GNI PROPOSALS ON NEW CONNECTIONS POLICY JANUARY 2015

Size: px
Start display at page:

Download "GNI PROPOSALS ON NEW CONNECTIONS POLICY JANUARY 2015"

Transcription

1 2015 GNI PROPOSALS ON NEW CONNECTIONS POLICY JANUARY 2015

2 Contents Background... 2 Rationale for Change... 2 Proposal 1: Amendments to Financial Security Criteria... 3 Proposal 2: Inclusion of Transmission Revenue in all appraisals... 8 Proposal 3: Amendment of Institutional I & C Customers Proposal 4: Proposals on Existing Gas Areas Proposal 5: Group Sites (different entities, same corridor) Proposal 6: Group Sites (same entity, different sites) Proposal 7: Treatment of CNG Connections Summary & Conclusions GNI proposals on Connection Policy Dec 14 1

3 Background The Connections Policy was approved by the CER on 6th April, 2006 and is a single connections policy dealing with connections to both the Transmission and Distribution networks. The policy sets out the detailed criteria for the evaluation of extensions to the gas network, including extensions to towns not currently served by natural gas. While there were some changes to the policy in the interim, the current policy has been in effect since April This paper seeks to outline some proposed amendments to the connections policy to enhance the level of economic connections to the gas network. The context of this review is that areas of the current policy may be hampering the full realisation of the potential economically efficient demand and load growth available for the gas network in Ireland. While the overall risk will be increased, Gas Networks Ireland (GNI) believe that this is mitigated as these proposed changes will facilitate additional connections, who would not otherwise connect to the Natural Gas network under the existing Connections Policy. The addition of the extra load to the system will have the effect of reducing tariffs for existing customers in the long term. Separate to this review of the Connections Policy, GNI is working on the roll-out of a range of initiatives aimed at furthering public awareness of the availability and benefits of natural gas versus other fuels. Initiatives to promote the use of natural gas as a clean, efficient and cost competitive fuel for transport, along with integration of biogas in the network are also currently being implemented. Rationale for Change There are significant benefits associated with increasing the load on the gas network. A key benefit is the ability to spread the cost of running the network over a larger customer base, thus achieving economies of scale and a lower tariff rate for customers. New incremental load also offsets decreases in consumption arising from the loss of existing gas sites (e.g. disconnected sites) and/or lower gas usage by existing gas sites. Encouraging the connection of new customer load where it is efficient which should in the medium and long term increase throughput and reduce unit tariffs for all gas customers --- Current Connection Policy GNI proposals on Connection Policy Dec 14 2

4 Proposal 1: Amendments to Financial Security Criteria Background and Key Issues: Under the provisions of the current connections policy, Financial Security (FS) is required where the total cost of a connection, less the Customer Contribution, is at least 250,000. Where a connection meets this threshold, the customer must provide appropriate Financial Security in accordance with the Financial Security policy and sign up to a Large Network Connection Agreement (LNCA). In light of feedback from new and potential customers, a review of the 250k threshold is appropriate. While there will always be increased risk associated with adjusting the requirements of FS to make it easier for more customers to connect to the network, it is important to ensure growth such that tariffs for existing customers will not increase in the long term. This needs to be balanced with the Regulated Asset Base being underpinned appropriately by the provision of Financial Security. It is not proposed to amend section of the current Connections Policy which states that for Large Daily Metered and Daily Meters customers, a de minimis level of capacity will be set in the Capacity Register for the term required to pay back the outstanding connection costs. The de minimis level of capacity will be based on the projected load profile provided by the customer and used in the connection appraisal. The risk of an LDM or DM customer booking less capacity than was appraised would therefore not materialise. The increased risk associated with the proposed changes is reduced to the possibility of a new I&C customer disconnecting. In practice, few large customers disconnect within their capacity commitment period, and in general, if a large customer does disconnect, a new customer will take over the premises. Considering the above, and after completing an analysis of the need for Financial Security, it is clear that the additional throughput stemming from these otherwise non-users, will bring down the tariffs in the long term and benefit all customers on the network. It is the view of GNI that the benefits of additional growth outweighs the overall risk to the system as a result of the changes proposed. For example, GNI have identified a number of customers who have expressed interest in connecting but have highlighted the LNCA and the Financial Security as a barrier to proceeding with a connection. GNI has done some analysis and if three of these missed opportunities did connect to the Natural Gas network, the impact is a potential 0.24% reduction in the Distribution tariff. GNI proposals on Connection Policy Dec 14 3

5 GNI proposed changes Proposed amendments to the FS for new connections are outlined below: i. Increase the FS threshold ii. iii. Introduce a tiered threshold for FS that recognises the relative payback period for alternative projects Adjust the credit rating applied to Letters of Credit for Financial Security associated with new connections Proposal 1.1: FS Threshold GNI believe it is appropriate the raise threshold at which Financial Security applies. A base threshold of 500k is proposed as GNI s view is that the current threshold of 250k is too low. Proposal 1.2: Tiered Threshold GNI believe it is appropriate to introduce a tiered threshold to more appropriately reflect the relative payback periods of alternative connections. If Project A has a quicker payback period than Project B then all else being equal, the relative financial risk of Project A is lower and this should be reflected by the requirement for Financial Security. The GNI proposals are as follows: If the project becomes NPV positive in 7 years or more, and/or a supplemental contribution is required, the proposed threshold for Financial Security is 500k. If the project becomes NPV positive in years 4, 5 or 6, the proposed threshold for Financial Security is 750k. If the project becomes NPV positive in 3 years or less, the proposed threshold whereby Financial Security is required, is 1m. NPV Positive in Threshold LNCA Required FS Required >= 7 years 500K Above Threshold only Above Threshold only 4-6 years 750K Above Threshold only Above Threshold only <= 3 years 1m Above Threshold only Above Threshold only Note: For all of the above cases, the current threshold is 250k and a Large Network Connection Agreement is required. GNI proposals on Connection Policy Dec 14 4

6 The proposal is that a Large Network Customer Agreement is only required when the FS threshold is met, an NPV amount under the appropriate threshold is covered by using the standard I&C Agreement. The benefit of this amendment is that the FS requirement is more closely based on the risk profile of the new connection regarding the speed of payback for investment in the gas network i.e. recognising the relative risk of different projects with different payback periods. If Project A has a quicker payback period than Project B then all else being equal, the relative financial risk of Project A is lower and this should be reflected by the requirement for Financial Security. In this way, connections that cover their costs and contribute downward pressure to tariffs in a relatively short period are facilitated and incentivised to connect to the gas network through the removal of the requirement for financial security. Proposal 1.3 Financial Security Credit Ratings Under the current financial security policy, if the connecting entity is rated BBB or higher by S & P and/or BBB or higher by Fitch and/or Baa2 or higher by Moody s the customer will be exempt from providing financial security. Connections by such entities are not considered the norm however. Financial security is required in the majority of cases. The most popular (and practical) form of financial security for new connections is a letter of credit. Under the current financial security policy, the letter of credit must be issued by either: (a) a Bank with long term unguaranteed unsubordinated debt rated at least AA by S&P and/or AA2 by Moody s and/or AA by Fitch. OR (b) a subsidiary of a Bank which has total balance sheet assets of not less than 1,000 million (or equivalent in other currencies) and the long term unguaranteed unsubordinated debt that is rated at least A by S&P or A2 by Moody s or A by Fitch. Whilst many banking institutions would have met this criteria when the policy was initially written, the benchmark needs to be reviewed to allow connecting customers procure a letter of credit from robust financial institutions that they regularly transact with. To achieve this, GNI s view is that the financial security approach applied to shippers financial security (which is typically of a much larger scale than new connections) should be differentiated from that applied to new connections. GNI proposals on Connection Policy Dec 14 5

