Extended Reserve Selection Methodology

Size: px
Start display at page:

Download "Extended Reserve Selection Methodology"

Transcription

1 Extended Reserve Selection Methodology Extended Reserve Manager Version February 2017

2 Revision history Version Date Description Author August 2016 Draft presented to the Authority and System Operator for comment as per 5(2), Part 2, Schedule 8.5, of the Code September 2016 Incorporating feedback from Authority staff received 9-13 September October 2016 Incorporating changes in response to comments from the system operator received 20 September December 2016 Incorporating consultation feedback Extended Reserve Manager Extended Reserve Manager Extended Reserve Manager Extended Reserve Manager January 2017 Incorporating Authority staff and SO comments on the postconsultation draft Extended Reserve Manager February 2017 Edits as requested by Authority. Extended Reserve Manager February 2017 Finalised after approval by the Authority Extended Reserve Manager Extended reserve manager Extended Reserve Selection Methodology v February of 31

3 CONTENTS CONTENTS... 3 Purpose of this document... 4 Interpretation... 4 Asset owners that are required to provide information... 5 Information that asset owners are required to provide... 6 Timeframe within which information must be provided... 6 Basis on which extended reserve is selected... 6 Default terms and conditions... 9 Payments for extended reserve provision... 9 Schedule 1 Information each asset owner must provide Part 1 Information for an extended reserve selection process Part 2 Information definition Schedule 2 Default terms and conditions for extended reserve providers Interpretation Provision of extended reserve Permanent loss of capability Provision of information for periodic performance reporting Management of change during implementation Schedule 3 Values used for selection Part 1: Expected interruption hours per year by AUFLS block Part 2: Expected interruption cost of 2 hour unanticipated outage by customer class Part 3: Standard AUFLS provision cost compensation rates Part 4: Model parameters Schedule 4 Model formulation Schedule 5 Extended Reserve Procurement Schedule template Schedule 6 Payment calculation Extended reserve manager Extended Reserve Selection Methodology v February of 31

4 Purpose of this document This is the extended reserve selection methodology (methodology) published by the extended reserve manager under clause 8.54G of the Electricity Industry Participation Code 2010 (Code) on [insert date]. It specifies how the extended reserve manager will procure extended reserve to meet the requirements set out in the extended reserve technical requirements schedule. Interpretation 1. Terms in bold font not listed in clause 2 have the meaning given to them by the Electricity Industry Act 2010, the Electricity Industry Participation Code 2010 (Code), or the extended reserve technical requirements schedule. 2. In this methodology, unless the context otherwise requires, AUFLS means automatic under-frequency load shedding AUFLS region means the group of grid exit points in the North Island AUFLS relay means a control device capable of measuring system frequency and initiating a trip signal to switchgear in compliance with the AUFLS system requirements set out in the extended reserve technical requirements schedule average annual offtake means the gross annual average of the flow of electricity from the grid at the grid exit points relevant to an asset owner as recorded by the reconciliation manager, measured in megawatts change request means a request from an extended reserve provider to the system operator to alter a date proposed in its approved implementation plan data specification means the extended reserve manager s published document specifying the requirements that asset owners must adhere to when providing information to the extended reserve manager including formatting and information transfer requirements demand unit means a distribution circuit feeder or group of feeders that is capable of being automatically disconnected as a discrete unit within an AUFLS system ERM calendar means the operations calendar in which the periodic information deadlines are published, as updated from time to time by the extended reserve manager to provide at least 6 months of forward dates at all times existing demand unit means a demand unit that is providing AUFLS under the requirements existing at the start of an extended reserve selection process Extended reserve manager Extended Reserve Selection Methodology v February of 31

5 existing relay means an AUFLS relay that is already installed on a demand unit at the deadline date for information provision for an extended reserve selection process flexible AUFLS supply means the group of flexible demand units selected in a selection process flexible demand unit means a demand unit that has been selected for flexible service as identified in the extended reserve procurement schedule net demand means the total demand on a demand unit excluding the estimated interruptible load new relay means an AUFLS relay that is not an existing relay periodic information deadlines means the deadlines for extended reserve providers to provide information to the extended reserve manager for each reporting period, which shall be 10 business days for information provision and 25 business days for information revision after each reporting period. periodic performance report means a report prepared by the extended reserve manager to assess the performance of extended reserve under Code clause 8.54TC permanent loss of capability means, in relation to a demand unit, that the demand unit can no longer perform its extended reserve function, where such change is brought about by a permanent reconfiguration of the extended reserve provider s network relevant historical period means the period that the extended reserve manager notifies at the start of an extended reserve selection process, likely to be four years ending on a recently completed month reporting period means a period of time usually expressed in consecutive calendar months covered by a periodic performance report prepared by the extended reserve manager to assess the performance of the selected AUFLS supply against the AUFLS block requirements standby AUFLS supply means flexible AUFLS supply that is not armed standby demand unit means a flexible demand unit that is not armed Asset owners that are required to provide information 3. Each North Island asset owner that has an average annual offtake greater than 1 megawatt (MW) in the relevant historical period must provide information to the extended reserve manager according to the terms in this methodology. Extended reserve manager Extended Reserve Selection Methodology v February of 31

6 4. This methodology does not apply to the South Island. Information that asset owners are required to provide 5. During an extended reserve selection process, each asset owner (identified in clause 3) must provide the information set out in Schedule 1 to the extended reserve manager. Timeframe within which information must be provided 6. An asset owner must provide the information set out in clause 5 on or before the selection deadline dates notified by the extended reserve manager. The deadline dates are set (a) (b) at least 50 business days after the extended reserve manager s request; and at least 20 business days following a data revision request. Basis on which extended reserve is selected 7. The aim of the methodology is to select the most suitable set of demand units for extended reserve that meets the extended reserve technical requirements schedule and Code as follows (a) To meet the AUFLS block requirements with adequate confidence over a period of up to 60 future months, this methodology aims to select demand units (i) (ii) (iii) that in aggregate have supplied more load than the minimum and less load than the maximum AUFLS block percentages in each AUFLS region in the latest 2 years of the relevant historical period; that in aggregate have an annual mean armed AUFLS block supply in each AUFLS region of no less than the target AUFLS block percentage in the latest year of the relevant historical period; and that reflect a preference for AUFLS systems that are capable of faster total AUFLS operating times over AUFLS systems that have slower total AUFLS operating times. (b) (c) To respond to the system operator s advice regarding the requirement in clause 16(b) of the extended reserve technical requirements schedule, the methodology has the option of applying a GXP constraint to limit the quantity of load (MW) selected from one or more GXPs. To reflect a balance of interests between potential extended reserve providers as required by clause 8.54H(2)(a) of the Code, this methodology will select no more than Extended reserve manager Extended Reserve Selection Methodology v February of 31

7 60% of the average annual offtake of each asset owner measured against the most recent year in the relevant historical period. (d) During the consultation period on the draft extended reserve procurement schedule each selected extended reserve provider is required to raise and resolve with the system operator any foreseeable difficulty in meeting their participant rolling outage plan (PROP) obligations alongside their selected quantity of extended reserve. If the system operator submits to the extended reserve manager that the resulting adjustment that would be required to PROPs does not support efficient operation or system security, then the extended reserve manager may adjust the extended reserve procurement schedule to resolve or reduce the problem. When adjusting the procurement schedule the extended reserve manager must aim for the least impact on extended reserve providers. The extended reserve manager will reconsult with affected parties on the changed selection result, providing an explanation of the problem that had to be resolved and the selection adjustment that was made to resolve it. The extended reserve manager may use one of these methods or a similar method to adjust the procurement schedule: (i) withdraw one or more selected demand units and/or switch the armed status of a flexible demand unit; or (ii) withdraw one or more demand units and then re-run the selection process without the demand unit; or (iii) re-run the selection process with a lower selection cap. (e) (f) To procure extended reserve cost-effectively as required by clause 8.54H(2)(b) of the Code, this methodology takes into account the values set out in Schedule 3 and seeks to minimise the objective function in the model formulation in Part 1 of Schedule 4. To seek an appropriate balance between certainty in the provision of extended reserve and flexibility to accommodate changes in circumstances and technologies as required by clause 8.54H(2)(c) of the Code, the methodology aims to (i) (ii) select at least 10% of the annual average target level for each AUFLS block from the latest year of the relevant historical period to be initially set as armed flexible AUFLS supply, ensuring that the quantity selected can cover the removal of the largest selected demand unit in each AUFLS block; select at least an additional 10% of the annual average target level for each AUFLS block from the latest year of the relevant historical period to be Extended reserve manager Extended Reserve Selection Methodology v February of 31

