Possible Financing Schemes for Current and Near Term Nuclear Power Projects
|
|
- Camron Anderson
- 6 years ago
- Views:
Transcription
1 Possible Financing Schemes for Current and Near Term Nuclear Power Projects Workshop on Technology Assessment of Small and Medium-sized Reactors for Near Term Deployment Headquarters, Vienna, Austria, 8 December 2011 Nadira Barkatullah Department of Nuclear Energy, Planning and Economic Studies Section International Atomic Energy Agency
2 Key Media News on Nuclear Economics Nuclear Costs to Rise Following Fukushima Disaster (Energy Business Daily, April 25th, 2011) Economics, not public sentiment drives nuclear financing (Nucleonics Week 23 June 2011) The economics of nuclear power may deteriorate in comparison with other generating technologies in the wake of the Fukushima accident (OECD International Energy Agency, 2011 World Energy Outlook) Eurozone: Sovereign Debt Becomes a Credit Crunch (Forbes 25 November, 2011) U.A.E. s Nuclear Power Program said to cost $30 Billion (Bloomberg Business week, 28 November, 2011) Concerns Persist Over Economic Impact of Bank Liquidity Contagion Risks in Europe (S&P Capital IQ Lookout Report, December 2011) 2
3 GWe Nuclear Power Current Status On 6 December 2011, 434 nuclear power plants (NPPs) operated in 30 countries worldwide, with a total installed capacity of 368 GWe NPPs under construction
4 Overview What is Special in Financing of Nuclear Power Projects Sources and Types of Financing Existing and Emerging Financing Schemes and possible trend Contractual and Ownership Arrangements Concluding Comments 4
5 What is Special in Financing of NPP Projects The Economics of Nuclear Key Advantages of the Nuclear Power Relatively low fuel cost: economic competiveness Price stability Current fleet performance of nuclear reactors Long life time Guarantee for energy supply Clean source of energy Economic development: job creation and contribution to national high technologies sector Key Challenges to the Nuclear Power Complex and highly capital intensive: high upfront capital costs, which are difficult to finance Sensitive to interest rates Long lead times (planning, construction, etc) Long payback periods Construction cost uncertainty and completion risk Regulatory/policy risks (revised safety measures) New financing structures required to attract private investors 5 5
6 What is Special in Financing of NPP Projects Key Challenges to the Nuclear Power The Economics of Nuclear Complex and highly capital intensive: high upfront capital costs Sensitive to interest rates Long lead times (planning, construction, etc) and Long payback periods Might be less challenging for SMRs Completion risk Cost uncertainty Other Financial Risks Regulatory/policy risks (revised safety measures) New financing structures required to attract private investors Challenging for all types of reactors - SMRs and Large Reactors (LR) 6 6
7 NPPs overnight capital cost uncertainty Source: OECD: Current Status, Technical Feasibility and Economics of Small Medium Reactors. June
8 NPPs overnight capital cost uncertainty Economies of scale challenge Source: OECD: Current Status, technical Feasibility and Economics of Small Medium Reactors, June
9 Overnight costs ($/kw) NPPs overnight capital cost uncertainty For SMR the cost might be lower (less than billion) but $/kwe might be the same or higher North America Europe Asia : Data collected from various publications and studies to keep track of nuclear power plants investment costs, since 2008 (updated Nov 2011) All data in 2008 USD 9
10 Construction Duration Construction and IDC Construction duration of SMR could be shorter compared to LR resulting in lower IDC % of overnight capital cost Interest Share (5%) Interest Share (10%) Modular reactors may reduce risk associated with construction
11 Business risk Main Financial Risks So what are the main financial risks associated with an investment? Sales or Revenue risk Operating risk Financial risks Credit risk (sovereign and corporate) Market risk (currency, fixed-income, equity and commodities)
12 Default Speculative Grade Investment Grade Major Financial risks: Credit Risk Fitch Standard & Poors Moody's AAA AAA Aaa AA+ AA+ Aa1 AA AA Aa2 AA- AA- Aa3 A+ A+ A1 A A A2 A- A- A3 BBB+ BBB+ Baa1 BBB BBB Baa2 BBB- BBB- Baa3 BB+ BB+ Ba1 BB BB Ba2 BB- BB- Ba3 B+ B+ B1 B B B2 B- B- B3 CCC+ Caa1 CCC CCC Caa2 CCC- Caa3 CC CC Ca C C C D D C Easier to borrow: lower interest rate Tough to borrow: higher interest rates
13 Foreign exchange risk What is foreign exchange rate risk? The risk of an investment's value changing due to adverse movement in the currency exchange rates Import NPP equipment value 1.5m MXN at USD/MXN=15 Financial crisis Import NPP equipment value 1m MXN at USD/MXN=10 Source: Yahoo Finance December 2011
14 Major Financial risks: Market risks Commodity prices: Power Plant Construction Cost Index (PCCI) Power plant construction cost pressure returning (July 2011) Oct 2008 Financial Crisis Metals Index Industrial Input Average Petroleum Spot Index Source: IMF (April 2011)
15 Factors that Influence Financing NPPs Enhancement of safety and impact on investment cost Increased regulatory risk and uncertainty in the regulatory process Negative public perception of nuclear Multinational Banks policy on credit availability Construction Supply Chain risks Deregulated electricity market rules and regulation Operational performance risk Nuclear liability and insurance on how to cap and allocate the extraordinary nuclear occurrences Management of spent fuel and waste, and decommissioning 15
16 What is appropriate financing model Financing and cost of finance What are the sources and types of finance? What are the different financing models employed in the nuclear industry?
