Submitted to the CAISO through the CAISO BPM Change Management application

Size: px
Start display at page:

Download "Submitted to the CAISO through the CAISO BPM Change Management application"

Transcription

1 March 18, 2014 Submitted to the CAISO through the CAISO BPM Change Management application RE: Appeal of the Large-scale Solar Association to CAISO BPM Change Management Executive Committee on limited issues in the final BPM for Queue Management (PRR 700) The Large-scale Solar Association (LSA) hereby submits this Appeal of the final new BPM for Queue Management (BPM). LSA supports the CAISO s centralization of Queue Management provisions in a separate BPM, including those related to Material Modification Assessments (MMAs) that resulted from the stakeholder process for Interconnection Process Enhancements (IPE) Topic 15. LSA has been an active participant in the stakeholder process for PRR 700 and very much appreciates the CAISO s incorporation of most of the changes recommended by LSA in its various comment submissions. However, there are two remaining issues where LSA fears that the language in the BPM will be detrimental to the generator-interconnection process. Those issues, which are the subject of this Appeal, are as follows: Timing for processing MMA requests: The BPM would prohibit processing of MMA and other modification requests for nearly half of every year (5.5 consecutive months), potentially delaying consideration of project equipment or configuration changes needed to meet critical Power Purchase Agreement (PPA) or Generator Interconnection Agreement (GIA) development deadlines. Moreover, the applicability of those restrictions is not clear, and the restrictions themselves are not clearly defined in any posted document. PTO submission of modification requests to CAISO: The BPM states that the CAISO believes that Participating Transmission Owners (PTOs) should submit requests to the CAISO for approval of schedule changes due to construction delays for Network Upgrades (NUs) or PTO s Interconnection Facilities (IFs). However, the safeguards contained in the information requirements for such submission would be meaningless if the PTO can simply choose not to follow this process. LSA asks the CAISO to revise the BPM in the manner described below. (1) Remove the timing prohibition on submission and processing MMA and other modification requests during and just before interconnection studies, especially during the GIDAP Reassessment process. (2) Require PTO submission of requests to the CAISO for approval of schedule changes due to NU or IF construction delays, and notice to ICs of such changes. These issues, and the grounds for the Appeal in each area, are explained further below. 1

2 TIMING FOR PROCESSING MMA REQUESTS Background Section 3 of the BPM states as follows: The CAISO will not process modification requests from projects while the project is being studied during the Phase I Interconnection Study process or Phase II Interconnection Study process for that project, or other studies applicable to that project. The reason for this is that once a study commences, the study assumptions cannot be changed. Otherwise, the study would need to be re-started with the updated information based on the modification requests. In addition, it would not be possible for the CAISO to evaluate the potential impacts of the proposed modification on other projects during the pendency of one of these studies. Information about study timeframes is available on the CAISO website under Planning> Generator Interconnection > GIDAP Customer guidelines ( Modification requests should be submitted no later than 45 calendar days prior to the start of a study that applies to the affected generation project to avoid processing delays due to the study process. As stated elsewhere in this BPM, if an assessment cannot be completed within the 45 day timeline, the CAISO will notify the Interconnection Customer and provide an estimated completion date with an explanation of the reasons why additional time is required. Modification requests received during applicable studies will be logged and reviewed for completeness and, when the study process is complete, the modification requests will be evaluated Grounds for Appeal LSA appeals these provisions on several grounds. Modifications that are not material would not impact ongoing studies. According to CAISO figures provided in the IPE process, the vast majority of MMA requests from Interconnection Customers (ICs) are found not to be material, i.e., they do not adversely impact other projects in the queue or PTOs. If the changes are not material, they would not require study changes or re-starts, so this rationale does not seem rational. The BPM and referenced document are unclear and confusing. It was clear from the discussions in the stakeholder process that the other studies applicable to that project is intended to include the annual GIDAP Reassessment, which technically applies to all cluster-study projects even those that were processed under the prior GIP rules and not the GIDAP. However, despite several LSA questions and comments on this point, the final BPM does not include any mention of the Reassessment. Moreover, the referenced document (Document) for which the link is provided is entitled Cluster 5. While the Document does contain dates for the annual GIDAP Reassessment, an IC with a project in another cluster would have to know that: (1) the information in this document applies to its project even though it only references Cluster 5; and (2) the annual GIDAP Reassessment applies to its project at all (see above). Also, CAISO study schedules can vary from year to year. Thus, LSA s recommendation during the stakeholder process that the CAISO issue a Market Notice and/or make a more obvious posting of the MMA processing timelines is needed so that the market is aware of the applicable dates each study cycle. 2

3 The modification-processing timing restrictions are simply unworkable. That is the most serious problem with this section of the BPM. First, the Reassessment process timeframe in the Document is approximately 4 months. Adding 45 days lead time (1.5 months), per the BPM, would mean that no cluster-project modification requests would be processed for 5.5 consecutive months each year (with much tighter timing for projects still going through the interconnection-study process (where Phase I and Phase II Study times would also be off-limits)). Prohibiting modification-request processing for nearly half of every year could significantly hamper the interconnection process. For example, critical project equipment or configuration changes could wait many months for CAISO approval, potentially delaying project development and construction schedules (which, of course, would require additional modification requests) and impairing IC ability to meet critical PPA deadlines. Second, it is not clear whether these timing limitations apply to PTO requests for schedule or plan-of-service changes (see below), since the BPM language appears to apply to all modification requests. As opposed to project equipment or configuration changes (which would only be allowed if found to be immaterial), such PTO requests would almost surely impact study results, and thus should be accounted for in ongoing studies, to the extent possible. Certainly, once the PTO identifies potential GIA milestone delays, the PTO and IC should not have to wait many months for the CAISO to process the request. Such delays could postpone conforming GIA amendments and delay permitting and construction activities during the wait. Prompt processing of MMA requests is particularly critical given the potential expiration of vital tax credits at the end of Aside from the PPA consequences of failure to meet GIA deadlines, loss of those tax credits and other financial incentives could well render some projects uneconomic and thus cause them to fail. The off-takers for those projects would then lose the RPS credits and other benefits that they are counting on receiving from the projects. Requested change The CAISO should revise the BPM to remove the prohibition against MMA request processing during most interconnection studies, especially annual GIDAP Reassessments. Reasonable exceptions (circumstances when MMA requests would not be processed) should be limited, if at all, to: MMA requests within 45 days of, and during, Phase I Studies. Projects at this stage are still in an early form, and there are opportunities to make many of the same changes that would otherwise be processed in an MMA request through resubmission of Interconnection Request Appendix B, after the Phase I Study Results Meeting. MMA requests that are more likely to impact the outcome of Interconnection Studies. MMA requests for other changes should be allowed at any time. 3

