M52: Delays, Stop Work Orders, and Termination in Grants and Contracts
|
|
- Bertram Stone
- 5 years ago
- Views:
Transcription
1 M52: Delays, Stop Work Orders, and Termination in Grants and Contracts Presented by: J. Michael Slocum, Esquire SLOCUM & BODDIE, P.C Shawnee Road, Suite 300 Alexandria, Virginia (703)
2 Government Action and Institution Reaction Actual and potential funding gaps/ deficiencies and budget cuts will affect contract and grant processes and existing and prospective government contracts and funding agreements Government has discretion as to how it will proceed in light of funding shortfalls and cuts What should be the counter-responses? 2
3 Reduced Funds Cause Contract/agreement changes Performance period delays Termination 3
4 Typical Damages Idle equipment and facilities Labor, material, and other cost escalation Unabsorbed overhead Disruption Acceleration 4
5 Unabsorbed Overhead What is it? What must the recipient prove for entitlement? How does the recipient prove quantum? (continued) 5
6 Unabsorbed Overhead (2) Calculation The difference between the amount bid and the amount you were able to allocate or The amount calculated using Eichleay formula 6
7 Disruption, Loss of Efficiency, Loss of Productivity Death by a thousand cuts Work not necessarily stopped, just more difficult Anything that affects the productivity the recipient would have achieved Can be combined with added, deleted, substituted, delayed or accelerated work Can be sole basis (continued) 7
8 Disruption, Loss of Efficiency, Loss of Productivity (2) Causes Delay due to adverse weather Changes Learning curve disruptions Out-of-sequence work Trade packing Anything else that affects productivity (continued) 8
9 Disruption, Loss of Efficiency, Loss of Productivity (3) Increased labor costs More direct hours to do the work More time lost to absenteeism and tardiness More time lost to rework Increased material costs due to rejects 9
10 Proving Loss of Productivity Flexy Plan Industry GSBCA 4117, 76-1 BCA Batteast Construction Co., Inc. ASBCA 35818, 92-1 BCA Shea, Proving Productivity Losses in Government Contracts, 18 Pub. Cont. L.J. 414 (1989) 10
11 Acceleration Costs Hidden Disruption loss of efficiency Clear Overtime wages More workers More equipment Expedited deliveries 11
12 Contracts and Assistance Mechanisms for Adjustments Government insists on the right to make changes in work during performance Contractor has the compensating right of access to an equitable adjustment in contract price and/or schedule whenever a change is made Rights are established in various FAR Changes clauses in contracts, but may not be explicit in agreements. 12
13 FAR Changes Clauses Changes Fixed- Price Changes Cost- Reimbursement Changes T&M or LH Changes Changes and Changed Conditions Change Order Accounting Notification of Changes Time Extensions Variations in Quantity Differing Site Conditions Continuity of Service Suspension of Work Stop-Work Order Government Delay of Work 13
14 Agreements May Not Have Equivalent Terms For Instance: DARPA 4. Amendment of Agreement: (a) Amendments maybe requested by either party. The Recipient shall detail the technical, chronological, and financial impact of the proposed amendment to the program. Changes are effective only after the agreement has been modified. (b) The Agreements Officer or the AAO may unilaterally issue minor or administrative agreement modifications (e.g., changes in the paying office or appropriation data, changes to Government personnel identified in the agreement, etc.) 14
15 So What If Grants Officer Orders Change Without Clause? Theory v. Reality Even if the directed change is breach of contract (because the Grants Officer is without authority) Recipient should probably still perform and file for damages. If the Recipient is terminated, even if the government is wrong, the effort is over and only damages (or in very rare cases, an injunction) will be awarded. Therefore Recipient response is some sort of Request for Equitable Adjustment 15
16 What is the Equitable Adjustment? FAR does not define an equitable adjustment FAR does not explain how they are to be computed These interpretations have largely been left to the courts Even more murky for GCAs (continued) 16
17 What is the Equitable Adjustment? (2) The cost impact or harm of a change or changes Corrective measure used to make the harmed party whole Difference between the reasonable cost of performance Without the change or changes, and With the change or changes 17
18 What Needs To Be Proven? A need for an adjustment (HARM) The connection of these circumstances and amounts to the contract (ENTITLEMENT) The reasonableness of the adjustment amount (QUANTUM) 18
19 Types of Changes Express or formal change Directed by the CO/GO Bilateral change including an agreed-to price Unilateral issued prior to the agreement on price Contractor must perform if within the scope of the contract But not so clear if the agreement is a GCA or other type of agreement (including CRADAs and other transactions) Constructive change Government does not know or refuses to recognize the change Up to the Contractor/ Recipient to recognize a change situation Government needs to be convinced of the value of the change Almost always priced after the change has occurred 19
20 Identifying the Adjustment Situation Recognizing situation early makes it easier to: Obtain evidence of entitlement Gather actual cost information Negotiate with the government Defend against claims of untimely performance 20
21 Common Causes of Constructive Changes Differing interpretation of performance/ payment requirements Acts of over-zealous direction, inspection or control Defective statement of work or specifications Failure of the government to disclose superior knowledge Acceleration of performance (continued) 21
22 Common Causes of Constructive Changes (2) Late or unusable data, property or other materials Failure to cooperate on the part of the government Exercising an option after right to exercise expires Variance in quantities Untimely notices Differing conditions 22