8 initially set as standby AUFLS supply, ensuring that the quantity selected can cover the removal of the largest selected demand unit in each AUFLS block; (iii) (iv) (v) (vi) select flexible demand units from demand units that are identified by the asset owner as flexible-capable using SCADA remote control to achieve faster arming and disarming response times; require each asset owner to configure each demand unit with the AUFLS settings for as many AUFLS blocks for which the demand unit is capable of meeting the AUFLS system requirements 1 ; reduce the risk of a violation of a minimum AUFLS block threshold due to a temporary outage of any selected demand unit by applying a load buffer to the minimum threshold that is equivalent to the largest proportion of any one demand unit s load to the region load in any trading period in all AUFLS blocks in the latest 2 years of the relevant historical period; and to reduce risk arising from input data imperfections, apply an additional safety margin of up to 0.5% of North Island load to each lower and/or upper AUFLS block threshold to select within a tighter range than technically required. 8. In a selection process the extended reserve manager will use demand unit data from samples of trading periods in the relevant historical period and will estimate years of demand unit load information not provided by asset owners. 9. To meet the objectives set out in clause 8, the extended reserve manager will select extended reserve in each AUFLS region by allocating demand units to AUFLS blocks including some for flexible service while seeking to minimise procurement costs as set out in the model formulation in Part 1 of Schedule During each periodic review of selected demand unit performance after publication of an extended reserve procurement schedule, the extended reserve manager will run a flexible solve (as set out in the model formulation in Part 2 of Schedule 4) to determine which of the flexible demand units should be armed or disarmed to maintain the best available AUFLS block performance. 11. If called upon by the Electricity Authority to undertake a limited selection process under clause 8.54J(3) of the Code, the extended reserve manager will select additional 1 Noting that a demand unit with an existing relay can only be tested for AUFLS block 4 where the existing relay has df/dt functionality. Extended reserve manager Extended Reserve Selection Methodology v February of 31

9 extended reserve by seeking to minimise selection costs as set out in the model formulation in Part 3 of Schedule 4. Default terms and conditions 12. For the purpose of clause 8.54G(3)(g) of the Code, the default terms and conditions set out in Schedule 2 of this methodology apply to each extended reserve provider. Payments for extended reserve provision 13. Payments to asset owners for providing extended reserve are set to $0. Extended reserve manager Extended Reserve Selection Methodology v February of 31

10 Schedule 1 Information each asset owner must provide Part 1 Information for an extended reserve selection process 1. In an extended reserve selection process each asset owner must provide the information described in Part 2 of this Schedule for at least 60% of its average annual offtake (as measured against the most recent year), for the relevant historical period, noting that (a) if an asset owner s available offtake after the subtraction of interruptible load is less than 60% of its average annual offtake then the target amount for that asset owner to provide is the remaining amount of offtake unless the asset owner can provide the extended reserve manager with sufficient evidence that it should further exclude load on the basis that for a demand unit: (i) the load is highly unlikely to be durable over the 5-year period that applies to an extended reserve procurement; or (ii) the interruption cost is more than $100,000 per MWh; or (iii) the load within a half-hour trading period routinely exhibits significant variability such that the average load for a half hour is a poor predictor of the instantaneous load within the half hour; or (iv) the asset owner cannot derive half hourly demand information from available metered demand information;or (v) the demand unit's load serves an industrial process which is strongly linked to one or more embedded generators and - this linkage is such that the electrical output from the embedded generator(s) is dependent on the continued operation of the industrial process, and - this dependency is not adequately accounted for in the available historic demand unit load. (b) if during a selection process the extended reserve manager notifies asset owners that additional information is required, an asset owner must provide the additional information within 20 business days of the request. 2. In providing the information in clause 1 of this Schedule, each asset owner must adhere to the data specification and is advised to be familiar with their obligations under clause 8.1A of the Code, which is in force from 19 January Extended reserve manager Extended Reserve Selection Methodology v February of 31

11 3. The following provisos apply to the asset owner when providing the information in clause 1 of this Schedule (a) (b) (c) (d) (e) the asset owner must use reasonable endeavours to subtract any interruptible load supplied by the demand unit from the load profile information supplied (item 24 of Part 2 of the Schedule); any demand unit that contains 100% of the public health and safety customer type (item 24 of Part 2 of this Schedule) is not eligible for submission; the asset owner must exercise discretion to not provide a demand unit supplying power to any customer that in the asset owner s view is unsuitable for extended reserve; the asset owner must in good faith where possible not submit demand units that are likely to be reconfigured within the next five years; and an asset owner cannot withdraw a submitted demand unit from a selection process after the closing date for data provision for that selection process. 4. In a limited selection process under clause 8.54J(3) of the Code, the extended reserve manager will issue a request for information to one or more asset owners and specify in the request the information needed for the limited selection process and the deadlines. Extended reserve manager Extended Reserve Selection Methodology v February of 31

12 Part 2 Information definition This table provides a description of the information required for each demand unit. The detailed requirements are set out in the data specification. Item Attributes Description 1 Demand unit identifier 2 Participant identifier Valid demand unit identifier. Valid participant identifier issued by the Electricity Authority of the asset owner who owns the demand unit. 3 GXP Valid grid exit point code. 4 Owner of relay Specify if owned by the asset owner or by Transpower. 5 Number of existing relays Number of existing relays in the demand unit. 6 Relay ID A unique relay identifier. 7 Number of new relays Number of new relays the asset owner would require in the demand unit if it is selected. (New relays must be installed with df/dt functionality as well as under frequency functionality.) 8 Feeders Asset owners may choose to list the feeders that comprise the demand unit. This is optional, field may be left blank. 9 Zone substation The zone substation identifier at which the switchgear that controls the demand unit is located, if any. 10 Currently allocated block The AUFLS block the demand unit is currently allocated to (if any), including current allocation to any AUFLS block under the AUFLS obligations in force before the first extended reserve selection process. 12 df/dt functionality Whether the AUFLS relay(s) on the demand unit will have df/dt as well as under frequency (u/f) functionality when in service. 13 Fast response capable Whether the submitted demand unit is reasonably expected to be capable of responding within 250 milliseconds (ms) (fast) or between 250 ms and 400 ms (standard). 14 Flexible capable Whether the demand unit can be armed and disarmed via SCADA remote control within 1 business day of request. 15 Embedded generation The aggregate maximum capacity (in megawatts) of embedded generation that is connected to the demand unit. Embedded generation is any form of generating plant connected to, and with the capability to inject electricity into, the demand unit. 16 Interruptible load The annual average quantity (in megawatts) of interruptible load that has been subtracted from each half hour of the demand unit load under item Residential The proportion of the demand unit s load that is residential. 18 Light industrial & primary industry The proportion of this demand unit s load that is light industrial and primary industry. Extended reserve manager Extended Reserve Selection Methodology v February of 31

13 19 Heavy industrial The proportion of this demand unit s load that is heavy industrial. 20 Commercial The proportion of this demand unit s load that is commercial. 21 Public health and safety The proportion of this demand unit s load that is public health and safety. 22 Large user The proportion of the demand unit s load that is large user load. A large user is a distributor s customer who consumes more than 25 GWh/yr or is a direct consumer. 23 Expected interruption cost 24 Half hourly demand data in MW 25 Configuration to AUFLS blocks The expected interruption cost ($/MWh) for a 2-hour outage by a large user or a direct consumer (or the aggregated average if there are several large users on the same demand unit). Half-hourly information (in MW) for each demand unit identified against each trading period in the relevant historical period (for a selection process), and in the reporting period (for the periodic monitoring process). The information is defined as the average active power, minus any interruptible load, in the relevant trading period. The information must be calculated where SCADA data is used using the maximum number of available data samples within the trading period. Where historical data is not available for a trading period an estimate must be provided. The information provided for each trading period must be identified as metered or estimated. The AUFLS block settings to which the demand unit is configured and tested. Not relevant to the initial selection process. Extended reserve manager Extended Reserve Selection Methodology v February of 31

