(U 338-E) 2018 General Rate Case A Workpapers. 3 rd ERRATA. T&D- Grid Modernization SCE-02 Volume 10
|
|
- Abigayle Rich
- 6 years ago
- Views:
Transcription
1 (U 338-E) 2018 General Rate Case A Workpapers 3 rd ERRATA T&D- Grid Modernization SCE-02 Volume 10 September 2016
2 124a Customer Interruption Cost Analysis Results Year 1 Customer Interruption Cost Analysis Results Southern California Edison (SCE) retained Nexant to estimate the costs that customers incur as a result of sustained and momentary interruptions 1 on its system. Using three years of historical power interruption data from SCE, this report provides lower and upper bound estimates of the average cost per customer minute interrupted (CMI) and the average cost per momentary interruption for each customer. Table 1-1 shows the results of the customer interruption cost per CMI analysis (in 2016$). The lower bound of the cost per CMI estimate is based on the following nationwide study: Lawrence Berkeley National Laboratory (LBNL) Report No. LBNL-6941E, Updated Value of Service Reliability Estimates for Electric Utility Customers in the United States. 2 The upper bound is based on a comparative analysis of the LBNL report and the 2012 systemwide customer interruption cost survey by Pacific Gas & Electric Company (PG&E). 3 This comparative analysis found that the nationwide LBNL study underestimates interruption costs in California by about 40%. The lower bound of the average cost per CMI for SCE s service territory across the three years analyzed is $ ($907,530,958954,553,754 average total estimated cost / 546,328,512550,198,137 average total CMI). This is 40% lower than the upper bound of $ cost per CMI. The Customer Average Interruption Duration Index (CAIDI) represents the average duration a customer can expect for a given interruption. In other words, a customer in SCE s territory has, on average, an expected duration of minutes for any interruption (546,328,512550,198,137 total CMI / 4,665,0564,657,020 total number of customers affected 4 ). Total # of Interruptions Table 1-1: Interruption Costs per Customer Minute Interrupted Avg. # of Customers Affected Total CMI CAIDI (Minutes) Total Estimated Costs (2016$) Cost per CMI (2016$) Lower Upper , ,781, $877,824,659$890,853,398 $1.72$1.74 $2.88$ , ,851, $946,475,040$960,908,574 $1.68$1.71 $2.83$ ,07327, ,352,948577,961, $898,293,174$1,011,899,290 $1.59$1.75 $2.66$2.94 Average 25, ,328,512550,198, $907,530,958$954,553,754 $1.66$1.73 $2.79$2.91 Table 1-2 shows the results of the customer cost analysis for momentary interruptions. The lower bound of the average cost per momentary interruption per customer across the three years analyzed is $68 67 ($445,698,777451,460,362 average total estimated cost / 6,635,703 total number of customers affected). This is 40% lower than the upper bound of around 1 SCE defines a momentary interruption as an interruption lasting five minutes or less. 2 Sullivan, M.J., J. Schellenberg, and M. Blundell (2015). Updated Value of Service Reliability Estimates for Electric Utility Customers in the United States. Lawrence Berkeley National Laboratory Report No. LBNL-6941E. 3 Sullivan, M.J., J. Schellenberg and others (2012). Pacific Gas & Electric Company s 2012 Value of Service Study. Filed in PG&E s General Rate Case. 4 Total number of customers affected is not shown in Table 1-1, but can be approximated by multiplying the total number of interruptions by the average number of customers affected. 124a
3 125a Customer Interruption Cost Analysis Results Year $ Although there were fewer momentary interruptions compared to sustained interruptions, each momentary interruption affected more customers on average. The Momentary Average Interruption Frequency Index (MAIFI) represents the average number of momentary interruptions a customer experiences during a year. Overall, any SCE customer can expect to experience a little over one momentary interruption per year (6,635,703 total number of customer interruptions / 5,005,487 total system customers). Total # of Momentary Interruptions Table 1-2: Customer Interruption Costs per Momentary Interruption Total # of Customer Interruptions Avg. # of Customers Affected MAIFI Total Estimated Costs (2016$) Cost per Momentary Interruption per Customer (2016$) Lower Upper ,902 5,972, $410,614,837$416,005,282 $68.8$69.7 $115.4$ ,460 6,802, $456,181,510$462,049,113 $67.1$67.9 $112.5$ ,206 7,132, $470,299,984$476,326,690 $65.9$66.8 $110.6$112.0 Average 7,523 6,635, $445,698,777$451,460,362 $67.2$68.0 $112.7$ Application of PG&E Study to Estimate Upper s In 2012, Nexant conducted a systemwide customer interruption cost survey among PG&E s residential and business customers. To assess the extent to which the LBNL meta-analysis underestimates customer interruption costs in California, Nexant conducted a comparative analysis of the 2015 LBNL study and the 2012 PG&E study. This comparative analysis found that the nationwide LBNL study underestimates interruption costs in California by about 40%. While the lower bound of the cost per CMI estimate is based on the nationwide 2015 LBNL meta-analysis, the upper bound adjusts for the 40% underestimate that was identified in the comparative analysis. The methodology is described in more detail in Section 2.3. This underestimate may be due to the higher costs of living and of doing business in California. While the nationwide 2015 LBNL meta-analysis adjusts for the varying distribution of industries, customer usage, demographics, and some other factors across states, it does not include variables that adjust for general economic drivers such as varying costs and productivity across states. Therefore, the results from the 2012 PG&E are used as a proxy for the extent to which the LBNL study underestimates customer interruption costs in California. Given that the LBNL study may not underestimate costs as much for SCE, this estimate is characterized as an upper bound. 125a