7 GNI proposed changes Taking account of the current financial circumstance along with customer feedback during discussions with potential new customers as part of the connection process has highlighted difficulties for new customers (e.g. I&C sector) in putting the required provisions of the current financial security policy in place such that they are unable to use the banks they regularly transact with. GNI therefore propose the addition of the following text within clause of the Financial Security Policy: In respect specifically of new connections, and with the prior written approval of the Transporter and where the Financial Security Amount is less than or equal to 1,000,000, an irrevocable standby letter of credit in or substantially in the form attached at Appendix 1, or in such other form as may be acceptable to the Transporter (a Letter of Credit ) issued for the account of the Counterparty in favour of the Transporter which Letter of Credit shall allow for partial drawings, if necessary, and shall provide for payment to the Transporter forthwith on demand and shall be issued by a Bank with long-term unguaranteed unsubordinated debt rated at least BBB by S&P and/or Baa2 by Moody s and/or BBB by Fitch and which has total balance sheet assets of not less than 1,000 million (or equivalent in other currencies) GNI proposals on Connection Policy Dec 14 6

8 A summary of the initiatives on financial security is outlined below: Initiative Number Outline of Initiative Rationale 1 Increase the base threshold for both the Financial Security and Large Network Connection Agreement from 250k to 500k 2 Introduce a tiered threshold (ranging from 500k to 1m) for financial security that reflects the relative payback period 3 Adjust the minimum credit ratings requirement where the Financial Security amount is <= 1m GNI s view is that the value/threshold of FS was set too low initially In addition, the threshold needs to be adjusted to reflect time value of money changes since the policy was last updated. This change provides a risk-adjusted approach to financial security under which connections that involve lower financial security should have more flexibility Taking account of the current financial circumstance along with customer feedback during discussions with potential new customers as part of the connection process has highlighted difficulties for new customers (e.g. I&C sector) in putting the required provisions of the current financial security policy in place such that they are unable to use the banks they regularly transact with. GNI proposals on Connection Policy Dec 14 7

9 Proposal 2: Inclusion of Transmission Revenue in all appraisals Each new connection provides incremental revenue for both the transmission and distribution networks. However, under the current policy, only the following sectors recognise transmission revenue in the appraisal exercise: 1. New Towns 2. Loads with consumption greater than 57.5 GWh/annum 3. Connections that involve investment in transmission assets 2.1 Transmission Exit Capacity Revenue: At the time of the last policy change, there was extensive flexibility for shippers to optimise their transmission exit capacity bookings through internal transfers in their portfolio and trading with other shippers. Therefore it was very difficult to determine the incremental benefit of a new connection on transmission exit revenue. A recent key change in the market has seen the removal of trading transmission exit capacity on a secondary basis. In the new market structure, shippers need to book peak capacity pertaining to each gas point and cannot rely on a portfolio effect to transfer transmission exit between points (or trade with shippers). It is therefore appropriate to recognise the incremental transmission exit revenue benefit from each connection, and amend the Connection Policy accordingly to reflect this. With this in mind, it is proposed that transmission exit revenue be extended to the appraisal of all categories of connection (i.e. Transmission exit revenue should be included in the appraisal for all sectors). This would be based on a commitment by the customer on de minimis transmission exit bookings for the required period which ensures that the Transmission Exit Capacity revenue does indeed materialise. Even though the fact that no Large Network Connection Agreement would be applied, a contract is still put in place and the customer would have an obligation to book the de minimis level of capacity as per the Connections Policy. Under the current Connections Policy, only 80% of Distribution revenues are generally included in the appraisal, therefore the de minimis level of capacity only applies to Distribution Supply Point Capacity. However, if Transmission revenues were included in the appraisals, it is proposed that Transmission Exit Capacity would also be included in the de minimis level of capacity required and the customer would be obliged to book both the de minimis level of Distribution Supply Point Capacity and Transmission Exit Capacity until the cost of the connection was paid off. GNI proposals on Connection Policy Dec 14 8

10 2.2 Transmission Entry Capacity Revenue: In terms of transmission entry, shippers book this on a portfolio basis and are able to trade transmission entry with other shippers. It is assumed each connection will always offer incremental entry bookings to the network as the shipper must increase entry bookings to accommodate the new load. To establish what level of entry revenue is appropriate to include in the appraisal, GNI have undertaken a study to review the relative ratio of total transmission entry capacity bookings versus total exit bookings in recent years to assess the incremental value of new connections in terms of increased total transmission entry bookings. The findings are outlined in the chart below. Before the removal of secondary transmission exit capacity, there was generally a 1:1 ratio between entry and exit bookings, as shippers optimised their aggregate entry and exit portfolios. The impact of the removal of secondary exit capacity trading outlined above is clearly evident, where the ratio falls from c. 1:1 to 0.8:1 in Gas Year 13/14. The fall in the ratio is due to the following: Exit: Since the removal of secondary exit capacity trading, shippers need to book specific firm bookings prevailing to each exit gas point and can no longer spread its exit capacity portfolio across its sites. Therefore the outcome is more firm bookings on the exit side versus the previous regime which allowed a portfolio approach. Entry: In contrast, the market conditions for transmission entry remain unchanged and therefore the ratio of entry bookings (which were not affected by the market change) to exit bookings (which increased due to the market change) has therefore decreased. On this basis, GNI propose that a factor of 80% (0.8) be applied to peak day bookings of each new connection entry revenue calculation. For example, if peak = 100 KWh, then 80% * 100 KWh = 80KWh is the volume included for incremental transmission entry revenue. GNI proposals on Connection Policy Dec 14 9

11 02-Oct Nov Jan Mar May Jul Sep Oct Dec Feb Apr Jun Aug Sep Nov Jan Mar May Jul Aug Oct Dec Feb Apr Jun Aug Sep Nov Jan Mar May Jul Aug-2014 Ratio of Total Entry Bookings to Total Exit Bookings Source: GNI Analysis The key benefits of these changes would be evident in the Medium and Small IC category of the connection policy, where currently the transmission revenue (both entry and exit) are not considered in appraisals. However Transmission revenue is received from these customers through shipper bookings, and therefore should be reflected in the appraisals. The overall benefit that this will bring will vary depending on the requirements of the specific connection: For connections which pay the 30% contribution charge and also pay a supplemental charge, there should be a decrease (if not removal) of the supplemental charge as the commercial appraisal will be improved by the inclusion of the transmission revenues. There should also be a decrease in the time for which Financial Security is required. For connections which pay the 30% contribution and are not required to pay a supplemental charge, the benefit will be that the length of time that Financial Security is required should decrease. All appraisals that currently don t recognise transmission revenue will benefit to a greater or lesser extent from this change, but the inclusion of the transmission revenue is reflective of the incremental value the new site offers in contributing to the remuneration of the network. The inclusion of such revenues should lead to a reduced upfront contribution by the customer and/or reduced financial security obligations which will make the connection to gas more commercially attractive to the prospective customer. GNI proposals on Connection Policy Dec 14 10

12 For the avoidance of doubt, this proposed amendment is only applicable to connections where transmission revenue is not recognised where it is already accounted for in appraisals (e.g. new towns) the appraisal continues as is. Initiative Number Outline of Initiative Rationale 1 Include TX Exit Revenue (100%) to all appraisals which currently don t recognise transmission revenue 2 Include TX Entry Revenue (80%) to all appraisals which currently do not recognise transmission revenue. Recent market changes which removed secondary exit support the inclusion of TX exit to all sectors. Each new connection provides some level of incremental entry capacity to the network. Based on historic data, a factor of 80% (0.8) is proposed. GNI proposals on Connection Policy Dec 14 11