14 Schedule 2 Default terms and conditions for extended reserve providers In accordance with clause 8.54G(3)(g) of the Code, this Schedule sets out the default terms and conditions specifying the basis on which extended reserve must be provided. Interpretation 1. Terms in bold font have the meaning given to them by the Electricity Industry Act 2010, the Electricity Industry Participation Code 2010 (Code), the extended reserve technical requirements schedule and the extended reserve selection methodology. Provision of extended reserve 2. The extended reserve provider must comply with all clauses relevant to an extended reserve provider in the extended reserve technical requirements schedule. 3. The extended reserve provider must prepare for service each demand unit identified in an extended reserve procurement schedule. 4. In preparing the demand unit, the extended reserve provider must (a) (b) (c) (d) (e) (f) configure and test each demand unit with the AUFLS settings to which the demand unit has been allocated; configure and test each demand unit with the AUFLS settings for as many other AUFLS blocks for which settings are available on the AUFLS relay and that the AUFLS relay on that demand unit is capable of holding while meeting the AUFLS system requirements; ensure a demand unit selected for flexible service is capable of remote control by SCADA; install each new relay that is identified on the demand unit in the extended reserve procurement schedule. Each new relay must have under frequency and df/dt functionality; install df/dt functionality on any existing relay that is selected for AUFLS block 4 and that does not already have df/dt functionality; and ensure each demand unit meets the required performance standards and testing requirements in the extended reserve technical requirements schedule on or before the start date for that demand unit in the extended reserve schedule. Extended reserve manager Extended Reserve Selection Methodology v February of 31

15 5. The extended reserve provider must (a) (b) (c) (d) (e) (f) arm each demand unit that is designated to be armed by 16:00 hours on the start date specified in the extended reserve schedule; ensure each standby demand unit is available for service by the start date specified in the extended reserve schedule; endeavour in accordance with good electricity industry practice to maintain the ability of each demand unit to perform its AUFLS function at all times, restoring any temporary loss as soon as practicable; arm or disarm a flexible demand unit upon receipt of an arming or disarming date in an updated statement of extended reserve obligations by 16:00 hours on the business day stated in the extended reserve schedule, which may be one business day after the statement of extended reserve obligations is reissued; arm a flexible demand unit to a different AUFLS block setting by the start date specified in the extended reserve schedule for the different AUFLS block, by 16:00 hours on the business day stated in the extended reserve schedule, which may be 5 business days after the statement of extended reserve obligations is reissued; and disarm a demand unit by 16:00 hours on a stop date for that demand unit specified in the extended reserve schedule. 6. As soon as practicable after an extended reserve provider discovers any demand unit status is not compliant with its statement of extended reserve obligation (reflected in the extended reserve schedule), the extended reserve provider must provide the system operator with the date when the non-compliant situation started and the date by which the non-compliant situation will be rectified. 7. For the avoidance of doubt, while a demand unit is on standby (i.e. not armed to supply AUFLS) it may be utilised for energy shortage events and considered for participant rolling outage plans. 8. For the avoidance of doubt, selection for extended reserve does not prevent or inhibit load entering or leaving the instantaneous reserve market. An extended reserve provider must reflect any change to the quantity of interruptible load on a demand unit in the load profile submitted for each reporting period. Extended reserve manager Extended Reserve Selection Methodology v February of 31

16 Permanent loss of capability 9. The extended reserve provider may withdraw a demand unit due to its permanent loss of capability. 10. In respect to a permanent loss of capability of a demand unit (whether armed or on standby), the extended reserve provider must (a) notify the system operator of the stop date and the identity of the demand unit (i) (ii) at the time the change is planned, where the change resulting in the permanent loss of capability is planned; or as soon as practicable, where the cause is unplanned. (b) continue to provide load profile information to the extended reserve manager on the demand unit until the end of the reporting period in which the demand unit ceases to contribute to extended reserve. Provision of information for periodic performance reporting 11. The extended reserve provider must provide the extended reserve manager with load information (as described in item 24 of Part 2 of Schedule 1) for each demand unit for each reporting period in accordance with the data specification. 12. The reporting period length is four months. The information described in clause 10 of this Schedule must be supplied on or before the periodic information deadlines published in the ERM calendar, noting that (a) (b) the initial reporting period will be for a longer period from the end of the relevant historical period to the end of a recently completed month as specified in the ERM calendar; and the information must be supplied for every selected demand unit, in each reporting period, regardless of the start date for the demand unit set out in the extended reserve schedule. Management of change during implementation 13. The extended reserve provider must submit a change request to the system operator for any proposed changes to the stop and start dates published in the extended reserve schedule where the variation affects one or more demand units whose aggregated average annual offtake is greater than 1 MW or where the date varies by more than 5 business days from the date agreed in the implementation plan. Extended reserve manager Extended Reserve Selection Methodology v February of 31

17 14. The extended reserve provider must provide the following information within a change request (a) (b) (c) (d) (e) the name of each demand unit associated with the request; agreed start/stop dates as published in the extended reserve schedule; proposed new start/stop dates; the point of contact for managing the request; and the updated implementation plan. 15. The extended reserve provider must submit each change request as soon as practicable after the extended reserve provider becomes aware of the need. 16. The extended reserve provider must comply with any updates from the system operator to the extended reserve schedule including alterations to agreed implementation plan dates, where other changes occur or are proposed to occur. Extended reserve manager Extended Reserve Selection Methodology v February of 31

18 Schedule 3 Values used for selection Part 1: Expected interruption hours per year by AUFLS block b AUFLS block EIH(b) = Expected hours of interruption per year 1 AUFLS block AUFLS block AUFLS block AUFLS block Part 2: Expected interruption cost of 2 hour unanticipated outage by customer class k Customer class IC(k) = Expected Interruption Cost ($/MWh) 1 Residential 15,900 2 Light industrial & primary industry 8,200 3 Heavy industrial 19,500 4 Commercial 37,200 5 Public health and safety 100,000 6 User submitted (>25 GWh/yr) Unique value provided in response to Schedule 1, Part 2, Item 23 Extended reserve manager Extended Reserve Selection Methodology v February of 31

19 Part 3: Standard AUFLS provision cost compensation rates Each payment item is applied per AUFLS relay unless otherwise stated. Item Payment item Annual cost 1 AUFLS system administration cost (per extended reserve provider) $10,080/yr 2 Test maintenance cost $99.50/yr = net present value of $1130 in 10 years assuming a nominal interest rate of 6% and an average rate of inflation of 1.5%. 3 Relay configuring cost $1,533.39/yr = $6,470*CRF 4 Relay initial testing cost $2,931.69/yr = $12,370*CRF 5 Base relay capital cost $5,133.42/yr = $21,660*CRF 6 Additional df/dt cost $4,064.55/yr = $17,150*CRF 7 Fast response cost $0/yr 8 Flexible service cost $0/yr Where: CRF = capital recovery factor = 1/USPVF(6%,5) = USPVF(i, n) is the uniform series present value factor for n years at rate i % per annum = ((1+i) n -1)/(i*(1+i) n ) Part 4: Model parameters These model parameters are applied in the selection process. Item Description Parameter 1 Relay fast response benefit: the system benefit applied to each AUFLS relay that is capable of responding within 250 ms (as submitted under item 13, Part 2, Schedule 1) -$200/yr 2 Flexible demand unit size limit requirement 2 MW Extended reserve manager Extended Reserve Selection Methodology v February of 31

20 Schedule 4 Model formulation Extended reserve manager Extended Reserve Selection Methodology v February of 31

21 Extended reserve manager Extended Reserve Selection Methodology v February of 31

22 Extended reserve manager Extended Reserve Selection Methodology v February of 31

23 Extended reserve manager Extended Reserve Selection Methodology v February of 31

24 Extended reserve manager Extended Reserve Selection Methodology v February of 31

25 Extended reserve manager Extended Reserve Selection Methodology v February of 31

26 Extended reserve manager Extended Reserve Selection Methodology v February of 31

27 Extended reserve manager Extended Reserve Selection Methodology v February of 31

28 Schedule 5 Extended Reserve Procurement Schedule template Variable Units Description Run ID Unique code Run identifier Participant_ID Unique code Extended reserve provider identifier as per Schedule 1, item 2 Demand_Unit_ID Unique code Demand unit identifier as per Schedule 1, item 1 Region_num [1 to 3] AUFLS region number GXP Unique code Valid GXP code ANL MW Average net demand calculated as per Schedule 6 Block_num [1 to 4] Allocated AUFLS block Selected_flag [0,1] 1 if selected, 0 otherwise Flexible_flag [0,1] 1 if selected as flexible AUFLS supply, 0 otherwise Armed_flag [0,1] 1 if selected to be armed initially, 0 otherwise Reconfig_flag [0,1] 1 if selection requires AUFLS relay to be reconfigured, 0 otherwise Test_flag [0,1] 1 if selection requires AUFLS relay to be tested, 0 otherwise New_flag [0,1] 1 if selection requires a new AUFLS relay, 0 otherwise ROP $/year Relay Operating Payment calculated as per Schedule 6 RFP $/year Relay Flexibility Payment calculated as per Schedule 6 RFRP $/year Relay Fast Response Payment calculated as per Schedule 6 ASAP $/year AUFLS System Administration Payment, calculated as per Schedule 6 Extended reserve manager Extended Reserve Selection Methodology v February of 31

