1 Scotland - Norway Technology Partnership Event 2015 Key legal issues in a decommissioning project 26 November 2015 From Kluge; Partner Thomas Abrahamsen (Head of Energy Practice Group) Disclaimer: The content of this presentation can not be relied upon as legal advice from Kluge. Kluge will not accept any liability, in whatever form or shape, in connection with this presentation.

2 Three topics Legal framework Differences between decom and offshore fabrication Contract issues relevant for UKCS and NCS

3 Legal framework Norwegian legal framework: Removal is a statutory obligation resting on the licensee and the owner, cf. Chapter 5 of the Norwegian Petroleum Act International legal framework: Law of the Sea Convention, OSPAR Convention, IMO Guidelines Main rule: The entire installation shall be removed Exception: Large steel frame and concrete structures No capital in the license for decom costs to be covered by cash calls during the project Licensee carry full ownership risk until the decom project is completed carries counterparty risk for Contractor (financial risk) Removal contracts are in-house standards No standard contract (agreed form) developed yet Existing removal contracts are based on standard contracts used by the industry (NF 07, NTK MOD 07, NCS 05, LOGIC Marine Construction (with appendix)) LOGIC planned to draft a decom standard status unknown Standard format - EPCI approach = EPRD contract (Engineering, Preparation, Removal and Disposal) with one Contractor using subcontractors HSE «see to duty»: Decom projects involves complex and difficult offshore work (heavy lift, «hot work», etc.). Safe to assume that the operator potentially can have an opinion as to exactly how the scope of work is executed. Example: Yme was deemed by the operator not to be safe. Dispute with Contractor SBM

4 Decom is not reversed fabrication significant differences Difference in scope of work: Regular offshore contract (NF 07, NTK 07 MOD and NCS 05) scope is to deliver a physical object + related services Decom project: Basically a service contract Why bother with this difference? Can be important in many situations transfer of risk, warranties, guarantees, insurance, etc. Important to remember this fundamental difference in the contract drafting Most of decom work scope is done offshore whereas in a construction project hook up and installation is done offshore but bulk of construction in done onshore The facility has probably been changed, modified, developed, re-built, etc. over a period of years. Current owner will have difficulties in presenting updated and correct and complete information to the contractor in terms of the current status of the facility. Marine spread (heavy lifting vessels) constitutes a significant part of the total cost and vessels may be unique/difficult to replace Progress is of less importance in the removal contracts compared to fabrication contracts (no first oil, more sensitive to VOR s, less willing to pay for that perfect solution )

5 Drafting the Scope of Work (SoW) Either Catch all -defining the performance: The work required for removing the installation Minimizing the need for amendments/clarifications through right to instruct Seemingly, the result is a clarified work obligation although the scope of work is uncertain Significant compensation risk related to scope of work allocated to Contractor Leaving little room for VOR s (compensation and/or schedule) Or Detailed description of the installation to be removed, which and how the work shall be performed Less compensation risk related to scope of work allocated to Contractor Leaving more room for VOR s (compensation and/or schedule)

6 Drafting issues related to the marine spread (1) Is lump sum or firm prices for the heavy lifting vessel really lump sum or really firm? Standard solutions : Rig contracts: Time risk with Company Subsea projects: Time risk with Contractor (cause of delay will decide) Decom projects: Hybrid needs to be negotiated Our finding often the contract is not clear on this significant risk allocation (!) Example: Lump sum language used in the T&C s, however with estimate language in the compensation schedule how to interpret? Typical decom risk: What if the marine operation takes more time because Contractor has been given wrong or non complete information from Company about the condition of the facility prior to contact award?

7 Drafting issues related to the marine spread (2) Starting point: At the time of contract award the Company is not entire certain when they will be ready with preparatory works The Contractor (or vessel owner) has a number of projects and a limited number of vessels that can serve these projects Who decides the specific time of performance of the marine operation? Contractual obligation for the contractor to carry out the work within a time slot, or does the contractor have the freedom to choose when to carry out the work? Standard solution: Notifications procedures from Company for initiation of offshore operations + duty to offer designated vessel + caveat for availability of the spread (seldom substitute vessels) What does availability of the spread mean? Other campaigns when are they contracted (first come, best served?) Willful breach of contract chasing a more profitable contract (who is in control?) What if Company changes the time window? Negotiations on priority Our finding: Surprisingly this is often not clear in the contract. These matters should be explicitly addressed negotiated and regulated in the contract.