13 Proposal 3: Amendment of Institutional I & C Customers The connections policy outlines that an Institutional I&C Customer is one which as a result of their load characteristics are likely to remain connected to the network for a longer period of time than a typical commercial enterprise. The current connections policy allows for a 20 year appraisal for such connection types which are institutional in nature and a list of Institutional I&C Customers is provided in Annex 3 of the current connections policy. GNI propose to include five more connection types to this list: Ports Bus Stations Waste Collection Depots Biogas Injection Facility Retail CNG Forecourts The first two additions are institutional types which are built for long term use (ports/bus stations). The remaining three additions are typically significant long term investments to provide services on a long term basis to customers: Waste collection depots are built to provide municipal services to customers for a year lifetime at a specific location Biogas plants will inject gas into the grid at the specified location for a prolonged period of time with potential expansion. Including biogas injection facilities to the institutional I & C list would encourage more installations. This in turn would support the requirement for EU Member States to undertake measures to assist the wider use of gas from renewable sources. Note biogas plants will typically be injecting/entering gas in the system whereas conventional connections in the connections policy are exit points that offtake gas from the grid. However, the exercise at the start of connecting the facility to the gas grid by way of extending the gas network can follow the same principles. Retail CNG forecourts would be developed at strategic locations to provide long-term refuelling services to CNG vehicles. GNI proposals on Connection Policy Dec 14 12

14 To summarise, GNI would propose that the list would include new additions as follows: Current List Schools Third Level Colleges Hospitals Prisons Garda Stations Stadiums Airports (airport specific infrastructure only) Railway stations Museums/Heritage Sites Fire/Ambulance Station Army Barracks Government Buildings Additional New Sites Ports Bus Stations Waste Collection Depots Biogas Injection Facility Retail CNG Forecourts Initiative Number Outline of Initiative Rationale 1 Amend institutional list to reflect additions above Extend list to other forms of institutional sites which merit a 20 year appraisal due to longevity of tenure GNI proposals on Connection Policy Dec 14 13

15 Proposal 4: Proposals on Existing Gas Areas The purpose of this proposal is to develop a policy to allow for infill projects in areas close to or including the existing gas network. The Connection Policy as it stands does not specifically address opportunities for infill in urban or suburban areas i.e. industrial zones/streets/regions that could be connected with a minimal incremental increase to the existing infrastructure. There is therefore the risk of missing opportunities for new connections and load growth, as the existing gas infrastructure is not utilised to its fullest extent on an economic basis. The existing Connections Policy does not facilitate the efficient extension of the network into an area within an already connected city/town. In practice, there are some areas within cities that could potentially be the equivalent of a small town, however, there are limited methods of connecting the areas outside of connecting a single customer (using a 7 or 20 year appraisal or appraise as a non-gas estate). This has resulted in potential missed opportunities to grow the network in existing gas areas. On this basis, GNI have two key proposals: 4.1 Introduction of a Suburb Policy GNI would advocate the introduction of an infill suburb policy under the following criteria: (i) Use the mechanics of the new towns model(see description below) to appraise these projects (ii) Where the overall investment <= 1m (iii) (iv) Where the upstream investment in the network is <= 100k The largest user is <= 50% of the total projected volumes New Towns Model: As per section 8 of the Connections Policy, New Towns are evaluated over 25 years for both Industrial Commercial Customers and New Housing to reflect the lower risk and broader growth opportunities of a diversified area load base. The economic test includes both Transmission and Distribution revenue and considers the long term potential of the entire area. It is proposed that funding for such infill suburb projects would be applied to the most economic projects with each project scored and appraised by GNI against an annual funding allowance from the CER. GNI proposals on Connection Policy Dec 14 14

16 4.2 Removal of Domestic Connection Fee in certain circumstances At present new domestic connections pay a fee of 250. GNI believe there is merit in waiving the domestic connection fee in certain circumstances to increase/accelerate the rate of new domestic connections in new towns or targeted suburbs/regions. To compete in the energy source market GNI need to entice new customers to join the gas network. A removal of the domestic connection fee in these circumstances will assist in the take up during various campaigns. Natural Gas is clean, convenient and cheap. Natural gas is always available, no ordering or storage is required; it is compatible with contemporary appliances and is the most environmentally friendly of all fossil fuels. The removal of the connection fee in certain circumstances will encourage growth in the domestic sector. Initiative Number Outline of Initiative Rationale 1 Apply new infill Suburb policy as outlined above. 2 Domestic Housing contribution for targeted suburb/urban areas and new towns allow the domestic housing connection fee to be waived under certain circumstances The new towns model could easily be adapted to streets/zones/regions ( suburbs ) and would provide consistency of application in growing out the network. Previous I&C infill appraisals didn t include take up of domestic connections arising as a result of the infill project Will increase/accelerate the rate of connection in new towns and ensures that no opportunities are missed GNI proposals on Connection Policy Dec 14 15

17 Proposal 5: Group Sites (different entities, same corridor) This proposal will only come into effect when the total investment of the project is greater than 1m. If the project is less than 1m, Proposal 4 (Infill Suburb Proposals on Existing Gas Areas) will apply. The current connections policy is silent on circumstances where GNI are approached by a number of companies or entities simultaneously on a corridor/route who collectively want to connect to the network. The current policy appraises each connection query on a case-by-case basis and GNI would like to formalise the approach for multi-clients on the same corridor. The principle would remain that GNI are remunerated for the aggregate cost of the connection, but a pro-forma share of costs would be proposed to the clients but on a case by case basis, an alternative cost sharing mechanism could be developed/agreed. To reflect this into the policy, GNI propose that the following wording would be added to the opening section of the Connections Policy which outlines the objectives/principles of the policy: Joint cost sharing mechanisms for simultaneous multiple connections from one aggregate project should be encouraged (e.g. a joint proposal from multiple potential customers on the same corridor). The key component is that the aggregate cost of the connection is fully paid through an appropriate cost sharing mechanism funded by the various clients. This cost sharing mechanism can be reviewed on a case by case basis Initiative Number Outline of Initiative Rationale 1 Apply multi-client model on a case-by-case basis whilst retaining the principles of the Connections Policy. The sharing mechanism should be flexible (including input from the clients involved), with the key issue being that the aggregate cost of connection is remunerated. This provides clarity to situations where multi-clients simultaneously want to connect to the grid. GNI proposals on Connection Policy Dec 14 16

18 Proposal 6: Group Sites (same entity, different sites) The current connections policy is silent on circumstances where GNI are approached by a company/entity to connect a number of their locations e.g. chain of retail outlets. The current policy appraises each connection query on a case-by-case basis and GNI would like to formalise the approach for multi-sites for the same client, recognising the portfolio benefit of getting all the sites rather than potentially none. If we consider the different sites as one entity rather than a number of different sites and look at the NPV as a whole, GNI feel that this would encourage more connections. If an entity is looking to set up or standardise multiple locations in Ireland, being able to apply for new connections for all of their sites with one enquiry could act as an incentive and it also offers economies of scale in progressing the multiple connections under one aggregate project. The risk in not considering this approach is that potential multi-national companies and existing indigenous companies may not decide to expand / set up in Ireland as they may take an all or nothing approach with their sites. Therefore GNI feels that multiple sites from the same company/entity should be group-appraised, with net contribution calculated in aggregate as this will encourage new connections overall. Initiative Number Outline of Initiative Rationale 1 Multiple sites from the same company/entity would be group-appraised, with net contribution calculated in aggregate. Recognises portfolio benefit of multiple sites simultaneously under one connection/one contribution. This initiative would assist in the rollout of CNG infrastructure particularly in the event that an existing forecourt operator was interested in building a network of filling stations to adopt the fuel. GNI proposals on Connection Policy Dec 14 17