4 The CAISO has had considerable experience by now with the MMA request process and could define a limited number of MMA request types that have sometimes been found to be material in the past (for example, maybe COD extensions for more than 6 months). This list could be defined in a BPM and modified over time to reflect additional experience in the future. If the CAISO does not accept the recommendations above and retains the MMA request restrictions in the final BPM, it should at least: (1) clarify in the BPM that the annual GIDAP Reassessment is one of the applicable studies; and (2) publish (with a Market Notice) a separate annual study schedule before the start of each year, updated whenever changes become apparent. PTO SUBMISSION OF MODIFICATION REQUESTS The BPM addresses PTO submission of modifications to the CAISO in two places (emphases added): 3. Overview of Modification Provisions The CAISO believes the Participating TO should submit a modification request to the CAISO if the Participating TO proposes changes to the scope of, or schedule for, planned Network Upgrades or PTO's Interconnection Facilities. The Participating TO should include in the request a description of the proposed changes, the Interconnection Customers that they believes will be impacted, the impacts on those Interconnection Customers, a description of potential alternatives considered, if applicable, and the reason for selecting the proposed modification Milestone Extension When Network Upgrades Are Delayed (sub-section of Section Modifications That Are Approved Without Material Modification Assessment) In the event that the Participating TO determines that construction of a Network Upgrade, required pre-cursor Network Upgrade, or Participating TO s Interconnection Facilities are delayed and that any project milestones must be modified due to that schedule change, the Participating TO shall provide notice to the CAISO and the Interconnection Customer(s) it believes are impacted by the delay that includes the previous In-Service Date and the new In- Service Date, as well as any other required modifications. The Participating TO notice to the CAISO should include a description of the proposed changes, the Interconnection Customer(s) that they believe will be impacted, the impacts on those Interconnection Customer(s), a description of potential alternatives considered, if applicable, and the reason for selecting the proposed modification. The Participating TO notice to the Interconnection Customer should include a description of the proposed changes, a description of potential alternatives considered, if applicable, and the reason for selecting the proposed modification. Grounds for Appeal LSA supports PTO submission of changes due to NU or IF construction delays to the CAISO and affected ICs, and CAISO examination of the justification for the changes and alternatives considered. These provisions will implement a clear process for changes that today are often dictated by PTOs without adequate notice or explanation to ICs. The language regarding content of the change notices was suggested by LSA, and we appreciate the CAISO s incorporation of those suggestions. 4

5 However, LSA appeals the BPM language because it is contradictory. Section 3 states that the CAISO believes that PTOs should submit these changes, while Section says that PTOs shall submit them. Requested change The BPM should require PTO submission for CAISO approval, and notice to affected ICs, of schedule changes due to NU or IF construction delays. The CAISO oversight process will not be effective if PTOs can simply skip it. Specifically, BPM Section 3 should be revised as follows, to be consistent with BPM Section : 3. Overview of Modification Provisions The CAISO believes tthe Participating TO should must submit a modification request to the CAISO if the Participating TO proposes changes to the scope of, or schedule for, planned Network Upgrades or PTO's Interconnection Facilities. The Participating TO should include in the request a description of the proposed changes, the Interconnection Customers that they believes will be impacted, the impacts on those Interconnection Customers, a description of potential alternatives considered, if applicable, and the reason for selecting the proposed modification. 5

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted Shannon Eddy, Executive Director eddyconsulting@gmail.com Tim Mason, Policy Director tim@largescalesolar.org Adam Foltz Director of Interconnection

More information

Interconnection Process Enhancements Initiative

Interconnection Process Enhancements Initiative Interconnection Process Enhancements Initiative Stakeholder Web Conference March 30, 2015 Agenda Time Topic Speaker 1:00-1:10 Introduction, Stakeholder Process Kristina Osborne 1:10-2:50 Issue Paper Topic

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted Adam Foltz Director of Interconnection and Transmission Sustainable Power Group 415.692.7578 AFoltz@Spower.com SPower September 24, 2018

More information

Business Practice Manual For. Queue Management. Version 12

Business Practice Manual For. Queue Management. Version 12 Business Practice Manual For Queue Management Version 12 Revision Date: March 4June 27, 2014 Approval History Approval Date: February, 2014 Effective Date: March, 2014 BPM Owner: Deb Le Vine BPM Owner

More information

Business Practice Manual For. Generator Management. Version 8

Business Practice Manual For. Generator Management. Version 8 Business Practice Manual For Generator Management Version 8 Revision Date: June 30, 2015 Approval History Approval Date: February, 2014 Effective Date: March, 2014 BPM Owner: Deb Le Vine BPM Owner s Title:

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted Fernando E. Cornejo fernando.cornejo@sce.com Southern California Edison June 8, 2018 Please use this template to provide your written comments