23 Delays in Performance Excusable Delays In Fixed Price situations -- does NOT allow for recovery of the cost of the delay Does allow for an extension or adjustment to contractual delivery requirements Compensable Delays Allows for the recovery of costs associated with the delay Allows for an extension or adjustment to contractual delivery dates No Cost extensions Compensation issues are different in Cost Reimbursement situations than in Fixed Price situations. Increased compensation v. Increased Cost Ceiling 23
24 Excusable Delays Labor strikes Weather Sovereign acts of the government Subcontractor or supplier delays Unforeseeable unavailability of materials Floods Fire Epidemic Embargo Acts of God Financial difficulties caused by government 24
25 Compensable Delays Fixed Price Not issuing the Notice to Proceed within a reasonable time Not making the site available or allowing access to the site Government interference with the contractor s work Failure of the government to cooperate in a timely manner Government delay in providing established funding Unreasonable delay in inspecting work Unreasonable delay in issuing change orders Unreasonable delays in gaining government approval 25
26 Delay Risks in Cost Reimbursement Situations A common misconception cost reimbursable contract is a no-lose proposition In reality, government shifts at least some risk Ceiling price Disallowed cost Cost sharing 26
27 Recovery of the Costs of Delay Fixed Price Entitled to recovery of delay costs when the delay is unreasonable in duration Contractor responsibility to establish the unreasonableness of delay Determined on a case-by-case basis Contractor s ability to mitigate the delay can impact the determination of reasonableness (continued) 27
28 Recovery of the Costs of Delay Fixed Price (2) Can recover the entire cost of delay if it is the fault of the government If the delay is the result of the exercise of a contractual right, the contractor is responsible only for the unreasonable portion of the delay No recovery for the costs of delay is possible if there are concurrent delays 28
29 Recovery of the Costs of Delay Fixed Price and Cost Reimbursement Cost of acceleration whether successful or not Delay from the time that Contractor/ Recipient could have reasonably expected to complete performance even if that date is earlier than stated in the contract/ agreement 29
30 Timely Notification of a Constructive Change Contracts some clauses may limit recovery to a set period prior to the time the contractor gives notice Notification of Changes Clause FAR Requires notification of a change within 30 days Government position NO recovery if not in compliance with the notification requirements 30
31 Notification Reality Courts have taken a broader view Most courts do not bar recovery unless: Party was prejudiced (HARMED) by the failure to provide timely notice The Party would have taken corrective action different than that actually taken had timely notice been given 31
32 Time and Material and Cost Contracts and Agreements Sporadic utilization of people causes the loss of planned efficiencies Delays reduced the overall level of effort anticipated not supporting the discounts provided Personnel had to be released or reassigned and rehiring and retraining expenses were incurred Planned personnel were not available when needed due to delays and those with more or less qualifications had to be used Performance delays do not allow recovery of indirect costs included in the negotiated rates creating unabsorbed overhead 32
33 Cost-type and Award Fee Contracts You have an award-fee, cost-type contract with negotiated target costs, base fees and award fees based on established performance parameters Start of the contract is delayed immediately after award Continual changes are made extending the contract s performance and impacting the established performance standards Increased costs incurred are paid but the base fee remained fixed No relief is given in the parameters for earning the award fees which also remain fixed Extension of the contract performance period impacts performance of other contracts at higher fees 33
34 The Would-Have-Cost/ But For Principle REA should be calculated based on the difference between the: Reasonable cost of performing on the contract without the change May be less than the amount originally proposed Reasonable cost of performing on the contract with the change 34
35 Adjustments to Direct Labor Labor rates Labor classes Labor hour efficiencies 35
36 Adjustments to Direct Material or ODC s Escalation Loss of efficiency Changes in vendors 36
37 Reclassification of Normally Indirect Costs Costs must be incurred specifically as a result of the change Avoid double counting 37
38 Unabsorbed or Misallocated Indirect Expenses A request to recoup overhead costs allocated to other work The amount of indirect expense incurred which would have been allocated to the contract Eichleay Calculation approximate determination of daily indirect expenses multiplied by the number of days of delay 38
39 Extended Program/ Contract Support Time-oriented core support function Extension of the contract period requires retention of the program/contract support function Includes program management, quality control, production management, project management, etc. 39
40 Idle or Excess Facilities and Capacity Idle facilities completely unused and excess Idle capacity partially unused facilities Costs include maintenance, repair, rent, taxes, insurance and depreciation Must try to eliminate if possible and practical Idle facility costs cannot be recovered unless Necessary to meet fluctuations in workload Were necessary when acquired Idle capacity is the cost of doing business 40
41 Personnel Costs Severance costs Required by law Required by an employee-employer agreement Paid under an established policy or implied agreement Re-hire and training costs Applies to both released and reassigned employees 41
42 Material and Equipment Storage Costs Occupancy costs (based on square footage utilized) Additional security Shelf life Re-inspection Stocking and re-stocking Inventory control costs 42