17 Financing So what is Financing? Providing necessary capital through issuance and sale of debt and/or equity Debt Financing Equity Financing Local banks international financial institutions export credit agencies Suppliers Local and foreign investors Shareholder Capital markets: like IPO international development organizations Capital markets Cost of debt: Interest paid Cost of capital: return on capital
18 Financing: Cost of finance In simple case weighted average cost of capital (WACC) is:* WACC = Debt Debt +Equity Rd + Equity Debt +Equity Re Where: Rd is the cost of debt Re is the cost of equity Generally, for nuclear the cost of finance is higher with risk premium of x% above other power generation assets added to the interest rate * Without any tax adjustment
19 Types of Financing Government State Budget (like, tax revenue) Equity ownership Government incentives (like, loan guarantee, construction delay insurance, guaranteed long term power purchases agreements) Export credit Long-term Infrastructure bonds issuance 19
20 Government Financing Traditional Government financing: take all risks and costs Utilities (Generators) borrow on balance sheet Who finally pays for all the costs? Essentially 100% risk on the customer: All costs: construction and operations passed on to the customer!
21 Government Financing Traditional Methods of Financing Multilaterals Government Budget Official Borrowing Commercial Banks Export Credit Agency Public Utility Nuclear Power Project 21
22 Nuclear: Traditional Financing Model Export Credit Agency (trade finance): Provides financing services such as guarantees, loans and insurance to domestic companies for their activities in order to promote exports in the domestic country: ECA Credit Insurance Commercial Banks Credit Repayment Customer How does it works? Foreign Buyer Exporter Payment on Delivery Letter of Undertaking Lending Bank Cover ECA
23 Types of Financing Governments seeks private sector participation Industry financing Corporate finance or balance sheet finance Project Finance (non or limited recourse): Long term finance based on the projected cash flow of the project (In nuclear pure project finance is still not applied but some combination of corporate finance and project finance hybrid finance Co-operative finance or hybrid financing Innovative financing methods 23
24 Industry Financing Corporate finance or balance sheet finance: borrowing or raising equity against the assets of the company as a whole. A bank or bond holder which provides funds to the company has a claim against the company s whole cashflows, unless the loan is secured against a particular asset, as is common for mortgages. Risk of that investment is borne by all providers of capital to that company Example EDF, Enel, RWE, E.On GDF SUEZ.. Applicable for SMR 24 24
25 Industry Financing: New trends emerging Co-operative model or hybrid financing :Olkiluoto 3 or Finnish Model: Expanding equity partners to diversity risk Debt Financing 75% TVO 25% Equity Debt holders: Market rate Shareholders: Equity injection shareholder loan no dividends 6 Shareholders Power use in own operation Other power off-takers (about 60) Power use in own operation External Market Characteristics of hybrid financing (corporate/project finance): The project financed on the balance sheet of TVO (Finland Private Power Company) Part of equity and loan is provided by the large customers A long-term PPA with large customers ensuring future stable revenue stream from the project Leverage characteristics similar to project finance Export credit guarantee by the French and Swedish Government
26 Industry Financing: New trends emerging Project Finance: Some trend emerging as new partnerships are formed to diversity risk 26
27 Industry Financing: New trends emerging Equity Investment by vendors: the new market trend? the extend of investment will depend on the structure of project Partnerships: Partnership between Babcock & Wilcox and Bechtel - has signed a letter of intent with the Tennessee Valley Authority (TVA) which defines the project plans for constructing up to six small modular reactors 27
28 Risk transferability from public to private Financing trends emerging Combination of models emerging and likely to be widely used Project Finance Combination of models proposed and already in use Co-operative Models Combination of models widely used Corporate Finance Government Financing Ownership transferability from public to private
29 Contractual Arrangements Basically there are the following main types of contractual approach that have been applied for NPP projects: Turnkey contract: a single contractor or a consortium of contractors takes the technical responsibility for the whole NPP project. Split-package: the overall responsibility is divided between a relatively small number of contractors, each building a large section of the work. Multi-contract: the owner or its architect-engineer assumes overall responsibility for engineering and managing the NPP project, issuing a large number of contracts. 29
30 Ownership and Contractual Arrangements Public Private Partnership Options Broad Category Main variants Ownership of capital assets Responsibility of investments Assumption of risk Duration of contract (years) Supply and Management Contracts Operational/ Maintenance Management Public Public (O) Public/Private (M) Public (O) Public/Private (M) 1-5 Lease Lease Public Public Public/Private 3-20 Concession** BOT* Public/Private Public/Private Public/Private Private Ownership of Assets BOO Private Private Private Indefinite Build-Operate-Transfer (BOT) has many other variants such as Build-Transfer-operate (BTO), Build-Own-Operate-Transfer (BOOT) and Build-Rehabilitate-Operate-Transfer (BROT). **Franchise contracts are also a type of concession arrangements with 3-7 years of durations.