More information

Business Practice Manual For. Generator Management. Version 76

Business Practice Manual For. Generator Management. Version 76 Business Practice Manual For Generator Management Version 76 Revision Date: April 30, 3015June 1, 2015 Approval History Approval Date: February, 2014 Effective Date: March, 2014 BPM Owner: Deb Le Vine

More information

Link to Generator Interconnection and Deliverability Allocation Procedures Cluster Process Summary provided

Link to Generator Interconnection and Deliverability Allocation Procedures Cluster Process Summary provided 1 2 3 Link to Generator Interconnection and Deliverability Allocation Procedures Cluster Process Summary provided 4 This is how you enter our Interconnection Study Process, a.k.a. the queue. App DD Section

More information

Business Practice Manual For. Generator Management. Version Revision Date: August 7September 8, Page i

Business Practice Manual For. Generator Management. Version Revision Date: August 7September 8, Page i Business Practice Manual For Generator Management Version 2021 Revision Date: August 7September 8, 2017 Page i Approval History Approval Date: February, 2014 Effective Date: March, 2014 BPM Owner: Deb

More information

Interconnection Process Enhancements. Draft BPM Language Topic 15 Material Modification Review

Interconnection Process Enhancements. Draft BPM Language Topic 15 Material Modification Review Interconnection Process Enhancements Draft BPM Language Topic 15 Material Modification Review November 18, 2013 1 Table of Contents 9. Overview of Modification Provisions... 4 9.1. Timing of Modification

More information

Business Practice Manual For. Generator Management. Version Revision Date: July 5October 1, Page i

Business Practice Manual For. Generator Management. Version Revision Date: July 5October 1, Page i Business Practice Manual For Generator Management Version 2223 Revision Date: July 5October 1, 2018 Page i Approval History Approval Date: February, 2014 Effective Date: March, 2014 BPM Owner: Deb Le Vine

More information

2018 Interconnection Process Enhancements. Addendum #2 to Draft Final Proposal

2018 Interconnection Process Enhancements. Addendum #2 to Draft Final Proposal 2018 Interconnection Process Enhancements Addendum #2 to Draft Final Proposal December 21, 2018 Table of Contents 1. Introduction... 2 2. Stakeholder Process... 2. Scope... 7. Interconnection Financial

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted Fernando E. Cornejo fernando.cornejo@sce.com Southern California Edison February 7, 2018 Please use this template to provide your written

More information

2018 Interconnection Process Enhancements (IPE) Stakeholder Call May 21, :00 a.m. 4:00 p.m. (Pacific Time)

2018 Interconnection Process Enhancements (IPE) Stakeholder Call May 21, :00 a.m. 4:00 p.m. (Pacific Time) 2018 Interconnection Process Enhancements (IPE) Stakeholder Call May 21, 2018 10:00 a.m. 4:00 p.m. (Pacific Time) Agenda Time Item Speaker 10:00-10:10 Stakeholder Process and Schedule Jody Cross 10:10-10:15

More information

Generator Interconnection and Deliverability Allocation Procedures (GIDAP) Business Practice Manual (BPM) 6.1.4

Generator Interconnection and Deliverability Allocation Procedures (GIDAP) Business Practice Manual (BPM) 6.1.4 1 2 3 Estimated schedule. Does not include Generator Interconnection Agreement, construction and New Resource Interconnection (NRI) process (full network model, metering and telemetry, etc.) which is 6/7

More information

2018 Interconnection Process Enhancements (IPE) Issue Paper

2018 Interconnection Process Enhancements (IPE) Issue Paper 2018 Interconnection Process Enhancements (IPE) Issue Paper Stakeholder Meeting January 24, 2018 10:00 a.m. 4:00 p.m. (Pacific Time) Agenda Time Item Speaker 10:00-10:10 Stakeholder Process and Schedule

More information

Business Practice Manual For. Generator Management. PRR: Clarifying changes to Generator Retirement Process

Business Practice Manual For. Generator Management. PRR: Clarifying changes to Generator Retirement Process Business Practice Manual For Generator Management PRR: Clarifying changes to Generator Retirement Process Page 1 11. Retirement PLEASE NOTE Scenario 4 creates a process for a Generating Unit that wants

More information

GIDAP Cluster Process Updated October 31, 2016

GIDAP Cluster Process Updated October 31, 2016 GIDAP Cluster Process Updated October 31, 2016 (Tariff Appendix DD Section number references shown in bold italics) Applicable portions copied into meeting minutes. All MW references in document denote

More information

2018 Interconnection Process Enhancements (IPE) Web conference January 3, :00 p.m. 3:00 p.m. (Pacific Time)

2018 Interconnection Process Enhancements (IPE) Web conference January 3, :00 p.m. 3:00 p.m. (Pacific Time) 2018 Interconnection Process Enhancements (IPE) Web conference January 3, 2019 1:00 p.m. 3:00 p.m. (Pacific Time) Agenda Time Item Speaker 1:00-1:10 Stakeholder Process and Schedule Jody Cross 1:10-1:20

More information

2015 Modification Assessment Cost and Accounting Report March 1, 2017

2015 Modification Assessment Cost and Accounting Report March 1, 2017 2015 Modification Assessment Cost and Accounting Report March 1, 2017 Prepared by: Raeann Quadro California Independent System Operator Table of Contents 1. Executive Summary 1.1. Purpose and Scope 1.2.