4 126a 2 Nexant analyzed historical power interruptions and customer level data to estimate the total cost of interruptions for SCE customers, cost per CMI, and cost per momentary interruption. The remainder of this section provides a brief overview of the methodology used to quantify interruption costs and summarizes the analysis that was done using that methodology in this specific application. 2.1 Estimating Customer Interruption Costs The preferred method for estimating customer interruption costs is a survey that describes several hypothetical interruption scenarios and asks customers to detail the costs that they would experience under those conditions, as described in the Electric Power Research Institute s Outage Cost Estimation Guidebook. 5 Various parties have proposed alternative approaches for estimating customer interruption costs. The strengths and weaknesses of each approach are described in a literature review for the National Association of Regulatory Utility Commissioners. 6 As discussed in that review, customer surveys are the preferred method for estimating customer interruption costs because they directly measure the costs that customers experience under a variety of interruption scenarios without relying on the relatively weak assumptions that alternative methods use. The primary drawback of surveys is that they require collecting detailed information from large, representative samples of residential, commercial, and industrial (C&I) customers. As a result, only a few of the largest utilities in the U.S. have conducted customer interruption cost surveys. To address this barrier, the Department of Energy (DOE), LBNL, and Nexant have been working together for over a decade to make reasonable interruption cost estimates readily available for utilities that have not conducted their own surveys. The first step in developing a national estimate of interruption costs was to combine results from all of the interruption cost surveys that were conducted using the methods outlined in the Outage Cost Estimation Guidebook. This aggregate statistical study, called a meta-analysis, was first done in 2003 (with results from 24 surveys) and then updated in 2009 and 2015 (with results from 34 surveys, including the original 24) Analysis of Historical Interruptions In this analysis, Nexant applied the econometric models from the 2015 meta-analysis of nationwide customer interruption costs. These models are the same equations that serve as the basis for the Interruption Cost Estimate (ICE) Calculator, which is a publicly-available, online tool that estimates customer reliability benefits associated with user-specified reliability improvements that arise from smart grid and other types of investments. 8 In this case, Nexant 5 Sullivan, M.J., and D. Keane (1995). Outage Cost Estimation Guidebook. Report no. TR Palo Alto, CA: EPRI. 6 Sullivan, M.J., and J. Schellenberg (2011). Evaluating Smart Grid Reliability Benefits For Illinois. National Association of Regulatory Utility Commissioners Report. 7 Sullivan, M.J., J. Schellenberg, and M. Blundell (2015). Updated Value of Service Reliability Estimates for Electric Utility Customers in the United States. Lawrence Berkeley National Laboratory Report No. LBNL-6941E. 8 Available here: Developed by DOE, LBNL and Nexant. 126a
5 127a did not use the ICE Calculator itself because SCE was able provide granular customer information and historical power interruption data to conduct a more robust, disaggregated analysis that fully leverages the econometric models from the 2015 meta-analysis. Nexant analyzed both sustained and momentary interruptions specifically for the past three years ( ), and linked this historical interruption information with SCE s customer database to customize the interruption cost estimates to the specific circuits that were affected by each interruption. The following outlines the main steps of the analysis: 1. Generate key model inputs using SCE s customer database; 2. Estimate interruption costs for all customers on a given circuit; 3. Combine individual customers interruption costs with the historical interruption data at the circuit level; 4. Interpolate to generate interruption costs for every historical interruption and scale each cost by the number of customers affected; and 5. Aggregate the individual costs to generate total interruption costs for all sustained and momentary interruptions for each year, Generate key model inputs Using customer level characteristics data, the econometric models produce interruption cost estimates for various scenarios for each circuit in SCE s territory. The models can estimate costs for any interruption lasting up to 960 minutes. Key inputs include customer class (residential, small C&I and medium and large C&I), usage (annual kwh 9 ), and industry type (for C&I customers only), since average interruption costs vary significantly across these factors. These inputs vary with the distribution of customers at each circuit, which is captured in the customer characteristics data. The result is estimates for interruption costs of various durations, seasons, and times of day, specific to the customer mix on each circuit. This information is combined with the database of historical interruptions to estimate total interruption costs, total CMI, and cost per CMI, and cost per momentary interruption Estimate interruption costs for individual customers and combine with historical interruption data The econometric models use the inputs generated from the customer characteristics data to estimate interruption costs for all customers on a given circuit for a fixed set of interruption scenarios. 10 The resulting dataset contains estimates for interruption costs of various durations, 11 seasons, and times of day that are specific to the customer mix on each circuit. 9 The interruption cost is assumed to be zero for customers with zero annual kwh. 10 An interruption scenario is defined by a duration, time of day the interruption occurs, and the season in which the interruption occurs. 11 Due to limitations in the underlying survey data from the meta-analysis, the econometric models cannot reliably estimate costs for interruptions longer than 16 hours (960 minutes). Therefore, interruptions longer than 960 minutes were capped at 960 minutes. 127a