31 Type Ownership and Contractual Arrangements Built Own Operate and Transfer Explanation Build-operate-and-transfer (BOT) Build-own-and-operate (BOO) Build-and-transfer Build-lease-and-transfer A contractual arrangement whereby the project company undertakes the construction, including financing, of a given infrastructure facility, the operation maintenance thereof. The project company: - operates the facility over a fixed term - charge facility users (customers) appropriate tolls, fees, rentals, etc - the charges do not exceeding those proposed in its bid or as negotiated - to recover its investment, and operating and maintenance expenses - at the end of the fixed term, transfers the facility to the government A contractual arrangement whereby a project company is authorized to finance, construct, own, operate and maintain an infrastructure. The project company: - allowed to recover its total investment, operating and maintenance costs plus a reasonable return thereon by collecting tolls, fees, rentals or other charges from facility users. A contractual arrangement whereby the project company undertakes the financing and construction of a given infrastructure. The project company: - upon completion turns the asset to the government - Government pays the company on an agreed schedule its total investments expended on the project, plus a reasonable rate of return A contractual arrangement whereby a project company is authorized to finance and construct an infrastructure. The project company: - upon its completion turns the asset over to the government concerned on a lease arrangement for a fixed period after which ownership of the facility is automatically transferred to the government Build-transfer-and-operate A contractual arrangement whereby the public sector contracts out the building of an infrastructure facility to a private entity such that the contractor builds the facility on a turn-key basis, assuming: - cost overrun, delay and specified performance risks - once the facility is commissioned satisfactorily, title is transferred to the implementing agency/lgu - The private entity, however, operates the facility on behalf of the implementing agency/lgu under an agreement.
32 Contractual/Ownership Arrangements: New trends emerging For a first time a build-own-operate (BOO) contact, where Rosatom will BOO the VVER nuclear units at Akkuyu, in Turkey Project company legal entity incorporated in Turkey Founders:5 Russian government companies affiliated with Rosatom Russian Party to retain majority stake during the whole lifetime of the Project (51%-100%) Turkish Party hasn t intended to finance equity of the Project Company Turkey TETAS, Turkish utility Site Project support guarantees PPA Project Company Obtaining of all necessary licenses and permits Project management Funding engagement Contracting Decommissioning & waste management EPC contract EPC-contractor Atomstroyexport O&M contract NPP Operator Rosenergoatom Fuel Supply contract Nuclear Fuel Supplier TVEL Advisory Service (Legal and Financial) Consulting service (Architect Engineer) Agency agreement Electricity Trading Company INTER RAO UES
33 Concluding Comments Firm government commitment and support - imminent Pure project finance is still challenging for nuclear: more difficult due to Fukushima accident, foreseeable risk is unnecessary safety measures might increase the cost of NPPs adding to higher premium October 2008 global financial crisis and strict financial industry regulation will impact liquidity and make financing tough for investors, like Basel III, that will force banks to increase the capital reserve and to be vigilant regarding risky projects, like NPPs Governments also urging multilateral financial institutions like World Bank, EBRD, to assist with the financing of NPPs Private financing will be in the form of JV among utilities with robust balance sheets and financial risk management strategy Construction risk is rated no 1 so to gain confidence of investors the industry needs more projects on Schedule and within Budget 33
34 Thank you for your attention! atoms for peace. 34
35 no. of construction starts Nuclaer power - construction starts
36 Nuclear: Traditional Financing Model OECD Arrangements and some features: Scope of export credit ECA funding cost * Crucial funding source for new builds Export credit advantage Constrains on ECA support Financing of up to 85% of the off-shore portion Banking fees Without guarantee commercial banks are cautions of lending Loan Term 18 yrs repayment period Ability to finance ECA premium and IDC ECA support limited by export content Support for local content is 15-30% of the off-shore portion Interest rate:libor/euribor +bank margin (depends on country risk assessment) State involvement brings significant funding capacity Flexible repayment structure: - Straight line or levelised (mortgage style) payment schedule Sovereign debt capacity - Possible postponement of starting payment * The ECA funding cost levels depend on country category for some countries that fall in high risk category fees can be very high, as risk premium is added.
Joint ICTP-IAEA School of Nuclear Energy Management August Financing Nuclear Projects. N. Barkatullah IAEA, Vienna Austria
2257-13 Joint ICTP- School of Nuclear Energy Management 8-26 August 2011 Financing Nuclear Projects N. Barkatullah, Vienna Austria Financing of Nuclear Power Projects /ICTP School of Nuclear Energy Management
More informationFinancing Infrastructure Projects: Challenges and Approaches
Financing Infrastructure Projects: Challenges and Approaches Dr Nadira Barkatullah Director of Economics, AECOM 2017 Australian Conference for Economist July 19-21, 2017 Sydney, Australia Overview Capital
More informationA Guide to Investing In Corporate Bonds
A Guide to Investing In Corporate Bonds Access the corporate debt income portfolio TABLE OF CONTENTS What are Corporate Bonds?... 4 Corporate Bond Issuers... 4 Investment Benefits... 5 Credit Quality and