8 Allocation of risk for the condition of the installation (1) The facility has often been changed, modified, developed, re-built, etc. over a period of years. Current owner will have difficulties in presenting updated and correct and complete information to the contractor in terms of the current status of the facility Who to carry the risk for errors in drawings, specifications, etc. + unforeseen circumstances during the execution of the work? Market practice: Company will propose that Contractor assumes this risk Will present massive amounts of data to Contractor Understanding, planning and pricing the Scope of Work is made a duty for the Contractor Real contract issue: When can Contractor present a VOR?

9 Allocation of risk for the condition of the installation (2) Three variation order text examples from our review of the decom contracts The installation is as is Transfers significant risk to Contractor Firms up a lump sum approach No limitations? What about the principle of materially different cf. Sale of Goods Act Section 19? Variation order for conditions which are materially different from assumptions What is materially different? Delta between actual condition and the condition a professional and prudent contractor should have expected, given the available information Key word is extraordinary Variation order, unless the impediment could reasonable have been foreseen by an experienced contractor No materiality threshold More contractor friendly regime

10 Thank you for your attention!

11 Back up slides Compensation reimbursable or lump sum Weather risk Pre Removal Surveys The Company s contractual obligations Guarantee provisions Insurance 1

12 Compensation reimbursable or lump sum Decom contracts are often labelled as lump sum contracts, but they have some elements that are not lump sum Disposal of hazardous waste Marine spread Is lump sum the right compensation format for decom contracts? Relevant arguments Who knows the facility best often the Company (especially if owned over a period of many years) Which of the parties are better suited to make judgement calls about the scope of work, methods, etc. Is the Scope of Work firm enough to allow a lump sum pricing? To what extent has the Contractor being offered site visits and been able to understand the condition of the facility? Market conditions are the Contractors willing to take lump sum risk (or should they be)?

13 Weather risk Weather risk = not getting paid for downtime due to weather Contract needs to clarify weather risk NSC 05: Weather risk carried by Company Market practice: Often carried by Contractor Case: Is weather risk transferred when the operation is postponed? Summer campaign moved to winter. Is it necessary to distinguish between delay caused by the Contractor and delay caused by the Company? Caused by Contractor Contractor retains weather risk (time + cost) Caused by Company By choice For convenience For unforeseen circumstances Schedule consequences is a Company risk if caused by Company. What about compensation risk (not getting paid)?

14 Pre Removal Surveys Pre Removal Surveys is another tool Variations/Changes can be submitted in a limited period of time Advantage: Contractor is afforded some room to present change orders What is the downside what was the trade off? More strict regime afterwards?

15 The Company s contractual obligations Company needs to provide certain assistance Provide as-builts, documentation, etc. Access for on-site visits Removal plan important premise for scope of work Interface with authorities are responsible for all offshore operations of the license (including decom) Temporary plugging Shutting down production Prepare for decom Granting access to site when campaign starts Flotel, Heli-transport Our finding these Company duties are not properly reflected in the decom contracts Consequence: Contractor will have to rely on principle of reasonable assistance = risk related to VOR s, schedule, cost/profitability Contractor needs to be clear on what the Company is expected to do what, when, how + remedies if not

16 Guarantee provisions to be tailor made Application of Sales of Goods Act? General view within Norwegian offshore law the Act will apply for purchases What about decom contracts? Since this is mainly services this Act is not likely to apply No need for extensive guarantee provisions Decom project is a service rendered and the contract object is to be scrapped = necessary to re-write the standard guarantee provisions in existing standards

17 Insurance provisions Insurance provisions & knock for knock needs to be tailor made Standard offshore contracts = operator s CAR insurance protects both parties contractor is only exposed to a defined sum (deductible) Decom projects: A special insurance should be taken out, often by the operator, however with contractor having protection under the insurance policy

RMN. Offshore Decommissioning Conference P & A Rig Consortiums Cost Savings and Other Benefits

RMN. Offshore Decommissioning Conference P & A Rig Consortiums Cost Savings and Other Benefits RMN Offshore Decommissioning Conference 2017 P & A Rig Consortiums Cost Savings and Other Benefits About Rig Management Group (RMG) Rig Management Group ( RM ) established in 2006. Main activity : Establish

More information

Staff Paper Date October 2009

Staff Paper Date October 2009 IASB Meeting Agenda reference Appendix to Paper 7 Staff Paper Date October 2009 Project Liabilities amendments to IAS 37 Topic In June 2005, the Board published for comment an Exposure Draft of Proposed