43 Settlement Expenses Costs generated internally or through outside resources are recoverable Internal costs must be removed from any indirect rate pool to eliminate double recovery Generally includes accounting, legal, clerical and similar costs Once the contracting officer makes his/her decision costs incurred are not recoverable do a good job the first time!!!! 43
44 Profit Considerations Changes in contract performance can impact a contractors ability to recover anticipated profits or profit levels sufficient to reward the contractor for performance Certain changes clauses allow changes in price and profit Need to justify the profit requested No profit on settlement costs These clauses allow for adjustments to price or fee Stop Work Order Changes- Fixed Price Changes-Cost Reimbursement Changes-T&M or Labor Hour 44
45 REA Certification Requirements Certification required under Contracting rules but must check for GCAs The Truth In Negotiation Act (TINA) requires certification in non-competitive contracts or contract modifications over $750,000 Failure to disclose accurate, complete and current cost or pricing data results in defective pricing Result in downward price adjustments along with civil and criminal penalties. 45
46 Termination Reimbursement Concept Objective is to reimburse the contractor/ Recipient fairly for: Work completed Preparations made for the terminated portion of the contract Provide a reasonable allowance for profit (where applicable) Provide an adjustment for anticipated contract loss 46
47 Methods of Settlement Negotiated agreement Determination by the Termination Contracting/Grants Officer (TCO) Costing or vouchering-out under costreimbursement contracts Combination of these methods 47
48 What is Fair Compensation? Matter of judgment No exact measure Various methods are equally appropriate No strict accounting principles Cost and accounting data are guides When appropriate use Estimated costs Compromise differences Negotiate doubtful cost recovery Other data maybe equally reliable 48
49 Contractor/Recipient Instructions Stop work immediately on terminated portion Terminate all open subcontracts Protect and preserve property of the government and dispose as directed Settle subcontract termination liabilities Promptly submit termination proposal 49
50 Subcontractor Termination Responsibility of the prime Prime performs role of TCO Subcontractor has no rights against the government Promptly notify TCO of subcontractor legal proceedings arising from the termination Subcontract settlement costs are recoverable as settlement expenses Prime is responsible for audit and negotiation of subcontractor A-110 requirement for T for C is now apparent! 50
51 No Cost Settlement Permitted under certain conditions No cost incurred under the terminated portion of the contract/agreement Contractor/subcontractor willing to waive incurred cost recovery No credits/amounts are due to the government under the contract 51
52 Inventory Basis Settlement Fixed Price Situations Separately itemizes cost associated with: Termination inventory (including shipped not billed) Unamortized initial/start-up costs Costs of terminating Settlement expenses Settlement with lower tier subcontractors Allowance for profit 52
53 Inventory Basis Settlement Amount claimed is reduced for: Un-liquidated advances and progress payments Disposals and other credits Anticipated contract loss 53
54 Total Cost Basis Settlement Itemizes all costs incurred up to the termination date Adds an adjustment for profit Reduced for: Anticipated contract loss Price of items completed and delivered prior to the termination Un-liquidated advance and progress payments Disposals and other credits (continued) 54
55 Total Cost Basis Settlement (2) Usually only authorized for: Complete contract terminations Contracts where contract activity has not yet started Where the accounting system cannot establish unit costs for work-in process Contracts that do not specify unit prices 55
56 Inventory vs. Total Cost Basis Settlement Inventory basis places risk on the contractor Limits recovery to residual items Contractor has burden to prove: Claimed costs were incurred Cost are allocable Total cost basis places risk on the government Recovery equals difference between what was incurred and what was paid 56
57 Percentage of Completion Basis Settlement Rarely used for contracts, but common for GCAs (hard to determine, must be negotiated) Establishes percentage of completion applied to total contract price Subtract all prior payments Price of items completed and delivered prior to the termination Un-liquidated advance and progress payments 57
58 Cost-Type Contract/GCA Settlement Contractor proposes all costs incurred Deduct previous payments Adjust fee based upon contract Voucher out all costs incurred Vouchering out limited to last day of sixth month following termination date Negotiate any remaining costs incurred 58
59 Failure to Exercise Priced Options Appears to be currently in favor Not considered a termination Hope to avoid termination settlement costs Areas of concern Amortization of costs over more than the base year Competitive strategy Need to contractually ensure cost recovery De-mobilization Facility refurbishment 59
60 Timing of Settlement Proposal Submission Proposal must be filed within one year of effective date of termination (contracts) Written request for extension Receive written permission for extension Failure to submit permits unilateral determination of amount due Proposal must be submitted in proper format on proper forms (work with TCO) 60
61 Need for a Request for Equitable Adjustment Before preparation and submission of termination settlement proposal the contractor should: Definitize any outstanding contractual changes Ensure all negotiated changes are included in the contract value Prepare, submit and negotiate any conditions resulting in the need for an REA WHY? Mitigate the impact of the loss factor application 61
62 Pre-contract Costs Cost must be incurred Directly pursuant to contract negotiation In anticipation of contract award To meet the proposed contract performance schedule Allowable to the extent they would have been allowable if incurred after contract award An advance agreement is advisable Types of pre-contract costs Bid and proposal Costs of contract performance Plant alteration/ rearrangement Recruitment and hiring 62