More informationEnergy Strategy Reviews
Energy Strategy Reviews 18 (2017) 127e140 Contents lists available at ScienceDirect Energy Strategy Reviews journal homepage: www.ees.elsevier.com/esr Current status and emerging trends in financing nuclear
More informationFixed Income Update: Structuring Portfolios for a Rising Interest Rate Environment
Fixed Income Update: Structuring Portfolios for a Rising Interest Rate Environment February 16, 2017 Thomas S. Sawyer Sawyer Falduto Asset Management, LLC 630-941-8560 tsawyer@sawyerfalduto.com Introduction
More informationEconomics 173A and Management 183 Financial Markets
Economics 173A and Management 183 Financial Markets Fixed Income Securities: Bonds Bonds Debt Security corporate or government borrowing Also called a Fixed Income Security Covenants or Indenture define
More informationMarkit iboxx EUR Rating Rules
Markit iboxx EUR Rating Rules April 2010 Contents 1 Rating... 3 2 Rating Cut-Off Dates... 3 3 Markit iboxx Average Rating - Methodology... 3 4 Further information... 5 2 1 Rating All bonds in the Markit
More informationREGULATION ON BANK CAPITAL ADEQUACY. Article 1 Purpose and Scope
Pursuant to Article 23, paragraph 1, Article 35, paragraph 1, subparagraph 1.1 of the Law No. 03/L-209 on the Central Bank of the Republic of Kosovo (Official Gazette of the Republic of Kosovo, No. 77/16,
More informationREGULATION ON BANK CAPITAL ADEQUACY. Article 1 Purpose and Scope
Pursuant to Article 35, paragraph1, to Article 35, paragraph 1, subparagraph 1.1 of the Law No. 03/L-209 of the Central Bank of the Republic of Kosovo (Official Gazette of the Republic of Kosovo, No. 77/16
More informationFixed Income Investment
Fixed Income Investment Session 1 April, 24 th, 2013 (Morning) Dr. Cesario Mateus www.cesariomateus.com c.mateus@greenwich.ac.uk cesariomateus@gmail.com 1 Lecture 1 1. A closer look at the different asset
More informationTreasury Policy. Purpose of this policy:
Purpose of this policy: The purpose of this policy is to set out appropriate parameters as deemed fit by the Board for ELEXON s banking arrangements, in order to minimise counterparty risk, while delivering
More informationJoint ICTP-IAEA School on Nuclear Energy Management. 15 July - 3 August, Financing Structures for a Nuclear Power Plant Project
2473-36 Joint ICTP- School on Nuclear Energy Management 15 July - 3 August, 2013 Financing Structures for a Nuclear Power Plant Project P. Warren, Vienna, Austria Financing Structures for a Nuclear Power
More informationNUCLEAR NEW BUILD: INSIGHTS INTO FINANCING AND PROJECT MANAGEMENT. Dr. Jan Horst Keppler, Senior Economic Advisor NEA Nuclear Development Division
NUCLEAR NEW BUILD: INSIGHTS INTO FINANCING AND PROJECT MANAGEMENT Dr. Jan Horst Keppler, Senior Economic Advisor NEA Nuclear Development Division Context Results are based on study of the OECD Nuclear
More informationFINANCING OPTIONS AVAILABLE FOR COAL-FIRED POWER IN ASIA DUNCAN RITCHIE CEO, AEQUERO
FINANCING OPTIONS AVAILABLE FOR COAL-FIRED POWER IN ASIA DUNCAN RITCHIE CEO, AEQUERO 3 rd Annual Emerging Asian Coal Markets, Vietnam 5 6 November 2014 1 Background to Aequero Aequero CEO led ANZIB office
More informationRating Action: TIAA-CREF, New York Life, Northwestern Mutual (Affirmation, Outlook Revision)
Rating Action: TIAA-CREF, New York Life, Northwestern Mutual (Affirmation, Outlook Revision) On December 11, Moody s Investors Service affirmed the Aaa (Exceptional) insurance financial strength ratings
More informationI. Asset Valuation. The value of any asset, whether it is real or financial, is the sum of all expected future earnings produced by the asset.
1 I. Asset Valuation The value of any asset, whether it is real or financial, is the sum of all expected future earnings produced by the asset. 2 1 II. Bond Features and Prices Definitions Bond: a certificate
More informationForward Exchange Contracts and Foreign Exchange Swaps
Forward Exchange Contracts and Foreign Exchange Swaps Product Disclosure Statement Issued by Bank of New Zealand Prepared as at 26 October 2017 This document replaces the BNZ Product Disclosure Statement
More informationNational Ratings Definitions
National Ratings Definitions AM Best Rating Descriptor Definition A++ Superior Assigned to companies that have, in our opinion, a superior ability to meet their ongoing insurance obligations. A++ Superior
More informationNigeria Infrastructure Building Conference 2014
Nigeria Infrastructure Building Conference 2014 May 2011 Project Finance as a viable option for financing Infrastructure Projects P R E P A R E D B Y: Helen Brume Divisional Head, Power, Infrastructure
More informationHigh Yield. LarrainVial Seminario Mercados Globales - Ideas Hans Stoter Head of Credit Investments ING Investment Management
High Yield Hans Stoter Head of Credit Investments ING Investment Management LarrainVial Seminario Mercados Globales - Ideas 2010 Santiago, Lima May 11 13, 2010 What is High Yield Corporate debt with rating
More informationPROJECT FINANCE GLOSSARY
API Gravity Availability Barrel Barrel of oil equivalent Barter Base load plant Berne Union Bid Bond BOT BPCD BTU Bullion Buyer Credit Capacity charge A measure of density of Crude Oil or other liquid
More informationRISKS ASSOCIATED WITH INVESTING IN BONDS
RISKS ASSOCIATED WITH INVESTING IN BONDS 1 Risks Associated with Investing in s Interest Rate Risk Effect of changes in prevailing market interest rate on values. As i B p. Credit Risk Creditworthiness
More informationValuing Bonds. Professor: Burcu Esmer
Valuing Bonds Professor: Burcu Esmer Valuing Bonds A bond is a debt instrument issued by governments or corporations to raise money The successful investor must be able to: Understand bond structure Calculate
More informationFocus on. Fixed Income. Member SIPC 1 MKD-3360L-A-SL EXP 31 JUL EDWARD D. JONES & CO, L.P. ALL RIGHTS RESERVED.