More information

Guide. Commission Recommendation

Guide. Commission Recommendation Guide to the Commission Recommendation on the management of financial resources for the decommissioning of nuclear installations, spent fuel and radioactive waste (2006/851/Euratom) 1 2 Objective of the

More information

Upstream Risks. 18 th September 2013, Oslo, Norway. June 15, 2009 PAGE 1

Upstream Risks. 18 th September 2013, Oslo, Norway. June 15, 2009 PAGE 1 Upstream Risks 18 th September 2013, Oslo, Norway PAGE 1 Agenda Hess Upstream Risks Commercial/Political Exploration/Technical Construction Operations Pollution Insurability Decommissioning Risk Allocation

More information

STANDARD TERMS & CONDITIONS for Construction, Engineering & Electrical Works

STANDARD TERMS & CONDITIONS for Construction, Engineering & Electrical Works STANDARD TERMS & CONDITIONS for Construction, Engineering & Electrical Works Table of Contents 1. DEFINITIONS...2 2. CONTRACT FORMATION...2 3. GENERAL OBLIGATIONS...2 4. VARIATION...2 5. CONTRACT PRICE

More information

6 December Company presentation

6 December Company presentation 6 December 2017 Company presentation Disclaimer All statements in this presentation other than statements of historical fact are forward-looking statements, which are subject to a number of risks, uncertainties,

More information

Standard Trading Terms and Conditions

Standard Trading Terms and Conditions Standard Trading Terms and Conditions 1. Interpretation 1.1. In these Terms and Conditions: 1.1.1. Agreement means the definition in clause 2.2 below. 1.1.2. Aqua-Tech means Baronial Pty Ltd (ACN 146 402

More information

VIRIDOR WASTE MANAGEMENT LIMITED TERMS AND CONDITIONS OF TRADE

VIRIDOR WASTE MANAGEMENT LIMITED TERMS AND CONDITIONS OF TRADE VIRIDOR WASTE MANAGEMENT LIMITED TERMS AND CONDITIONS OF TRADE The Supplier will collect/accept Waste for disposal and will supply/deliver quarried or other material subject to the conditions set out below:

More information

Office for Capital Facilities

Office for Capital Facilities Office for Capital Facilities Guidance Document CLC8 Issued: April 2013 Revised: June 2013 Administration of Construction Field Orders A reference guide to assist in the management of changes on construction

More information

General Terms of Project lifting/transport involving engineering

General Terms of Project lifting/transport involving engineering General Terms of Project lifting/transport involving engineering 1. General provisions 1.1. General provisions and scope 1.1.1. These General Terms applies when the Lift & Transport Department of Lindø

More information

Subcontract Flowdown Best Practices from Both the Prime and Subcontractor Perspective

Subcontract Flowdown Best Practices from Both the Prime and Subcontractor Perspective Subcontract Flowdown Best Practices from Both the Prime and Subcontractor Perspective Breakout Session #: C16 Presented by: Philip R. Seckman Christopher W. Myers Date: July 22, 2013 Time: 4:00-5:15 Agenda

More information

The New NZS 3910:2013

The New NZS 3910:2013 The New NZS 3910:2013 Introduction On the 1 st of October 2013, NZS 3910:2013 Conditions of Contract for Building and Civil Engineering Construction was released by New Zealand Standards. This is the first

More information

Joint OHS Committees in the NL Offshore Area

Joint OHS Committees in the NL Offshore Area Joint OHS Committees in the NL Offshore Area Supplementary Information/Clarification to OHS Committee Training August 2009 Purpose of this presentation To emphasize that the purpose and functioning of

More information

SIGMA Public Procurement Training Manual. Update 2015

SIGMA Public Procurement Training Manual. Update 2015 SIGMA Public Procurement Training Manual Update 2015 Module G 2 Rue André Pascal 75775 Paris Cedex 16 France mailto:sigmaweb@oecd.org Tel: +33 (0) 1 45 24 82 00 Fax: +33 (0) 1 45 24 13 05 www.sigmaweb.org

More information

Treaty. Politics, Economics & Society

Treaty. Politics, Economics & Society Politics, Economics & Society On its discovery in June 1971, the Frigg Field was the largest known offshore gas-field, and was then the most northerly in the North Sea. The North Sea is a harsh environment