29 Schedule 6 Payment calculation 1. The standard annual payment applied to each extended reserve provider in the selection process is the sum of the AUFLS System Administration Payment ASAP; the Relay Operating Payment ROP(j); the Relay Fast Response Payment RFRP(j); the Relay Flexibility Payment RFP(j); the Demand Unit Interruption Payment DUIP(j); and the Relay Capital Payment RCP(j) over all selected demand units j belonging to that extended reserve provider that are in service. The AUFLS System Administration Payment for each extended reserve provider selected to provide one or more demand units is given by: ASAP = RC(1) where: RC(1) = AUFLS system administration cost in $/yr from Schedule 3 Part 3 item 1. The Relay Operating Payment for selected demand unit j is given by: ROP(j) = (RC(2)*NR) where: RC(2) = Test maintenance cost in $/yr from Schedule 3 Part 3 item 2; and NR = Total number of AUFLS relays per demand unit. The Relay Fast Response Payment (RFRP) for selected demand unit j is given by: RFRP(j) = RC(7) if j is selected and is capable of operating within 250ms as advised by the asset owner in Schedule 1 Part 2 item 13, or = 0 otherwise. where: RC(7) = Fast Response Cost in $/yr from Schedule 3 Part 3 item 7. The Relay Flexibility Payment (RFP) for selected demand unit j is given by: RFP(j) = RC(8) if j is selected for flexible AUFLS service, or Extended reserve manager Extended Reserve Selection Methodology v February of 31

30 = 0 otherwise. where: RC(8) = Flexible Service Cost in $/yr from Schedule 3 Part 3 item 8. The Demand Unit Interruption Payment for selected demand unit j is given by: DUIP(j) = (IC(j) * EIH(block(j)) * ANL(j)) where: 6 IC(j) = k=1 LS(k, j) IC(k) ; where: IC(j) = the expected demand unit interruption cost $/MWh for j; IC(k) = the generic expected interruption cost for customer class k from Schedule 3 Part 2 and Schedule 1, Part 2 item 23; LS(k,j) = the estimated proportion of demand unit j s load for customer class k. Customer class k is as per Schedule 3 Part 2. Estimated proportions are from Schedule 1, Part 2 items 17 through 22; block(j) = the AUFLS block number assigned to j in the selection process; EIH(block(j)) = the expected interruption hours /yr for block(j) from Schedule 3 Part 1; and ANL(j) = the average net demand in MW for j = the sum over all half hours, h, in the most recent 12 months of the relevant historical period of MW(j,h) as defined in Schedule 4 divided by the total number of half hours in the most recent 12 months of the relevant historical period. The Relay Capital Payment for selected demand unit j is given by: RCP(j) = { relays on demand unit j RC(3) if the AUFLS relay is required to be configured to a new AUFLS block setting; + RC(4) if the AUFLS relay is required to be tested as a result of selection for extended reserve; + RC(5) if a new AUFLS relay is required to be installed on j; and + RC(6) if the AUFLS relay is required to have df/dt functionality for the AUFLS block} = 0 if the number of whole months between the commencement of providing extended reserve under the extended reserve schedule and the payment month is greater than 60 Extended reserve manager Extended Reserve Selection Methodology v February of 31

31 where: RC(3) = Relay Configuring Cost in $/yr, per AUFLS relay, from Schedule 3 Part 3 item 3; RC(4) = Relay Initial Testing Cost in $/yr, per AUFLS relay, from Schedule 3 Part 3 item 4; RC(5) = Base Relay Capital Cost in $/yr, per AUFLS relay, from Schedule 3 Part 3 item 5; and RC(6) = Additional df/dt relay cost in $/yr, per AUFLS relay, from Schedule 3 Part 3 item The extended reserve manager uses the characteristics of the demand unit submitted by the asset owner in the selection process as follows (a) (b) (c) (d) (e) (f) (a) for each existing relay a demand unit will attract the configuring cost if selected for an AUFLS block that it was not allocated to when entering the selection process; for each existing relay a demand unit will attract the initial testing cost for the first time it is selected for extended reserve; for each existing relay a previously selected demand unit will attract the initial testing cost in a subsequent selection round if it is required to move to an AUFLS block for which the relay setting has not previously been tested; for each existing relay a demand unit that is submitted without df/dt functionality will attract the additional df/dt cost when selected for AUFLS block 4, for each new relay a demand unit will attract the base relay installation cost and the initial testing cost; the pool of flexible demand units will be selected from those that the asset owner submits will be capable of being armed and disarmed via SCADA remote control; and the AUFLS system administration cost will be applied only to the first demand unit selected from an asset owner. Extended reserve manager Extended Reserve Selection Methodology v February of 31

Contents Introduction Chapter 1 - Security Policy... 6

Contents Introduction Chapter 1 - Security Policy... 6 Policy statement Contents Introduction... 5 PURPOSE... 5 SYSTEM OPERATOR POLICIES TO ACHIEVE THE PPOS and dispatch objective... 5 Avoid Cascade Failure... 5 Frequency... 6 Other Standards... 6 Restoration...

More information

AUFLS information paper

AUFLS information paper AUFLS information paper Contents 1 Introduction... 1 2 The under-frequency management challenge... 1 3 Overview of current arrangements... 3 3.1 The current AUFLS exemptions... 4 4 Initiatives to address

More information

Distributed Generation Connection Standard ST B Planning Engineer. Network Planning Manager. General Manager Network

Distributed Generation Connection Standard ST B Planning Engineer. Network Planning Manager. General Manager Network Effective Date 1 May 2018 Issue Number 1.1 Page Number Page 1 of 26 Document Title Distributed Generation Connection Standard Document Number ST B1.1-001 Document Author Planning Engineer Document Reviewer

More information

Clearing Manager. Financial Transmission Rights. Prudential Security Assessment Methodology. 18 September with September 2015 variation

Clearing Manager. Financial Transmission Rights. Prudential Security Assessment Methodology. 18 September with September 2015 variation Clearing Manager Financial Transmission Rights Prudential Security Assessment Methodology with September 2015 variation 18 September 2015 To apply from 9 October 2015 Author: Warwick Small Document owner:

More information

Network Loss Factor Methodology

Network Loss Factor Methodology Network Loss Factor Methodology 2014-2015 Date: 12 th February 2014 T a b l e o f C o n t e n t s 1. I n t r oduction... 2 2. B a c k g r o u n d... 2 3. D e f i n i t i o n s a n d A b b r e v i a t i

More information

OtagoNet Joint Venture INFORMATION DISCLOSURE PREPARED IN ACCORDANCE WITH SUBPART 3 OF PART 4A OF THE COMMERCE ACT 1986

OtagoNet Joint Venture INFORMATION DISCLOSURE PREPARED IN ACCORDANCE WITH SUBPART 3 OF PART 4A OF THE COMMERCE ACT 1986 OtagoNet Joint Venture INFORMATION DISCLOSURE PREPARED IN ACCORDANCE WITH SUBPART 3 OF PART 4A OF THE COMMERCE ACT 1986 FOR THE YEAR ENDED 31 MARCH 2010 CONTENTS 1. Introduction... 3 2. Disclaimer... 3

More information

Information Disclosure prepared according to. subpart 3 of the Part 4A Commerce Act 1986

Information Disclosure prepared according to. subpart 3 of the Part 4A Commerce Act 1986 Information Disclosure prepared according to subpart 3 of the Part 4A Commerce Act 1986 For the Assessment Period: 1 April 2007-31 March 2008 I. Contents I. Introduction... 4 II. Structure of Eastland

More information

RevisedAmended Pproposed revisions to the Access Arrangement for the Western Power Network

RevisedAmended Pproposed revisions to the Access Arrangement for the Western Power Network RevisedAmended Pproposed revisions to the Access Arrangement for the Western Power Network Formatted: Top: 2.5 cm Formatted: Font: (Default) Arial, 30 pt, Bold Formatted: Font: (Default) Arial, 30 pt,

More information

September 30th, 2013 Dave and TFSS, Please find attached final responses to the clarification requests on the NPCC Regional Standard for Automatic UFLS PRC -006-NPCC-1 as reviewed and approved during the

More information

OtagoNet Joint Venture

OtagoNet Joint Venture OtagoNet Joint Venture INFORMATION DISCLOSURE PREPARED IN ACCORDANCE WITH SUBPART 3 OF PART 4A OF THE COMMERCE ACT 1986 FOR THE YEAR ENDED 31 MARCH 2011 CONTENTS 1. Introduction... 3 2. Disclaimer... 3

More information

Information Disclosure

Information Disclosure Electricity Ashburton Limited trading as EA Networks Information Disclosure Prepared according to subpart 3 of the Part 4A Commerce Act 1986 Assessment Period: 1 April 2011 31 March 2012 Date: 11 December

More information

Standard Development Timeline

Standard Development Timeline PRC 012 2 Remedial Action Schemes Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective.