Focus on Fixed Income www.edwardjones.com Member SIPC 1 5 HOW CAN I STAY ON TRACK? 4 HOW DO I GET THERE? 1 WHERE AM I TODAY? MY FINANCIAL NEEDS 3 CAN I GET THERE? 2 WHERE WOULD I LIKE TO BE? 2 Our Objectives
More informationCALIFORNIA BONDS: 101
CALIFORNIA BONDS: 101 A Citizen s Guide to General Obligation Bonds 2016 EDITION JOHN CHIANG CALIFORNIA STATE TREASURER SECTION 1 BONDS 101: Q&A Q. What is a municipal bond? A. A bond is a loan. There
More informationFUNDAMENTALS OF CREDIT ANALYSIS
FUNDAMENTALS OF CREDIT ANALYSIS 1 MV = Market Value NOI = Net Operating Income TV = Terminal Value RC = Replacement Cost DSCR = Debt Service Coverage Ratio 1. INTRODUCTION CR = Credit Risk Y.S = Yield
More informationInfrastructure Project Finance using Debt Fund Vehicles
Infrastructure Project Finance using Debt Fund Vehicles Ralf Garrn, Managing Director Euler Hermes Rating GmbH Agenda 1 Introduction to Euler Hermes 2 Capital Market Union 3 Renewable Project Finance Ratings
More informationGOLDMAN SACHS BANK (EUROPE) PLC
AS AT 31 DECEMBER 2009 GOLDMAN SACHS BANK (EUROPE) PLC PILLAR 3 DISCLOSURES Table of Contents 1. Overview 1 2. Basel II and Pillar 3 1 3. Scope of Pillar 3 1 4. Capital Resources and Capital Requirements
More informationAn Introduction to Bonds
An Introduction to Bonds Agenda Bond basics Different types of bonds Bond features Yield and tax considerations Bond risks Credit quality Bond investing strategies and client suitability Defining Characteristics
More informationAtoms for the Future New Build
Atoms for the Future 2014 - New Build Tony Ward 13 October 2014, Paris EU approves Hinkley Point C State Aid case 2 8 October 2014 - A hugely significant step.2 years after Generic Design Assessment approval
More informationDebt markets. International Financial Markets. International Financial Markets
Debt markets Outline Instruments Participants Yield curve Risks 2 Debt instruments Bank loans most typical Reliance on private information Difficult to transfert to third party Government and commercial
More informationFixed income for your portfolio
Fixed income for your portfolio November 2017 2 Fixed income for your portfolio Defence Fixed income investments such as bonds are widely used in portfolios to enhance income and compliment low risk interest
More informationRisk and Term Structure of Interest Rates
Risk and Term Structure of Interest Rates Economics 301: Money and Banking 1 1.1 Goals Goals and Learning Outcomes Goals: Explain factors that can cause interest rates to be different for bonds of different
More informationFinancing an NPP: Foundation Knowledge
9 May 2014 Bucharest, Romania Financing an NPP: Foundation Knowledge IFNEC Steering Group Meeting Overview of Presentation Market Conditions and Challenges Key Terms Current Trends Project Development
More informationIssues and Challenges for Merchant Nuclear
Issues and Challenges for Merchant Nuclear Edward Kee Vice President U.S. NRC 10 CFR 50.33(f) Financial Qualifications for Merchant Plant COL Applicants 11 Oct 2012 Disclaimer The slides that follow are
More informationBasel II Pillar 3 Disclosure As at 30 June Overview
Basel II Pillar 3 Disclosure As at Overview The Royal Bank of Scotland Berhad and its subsidiaries (collectively the Group ) adopted the Standardised Approach in determining the capital requirements for
More informationAustralia and New Zealand Banking Group Limited New Zealand Branch General Disclosure Statement
Australia and New Zealand Banking Group Limited New Zealand Branch General Disclosure Statement FOR THE YEAR ENDED 30 SEPTEMBER 2010 NUMBER 8 ISSUED NOVEMBER 2010 Australia and New Zealand Banking Group
More informationBond Valuation. Capital Budgeting and Corporate Objectives
Bond Valuation Capital Budgeting and Corporate Objectives Professor Ron Kaniel Simon School of Business University of Rochester 1 Bond Valuation An Overview Introduction to bonds and bond markets» What
More informationBasel II Pillar 3 Disclosure As at 30 June Overview
Basel II Pillar 3 Disclosure As at Overview The Royal Bank of Scotland Berhad and its subsidiaries (collectively the Group ) adopted the Standardised Approach in determining the capital requirements for
More informationState Board of Administration Finance. Investment Portfolio Guidelines
State Board of Administration Investment Portfolio Guidelines Portfolio Names: Florida Hurricane Catastrophe Fund (FHCF) State Board of Administration Finance Corporation Pre-Event Liquidity Fund (Corporation)
More informationLearn about bond investing. Investor education
Learn about bond investing Investor education The dual roles bonds can play in your portfolio Bonds can play an important role in a welldiversified investment portfolio, helping to offset the volatility
More informationClean Technology Fund (CTF) Proposal for CTF 2.0
Clean Technology Fund (CTF) Proposal for CTF 2.0 Outline Clean Technology Fund: 2008 to 2016 The Journey so far Changing climate in a changing world SDGs, Paris Agreement Unique opportunity Use of assets
More informationBonds explained. Member of the London Stock Exchange
Bonds explained Member of the London Stock Exchange Killik & Co We pride ourselves on being a relationship firm. Each client has their own dedicated Broker, who acts as the single point of contact to provide
More informationNavigating the Credit Cycle
Navigating the Credit Cycle Dan Henken, CFA - Portfolio Manager - Technology Media & Telecom Analyst John Leiviska, CFA - Minnesota Life Portfolio Manager Tom Houghton, CFA - Total Return Portfolio Manager
More informationPlenary 2: Public-Private Partnerships. Monday, 12:00 to 13:00
Plenary 2: Public-Private Partnerships Monday, 12:00 to 13:00 Session agenda 1. What is PPP? 2. When are PPPs appropriate and where have they been used? 3. PPI in South Asia 4. Key terms 5. Summary and
More informationUTILITY SYSTEM IMPROVEMENT FINANCING
UTILITY SYSTEM IMPROVEMENT FINANCING Stauder, Barch & Associates Ann Arbor 1 UTILITY SYSTEM FINANCING OPTIONS POSSIBLE FUNDING SOURCES Utility System Reserves Grants Bond Financing (Including SRF) Installment
More informationCity of Tucson Finance
City of Tucson Finance Proudly Presented By: Silvia Amparano, CPA, CPFO Finance Director Association of Government Accountants Southern Arizona Chapter October 12, 2016 1 Agenda Governmental Accounting
More informationChapter Six. Bond Markets. McGraw-Hill /Irwin. Copyright 2001 by The McGraw-Hill Companies, Inc. All rights reserved.
