Port of Tacoma Semi-Annual Project Progress Report

Size: px
Start display at page:

Download "Port of Tacoma Semi-Annual Project Progress Report"

Transcription

1 Port of Tacoma Semi-Annual Project Progress Report

2 Port of Tacoma Leadership Port of Tacoma Commission Connie Bacon President John Wolfe Chief Executive Officer Don Johnson Second Assistant Secretary Dick Marzano Vice President Don Meyer Secretary Clare Petrich First Assistant Secretary

3 Semi-Annual Project Progress Report Introduction Created by Pierce County citizens in 1918, the Port of Tacoma is a powerful economic engine in Pierce County and throughout the State of Washington, creating significant private investment and family-wage jobs within the region. Port activities account for more than 29,000 jobs and contribute more than $223 million each year in state and local taxes that support schools, roads, police, and fire protection. The intent of this report is to provide Port Commission with high level information on the status of Port s projects. About the Report The report will provide general information on the project description, status, significant developments, schedule, cost, and risks. The Port implements a number of different types of projects and not all information may be relevant to a specific report; as such, the reports may vary in detail and content. The report includes the project name, project number, authorized amount, project phase, current estimate at completion, cost to date, and estimated completion date. The report also includes information on status related to scope, schedule, and budget. : of spending, agreements, administrative actions, real property actions, and other items as outlined by the Master Policy by the Commission or Chief Executive Officer or the CEO s delegate. s are frequently phased parallel to specific project stages. For example, the CEO may authorize preliminary work for assessing the opportunity and conceptual design. Port Commission would typically authorize work, in a phased or staged approach, for design and then construction. Current Estimate: The current estimate represents the expected cost of the project at the time the quarterly report is prepared and submitted. It represents the total estimated cost anticipated for completion of the project. Cost to Date: The cost to date are actual costs that are recorded in the accounting system as project costs. Cost to date represents a specific date, typically the last day of the reporting quarter. Significant Developments: Covers items such as accomplishments, significant events or milestones, contract advertisements and awards, upcoming activities, environmental issues, and scope changes. 1

4 Port of Tacoma Semi-Annual Project Progress Report Schedule: Includes information on the project schedule, including variances since the last report such as contract extensions and information on critical dates. : Addresses the total estimated cost of the project and includes information on the overall project cost status, recent Commission authorizations, and any variances such as forecasted overruns or savings. Addresses the amount identified in the Capital Improvement Plan for the project and includes information on the overall budget status, and any variances such as forecasted overruns or savings. : Describes any significant risk of delay, any significant risk to cost, or any significant change orders. These reports are intended to meet the reporting requirements of the Port s Master Policy, paragraph IV. B. 8. 2

5 MID No , , , , , Port of Tacoma Semi-Annual Project Progress Report Project Title Upper Clear Creek Mitigation 4 Page 3009 Taylor Way MTCA Interim Actions and CAP 5-6 Pier 4 Phase I Removal Action 7 Overall Project Status Schedule Parcel 14 Grading and Site Stabilization 8 Lower Wapato Combined Habitat 9 North Lead Rail Improvements East 11th St Deconstruction & Remediation Kaiser Remediation AO DE Marine View Drive Structures Demolition 15 Mouth of Hylebos Port Parcel 2 Petroleum Contamination AO DE PQ Contamination Taylor Way Arkema RI/FS/CAP AO DE & 2920 Taylor Way Port Parcel 1B-EBC AO DE Arkema North Boundary Allocation Report Port of Tacoma Road Reconstruction ILA with City of Tacoma Saltchuk Aquatic Mitigation Site - Preliminary Design , , , Shoreline Stabilization Roof Replacement at 401 Alexander Ave Bldg PCT Electrical Testing and Repair Repairs to Bldgs at 2602 & 2608 Port of Tacoma Rd 30 Parcel 103 Steam Plant Property Cleanup 31 Surface and Tamp Rail 32 Replace SIM Rail Switches 33 Roof Replacement at 3701 Taylor Way 34 Alexander Avenue Wetland Maytown Oversight 36 Executive s for 37 Budget Key Completed Final Report for this Project Project within or ahead of target budget and schedule Either target schedule or budget is off Both target schedule and budget are off Negative Variance Status New Variance Previously Reported Schedule Completion on the Project Reports refers to: Substantial Completion 3

6 Upper Clear Creek Mitigation Project MID No: : $9,064,000 Construction Current Estimate: $8,980,975 Cost to Date: $7,898,685 Start: 7/19/2012 Schedule Completion: 3/31/2018 Project Manager: David Myers Schedule: On or Ahead The project is developing a 40 plus acre habitat site to meet requirements of a settlement with the EPA and DOJ as well as establish a significant mitigation bank to be used for future critical area impacts Significant Developments/ Changes associated with other Port projects. The project will provide riparian and salmon habitat in conjunction The project has reached partial substantial with related buffers. completion The Construction portion of the project reached partial substantial completion on June 24, The plant establishment period and project substantial complete are slated for March 31, No additional authorizations are anticipated at this time. Noting to report The Capital Improvement Plan allocates $9,064,000, through 2020 None at this time. 4

7 3009 Taylor Way MTCA Interim Actions and Cleanup Action Plan Project MID No: : $13,769,050 Close Out Current Estimate: $13,769,050 Cost to Date: $13,103,047 Start: 5/31/2007 Schedule Completion: 8/1/2016 Project Manager: Scott Hooton Schedule: On or Ahead Looking forward, the scope of this effort consists of: Implementing the groundwater monitoring plan in the CAP. Significant Developments/ Changes File an Environmental Covenant with the Pierce County Recorder s Office. Ecology executed Agreed Order DE requiring implementation of the Cleanup Action Plan (CAP) on 7/7/16. The Agreed Order is a legal agreement to begin long term monitoring at the former Atofina Chemical Log Yard Site located at 3009 Taylor Way. The antecedent public comment period ran from May 26-June 27, Citizens for a Healthy Bay offered comment expressing appreciation for the substantial cleanup effort conducted by the Port and support for the long-term groundwater monitoring plan. Upon receipt of the executed Agreed Order, Port staff will file the environmental covenant, schedule the installation of groundwater monitoring wells, and initiate long term monitoring. Provide Ecology with 30-day notice prior to property transfer and provide for the continuing implementation of the Order. Reimburse Ecology for oversight costs. The total project cost including all stages is estimated at $13,769,050. Project costs are partially offset by MTCA grant reimbursements, of which $4,022,538 has been received to date. An additional grant for past costs in the amount of $2,900,000 was approved by Ecology on June 17,

8 3009 Taylor Way MTCA Interim Actions and Cleanup Action Plan Commission authorized entry into Agreed Order DE for implementation of the Cleanup Action Plan (CAP) on 4/28/16. Costs for the remediation of the property (MIDs and ) have been capitalized. Annual depreciation is $97,000. Project costs related to Agreed Order DE will be expensed as incurred. The Capital Improvement Plan allocates $264,000 through 2020 (MID ). If monitoring data do not indicate declining or stable concentrations of metals in groundwater, Ecology may require additional sampling along the bank of the Hylebos Waterway and other corrective action. 6

9 Pier 4 Phase I Removal Action Project MID No: : $18,098,600 Close Out Current Estimate: $15,600,000 Cost to Date: $15,481,166 Start: 8/2/2012 Schedule Completion: 11/30/2016 Project Manager: Stanley Ryter Schedule: On or Ahead Demolish Pier 4. Dredge and dispose of contaminated material until site is clean as determined by the Environmental Protection Agency. Significant Developments/ Changes Environmental Protection Agency declared the site clean on 2/18/16. Contractor achieved final completion on 4/30/2016. Final report to EPA in progress. Financial close out to follow in 2 nd half of No new authorizations in this reporting period. Total project costs are estimated to be $15,600,000 at closeout. Financially, the project is over 99% complete. The Capital Improvement Plan allocates $16,477,000 through No significant risks remain. 7

10 Parcel 14 Grading and Site Stabilization Project MID No: : $10,300,000 Completed Current Estimate: $4,900,000 Cost to Date: $4,766,295 Start: 10/4/2012 Schedule Completion: 3/24/2016 Project Manager: David Myers [ Insert project graphic ] Advanced Mitigation Area 12 th Street Future 167 ROW Development Area (+/ - 82 Acres ) Schedule: On or Ahead Complete the rough grading to accommodate future commercial use and prevent critical areas from developing on approximately 93 acres of the site. Significant Developments/ Changes None This is final report. Commission authorization of $10,300,000 includes $5,400,000 for the advanced mitigation project which is currently on hold. Project was completed for less than the current estimate. The current Capital Improvement Plan allocates $4,790,000 through None No additional authorizations are needed for this work. 8

11 Lower Wapato Combined Habitat Project MID No: : $10,300,000 Design Current Estimate: $5,400,000 Cost to Date: $678,404 Start: 10/4/2012 Schedule Completion: Unknown Project Manager: David Myers [ Insert project graphic ] Advanced Mitigation Area 12 th Street Future 167 ROW Development Area (+/ - 82 Acres ) th Schedule: Delayed Construct a 17 acre habitat site for critical area impacts associated with other Port development projects. Significant Developments/ Changes None Current estimate is based on 95% level design. This project is currently on hold The Capital Improvement Plan allocates $5,400,000 through Commission authorization of $10,300,000 included $4,900,000 for work recently completed on the development portion of the site. Tribal issues have delayed permit approvals. State funding of the transportation package that includes SR167 could result in the loss of a location to place the spoils from this project increasing the project costs and potentially increasing the Port s financial contribution to the SR 167 project. 9