More information

Project Assessment Conclusions Report

Project Assessment Conclusions Report Powerlink Queensland Project Assessment Conclusions Report 27 August 2018 Addressing the secondary systems condition Disclaimer While care was taken in preparation of the information in this document,

More information

Electricity Distribution Information Disclosure Determination 2012 (consolidated in 2015)

Electricity Distribution Information Disclosure Determination 2012 (consolidated in 2015) ISBN 978-1-869454-39-5 Project no. 14.09:15.01/14700:14699 Public version Electricity Distribution Information Disclosure Determination 2012 (consolidated in 2015) Date of consolidation: 24 March 2015

More information

HORIZON ENERGY DISTRIBUTION LIMITED

HORIZON ENERGY DISTRIBUTION LIMITED HORIZON ENERGY DISTRIBUTION LIMITED THRESHOLD COMPLIANCE STATEMENT FOR THE ASSESSMENT DATE, 31 MARCH 2010 Pursuant to the Commerce Act (Electricity Distribution Thresholds) Notice 2004 and Amendment Notice

More information

Information Disclosure by Aurora Energy Ltd for the year ended 31 March 2008

Information Disclosure by Aurora Energy Ltd for the year ended 31 March 2008 Information Disclosure by Aurora Energy Ltd for the year ended 31 March 2008 Pursuant to the ELECTRICITY DISTRIBUTION (INFORMATION DISCLOSURE) REQUIREMENTS 2008 INDEX Page A Statutory Declaration for Publicly

More information

Transpower Individual Price-Quality Path Determination NZCC XX

Transpower Individual Price-Quality Path Determination NZCC XX 1 Project no. 14.11/14120 Public version Transpower Individual Price-Quality Path Determination NZCC XX The Commission: S Begg P Duignan Dr S Gale Summary of the determination: Pursuant to Part 4 of the

More information

Solar Feed-In Tariff (FIT) Scheme Terms. Victoria. Version January Tango Energy Pty Ltd ABN

Solar Feed-In Tariff (FIT) Scheme Terms. Victoria. Version January Tango Energy Pty Ltd ABN Solar Feed-In Tariff (FIT) Scheme Terms Victoria Version 2.1 1 January 2019 Tango Energy Pty Ltd ABN 43 155 908 839 tangoenergy.com Table of Contents Feed-In Tariff Scheme Terms... 3 Preamble... 3 1 About

More information

Information Disclosure prepared according to subpart 3 of Part 4A of the Commerce Act 1986

Information Disclosure prepared according to subpart 3 of Part 4A of the Commerce Act 1986 Information Disclosure prepared according to subpart 3 of Part 4A of the Commerce Act 1986 For the Year Ended 31 March 2011 SUPPLEMENTARY UNAUDITED INFORMATION EXPLANATORY NOTE (UNAUDITED) This is an explanatory

More information

DS3 System Services Protocol Interim Arrangements

DS3 System Services Protocol Interim Arrangements DS3 System Services Protocol Interim Arrangements DS3 System Services Implementation Project August 2017 Version 2.1 Contents 1 Introduction... 3 2 Governance... 5 3 Compliance Requirements... 6 4 Performance

More information

EXCERPTS from the SAMS-SPCS SPS Technical Reference

EXCERPTS from the SAMS-SPCS SPS Technical Reference Problem Statement The existing NERC Glossary of Terms definition for a Special Protection System (SPS or, as used in the Western Interconnection, a Remedial Action Scheme or RAS) lacks clarity and specificity

More information

Consultation paper. Review of Guaranteed Service Levels to apply in Queensland from 1 July 2020

Consultation paper. Review of Guaranteed Service Levels to apply in Queensland from 1 July 2020 Consultation paper Review of Guaranteed Service Levels to apply in Queensland from 1 July 2020 February 2018 Queensland Competition Authority 2018 The Queensland Competition Authority supports and encourages

More information

Settlement and prudential security methodologies. 15 April 2015 Version 1.1

Settlement and prudential security methodologies. 15 April 2015 Version 1.1 Settlement and prudential security methodologies 15 April 2015 Version 1.1 Version Control Version Date Status Comment 1.0 25/07/2014 Approved by Authority Initial release 1.1 15/04/2015 Draft submitted

More information

CUSC - SECTION 3 USE OF SYSTEM CONTENTS

CUSC - SECTION 3 USE OF SYSTEM CONTENTS CUSC - SECTION 3 USE OF SYSTEM CONTENTS 3.1 Introduction PART IA - GENERAL - GENERATION 3.2 Rights to Use the National Electricity Transmission System 3.3 Other Site Specific Technical Conditions for Embedded

More information

ARRANGEMENT OF REGULATIONS

ARRANGEMENT OF REGULATIONS L.I.1935 ELECTRICITY SUPPLY AND DISTRIBUTION (STANDARDS OF PERFORMANCE) REGULATIONS, 2008 Regulation 1. Purpose 2. Application ARRANGEMENT OF REGULATIONS Purpose and Application Application for new service

More information

9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the

9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the First Revised Sheet No. 121 ORIGINAL VOLUME NO. I Replacing Original Sheet No. 121 9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. 9.1 Nature of Relationship. Each Participating TO shall enter into

More information

stated. This Ruling applies is the issue Manager. b) of Asteron A Life PO P Box 2198 Wellington W 6140 New N Zealand Telephone: T

stated. This Ruling applies is the issue Manager. b) of Asteron A Life PO P Box 2198 Wellington W 6140 New N Zealand Telephone: T Office O of the Chief Tax Counsel Te T Tari o te Rōia Tāke Matua Asteron A Life 555 Featherstonn Street PO P Box 2198 Wellington W 6140 New N Zealand Telephone: T 044 890-1500 Facsimile F Numbers: Chief

More information

Future Development Plan:

Future Development Plan: Standard BAL-007-1 Balance of Resources and Demand Standard Development Roadmap This section is maintained by the drafting team during the development of the standard and will be removed when the standard

More information

Expenditure Forecast Methodology

Expenditure Forecast Methodology Forecast Methodology Regulatory Control Period 2018-19 to 2022-23 Version 1.0 Security Classification: Public ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box

More information

Nelson Electricity Ltd Asset Management Plan Update

Nelson Electricity Ltd Asset Management Plan Update Nelson Electricity Ltd Asset Management Plan Update April 2017 March 2027 April 2017 Nelson Electricity Ltd central Nelson city view In accordance with the Commerce Act Electricity Distribution Information

More information

ELECTRA LIMITED 2010 INFORMATION FOR DISCLOSURE. Pursuant to Secton 57T of the Commerce Act 1986

ELECTRA LIMITED 2010 INFORMATION FOR DISCLOSURE. Pursuant to Secton 57T of the Commerce Act 1986 ELECTRA LIMITED 2010 INFORMATION FOR DISCLOSURE Pursuant to Secton 57T of the Commerce Act 1986 - - Table of contents Certificate for Disclosed Information 2 Statutory Declaration for Publicly Disclosed

More information

Transpower Individual Price-Quality Path Determination 2015

Transpower Individual Price-Quality Path Determination 2015 ISBN 978-1-869456-27-6 Project no. 14.11/14120 Public version Transpower Individual Price-Quality Path Determination 2015 This consolidated version of the principal determination and amendment determinations

More information

Connection and Use of System Charge Methodology Statement ("Condition 25 Statement")

Connection and Use of System Charge Methodology Statement (Condition 25 Statement) Connection and Use of System Charge Methodology Statement ("Condition 25 Statement") Revised Effective Date: 1 st January 2016 Approved by the Authority for Electricity Regulation, Oman Connection and

More information

Network Loss Factor Methodology

Network Loss Factor Methodology Network Loss Factor Methodology 2011-2012 Date: 28 February 2011 Table of Contents 1. Introduc t ion...1 2. Ba ckground...1 3. Definit ions a nd Abbrev iat ions...2 4. N etwork Energ y L oss es...3 4.1

More information

MODEL INTERCONNECTION PROCEDURES

MODEL INTERCONNECTION PROCEDURES MODEL INTERCONNECTION PROCEDURES 2009 EDITION Introduction IREC first developed model interconnection procedures in 2005 in an effort to capture emerging best practices in this vital area. Since that time,