Chapter Six Bond Markets Overview of the Bond Markets A bond is is a promise to make periodic coupon payments and to repay principal at maturity; breech of this promise is is an event of default carry
More informationFixed Income Securities: Bonds
Economics 173A and Management 183 Financial Markets Fixed Income Securities: Bonds Updated 4/24/17 Bonds Debt Security corporate or government borrowing Also called a Fixed Income Security Covenants or
More informationAgenda. Power Division Fortum s nuclear generation Nuclear capacity upgrades in Sweden Nuclear s strategic role
1 2 Agenda Power Division Fortum s nuclear generation Nuclear capacity upgrades in Sweden Nuclear s strategic role 3 Power key figures Q2/2010 Operations in Finland, Sweden, UK, Germany, UAE 1,700 employees
More informationThe Evolution of High-Yield Bonds into a Vital Asset Class
Allianz Global Investors White Paper Series The Evolution of High-Yield Bonds into a Vital Asset Class 07/2016 Executive Summary With high-quality bond yields near all-time lows, investors have looked
More informationFinancial Literacy Series Investing
Financial Literacy Series Investing January 31, 2018 Robert Turnquest, CFA, CAIA Agenda What is investing? Types of investments Stocks Bonds Mutual funds Developing your personal portfolio Risk vs. return
More informationAnnual Investment Policy of the Pooled Investment Fund
SACRAMENTO COUNTY Annual Investment Policy of the Pooled Investment Fund CALENDAR YEAR 2017 Approved by the Sacramento County Board of Supervisors December 6, 2016 Resolution No. 2016-0938 Table of Contents
More informationMBF1223 Financial Management Prepared by Dr Khairul Anuar
MBF1223 Financial Management Prepared by Dr Khairul Anuar L3 Project Financing www.mba638.wordpress.com Objectives To understand what project financing is and what steps are involved in securing and managing
More informationBond Valuation. FINANCE 100 Corporate Finance
Bond Valuation FINANCE 100 Corporate Finance Prof. Michael R. Roberts 1 Bond Valuation An Overview Introduction to bonds and bond markets» What are they? Some examples Zero coupon bonds» Valuation» Interest
More informationRHB Investment Bank Berhad Basel II Pillar 3 Quantitative Disclosures. 30 June 2017
RHB Investment Bank Berhad Basel II Pillar 3 Quantitative Disclosures 30 June 2017 Contents Page(s) Statement by Chief Executive Officer 2 Introduction 3 Scope of Application 3 List of Tables Table No
More informationUNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C FORM 6-K REPORT OF FOREIGN PRIVATE ISSUER
UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C. 20549 FORM 6-K REPORT OF FOREIGN PRIVATE ISSUER PURSUANT TO RULE 13a-16 OR 15d-16 UNDER THE SECURITIES EXCHANGE ACT OF 1934 Date: March
More informationAustralia and New Zealand Banking Group Limited New Zealand Branch Disclosure Statement
Australia and New Zealand Banking Group Limited New Zealand Branch Disclosure Statement FOR THE YEAR ENDED 30 SEPTEMBER 2011 NUMBER 11 ISSUED NOVEMBER 2011 Australia and New Zealand Banking Group Limited
More informationThe Case for A Rated Issuers
The Case for A Rated Issuers August 31, 2012 PFM Asset Management LLC One Keystone Plaza, Suite 300 N. Front & Market Sts Harrisburg, PA 17101 (717) 232-2723 Contents Tab I Overview of the Corporate Market
More informationCARRIER FINANCIAL STRENGTH RATINGS Financial ratings reflect an insurance company's claims paying ability
CARRIER FINANCIAL STRENGTH RATINGS Financial ratings reflect an insurance company's claims paying ability Source Carrier A.M. Best Standard & Poor s Moody s Fitch 1 Unum A A A2 A 2 John Hancock A+ AA-
More informationFirst Trust Intermediate Duration Preferred & Income Fund Update
1st Quarter 2015 Fund Performance Review & Current Positioning The First Trust Intermediate Duration Preferred & Income Fund (FPF) produced a total return for the first quarter of 2015 of 3.84% based on
More informationUBS AG Standalone financial statements and regulatory information for the year ended 31 December 2016
UBS AG Standalone financial statements and regulatory information for the year ended 31 December 2016 Table of contents 1 UBS AG standalone financial statements (audited) 26 UBS AG standalone regulatory
More informationTITLE IV NUCLEAR MATTERS Subtitle A Price-Anderson Act Amendments
REDLINE OF CHAIRMAN S MARK 0 SEC. 0. SHORT TITLE. TITLE IV NUCLEAR MATTERS Subtitle A Price-Anderson Act Amendments This subtitle may be cited as the Price-Anderson Amendments Act of 00. SEC. 0. EXTENSION
More information08 A p r i l V o l u m e b y G l a c i e r R e s e a r c h
FUNDS ON FRIDAY b y G l a c i e r R e s e a r c h 08 A p r i l 2 0 1 6 V o l u m e 8 5 6 Will investor sentiment dictate capital flows amidst a possible downgrade of South Africa s sovereign debt rating?