12 North Lead Rail Improvements Project MID No: : $18,100,000 Construction Current Estimate: $18,100,000 Cost to Date: $3,861,831 Start: 8/31/2010 Schedule Completion: 5/1/2017 Project Manager: Carol Rhodes Schedule: On or Ahead Construct track modification for the expansion and operation of two (2) new 7,000 foot intermodal tracks between Alexander Ave and Milwaukee Way within the Tacoma Rail Yard for future industrial Significant Developments/ Changes Construction Contract executed on 6/13/16. Owner furnished materials began delivery on 6/23/16. development to the East Blair Peninsula. Project includes modification of the west end of the yard to improve operational flexibility and fluidity in the rail corridor. Project remains on schedule. Project authorized on March 17, 2016 in the amount of $12,092,050 for a total of $18,100,000. No other authorizations are anticipated. Estimated cost is currently $18,100,000, which will cover all project costs including design and construction. The Capital Improvement Plan allocates $18,409,150, through Construction is in an active rail yard. Detailed construction sequencing has been prepared to maintain rail operations and minimize operational impacts to construction schedule. 10

13 1940 East 11th St Deconstruction & Remediation Project MID No: : $125,000 RI/FS Current Estimate: $260,000 Cost to Date: $10,749 Start: 2/12/2016 Schedule Completion: 6/30/2017 Project Manager: Rob Healy Schedule: Delayed The 2016 scope of work includes anticipated staff Forecast Overrun time and attorney s fees to advance the claim, and staff and consulting fees to oversee possible remediation actions within the fenced area. Significant Developments/ Changes At the end of 2015 the project for demolishing the 117,000 SF PCB-contaminated building was completed and closed. However, two outstanding issues remained; the $1.9M claim tendered to the former property owner was unresolved, and residual chlorinated VOCs remain in soil and groundwater on the property. On January 26, 2016 Executive of $125,000 was provided to advance the tendered claim and oversee possible remedial actions on the property. Negotiations with the property owner have proved unsuccessful, and a more aggressive litigation approach is required. Due to opposing counsel s irascible reputation, our attorney has recommended a legal budget of $125,000 to continue pursuing cost recovery and contribution for past contaminant releases at the site. This exceeds the original estimate for legal costs and will require additional Executive to proceed. Cost estimate is $260,000 with $10,749 spent through June 2016 for settlement negotiations, preparation of the claim, and preparation and filing of the lawsuit. The Capital Improvement Plan allocates $150,000 through This will be updated for the CIP. Settlement negotiations toward a non-judicial solution may be unfruitful. Site cleanup may not be advanced in a timely manner to meet the needs of a redevelopment project. 11

14 1940 East 11th St Deconstruction & Remediation Project schedule to be determined based on further negotiations and possible outcome of the lawsuit. Exec Auth ($125,000 January 26, 2016) Exec Auth ($135,000 Pending) 12

15 Kaiser Remediation Agreed Order DE-5698 Project MID No: : $10,555,930 Close Out Current Estimate: $10,555,930 Cost to Date: $10,509,209 Start: 2/10/2003 Schedule Completion: 10/1/2016 Project Manager: Scott Hooton Schedule: On or Ahead Looking forward, the scope of this effort consists of: Cooperate in Ecology s public participation process. Implementing the groundwater monitoring plan Significant Developments/ Changes in the CAP. Comply with the provisions of the Materials Commission authorization for entry into a consent Management Plan (MMP) for remnant decree for implementation of a Cleanup Action Plan contamination. (CAP) will be requested on 7/21/16. The consent decree is a legal agreement to begin long-term Vacate an existing covenant and consent decree. monitoring at the former Kaiser aluminum smelter. File a new covenant and consent decree. Ecology will initiate a 30-day public comment period beginning on August 4, Upon entry of the consent decree in Pierce County Superior Court, Port staff will initiate long-term monitoring and the MMP. No additional authorizations have been requested since the last report. The total project cost including all stages is estimated at $10,802,930. Project costs are partially offset by MTCA grant reimbursements, of which $2,634,000 has been received to date. 13

16 Kaiser Remediation Agreed Order DE-5698 Costs to implement the consent decree will begin in 2016 and are included in the environmental operating expenses. Costs for future years will be included in the associated future annual operating budget and will be reflected in the five year plan of finance. The Capital Improvement Plan allocates $247,000 through 2020 (MID ). The MMP requires Ecology approval for larger, nonroutine construction projects which will substantially disturb remnant contamination. This approval process may increase costs and cause schedule delays for a future development action. 14

17 Marine View Drive Structures Demolition Project MID No: : $706,340 Close Out Current Estimate: $658,295 Cost to Date: $514,764 Start: 12/20/2013 Schedule Completion: 12/31/2015 Project Manager: Pedro Reyes Schedule: On or Ahead Demo 6 structures Significant Developments/ Changes The original project was to demo four structures then two additional structures were added to the original scope. The contract was extended due to severe erosion that occurred shortly after removal of the structures. The contract was also extended under an emergency authorization to prevent further erosion of the bank. The estimated cost is currently $701,195, which covers 100% level design and environmental permitting, and the demolition. Additional land acquisition costs are not included in this project authorization. The mid-year Capital Improvement Plan allocates $1,052,000. This is the final report. No new authorizations All work is complete. 15

18 Mouth of the Hylebos Project MID Nos: , , , , , : $2,230,000 Long Term Monitoring RI/FS Current Estimate: $2,230,000 Cost to Date: $1,027,985 Start: 6/20/2013 Schedule Completion: 12/31/2017 Project Manager: Rob Healy Schedule: On or Ahead Specific 2015 through 2017 tasks include: Issuance of quarterly reports. Significant Developments/ Changes The OMMPs for segments 3 through 5, and Slip 1 have been approved. Approval of Pier 24 & 25 OMMP is anticipated shortly. With the approval of the OMMPs bulk sediment sampling will begin next month. Long-term monitoring at Slip 1 and Piers 24 & 25 will also begin in Initial Project, $200,000, June 20, Increase, $325,000, September 18, Increase, $1,705,000, February 19, Work toward resolution of cost overrun claims for previous remedial actions. Work toward certification of completion of construction for tasks previously accomplished. Revisions to the draft OMMPs at Slip 1, Piers 24 & 25, and Segments 3 through 5 of the Waterway. Implementation of long-term monitoring at Slip 1, Piers 24 & 25, and Segments 3 through 5 of the Waterway. Monitor the design of American Construction s habitat area. Storm water source control monitoring on Port properties adjacent to the Hylebos. Estimated cost is currently $2,230,000 which will cover at a minimum long-term monitoring through 2017 at Mouth of Hylebos Segments 3, 4, and 5, Slip 1, and Piers 24 &

19 Mouth of the Hylebos The Capital Improvement Plan allocates $4,467,000 through This includes estimated potential monitoring costs beyond Next steps for the project depend on results of the upcoming bulk sediment sampling. If concentrations are above sediment quality objectives the remedy may be deemed a failure and more active remedial actions could be required. 17

20 Port Parcel 2 Petroleum Contamination Agreed Order DE-9835 Project MID No: : $1,647,500 Preliminary Design Current Estimate: $1,647,500 Cost to Date: $1,278,189 Start: 12/3/2007 Schedule Completion: 12/31/2017 Project Manager: Rob Healy Schedule: Delayed The project scope includes completing an RI/FS for the site, assisting ecology in preparing a cleanup action plan, and reimbursing Ecology for their oversight costs. Significant Developments/ Changes The remedial investigation report was submitted earlier this year. Ecology comments have been received and are being addressed. The feasibility study will begin later this year, to be submitted to ecology by the end of the year. FS to be submitted by end of DCAP to be prepared and submitted by the middle The last Commission increase in authorization was June 5, 2014 to complete the Agreed Order requirements. Estimated cost is currently $1,647,500 which will cover the scope tasks presented above. The Capital Improvement Plan allocates $466,000 through 2020 to complete the RI/FS/DCAP. $4,900,000 is allocated to complete the remedy. The petroleum contamination is present on the north end of the PSE property development site. PSE development is occurring on the south end of the site. Care is needed during design and construction to minimize the potential for disturbing the petroleum contamination. 18

21 PQ Contamination 1202 Taylor Way Project MID No: : $837,000 Preliminary Design Current Estimate: $837,000 Cost to Date: $392,833 Start: 4/1/2007 Schedule Completion: 12/31/2016 Project Manager: Scott Hooton Schedule: Delayed Looking forward, the scope of this effort consists of: PQ and the Port will collaborate in the development of a RI/FS and CAP. Significant Developments/ Changes PQ will pay 60% and the Port will pay 40% of future shared costs PQ entered into the Interim Cost Sharing Agreement on March 17, The Port and PQ have begun discussions on the scope, schedule and budget for completing a feasibility study and revising the remedial investigation report Expenditures in the CIP budget are programmed to occur before These costs will be rolled forward into 2018, and site remediation will likely occur during 2019 or later. A more formal project schedule will be negotiated with PQ under the Cost Sharing Agreement. Project cost is currently $837,000, which is expected to be sufficient to complete the authorized scope of work. Project costs are partially offset with reimbursements from PQ under the Interim Cost Sharing Agreement; PQ remittances to date total $280,000. The Capital Improvement Plan allocates $444,167 through