More information

Business Practice Manual For. Generator Management. PRR: Clarifying changes to Generator Retirement Process. Formatted: Font: 24 pt, Kern at 14 pt

Business Practice Manual For. Generator Management. PRR: Clarifying changes to Generator Retirement Process. Formatted: Font: 24 pt, Kern at 14 pt Business Practice Manual For Generator Management Formatted: Font: 24 pt, Kern at 14 pt PRR: Clarifying changes to Generator Retirement Process Page 1 11. Retirement PLEASE NOTE Scenario 4 creates a process

More information

Temporary Suspension of Resource Operations. Issue Paper

Temporary Suspension of Resource Operations. Issue Paper Temporary Suspension of Resource Operations May 10, 2017 Market & Infrastructure Policy Table of Contents 1. Executive Summary... 3 2. Plan for Stakeholder Engagement... 3 3. Background and Scope of Initiative...

More information

IR Application Generator Facility Data Form Overview

IR Application Generator Facility Data Form Overview IR Application Generator Facility Data Form Overview Luba Kravchuk Senior Regional Transmission Engineer Resource Interconnection Fair February 27, 2019 Objective IR Application Generator Facility Data

More information

Exhibit 1 Hawaiian Electric Companies Development of the Proposed Final Variable RFPs

Exhibit 1 Hawaiian Electric Companies Development of the Proposed Final Variable RFPs Exhibit 1 Hawaiian Electric Companies Development of the Proposed Final Variable RFPs The Hawaiian Electric Companies 1 process for developing their draft request for proposals ( RFP ) for Firm Capacity

More information

2013 RPS Solicitation Request for Proposals Conference. January 13, 2014

2013 RPS Solicitation Request for Proposals Conference. January 13, 2014 2013 RPS Solicitation Request for Proposals Conference January 13, 2014 Overview of the Conference Introduction Safety Moment Words from Senior Management Overview Elements of the Bidder s Conference Meet

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Request for Modifications to SCE s Renewable Auction Mechanism ( RAM ) Program Pursuant to Decision 10-12-048 Rulemaking 11-05-005 (Filed

More information

Dominion Energy Virginia

Dominion Energy Virginia Request for Proposal 2017 Solicitation for New Photovoltaic Solar and Onshore Wind Power Supply Generation October 16, 2017 Dominion Energy Virginia TABLE OF CONTENTS Table of Contents PART I RFP Overview...

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Meridian Energy USA, Inc. ) Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Meridian Energy USA, Inc. ) Docket No. ER UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Meridian Energy USA, Inc. ) Docket No. ER13-1333-000 MOTION TO INTERVENE AND PROTEST OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR

More information

Settlements and ADR Time Bars. Market Subcommittee February 8, 2018

Settlements and ADR Time Bars. Market Subcommittee February 8, 2018 Settlements and ADR Time Bars Market Subcommittee February 8, 2018 Purpose and Key Takeaways Purpose Update stakeholders on proposed Tariff revisions establishing time limits for disputes, corrections

More information

Clean Coalition comments on Proposed CREST PPA

Clean Coalition comments on Proposed CREST PPA Southern California Edison CREST Reform Clean Coalition comments on Proposed CREST PPA Tam Hunt, Attorney and Policy Advisor for the Clean Coalition June 22, 2011 1 Clean Coalition Comments on Proposed

More information

Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements. Straw Proposal

Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements. Straw Proposal Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements June 20, 2017 Market & Infrastructure Policy Table of Contents 1. Executive Summary... 3 2. Plan for Stakeholder Engagement... 4 3.

More information

Studies, Study Results, & Project Cost Responsibility

Studies, Study Results, & Project Cost Responsibility Studies, Study Results, & Project Cost Responsibility Abhishek Singh, Lead Regional Transmission Engineer Resource Interconnection Fair March 6, 2018 Objective Understand the study processes and study

More information

Smart Grid Compressed Air Energy Storage Demonstration Project Request for Offers

Smart Grid Compressed Air Energy Storage Demonstration Project Request for Offers Smart Grid Compressed Air Energy Storage Demonstration Project Request for Offers (CAES RFO) 2015 PARTICIPANTS WEBINAR October 29, 2015 Q&A / Audio Replay PG&E will take questions via email only during

More information

Temporary Suspension of Resource Operations BBB Issue Paper

Temporary Suspension of Resource Operations BBB Issue Paper Temporary Suspension of Resource Operations BBB Issue Paper Stakeholder Conference Call May 19, 2017 9:00 a.m. 12:00 p.m. Pacific Time Keith Johnson Infrastructure and Regulatory Policy Manager Agenda

More information

Qualifying Facility Avoided Cost Procedures

Qualifying Facility Avoided Cost Procedures I.P.U.C. No. 1 Original Sheet No. 38.1 ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. 38 STATE OF IDAHO Qualifying Facility Avoided Cost Procedures PREFACE: 1. The process outlined in this Schedule

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket No. ER18-641-000 Operator Corporation ) MOTION TO INTERVENE AND PROTEST OF THE DEPARTMENT

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) MOTION TO INTERVENE AND PROTEST OF ACCIONA WIND ENERGY USA LLC

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) ) ) MOTION TO INTERVENE AND PROTEST OF ACCIONA WIND ENERGY USA LLC UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southwest Power Pool, Inc. ) ) ) ) ) Docket No. ER14-781-000 MOTION TO INTERVENE AND PROTEST OF ACCIONA WIND ENERGY USA LLC In accordance

More information

Proposal Concerning Modification to Smart Grid Small Generator Interconnection Procedures Appended to LIPA s Tariff for Electric Service

Proposal Concerning Modification to Smart Grid Small Generator Interconnection Procedures Appended to LIPA s Tariff for Electric Service Proposal Concerning Modification to Smart Grid Small Generator Interconnection Procedures Appended to LIPA s Tariff for Electric Service Requested Action: The Long Island Power Authority ( LIPA or the

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator ) Docket No. ER14-2824-000 Corporation ) ) MOTION TO INTERVENE, LIMITED PROTEST AND COMMENTS

More information

2014 Modification Assessment Cost and Accounting Report July 1, 2015

2014 Modification Assessment Cost and Accounting Report July 1, 2015 2014 Modification Assessment Cost and Accounting Report July 1, 2015 Prepared by: Raeann Quadro Version: 1 California Independent System Operator Table of Contents 1. Executive Summary 1.1. Purpose and

More information

First Revision of Sheet No P.S.C.U. No. 50 Canceling Original Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO.