6 128a Nexant received data on every interruption that occurred in SCE s service territory for the years 2013 through This database contained key attributes of each interruption, including date and time of the occurrence, interruption duration, the circuit it occurred on, the total number of customers affected, and an indicator for momentary interruptions. This information was then combined with estimates of individual customer interruption costs from the econometric models at the circuit level. The result is a cost estimate for every historical interruption on a given circuit, but for the set of interruption durations used as inputs in the econometric models Interpolate and aggregate to generate total annual costs In order to generate cost estimates for every historical interruption given the actual durations, the previous dataset is used to interpolate the missing cost estimates for all durations ranging from zero to 960 minutes. This step produces interruption cost estimates for all historical interruptions that reflect their true interruption durations. The cost estimates are then scaled by the ratio of the number of customers affected by the interruption to the total number of customers served by that circuit. This step assumes that the customer mix affected by the interruption is the same as the distribution of customers on that circuit as a whole. After the costs are scaled, each interruption is flagged as either a sustained or momentary interruption, and the costs are summed to generate aggregate interruption costs per year by interruption type. This step also aggregates the data to generate the other interruption metrics shown in Tables Table 1-1 andtable 1-2 (e.g., total number of interruptions, total CMI, and overall MAIFI). 2.3 Application of PG&E Study to Estimate Upper s The 2015 meta-analysis is based on data that mostly includes utilities from areas of the country that are known to have lower costs of living and of doing business than in California. Therefore, the customer interruption costs based on this meta-analysis are characterized as a lower bound. To assess the extent to which the LBNL meta-analysis underestimates customer interruption costs in California, Nexant conducted a comparative analysis of the 2015 meta-analysis and the 2012 PG&E systemwide customer interruption cost study. As in the analysis described in Section 2.1, Nexant estimated interruption costs for PG&E customers using the 2015 metaanalysis. Nexant then compared those results to the average customer interruption costs from the 2012 PG&E survey for a 4-hour interruption on a summer weekday afternoon. 13 Table 2-1 summarizes the results of this comparative analysis by customer class. The estimated interruption costs from the 2015 meta-analysis are nearly 45% lower than the PG&E survey results for residential customers, around 39% lower for small/medium businesses and nearly 57% lower for large businesses. Overall, the population-weighted average cost for this interruption scenario is $743 per PG&E customer based on the survey. The meta-analysis produces a population-weighted average cost estimate that is 40.4% lower, at $443. The upper 12 To avoid double counting, Nexant removed the July 15, 2015 Chestnut outage record from the analysis, given that those customer interruption minutes were distributed to other records in the dataset. 13 This power interruption scenario is used in the comparative analysis because it is the scenario that is most common across both studies. 128a
7 129a bound estimates of cost per CMI and the cost per momentary interruption in Tables 1-1 and 1-2 were adjusted for this underestimate. Given that the LBNL study may not underestimate costs as much for SCE as it does for PG&E in this comparative analysis, these estimates are characterized as an upper bound. Table 2-1: Comparison of 2012 PG&E Survey Results and Estimated Customer Interruption Costs from 2015 Meta-Analysis (4-hour Interruption on a Summer Weekday Afternoon) Customer Class PG&E Population Average Interruption Cost from PG&E Survey Estimated Interruption Cost from 2015 Metaanalysis % Underestimated Residential 4,196,099 $14.70 $ % Small/Medium Business 360,850 $8,700 $5, % Large Business 1,225 $152,914 $65, % Overall 4,558,174 $743 $ % 129a
Circuit Reliability Review
Circuit Reliability Review Carpinteria January 2018 Building a Smarter Grid for Southern California Southern California Edison is developing an electric grid to support California s transition to a clean
More informationCircuit Reliability Review
Circuit Reliability Review Goleta January 2018 Building a Smarter Grid for Southern California Southern California Edison is developing an electric grid to support California s transition to a clean and
More informationCircuit Reliability Review
Circuit Reliability Review Malibu January 2018 Building a Smarter Grid for Southern California Southern California Edison is developing an electric grid to support California s transition to a clean and
More informationCircuit Reliability Review
Circuit Reliability Review Tehachapi January 2018 Building a Smarter Grid for Southern California Southern California Edison is developing an electric grid to support California s transition to a clean
More informationCircuit Reliability Review
Circuit Reliability Review Camarillo January 2018 Building a Smarter Grid for Southern California Southern California Edison is developing an electric grid to support California s transition to a clean