22 PQ Contamination 1202 Taylor Way Commission authorized Port staff to enter into the agreement with PQ to complete a Remedial Investigation, Feasibility Study (RI/FS) and draft Cleanup Action Plan (CAP) on March 17, of work is subject to change depending on agency direction. Monies received from PQ are potentially subject to reallocation under the agreement. 20

23 Arkema RI/FS/CAP Agreed Order DE & 2920 Taylor Way Project MID No: : $3,440,741 Preliminary Design Current Estimate: $3,440,741 Cost to Date: $3,232,173 Start: 5/31/2007 Schedule Completion: 2/12/2016 Project Manager: Scott Hooton Schedule: On or Ahead Looking forward, the scope of this effort is anticipated to include: FS Data Gap Investigation Significant Developments/ Changes Treatability Studies Technology Screening and Alternative Preparation of a data gap workplan for the Evaluation Feasibility Study is underway. Upon Ecology Interim Action(s) approval, Commission authorization will be FS Reporting requested to increase the Project to include workplan implementation costs. Implementation of the data gap workplan is planned for 2016 and The Feasibility Study (FS) is scheduled for completion in Estimated cost is currently $3,440,741 which is expected to be sufficient to complete the FS Data Gap workplan. Additional funding will be required to complete the items in the above-listed scope. Project costs are partially offset by a $3,115,807 MTCA grant, of which $1,366,626 has been paid out No additional authorizations have been requested to the Port. since the last report. 21

24 Arkema RI/FS/CAP Agreed Order DE & 2920 Taylor Way The Capital Improvement Plan allocates $4,485,000, through Selection of a cost-effective remedial approach that is compatible with an undefined future industrial land use. 22

25 Port Parcel 1B (EBC) Agreed Order DE-9553 Project MID No: : $1,438,000 RI/FS Current Estimate: $1,438,000 Cost to Date: $1,318,432 Start: 1/17/2013 Schedule Completion: 12/30/2016 Project Manager: Rob Healy Schedule: Delayed The project scope includes completing an RI/FS and DCAP for the site, assisting ecology in preparing a cleanup action plan, and reimbursing Ecology for their oversight costs. Significant Developments/ Changes The final remedial investigation and feasibility study was approved by Ecology on March 3, The draft cleanup action plan is under Ecology review. Upon approval, the next step is to negotiate a Consent Decree with Ecology to implement remedy. Ecology approval of the draft cleanup action plan is anticipated in August Commission authorization of the negotiated Consent Decree is anticipated by the end of The last Commission approval was April 22, 2014 providing project authorization to complete the Agreed Order requirements. Project cost is currently $1,438,000 which will cover the scope tasks presented above. The Capital Improvement Plan allocates $1,223,000 through 2020 to complete the RI/FS and DCAP, and implement the remedy. Encountering unanticipated conditions during remedy implementation. 23

26 Arkema North Boundary Allocation Report Project MID No: : $337,400 Preliminary Design Current Estimate: $337,400 Cost to Date: $188,246 Start: 3/12/2014 Schedule Completion: 3/31/2017 Project Manager: Scott Hooton Schedule: Delayed Looking forward, the scope of this effort consists of: Technical review of USG deliverables to Ecology NBA Allocation Report Significant Developments/ Changes NBA Legal Strategy memo from counsel Mediation agreement negotiation USG and the Port have exchanged memos summarizing information that would form the technical basis for allocating costs for the remediation of the North Boundary Area (NBA). Face-to-face meetings and a series of telephone conference calls have not resulted in any substantive progress in resolving the Port s $195,000 indemnification claim. The allocation report will be completed during late 2016 and mediation agreement discussions are expected to be concluded in No additional authorizations have been requested since the last report. Estimated cost is currently $337,000, and is sufficient to complete the above-listed scope. The Capital Improvement Plan allocates $856,000, through Resolving the Port s indemnity claim may not be feasible without filing suit against Thermafiber and USG. It may be advisable to remediate the NBA so that sufficient monetary damages accrue to the Port to justify the expense of contested litigation. This would allow for the redevelopment of a portion of the Arkema property and a final resolution of the Port s claim 24

27 Port of Tacoma Road Reconstruction ILA with City of Tacoma Project Project MID No: s: $866K original ILA + $180K amendment for additional scope Completed Current Estimate $11,800,000 w/ additional scope: Cost to Date: $11,800,000 Start: 5/4/2015 Schedule Completion: 7/31/2016 Project Manager: Evette Mason Original Schedule: Completed Replace surface pavements with concrete between the curb lines on Port of Tacoma Road from E 11th St to Marshall Way (approx. 7,300 LF). Install concrete Significant Developments/ Changes sidewalk where missing; Restripe per original channelization; Install permanent signals at WUT (Lot F) and Lincoln Ave; Install conduit for future ITS. In January 2016, Transportation Improvement Board provided additional funding for this project from SR509 grade separation to Marshall. City of Tacoma provided an additional $662,000 and Port Commission approved an ILA amendment for an additional $180,000 for the expanded scope of work. Final project cost is $11,800,000. Port s final payment made July 15, Per the COT Project Manager, project is 99 percent complete with two punch list items: Removal of old curb and complete expansion joint. This is the final report. Commission ILA Amendment #1 March 17, Budget The Port s contributions were incurred as nonoperating expenses. None project is complete. 25

28 Saltchuk Aquatic Mitigation Site Preliminary Design Project MID No: : $745,000 Preliminary Design Current Estimate: $660,435 Cost to Date: $660,435 Start: 10/13/2013 Schedule Completion: 1/1/2016 Project Manager: Stanley Ryter Schedule: Delayed Design and construct an aquatic mitigation site and shore restoration. Significant Developments/ Changes Project on hold during entire reporting period. Project may be revived to include only shoreline restoration under a new commission authorization. Project sponsor investigating feasibility of purchasing one remaining shoreline parcel in Q3 of No new authorizations since the last report. $660,435 has been spent to date to cover Basis of Design and permit package. Project on hold as sponsor re-scopes the project. The Capital Improvement Plan allocates $1, through Project on hold 26

29 Shoreline Stabilization Project MID Nos: , , , : $776,760 Close Out Current Estimate: $520,385 Cost to Date: $492,533 Start: 9/9/2013 Schedule Completion: 1/18/2016 Project Manager: Pedro Reyes Schedule: Completed Restore the shoreline that has washed away at APMT, OCT, TOTE, and Husky. Significant Developments/ Changes The parcel at East F St was sold prior to the completion of the design phase. The work at EBC was removed due to slag along the shoreline that must be removed prior to restoration and will be completed as part of a larger interim action plan. This is the final report. No new authorizations Project cost is $492,533, which is less than the current estimate and covers 100% level design and construction. The Capital Improvement Plan allocated $776,760. Project is complete 27

30 Roof Replacement at 401 Alexander Ave Bldg 9407 Project MID No: : $4,935,000 Construction Current Estimate: $4,860,060 Cost to Date: $4,076,419 Start: 12/15/2013 Schedule Completion: 12/31/2016 Project Manager: Carol Rhodes Schedule: On or Ahead Bldg 9405 at the EBC identified to need extensive roof and structure repairs and replacement as well as electrical and fire protection system upgrades. Work is being planned to provide a 20-year useful life expectancy for the building. Significant Developments/ Changes Roof and structural repairs complete. Electrical upgrades ongoing. Project on schedule Project cost is currently $4,860,060, which will cover all project costs. The Capital Improvement Plan allocates $4,860,060, No new authorizations. through None. 28

31 PCT Electrical Testing and Repair Project MID No: : $750,000 Close Out Current Estimate: $425,000 Cost to Date: $410,700 Start: 10/27/2014 Schedule Completion: 6/30/2016 Project Manager: Stanley Ryter Schedule: On or Ahead Electrical testing and troubleshooting at Pierce County Terminal. Replacement of power factor correction units and addition of power quality metering. Significant Developments/ Changes Power quality metering installed. Maintenance and Engineer have ability to view data from desktop computer. Project physically complete. Estimated cost at completion is currently $425,000. System training complete June 30th. All physical work complete. No new authorizations in this reporting period. The Capital Improvement Plan allocates $750,000 through System needs to operate through next peak season to confirm all issues are addressed. 29

32 Repair to Bldgs at 2602 & 2608 Port of Tacoma Rd Project MID No: : $408,000 Close Out Current Estimate: $389,955 Cost to Date: $389,955 Start: 2/15/2015 Schedule Completion: 4/30/2016 Project Manager: Carol Rhodes Schedule: Completed New emulsion coating on barrel roof of Replace canopies on both buildings, repair water damage within office space of Significant Developments/ Changes Project complete. Total project cost at completion is $389,955, which is below the original estimate. This is the final report. The Capital Improvement Plan allocates $408,000 through No new authorizations. None. 30

33 Parcel 103 Steam Plant Property Cleanup Project MID No: : $725,163 Preliminary Design Current Estimate: $725,163 Cost to Date: $512,490 Start: 2/12/2016 Schedule Completion: 12/31/2017 Project Manager: Rob Healy Schedule: Delayed Collection of additional soil and groundwater data to fill data gaps to support completion of the RI. Completion Remedial Investigation, Feasibility Report and Draft Cleanup Action Plan under Ecology s Significant Developments/ Changes Voluntary Cleanup Program (VCP). Conduct settlement discussions with City for their Two groundwater monitoring events have been portion of cleanup costs. completed and based on these results Settlement discussions with the City will re-commence. Project has been slowed due to reduced staff levels in Environmental Remediation. An application to the voluntary cleanup program is on hold. The target date for completed a draft cleanup action plan is tentatively the end of Cost is currently $725,163 to cover the above scope. The current estimate is unchanged from the original. The Capital Improvement Plan allocates $222,000 through 2020 for site investigation activities. Previous Commission 3/19/15 The Port and City may not be able to reach a settlement on past costs. Ecology preferred remedy may interfere with tenant or development action. 31