19 Proposal 7: Treatment of CNG Connections The current connections policy is silent on the treatment of CNG connections as this in itself is a new technology. GNI proposes to have a clear outline in the policy regarding CNG connections. This will not preclude end users from installing their own equipment once all safety requirements have been satisfied, but where GNI build the compression and multi-storage equipment, the investment must be remunerated under the principles of the connections policy. One of the critical elements of the market for natural gas in transport is the availability of vehicles. Without a strategic network of refuelling infrastructure the manufacturers will not commit vehicles to the market. Without GNI s involvement, refuelling islands may appear without any unified national network overview. GNI are of the opinion that the provision of CNG refuelling stations at this early stage of the market will require the support and involvement of the natural gas system operator. The benefits of this approach are: High quality refuelling infrastructure in the market; Long-term view taken; Market introduction supported; Application of gas technical experience; National infrastructure support; Lower financial burden on end user; Consistent technical application across the market; and Higher probability of market adoption. In line with the current Connections Policy, customers will make a contribution of 30% towards the cost of the connection. An economic test will be undertaken (in line with existing policy), which will dictate that if the customer s capacity charges over a seven year period do not meet the cost of the remaining 70% of the cost of connection, the customer must pay the difference GNI proposals on Connection Policy Dec 14 18

20 Initiative Number Outline Initiative of Rationale 1 Include compression and multi-stage storage in the connection. Reduce costs for the gas user through increased use of gas network assets and long term reductions in tariffs 30% contribution from the customer and economic test to protect the gas user from inefficient investments Maintains consistency of service and quality GNI responsible for maintenance and care of the compression and storage The inclusion of CNG in the connection will allow GNI to provide necessary support to the market development of CNG in Ireland. Vehicle manufacturers and after sales converters will not serve the Irish market until sufficient refuelling infrastructure is in place. To date private industry has failed to provide the necessary refuelling infrastructure and so the CNG in transport market for Ireland has failed to develop. GNI proposals on Connection Policy Dec 14 19

21 Summary & Conclusions To summarise, GNI propose to amend the Connections Policy in the following ways: (i) (ii) (iii) (iv) (v) (vi) (vii) Amend the FS provisions to include tiered thresholds Recognise transmission revenue in all appraisals Extend the list of I&C institutional customers Formalise the development of infill suburb/urban projects Clarify treatment of group sites (different entities, same corridor) Clarify treatment of group sites (same entity, different sites) Clarify the treatment of CNG connections Many of the changes are to provide clarity on the treatment of certain connection types and to apply consistency (e.g. recognising transmission revenue in all appraisals). GNI believe the incorporation of these proposals are aligned with the overall principles of the policy and will assist in economically and efficiently extending the level of connections to the network, helping to spread the cost of the network across a larger number of users. GNI proposals on Connection Policy Dec 14 20

FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY

FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY FDD FIRM STORAGE SERVICE NORTHERN NATURAL GAS COMPANY FIRM STORAGE SERVICE OPTIONS Northern s firm storage service is provided pursuant to the FDD Rate Schedule located in Northern s FERC Gas Tariff. The

More information

Energy Balancing Credit Risk Management. An Overview

Energy Balancing Credit Risk Management. An Overview Energy Balancing Credit Risk Management An Overview Energy Balancing Background Network code assigns responsibility for Energy Balancing as follows: National Grid is responsible for maintaining an overall

More information

Electric Price Outlook for Indiana High Load Factor (HLF) customers December 2016

Electric Price Outlook for Indiana High Load Factor (HLF) customers December 2016 Electric Price Outlook for Indiana High Load Factor (HLF) customers December 2016 Price projection We project our prices for High Load Factor customers to increase 4 to 6 percent in 2017 compared to 2016.

More information

Large Commercial Rate Simplification

Large Commercial Rate Simplification Large Commercial Rate Simplification Presented to: Key Account Luncheon Red Lion Hotel Presented by: Mark Haddad Assistant Director/CFO October 19, 2017 Most Important Information First There is no rate

More information

Electric Price Outlook for Indiana Low Load Factor (LLF) customers December 2016

Electric Price Outlook for Indiana Low Load Factor (LLF) customers December 2016 Electric Price Outlook for Indiana Low Load Factor (LLF) customers December 2016 Price projection We project our prices for Low Load Factor customers to increase 4 to 6 percent in 2017 compared to 2016.

More information

Proposed Regulated Tariff Formula (RTF) for Eligible Customers 1 April March 2004

Proposed Regulated Tariff Formula (RTF) for Eligible Customers 1 April March 2004 Proposed Regulated Tariff Formula (RTF) for Eligible Customers 1 April 2003 31 March 2004 CER/03/031 24 th February 2003 Background The Gas (Interim) (Regulation) Act 2002 and a Ministerial Order issued

More information

Gas Innovation Reporting Framework

Gas Innovation Reporting Framework An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Gas Innovation Reporting Framework Information Paper Information Paper Reference: CRU/18/180 Date Published: 30/08/2018 Closing Date:

More information

Saving Money On Electricity Bills With Solar

Saving Money On Electricity Bills With Solar Saving Money On Electricity Bills With Solar A Net Metering Case Study As electricity rates continue to rise, smart businesses are locking in their energy costs to protect themselves against growing operating

More information

Capacity Reservation Policy

Capacity Reservation Policy Capacity Reservation Policy Abstract This document summarises the current Bord Gáis Transportation ( BGT ) process for calculating Reserved Capacity ( RC ) and Supply Point Capacity ( SPC ) reservations.

More information

European Workgroup. European Workgroup 3 rd April 2014

European Workgroup. European Workgroup 3 rd April 2014 European Workgroup Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. European Workgroup 3 rd

More information

Gas Networks Ireland Allowed Revenue and Distribution Tariffs 2016/17

Gas Networks Ireland Allowed Revenue and Distribution Tariffs 2016/17 Gas Networks Ireland Allowed Revenue and Distribution Tariffs 2016/17 Decision Paper Reference: CER/16/244 Date Published: 25 th August 2016 Queries to: Colm Ó Gormáin cogormain@cer.ie Executive Summary

More information

Tariff for Virtual Reverse Flow Product at Moffat

Tariff for Virtual Reverse Flow Product at Moffat Tariff for Virtual Reverse Flow Product at Moffat DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: FURTHER INFORMATION: Decision Paper CER/11/190 11 th November 2011 cjohnston@cer.ie The Commission for Energy

More information

Prepayment Metering in the Electricity and Gas Markets

Prepayment Metering in the Electricity and Gas Markets Prepayment Metering in the Electricity and Gas Markets DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: CLOSING DATE: RESPONSES TO: Consultation Paper CER/11/166 25 th August 2011 15 th September 2011 efarrelly@cer.ie

More information

Gas Networks Ireland Transmission Tariffs and Tariff Information 2018/19

Gas Networks Ireland Transmission Tariffs and Tariff Information 2018/19 An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Gas Networks Ireland Transmission Tariffs and Tariff Information 2018/19 Information Paper Information Paper Reference: CRU/18/179

More information

CONTENTS COMMENTARY CHARTS TABLES GLOSSARY. Section 1: Headline Inflation Section 2: Core Inflation

CONTENTS COMMENTARY CHARTS TABLES GLOSSARY. Section 1: Headline Inflation Section 2: Core Inflation COMMENTARY CONTENTS Section 1: Headline Inflation Section 2: Core Inflation CHARTS 1. National Rates of Inflation, January 2010 April 2013 2. Monthly Changes in the Cost-of-Living Index, January 2010 April

More information

Gas Networks Ireland Allowed Revenue and Transmission Tariffs 2017/18 Decision Paper