First Revision of Sheet No P.S.C.U. No. 50 Canceling Original Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. First Revision of Sheet No. 38.1 P.S.C.U. No. 50 Canceling Original Sheet No. 38.1 ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. 38 STATE OF UTAH Qualifying Facility Procedures PREFACE: 1. The process

More information

Amendment to extend exceptional dispatch mitigated energy settlement rules and modify residual imbalance energy settlement rules

Amendment to extend exceptional dispatch mitigated energy settlement rules and modify residual imbalance energy settlement rules California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Nancy Saracino, Vice President, General Counsel & Chief Administrative Officer Date: September 7, 2012 Re:

More information

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON ORDER NO. 10-132 ENTERED 04/07/10 BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON UM 1401 In the Matter of PUBLIC UTILITY COMMISSION OF OREGON Investigation into Interconnection of PURPA Qualifying Facilities

More information

FERC Issued Order No. 773-A on Rehearing and Clarification of NERC Bulk Electric System Definition and Exceptions Process under Rules of Procedure

FERC Issued Order No. 773-A on Rehearing and Clarification of NERC Bulk Electric System Definition and Exceptions Process under Rules of Procedure To: From: Winston & Strawn Clients Raymond B. Wuslich Roxane E. Maywalt Date: Subject: FERC Issued Order No. 773-A on Rehearing and Clarification of NERC Bulk Electric System Definition and Exceptions

More information

Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA Distribution Systems

Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA Distribution Systems Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA Distribution Systems -1- TABLE OF CONTENTS Section I. Application Process..

More information

Review of Reliability Must Run and Capacity Procurement Mechanism

Review of Reliability Must Run and Capacity Procurement Mechanism Review of Reliability Must Run and Capacity Procurement Mechanism Draft Final Proposal for Phase 1 Items and Items under Consideration for Phase 2 March 13, 2018 Market & Infrastructure Policy Table of

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents APPENDIX HH Generation Interconnection Agreement Amendment Re: Generator Downsizing... 2 1 APPENDIX HH Generation Interconnection Agreement Amendment Re: Generator Downsizing This Appendix

More information

Stakeholder Comments Template

Stakeholder Comments Template Stakeholder Comments Template Submitted by Company Date Submitted Jaime Rose Gannon jrg@cpuc.ca.gov 415-846-4365 California Public Utilities Commission 3/11/2019 Please use this template to provide your

More information

Order No. 126/18. September 18, 2018 (Amended)

Order No. 126/18. September 18, 2018 (Amended) AN APPLICATION BY MANITOBA HYDRO TO REVIEW AND VARY ORDER 59/18 TIME-OF-USE RATE DIRECTIVE 29 AND REVIEW AND VARY ORDER 59/18 TECHNICAL CONFERENCE ON RETAINED EARNINGS DIRECTIVE 9 PURSUANT TO THE PUBLIC

More information

Re: Transit Asset Management; National Transit Database; Proposed Rule (Docket Number FTA )

Re: Transit Asset Management; National Transit Database; Proposed Rule (Docket Number FTA ) November 20, 2015 Honorable Therese McMillian Acting Administrator Federal Transit Administration United States Department of Transportation 1200 New Jersey Avenue SE Washington, DC 20590 Re: Transit Asset

More information

California Independent System Operator Corporation Fifth Replacement FERC Electric Tariff

California Independent System Operator Corporation Fifth Replacement FERC Electric Tariff Table of Contents 10. Metering... 2 10.1 General Provisions... 2 10.1.1 Role Of The CAISO... 2 10.1.2 Meter Data Retention By The CAISO... 2 10.1.3 Netting... 2 10.1.4 Meter Service Agreements... 4 10.1.5

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 25. Interconnection of Generating Units and Facilities... 2 25.1 Applicability... 2 25.1.1 Interconnection Request and Generating Unit Requirements... 2 25.1.2 Affidavit Requirements...

More information

regarding Class Year Process Improvements

regarding Class Year Process Improvements Proposed Tariff Revisions regarding Class Year Process Improvements Steve Corey Manager, Interconnection Projects New York Independent System Operator Management Committee (MC) October 31, 2012 2012 New

More information

California Independent System Operator Corporation Fifth Replacement FERC Electric Tariff

California Independent System Operator Corporation Fifth Replacement FERC Electric Tariff Table of Contents 10. Metering... 2 10.1 General Provisions... 2 10.1.1 Role of the CAISO... 2 10.1.2 Meter Data Retention by the CAISO... 2 10.1.3 Netting... 3 10.1.4 Meter Service Agreements... 4 10.1.5

More information

Business Practice Manual for Rules of Conduct Administration. Version 45

Business Practice Manual for Rules of Conduct Administration. Version 45 Business Practice Manual for Rules of Conduct Administration Version 45 Last Revised: August 2, 2010 August,October xx04, 2011 Approval History Approval Date: March 13, 2009 Effective Date: March 31, 2009

More information

It's more than just numbers

It's more than just numbers What are the goals of a business? It's more than just numbers Make a profit Remain in a healthy financial position Make good use of cash flow FINANCIAL STATEMENTS AND THE DETAILS What is a Financial Statement?