34 Surface and Tamp Rail Project MID No: : $484,440 Close Out Current Estimate: $458,672 Cost to Date: $458,672 Start: 12/7/2015 Schedule Completion: 1/22/2016 Project Manager: Jan Shawyer Schedule: Completed Correcting rail grade settlement along the direction of travel Correcting rail alignment horizontally between adjacent rails Significant Developments/ Changes Correcting rail alignment vertically between adjacent rails With one bidder only, additional funds were requested of Commission to perform the work. This is the final report. Total Project cost of $458,672 covered all staff, Maintenance and construction tasks. No new authorizations. The Capital Improvement Plan allocates $484,440 through None. 32

35 Replace SIM Rail Switches Project MID No: : $935,000 Close Out Current Estimate: $604,606 Cost to Date: $604,606 Start: 12/6/2015 Schedule Completion: 1/13/2016 Project Manager: Jan Shawyer Schedule: Completed Procurement of long lead components and materials to support schedule Significant Developments/ Changes Replace 5 turnouts complete with switches and The work was performed using 3 day workweek of 10 hour days for Saturday, Sunday and Monday in order to accommodate restrictions from Tacoma Rail, PSR and Union Pacific. This is the final report. other components Replace ballast and ties and tamp Total cost of $604,606 covered all staff, design, procurement, disposal and construction tasks and is less than the original estimate. No new authorizations. The Capital Improvement Plan allocated $935,000 through None. 33

36 Roof Replacement at 3701 Taylor Way Project MID No: : $1,754,000 Completed Current Estimate: $1,443,921 Cost to Date: $1,392,286 Start: 9/15/2013 Schedule Completion: 5/6/2016 Project Manager: Carol Rhodes Schedule: Completed The building is in need of extensive roof repairs and replacement. Work includes replacement of roof, structural repairs and roof anchors for maintenance access. Significant Developments/ Changes Project complete The total cost to date is $1,392,286, which is less than the estimated cost. This is the final report. The Capital Improvement Plan allocates $1,754,000 through No new authorizations None 34

37 Alexander Avenue Wetland Project MID No: : $328,000 Close Out Current Estimate: $328,000 Cost to Date: $317,442 Start: 5/7/2013 Schedule Completion: 6/20/2016 Project Manager: David Myers Schedule: Completed Re-establishment of a 2 acre critical area as part of a settlement with the EPA and DOJ. Significant Developments/ Changes The project is complete and has met the first two year bench marks as set forth in the settlement. The total cost is $317,442, which is less than the current estimate. This is the final report. The Capital Improvement Plan allocates $328,000 through Additional project authorization of $28,000 was obtained in May None. 35

38 Maytown Oversight Project MID No: : $470,000 Construction Current Estimate: $470,000 Cost to Date: $272,556 Start: 9/19/2013 Schedule Completion: 9/28/2018 Project Manager: Thais Howard Schedule: On or Ahead This project is for oversight activities associated with the Maytown Mine site. The Port is maintaining the mining permit viability to preserve the property s highest and best use for the purpose of sale. Significant Developments/ Changes The property has not received any purchase offers. Port staff continue to market the property and have conducted several site visits for potential buyers. Project cost is currently $470,000, which will cover the current scope of work. This project will continue until the property is sold. The Capital Improvement Plan allocates $470,000 through Project authorization for an additional $170,000 was obtained in March 2016 for additional costs associated with preserving the permit. of work and additional budget may be required if property is not sold. 36

39 Port of Tacoma Executive s January June 2016 No Serial No. POT POT POT POT POT POT POT POT POT POT POT POT POT POT POT POT POT POT Project Title Electronic Stormwater Inspection Program Brown & Haley Cleanup Investigation Trident Bldg 592 Electrical Service Replacement Trident Bldg 592 Electrical Service Replacement Parcel 94 Feasibility Study 2016 Arkema Site Vegetation Management Ecology Puget Sound Maritime Air Emission Inventory Grant Marc Street Easement and Stormwater Review 2000 Taylor Way Bldg Painting Demo 1202 POT Rd (Key Bank Bldg) Tap water lead testing Bull Rail Replacement on Piers 24 & Taylor Way Bldg Painting PSPG 2015 Cameras & TWIC Readers Port Survey Control Update 2016 Tap Water Lead Testing Public Presentation Training Marc Street Soil Sampling TOTALS 37 $ this request $25,000 $125,000 $26,000 $89,000 $29,700 $75,000 $50,000 $20,000 $106,000 $182,000 $7,500 $137,000 $153,000 $40,000 $50,000 $7,500 $4,500 $5,000 $1,132,200

Port of Tacoma Semi-Annual Project Progress Report

Port of Tacoma Semi-Annual Project Progress Report Port of Tacoma Semi-Annual Project Progress Report Port of Tacoma Leadership Port of Tacoma Commission Connie Bacon Second Assistant Secretary John Wolfe Chief Executive Officer Don Johnson First Assistant

More information

Port of Tacoma Semi-Annual Project Progress Report

Port of Tacoma Semi-Annual Project Progress Report Port of Tacoma Semi-Annual Project Progress Report Port of Tacoma Leadership Port of Tacoma Commission Don Johnson Secretary John Wolfe Chief Executive Officer Dick Marzano Second Assistant Secretary John

More information

COMMISSION AGENDA Item No:

COMMISSION AGENDA Item No: COMMISSION AGENDA Item No: 4A Meeting: 4/19/18 DATE: April 4, 2018 TO: FROM: Port Commission John Wolfe, Chief Executive Officer Sponsor: Jason Jordan, Director, Environmental and Planning Services Project

More information

THE NORTHWEST SEAPORT ALLIANCE MEMORANDUM

THE NORTHWEST SEAPORT ALLIANCE MEMORANDUM THE NORTHWEST SEAPORT ALLIANCE MEMORANDUM MANAGING MEMBERS Item No. 5A BRIEFING ITEM Date of Meeting DATE: March 21, 2017 TO: FROM: SUBJECT: Managing Members, John Wolfe, Chief Executive Officer Project

More information

THE NORTHWEST SEAPORT ALLIANCE MEMORANDUM

THE NORTHWEST SEAPORT ALLIANCE MEMORANDUM THE NORTHWEST SEAPORT ALLIANCE MEMORANDUM MANAGING MEMBERS Item No. 4A ACTION ITEM Date of Meeting DATE: April 18, 2017 TO: FROM: Managing Members, John Wolfe, Chief Executive Officer Project Managers:

More information

Resolution PT

Resolution PT Item No.: 6E_Attach Date of Meeting: February 22, 2018 Resolution 2018-01-PT Special Commission Study Session February 5, 2013 A RESOLUTION amending and superseding Resolution No. 2017-01-PT and all prior

More information

Port of Olympia 2018 Capital Investment Plan by Line of Business 11/27/2017 Data. Type Line of Business '2018 '2019 '2020 '2021 '2022 Sum of Total

Port of Olympia 2018 Capital Investment Plan by Line of Business 11/27/2017 Data. Type Line of Business '2018 '2019 '2020 '2021 '2022 Sum of Total Port of Olympia 2018 Capital Investment Plan by Line of Business 11/27/2017 Data Type Line of Business '2018 '2019 '2020 '2021 '2022 Sum of Total Carry Forward Admin/IT $ 80,762 $ - $ - $ - $ - $ 80,762

More information

Comprehensive Annual Financial Report. Port of Tacoma, Washington As of and for the years ended December 31, 2016 and 2015

Comprehensive Annual Financial Report. Port of Tacoma, Washington As of and for the years ended December 31, 2016 and 2015 Comprehensive Annual Financial Report Port of Tacoma, Washington As of and for the years ended December 31, 2016 and 2015 COMPREHENSIVE ANNUAL FINANCIAL REPORT As of and for the years ended December 31,

More information

North Basin - EPA Administrative Settlement Agreement. Board of Directors July 20, 2016

North Basin - EPA Administrative Settlement Agreement. Board of Directors July 20, 2016 North Basin - EPA Administrative Settlement Agreement Board of Directors July 20, 2016 1 Statement of Work Objective The Settlement Agreement requires OCWD to conduct a Remedial Investigation and Feasibility

More information

Date of Meeting: November 7, 2017 Item No.: 4D_Supp PROJECT AUTHORIZATION FOR PARCEL 77 AUTO TERMINAL DEVELOPMENT

Date of Meeting: November 7, 2017 Item No.: 4D_Supp PROJECT AUTHORIZATION FOR PARCEL 77 AUTO TERMINAL DEVELOPMENT Date of Meeting: November 7, 2017 Item No.: 4D_Supp PROJECT AUTHORIZATION FOR PARCEL 77 AUTO TERMINAL DEVELOPMENT Project Authorization As referenced in NWSA Resolution No. 2016-04, Exhibit A, Delegation

More information

Environmental Programs Director. Planning and Development Director. Economic Development Specialist

Environmental Programs Director. Planning and Development Director. Economic Development Specialist MINUTES OF THE PORT OF BELLINGHAM COMMISSION MEETING HELD TUESDAY, JUNE 17, 2014 HARBOR CENTER BUILDING CONFERENCE ROOM 1801 ROEDER AVENUE, BELLINGHAM, WASHINGTON Present: Commissioners: Michael McAuley

More information

AGREEMENT Between The Northwest Seaport Alliance and Seattle City Light For Terminal 5 Modernization. Recitals

AGREEMENT Between The Northwest Seaport Alliance and Seattle City Light For Terminal 5 Modernization. Recitals AGREEMENT Between The Northwest Seaport Alliance and Seattle City Light For Terminal 5 Modernization This Agreement is made and entered into this day of, 2016, by and between the City of Seattle, a municipal

More information

PURCHASE AND SALE AGREEMENT. Among. GEORGIA-PACIFIC WEST, INC., an Oregon Corporation. GEORGIA-PACIFIC CORPORATION, a Georgia Corporation.