Gas Networks Ireland Allowed Revenue and Transmission Tariffs 2017/18 Decision Paper Gas Networks Ireland Allowed Revenue and Transmission Tariffs 2017/18 Decision Paper Reference: CER/17/275 Date Published: 30/08/2017 Queries to: Daniel Ward dward@cer.ie Public Impact Statement Gas Networks

More information

Compressed Natural Gas Funding Request Decision Paper. Decision Paper

Compressed Natural Gas Funding Request Decision Paper. Decision Paper Compressed Natural Gas Funding Request Decision Paper Decision Paper Reference: CER/16/313 Date Published: 24/11/2016 Executive Summary The Commission for Energy Regulation (CER) is today, 24 November

More information

GMARG Meeting. Ashling Hotel, Thursday 20 th August 2015

GMARG Meeting. Ashling Hotel, Thursday 20 th August 2015 GMARG Meeting Ashling Hotel, Thursday 20 th August 2015 Today s Agenda 1. Introduction 2. Review of Previous Minutes and Actions 16 July 2015 3. SMART Metering Update 4. GNI Presentation on Site Specific

More information

Making sense of the housing market

Making sense of the housing market Making sense of the housing market CHC Annual Conference December 2016 Helen Collins Market overview Government priorities Reclassification and deregulation 20,000 homes Abolish RTB Home ownership Help

More information

Half Year Results 6 Months Ended 30 June July 2018

Half Year Results 6 Months Ended 30 June July 2018 Half Year Results 6 Months Ended 30 June 2018 24 July 2018 Agenda Operations and Business Review Will Gardiner, CEO Financial Review Den Jones, Interim CFO Delivering the Strategy Will Gardiner, CEO 2

More information

BEPS Action 4. Webinar. 6 July 2016

BEPS Action 4. Webinar. 6 July 2016 BEPS Action 4 Webinar 6 July 2016 With you today Daniel Head Global Transfer Pricing Services Partner, London, KPMG LLP Tel: +44 (0)161 246 4742 daniel.head@kpmg.co.uk Kashif Javed International Tax Associate

More information

Performance Report October 2018

Performance Report October 2018 Structured Investments Indicative Report October 2018 This report illustrates the indicative performance of all Structured Investment Strategies from inception to 31 October 2018 Matured Investment Strategies

More information

Contact for further information: Keith Mattinson - Director of Corporate Services Telephone Number

Contact for further information: Keith Mattinson - Director of Corporate Services Telephone Number LANCASHIRE COMBINED FIRE AUTHORITY RESOURCES COMMITTEE Meeting to be held on 28 June 2017 YEAR END TREASURY MANAGEMENT OUTTURN 2016/17 (Appendix 1 refers) Contact for further information: Keith Mattinson

More information

Direction to ESB PES on Tariffs to apply from 1 st November 2007 CER/07/191

Direction to ESB PES on Tariffs to apply from 1 st November 2007 CER/07/191 Direction to ESB PES on Tariffs to apply from 1 st November 2007 CER/07/191 22 October 2007 1 Contents 1 Background... 3 1.1 Consultation Background... 3 1.2 Large Energy Users... 4 1.3 Format of the paper...

More information

Investing in Australian Small Cap Equities There s a better way

Investing in Australian Small Cap Equities There s a better way Investing in Australian Small Cap Equities There s a better way Greg Cooper, Chief Executive Officer, Australia November 2017 Executive Summary This paper explores the small cap Australian Shares market,

More information

HYDROELECTRIC INCENTIVE MECHANISM

HYDROELECTRIC INCENTIVE MECHANISM Filed: 0-0- EB-0-000 Tab Schedule Page of 0 0 HYDROELECTRIC INCENTIVE MECHANISM.0 PURPOSE This evidence provides a description of the hydroelectric incentive mechanism and presents a review of how this

More information

Electric Price Outlook for Indiana High Load Factor (HLF) customers September 2015

Electric Price Outlook for Indiana High Load Factor (HLF) customers September 2015 Electric Price Outlook for Indiana High Load Factor (HLF) customers September 2015 Price projection Duke Energy Indiana s prices continue to drop for the fourth quarter of 2015. Depending on your total

More information

Regulation of Gas Installers with Respect to Safety, Definition for the Scope of Gas Works

Regulation of Gas Installers with Respect to Safety, Definition for the Scope of Gas Works Regulation of Gas Installers with Respect to Safety, Definition for the Scope of Gas Works DOCUMENT Final Decision Paper TYPE: REFERENCE: CER/09/083 DATE PUBLISHED: QUERIES TO: 19 th dlynch@cer.ie The

More information

European Update. 1 st October 2015

European Update. 1 st October 2015 European Update Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. 1 st October 2015 1. General

More information

Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets

Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets Energy Budgeting and Procurement: Securing Stable Energy Prices in Today s Volatile Markets Advisory Service for Energy and Climate Change John Lambert Senior Business Development Manager Direct Energy

More information

Decision on Electricity Network Connection Policy

Decision on Electricity Network Connection Policy Decision on Electricity Network Connection Policy DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: QUERIES TO: Decision Paper CER/09/138 25 August 2009 John Orme (distribution@cer.ie) The Commission for Energy

More information

Looking at a Variety of Municipal Valuation Metrics

Looking at a Variety of Municipal Valuation Metrics Looking at a Variety of Municipal Valuation Metrics Muni vs. Treasuries, Corporates YEAR MUNI - TREASURY RATIO YEAR MUNI - CORPORATE RATIO 200% 80% 175% 150% 75% 70% 65% 125% Average Ratio 0% 75% 50% 60%

More information

Energy Efficiency Opportunities Report. AMP Limited Public Report

Energy Efficiency Opportunities Report. AMP Limited Public Report Energy Efficiency Opportunities Report 2009 AMP Limited Public Report 1 Period to which this report relates Start 1 July 2008 End 30 June 2009 Part 1 Information on s completed to date Table 1.1 Description

More information

Effective Investment Policy and Strategies

Effective Investment Policy and Strategies Agenda for Today Effective Policy and Strategies For Today s Economic Environment Objectives and Goals Decisions Policy Permissible s Strategy Implementation Case Studies 2 Objectives & Goals Making Informed

More information

How to get connected to our natural gas transmission system. LNG terminals and underground storage facilities

How to get connected to our natural gas transmission system. LNG terminals and underground storage facilities How to get connected to our natural gas transmission system LNG terminals and underground storage facilities Page 2 of 10 Contents 1 INTRODUCTION... 3 2 COMMERCIAL AND CONTRACTUAL PROCEDURE FOR CONNECTING

More information

Commodity and Interest Rate Hedging Overview

Commodity and Interest Rate Hedging Overview Commodity and Interest Rate Hedging Overview November 1, 2016 The following information is current as of November 1, 2016. Memorial Production Partners LP (MEMP) intends to update this information quarterly

More information

Development of Economy and Financial Markets of Kazakhstan

Development of Economy and Financial Markets of Kazakhstan Development of Economy and Financial Markets of Kazakhstan National Bank of Kazakhstan Macroeconomic development GDP, real growth, % 116 112 18 14 1 113,5 11,7 216,7223,8226,5 19,8 19,8 19,3 19,619,7 199,

More information

Reactive Power Market Tender Development Initial Proposals

Reactive Power Market Tender Development Initial Proposals Reactive Power Market Tender Development Initial Proposals Background Obligatory Reactive Power is a mandatory service for which the requirement sits within the Grid Code (CC6.3.2). The obligatory service

More information

The 20 Minute Guide To Managed Accounts

The 20 Minute Guide To Managed Accounts The 20 Minute Guide To Managed Accounts E X P E R I E N C E I N V E S T M E N T I N N O V A T I O N Drashta Capital Pty Ltd - Australian Financial Services Licence no. 451890 - ABN 27 156 481 373 INTRODUCTION