More information

FERC Order 1000 Compliance Initiative. Straw Proposal (regional requirements), posted May 22, 2012

FERC Order 1000 Compliance Initiative. Straw Proposal (regional requirements), posted May 22, 2012 Stakeholder Comments Template FERC Order 1000 Compliance Initiative Straw Proposal (regional requirements), posted May 22, 2012 Please submit comments (in MS Word) to fo1k@caiso.com no later than the close

More information

PwC Comment Letter on the Exposure Draft issued by the IESBA, July 2007

PwC Comment Letter on the Exposure Draft issued by the IESBA, July 2007 PricewaterhouseCoopers LLP 1 Embankment Place London WC2N 6RH Telephone +44 (0) 20 7583 5000 Facsimile +44 (0) 20 7822 4652 www.pwc.com/uk Senior Technical Manager International Ethics Standards Board

More information

Smart Grid Small Generator Interconnection Procedures For Distributed Generators Less than 10 MW Connected in Parallel with LIPA s Radial

Smart Grid Small Generator Interconnection Procedures For Distributed Generators Less than 10 MW Connected in Parallel with LIPA s Radial Smart Grid Small Generator Interconnection Procedures For Distributed Generators Less than 10 MW Connected in Parallel with LIPA s Radial Distribution Systems Revised January 1, 2017 TABLE OF CONTENTS

More information

83C Questions and Answers

83C Questions and Answers 83C Questions and Answers (2) Section 1.7.4.1 Can the Evaluation Team provide guidance on the scope and amount of information that could be requested from ISO-NE, and the expected magnitude of any associated

More information

AUDIT UNDP AFGHANISTAN. Local Governance Project (Project No ) Report No Issue Date: 23 December 2016

AUDIT UNDP AFGHANISTAN. Local Governance Project (Project No ) Report No Issue Date: 23 December 2016 UNITED NATIONS DEVELOPMENT PROGRAMME AUDIT OF UNDP AFGHANISTAN Local Governance Project (Project No. 90448) Report No. 1745 Issue Date: 23 December 2016 Table of Contents Executive Summary i I. About the

More information

Re: Rulemaking docket matter No.34: Concept Release on Possible Revisions to PCAOB Standards Related to Reports on Audited Financial Statements

Re: Rulemaking docket matter No.34: Concept Release on Possible Revisions to PCAOB Standards Related to Reports on Audited Financial Statements www.lilly.com Eli Lilly and Company Lilly Corporate Center Indianapolis, Indiana 46285 U.S.A. September 30, 2011 Office of the Secretary PCAOB 1666 K Street N.W. Washington, D.C. 20006-2803 Re: Rulemaking

More information

Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements. Issue Paper

Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements. Issue Paper Capacity Procurement Mechanism Risk-of-Retirement Process Enhancements May 10, 2017 Market & Infrastructure Policy Table of Contents 1. Executive Summary... 3 2. Plan for Stakeholder Engagement... 3 3.

More information

Replies to Questions

Replies to Questions BANKING STAKEHOLDER GROUP Replies to Questions DISCUSION PAPER DP/2017/03 on the EBA s approach to Significant Risk Transfer in Securitisation 1 Replies to Questions Foreword and background The BSG welcomes

More information

Net Metering Program Capacity Allocation Procedures

Net Metering Program Capacity Allocation Procedures Net Metering Program Capacity Allocation Procedures The following required procedures for net metering capacity allocation (hereinafter, allocation ) shall apply to all projects with an existing allocation

More information

REASONS FOR DECISION. January 16, 2014 BEFORE:

REASONS FOR DECISION. January 16, 2014 BEFORE: Page 1 of 20 IN THE MATTER OF BRITISH COLUMBIA HYDRO AND POWER AUTHORITY MANDATORY RELIABILITY STANDARDS ASSESSMENT REPORT NO. 6 AND THE DETERMINATION OF RELIABILITY STANDARDS FOR ADOPTION IN BRITISH COLUMBIA

More information

New York State Public Service Commission

New York State Public Service Commission PSC NO. 220 ELECTRICITY ADDENDUM TYPES: SIR NIAGARA MOHAWK POWER CORPORATION ADDENDUM NO. 7 INITIAL EFFECTIVE DATE: AUGUST 16, 2017 STAMPS: ISSUED IN COMPLIANCE WITH ORDER IN CASE 16-E-0560 Issued August

More information

Questions and Answers on the Serious Deficiency Process in the Child and Adult Care Food Program (CACFP)

Questions and Answers on the Serious Deficiency Process in the Child and Adult Care Food Program (CACFP) United States Department of Agriculture Food and Nutrition Service 3101 Park Center Drive Alexandria, VA 22302-1500 Memo Code: CACFP 03-2006 November 7, 2005 SUBJECT: TO: Questions and Answers on the Serious

More information

POWER PURCHASE AND SALE AGREEMENT. between [BUYER S NAME] and [SELLER S NAME] (ID #[Number])

POWER PURCHASE AND SALE AGREEMENT. between [BUYER S NAME] and [SELLER S NAME] (ID #[Number]) POWER PURCHASE AND SALE AGREEMENT between [BUYER S NAME] and [SELLER S NAME] (ID #[Number]) Standard Contract for Qualifying Facilities with a Power Rating that is Less than or Equal to 20MW TERMS THAT

More information

Discussion Paper. Treatment of structural FX under Article 352(2) of the CRR EBA/DP/2017/ June 2017

Discussion Paper. Treatment of structural FX under Article 352(2) of the CRR EBA/DP/2017/ June 2017 EBA/DP/2017/01 22 June 2017 Discussion Paper Treatment of structural FX under Article 352(2) of the CRR Contents 1. Responding to this Discussion Paper 3 2. Executive Summary 4 3. Background and Rationale

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket No. ER18-1169-000 Operator Corporation ) MOTION TO INTERVENE AND PROTEST OF THE DEPARTMENT