More informationHSBC Portfolios - World Selection 1
HSBC Portfolios - World Selection 1 J Share Class AC 30 Jun 2018 AC 30/06/2018 Fund Objective and Strategy Investment Objective The Fund aims to provide long term total returns (meaning income and capital
More informationPresentation to GIOA. March 2015
Presentation to GIOA March 2015 Safe Harbor Statement This document contains forward looking statements relating to future events and future performance. All statements other than those that are purely
More informationKnowledgeable Customer Capability and Considerations under Different Contracting and Ownership Structures
8 April 2014 Obninsk, Russia Knowledgeable Customer Capability and Considerations under Different Contracting and Ownership Structures PAUL MURPHY IAEA Technical Meeting on Becoming a Knowledgeable Customer
More informationGazprom. Consolidated 2008 IFRS Financial Results Presentation
Gazprom Consolidated 2008 IFRS Financial Results Presentation Disclaimers This presentation has been prepared by OJSC Gazprom (the Company ), and comprises the slides for a presentation to investors concerning
More informationRatings for Local Government Investment Pools
Ratings for Local Government Investment Pools Roger Merritt, Managing Director Government Investment Officers Association Las Vegas, March 2012 Agenda / overview Fitch s rating criteria for local government
More information...:... Securing financing for cold climate projects. Justin Jeffs Head of Investment & Economics. !'e,
.:.,...... :,\....:... =-,...,.:..!'e, Securing financing for cold climate projects Justin Jeffs Head of Investment & Economics Intro to Triventus Consulting 1.0 European wind power an investor perspective
More informationProduct Disclosure Statement
FOREIGN EXCHANGE TRANSACTIONS Product Disclosure Statement 28 November 2018 Kiwibank Limited as issuer This document is a replacement product disclosure statement, replacing the Product Disclosure Statement
More informationBank of China (Malaysia) Berhad Risk Weighted Capital Adequacy Framework (Basel II) Disclosure Requirements (Pillar 3) 31 Dec 2014
Risk Weighted Capital Adequacy Framework (Basel II) Disclosure Requirements (Pillar 3) 31 Dec 2014 CONTENTS 1. Introduction 2. Scope of Application 3. Capital 3.1 Capital Management 3.2 Capital Adequacy
More informationPILLAR 3 DISCLOSURE CITIBANK BERHAD
CITIBANK BERHAD PILLAR 3 DISCLOSURE CONTENTS Introduction Capital Adequacy Capital Structure Risk Management Credit Risk Securitization Market Risk Operational Risk Equities Interest Rate Risk/ Rate of
More informationSupplementary Regulatory Capital Disclosure
Supplementary Regulatory Capital Disclosure For the period ended January 31, 2017 For further information, please contact: John Ferren, Senior Vice-President, Corporate CFO and Investor Relations (416)
More informationReading. Valuation of Securities: Bonds
Valuation of Securities: Bonds Econ 422: Investment, Capital & Finance University of Washington Last updated: April 11, 2010 Reading BMA, Chapter 3 http://finance.yahoo.com/bonds http://cxa.marketwatch.com/finra/marketd
More informationPortugal. Main Economic Indicators
Portugal Main Economic Indicators January, 2016 Contents 1 - Macroeconomic Indicators 2 - Macroeconomic Indicators - Forecasts 3 - Gross Value Added 4 - Employment 5 - Risk Indicators 1. Macroeconomic
More informationBank of China (Malaysia) Berhad Risk Weighted Capital Adequacy Framework (Basel II) Disclosure Requirements (Pillar 3) 30 June 2015
Risk Weighted Capital Adequacy Framework (Basel II) Disclosure Requirements (Pillar 3) 30 June 2015 CONTENTS 1. Introduction 2. Scope of Application 3. Capital 3.1 Capital Management 3.2 Capital Adequacy
More informationCounterparty Credit Default Swap Rates
Counterparty Credit Default Swap Rates 1 December 2017 This information is for financial advisers only and should not be presented to, or relied upon by, private investors. 1 Credit default swaps Bloomberg/Meteor
More informationCounterparty Credit Default Swap Rates
Counterparty Credit Default Swap Rates 22 June 2018 This information is for financial advisers only and should not be presented to, or relied upon by, private investors. 1 Credit default swaps Bloomberg/Meteor
More informationAssessment in the Area of Economics. Pablo Florido MANAGING DIRECTOR FLORESTAN TECHNOLOGY ARGENTINA
Workshop on IAEA Tools for Nuclear Energy System Assessment (NESA) for Long Term Planning and Development (Technical Cooperation Project INT/4/142) July 20-23 23 2009, Vienna, Austria Assessment in the
More informationUndertaking Successful PPPs in Kazakhstan
Undertaking Successful PPPs in Kazakhstan Stephen Watson Head of Service PPP Astana, Kazakhstan 24 October 2013 image courtesy of stock.xchng Contents PPP Principles PPPs in Kazakhstan Renewables in Kazakhstan
More informationBank of China (Malaysia) Berhad Risk Weighted Capital Adequacy Framework (Basel II) Disclosure Requirements (Pillar 3) 30 June 2014
Risk Weighted Capital Adequacy Framework (Basel II) Disclosure Requirements (Pillar 3) 30 June 2014 CONTENTS 1. Introduction 2. Scope of Application 3. Capital 3.1 Capital Management 3.2 Capital Adequacy