More information

MODEL STANDING OFFER TERMS & CONDITIONS FOR BASIC CONNECTION SERVICES FOR RETAIL CUSTOMERS WHO ARE SMALL GENERATORS 3602

MODEL STANDING OFFER TERMS & CONDITIONS FOR BASIC CONNECTION SERVICES FOR RETAIL CUSTOMERS WHO ARE SMALL GENERATORS 3602 MODEL STANDING OFFER TERMS & CONDITIONS FOR BASIC CONNECTION SERVICES FOR RETAIL CUSTOMERS WHO ARE SMALL GENERATORS 3602 SA Power Networks www.sapowernetworks.com.au 3602 - MSO T_C's for BCS for Retail

More information

DRAFT STCP 18-1 Issue 004 Connection and Modification Application

DRAFT STCP 18-1 Issue 004 Connection and Modification Application STCP 18-1 Connection and Modification Application Draft Issue 004 - June 2014 DRAFT STCP 18-1 Issue 004 Connection and Modification Application STC Procedure Document Authorisation Party Name of Party

More information

Access arrangement. JGN s NSW gas distribution networks. 1 July June [June 2015]

Access arrangement. JGN s NSW gas distribution networks. 1 July June [June 2015] Access arrangement JGN s NSW gas distribution networks 1 July 2015 30 June 2020 [June 2015] (Incorporating revisions required by AER Final Decision 3 June 2015) Contents 1 Introduction 1 2 Services policy

More information

Electricity Distribution (Information Disclosure) Requirements October 2008

Electricity Distribution (Information Disclosure) Requirements October 2008 Electricity Distribution (Information Disclosure) Requirements 2008 31 October 2008 ELECTRICITY DISTRIBUTION (INFORMATION DISCLOSURE) REQUIREMENTS 2008 1. Title, commencement, and application Contents

More information

Common Quality Development Plan Evaluation of Options

Common Quality Development Plan Evaluation of Options Common Quality Development Plan Evaluation of Options Table of Contents Introduction and Purpose... 4 Background... 4 Summary... 6 Overall Approach... 10 Frequency Development... 12 Overview of current

More information

Attachment C: How capital expenditure is proposed and approved under the capex IM

Attachment C: How capital expenditure is proposed and approved under the capex IM ISBN no. 978-1-869455-84-2 Project no. 14.09/16274 Public version Attachment C: How capital expenditure is proposed and approved under the capex IM Transpower capex input methodology review - Proposed

More information

Effective for SERC Region applicable Registered Entities on the first day of the first calendar quarter after approved by FERC.

Effective for SERC Region applicable Registered Entities on the first day of the first calendar quarter after approved by FERC. Effective Date Effective for SERC Region applicable Registered Entities on the first day of the first calendar quarter after approved by FERC. Introduction 1. Title: Automatic Underfrequency Load Shedding

More information

Solar Premium Feed-In Tariff (PFIT) Scheme Terms. Victoria. Version June Tango Energy Pty Ltd ABN

Solar Premium Feed-In Tariff (PFIT) Scheme Terms. Victoria. Version June Tango Energy Pty Ltd ABN Solar Premium Feed-In Tariff (PFIT) Scheme Terms Victoria Version 2.0 4 June 2018 Tango Energy Pty Ltd ABN 43 155 908 839 tangoenergy.com Table of Contents Premium Feed-In Tariff Scheme Terms... 3 Preamble...

More information

New Mexico Public Regulation Commission P. O. Box Paseo de Peralta Santa Fe, New Mexico 87504

New Mexico Public Regulation Commission P. O. Box Paseo de Peralta Santa Fe, New Mexico 87504 THE NEW MEXICO INTERCONNECTION MANUAL (To be Used in Conjunction with New Mexico Public Regulation Commission Rule 17.9.568 NMAC, Interconnection of Generating Facilities with a Rated Capacity Up to and

More information

TRIP OF MULTIPLE TRANSMISSION ELEMENTS IN THE SOUTHERN NSW AREA, 11 FEBRUARY 2017

TRIP OF MULTIPLE TRANSMISSION ELEMENTS IN THE SOUTHERN NSW AREA, 11 FEBRUARY 2017 TRIP OF MULTIPLE TRANSMISSION ELEMENTS IN THE SOUTHERN NSW AREA, 11 FEBRUARY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: 15 September 2017 INCIDENT CLASSIFICATIONS

More information

Station Power Standby Service Schedule Designation R3 Standard Contract Rider No. 3

Station Power Standby Service Schedule Designation R3 Standard Contract Rider No. 3 Station Power Standby Service Schedule Designation R3 Standard Contract Rider No. 3 DE 963-1826 2/17 THIS RIDER, dated 20, is attached to and becomes a part of an electric service agreement dated 20, between,

More information

Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA Distribution Systems

Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA Distribution Systems Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA Distribution Systems -1- TABLE OF CONTENTS Section I. Application Process..

More information

Handbook for Optimised. Deprival Valuation of System Fixed Assets of. Electricity Lines Businesses

Handbook for Optimised. Deprival Valuation of System Fixed Assets of. Electricity Lines Businesses Handbook for Optimised Deprival Valuation of System Fixed Assets of Electricity Lines Businesses REVISED DRAFT FOR CONSULTATION 9 July 2004 Adjusted for Transpower Comments Deleted: 15 Deleted: 14 Inserted:

More information

FINAL Framework and Approach for Powerlink

FINAL Framework and Approach for Powerlink FINAL Framework and Approach for Powerlink For the regulatory control period commencing 2017 June 2015 Powerlink 2017 22 Framework and approach 1 Powerlink 2017 22 Framework and approach 2 Powerlink 2017

More information

SCHEDULE 72 INTERCONNECTIONS TO NON-UTILITY GENERATION

SCHEDULE 72 INTERCONNECTIONS TO NON-UTILITY GENERATION Idaho Power Company Second Revised Sheet No. 72-1 I.P.U.C. No. 29, Tariff No. 101 First Revised Sheet No. 72-1 PUBLIC UTILITIES COMMISSION AVAILABILITY Service under this schedule is available throughout

More information

Electricity Distribution Information Disclosure Amendments Determination 2017 [2017] NZCC 33

Electricity Distribution Information Disclosure Amendments Determination 2017 [2017] NZCC 33 ISSN 1178-2560 Project no. 16104: 16275 Public version Electricity Distribution Information Disclosure Amendments Determination 2017 [2017] NZCC 33 The Commission: Sue Begg Dr Stephen Gale Dr Mark Berry

More information

AGREEMENT FOR PURCHASE OF AS-AVAILABLE ENERGY AND/OR PARALLEL OPERATION WITH A QUALIFYING FACILITY TABLE OF CONTENTS

AGREEMENT FOR PURCHASE OF AS-AVAILABLE ENERGY AND/OR PARALLEL OPERATION WITH A QUALIFYING FACILITY TABLE OF CONTENTS ProgressEnergy SECOND REVISED SHEET No. 9.100 CANCELS FIRST REVISED SHEET No. 9.100 AGREEMENT FOR PURCHASE OF AS-AVAILABLE ENERGY AND/OR PARALLEL OPERATION WITH A QUALIFYING FACILITY TABLE OF CONTENTS

More information

Regulation of the NZ electricity market. Presentation to EMAN 410 Students, University of Otago 19 July 2013 Carl Hansen

Regulation of the NZ electricity market. Presentation to EMAN 410 Students, University of Otago 19 July 2013 Carl Hansen Regulation of the NZ electricity market Presentation to EMAN 410 Students, University of Otago 19 July 2013 Carl Hansen Overview Current regulatory arrangements for electricity Overview of NZ electricity

More information

The strategic reserve a mechanism to cover structural shortages

The strategic reserve a mechanism to cover structural shortages Balance The strategic reserve a mechanism to cover structural shortages Elia has been given the task of organising a strategic reserve mechanism to cover the structural shortages in the winter period.