More information

Guidelines for Geothermal Projects Content of Standard Contracts

Guidelines for Geothermal Projects Content of Standard Contracts Guidelines for Geothermal Projects Content of Standard Contracts Doc. No.: WPDK2017-RE028 Date: 18-12-2017 Revision: Original Content of Standard Contracts WPDK2017-RE028 2/10 Revisions Rev. Date Description

More information

REPORT On the public consultation on new initiative regarding dismantling of ships

REPORT On the public consultation on new initiative regarding dismantling of ships EUROPEAN COMMISSION DIRECTORATE-GENERAL ENVIRONMENT Directorate G - Sustainable Development and Integration ENV.G.4 - Sustainable Production & Consumption REPORT On the public consultation on new initiative

More information

Slide 1. Slide 2. Slide 3 LEARNING OBJECTIVES WHAT S THE DIFFERENCE? PERSONAL AND PROFESSIONAL EXCELLENCE

Slide 1. Slide 2. Slide 3 LEARNING OBJECTIVES WHAT S THE DIFFERENCE? PERSONAL AND PROFESSIONAL EXCELLENCE Slide 1 PERSONAL AND PROFESSIONAL EXCELLENCE Contract Administration Beginning With the End in Mind David E. Nash, CPPO, CPPB 50 TH ANNUAL CONFERENCE MAY 24-27, 2017 ORLANDO, FLORIDA Slide 2 LEARNING OBJECTIVES

More information

DECOM NORTH SEA and SOCIETY OF UNDERWATER TECHNOLOGY SALVAGE AND DECOMMISSIONING REVIEW OF NEW CONTRACT TEMPLATE OPTIONS

DECOM NORTH SEA and SOCIETY OF UNDERWATER TECHNOLOGY SALVAGE AND DECOMMISSIONING REVIEW OF NEW CONTRACT TEMPLATE OPTIONS DECOM NORTH SEA and SOCIETY OF UNDERWATER TECHNOLOGY SALVAGE AND DECOMMISSIONING REVIEW OF NEW CONTRACT TEMPLATE OPTIONS Executive Summary Decommissioning is an obligation and liability rather than an

More information

THE HONG KONG INSTITUTE OF SURVEYORS PQSL EVENT ON 7 NOVEMBER 2016

THE HONG KONG INSTITUTE OF SURVEYORS PQSL EVENT ON 7 NOVEMBER 2016 THE HONG KONG INSTITUTE OF SURVEYORS PQSL EVENT ON 7 NOVEMBER 2016 INTRODUCTION TO THE STANDARD FORM OF CONTRACT FOR MAINTENANCE AND RENOVATION WORKS FOR USE IN HONG KONG, FIRST EDITION 2013 Sr. TANG Ki

More information

(Last amended 18 December 2017, cf. page 4)

(Last amended 18 December 2017, cf. page 4) REGULATIONS RELATING TO MANAGEMENT AND THE DUTY TO PROVIDE INFORMATION IN THE PETROLEUM ACTIVITIES AND AT CERTAIN ONSHORE FACILITIES (THE MANAGEMENT REGULATIONS) (Last amended 18 December 2017, cf. page

More information

How Project Management can add value to contract negotiations

How Project Management can add value to contract negotiations How Project Management can add value to contract negotiations Lessons Learned from a clean up project Robert Gallmann, Senior Legal Counsel NOVARTIS Pharma AG q Waste water treatment plant operated by

More information

Pareto Oil and Offshore Conference CEO Ivar Brandvold

Pareto Oil and Offshore Conference CEO Ivar Brandvold Pareto Oil and Offshore Conference 2017 CEO Ivar Brandvold Disclaimer This presentation has been produced by Fred. Olsen Energy ASA (the "Company") based on information which is publicly available. This

More information

On How Not to Draft Agreements

On How Not to Draft Agreements Things I Have Learned As An Arbitrator On How Not to Draft Agreements Barbara Kinosky Centre Law & Consulting Agenda and Sources Agenda 1. Advantages and Risks 2. Key Questions & Considerations 3. Related

More information

Booklet Layby. Buying on layby

Booklet Layby. Buying on layby Booklet Layby Buying on layby 2 Contents What is layby 2 Cancelling a layby 5 General questions 9 Store closure 10 1 What is layby? Layby is a popular way to buy goods when you can t afford to pay for