More informationCircuit Reliability Review
Circuit Reliability Review Ojai January 2018 Building a Smarter Grid for Southern California Southern California Edison is developing an electric grid to support California s transition to a clean and
More informationCircuit Reliability Review
Circuit Reliability Review Fillmore January 2018 Building a Smarter Grid for Southern California Southern California Edison is developing an electric grid to support California s transition to a clean
More informationCircuit Reliability Review
Circuit Reliability Review Mammoth Lakes January 2018 Building a Smarter Grid for Southern California Southern California Edison is developing an electric grid to support California s transition to a clean
More informationCircuit Reliability Review
Circuit Reliability Review Claremont January 2018 Building a Smarter Grid for Southern California Southern California Edison is developing an electric grid to support California s transition to a clean
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 62914-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 60975-E RATES Schedule TOU-BIP Sheet 5 Excess Energy Charges: For both
More informationCircuit Reliability Review
Circuit Reliability Review Kings District 5 January 2018 Building a Smarter Grid for Southern California Southern California Edison is developing an electric grid to support California s transition to
More informationCircuit Reliability Review
Circuit Reliability Review Hanford January 2018 Building a Smarter Grid for Southern California Southern California Edison is developing an electric grid to support California s transition to a clean and
More informationFeburary 28, 2006 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION
Akbar Jazayeri Director of Revenue and Tariffs Feburary 28, 2006 ADVICE 1972-E PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Employee Safety and Distribution Reliability
More informationNews from the Oklahoma Corporation Commission Matt Skinner, Public Information Phone: (405) , FAX: (405)
News from the Oklahoma Corporation Commission Matt Skinner, Public Information Phone: (405) 521-4180, FAX: (405) 521-6945 m.skinner@occemail.com April 28, 2006 KEEPING THE LIGHTS ON New Commission reliability
More informationReview and Validation of 2014 Southern California Edison Home Energy Reports Program Impacts (Final Report)
Review and Validation of 2014 Southern California Edison Home Energy Reports Program Impacts (Final Report) California Public Utilities Commission Date: 04/01/2016 CALMAC Study ID LEGAL NOTICE This report
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 61411-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 53858-E Schedule TOU-BIP Sheet 1 APPLICABILITY This Schedule is optional
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 64436-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 63592-E Sheet 1 OPTIONAL BINDING MANDATORY CURTAILMENT AGREEMENT BETWEEN
More informationLoad and Billing Impact Findings from California Residential Opt-in TOU Pilots
Load and Billing Impact Findings from California Residential Opt-in TOU Pilots Stephen George, Eric Bell, Aimee Savage, Nexant, San Francisco, CA ABSTRACT Three large investor owned utilities (IOUs) launched
More informationPhase III Statewide Evaluation Team. Addendum to Act 129 Home Energy Report Persistence Study
Phase III Statewide Evaluation Team Addendum to Act 129 Home Energy Report Persistence Study Prepared by: Adriana Ciccone and Jesse Smith Phase III Statewide Evaluation Team November 2018 TABLE OF CONTENTS
More informationCALIFORNIA ISO BASELINE ACCURACY ASSESSMENT. Principal authors. November 20, Josh Bode Adriana Ciccone
CALIFORNIA ISO BASELINE ACCURACY ASSESSMENT November 20, 2017 Principal authors Josh Bode Adriana Ciccone 1 Introduction...4 1.1 Key Research Questions... 5 1.2 Aggregated versus Customer Specific Baselines...
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 53895-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 50436-E Schedule SLRP Sheet 1 APPLICABILITY This Schedule is optional
More informationActual neighborhood of Sunrun customer homes
This presentation contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. Forward-looking statements
More information2016 Statewide Retrocommissioning Policy & Procedures Manual
2016 Statewide Retrocommissioning Policy & Procedures Manual Version 1.0 Effective Date: July 19, 2016 Utility Administrators: Pacific Gas and Electric San Diego Gas & Electric Southern California Edison
More informationTAC FIX IMPACT MODEL DETAILED OVERVIEW
TAC FIX IMPACT MODEL DETAILED OVERVIEW Contents Goal of Spreadsheet... 2 Drivers of transmission investment... 2 Note About Terminology... 3 Core Assumptions... 3 Load served locally for an example IOU,
More informationThe Total Resource Cost of Saved Energy for Utility Customer-Funded Energy Efficiency Programs
The work described in this presentation was funded by the National Electricity Delivery Division of the U.S. Department of Energy s Office of Electricity Delivery and Energy Reliability and the Office
More informationCommunity-Solar Utility Programs
Community-Solar Utility Programs Andrea Romano, CSVP Team Consultant Navigant Consulting November 2015 Community Solar Value Project interviewed five program managers at utilities across the United States
More informationFinancing or Incentives: Disentangling Attribution
Financing or Incentives: Disentangling Attribution Antje S. Flanders, Opinion Dynamics Corporation, Waltham, MA ABSTRACT Financing programs are getting more and more attention as program administrators
More informationElectric Rate Schedule GS-2 General Service - Demand
Page 1 of 5 Applicability This Schedule is applicable to general commercial customers having demands in excess of 20 kilowatts and less than 1,000 kilowatts, and public units for residential occupancy.