More information

SIMULTANEOUS TRIP OF SOUTH EAST No.1 AND No kv SVCs ON 31 JULY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES

SIMULTANEOUS TRIP OF SOUTH EAST No.1 AND No kv SVCs ON 31 JULY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES SIMULTANEOUS TRIP OF SOUTH EAST No.1 AND No.2 275 kv SVCs ON 31 JULY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: 20 September 2017 INCIDENT CLASSIFICATIONS

More information

Market Contract Terms

Market Contract Terms Market Contract Terms Electricity Market Retail Contract between Aurora Energy and you Aurora Energy Pty Ltd l ABN 85 082 464 622 21 Kirksway Place, Battery Point Tasmania 7004 Ph: 1300 132 003 Fax: (03)

More information

Applicable Balancing Services Volume Data Methodology Statement

Applicable Balancing Services Volume Data Methodology Statement Applicable Balancing Services Volume Data Methodology Statement Effective Date: 01 April 2018 Version Number: 8.0 Published in accordance with Standard Condition C16 of National Grid Electricity Transmission

More information

EDB Information Disclosure Requirements Information Templates for Schedules 1 10

EDB Information Disclosure Requirements Information Templates for Schedules 1 10 EDB Information Disclosure Requirements Information Templates for Schedules 1 10 Disclosure Date 31 August 2016 Disclosure Year (year ended) Templates for Schedules 1 10 excluding 5f 5g Template Version

More information

Newfoundland. Brunswick R1 NA NA NA NA NA NA NA NA NA

Newfoundland. Brunswick R1 NA NA NA NA NA NA NA NA NA Effective Dates Requirement Jurisdiction Alberta British Columbia Manitoba New Brunswick Newfoundland Nova Scotia Ontario Quebec Saskatchewan USA R1 NA NA NA NA NA NA NA NA NA 4/1/14 R2 NA NA NA NA NA

More information

TRANSGRID PRICING METHODOLOGY 2015/ /18. Contents

TRANSGRID PRICING METHODOLOGY 2015/ /18. Contents Pricing Methodology TRANSGRID PRICING METHODOLOGY 2015/16 2017/18 Contents Pricing Methodology 1 Introduction 3 2 Duration 3 3 Which services are subject to this pricing methodology? 4 4 Overview of the

More information

Compensation for damage and loss following electricity outage September 2015

Compensation for damage and loss following electricity outage September 2015 Compensation for damage and loss following electricity outage September 2015 Background EWOV receives and investigates complaints about claims for damage or loss following supply reliability or interruption

More information

PREMIUM FEED-IN TARIFF SCHEME TERMS

PREMIUM FEED-IN TARIFF SCHEME TERMS PREMIUM FEED-IN TARIFF SCHEME TERMS PREAMBLE These Terms set out the conditions on which we will purchase electricity from you, our Customer, if you are a Qualifying Customer for the Premium Feed-In Tariff

More information

Creation of a New Electricity Market Operation Service Provider and Minor Levy Regulation Amendments

Creation of a New Electricity Market Operation Service Provider and Minor Levy Regulation Amendments DRAFT File No: C/004/ME/004 OFFICE OF THE MINISTER OF ENERGY AND RESOURCES The Chair Cabinet Economic Growth and Infrastructure Committee Creation of a New Electricity Market Operation Service Provider

More information

Chorus UFB Services Agreement. Bitstream Services: Service Level Terms for Bitstream Services

Chorus UFB Services Agreement. Bitstream Services: Service Level Terms for Bitstream Services Chorus UFB Services Agreement Bitstream Services: Service Level Terms for Bitstream Services Reference Offer June 2018 - [Approved at Product Forum and published as interim pending CIP approval] 1 INTERPRETATION

More information

The Narragansett Electric Company d/b/a National Grid Tariff Advice Filing to Amend R.I.P.U.C. No Docket No.

The Narragansett Electric Company d/b/a National Grid Tariff Advice Filing to Amend R.I.P.U.C. No Docket No. Jennifer Brooks Hutchinson Senior Counsel July 13, 2012 Luly E. Massaro, Commission Clerk Rhode Island Public Utilities Commission 89 Jefferson Boulevard Warwick, RI 02888 RE: The Narragansett Electric

More information

INFORMATION DISCLOSURE PREPARED IN ACCORDANCE WITH ELECTRICITY INFORMATION DISCLOSURE DETERMINATION UNDER PART 4 OF THE COMMERCE ACT 1986

INFORMATION DISCLOSURE PREPARED IN ACCORDANCE WITH ELECTRICITY INFORMATION DISCLOSURE DETERMINATION UNDER PART 4 OF THE COMMERCE ACT 1986 PREPARED IN ACCORDANCE WITH ELECTRICITY DETERMINATION UNDER PART 4 OF THE COMMERCE ACT 1986 FOR THE YEAR ENDED 31 MARCH 2013 CONTENTS 1. Introduction... 3 2. Disclaimer... 3 3. Schedules... 4 i. Schedule

More information

Applicable Balancing Services Volume Data Methodology Statement

Applicable Balancing Services Volume Data Methodology Statement Applicable Balancing Services Volume Data Methodology Statement Version Effective Date: 1 April 20131 Effective in respect of Settlement Days from : 01 April 2011 ABSVD Methodology Statement 1 Version

More information

TRANSMISSION CHARGING STATEMENT

TRANSMISSION CHARGING STATEMENT TRANSMISSION CHARGING STATEMENT 1 September 2016 1 September 2016 TABLE OF CONTENTS Page 1 Introduction... 1 2 General System Charges... 4 3 Site Specific Charges... 5 4 Connection Assets... 8 5 Least

More information

Terms & Conditions. Our commitment to you! Electricity Customers (VIC, NSW, QLD, SA, WA)

Terms & Conditions. Our commitment to you! Electricity Customers (VIC, NSW, QLD, SA, WA) Terms & Conditions Our commitment to you! Electricity Customers (VIC, NSW, QLD, SA, WA) Introduction This Agreement is about the sale and supply of electricity to you as an Embedded Network customer. This

More information

EFFICIENT DISPATCH AND LOCALISED RECOVERY OF REGULATION SERVICES BUSINESS SPECIFICATION

EFFICIENT DISPATCH AND LOCALISED RECOVERY OF REGULATION SERVICES BUSINESS SPECIFICATION EFFICIENT DISPATCH AND LOCALISED RECOVERY OF REGULATION SERVICES BUSINESS SPECIFICATION PREPARED BY: DOCUMENT NO: 160-0392 VERSION NO: 1.01 EFFECTIVE DATE: 01/07/2010 ENTER STATUS: Market Operations Performance

More information

Dodo Power & Gas Energy Market Contract Terms and Conditions

Dodo Power & Gas Energy Market Contract Terms and Conditions Dodo Power & Gas Energy Market Contract Terms and Conditions Important Notice to the Consumer You have a right to cancel this agreement within 10 Business Days from

More information

INFORMATION DISCLOSURE PREPARED

INFORMATION DISCLOSURE PREPARED PREPARED IN ACCORDANCE WITH ELECTRICITY DETERMINATION UNDER PART 4 OF THE COMMERCE ACT 1986 FOR THE YEAR ENDED 31 MARCH 2013 CONTENTS 1. Introduction... 3 2. Disclaimer... 3 3. Schedules... 4 i. Schedule

More information

Kind of Service: Electric Class of Service: All Docket No.: U Order No.: 19 Part III. Rate Schedule No. 35 Effective: 3/31/16

Kind of Service: Electric Class of Service: All Docket No.: U Order No.: 19 Part III. Rate Schedule No. 35 Effective: 3/31/16 7 th Revised Sheet No. 35.1 Schedule Sheet 1 of 5 Replacing: 6 th Revised Sheet No. 35.1 35.0. LARGE COGENERATION RIDER 35.1. AVAILABILITY To any customer who takes service under the provisions of any

More information

Loss of Transmission Access Compensation Guidance Note for Customers

Loss of Transmission Access Compensation Guidance Note for Customers Loss of Transmission Access Compensation Guidance Note for Customers This document has been produced to complement the Loss of Transmission Access Compensation Claim Form. Both the claim form and this

More information

Electricity supply contract (deemed)

Electricity supply contract (deemed) Electricity supply contract (deemed) Tasmanian Networks Pty Ltd a CONTENTS Preamble...1 1. The Parties...1 2. Definitions and Interpretations...1 3. Do these terms and conditions apply to you?...1 4. What

More information

Con Edison Performance-Based Gas Demand Response Pilot Guidelines

Con Edison Performance-Based Gas Demand Response Pilot Guidelines Con Edison Performance-Based Gas Demand Response Pilot Guidelines 2018/19 Capability Period Last updated: 09/10/2018 Performance-Based Gas DR Pilot Guidelines Consolidated Edison Contents Acronyms and

More information

SPP Reserve Sharing Group Operating Process

SPP Reserve Sharing Group Operating Process SPP Reserve Sharing Group Operating Process Effective: 1/1/2018 1.1 Reserve Sharing Group Purpose In the continuous operation of the electric power network, Operating Capacity is required to meet forecasted