PURCHASE AND SALE AGREEMENT. Among. GEORGIA-PACIFIC WEST, INC., an Oregon Corporation. GEORGIA-PACIFIC CORPORATION, a Georgia Corporation. PURCHASE AND SALE AGREEMENT Among GEORGIA-PACIFIC WEST, INC., an Oregon Corporation GEORGIA-PACIFIC CORPORATION, a Georgia Corporation and THE PORT OF BELLINGHAM, a Washington municipal corporation Dated

More information

Port of Olympia Thurston County

Port of Olympia Thurston County Washington State Auditor s Office Financial Statements and Federal Single Audit Report Port of Olympia Thurston County Audit Period January 1, 2007 through December 31, 2007 Report No. 75377 Issue Date

More information

Date: December 5, 2017 To: Budget Committee From: Deputy City Manager Cluster B and Acting Chief Financial Officer Wards: Ward 30

Date: December 5, 2017 To: Budget Committee From: Deputy City Manager Cluster B and Acting Chief Financial Officer Wards: Ward 30 EX31.2w REPORT FOR ACTION Port Lands Flood Protection Date: December 5, 2017 To: Budget Committee From: Deputy City Manager Cluster B and Acting Chief Financial Officer Wards: Ward 30 SUMMARY This report

More information

KITSAP COUNTY DEPARTMENT OF COMMUNITY DEVELOPMENT

KITSAP COUNTY DEPARTMENT OF COMMUNITY DEVELOPMENT KITSAP COUNTY DEPARTMENT OF COMMUNITY DEVELOPMENT 614 DIVISION STREET MS-36, PORT ORCHARD WASHINGTON 98366-4682 Larry Keeton, Director (360) 337-7181 FAX (360) 337-4925 HOME PAGE - www.kitsapgov.com/dcd/

More information

Port of Seattle Commission. Delegation of Responsibility and Authority to the Executive Director. As Amended June 13, 2017

Port of Seattle Commission. Delegation of Responsibility and Authority to the Executive Director. As Amended June 13, 2017 Port of Seattle Commission Delegation of Responsibility and Authority to the Executive Director As Amended June 13, 2017 Document last updated June 20, 2017 Contents Preamble... 5 Section I: Objectives

More information

Statement of Policy. Milwaukee Metropolitan Sewerage District s Private Property Inflow and Infiltration Reduction Program.

Statement of Policy. Milwaukee Metropolitan Sewerage District s Private Property Inflow and Infiltration Reduction Program. Milwaukee Metropolitan Sewerage District s 2011-2020 Private Property Inflow and Infiltration Reduction Program Introduction Infiltration is the quantity of water entering a sewer system through such sources

More information

Marin County Flood Control and Water Conservation District FLOOD CONTROL ZONE 5 ADVISORY BOARD MAY 15, 2014 STAFF REPORT

Marin County Flood Control and Water Conservation District FLOOD CONTROL ZONE 5 ADVISORY BOARD MAY 15, 2014 STAFF REPORT FLOOD CONTROL ZONE 5 ADVISORY BOARD MAY 15, 2014 STAFF REPORT Item 1. Approval of Meeting Minutes for February 10, 2014 Recommended Action: Approve minutes. Item 2. Open Time for Items not on the Agenda

More information

SEMS-RM DOCID #

SEMS-RM DOCID # I. PURPOSE U.S. Environmental Protection Agency and Nevada Division of Environmental Protection National Priorities List Deferral Agreement Anaconda Copper Mine Site, Lyon County, Nevada SEMS-RM DOCID

More information

INTERAGENCY COORDINATION AGREEMENT ON WETLAND MITIGATION BANKING WITHIN THE REGULATORY BOUNDARIES OF CHICAGO DISTRICT, CORPS OF ENGINEERS January 1997

INTERAGENCY COORDINATION AGREEMENT ON WETLAND MITIGATION BANKING WITHIN THE REGULATORY BOUNDARIES OF CHICAGO DISTRICT, CORPS OF ENGINEERS January 1997 INTERAGENCY COORDINATION AGREEMENT ON WETLAND MITIGATION BANKING WITHIN THE REGULATORY BOUNDARIES OF CHICAGO DISTRICT, CORPS OF ENGINEERS January 1997 SECTION 1, PURPOSE The Chicago District of the U.S.

More information

DEPARTMENT OF THE ARMY OFFICE OF THE CHIEF OF ENGINEERS WASHINGTON, D.C

DEPARTMENT OF THE ARMY OFFICE OF THE CHIEF OF ENGINEERS WASHINGTON, D.C .t DEPARTMENT OF THE ARMY OFFICE OF THE CHIEF OF ENGINEERS WASHINGTON, D.C. 20314-1000 REPLY TO A TTENTION OF: CECW-PE (l0-1-7a) 1 3 OCT 199B SUBJECT: Tampa Harbor, Big Bend Channel, Florida THE SECRETARY

More information

CHAPTER House Bill No. 1123

CHAPTER House Bill No. 1123 CHAPTER 2003-173 House Bill No. 1123 An act relating to site rehabilitation of contaminated sites; creating s. 376.30701, F.S.; extending application of risk-based corrective action principles to all contaminated

More information

NAPA COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT Board Agenda Letter

NAPA COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT Board Agenda Letter Agenda Date: 6/7/2016 Agenda Placement: 8A Set Time: 1:30 PM PUBLIC HEARING Estimated Report Time: 20 Minutes NAPA COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT Board Agenda Letter TO: FROM: Board

More information

Proposed Planning Commission Work Program ( )

Proposed Planning Commission Work Program ( ) Proposed Planning Commission Work Program (2017-2019) The Planning Commission Work Program contains projects and planning activities that are slated for completion in or substantial progress during the

More information

Agreement Between the Port of Seattle and the Puget Sound Clean Air Agency Regarding Air Quality at Terminal 5

Agreement Between the Port of Seattle and the Puget Sound Clean Air Agency Regarding Air Quality at Terminal 5 Agreement Between the Port of Seattle and the Puget Sound Clean Air Agency Regarding Air Quality at Terminal 5 This Letter of Agreement ( Agreement ) is made by and among the Port of Seattle, a Washington

More information

ELTs as a Strategic Alternative to Traditional Environmental Remediation

ELTs as a Strategic Alternative to Traditional Environmental Remediation ELTs as a Strategic Alternative to Traditional Environmental Remediation Integrating Environmental Liabilities RemTech 2015 Banff, AB October 14, 2015 Real Estate Assets Assets Liabilities Presented by:

More information

GOAL 1: Protect coastal resources and human life and limit public expenditures in areas that are subject to destruction by natural disasters..

GOAL 1: Protect coastal resources and human life and limit public expenditures in areas that are subject to destruction by natural disasters.. GOALS, OBJECTIVES, AND POLICIES GOAL 1: Protect coastal resources and human life and limit public expenditures in areas that are subject to destruction by natural disasters.. OBJECTIVE 1.1: The City will

More information

MAINE TURNPIKE AUTHORITY. Project Development Process

MAINE TURNPIKE AUTHORITY. Project Development Process MAINE TURNPIKE AUTHORITY Project Development Process A Milestone Guide for the MTA, Consultant, & Partners to Build a MTA Project 10/20/16 1 P a g e INTRODUCTION: BACKGROUND AND APPLICABILITY The intent

More information

Updated Planning Commission Work Program ( )

Updated Planning Commission Work Program ( ) Updated Planning Commission Work Program (2017-2019) The Planning Commission Work Program contains projects and planning activities that are slated for completion in or substantial progress during the

More information

IMPLEMENTATION A. INTRODUCTION C H A P T E R

IMPLEMENTATION A. INTRODUCTION C H A P T E R C H A P T E R 11 IMPLEMENTATION A. INTRODUCTION This chapter addresses implementation of the General Plan. The Plan s seven elements include 206 individual actions. 1 Many are already underway or are on-going.