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 61411-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 53858-E Schedule TOU-BIP Sheet 1 APPLICABILITY This Schedule is optional
More informationDynamic Pricing Proposals of Southern California Edison Company in Compliance with D
Application No.: Exhibit No.: Witnesses: A.-0- SCE-01 Russ Garwacki Robert Thomas Lisa Vellanoweth (U -E) Dynamic Pricing Proposals of Southern California Edison Company in Compliance with D.0-0-0 Before
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 59484-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 52461-E RATES (continued) Schedule RES-BCT Sheet 2 All costs associated
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) )
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking Regarding Policies, Procedures and Rules for Development of Distribution Resources Plans Pursuant to Public
More informationPrepared Remarks of Edison International CEO and CFO First Quarter 2017 Financial Teleconference May 1, 2017, 1:30 p.m. (PDT)
Prepared Remarks of Edison International CEO and CFO First Quarter 2017 Financial Teleconference May 1, 2017, 1:30 p.m. (PDT) Pedro Pizarro, President and Chief Executive Officer, Edison International
More informationApplication No.: A Exhibit No.: SCE-1, Vol. 3. S. DiBernardo S. Samiullah D. Hopper G. Golden (U 338-E) Before the
Application No.: A.1-01- Exhibit No.: SCE-1, Vol. Witnesses: R. Thomas S. DiBernardo S. Samiullah D. Hopper G. Golden (U -E) SOUTHERN CALIFORNIA EDISON COMPANY S (U - E) TESTIMONY IN SUPPORT OF ITS APPLICATION
More informationSAFETY MODEL ASSESSMENT
Application No.: Exhibit No.: Witnesses: A.1-0- SCE-01 M. Marelli S. Menon N. Woodward (U -E) SAFETY MODEL ASSESSMENT Before the Public Utilities Commission of the State of California Rosemead, California
More informationAdvice 4991-E-C Issued by Date Filed July 23, 2018 Decision Robert S. Kenney Effective July 23, 2018 Vice President, Regulatory Affairs Resolution
Revised Cal. P.U.C. Sheet No. 42644-E Cancelling Revised Cal. P.U.C. Sheet No. 40233-E ELECTRC SCHEDULE E-BP Sheet 1 BASE NTERRUPTBLE PROGRAM APPLCABLTY: This rate schedule is available until modified
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 54897-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 53225-E Schedule CBP Sheet 1 APPLICABILITY The Capacity Bidding Program
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 34721-E Rosemead, California Cancelling Revised Cal. PUC Sheet No. 34487-E* 31479-E Schedule D-APS-E Sheet 1 APPLICABILITY Applicable to domestic service
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 59107-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 57595-E Schedule TOU-GS-3 Sheet 1 APPLICABILITY Applicable to single-
More informationHome Energy Reporting Program Evaluation Report. June 8, 2015
Home Energy Reporting Program Evaluation Report (1/1/2014 12/31/2014) Final Presented to Potomac Edison June 8, 2015 Prepared by: Kathleen Ward Dana Max Bill Provencher Brent Barkett Navigant Consulting
More informationAPPENDIX A - GLOSSARY
APPENDIX A - GLOSSARY 1. Photovoltaic (PV) or Solar (interchangeable): These are devices that generate electricity directly from sunlight via an electronic process that occurs naturally in certain types
More information2018 General Rate Case
Application No.: A.16-09- Exhibit No.: SCE-0, Vol. 08 Witnesses: J. R. Goizueta M. Flores A (U 338-E) 018 General Rate Case Transmission & Distribution (T&D) Volume 8 - Infrastructure Replacement Before
More informationApril 9, ADVICE 2099-E (Pacific Gas and Electric Company ID U 39 E) Public Utilities Commission of the State of California
April 9, 2001 ADVICE 2099-E (Pacific Gas and Electric Company ID U 39 E) Public Utilities Commission of the State of California Subject: Electric Interruptible Load Programs Pacific Gas and Electric Company
More informationIMPACT AND PROCESS EVALUATION OF AMEREN ILLINOIS COMPANY BEHAVIORAL MODIFICATION PROGRAM (PY5) FINAL OPINION DYNAMICS. Prepared for: Prepared by:
IMPACT AND PROCESS EVALUATION OF AMEREN ILLINOIS COMPANY S BEHAVIORAL MODIFICATION PROGRAM (PY5) FINAL Prepared for: AMEREN ILLINOIS COMPANY Prepared by: OPINION DYNAMICS 1999 Harrison Street Suite 1420
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 62425-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 57044-E Schedule DBP Sheet 1 APPLICABILITY This Schedule is optional for
More informationELECTRIC SCHEDULE E-OBMC Sheet 1 OPTIONAL BINDING MANDATORY CURTAILMENT PLAN
Revised Cal. P.U.C. Sheet No. 37149-E Cancelling Revised Cal. P.U.C. Sheet No. 29519-E ELECTRC SCHEDULE E-OBMC Sheet 1 APPLCABLTY: An Optional Binding Mandatory Curtailment (OBMC) Plan may be an alternative
More informationFrequently Asked Questions
Frequently Asked Questions Q: What is PBI? A: The Performance Based Incentive, or PBI, is one of two types of incentives offered by the California Solar Initiative (CSI) incentive program. PBI customers