63 Initial or Preparatory Costs Starting load cost not fully absorbed due to termination Excessive spoilage or scrap due to inexperienced labor Excessive idle time Subnormal production/output due to testing and changing production methods Training Loss of efficiency due to lack of employee familiarity with performance requirements Facility alterations and rearrangements Management and personnel organization Employment advertising Recruiting Interviewing Hiring Relocations 63
64 Severance Costs (Dismissal Wages) Abnormal or mass severance Estimates may be used in interim proposals Final settlement should be based on actual payments Must be: Required by law Employee-employer agreement Established policy or practice which implies agreement Need to document: Employees severed Time actually spent working on the contract terminated Whether they can perform other work Need for bumping (employee terminated did not work on contract terminated) 64
65 Leased Facilities Rental under unexpired leases Amount must be reasonable for contract period Contractor must make all reasonable efforts to terminate, assign, settle or reduce costs Alteration of leased facilities Must have been necessary for the performance of the contract 65
66 Settlement Costs Includes accounting, legal, clerical, etc. Can be performed internally, with external personnel or both Ensure qualification of external personnel Be sure to fully document efforts (what was done by whom) Recoverable as a cost of termination settlement 66
67 Profit Considerations Usually granted on preparations made and work done on terminated portion of the contract No profit granted on settlement costs No anticipatory profits or consequential damages No profit granted on loss contracts 67
68 Online Presentations Looking for a PowerPoint presentation? The majority of concurrent session materials will be available at or in the Conference App. Use your smartphone and link to the site by this QR code! 68
Sequestration and Terminations for Convenience
Sequestration and Terminations for Convenience J. Clark Pendergrass Lanier Ford Shaver & Payne P.C. 2101 West Clinton Ave., Suite 102 Huntsville, AL 35805 256-535-1100 jcp@lanierford.com www.lanierford.com
More informationChapter 12. Auditing Contract Termination Delay Disruption and Other Price Adjustment Proposals or Claims
Chapter 12 Auditing Contract Termination Delay Disruption and Other Price Adjustment Proposals or Claims Table of Contents 12-000 Auditing Contract Termination, Delay/Disruption, and Other Price Adjustment
More informationPresenters. Hobie Frady Beason & Nally. Brad English Maynard Cooper & Gale
Presenters Brad English Maynard Cooper & Gale benglish@maynardcooper.com 256.512.5705 Hobie Frady Beason & Nally hfrady@beasonnalley.com 256.533.1720 Preserve Your Right to Obtain an Equitable Adjustment:
More informationChanges, Terminations, and Claims
Changes, Terminations, and Claims J. Clark Pendergrass Lanier Ford Shaver & Payne P.C. 2101 West Clinton Ave., Suite 102 Huntsville, AL 35805 256-535-1100 jcp@lanierford.com www.lanierford.com Copyright
More informationCOMMON CLAIMS UNDER CONSTRUCTION CONTRACTS
888 17 th Street, NW, 11 th Floor Washington, DC 20006 Tel: (202) 857-1000 Fax: (202) 857-0200 COMMON CLAIMS UNDER CONSTRUCTION CONTRACTS You may download these slides at www.pilieromazza.com/presentations
More informationTERMINATION AHEAD SLOW DOWN
Contract Terminations Not So Convenient Presented by Paul Slemons & Darrell M. Hineman TERMINATION AHEAD SLOW DOWN Please Read This presentation has been prepared for information purposes and general guidance
More informationArticle 6 Modification and Termination of Contracts for Supplies and Services
Article 6 Modification and Termination of Contracts for Supplies and Services 16601. Contract Clauses and their Administration 16601. Contract Clauses and their Administration. (a) Introduction. The following
More informationCost Recovery Issues After A Termination For Convenience
Cost Recovery Issues After A Termination For Convenience Breakout Session # C15 Leslie Anderson, Program Manager, BAE Systems Greg Bingham, Vice President, The Kenrich Group Chelsea Taylor, Manager, The
More informationIt s inevitable, really.
It s inevitable, really. Given the budget pressure on the Federal government which already includes the use of Continuing Resolutions in lieu of budget appropriations, and may well include automatic sequestration
More informationTerminations: How to Cope with the Premature Death of Your Contract Presented By:
Terminations: How to Cope with the Premature Death of Your Contract Presented By: Cheryl Anderson canderson@redstonegci.com Jon Levin jlevin@maynardcooper.com Topics Covered Overview of Terminations Terminations
More informationSuccessfully Crafting and Prosecuting Contract Disputes Act Claims Against the Government
Successfully Crafting and Prosecuting Contract Disputes Act Claims Against the Government Webinar July 28, 2015 Sandy Hoe shoe@cov.com 202-662-5394 Justin Ganderson jganderson@cov.com 202-662-5422 Agenda
More informationConstruction Claims and Pitfalls. Including General Claims/ Requests for Equitable Adjustment (REAs)
Construction Claims and Pitfalls Including General Claims/ Requests for Equitable Adjustment (REAs) OVERVIEW What Went Wrong? REAs vs. Claims Measuring Delay Damages Differing Site Conditions Who Has Authority
More informationManaging Contract Terminations to Protect or Improve Your Profit Position A Guide to Winning Settlement Proposals. Mark J. Meagher Britton Nohe-Braun
Managing Contract Terminations to Protect or Improve Your Profit Position A Guide to Winning Settlement Proposals Mark J. Meagher Britton Nohe-Braun November 14, 2017 Agenda Terminations overview Current
More informationFederal Acquisition Regulations: What Every Surety Professional Should Make Sure Their Clients Know
Federal Acquisition Regulations: What Every Surety Professional Should Make Sure Their Clients Know Surety Association of San Diego April 12, 2011 What are the Federal Acquisition Regulations? The Federal
More informationWebinar: Making the Right Choices in Government Contracting Part 3
