 7 5.0 Security Procedures
More informationGuideline Safety performance reporting
Guideline Safety performance reporting Title of the document National Rail Safety Regulator Page1of4 Document reference number: A435175 Version No. Approved by Publication date 1.0 Executive Director National
More informationALAMEDA MUNICIPAL POWER INTERCONNECTION AGREEMENT GENERAL CONDITIONS
ALAMEDA MUNICIPAL POWER INTERCONNECTION AGREEMENT GENERAL CONDITIONS For Net Energy Metering of Residential, Commercial or Municipal Renewable Electrical Generation Facilities of 1 MW or Less These General
More informationSASKATCHEWAN OCCUPATIONAL HEALTH AND SAFETY REGULATIONS
SASKATCHEWAN OCCUPATIONAL HEALTH AND SAFETY REGULATIONS PART XXIII Asbestos Interpretation 330 In this Part: (a) asbestos means the fibrous form of crocidolite, amosite, chrysotile, anthophyllite, actinolite,
More informationPOLICY FOR RENOVATION AND CONSTRUCTION POLICY OVERVIEW
Updated: 05/17/2017 PROPERTY MATTERS POLICY FOR RENOVATION AND CONSTRUCTION Governing Authorities POLICY OVERVIEW This policy is set forth for the purpose of permitting the Ordinary and the parishes/institutions
More informationITW LTD T/A AVERY WEIGH-TRONIX SAFETY, HEALTH AND ENVIRONMENTAL INFORMATION
ITW LTD T/A AVERY WEIGH-TRONIX SAFETY, HEALTH AND ENVIRONMENTAL INFORMATION January 2018 1 Introduction We recognize that as a customer of Avery Weigh-Tronix, you require details of our management of safety,
More informationGAS SAFETY MANAGEMENT POLICY
GAS SAFETY MANAGEMENT POLICY Approved by Board Approved Date 22/03/2011 Version no. Review Date Q4 2013-14 S:\Central Services\Current Policies\Superseded Policies\Policy - Gas Safety.docx Page 1 of 9
More informationSTAFFORDSHIRE FIRE AND RESCUE SERVICE Copyright: Stoke-on-Trent and Staffordshire Fire and Rescue Authority 2011
STAFFORDSHIRE FIRE AND RESCUE SERVICE Copyright: Stoke-on-Trent and Staffordshire Fire and Rescue Authority 2011 TITLE: RISK BASED INSPECTION PROGRAMME AND GUIDANCE. DOCUMENT: New document CONTENTS Introduction
More informationTECH. Esurance TECH Application Form INSURANCE FOR TECHNOLOGY COMPANIES
TECH INSURANCE FOR TECHNOLOGY COMPANIES Esurance TECH Application Form Esurance TECH is an insurance package designed specifically for the technology sector. The policy includes Professional Indemnity,
More informationContractors Induction Booklet. Contractor s Name:
Contractors Induction Booklet Date Contractor s Name: Business Name: The following information relates to Work Health & Safety and has been designed and implemented by the Owner s Corporation (OC) and
More informationCONTRACTOR CONTROL DISCIPLINARY PROCESS
CONTRACTOR CONTROL DISCIPLINARY PROCESS 1.0 Purpose This safety instruction has been written to support HSP 2050 - Controlling Contractors, and shall be used in the event of Health, Safety and Environment
More informationCabinet Resources Committee Date 4
AGENDA ITEM: 18 Pages 147 153 Meeting Cabinet Resources Committee Date 4 th April 2012 Subject Report of Summary Extension of Term Maintenance Contracts Cabinet Member for Resources and Performance To
More informationSupplier accreditation instructions
Supplier accreditation instructions Synergy s supplier accreditation process has been established to ensure that potential liability risks are managed, internal processes support best practice principles,
More informationPractical Asbestos Management
Faithful+Gould Practical Asbestos Management IOSH East Anglia Branch Newmarket Racecourse 20th October 2017 Asbestos Surveys 1. Management Survey Duty to identify the presence of acms Duty to manage acms
More informationCPM. Application Form INSURANCE FOR CYBER, PRIVACY & MEDIA RISKS
CPM INSURANCE FOR CYBER, PRIVACY & MEDIA RISKS Application Form This is an application for a cyber, privacy and media liability package policy aimed at a wide range of companies and professionals. CPM
More informationControl of Contractors Policy
Reference Number: UHB 163 Version Number: 2 Date of Next Review: 19/07/2019 Previous Trust/LHB Reference Number: Control of Contractors Policy Policy Statement To ensure the Health Board delivers its aims,
More informationRisk Assessment Policy (Trust, Summer, Senior and Prep School & EYFS)
Risk Assessment Policy (Trust, Summer, Senior and Prep School & EYFS) Introduction St Bede s School Trust (hereafter referred to as Bede s) clearly recognises that a failure to take reasonable safety precautions
More information