More informationHearing on Temporary Rates. EXHIBIT A Page 1 of 48
Hearing on Temporary Rates October 25, 2011 EXHIBIT A Page 1 of 48 Page 2 of 48 EPE Overview Serving El Paso for over 110 years 1 of 3 publicly l traded d companies in El Paso Over 950 employees Significant
More informationIncreasing Variability in SAIDI and Implications for Identifying Major Events Days
Increasing Variability in SAIDI and Implications for Identifying Major Events Days IEEE Power & Energy Society General Meeting 2014 July 30, 2014 National Harbor, MD Joseph H. Eto Kristina H. LaCommare
More information2018 General Rate Case. Transmission & Distribution (T&D) Volume 3 R System Planning
Application No.: Exhibit No.: Witnesses: A.1-0- A SCE-0, Vol. 0 R A E. Takayesu (U -E) 01 General Rate Case rd Errata ERRATA Transmission & Distribution (T&D) Volume R System Planning Before the Public
More informationSummary of Ratepayer-Funded Electric Efficiency Impacts, Budgets, and Expenditures
Summary of Ratepayer-Funded Electric Efficiency Impacts, Budgets, and Expenditures IEE Brief January 2012 Summary of Ratepayer-Funded Electric Efficiency Impacts, Budgets and Expenditures (2010-2011)
More informationThe Utility Business Model and Energy Efficiency
The Utility Business Model and Energy Efficiency i Arkansas Sustainable Energy Resources Docket July 15, 2009 Richard Sedano The Regulatory Assistance Project 50 State Street, Suite 3 Montpelier, Vermont
More informationBetter Buildings Neighborhood Program: An Economic Impact Analysis of a Whole-Building Retrofit Program
Better Buildings Neighborhood Program: An Economic Impact Analysis of a Whole-Building Retrofit Program Matthew Koson, Evergreen Economics, Portland, OR Stephen Grover, Evergreen Economics, Portland, OR
More informationPG&E Corporation. Fourth Quarter Earnings Call February 21, 2013
1 PG&E Corporation Fourth Quarter Earnings Call February 21, 2013 This presentation is not complete without the accompanying statements made by management during the webcast conference call held on February
More informationIllinois Grid Mod by Formula Rate & Next Grid
Illinois Grid Mod by Formula Rate & Next Grid Ann McCabe, Consultant, Illinois Commissioner 2012-2017 Customer Vision Stakeholder Group, July 23, 2018 Introduction Each state is different. Statutes/legislation
More informationPERFORMANCE BASED FORMULA RATES IN ILLINOIS
PERFORMANCE BASED FORMULA RATES IN ILLINOIS Mid-Atlantic Distributed Resources Initiative Working Group Meeting # 47 Exploration of Emerging Revenue Recovery Models October 10, 2017 Trenton, New Jersey
More informationCRR Auction Analysis Report
Report November 21, 2017 Prepared by: MQRI California Independent System Operator The following ISO staff contributed to this report: Danielle Tavel Abhishek Hundiwale Jie Duan Nongchao Guo Jim McClain
More informationActive Demand Reduction Cost-Effectiveness Considerations. PA Presentation for EEAC November 15, 2017
Active Demand Reduction Cost-Effectiveness Considerations PA Presentation for EEAC November 15, 2017 On the hunt for benefits Current Benefits Claimed DPU 11-120-A, Phase II January 31, 2013 3.4.3.3 Program
More informationFinancial Implications of using Energy Efficiency to contribute towards meeting a Federal RES: Case Study of Kansas
Financial Implications of using Energy Efficiency to contribute towards meeting a Federal RES: Case Study of Kansas Peter Cappers Charles Goldman Lawrence Berkeley National Laboratory ACE 5 th National
More informationCASE 17-M-0178 Draft Discussion Document, November 2017 Session, Publicly Released November 15, 2017 STATE OF NEW YORK PUBLIC SERVICE COMMISSION
STATE OF NEW YORK PUBLIC SERVICE COMMISSION At a session of the Public Service Commission held in the City of COMMISSIONERS PRESENT: CASE 17-M-0178 - Petition of Orange and Rockland Utilities, Inc. for
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA. And Related Matters. Application Application
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of San Diego Gas & Electric Company (U902E) for Authority to Implement Optional Pilot Program to Increase Customer Access to
More informationAPPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST
Seventh Northwest Conservation and Electric Power Plan APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Contents Introduction... 3 Key Findings... 3 Background... 5 Methodology... 7 Inputs and Assumptions...
More informationECONorthwest. Introduction. Data sources and methods
ECONorthwest DATE: April 28, 2014 TO: FROM: Board of Directors, Lane Transit District Andrew Dyke, Senior Economist SUBJECT: RECENT ECONOMIC PERFORMANCE OF THE EUGENE-SPRINGFIELD METROPOLITAN STATISTICAL
More information2015 Load Impact Evaluation of Pacific Gas and Electric Company s Residential Time-Based Pricing Programs: Ex-Post and Ex-Ante Report.