More information

Proposed federal plan and model trading rules -draft discussion comments-

Proposed federal plan and model trading rules -draft discussion comments- Proposed federal plan and model trading rules -draft discussion comments- The comments provided below are draft only, and are intended to stimulate stakeholder discussion and input. The MPCA and Department

More information

Summary of Prior CAISO Filings and Commission Orders Concerning CAISO Market Redesign Efforts

Summary of Prior CAISO Filings and Commission Orders Concerning CAISO Market Redesign Efforts Summary of Prior CAISO Filings and Commission Orders Concerning CAISO Market Redesign Efforts 1. Commission Directives to Submit a Market Redesign Plan The direct origin of the requirement that the CAISO

More information

March 23, Monica Jackson Office of the Executive Secretary Consumer Financial Protection Bureau 1700 G Street NW Washington, DC 20552

March 23, Monica Jackson Office of the Executive Secretary Consumer Financial Protection Bureau 1700 G Street NW Washington, DC 20552 March 23, 2015 Monica Jackson Office of the Executive Secretary Consumer Financial Protection Bureau 1700 G Street NW Washington, DC 20552 Re: Prepaid Accounts under the Electronic Fund Transfer Act (Regulation

More information

Notice of Proposed Rulemaking Action Title 28, California Code of Regulations

Notice of Proposed Rulemaking Action Title 28, California Code of Regulations Arnold Schwarzenegger, Governor State of California Business, Transportation and Housing Agency Department of Managed Health Care Office of Legal Services 980 Ninth Street, Suite 500 Sacramento, CA 95814-2725

More information

Managed Care Contracting

Managed Care Contracting NATIONAL COUNCIL FOR BEHAVIORAL HEALTH Managed Care Contracting presented by: Adam J. Falcone, Esq. Partner of FIDELL LLP Disclaimer This presentation has been prepared by the attorneys of Feldesman Tucker

More information

DISABILITY RIGHTS NEW MEXICO

DISABILITY RIGHTS NEW MEXICO DISABILITY RIGHTS NEW MEXICO 1720 Louisiana Blvd. NE, Suite 204 Albuquerque, New Mexico 87110 TEL/TTY: (505) 256-3100 FAX: (505) 256-3184 State-wide Toll Free 1-800-432-4682 WEBSITE: www.drnm.org EMAIL:

More information

Re: Implementation of the Alternative Energy Portfolio Standards Act of 2004 Docket No. L

Re: Implementation of the Alternative Energy Portfolio Standards Act of 2004 Docket No. L 201 California Street, Suite 630 San Francisco, California 94111 September 3, 2014 Via Electronic Filing Rosemary Chiavette, Secretary PA Public Utilities Commission PO Box 3265 Harrisburg, PA 17105-3265

More information

Business Practice Manual For The Energy Imbalance Market. Version 89

Business Practice Manual For The Energy Imbalance Market. Version 89 Business Practice Manual For The Energy Imbalance Market Version 89 Revision Date: Jan 02, 2018May 31, 2017 Approval History Approval Date: October 2, 2014 Effective Date: October 2, 2014 BPM Owners: Mike

More information

Ellen Wolfe Resero Consulting for WPTF. February 28, 2018

Ellen Wolfe Resero Consulting for WPTF. February 28, 2018 Western Power Trading Forum Comments on CAISO CRR Auction Efficiency Workshop and Stakeholder Process Ellen Wolfe Resero Consulting for WPTF February 28, 2018 WPTF appreciates the ability to submit these

More information

-commerce EU VAT FORUM. IMPROVING COOPERATION BETWEEN BUSINESSES AND TAX ADMINISTRATION FOR EU VAT REFUNDS (Electronic Portal and 13th Directive)

-commerce EU VAT FORUM. IMPROVING COOPERATION BETWEEN BUSINESSES AND TAX ADMINISTRATION FOR EU VAT REFUNDS (Electronic Portal and 13th Directive) EU VAT FORUM IMPROVING COOPERATION BETWEEN BUSINESSES AND TAX ADMINISTRATION FOR EU VAT REFUNDS (Electronic Portal and 13th Directive) Status / Current situation VAT refund efficiency is an important topic

More information

PG&E s Bidders Webinar

PG&E s Bidders Webinar PG&E s Bidders Webinar PG&E s Request for Offers: Bioenergy Renewable Auction Mechanism (BioRAM) July 7, 2016 Agenda Topics Introduction Solicitation Overview Eligibility Requirements PPA Overview Evaluation

More information

Reliability Must Run and Capacity Procurement Mechanism Enhancements

Reliability Must Run and Capacity Procurement Mechanism Enhancements Reliability Must Run and Capacity Procurement Mechanism Enhancements Draft Final Proposal January 23, 2019 Market & Infrastructure Policy Table of Contents 1. Executive Summary... 3 2. Plan for Stakeholder

More information

165 FERC 61,140 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ACCEPTING COMPLIANCE FILING SUBJECT TO CONDITION

165 FERC 61,140 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ACCEPTING COMPLIANCE FILING SUBJECT TO CONDITION 165 FERC 61,140 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Neil Chatterjee, Chairman; Cheryl A. LaFleur and Richard Glick. California Independent System Operator

More information

Proposed Repeals: N.J.A.C. 11:24B-2.5 and 11:24B Appendix Exhibits 3 through 8. Proposed Repeals and New Rules: N.J.A.C. 11:24B-2.8 and 2.