More information

Absolute Return Fixed Income: Taking A Different Approach

Absolute Return Fixed Income: Taking A Different Approach August 2015 Absolute Return Fixed Income: Taking A Different Approach Executive Summary Historically low global fixed income yield levels present a conundrum for today s fixed income investors. Increasing

More information

Portuguese Banking System: latest developments. 2 nd quarter 2017

Portuguese Banking System: latest developments. 2 nd quarter 2017 Portuguese Banking System: latest developments nd quarter 17 Lisbon, 17 www.bportugal.pt Prepared with data available up to th September of 17. Portuguese Banking System: latest developments Banco de Portugal

More information

Proposed Direction to Bord Gáis Energy Supply regarding the application of the Regulated Tariff Formula

Proposed Direction to Bord Gáis Energy Supply regarding the application of the Regulated Tariff Formula Proposed Direction to Bord Gáis Energy Supply regarding the application of the Regulated Tariff Formula CER/04/089 1. Introduction The Regulated Tariff Formula ( RTF ) took effect on 1 April 2003 for gas

More information

Performance & Financial Analysis

Performance & Financial Analysis Performance & Financial Analysis Prepared January 11, 2015 for Mr. Happy Smart 100 Easy Street Tyler, TX 75703 Phone: (903) 555-5555 Email: hsmart@smartman.com Prepared by K. Dale Beggs President GreenLife

More information

European Update. 5 January 2017

European Update. 5 January 2017 European Update 5 January 2017 1. General Update 2 Code Status Update Code Current Status Implementation date CAM amendments Incremental Capacity EP/Council Scrutiny UNC MOD 598 raised EP/Council Scrutiny

More information

FINANCIAL MANAGEMENT STRATEGY REPORT ON OUTCOMES FOR THE YEAR ENDED MARCH 31, 2016

FINANCIAL MANAGEMENT STRATEGY REPORT ON OUTCOMES FOR THE YEAR ENDED MARCH 31, 2016 FINANCIAL MANAGEMENT STRATEGY REPORT ON OUTCOMES FOR THE YEAR ENDED MARCH 31, 2016 Manitoba Finance General Inquiries: Room 109, Legislative Building Winnipeg, Manitoba R3C 0V8 Phone: 204-945-5343 Fax:

More information

APPROVED February 27, 2018 DIRECTOR of PUBLIC UTILITY DIVISION

APPROVED February 27, 2018 DIRECTOR of PUBLIC UTILITY DIVISION February 27, 2018 February 27, 2018 February 27, 2018 Supplemental Page Fuel Cost Adjustment Factors Public Service Company Oklahoma Fuel Cost Adjustment Factors ($/kwh) Period Service Service Service

More information

Executive Summary. July 17, 2015

Executive Summary. July 17, 2015 Executive Summary July 17, 2015 The Revenue Estimating Conference adopted interest rates for use in the state budgeting process. The adopted interest rates take into consideration current benchmark rates

More information

SECOND QUARTER 2017 RESULTS. August 3, 2017

SECOND QUARTER 2017 RESULTS. August 3, 2017 SECOND QUARTER 2017 RESULTS August 3, 2017 FORWARD LOOKING STATEMENTS AND NON-GAAP FINANCIAL MEASURES This presentation contains forward-looking statements based on current expectations, including statements

More information

Media Release 9 th March 2015

Media Release 9 th March 2015 Media Release 9 th March 2015 Index declines as positive feeling towards government policy on saving fades More than half of consumers dissatisfied with the amount they save The Nationwide UK (Ireland)

More information

Explanatory Memorandum to the Education (Student Loans) (Repayment) (Amendment) Regulations 2018

Explanatory Memorandum to the Education (Student Loans) (Repayment) (Amendment) Regulations 2018 Explanatory Memorandum to the Education (Student Loans) (Repayment) (Amendment) Regulations 2018 This Explanatory Memorandum has been prepared by the Higher Education Division and is laid before the National

More information

XML Publisher Balance Sheet Vision Operations (USA) Feb-02

XML Publisher Balance Sheet Vision Operations (USA) Feb-02 Page:1 Apr-01 May-01 Jun-01 Jul-01 ASSETS Current Assets Cash and Short Term Investments 15,862,304 51,998,607 9,198,226 Accounts Receivable - Net of Allowance 2,560,786

More information

Portuguese Banking System: latest developments. 3 rd quarter 2017

Portuguese Banking System: latest developments. 3 rd quarter 2017 Portuguese Banking System: latest developments 3 rd quarter 217 Lisbon, 218 www.bportugal.pt Prepared with data available up to 18 th December of 217 for macroeconomic and financial market indicators,

More information

Financial Analysis Shows Conowingo Revenues Insufficient to Fund Additional Sediment Mitigation

Financial Analysis Shows Conowingo Revenues Insufficient to Fund Additional Sediment Mitigation Exelon Generation Media Statement Information Contact: Deena O Brien, Exelon Regional Communications Manager, 610-765-5331 Financial Analysis Shows Conowingo Revenues Insufficient to Fund Additional Sediment

More information

M A N I T O B A ) Order No. 85/14 ) THE PUBLIC UTILITIES BOARD ACT ) July 24, 2014

M A N I T O B A ) Order No. 85/14 ) THE PUBLIC UTILITIES BOARD ACT ) July 24, 2014 M A N I T O B A ) Order No. 85/14 ) THE PUBLIC UTILITIES BOARD ACT ) BEFORE: Régis Gosselin, MBA, CGA, Chair Marilyn Kapitany, BSc (Hons), MSc, Member Neil Duboff, BA (Hons), LLB, TEP, Member CENTRA GAS

More information

Distribution Tariffs. For the. Gas Year 2016/17

Distribution Tariffs. For the. Gas Year 2016/17 Distribution Tariffs For the Gas Year 2016/17 17 th August 2016 1. Introduction Gas Networks Ireland (GNI) welcomes the opportunity to present its paper to the CER on the Distribution Tariffs for 2016/17.

More information

THE B E A CH TO WN S O F P ALM B EA CH

THE B E A CH TO WN S O F P ALM B EA CH THE B E A CH TO WN S O F P ALM B EA CH C OU N T Y F LO R I D A August www.luxuryhomemarketing.com PALM BEACH TOWNS SINGLE-FAMILY HOMES LUXURY INVENTORY VS. SALES JULY Sales Luxury Benchmark Price : 7,

More information

Ontario Energy Board RP Board Proposal Regulated Price Plan for Electricity Consumers. Submission of Aegent Energy Advisors Inc.

Ontario Energy Board RP Board Proposal Regulated Price Plan for Electricity Consumers. Submission of Aegent Energy Advisors Inc. Ontario Energy Board RP-2004-0205 Board Proposal Regulated Price Plan for Electricity Consumers Submission of Aegent Energy Advisors Inc. December 21, 2004 INTRODUCTION Aegent Energy Advisors Inc. (Aegent)

More information

Cash & Liquidity The chart below highlights CTA s cash position at March 2017 compared to March 2016.

Cash & Liquidity The chart below highlights CTA s cash position at March 2017 compared to March 2016. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for March 2017 Date: May 10, 2017 I. Summary CTA s financial results are $0.6 million favorable to budget

More information

WESTERN MASSACHUSETTS

WESTERN MASSACHUSETTS Page 1 of 5 PART A - TOTAL DELIVERY RATES (1) Reconciling Rates = Sum of Part B Rates MDPU Service Rate Base Reconciling Total Revenue Energy Efficiency Charge (EEC) Renewable Total Schedule No. Area Component

More information

GLOBAL MATTERS: IS INFRASTRUCTURE A BOND PROXY?