Public Contracting Institute LLC Webinar: Making the Right Choices in Government Contracting Part 3 Presented by Richard D. Lieberman, FAR Consultant, Website: www.richarddlieberman.com. Email rliebermanconsultant@gmail.com.
More informationSection 108. PROSECUTION AND PROGRESS
108.01 Section 108. PROSECUTION AND PROGRESS 108.01. Subcontracting of Contract Work. No portion of the contract may be subcontracted, other than the providing of necessary materials, except as provided
More information108 PROSECUTION AND PROGRESS SECTION 108 PROSECUTION AND PROGRESS
SECTION 108 PROSECUTION AND PROGRESS 108.1 NOTICE TO PROCEED a. General. For each Project, the Engineer will issue to the Contractor a Notice to Proceed, a written notice to the Contractor to begin the
More informationContract Administration Final Exam
Contract Administration Final Exam 1. You want to solicit bids for a one year contract for concrete to support your roadway construction work. At this time, prices are fluctuating due to high demand and
More informationTerms & Conditions Supply of Goods or Services
Terms & Conditions Supply of Goods or Services 1. DEFINITIONS In these terms and conditions: Agreement means an agreement between the Purchaser and Supplier for the supply of Goods or Services constituted
More information108 PROSECUTION AND PROGRESS SECTION 108 PROSECUTION AND PROGRESS
SECTION 108 PROSECUTION AND PROGRESS 108.1 NOTICE TO PROCEED a. General. For each project, the Engineer will issue to the Contractor a Notice to Proceed, a written notice to the Contractor to begin the
More informationOREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)
OREGON STATE UNIVERSITY CM/GC CONTRACT (Construction Manager/General Contractor) THE CONTRACT IS BETWEEN: OWNER: Oregon State University And CONSTRUCTION MANAGER/ GENERAL CONTRACTOR (referred to as Contractor
More informationTITLE 70: DEPARTMENT OF FINANCE SUBCHAPTER COST AND PRICE ANALYSIS REGULATIONS
SUBCHAPTER 70-30.1 COST AND PRICE ANALYSIS REGULATIONS Part 001 General Provisions 70-30.1-001 Overview and Summary 70-30.1-005 Scope 70-30.1-010 Definitions Part 100 Policy; Cost or Pricing Data 70-30.1-101
More informationGovernment Contracts Pricing Strategies and Rate Structures
Government Contracts Pricing Strategies and Rate Structures Presented By: Brandon Smith bsmith@anglincpa.com Jon Levin jlevin@maynardcooper.com Provisional Billing Rates Provisional, Target, Budget, Billing,
More informationClaim Avoidance on Highway Projects
Claim Avoidance on Highway Projects Joseph R. Hellenbrand, P. E., PSP Capital Project Management, Inc. ASHE National Conference Bismarck, North Dakota June 13, 014 1 Joe Hellenbrand P.E.; PSP 0 years of
More informationDESERT COMMUNITY COLLEGE DISTRICT General Terms and Conditions
DESERT COMMUNITY COLLEGE DISTRICT www.collegeofthedesert.edu General Terms and Conditions 1. PURCHASE ORDER DEFINED: The term purchase order as used in these terms conditions means the document entitled
More informationCummins South Africa (Pty) Limited
Cummins South Africa (Pty) Limited STANDARD TERMS AND CONDITIONS 1 General 1.1 This Agreement contains all the terms and conditions between the Customer and Cummins South Africa (Pty) Ltd (Cummins). 1.2
More informationAGREEMENT FOR ENGINEERING SERVICES (AHTD VERSION COST PLUS FEE) JOB NO. FEDERAL AID PROJECT ( FAP ) NO. JOB TITLE PREAMBLE
AGREEMENT FOR ENGINEERING SERVICES (AHTD VERSION COST PLUS FEE) JOB NO. FEDERAL AID PROJECT ( FAP ) NO. JOB TITLE PREAMBLE THIS AGREEMENT, entered into this day of, by and between the Arkansas State Highway
More informationDocument A Exhibit A Determination of the Cost of the Work
Document A121 2014 Exhibit A Determination of the Cost of the Work THE OWNER: (Name, legal status, address and other information) THE CONTRACTOR: (Name, legal status, address and other information) This
More informationStandard Form of Agreement Between Contractor and Subcontractor
Document A401 2007 Standard Form of Agreement Between Contractor and Subcontractor AGREEMENT made as of the in the year (In words, indicate day, month and year.) day of BETWEEN the Contractor: (Name, legal
More informationSlide 1. Slide 2. Slide 3 LEARNING OBJECTIVES WHAT S THE DIFFERENCE? PERSONAL AND PROFESSIONAL EXCELLENCE
Slide 1 PERSONAL AND PROFESSIONAL EXCELLENCE Contract Administration Beginning With the End in Mind David E. Nash, CPPO, CPPB 50 TH ANNUAL CONFERENCE MAY 24-27, 2017 ORLANDO, FLORIDA Slide 2 LEARNING OBJECTIVES
More informationEthical Contract Negotiation
Ethical Contract Negotiation Texas Society of Professional Engineers May 16, 2006 Brian W. Erikson Quilling, Selander, Cummiskey & Lownds, P.C. 2001 Bryan Street, Suite 1800 Dallas, Texas 75201 (214) 880-1844
More informationSUPPLIER - TERMS AND CONDITIONS Materials and Goods
SUPPLIER - TERMS AND CONDITIONS Materials and Goods 1. BINDING EFFECT; ACCEPTANCE. This purchase order and all subsequent purchase orders delivered by Buyer to Seller (each, an "order"), shall be governed
More informationGeneral Terms and Conditions of Sale of DMS Enterprise GmbH
General Terms and Conditions of Sale of DMS Enterprise GmbH These General Terms and Conditions have been prepared in English only for information purposes. When in doubt about meaning and intention of
More informationGeneral Terms and Conditions of Siemens EOOD, Building Technologies Division
General Terms and Conditions of Siemens EOOD, Building Technologies Division 1. Subject of the Agreement The Customer receives the right to purchase under these general trading conditions specified products
More informationTerre View Research Facility Relocation Washington State University Pullman, WA Project Manual
Terre View Research Facility Relocation Washington State University Pullman, WA Project Manual Project No. 9574-2018 Issued 7/19/2017 Washington State University Facility Services, Capital Terre View Research
More informationAGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES
AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES AGREEMENT made by and between, hereinafter called the Owner, and SITESCOMMERCIAL, LLC 185 WIND CHIME COURT, SUITE
More informationARTICLE 8 - OWNER S RESPONSIBILITIES