Proposed Repeals: N.J.A.C. 11:24B-2.5 and 11:24B Appendix Exhibits 3 through 8. Proposed Repeals and New Rules: N.J.A.C. 11:24B-2.8 and 2. INSURANCE DEPARTMENT OF BANKING AND INSURANCE OFFICE OF LIFE AND HEALTH Organized Delivery Systems Proposed Readoption with Amendments: N.J.A.C. 11:24B Proposed Repeals: N.J.A.C. 11:24B-2.5 and 11:24B

More information

Rulemaking implementing the Exchange provisions, summarized in a separate HPA document.

Rulemaking implementing the Exchange provisions, summarized in a separate HPA document. Patient Protection and Affordable Care Act: Standards Related to Reinsurance, Risk Corridors and Risk Adjustment Summary of Proposed Rule July 15, 2011 On July 15, 2011, the Department of Health and Human

More information

DRAFT REQUEST FOR PROPOSALS FOR VARIABLE RENEWABLE DISPATCHABLE GENERATION ISLAND OF O AHU OCTOBER 23, Docket No

DRAFT REQUEST FOR PROPOSALS FOR VARIABLE RENEWABLE DISPATCHABLE GENERATION ISLAND OF O AHU OCTOBER 23, Docket No PAGE 1 OF 35 DRAFT REQUEST FOR PROPOSALS FOR VARIABLE RENEWABLE DISPATCHABLE GENERATION ISLAND OF O AHU OCTOBER 23, 2017 Docket No. 2017-0352 This Request for Proposals ( RFP ) is a DRAFT only. Hawaiian

More information

Accounting Changes and Error Corrections

Accounting Changes and Error Corrections Accounting Changes and Error Corrections 4 CPE Hours d PDH Academy PO Box 449 Pewaukee, WI 53072 www.pdhacademy.com pdhacademy@gmail.com 888-564-9098 CONTINUING EDUCATION for Certified Public Accountants

More information

Business Practice Manual for Settlements & Billing

Business Practice Manual for Settlements & Billing Business Practice Manual for Settlements & Billing Version 110 Last Revised: August 27April 1, 20132 Version 101 Last Revised: August April 271, 20123 Page 1 Approval History: Approval Date: 8-30-2012

More information

CREDIT RATING AGENCIES (CRA III) 27 February Position

CREDIT RATING AGENCIES (CRA III) 27 February Position CREDIT RATING AGENCIES (CRA III) 27 February 2012 Position Context The European Regulation of September 2009 on credit rating agencies ( agencies ), which came into force in December 2010, requires in

More information

June 3, Ms. Monica Jackson Office of the Executive Secretary Consumer Financial Protection Bureau 1700 G Street N.W. Washington, D.C.

June 3, Ms. Monica Jackson Office of the Executive Secretary Consumer Financial Protection Bureau 1700 G Street N.W. Washington, D.C. Robert R. Davis Executive Vice President Mortgage Markets, Financial Management & Public Policy (202) 663-5588 RDavis@aba.com Ms. Monica Jackson Office of the Executive Secretary Consumer Financial Protection

More information

New York State Public Service Commission

New York State Public Service Commission PSC NO. 220 ELECTRICITY ADDENDUM TYPES: SIR NIAGARA MOHAWK POWER CORPORATION ADDENDUM NO. 9 INITIAL EFFECTIVE DATE: NOVEMBER 2, 2018 STAMPS: ISSUED IN COMPLIANCE WITH ORDER IN CASE 18-E-0018 Issued October

More information

UNITED STATES OF AMERICA 117 FERC 61,356 FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA 117 FERC 61,356 FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA 117 FERC 61,356 FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Joseph T. Kelliher, Chairman; Suedeen G. Kelly, Marc Spitzer, Philip D. Moeller, and Jon Wellinghoff.

More information

Rocky Mountain Power Docket No Witness: Cindy A. Crane BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER

Rocky Mountain Power Docket No Witness: Cindy A. Crane BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Rocky Mountain Power Docket No. 17-035-40 Witness: Cindy A. Crane BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Supplemental Direct and Rebuttal Testimony of Cindy A. Crane

More information

Problems with the Current HCPCS Process and Recommendations for Change

Problems with the Current HCPCS Process and Recommendations for Change Background As described on the CMS website, Level I of HCPCS is comprised of CPT-4, a numeric coding system maintained by the American Medical Association (AMA). CPT-4 is a uniform coding system consisting

More information

Chemical Sensitivities Manitoba

Chemical Sensitivities Manitoba Chemical Sensitivities Manitoba www.preventcancernow.ca June 19, 2016 Executive Director Program Development and Engagement Division Environment and Climate Change Canada Gatineau, Quebec K1A 0H3 Canada

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) California Independent System ) Docket Nos. ER06-615-000 Operator Corporation ) ER07-613-000 ) ) (not consolidated) ) STATUS REPORT

More information

LICENCE FOR PUBLIC ELECTRICITY SUPPLIER KOSOVO POWER CORPORATION J.S.C. Division of Supply

LICENCE FOR PUBLIC ELECTRICITY SUPPLIER KOSOVO POWER CORPORATION J.S.C. Division of Supply LICENCE FOR PUBLIC ELECTRICITY SUPPLIER ISSUED TO: KOSOVO POWER CORPORATION J.S.C Division of Supply Registration number: ZRRE/Li_06/12 Adresa: Rr. Hamdi Mramori nr. 1, 10000 Prishtinë, Kosovë Tel: 038

More information

83D Questions and Answers

83D Questions and Answers 83D Questions and Answers (20) Section 2.2.2.7 Please provide further clarification on the methodology that will be used to calculate Winter Peak generation: cumulative averages over 8am-11pm peak hours?

More information

Distribution Group Study Process. August 26, 2014

Distribution Group Study Process. August 26, 2014 Distribution Group Study Process August 26, 2014 Agenda Overview Applying for DGSP DGSP Interconnection Process Applicability and Utility Contacts Questions 2 Process Overview Open Window Period Evaluation

More information