2015 Evaluation of Pacific Gas and Electric Company s Residential Time-Based Pricing Programs: Ex-Post and Ex-Ante Report Public Version CALMAC Study ID PGE0371 Steven D. Braithwait Daniel G. Hansen David
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Request for Modifications to SCE s Renewable Auction Mechanism ( RAM ) Program Pursuant to Decision 10-12-048 Rulemaking 11-05-005 (Filed
More informationActive Transportation Health and Economic Impact Study
Active Transportation Health and Economic Impact Study November 7, 2016 Please recycle this material. SCAG 2789.2017.02.22 Contract No. 15-019-C1 Active Transportation Health and Economic Impact Study
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 59483-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 51843-E APPLICABILITY Schedule RES-BCT Sheet 1 This Schedule is optional
More informationWHAT S THE VALUE OF LIFE?
WHAT S THE VALUE OF LIFE? AUGUST 15, 2018 KAREN MAOZ ROBERT NEUMANN NAVIGANT CONSULTING, INC. 0 / 2017 NAVIGANT CONSULTING, INC. ALL RIGHTS RESERVED EFFECTIVE USEFUL LIFE DEFINITION Effective Useful Life
More informationOntario Energy Board
Ontario Energy Board Commission de l énergie de l Ontario Ontario Energy Board Filing Requirements For Electricity Transmission Applications Chapter 2 Revenue Requirement Applications February 11, 2016
More informationCalifornia Net Energy Metering Ratepayer Impacts Evaluation
California Net Energy Metering Ratepayer Impacts Evaluation October 2013 Introduction to the California Net Energy Metering Ratepayer Impacts Evaluation Prepared by California Public Utilities Commission
More informationEconomic Development Rate-Expansion Agreement. Form
Southern California Edison Revised Cal. PUC Sheet No. 62204-E Rosemead, California (U 338-E) Cancelling Original Cal. PUC Sheet No. 56652-E Sheet 1 Economic Development Rate-Expansion Agreement (To be
More information40 th Annual EEI Finance Conference
40 th Annual EEI Finance Conference Hollywood, FL November 6-8, 2005 Forward-Looking Statements Disclosure The following presentation contains some forward-looking statements with respect to Westar Energy
More informationDRAFT. California ISO Baseline Accuracy Work Group Proposal
DRAFT California ISO Baseline Accuracy Work Group Proposal April 4, 2017 1 Introduction...4 1.1 Traditional baselines methodologies for current demand response resources... 4 1.2 Control Groups... 5 1.3
More information2018 General Rate Case
Application No.: Exhibit No.: Witnesses: A.1-0-001 SCE-TURN-01 S. Menon (SCE) W. Marcus (TURN) (U -E) 01 General Rate Case SCE-TURN Joint Supplemental Testimony Regarding SPIDA Software Disallowance Scenarios
More informationExhibit Table 1: PG&E Corporation Business Priorities
Exhibit 99.2 Table 1: PG&E Corporation Business Priorities 2006-2010 1. Advance business transformation 2. Provide attractive shareholder returns 3. Increase investment in utility infrastructure 4. Implement
More informationSouthern California Edison Original Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Cal. PUC Sheet No.
Southern California Edison Original Cal. PUC Sheet No. 56653-E Rosemead, California (U 338-E) Cancelling Cal. PUC Sheet No. Sheet 1 Economic Development Rate-Retention Agreement Form No. 14-960 (To be
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 66505-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 65449-E Schedule LS-3 Sheet 1 APPLICABILITY Applicable to metered service
More information2013 Custom Impact Evaluation Industrial, Agricultural, and Large Commercial
Final Report 2013 Custom Impact Evaluation Industrial, Agricultural, and Large Commercial Submitted to: California Public Utilities Commission 505 Van Ness Avenue San Francisco, CA 94102 Submitted by:
More informationResidential Rate OIR Rate Design and Bill Impact Analysis Model
Residential Rate OIR Rate Design and Bill Impact Analysis Model Table of Contents Table of Contents... 1 Overview... 3 Embedded Help Function... 3 Using the Model... 4 Description of Inputs and Running
More informationA Bottom-Up Approach to Sustained Curtailment and Comfort for Controlled Demand Response
A Bottom-Up Approach to Sustained Curtailment and Comfort for Controlled Demand Response Marc Frincu and Zachary Gima Dept. of Electrical Engineering University of Southern California http://ganges.usc.edu/wiki/smart_grid
More informationHelium Gas Turbine Reactor Technical Challenges:
Helium Gas Turbine Reactor Technical Challenges: A Characterization for Use in Focusing R&D Resources TP-114690 WARNING: Please read the Export Control Agreement on the back cover. Effective October 22,
More informationPG&E Corporation. Second Quarter Earnings Call. July 31, 2013
PG&E Corporation Second Quarter Earnings Call July 31, 2013 This presentation is not complete without the accompanying statements made by management during the webcast conference call held on July 31,
More informationImpact Evaluation of 2014 San Diego Gas & Electric Home Energy Reports Program (Final Report)
Impact Evaluation of 2014 San Diego Gas & Electric Home Energy Reports Program (Final Report) California Public Utilities Commission Date: 04/01/2016 CALMAC Study ID LEGAL NOTICE This report was prepared
More informationSouthern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.