More information

Benefits and Challenges of Port-Sponsored Mitigation Banks

Benefits and Challenges of Port-Sponsored Mitigation Banks Benefits and Challenges of Port-Sponsored Mitigation Banks Presented by Dan Berlin, PWS October 10, 2018 1 Presentation Outline Mitigation Overview Mitigation Banking Process Port-Led Mitigation Banking

More information

DEPARTMENT OF THE ARMY U. S. Army Corps of Engineers CECW-CP Washington, DC APPENDIX F CONTINUING AUTHORITIES PROGRAM TABLE OF CONTENTS

DEPARTMENT OF THE ARMY U. S. Army Corps of Engineers CECW-CP Washington, DC APPENDIX F CONTINUING AUTHORITIES PROGRAM TABLE OF CONTENTS ER-1105-2-100 DEPARTMENT OF THE ARMY U. S. Army Corps of Engineers CECW-CP Washington, DC 20314-1000 Regulation 31 January 2007 ER 1105-2-100 APPENDIX F CONTINUING AUTHORITIES PROGRAM TABLE OF CONTENTS

More information

DEPARTMENT OF THE ARMY OFFICE OF THE CHIEF OF ENGINEERS WASHINGTON, D.C

DEPARTMENT OF THE ARMY OFFICE OF THE CHIEF OF ENGINEERS WASHINGTON, D.C DEPARTMENT OF THE ARMY OFFICE OF THE CHIEF OF ENGINEERS WASHINGTON, D.C. 20310-2600 REPLY TO ATTENTION OF CECW-P (1105-2-10a) 0 2 JUN 2003 THE SECRETARY OF THE ARMY 1. I submit for transmission to Congress

More information

Public Notice. Activity: Fort Worth District Mitigation Banks. Date: January 24, 2019

Public Notice. Activity: Fort Worth District Mitigation Banks. Date: January 24, 2019 Public Notice Number: CESWF-18-MITB Activity: Fort Worth District Mitigation Banks Date: January 24, 2019 Purpose The purpose of this Public Notice is to inform you of mitigation banking guidelines being

More information

Public Notice. Number: CESWF-12-MITB Activity: Fort Worth District Mitigation Banks Date: June 27, 2016

Public Notice. Number: CESWF-12-MITB Activity: Fort Worth District Mitigation Banks Date: June 27, 2016 Public Notice Number: CESWF-12-MITB Activity: Fort Worth District Mitigation Banks Date: June 27, 2016 Purpose The purpose of this Public Notice is to inform you of mitigation banking guidelines being

More information

COMMUNITY REDEVELOPMENT AGENCY OF THE CITY OF LOS ANGELES, CA M E M O R A N D U M ROBERT R. OVROM, CHIEF EXECUTIVE OFFICER

COMMUNITY REDEVELOPMENT AGENCY OF THE CITY OF LOS ANGELES, CA M E M O R A N D U M ROBERT R. OVROM, CHIEF EXECUTIVE OFFICER COMMUNITY REDEVELOPMENT AGENCY OF THE CITY OF LOS ANGELES, CA M E M O R A N D U M 10 DATE: DECEMBER 16, 2004 CN3320 TO: FROM: RESPONSIBLE PARITES: SUBJECT: AGENCY COMMISSIONERS ROBERT R. OVROM, CHIEF EXECUTIVE

More information

Recommendation to the Board Final Action

Recommendation to the Board Final Action MOTION NO. M2015-78 Construction Services for the Point Defiance Bypass Project MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 8/13/15 8/27/15 Recommendation to the

More information

Port of Tacoma 2019 Budget

Port of Tacoma 2019 Budget Port of Tacoma 2019 Budget Ships in the Blair Waterway with Mt. Rainier in the distance Statutory Budget and Tax Levy adopted: November 29, 2018 The Port of Tacoma has been a recipient of the Government

More information

DEVELOPER EXTENSION AGREEMENT

DEVELOPER EXTENSION AGREEMENT DEVELOPER EXTENSION AGREEMENT SILVER LAKE WATER DISTRICT APPLICATION AND AGREEMENT TO CONSTRUCT EXTENSION TO DISTRICT SYSTEM Project: Developer: The undersigned, Developer (also referred to as Owner )

More information

BERKELEY UNIFIED SCHOOL DISTRICT

BERKELEY UNIFIED SCHOOL DISTRICT BERKELEY UNIFIED SCHOOL DISTRICT TO: Javetta Cleveland and Neil Smith, Co-Superintendents FROM: Lew Jones, Director of Facilities DATE: June 26, 2013 SUBJECT: Approval of the 2013/14 Measure H Annual Plan

More information

Date of Meeting: 04/04/17 Item No.: 5A_Supp UPDATES TO THE NORTHWEST SEAPORT ALLIANCE CHARTER

Date of Meeting: 04/04/17 Item No.: 5A_Supp UPDATES TO THE NORTHWEST SEAPORT ALLIANCE CHARTER Date of Meeting: 04/04/17 Item No.: 5A_Supp UPDATES TO THE NORTHWEST SEAPORT ALLIANCE CHARTER 1 Updates to The Northwest Seaport Alliance Charter BRIEFING REQUESTED: This is a briefing of the proposed

More information

Santa Clara Valley Water District

Santa Clara Valley Water District FINAL AUDIT REPORT Santa Clara Valley Water District Clean, Safe Creeks and Natural Flood Protection Program June 15, 2012 Prepared by: Moss Adams LLP 999 Third Avenue, Suite 2800 Seattle, Washington 98104

More information

The Northwest Seaport Alliance. Financial Report December 31, 2016

The Northwest Seaport Alliance. Financial Report December 31, 2016 Financial Report December 31, 2016 The Northwest Seaport Alliance Financial Report For The Year Ended December 31, 2016 Contents Independent auditor s report 1-2 Management s discussion and analysis 3-8

More information

Frequently Asked Questions about the PCILF Program

Frequently Asked Questions about the PCILF Program Frequently Asked Questions about the PCILF Program So, you want to use the PCILF Program? Here s what you need to know: 1. What is the PCILF Program? The Pierce County In-Lieu Fee (PCILF) Program is a

More information

GENERAL PROVISIONS I. WORK REQUIREMENTS

GENERAL PROVISIONS I. WORK REQUIREMENTS GENERAL PROVISIONS I. WORK REQUIREMENTS 1. Inspection The Permittee shall request initial inspection from the County at 408-573-2429 a minimum of twenty-four (24) hours prior to any work being performed.

More information

RESOLUTION NO. R Baseline Budget and Schedule, and Approve Gates 5 and 6 for the East Link Extension

RESOLUTION NO. R Baseline Budget and Schedule, and Approve Gates 5 and 6 for the East Link Extension RESOLUTION NO. R2015-04 Baseline and Schedule, and Approve Gates 5 and 6 for the East Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Board 04/23/15 Final Action Ahmad Fazel, DECM Executive

More information

MVMCC CAPITAL IMPROVEMENT PROGRAM (CIP) UPDATE AND ADOPTING A RESOLUTION APPROVING A MVMCC CAPITAL BUDGET ALLOCATION AMENDMENT

MVMCC CAPITAL IMPROVEMENT PROGRAM (CIP) UPDATE AND ADOPTING A RESOLUTION APPROVING A MVMCC CAPITAL BUDGET ALLOCATION AMENDMENT STAFF REPORT MEETING DATE: October 20, 2015 TO: FROM: City Council Cathy Capriola, Assistant City Manager Matt Greenberg, Park General Manager Tony Williams, Senior Civil Engineer 922 Machin Avenue Novato,

More information

77th OREGON LEGISLATIVE ASSEMBLY Regular Session. Enrolled. House Bill 2800 CHAPTER... AN ACT

77th OREGON LEGISLATIVE ASSEMBLY Regular Session. Enrolled. House Bill 2800 CHAPTER... AN ACT 77th OREGON LEGISLATIVE ASSEMBLY--2013 Regular Session Enrolled House Bill 2800 Sponsored by Representatives READ, BENTZ, Senators BEYER, STARR CHAPTER... AN ACT Relating to the Interstate 5 bridge replacement

More information

Briefing to Citizens of Canon City

Briefing to Citizens of Canon City Briefing to Citizens of Canon City Superfund Process Current Status What the 2014 RI/FS Settlement Agreement is What the 2014 RI/FS Settlement Agreement is not Public Participation Statement of Work (SOW)

More information

King County Flood Control District Flood Risk Reduction Work Program and Accomplishments

King County Flood Control District Flood Risk Reduction Work Program and Accomplishments King County Flood Control District Flood Risk Reduction Work Program and Accomplishments Brian Murray Water and Land Resources Division April 26, 2016 Department of Natural Resources and Parks Water and

More information

PERSONAL SERVICES AGREEMENT NO

PERSONAL SERVICES AGREEMENT NO 3D Attchment 1 PERSONAL SERVICES AGREEMENT NO. 070530 PROJECT: World Trade Center Tacoma Promotion 2017 CONSULTANT: World Trade Center Tacoma, 950 Pacific Ave., Suite 310, Tacoma, WA 98402 PROJECT MANAGER:

More information

Cancelled. Final Action

Cancelled. Final Action RESOLUTION NO. R2018-16 Baseline Budget and Schedule for the Lynnwood Link Extension MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 05/10/2018 05/24/2018 Cancelled

More information

TAX LEVY A. TAX AT A GLANCE B. TAX LEVY SOURCES VIII-1

TAX LEVY A. TAX AT A GLANCE B. TAX LEVY SOURCES VIII-1 A. TAX AT A GLANCE TAX LEVY The maximum allowable levy for 2018 is $101.6 million. For 2018 the levy will be $72.0 million. The estimated millage rate is $0.1358. The 2018 levy will be used for: o General

More information

Railroad-DOT Mitigation Strategies (R16) Resurfacing Agreements

Railroad-DOT Mitigation Strategies (R16) Resurfacing Agreements Railroad-DOT Mitigation Strategies (R16) Resurfacing Agreements Resurfacing projects are among the most common and routine types of projects regularly conducted by highway agencies. When resurfacing projects

More information

Funding Partnership with Foss Waterway Development Authority for Parks on the Foss Capital Campaign