properly integrate with such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering their work and will only cut or alter their work with the written
More informationBest Practices in Drafting U.S. Government Subcontract Terms and Conditions. June 10, Vanessa L. Miller Erin L. Toomey
Attorney Advertising Prior results do not guarantee a similar outcome Models used are not clients but may be representative of clients 321 N. Clark Street, Suite 2800,Chicago, IL 60654 312.832.4500 Best
More informationARTICLE 1 ARTICLE 3 CONTRACTOR THE SUBCONTRACT DOCUMENTS ARTICLE 2 MUTUAL RIGHTS AND RESPONSIBILITIES
ARTICLE 1 THE SUBCONTRACT DOCUMENTS 1.1 The Subcontract Documents consist of (1) this Agreement; (2) the prime Contract, consisting of the Agreement between the Owner and Contractor and the other Contract
More informationDIVISION 1 GENERAL REQUIREMENTS SECTION MODIFICATION PROCEDURES AND PRICING OF CHANGED WORK
DIVISION 1 GENERAL REQUIREMENTS SECTION 01 2600 MODIFICATION PROCEDURES AND PRICING OF CHANGED WORK PART 1 GENERAL 1.01 SUMMARY A. Section includes requirements that supplement the paragraphs of Document
More informationAIA Document A103 TM 2007
AIA Document A103 TM 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is the Cost of the Work plus a fee without a Guaranteed Maximum Price AGREEMENT made as of the
More information! " # $ " % made as of the 24 day of May in the year 2006 (In words, indicate day, month and year) the Owner: (Name, address and other information)
! " # $ " % made as of the 24 day of May in the year 2006 (In words, indicate day, month and year) the Owner: (Name, address and other information) Wynne Public Schools P.O. Box 69 Wynne, AR 72396 Telephone
More informationThe BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY
The BASICS of CONSTRUCTION ACCOUNTING Workshop GLOSSARY From Financial Management & Accounting for the Construction Industry, CFMA. Accounts Payable Obligations to pay for goods and services that have
More informationMAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS
MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 CHANGES... 1 2.1 BC Hydro s Right to Require Changes... 1 2.2 Restrictions on Changes... 1 2.3
More informationStandard Form of Agreement Between. Owner and Design-Builder Cost Plus Fee with an Option for a Guaranteed Maximum Price
November 3, 2014 Standard Form of Agreement Between Owner and Design-Builder Cost Plus Fee with an Option for a Guaranteed Maximum Price This document has important legal consequences. Consultation with
More informationStandard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk
CMAA Document CMAR-1 Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk 2004 EDITION This document is to be used in connection with CMAA Standard Form of Contract
More informationContract Clauses. B.1 General. Appendix B. Introduction. Numbering of Clauses
B.1.2 Appendix B B.1 General B.1.1 B.1.2 Introduction This Appendix sets forth the general clauses to be included in solicitations and contracts and clauses that (1) may be included at the discretion of
More informationTERMS AND CONDITIONS OF SALE. 1.1 the following words and expressions shall have the following meanings unless the context otherwise requires:
TERMS AND CONDITIONS OF SALE 1. DEFINITIONS In these standard terms and conditions: 1.1 the following words and expressions shall have the following meanings unless the context otherwise requires: Business
More informationFIXTURE TERMS & CONDITIONS Materials & Goods
FIXTURE TERMS & CONDITIONS Materials & Goods 1. BINDING EFFECT; ACCEPTANCE. This purchase order and all subsequent purchase orders delivered by Supplier to The Pep Boys Manny, Moe & Jack, and its affiliates,
More information4. CARGO PREFERENCE REQUIREMENTS 46 U.S.C CFR
FEDERAL CLAUSES 4. CARGO PREFERENCE REQUIREMENTS 46 U.S.C. 1241 46 CFR Part 381 Applicability to Contracts: The Cargo Preference requirements apply to all contracts involving equipment, materials, or commodities
More informationSession 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES
Audio Sessions Session 10 and 11 EXECUTING THE WORK & CLAIMS AND DISPUTES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 www.csinet.org This presentation
More informationTERMS AND CONDITIONS OF PURCHASE
TERMS AND CONDITIONS OF PURCHASE 1. GENERAL: For purposes of these Terms and Conditions of Purchase, the term Talbots shall mean The Talbots, Inc. The term Order shall mean, collectively: (i) a written
More informationPLYMOUTH TUBE COMPANY ( PLYMOUTH ) ORDER ACKNOWLEDGEMENT / INVOICE TERMS AND CONDITIONS Effective 07/01/2014
PLYMOUTH TUBE COMPANY ( PLYMOUTH ) ORDER ACKNOWLEDGEMENT / INVOICE TERMS AND CONDITIONS Effective 07/01/2014 1. ACCEPTANCE THE TERMS AND CONDITIONS AS HEREIN SET FORTH ARE INCORPORATED INTO PLYMOUTH S
More informationSTANDARD TERMS FOR SPARE PARTS AND/OR SITE SERVICES
STANDARD TERMS FOR SPARE PARTS AND/OR SITE SERVICES Definitions Term Contract Meaning the contract formed between Client and Contractor for the supply by Contractor of the Scope of Supply. Contractor 7
More informationGLWA PURCHASE ORDER TERMS AND CONDITIONS
1. Definitions Throughout this document the term Seller means the entity furnishing goods, services, and goods and services, and shall be synonymous with the term Supplier. The term Buyer means the Great
More informationSAMPLE DOCUMENT SUBCONTRACT AGREEMENT
SUBCONTRACT AGREEMENT THIS SUBCONTRACT, made this day of by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter "Subcontractor") with an office and
More informationContractor for any and all liability, costs, expenses, fines, penalties, and attorney s fees resulting from its failure to perform such duties.
SUBCONTRACT AGREEMENT THIS SUBCONTRACT, made this day of, 20 by and between (hereinafter "Contractor"), with an office and principal place of business at and (hereinafter "Subcontractor") with an office
More informationFirst Source Hiring and Local Business Enterprise Policy
First Source Hiring and Local Business Enterprise Policy City of Redevelopment Agency Table of Contents PART ONE. COVERAGE...4 PART TWO. DEFINITIONS...5 PART THREE. SUMMARIES...7 Section One. Section Two.