More information

Contract Modifications

Contract Modifications Brief 38 Public Procurement September 2016 Contract Modifications CONTENTS Introduction Permitted or non-substantial modifications of contracts during their term no procurement procedure required o Modifications

More information

GENERAL SALES TERMS BIOPROCESS PILOT FACILITY. 1 Definitions

GENERAL SALES TERMS BIOPROCESS PILOT FACILITY. 1 Definitions GENERAL SALES TERMS BIOPROCESS PILOT FACILITY 1 Definitions 1. In these general sale and supply Terms the following terms shall have the meaning set out below. (a) BPF: the Dutch limited liability company

More information

Section 7. General Conditions of Contract for the Procurement of Works

Section 7. General Conditions of Contract for the Procurement of Works Section 7. General Conditions of Contract for the Procurement of Works Table of Clauses A. General...3 1. Definitions...3 2. Interpretation...5 3. Language and Law...5 4. Project Manager s Decisions...5

More information

Pareto s oil and offshore conference. Jan Arve Haugan, President & CEO

Pareto s oil and offshore conference. Jan Arve Haugan, President & CEO Pareto s oil and offshore conference Jan Arve Haugan, President & CEO Well positioned for future market opportunities 1) Leading contractor within proven track record 2) Competitive position strengthened

More information

INVERCO COMMENTS ON LEGISLATIVE STEPS FOR THE PACKAGED RETAIL INVESTMENT PRODUCTS INITIATIVE

INVERCO COMMENTS ON LEGISLATIVE STEPS FOR THE PACKAGED RETAIL INVESTMENT PRODUCTS INITIATIVE INVERCO COMMENTS ON LEGISLATIVE STEPS FOR THE PACKAGED RETAIL INVESTMENT PRODUCTS INITIATIVE 1.- INTRODUCTION INVERCO (Spanish Association of Collective Investment Schemes and Pension Funds) represents

More information

Nutreco General Purchase Terms and Conditions

Nutreco General Purchase Terms and Conditions Nutreco General Purchase Terms and Conditions Article 1 - Definitions Agreement Conditions Contract Nutreco Order Products Seller : The purchase agreement between Nutreco and the Seller : The General Purchase

More information

CONDITIONS PRECEDENT TO LIABILITY IN INSURANCE CONTRACTS

CONDITIONS PRECEDENT TO LIABILITY IN INSURANCE CONTRACTS CONDITIONS PRECEDENT TO LIABILITY IN INSURANCE CONTRACTS PART TWO The Impact of the Insurance Act 2015 ANDREW J. TOBIN Cozen O Connor Solicitors & Registered Foreign Lawyers* 140 Fenchurch Street 3 rd

More information

Protocol of meeting Møte dato Date of meeting 2/

Protocol of meeting Møte dato Date of meeting 2/ 1 of 6 Saipem & Protocol of meeting Møte dato Date of meeting /11-005 Møte sted Location of Meeting HELL MØTETS FORMÅL: PURPOSE OF MEETING: Månedlig møte mellom Saipem SpA, Norwegian branch og S.E.A Monthly

More information

Exam Spring 2009: Marine Insurance

Exam Spring 2009: Marine Insurance Exam Spring 2009: Marine Insurance Some general comments on the student group, the course and the material The course in marine insurance is very new, and has only been offered three times. It is not an

More information

No.: 071 Established: Revision no.: 2 Rev. date: Page: 2

No.: 071 Established: Revision no.: 2 Rev. date: Page: 2 071 Norwegian Oil and Gas Recommended guidelines for additional information from the operators for the annual accounts and audit of the licence accounts Translated version No.: 071 Established: 01.01.2001

More information

CONTRACT FOR THE PROCUREMENT OF SERVICES FOR THE BERGEN- KIRKENES COASTAL ROUTE FOR THE PERIOD 1 JANUARY 2012 TO 31 DECEMBER 2019

CONTRACT FOR THE PROCUREMENT OF SERVICES FOR THE BERGEN- KIRKENES COASTAL ROUTE FOR THE PERIOD 1 JANUARY 2012 TO 31 DECEMBER 2019 CONTRACT FOR THE PROCUREMENT OF SERVICES FOR THE BERGEN- KIRKENES COASTAL ROUTE FOR THE PERIOD 1 JANUARY 2012 TO 31 DECEMBER 2019 l Introduction Based on open competitive bidding performed for the procurement