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 36. Congestion Revenue Rights... 3 36.1 Overview Of CRRs And Procurement Of CRRs... 3 36.2 Types Of CRR Instruments... 3 36.2.1 CRR Obligations... 3 36.2.2 CRR Options... 3 36.2.3 Point-To-Point

More information

The Victory Electric Cooperative Association, Inc. Schedule of Tariffs Table of Contents

The Victory Electric Cooperative Association, Inc. Schedule of Tariffs Table of Contents The Victory Electric Cooperative Association, Inc. Schedule of Tariffs Table of Contents Description Status Schedule Index All-Electric Service Active AE-17 2 Domestic Service Active D-17 3 Small Commercial

More information

WISCONSIN GAS LLC Gas Service Rates, Rules and Regulations. Tariff Book

WISCONSIN GAS LLC Gas Service Rates, Rules and Regulations. Tariff Book VOLUME 7 SHEET NO. 1.00 ORIGINAL SCHEDULE WISCONSIN GAS LLC AMENDMENT NO. 645 WISCONSIN GAS LLC Gas Service Rates, Rules and Regulations Tariff Book ISSUED 01-25-2006. EFFECTIVE FOR SERVICE FURNISHED ON

More information

SHORT-TERM OPERATING RESERVE DESPATCH PROCEDURE STOR DESPATCH PROCEDURE. for Non-Balancing Mechanism Participants

SHORT-TERM OPERATING RESERVE DESPATCH PROCEDURE STOR DESPATCH PROCEDURE. for Non-Balancing Mechanism Participants SHORT-TERM OPERATING RESERVE DESPATCH PROCEDURE STOR DESPATCH PROCEDURE for Non-Balancing Mechanism Participants Version 1.3 reviewed December 2008 ASP1 CONTENTS PART 1 - STOR DESPATCH INTRODUCTION...1

More information

Handbook for Optimised. Deprival Valuation of System Fixed Assets of. Electricity Lines Businesses

Handbook for Optimised. Deprival Valuation of System Fixed Assets of. Electricity Lines Businesses Handbook for Optimised Deprival Valuation of System Fixed Assets of Electricity Lines Businesses 30 August 2004 CONTENTS ABBREVIATIONS USED IN THE HANDBOOK... 3 PREFACE... 5 PART ONE: INTRODUCTION...

More information

Electricity Generation Feed-in Terms.

Electricity Generation Feed-in Terms. Electricity Generation Feed-in Terms. Victoria. Powerdirect Electricity Generation Feed-in Terms. 1. Eligibility for this Electricity Generation Feed-In Plan 1 2. About your Powerdirect Electricity Generation

More information

MainPower New Zealand Limited. Asset Management Plan

MainPower New Zealand Limited. Asset Management Plan MainPower New Zealand Limited. Asset Management Plan 2015 2025 MAINPOWER NEW ZEALAND LIMITED ASSET MANAGEMENT PLAN UPDATE 2015-2025 MainPower New Zealand Limited Asset Management Plan Update 2015-2025

More information

THE NARRAGANSETT ELECTRIC COMPANY TERMS AND CONDITIONS FOR DISTRIBUTION SERVICE

THE NARRAGANSETT ELECTRIC COMPANY TERMS AND CONDITIONS FOR DISTRIBUTION SERVICE THE NARRAGANSETT ELECTRIC COMPANY TERMS AND CONDITIONS FOR DISTRIBUTION SERVICE RIPUC No. 2217 Sheet 1 The following Terms and Conditions where not inconsistent with the rates are a part of all rates.

More information

PRC Remedial Action Schemes

PRC Remedial Action Schemes PRC-012-2 Remedial Action Schemes A. Introduction 1. Title: Remedial Action Schemes 2. Number: PRC-012-2 3. Purpose: To ensure that Remedial Action Schemes (RAS) do not introduce unintentional or unacceptable

More information

Default Price-Quality Path Compliance

Default Price-Quality Path Compliance Default Price-Quality Path Compliance Wellington Electricity Lines Limited Annual Compliance Statement 09 June 2014 Contents 1. INTRODUCTION... 3 1.1. Compliance with 2012 DPP Determination s price quality

More information

Market Contract Terms & Conditions.

Market Contract Terms & Conditions. Market Contract Terms & Conditions. 1. Background This contract is between: ERM Power Retail Pty Ltd ABN 87 126 175 460 who sells electricity to you at your premises (referred to as we, our or us ); and

More information

What to do if you think a bill s incorrect (p10)

What to do if you think a bill s incorrect (p10) What s in this brochure? It s full of the important stuff you need to know about your agreement with us. All your terms and conditions, including things like: What to do if you think a bill s incorrect

More information

Wellington Electricity CPP assessment of 2010/21 capex

Wellington Electricity CPP assessment of 2010/21 capex Commerce Commission P O Box 2351 Wellington 6140 For the Attention of: Kade Sheely 18th January 2018 Dear Kade Wellington Electricity CPP assessment of 2010/21 capex I am pleased to provide this briefing

More information

Branch Name Commerce Commission Wellington NEW ZEALAND 27 June 2011 ISBN:

Branch Name Commerce Commission Wellington NEW ZEALAND 27 June 2011 ISBN: Draft decision Minor Capital Expenditure and Operating Expenditure Allowances, and Quality Standards to apply to Transpower for the Remainder Period of Regulatory Control Period 1 Branch Name Commerce

More information

Uttar Pradesh Electricity Regulatory Commission

Uttar Pradesh Electricity Regulatory Commission Uttar Pradesh Electricity Regulatory Commission In exercise of the powers conferred under Section 181 of the Electricity Act, 2003 and all powers enabling it in this behalf, the Uttar Pradesh Electricity

More information

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. Glossary ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs. ALAP (as late as possible) A constraint placed on a task s timing to make it occur

More information

WISCONSIN ELECTRIC - GAS OPERATIONS Gas Service Rates, Rules and Regulations. Tariff Book

WISCONSIN ELECTRIC - GAS OPERATIONS Gas Service Rates, Rules and Regulations. Tariff Book VOLUME XVI SHEET NO. 1.00 ORIGINAL SCHEDULE WISCONSIN ELECTRIC - GAS OPERATIONS AMENDMENT NO. 489 WISCONSIN ELECTRIC - GAS OPERATIONS Gas Service Rates, Rules and Regulations Tariff Book ISSUED 01-25-2006.

More information

Section T: Settlement and Trading Charges. how Trading Charges for each Trading Party and National Grid are determined;

Section T: Settlement and Trading Charges. how Trading Charges for each Trading Party and National Grid are determined; BSC Simple Guide Section T: Settlement and Trading Charges Section T sets out: (a) (b) (c) how Trading Charges for each Trading Party and National Grid are determined; the data required in order to calculate

More information

DS3 System Services Protocol Regulated Arrangements

DS3 System Services Protocol Regulated Arrangements DS3 System Services Protocol Regulated Arrangements DS3 System Services Implementation Project 12 December 2017 Version 1.0 Contents 1 Introduction... 4 1.1 Service Provider Intermediary for a Providing

More information

Electricity Standard Terms and Conditions

Electricity Standard Terms and Conditions Electricity Standard Terms and Conditions 1 Our arrangement with you 1.1 In these terms and conditions, "We" is used to mean Electricity Direct Ltd, and "You" is used to mean you, our customer. 1.2 Our

More information

1.1 These regulations shall extend to whole of the State of Punjab.

1.1 These regulations shall extend to whole of the State of Punjab. THE PUNJAB STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION The, 2018 No.PSERC/Secy/Regu. - In exercise of the powers conferred under Section 181of the Electricity Act, 2003 (36 of 2003), and all other

More information

CASE 17-M-0178 Draft Discussion Document, November 2017 Session, Publicly Released November 15, 2017 STATE OF NEW YORK PUBLIC SERVICE COMMISSION

CASE 17-M-0178 Draft Discussion Document, November 2017 Session, Publicly Released November 15, 2017 STATE OF NEW YORK PUBLIC SERVICE COMMISSION STATE OF NEW YORK PUBLIC SERVICE COMMISSION At a session of the Public Service Commission held in the City of COMMISSIONERS PRESENT: CASE 17-M-0178 - Petition of Orange and Rockland Utilities, Inc. for

More information

Comparison of Performance-Based Capacity Models in ISO-NE and PJM June 2, 2016

Comparison of Performance-Based Capacity Models in ISO-NE and PJM June 2, 2016 Comparison of Performance-Based Capacity Models in ISO-NE and PJM June 2, 2016 Michael Borgatti, Director, RTO Services Gabel Associates, Inc. Michael.Borgatti@gabelassociates.com 732.296.0770 1 Goals

More information