More informationGeneral conditions of contract for the supply of machinery and spare parts (2006)
General conditions of contract for the supply of machinery and spare parts (2006) 1. General 1.1 The contract shall be deemed to have been entered into upon receipt of supplier's written acknowledgement
More informationINTERNATIONAL GRAND INVESTMENT CORPORATION TERMS AND CONDITIONS
INTERNATIONAL GRAND INVESTMENT CORPORATION TERMS AND CONDITIONS Except as otherwise provided on the face of this Purchase Order or Supply Contract (the Order ) which is attached hereto, the parties agree
More informationDocument A133 TM. AGREEMENT made as of the day of in the year Two Thousand and Sixteen. BETWEEN the Owner:
Document A133 TM 2009 Standard Form of Agreement Between Owner and Construction Manager as Constructor where the basis of payment is the Cost of the Work Plus a Fee with a Guaranteed Maximum Price AGREEMENT
More informationComparison of Major Contract Types. Incentive Firm (FPIF) Moderately uncertain
Principal Risk to be Mitigated Firm Fixed-Price (FFP) None. Thus, the contractor assumes all cost risk. Use When.. The requirement is well-defined. Contractors are experienced in meeting it. Market conditions
More informationCLAIMS, CHANGES, & TERMINATIONS. Chris Haile Tully McLaughlin Sharmistha Das
CLAIMS, CHANGES, & TERMINATIONS Chris Haile Tully McLaughlin Sharmistha Das 205 Agenda: Contract Changes Claims Administration and Procedure Terminations 206 Contract Changes Administration of Changes
More informationSubcontract and Material Vendor Costs. Steven M. Masiello Gale R. Monahan January 13, 2015
Subcontract and Material Vendor Costs Steven M. Masiello Gale R. Monahan January 13, 2015 mckennalong.com Subcontractor Cost Allowability Standards for Government Subcontracting DCMA/DCAA Subcontract Cost
More informationKey to Profitability
Key to Profitability Understanding Indirect Cost Allocation Rates Sam Davidson President, GovConConsulting2013, LLC govconconsulting2013@gmail.com/703-303-2701 Do you REALLY know what your products or
More informationSession 3 by Zoltán Záhonyi, FIDIC AIT,
Session 3 by Zoltán Záhonyi, FIDIC AIT, zoltan.zahonyi@zandpartners.com Contents of Session 3 Session 3: FIDIC 1999 Red Book Part 2 The Quality Issues (Plant, Materials and Workmanship) The Time is of
More informationAIA Document A Exhibit B
AIA Document A141-2004 Exhibit B Determination of the Cost of the Work for the following PROJECT: (Name and location or address) THE OWNER: (Name, legal status and address) THE DESIGN-BUILDER: (Name, legal
More informationCONSTRUCTION SCHEDULE DELAYS
Federal Publications - Construction Schedule Delays Washington, DC November, 2014 CONSTRUCTION SCHEDULE DELAYS Jessica Haire Fox Rothschild LLP Phone: 202-461-3109 E-mail: jhaire@foxrothschild.com What
More informationSHORT FORM STANDARD SUBCONTRACT. This Agreement is made this day of, 20, between
SHORT FORM STANDARD SUBCONTRACT This Agreement is made this day of, 20, between (Contractor) and (Subcontractor). The work described in Section I below shall be performed in accordance with the prime contract
More informationSAN ANTONIO WATER SYSTEM WATER AND/OR SANITARY SEWER CONSTRUCTION ADDITIONS TO THE GENERAL CONDITIONS FOR BEXAR COUNTY CDBG FUNDED PROJECTS
SAN ANTONIO WATER SYSTEM WATER AND/OR SANITARY SEWER CONSTRUCTION ADDITIONS TO THE GENERAL CONDITIONS FOR BEXAR COUNTY CDBG FUNDED PROJECTS The following changes are made to the Section II. Instruction
More informationHomewood Products Corporation, Selling Policy 100 Pittsburgh, PA USA Terms and Conditions of Sale
Homewood Products Corporation Selling Policy 100 Pittsburgh, PA USA15206 June 1, 2017 Terms and Conditions of Sale Products and Renewal Parts Domestic Sales Terms and Conditions of Sale Homewood Products
More informationGeneral Terms and Conditions of Sale
General Terms and Conditions of Sale April 2016 0 CONTENTS Clause Heading Page 1 Definitions and Interpretation...1 2 Basis of Contract...1 3 Description of the Goods and Services...2 4 Delivery and Acceptance
More informationDEFENSE ACQUISITION UNIVERSITY CON Negotiation and Administration of Supply Contracts
1 Given a complex fiscal law issue, and working in a team environment, generate a strategy which will resolve that issue. Interpret the major fiscal law statutes and regulations governing Federal contracting.
More informationMitigating Risk through Construction Contracts and Claims Avoidance
Mitigating Risk through Construction Contracts and Claims Avoidance By Jeremy S. Sharon, Esq. Wright, Fulford, Moorhead & Brown, P.A. 505 Maitland Avenue, Suite 1000 Altamonte Springs, Florida 32701 (407)
More informationRFP GENERAL TERMS AND CONDITIONS
RFP GENERAL TERMS AND CONDITIONS PUBLIC RECORD After an award is made, copies of the proposals will be available for public inspection, under the supervision of the City's Finance Department from 8:00
More information3.1.2 The Contractor shall perform the Work in accordance with the Contract Documents.
the portion of the Work affected by a material change. After the Owner furnishes the evidence, the Owner shall not materially vary such financial arrangements without prior notice to the Contractor. 2.2.2
More informationINDEPENDENT CONTRACTOR AGREEMENT
INDEPENDENT CONTRACTOR AGREEMENT This agreement is entered into as of, 2004, by and between Rensselaer Polytechnic Institute (hereinafter called Rensselaer"), a non-profit educational institution with
More informationAPPENDIX D PAGE 1 of 9. A. ACCESS TO RECORDS AND REPORTS 49 U.S.C. 5325; 18 CFR (i); 49 CFR
PAGE 1 of 9 Federal Transit Administration (FTA) Required Clauses for Operations Contracts under the 2011 Section 5310 Purchase of Service Contract for the Southeast NH RCC through COAST A. ACCESS TO RECORDS
More informationReal Estate Management Agreement
Real Estate Management Agreement (hereinafter referred to as "Owner") and Interchange Property Management (IPM) (hereinafter referred to as "Manager"), agree as follows: 1. The Owner hereby employs and
More informationGeneral conditions of contract 2016 for the supply of spare parts
General conditions of contract 2016 for the supply of spare parts AMT AG, Badstrasse 34, 5312 Döttingen (Switzerland) 1 General 1.1 The contract shall be deemed to have been entered into upon receipt of
More informationMARION COUNTY HEALTH SERVICES BUILDING RENOVATION PUBLIC IMPROVEMENT AGREEMENT
MARION COUNTY HEALTH SERVICES BUILDING RENOVATION PUBLIC IMPROVEMENT AGREEMENT THE CONTRACT IS BETWEEN: OWNER: MARION COUNTY A political subdivision of the state of Oregon And TBD Contractor (referred
More informationStandard Bid Terms Table of Contents
Table of Contents 1 GENERAL... 2 A SAMPLES... 2 B INTERPRETATION... 2 C FORM OF BID... 2 D BINDING BID... 2 E WITHDRAWAL OF BID... 2 F ACCEPTANCE OF BID... 3 G CONFLICTS OF INTEREST... 3 H PROTEST PROCEDURES...