Funding Partnership with Foss Waterway Development Authority for Parks on the Foss Capital Campaign Item No.: 5D Date of Meeting: July 17, 2018 Funding Partnership with Foss Waterway Development Authority for Parks on the Foss Capital Campaign July 26, 2018 Port of Tacoma Commission Meeting Commission

More information

This page intentionally blank. Capital Facilities Chapter Relationship to Vision. Capital Facilities Chapter Concepts

This page intentionally blank. Capital Facilities Chapter Relationship to Vision. Capital Facilities Chapter Concepts This page intentionally blank. Capital Facilities Chapter Relationship to Vision Vision County Government. County government that is accountable and accessible; encourages citizen participation; seeks

More information

Puyallup Shoreline Master Program FINAL, JAN

Puyallup Shoreline Master Program FINAL, JAN CHAPTER 1 INTRODUCTION A. PURPOSE AND INTENT 1. The purposes of this Shoreline Master Program are: a. To guide the future development of shorelines in the City of Puyallup in a positive, effective, and

More information

B. Resolution P Administration and Projects Committee STAFF REPORT October 1, 2015 Page 2 of 2 Changes from Committee Background MTC committed a

B. Resolution P Administration and Projects Committee STAFF REPORT October 1, 2015 Page 2 of 2 Changes from Committee Background MTC committed a Administration and Projects Committee STAFF REPORT Meeting Date: October 1, 2015 Subject Summary of Issues State Route 4 (SR4) East Widening Project Loveridge Road to SR160 (Projects 1406/3001) Request

More information

Staff: Rob Fix Executive Director Business Development Director. Planning and Development Director. Economic Development Specialist

Staff: Rob Fix Executive Director Business Development Director. Planning and Development Director. Economic Development Specialist MINUTES OF THE PORT OF BELLINGHAM COMMISSION MEETING HELD TUESDAY, MAY 7, 2013 HARBOR CENTER BUILDING CONFERENCE ROOM 1801 ROEDER AVENUE, BELLINGHAM, WASHINGTON Present: Jim Jorgensen President Michael

More information

Metrolinx-City of Toronto-Toronto Transit Commission Master Agreement for Light Rail Transit Projects

Metrolinx-City of Toronto-Toronto Transit Commission Master Agreement for Light Rail Transit Projects STAFF REPORT ACTION REQUIRED Metrolinx-City of Toronto-Toronto Transit Commission Master Agreement for Light Rail Transit Projects Date: October 23, 2012 To: From: Wards: City Council City Manager All

More information

CHAGRIN RIVER WATERSHED PARTNERS, INC. Lower Main Branch and East Branch Streambank Stabilization and Grassed Filter Strip Project

CHAGRIN RIVER WATERSHED PARTNERS, INC. Lower Main Branch and East Branch Streambank Stabilization and Grassed Filter Strip Project CHAGRIN RIVER WATERSHED PARTNERS, INC. Lower Main Branch and East Branch Streambank Stabilization and Grassed Filter Strip Project REQUEST FOR PROPOSALS August 4, 2014 SECTION A: SUPPLIES OR SERVICES AND

More information

Port of Long Beach. Legislation Text

Port of Long Beach. Legislation Text Port of Long Beach 4801 Airport Plaza Drive Long Beach, CA 90815 Legislation Text File #: HD-18-416, Version: 1 DATE: 8/27/2018 TO: Board of Harbor Commissioners FROM: Don Kwok, Acting Director of Finance

More information

U.S. NUCLEAR REGULATORY COMMISSION EXPERIENCE IMPLEMENTING A RISK-INFORMED GRADED APPROACH FOR INSTITUTIONAL CONTROLS TO RESTRICT SITE USE

U.S. NUCLEAR REGULATORY COMMISSION EXPERIENCE IMPLEMENTING A RISK-INFORMED GRADED APPROACH FOR INSTITUTIONAL CONTROLS TO RESTRICT SITE USE U.S. NUCLEAR REGULATORY COMMISSION EXPERIENCE IMPLEMENTING A RISK-INFORMED GRADED APPROACH FOR INSTITUTIONAL CONTROLS TO RESTRICT SITE USE R. L. Johnson U.S. Nuclear Regulatory Commission ABSTRACT The

More information

FUTURE STORMWATER CONTROLS PROGRAM RULES (ARTICLE 5)

FUTURE STORMWATER CONTROLS PROGRAM RULES (ARTICLE 5) FUTURE STORMWATER CONTROLS PROGRAM RULES (ARTICLE 5) Catskill Watershed Corporation PO Box 569 Margaretville, NY 12455 (845) 586-1400 Approved by the Board of Directors June 23, 1998 Revised April 5, 2016

More information

Lending for Septic Repairs The Hood Canal, WA Regional Loan Program. Terry Hull, Manager

Lending for Septic Repairs The Hood Canal, WA Regional Loan Program. Terry Hull, Manager Lending for Septic Repairs The Hood Canal, WA Regional Loan Program Terry Hull, Manager Enterprise Cascadia Septic Loan Unique Product - Unique Story Who we are Our experience in financing OSS upgrades

More information

Port of Tacoma 2018 Budget

Port of Tacoma 2018 Budget Port of Tacoma 2018 Budget Mount Rainier and cranes viewed from the Tacoma Tideflats Statutory Budget and Tax Levy adopted: November 14, 2017 The Port of Tacoma has been a recipient of the Government Finance

More information

REQUEST FOR PROPOSALS FOR BID TOWN OF MIDDLESEX, VERMONT TROPICAL STROM IRENE FEDERAL BUYOUT DEMOLITIONS

REQUEST FOR PROPOSALS FOR BID TOWN OF MIDDLESEX, VERMONT TROPICAL STROM IRENE FEDERAL BUYOUT DEMOLITIONS REQUEST FOR PROPOSALS FOR BID TOWN OF MIDDLESEX, VERMONT TROPICAL STROM IRENE FEDERAL BUYOUT DEMOLITIONS Contact: Sarah Merriman Town Clerk/Select Board Assistant Town of Middlesex 5 Church Street Middlesex,

More information

EAST CONTRA COSTA COUNTY HCP / NCCP MITIGATION FEE AUDIT DRAFT REPORT AND NEXUS STUDY. Prepared For: Prepared By:

EAST CONTRA COSTA COUNTY HCP / NCCP MITIGATION FEE AUDIT DRAFT REPORT AND NEXUS STUDY. Prepared For: Prepared By: EAST CONTRA COSTA COUNTY HCP / NCCP MITIGATION FEE AUDIT AND NEXUS STUDY DRAFT REPORT Prepared For: East Contra Costa County Habitat Conservancy Prepared By: Robert D. Spencer, Urban Economics Sally E.

More information

Port of Olympia 2017 Capital Investment Plan by Line of Business 11/28/16

Port of Olympia 2017 Capital Investment Plan by Line of Business 11/28/16 Port of Olympia 2017 Capital Investment Plan by Line of Business 11/28/16 Data Type Line of Business Sum of 2017 Sum of 2018 Sum of 2019 Sum of 2020 Sum of 2021 Sum of Total Carry Forward Admin/IT $ 107,446

More information

Tallahassee Brownfields Revolving Loan Fund Coalition

Tallahassee Brownfields Revolving Loan Fund Coalition Tallahassee Brownfields Revolving Loan Fund Coalition The Tallahassee Brownfields Revolving Loan Fund Coalition (BFC), comprised of the City of Tallahassee and the Tallahassee Community Redevelopment Agency,

More information

PIERCE COUNTY INVITATION TO BID SURPLUS PROPERTY SALE NUMBER 1022 FOR SALE OF SURPLUS GRAVEL

PIERCE COUNTY INVITATION TO BID SURPLUS PROPERTY SALE NUMBER 1022 FOR SALE OF SURPLUS GRAVEL PIERCE COUNTY INVITATION TO BID SURPLUS PROPERTY SALE NUMBER 1022 FOR SALE OF SURPLUS GRAVEL BIDS MUST BE SUBMITTED TO: CLERK OF THE COUNCIL 930 TACOMA AVE S RM 1046 TACOMA WA 98402-2176 AND WILL BE RECEIVED

More information

PERMIT Under the Environmental Conservation Law (ECL)

PERMIT Under the Environmental Conservation Law (ECL) PERMIT Under the Environmental Conservation Law (ECL) EMERGENCY GENERAL PERMIT GP-0-17-006 Lake Ontario Erosion Control Permittee and Facility Information Permit Issued To: Applicant shown on Application/Authorization

More information

In-Lieu Fee Program Instrument Outline For Proposed In-Lieu Fee Programs in the States of Kansas and Missouri

In-Lieu Fee Program Instrument Outline For Proposed In-Lieu Fee Programs in the States of Kansas and Missouri In-Lieu Fee Program Instrument Outline For Proposed In-Lieu Fee Programs in the States of Kansas and Missouri The U.S. Army Corps of Engineers (Corps) and U.S. Environmental Protection Agency joint regulation

More information

Port of Tacoma Annual Report 2013

Port of Tacoma Annual Report 2013 Port of Tacoma Annual Report 2013 Changing competitive landscape International container trade has changed dramatically in the past few years. These unprecedented challenges highlight the need for us

More information

1301: (a) The same purpose for which it was used originally;

1301: (a) The same purpose for which it was used originally; ACTION: Final DATE: 07/31/2017 11:27 AM 1301:7-9-16 Petroleum contaminated soil. (A) Purpose and scope. For the purpose of prescribing rules pursuant to divisions (A) and (E) of section 3737.88 and division