Southern California Edison Revised Cal. PUC Sheet No. 62812-E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No. 62650-E Schedule TOU-D-T Sheet 1 APPLICABILITY Applicable as an option
More information1. Advance business transformation. 2. Provide attractive shareholder returns. 3. Increase investment in utility infrastructure
Table 1: PG&E Corporation Business Priorities 2006-2010 1. Advance business transformation 2. Provide attractive shareholder returns 3. Increase investment in utility infrastructure 4. Implement an effective
More informationCHAPTER II NEW CURTAILMENT ORDER PREPARED DIRECT TESTIMONY OF STEVE WATSON BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA
Application No: Exhibit No.: Witness: A.1-0- Steve Watson Application of Southern California Gas Company (U 0 G) and San Diego Gas & Electric Company (U 0 G) for Authority to Revise their Curtailment Procedures
More informationF I L E D :59 PM
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA F I L E D 05-29-13 04:59 PM Order Instituting Rulemaking on the Commission s Own Motion to Conduct a Comprehensive Examination of Investor
More informationAttachment C. Bickmore. Self- Insured Workers' Compensation Program Feasibility Study
Attachment C Bickmore Wednesday, May 21, 2014 Mr. David Wilson City of West Hollywood 8300 Santa Monica Blvd. West Hollywood, CA 90069 Re: Self- Insured Workers' Compensation Program Feasibility Study
More informationPG&E Corporation. First Quarter Earnings Call. May 2, 2013.
PG&E Corporation First Quarter Earnings Call May 2, 2013 This presentation is not complete without the accompanying statements made by management during the webcast conference call held on May 2, 2013.
More informationEstimate of a Work and Save Plan in Georgia
1 JUNE 6, 2017 Estimate of a Work and Save Plan in Georgia Wesley Jones Sally Wallace 2 Introduction AARP Georgia commissioned the Center for State and Local Finance at Georgia State University to estimate
More informationJanuary 22, Establishment of Smart Energy Program and Modification of Summer Discount Plan in Compliance with Decision
Russell G. Worden Managing Director, State Regulatory Operations January 22, 2018 ADVICE 3731-E (U 338-E) PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ENERGY DIVISION SUBJECT: Establishment of
More informationCost Estimates for Alternative Tax Exemptions for Some HDFC Coops
MEMORANDUM Date: December 3, 2015 To: From: Subject: George Sweeting Geoffrey Propheter Cost Estimates for Alternative Tax Exemptions for Some HDFC Coops Introduction The Task Force on City-Owned Property
More information$15 Minimum Wage. November 15, 2016 Item 3.4. City of San José
$15 Minimum Wage November 15, 2016 Item 3.4 City of San José Context March 2013 Local minimum wage raised from $8 to $10 (Measure D) Adopted by San Jose voters on November 6, 2012 Will increase to $10.40
More information2017 Annual Electric Reliability Investment Initiative Report
BEFORE THE PUBLIC SERVICE COMMISSION OF MARYLAND IN THE MATTER OF THE APPLICATION OF ) BALTIMORE GAS AND ELECTRIC COMPANY ) CASE NO. 9326 FOR ADJUSTMENTS TO ITS ELECTRIC ) AND GAS BASE RATES ) 2017 Annual
More informationF.N.B. Corporation & First National Bank of Pennsylvania Capital Stress Test Results Disclosure
F.N.B. Corporation & First National Bank of Pennsylvania Capital Stress Test Results Disclosure Capital Stress Testing Results Covering the Time Period January 1, 2016 through March 31, 2018 for F.N.B.
More informationAkbar Jazayeri Vice President, Regulatory Operations Southern California Edison Company P O Box 800 Rosemead, CA 91770
STATE OF CALIFORNIA PUBLIC UTILITIES COMMISSION SAN FRANCISCO, CA 94102-3298 Edmund G. Brown Jr. Governor May 31, 2011 Advice Letter 2550-E Akbar Jazayeri Vice President, Regulatory Operations Southern
More informationImpact Evaluation of 2015 Marin Clean Energy Home Utility Report Program (Final Report)
Impact Evaluation of 2015 Marin Clean Energy Home Utility Report Program (Final Report) California Public Utilities Commission Date: 05/05/2017 CALMAC Study ID: CPU0158.01 LEGAL NOTICE This report was
More informationHistorical Performance of the U.S. ESCO Industry: Results from the NAESCO Project Database
LBNL-46070 Historical Performance of the U.S. ESCO Industry: Results from the NAESCO Project Database C.A. Goldman, P. Juergens, M. Fowlie, J. Osborn & K. Kawamoto,LBNL, Terry Singer, NAESCO Environmental
More informationToben Galvin, Laura Agapay, Randy Gunn Navigant Consulting; Walter Poor, Vermont Department of Public Service. Abstract
Benchmarking Utility DSM Delivery Performance: Results from a Comparative Review of Efficiency Vermont's 2008 Program Delivery Costs and Energy Abstract Toben Galvin, Laura Agapay, Randy Gunn Navigant
More informationFIVE YEAR PLAN FOR ENERGY EFFICIENCY
FIVE YEAR PLAN FOR ENERGY EFFICIENCY Executive Summary Prepared for: Holy Cross Energy Navigant Consulting, Inc. 1375 Walnut Street Suite 200 Boulder, CO 80302 303.728.2500 www.navigant.com July 15, 2011
More information