More informationPurchase Order Terms and Conditions Commercial Contracts
1. ACCEPTANCE: Purchase Order Terms and Conditions This purchase order represents Company's offer to purchase the goods or services ordered strictly in accordance with its stated terms and conditions.
More informationPART 3. Comprehensive Agreement Between Department and Design-Builder
PART 3 Between Department and Design-Builder This COMPREHENSIVE AGREEMENT for the I-64 Hampton Roads Bridge-Tunnel Project (the Agreement ) is made as of [ ], 2019 (the Agreement Date ), by and between
More informationProject # and Name Subcontract Firm Name Subcontract #: Appendix F - Subcontract Terms and Conditions
ARTICLE 1 - SUBCONTRACTOR'S WORK AND SCHEDULE 1.1 WORK: Subcontractor agrees to furnish all supervision, labor, materials, tools, equipment, services, storage, and whatever else is required to perform
More informationCONSTRUCTION CLAIMS DISCLOSURE (NRS )
CONSTRUCTION CLAIMS DISCLOSURE (NRS 113.135) This Construction Claims Disclosure is made as required by NRS 113.135 in contemplation of a Purchase and Sale Agreement (the "Agreement") which may be entered
More informationContract Pricing Reference Guides Volume 3 Chapter 9 Analysis of Indirect Costs
Contract Pricing Reference Guides Volume 3 Chapter 9 Analysis of Indirect Costs 9.0 - Chapter Introduction 9.1 - Identifying Pools And Bases For Rate Development o 9.1.1 - Identifying Indirect Cost Pools
More informationRisk Identification & Contract Risk Management
Risk Identification & Contract Risk Management In the world of geospatial Presenters Bob Hanson Senior Vice President, Michael Baker International Geospatial Practice Leader 717 221-2005 rhanson@mbakerintl.com
More informationPURCHASE ORDER TERMS & CONDITIONS
PO Terms & Conditions (Version 1: 2014/07) P a g e 1 PURCHASE ORDER TERMS & CONDITIONS 1. TERMS OF AGREEMENT The purchase order, together with these terms and conditions, and any attachments and exhibits,
More informationTERMS AND CONDITIONS
TERMS AND CONDITIONS 1. ENTIRE AGREEMENT. This Quotation ("Quotation"), including all of the terms and provisions set forth on both sides hereof, constitutes the entire agreement between Buyer, as identified
More informationIn every contract over $10,000, the provisions in A. and B. below apply: A. During the performance of this contract, the vendor agrees as follows:
The following Terms and Conditions are MANDATORY and shall be incorporated verbatim in any contract award: 1. APPLICABLE LAWS AND COURTS: This solicitation and any contract resulting from this solicitation
More informationAUTOTOOL, INC. TERMS AND CONDITIONS OF SALE
AUTOTOOL, INC. TERMS AND CONDITIONS OF SALE The following terms and conditions of sale as they appear at www.autotoolinc.com at the time of sale (the Terms and Conditions ) govern the sale of all materials,
More informationJob Acceleration: What Does It Really Cost You?
Job Acceleration: What Does It Really Cost You? Suing for damages caused by acceleration is not as common as suing for damages caused by delays. But that tide is turning, and you need to know how to document
More informationWESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT
WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT This Equipment Purchase Agreement ( Agreement ) is entered into this day of, 20, by and between the Western Riverside Council of Governments,
More informationGENERAL CONDITIONS OF ELECTRICAL INSTALLATION CONTRACT
GENERAL CONDITIONS OF ELECTRICAL INSTALLATION CONTRACT 1. Definition and Duration These conditions form part of a quotation submitted by the Contractor to the Client named in the quotation. The Contractor
More informationCOST AND PRICING: NO CONTRACT IS REALLY FINAL. Terry Albertson Skye Mathieson Liz Buehler
COST AND PRICING: NO CONTRACT IS REALLY FINAL Terry Albertson Skye Mathieson Liz Buehler 79 Three Phases Proposal Performance and Billing Final Payment 80 Proposal Forward pricing rates Labor rates Indirect
More informationOlympus Global - Standard Terms and Conditions of Sale (edition May 2010)
Olympus Global - Standard Terms and Conditions of Sale (edition May 2010) 1. INTERPRETATION 1.1 Definitions. In these Conditions, the following definitions apply: Business Day: a day (other than a Saturday,
More informationSTANDARD CONTRACT PROVISIONS
Government of the District of Columbia STANDARD CONTRACT PROVISIONS For Use With Specifications for District of Columbia Government Construction Projects (Revised January 2007) PLEASE RETAIN FOR YOUR REFERENCE
More informationServices Agreement - Terms and Conditions. Gold Support Premier Enterprise Support Services
Services Agreement - Terms and Conditions Gold Support Premier Enterprise Support Services BY ACCEPTING THE SERVICES AND SUPPORT DESCRIBED ON YOUR INVOICE, YOU AGREE TO BE BOUND BY AND ACCEPT THE TERMS
More informationPURCHASE ORDER TERMS AND CONDITIONS 1. ACCEPTANCE, SCOPE. This Purchase Order is for the purchase of goods, services, or both as described on the
PURCHASE ORDER TERMS AND CONDITIONS 1. ACCEPTANCE, SCOPE. This Purchase Order is for the purchase of goods, services, or both as described on the face of this document (collectively, Goods ) and is issued
More information