GLOBAL MATTERS: IS INFRASTRUCTURE A BOND PROXY? Greg Goodsell, 4D Infrastructure Greg has more than 0 years' experience in global financial markets encompassing a diverse array of roles in asset management, investment banking, stock broking and treasury.

More information

FOURTH QUARTER AND FULL-YEAR 2017 RESULTS. February 23, 2018

FOURTH QUARTER AND FULL-YEAR 2017 RESULTS. February 23, 2018 FOURTH QUARTER AND FULL-YEAR 2017 RESULTS February 23, 2018 FORWARD LOOKING STATEMENTS AND NON-GAAP FINANCIAL MEASURES This presentation contains forward-looking statements based on current expectations,

More information

Further information on mid-year tariff changes following the September 2010 Customer Seminars

Further information on mid-year tariff changes following the September 2010 Customer Seminars Further information on mid-year tariff changes following the September 2010 Customer Seminars National Grid received a number of questions at the Customer Seminars on National Grid s proposal to update

More information

Gas storage: overview and static valuation

Gas storage: overview and static valuation In this first article of the new gas storage segment of the Masterclass series, John Breslin, Les Clewlow, Tobias Elbert, Calvin Kwok and Chris Strickland provide an illustration of how the four most common

More information

Gas Networks Ireland Allowed Revenues and Transmission Tariffs 2015/16. Decision Paper CER/15/ st August Colm Ó Gormáin

Gas Networks Ireland Allowed Revenues and Transmission Tariffs 2015/16. Decision Paper CER/15/ st August Colm Ó Gormáin Gas Networks Ireland Allowed Revenues and Transmission Tariffs 2015/16 DOCUMENT TYPE: REFERENCE: Decision Paper CER/15/214 DATE PUBLISHED: 31 st August 2015 QUERIES TO: Colm Ó Gormáin cogormain@cer.ie

More information

Mechanics of Cash Flow Forecasting

Mechanics of Cash Flow Forecasting Texas Association Of State Senior College & University Business Officers July 13, 2015 Mechanics of Cash Flow Forecasting Susan K. Anderson, CEO Anderson Financial Management, L.L.C. 130 Pecan Creek Drive

More information

Monthly Trading Report Trading Date: May Monthly Trading Report May 2018

Monthly Trading Report Trading Date: May Monthly Trading Report May 2018 Trading Date: May 8 Monthly Trading Report May 8 Trading Date: May 8 Figure : May 8 (% change over previous month) % Major Market Indicators 9 8 Figure : Summary of Trading Data USEP () Daily Average Daily

More information

FUEL PRICE RISK MANAGEMENT POLICY REPORT "FUEL HEDGE"

FUEL PRICE RISK MANAGEMENT POLICY REPORT FUEL HEDGE FUEL PRICE RISK MANAGEMENT POLICY REPORT "FUEL HEDGE" Sep-18 FUEL PRICE RISK MANAGEMENT POLICY REPORT Sep-18 (Office of Management and Budget 09/30/2018) The Fuel Price Risk Management Policy approved

More information

FUEL PRICE RISK MANAGEMENT POLICY REPORT "FUEL HEDGE"

FUEL PRICE RISK MANAGEMENT POLICY REPORT FUEL HEDGE FUEL PRICE RISK MANAGEMENT POLICY REPORT "FUEL HEDGE" December 2018 FUEL PRICE RISK MANAGEMENT POLICY REPORT December 2018 The Fuel Price Risk Management Policy approved by the Board on February 16, 2006

More information

Looking to the medium term

Looking to the medium term Looking to the medium term Issued: 4 September 2013 Legal notice This presentation has been prepared to inform investors and prospective investors in the secondary markets about the Group and does not

More information

SCHOOL DISTRICT OF PALM BEACH COUNTY, FLORIDA SERIES 2014 TAN SALE

SCHOOL DISTRICT OF PALM BEACH COUNTY, FLORIDA SERIES 2014 TAN SALE SCHOOL DISTRICT OF PALM BEACH COUNTY, FLORIDA SERIES 2014 TAN SALE September 10, 2014 Palm Beach County School District TAN Cash flow Tax Anticipation Notes are short-term financings that allow the District

More information

GUAM POWER AUTHORITY. Management Discussion and Analysis Year Ended September 30, 2007

GUAM POWER AUTHORITY. Management Discussion and Analysis Year Ended September 30, 2007 GUAM POWER AUTHORITY Management Discussion and Analysis Year Ended September 30, 2007 The major issue in the 2007 financial statements is the allowance of $13.5 million being set up to cover the Department

More information

COMMISSION OF THE EUROPEAN COMMUNITIES COMMISSION STAFF WORKING DOCUMENT. Annex to the. Report from the Commission

COMMISSION OF THE EUROPEAN COMMUNITIES COMMISSION STAFF WORKING DOCUMENT. Annex to the. Report from the Commission COMMISSION OF THE OPEAN COMMUNITIES Brussels, 29.5.2008 SEC(2008)1938 COMMISSION STAFF WORKING DOCUMENT Annex to the Report from the Commission Annual Report from the Commission on the Guarantee Fund and

More information

LONDON BUSINESS SURVEY APRIL 2018

LONDON BUSINESS SURVEY APRIL 2018 LONDON BUSINESS SURVEY APRIL 2018 Sponsored by London s business climate 22% feel more optimistic for the economy over the next six months 25% feel more optimistic about their business prospects over the

More information

Savings Index maintains momentum in January

Savings Index maintains momentum in January Media Release Tuesday 10 th February 2015 Savings Index maintains momentum in January The Nationwide UK (Ireland) / ESRI Savings Index, which measures overall sentiment towards saving in Ireland, increased

More information

Supervisory Framework for Administration of Guarantees of Origin

Supervisory Framework for Administration of Guarantees of Origin Supervisory Framework for Administration of Guarantees of Origin DOCUMENT TYPE: Decision Paper REFERENCE: CER/11/824 DATE PUBLISHED: 17 November 2011 The Commission for Energy Regulation, The Exchange,

More information

KENTUCKY UTILITIES COMPANY Kentucky Retail 2018 Monthly Billing Adjustments

KENTUCKY UTILITIES COMPANY Kentucky Retail 2018 Monthly Billing Adjustments 2018 Monthly Billing Adjustments ENVIRONMENTAL COST RECOVERY SURCHARGE GROUP 1 GROUP 2 Rate GS, PS, FUEL ADJUSTMENT CLAUSE ($ per kwh) DSM RATES ($ per kwh)(1) Rate TODS,TODP, RTS Billed Off-System Rate

More information

August 31, 2016 Financial Report

August 31, 2016 Financial Report August 31, 2016 Financial Report Capital Metropolitan Transportation Authority 10/14/2016 Table of Contents SUMMARY REPORTS Budgetary Performance - Revenue 2 - Sales Tax Revenue 6 - Operating Expenses

More information

Portuguese Banking System: latest developments. 2 nd quarter 2018

Portuguese Banking System: latest developments. 2 nd quarter 2018 Portuguese Banking System: latest developments 2 nd quarter 218 Lisbon, 218 www.bportugal.pt Prepared with data available up to 26 th September of 218. Macroeconomic indicators and banking system data

More information

Release of EU Allowances in Germany

Release of EU Allowances in Germany Release of EU Allowances in Germany Annual report 2009 Annual report 2009 Between 1 January 2009 and 13 November 2009 KfW sold a total of 40 million EU allowances with an overall value of EUR 528,487,784.40.