More information

November 2016 Revision

November 2016 Revision APPENDIX C - SAFETY AND ENVIRONMENTAL ISSUES LICENSING AND OPERATORSHIP LICENSING AND OPERATORSHIP The Offshore Petroleum Licensing (Offshore Safety Directive) Regulations 2015 (the OSD Licensing Regulations)

More information

Overview of UK Offshore Oil and Gas Regulation. Andrew Taylor Head, Offshore Environmental Inspectorate DECC Energy Development Unit February 2016

Overview of UK Offshore Oil and Gas Regulation. Andrew Taylor Head, Offshore Environmental Inspectorate DECC Energy Development Unit February 2016 Overview of UK Offshore Oil and Gas Regulation Andrew Taylor Head, Offshore Environmental Inspectorate DECC Energy Development Unit February 2016 1988 Piper Alpha disaster explosion on Occidental s platform

More information

10 January SEB - Nordic Seminar 2018

10 January SEB - Nordic Seminar 2018 10 January 2018 SEB - Nordic Seminar 2018 Disclaimer All statements in this presentation other than statements of historical fact are forward-looking statements, which are subject to a number of risks,

More information

OSPAR Decision 98/3 on the Disposal of Disused Offshore Installations RECALLING the Convention for the Protection of the Marine Environment of the North East Atlantic, in particular Articles 2 and 5 of

More information

Experiences of FPSO Construction/Conversion Disputes: Learning the Lessons to Protect Budgets

Experiences of FPSO Construction/Conversion Disputes: Learning the Lessons to Protect Budgets Experiences of FPSO Construction/Conversion Disputes: Learning the Lessons to Protect Budgets 19 February 2019 K&L Gates, Jeremy Farr, Partner Copyright 2018 by K&L Gates LLP. All rights reserved. Petrojarl

More information

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015

The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 The Toler Firm LLC A Construction Law Firm Timothy N. Toler September 23, 2015 Negotiating 8 Key Contract Clauses from the Contractor s Perspective (Part 1 of 2) 1 This is the first of a two-part overview

More information

SOUTHERN RESPONSE CANTERBURY EARTHQUAKE RECONSTRUCTION PROJECT GENERAL CONDITIONS OF CONTRACT FOR HOUSING REBUILD AND REPAIRS

SOUTHERN RESPONSE CANTERBURY EARTHQUAKE RECONSTRUCTION PROJECT GENERAL CONDITIONS OF CONTRACT FOR HOUSING REBUILD AND REPAIRS SOUTHERN RESPONSE CANTERBURY EARTHQUAKE RECONSTRUCTION PROJECT GENERAL CONDITIONS OF CONTRACT FOR HOUSING REBUILD AND REPAIRS TABLE OF CONTENTS Background 1 1. Introduction 1 2. Contract Works 1 3. Project

More information

Dolphin Group ASA. SEB Nordic Seminar - 8 th January Atle Jacobsen (CEO) & Erik Hokholt (CFO)

Dolphin Group ASA. SEB Nordic Seminar - 8 th January Atle Jacobsen (CEO) & Erik Hokholt (CFO) Dolphin Group ASA SEB Nordic Seminar - 8 th January 2015 Atle Jacobsen (CEO) & Erik Hokholt (CFO) 2 Disclaimer This presentation includes and is based, inter alia, on forward-looking information and statements

More information

Splitting an EPC Contract

Splitting an EPC Contract Investing in Infrastructure International Best Practice in Project and Construction Agreements January 2016 Splitting an EPC Contract www.pwc.com.au The hidden dangers of split EPC Contracts One innovation

More information

Off-Site Manufacturing

Off-Site Manufacturing Off-Site Manufacturing The Legal Implications YORhub Conference 15 th November 2018 Dr Julie Morrissy A word of warning MODERNISE OR DIE 1 Modernise or die 2016 - The Farmer Review of the UK Construction

More information

General Terms & Conditions of Sale - December 2009

General Terms & Conditions of Sale - December 2009 General Terms & Conditions of Sale - December 2009 1. Area of Application 1.1 All Orders accepted by Eurofins Scientific, Inc. or any of its subsidiaries or affiliates (collectively, ES ) will be governed

More information

Fact Sheet 14 - Partnership Agreement

Fact Sheet 14 - Partnership Agreement - Partnership Agreement Valid from Valid to Main changes Version 2 27.04.15 A previous version was available on the programme website but all projects must use this version. Core message: It is a regulatory

More information

Single Source Contract Regulations 2014 Guidance Chapter 3 Pricing a Qualifying Defence Contract: The Cost Element