More information

Approach to Mine Risk Assessment and Risk Management under the Environmental Management Act

Approach to Mine Risk Assessment and Risk Management under the Environmental Management Act Approach to Mine Risk Assessment and Risk Management under the Environmental Management Act John E.H. Ward, B.C. Ministry of Environment NOAMI Risk Assessment Workshop Richmond, B.C. November 13, 2008

More information

Section moves to amend H.F. No as follows: 1.2 Delete everything after the enacting clause and insert:

Section moves to amend H.F. No as follows: 1.2 Delete everything after the enacting clause and insert: 1.1... moves to amend H.F. No. 3120 as follows: 1.2 Delete everything after the enacting clause and insert: 1.3 "Section 1. Minnesota Statutes 2016, section 103B.101, subdivision 9, is amended to read:

More information

SAN DIEGO UNIFIED PORT DISTRICT. Independent Auditors Report, Management s Discussion and Analysis and Basic Financial Statements

SAN DIEGO UNIFIED PORT DISTRICT. Independent Auditors Report, Management s Discussion and Analysis and Basic Financial Statements SAN DIEGO UNIFIED PORT DISTRICT Independent Auditors Report, Management s Discussion and Analysis and Basic Financial Statements Years Ended June 30, 2013 and June 30, 2012 Years Ended June 30, 2013 and

More information

Historic Preservation Tax Credit Program Guidelines Table of Contents

Historic Preservation Tax Credit Program Guidelines Table of Contents Table of Contents Section I General...........................................................1 A. Definitions.............................................................1 B. Program Overview......................................................

More information

SOUND TRANSIT STAFF REPORT MOTION NO. M D Street-to-M Street Track & Signal Project Preferred Alternative

SOUND TRANSIT STAFF REPORT MOTION NO. M D Street-to-M Street Track & Signal Project Preferred Alternative SOUND TRANSIT STAFF REPORT MOTION NO. M2007-126 D Street-to-M Street Track & Signal Project Preferred Alternative Meeting: Date: Type of Action: Staff Contact: Phone: Board 12/13/07 Discussion/Possible

More information

Interagency Regulatory Guide

Interagency Regulatory Guide Interagency Regulatory Guide Advance Permittee-Responsible Mitigation U.S. Army Corps of Engineers Washington State Department of Ecology Washington State Department of Fish and Wildlife US Army Corps

More information

BARTOW COUNTY UTILITY PERMIT PROCEDURES

BARTOW COUNTY UTILITY PERMIT PROCEDURES BARTOW COUNTY UTILITY PERMIT PROCEDURES A Utility Permit is required for utility work as specified in the Bartow County Utility Accommodation Ordinance. Work in a Bartow County right-of-way without a permit,

More information

Chairman Skinner and the VRE Operations Board. Authorization to Issue a Request for Proposals for Federal Legislative Services

Chairman Skinner and the VRE Operations Board. Authorization to Issue a Request for Proposals for Federal Legislative Services Agenda Item 8-A Consent Item To: From: Chairman Skinner and the VRE Operations Board Doug Allen Date: February 19, 2016 Re: Authorization to Issue a Request for Proposals for Federal Legislative Services

More information

RESOLUTION NO. 3605, as amended

RESOLUTION NO. 3605, as amended RESOLUTION NO. 3605, as amended A RESOLUTION of the Port Commission of the Port of Seattle repealing Resolution No. 3 18 1, and restating the master policy directive on the role and responsibilities of

More information

BOARD OF DIRECTORS MEETING

BOARD OF DIRECTORS MEETING Revised 12/10/14 See Item No. 11 SOUTHERN CALIFORNIA REGIONAL RAIL AUTHORITY BOARD OF DIRECTORS MEETING FRIDAY, DECEMBER 12, 2014 10:00a.m. LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY (METRO)

More information

1. Approve and accept the Comprehensive Park Design for the Orange County Great Park.

1. Approve and accept the Comprehensive Park Design for the Orange County Great Park. REQUEST FOR CITY COUNCIL ACTION COUNCIL MEETING DATE: TITLE: O~GE COUNTY GREAT PARK COMP~ PARK DESIGN City~ RECOMMENDED ACTION: 1. Approve and accept the Comprehensive Park Design for the Orange County

More information

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk CMAA Document CMAR-1 Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk 2004 EDITION This document is to be used in connection with CMAA Standard Form of Contract

More information

S-1 (1804) FAILURE TO MAINTAIN SATISFACTORY PROGRESS The provisions of Mn/DOT 1804 are supplemented as follows:

S-1 (1804) FAILURE TO MAINTAIN SATISFACTORY PROGRESS The provisions of Mn/DOT 1804 are supplemented as follows: S-1 (1804) FAILURE TO MAINTAIN SATISFACTORY PROGRESS The provisions of Mn/DOT 1804 are supplemented as follows: S-1.1 The last sentence of 1804 is deleted and replaced with the following: If the Contractor

More information

Mitigation Banking Factsheet

Mitigation Banking Factsheet EXHIBIT 57 Page 1 of 5 Wetlands You are here: EPA Home Office of Water Wetlands, Oceans, and Watersheds Wetlands Wetlands Fact Sheet Mitigation Banking Mitigation Banking Factsheet Compensating for Impacts

More information

RFP NO: REQUEST FOR PROPOSAL BUILDING DEMOLITION SERVICES CITY OF SOUTH BAY 335 SW 2ND AVENUE, SOUTH BAY, FLORIDA 33493

RFP NO: REQUEST FOR PROPOSAL BUILDING DEMOLITION SERVICES CITY OF SOUTH BAY 335 SW 2ND AVENUE, SOUTH BAY, FLORIDA 33493 RFP NO: 2017-03 REQUEST FOR PROPOSAL BUILDING DEMOLITION SERVICES CITY OF SOUTH BAY 335 SW 2ND AVENUE, SOUTH BAY, FLORIDA 33493 Advertisement for Request for Proposals CITY OF SOUTH BAY RFP NO: 2017-03

More information

Headquarters U.S. Air Force

Headquarters U.S. Air Force Headquarters U.S. Air Force AFCEE Performance Based Remediation (PBR) Program 11 May 2011 Ms. Rhonda Hampton, P.E. AFCEE PBR Topics AFCEE PBR History & Successes FY11 Air Force Environmental Clean-up Refocus

More information

Request for Proposals (RFP) For Services as General Counsel San Gabriel River Discovery Center Authority

Request for Proposals (RFP) For Services as General Counsel San Gabriel River Discovery Center Authority Request for Proposals (RFP) For Services as General Counsel San Gabriel River Discovery Center Authority 1. PURPOSE The Board (Board) of the San Gabriel River Discovery Center Authority (the Authority

More information

2011 All Source RFP Exhibit I

2011 All Source RFP Exhibit I Prototype Natural Gas Tolling Agreement Term Sheet Background: This Prototype Natural Gas Tolling Agreement Term Sheet ( Term Sheet ) sets forth the current requirements that PSE wants the Respondent to

More information

STORMWATER MANAGEMENT FUND DEPARTMENT OF ENVIRONMENTAL SERVICES

STORMWATER MANAGEMENT FUND DEPARTMENT OF ENVIRONMENTAL SERVICES DEPARTMENT OF ENVIRONMENTAL SERVICES Mission: To implement a comprehensive stormwater management program that balances the following goals: 1) to reduce the potential for stormwater threats to public health,

More information

SOUND TRANSIT STAFF REPORT RESOLUTION NO. R Sammamish Park-and-Ride Project Property Acquisition

SOUND TRANSIT STAFF REPORT RESOLUTION NO. R Sammamish Park-and-Ride Project Property Acquisition SOUND TRANSIT STAFF REPORT RESOLUTION NO. R2005-09 Sammamish Park-and-Ride Project Property Acquisition Meeting: Date: Type of : Staff Contact: Phone: Finance Committee Board ACTION 3/17/05 3/24/05 Discussion/Possible

More information

Overview: The CERCLA Process. Connie Sue Martin

Overview: The CERCLA Process. Connie Sue Martin Overview: The CERCLA Process Connie Sue Martin Overview Removal and/or Remediation Process Natural Resource Damage Assessment and Restoration CERCLA Comprehensive Environmental Response, Compensation and

More information

PROGRESS REPORT WATERFRONT PROGRAM. Q (January March) Highlights from Q1 2017

PROGRESS REPORT WATERFRONT PROGRAM. Q (January March) Highlights from Q1 2017 WATERFRONT PROGRAM PROGRESS REPORT Q1 2017 (January March) Highlights from Q1 2017 Advanced major Seawall Replacement construction between Pike and Union streets, reopened the area in front of the Seattle

More information

Application for the Voluntary Remediation Program

Application for the Voluntary Remediation Program FACT SHEET # 3 Voluntary Remediation Program (VRP) (307) 777-7752 http://deq.state.wy.us/volremedi/index.asp Application for the Voluntary Remediation Program In its 2000 session, the Wyoming Legislature

More information

ENBRIDGE ENERGY LIMITED PARTNERSHIP SPECIAL USE PERMIT

ENBRIDGE ENERGY LIMITED PARTNERSHIP SPECIAL USE PERMIT Page 1 of 6 Chequamegon- Nicolet National Forest ENBRIDGE ENERGY LIMITED PARTNERSHIP SPECIAL USE PERMIT Fact Sheet July 5, 2017 Situation: Enbridge Energy Limited Partnership (Enbridge) has requested to

More information