More information

United States, Toronto, London, Tokyo, Hong Kong, Singapore

United States, Toronto, London, Tokyo, Hong Kong, Singapore United States, Toronto, London, Tokyo, Hong Kong, Singapore Not financial product advice: This presentation is for information purposes only and is not financial or investment advice or a recommendation

More information

QUARTERLY FINANCIAL REPORT March 31, 2018

QUARTERLY FINANCIAL REPORT March 31, 2018 California Independent System Operator QUARTERLY FINANCIAL REPORT March 31, 2018 250 Outcropping Way Folsom, CA 95630 (916) 351-4000 CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION QUARTERLY FINANCIAL

More information

A Compelling Case for Leveraged Loans

A Compelling Case for Leveraged Loans A Compelling Case for Leveraged Loans EXECUTIVE SUMMARY In the current market environment, there are a number of compelling reasons to invest in leveraged loans. In a situation where most assets are trading

More information

PC4: REVIEW OF DISTRIBUTION REVENUES COMMISSION FOR ENERGY REGULATION (CER) FINAL REPORT JUNE 2017 TECHNICAL AND ECONOMIC REVIEW

PC4: REVIEW OF DISTRIBUTION REVENUES COMMISSION FOR ENERGY REGULATION (CER) FINAL REPORT JUNE 2017 TECHNICAL AND ECONOMIC REVIEW PC4: REVIEW OF DISTRIBUTION REVENUES COMMISSION FOR ENERGY REGULATION (CER) JUNE 2017 TECHNICAL AND ECONOMIC REVIEW FINAL REPORT Prepared by: Cambridge Economic Policy Associates Ltd In association with:

More information

Department of Market Monitoring White Paper. Potential Impacts of Lower Bid Price Floor and Contracts on Dispatch Flexibility from PIRP Resources

Department of Market Monitoring White Paper. Potential Impacts of Lower Bid Price Floor and Contracts on Dispatch Flexibility from PIRP Resources Department of Market Monitoring White Paper Potential Impacts of Lower Bid Price Floor and Contracts on Dispatch Flexibility from PIRP Resources Revised: November 21, 2011 Table of Contents 1 Executive

More information

Brexit and electricity interconnectors. Jason Mann

Brexit and electricity interconnectors. Jason Mann Brexit and electricity interconnectors Jason Mann 12 May 2018 Expansion of UK interconnection capacity driven by strong fundamentals and benign policies - but complicated by Brexit Mounting political pressures

More information

QUARTERLY FINANCIAL REPORT June 30, 2017

QUARTERLY FINANCIAL REPORT June 30, 2017 California Independent System Operator QUARTERLY FINANCIAL REPORT June 30, 2017 250 Outcropping Way Folsom, CA 95630 (916) 351-4000 CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION QUARTERLY FINANCIAL

More information

Ernst & Young IFRS Core Tools. IFRS Update. of standards and interpretations in issue at 28 February 2013

Ernst & Young IFRS Core Tools. IFRS Update. of standards and interpretations in issue at 28 February 2013 Ernst & Young IFRS Core Tools IFRS Update of standards and interpretations in issue at 28 February 2013 Contents Introduction 2 Section 1: New pronouncements issued as at 28 February 2013 4 Table of mandatory

More information

Agenda. Results Presentation 27 February Appendices 1 to

Agenda. Results Presentation 27 February Appendices 1 to Results Presentation 27 February 2018 51 Agenda Results Presentation 27 February 2018 Page Presented by Overview 1 Jeff Fairburn Review of operations 3 Jeff Fairburn Outlook 13 Jeff Fairburn Financial

More information

Interconnector (UK) Limited. Charging Statement related to the IUK Access Agreement and IUK Access Code Issue 14 Applicable from 22 November 2018

Interconnector (UK) Limited. Charging Statement related to the IUK Access Agreement and IUK Access Code Issue 14 Applicable from 22 November 2018 Interconnector (UK) Limited Charging Statement related to the IUK Access Agreement and IUK Access Code Issue 14 Applicable from 22 November 2018 Issue 14 22 November 2018 1. Introduction... 1 2. Reserve

More information

Review of the GB Regulatory and Legal Framework. John Hayling, UK Power Networks

Review of the GB Regulatory and Legal Framework. John Hayling, UK Power Networks Review of the GB Regulatory and Legal Framework John Hayling, UK Power Networks UK Power Networks An Introduction End Customers Millions Service Area km² Underground Network km Overhead Network km Energy

More information

Ernst & Young IFRS Core Tools April IFRS Update. of standards and interpretations in issue at 31 March 2012

Ernst & Young IFRS Core Tools April IFRS Update. of standards and interpretations in issue at 31 March 2012 Ernst & Young IFRS Core Tools April 2012 IFRS Update of standards and interpretations in issue at 31 March 2012 Contents Introduction 2 Section 1: New pronouncements issued as at 31 March 2012 4 Table

More information

Gas Networks Ireland Distribution Tariffs and Allowed Revenue 2018/19

Gas Networks Ireland Distribution Tariffs and Allowed Revenue 2018/19 An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Gas Networks Ireland Distribution Tariffs and Allowed Revenue 2018/19 Information Note Reference: CRU/18/101 www.cru.ie Date Published:

More information

TGC-1 9M 2017 IFRS Results. November 8, 2017 Saint Petersburg

TGC-1 9M 2017 IFRS Results. November 8, 2017 Saint Petersburg TGC-1 9M 2017 IFRS Results November 8, 2017 Saint Petersburg Disclaimer The information contained herein has been prepared using information available to Public Joint Stock Company Territorial generating

More information

The Economic Outlook for Real Estate Investors

The Economic Outlook for Real Estate Investors The Economic Outlook for Real Estate Investors Dr. Mark G. Dotzour College Station, TX mdotzour@gmail.com Beginning our Initial Approach for this Flight Now Still at high altitude at rapid speed, starting

More information

Interconnector (UK) Limited. Charging Statement related to the IUK Access Agreement and IUK Access Code Issue 15 Applicable from 01 January 2019

Interconnector (UK) Limited. Charging Statement related to the IUK Access Agreement and IUK Access Code Issue 15 Applicable from 01 January 2019 Interconnector (UK) Limited Charging Statement related to the IUK Access Agreement and IUK Access Code Issue 15 Applicable from 01 January 2019 Issue 15 01 January 2019 1. Introduction... 1 2. Reserve

More information

Foxtons Interim results presentation For the period ended 30 June 2018

Foxtons Interim results presentation For the period ended 30 June 2018 Foxtons Interim results presentation For the period ended 30 June 2018 Important information This presentation includes statements that are, or may be deemed to be, forward-looking statements. These forward-looking

More information

Initiative of National Department of Health to accelerate Health Infrastructure Service Delivery

Initiative of National Department of Health to accelerate Health Infrastructure Service Delivery Initiative of National Department of Health to accelerate Health Infrastructure Service Delivery To manage the mentioned challenges, in 2010/11, Financial year, the National Department of Health (NDOH)

More information

Asset Liability Management Report 4 Q 2018

Asset Liability Management Report 4 Q 2018 Asset Liability Management Report 4 Q 2018 Performance Indicators and Key Measures Cash, Investment and Debt Balances Book Value ($M) Restricted Cash and Investments 529.8 Unrestricted Cash and Investments

More information

Natural Gas Avoided Cost Meeting. 10 a.m. 12 p.m. May 12, 2017

Natural Gas Avoided Cost Meeting. 10 a.m. 12 p.m. May 12, 2017 Natural Gas Avoided Cost Meeting 10 a.m. 12 p.m. May 12, 2017 Agenda Introduction OPUC Energy Trust Schedule for updates Overview of Process to Update Avoided Costs Proposed Updates for 2017 Possible Future

More information

Development Fund for Iraq

Development Fund for Iraq IAMB & COFE Meeting May 1213, 2008 Summary Audit Results December 31, 2007 Content Scope of work and deliverables Entities covered Financial statement Outstanding data Key issues Internal control material

More information