More informationFixed Income Investor Update. innogy SE November 2016
Fixed Income Investor Update innogy SE November 2016 innogy at a glance Financial review innogy s credit profile innogy at a glance Successful implementation of innogy carve-out and IPO Dec Jan Feb Mar
More informationInterest Rate Swaps Product Disclosure Statement. Issued by Westpac Banking Corporation ABN AFSL
Interest Rate Swaps Product Disclosure Statement Issued by Westpac Banking Corporation ABN 33 007 457 141 AFSL 233714 Dated: 22 September 2017. This is a replacement product disclosure statement. It replaces
More informationSECTION I.1 - CREDIT RISK: STANDARDISED APPROACH General Principles
SECTION I.1 - CREDIT RISK: STANDARDISED APPROACH General Principles 1.0 Under the Standardised Approach, the exposure value of an asset shall be a) the balance-sheet value, and b) the resultant value of
More informationCounterparty Credit Default Swap Rates
Counterparty Credit Default Swap Rates 20 April 2018 This information is for financial advisers only and should not be presented to, or relied upon by, private investors. 1 Credit default swaps Bloomberg/Meteor
More informationCounterparty Credit Default Swap Rates
Counterparty Credit Default Swap Rates 27 April 2018 This information is for financial advisers only and should not be presented to, or relied upon by, private investors. 1 Credit default swaps Bloomberg/Meteor
More informationCounterparty Credit Default Swap Rates
Counterparty Credit Default Swap Rates 13 April 2018 This information is for financial advisers only and should not be presented to, or relied upon by, private investors. 1 Credit default swaps Bloomberg/Meteor
More informationLife Insurer Financial Profile
Life Insurer Financial Profile Company New York Life Ins Massachusetts Transamerica Life John Hancock Life & Mutual of Omaha Genworth Life Ins MedAmerica Ins Co Co Mutual Life Ins Ins Co Health Ins Ins
More informationMunicipal Bond Spotlight 1. Municipal Bonds 2. Government Agency Bonds, U.S. Treasuries 3,4. DANs, Federal Reserve 5. Brokered CDs, Business 101 8,9
July 2009 Contents Municipal Bond Spotlight 1 Municipal Bonds 2 Government Agency Bonds, U.S. Treasuries 3,4 DANs, Federal Reserve 5 Money In Your Pocket Tip of the Month, Economic Indicators Calendar
More informationAustralia and New Zealand Banking Group Limited - New Zealand Branch Disclosure Statement
Australia and New Zealand Banking Group Limited - New Zealand Branch Disclosure Statement FOR THE YEAR ENDED 30 SEPTEMBER 2012 NUMBER 16 ISSUED NOVEMBER 2012 Australia and New Zealand Banking Group Limited
More informationSupplementary Regulatory Capital Disclosure
Supplementary Regulatory Capital Disclosure For the period ended January 31, 2015 For further information, please contact: Geoff Weiss, Senior Vice-President, Corporate CFO and Investor Relations (416)
More informationJ.P. MORGAN CHASE BANK BERHAD (Incorporated in Malaysia)
FOR THE FINANCIAL YEAR ENDED 30 JUNE 2017 1 CAPITAL STRUCTURE AND ADEQUACY The capital adequacy ratios of the Bank are computed in accordance with Bank Negara Malaysia's revised Risk-Weighted Capital Adequacy
More informationPortugal. Main Economic Indicators
Portugal Main Economic Indicators September, 2018 Contents 1 - Macroeconomic Indicators 2 - Macroeconomic Indicators - Forecasts 3 - Gross Value Added 4 - Employment 5 - Risk Indicators 1. Macroeconomic
More informationING MVA ANNUITY A Single Premium Deferred Annuity (Standard Form # Nonqualified; may vary by state and not available in all states.
An Annuity Illustration using ING MVA ANNUITY (Standard Form #03502 8-00 Nonqualified; may vary by state and not available in all states.) Designed for: Mr. Wise Presented by: Financial Professional..,
More informationHouse Committee on Oversight
House Committee on Oversight 38 Studios Moral Obligation Bond Repayment May 8, 2014 What is RIPEC? RIPEC is an independent, nonprofit and nonpartisan public policy research and education organization.
More informationParticipating Forward Contracts
Participating Forward Contracts Product Disclosure Statement Issued by Westpac Banking Corporation ABN 33 007 457 141 AFSL 233714 Dated: 25 September 2018. This is a replacement product disclosure statement.
More informationRole of the Rating Agency. Pete McGinnis August 3, 2007
Role of the Rating Agency Pete McGinnis August 3, 2007 Presentation Outline What is a Nationally Recognized Statistical Rating Organization ( NRSRO ) The role of a rating agency in a bond deal and the
More informationThe role of Islamic rating agencies: Between alternative and competitor
Conference paper (excluding author names and affliations) (ICIEF) The role of Islamic rating agencies: Between alternative and competitor PREPRINT: PLEASE DO NOT QUOTE OR DISTRIBUTE Abstract: This study
More informationFinancing Renewables. EPG Summit, Prague. 3 December 2012
Financing Renewables EPG Summit, Prague 3 December 2012 The new paradigm This was then This is now Decarbonisation Value for money Ambitious goals Long-term policy GDP growth Market Policy Limited to no