Single Source Contract Regulations 2014 Guidance Chapter 3 Pricing a Qualifying Defence Contract: The Cost Element Single Source Contract Regulations 2014 Guidance Chapter 3 Pricing a Qualifying Defence Contract: The Cost Element Purpose 1. The guidance in this chapter relates to a Qualifying Defence Contract (QDC)

More information

Acquisition of Ferguson Group. 9 September 2014

Acquisition of Ferguson Group. 9 September 2014 Acquisition of Ferguson Group 9 September 2014 Strategic highlights Continuing our expansion in specialist containers Ferguson Group is a leading provider of container solutions (mostly cargocarrying units)

More information

BEPS ACTION 8 - IMPLEMENTATION GUIDANCE ON HARD-TO- VALUE INTANGIBLES

BEPS ACTION 8 - IMPLEMENTATION GUIDANCE ON HARD-TO- VALUE INTANGIBLES BEPS ACTION 8 - IMPLEMENTATION GUIDANCE ON HARD-TO- VALUE INTANGIBLES PUBLIC DISCUSSION DRAFT 30 June 2017 Copenhagen Economics welcomes the opportunity to comment on the OECD s Discussion Draft on Implementation

More information

SOLICITATION ADDENDUM

SOLICITATION ADDENDUM SOLICITATION ADDENDUM Date: 10-6-17 Subject: Provide Maintenance Services at SCI-Pittsburgh Solicitation Number: 6100043842 Due Date/Time: 10-12-17/2:00PM Addendum Number: 2 To All Suppliers: The Commonwealth

More information

Tuesday, March 17, 2015 Houston, TX. 10:30 11:45 a.m. BUILD YOUR HOUSE ON A SOLID FOUNDATION: BASIC CONTRACT DRAFTING FOR THE OIL FIELD

Tuesday, March 17, 2015 Houston, TX. 10:30 11:45 a.m. BUILD YOUR HOUSE ON A SOLID FOUNDATION: BASIC CONTRACT DRAFTING FOR THE OIL FIELD Tuesday, March 17, 2015 Houston, TX 10:30 11:45 a.m. BUILD YOUR HOUSE ON A SOLID FOUNDATION: BASIC CONTRACT DRAFTING FOR THE OIL FIELD Presented by Harold J. Flanagan, J.D. Partner Flanagan Partners LLP

More information

Contents. chapter 1 Introduction chapter 2 The sources of law chapter 3 The insurance contract... 36

Contents. chapter 1 Introduction chapter 2 The sources of law chapter 3 The insurance contract... 36 [start forord] Preface The first edition of this handbook on hull insurance in 2007 was based on the Norwegian Marine Insurance Plan 1996 Version 2007. This second edition is based on the present version

More information

23 August Q results and market update

23 August Q results and market update 23 August 2018 Q2 2018 results and market update Disclaimer All statements in this presentation other than statements of historical fact are forward-looking statements, which are subject to a number of

More information

Professor dr. juris Trine-Lise Wilhelmsen. The Nordic Marine Insurance Plan 2013 Version 2019, Cl. 2-8 and 2-9

Professor dr. juris Trine-Lise Wilhelmsen. The Nordic Marine Insurance Plan 2013 Version 2019, Cl. 2-8 and 2-9 Professor dr. juris Trine-Lise Wilhelmsen The Nordic Marine Insurance Plan 2013 Version 2019, Cl. 2-8 and 2-9 Background The previous regulation unclear about The exclusion for State intervention in 2-8:

More information

Norwegian tax regime for petroleum exploration - Case No 81036

Norwegian tax regime for petroleum exploration - Case No 81036 EFTA Surveillance Authority Rue Belliard 35 1040 Brussels, Belgium Your ref Our ref Date 17/3578-09.02.2018 Norwegian tax regime for petroleum exploration - Case No 81036 1. INTRODUCTION We refer to the

More information

Brexit considerations FOR BUSINESS CONTRACTS

Brexit considerations FOR BUSINESS CONTRACTS Brexit considerations FOR BUSINESS CONTRACTS d 1 Attorney advertising. Prior results do not guarantee a similar outcome. 2 With just over a year to Brexit, slated for 11.00pm on 29 March 2019, it is time

More information

Final Report Draft regulatory technical standards on indirect clearing arrangements under EMIR and MiFIR

Final Report Draft regulatory technical standards on indirect clearing arrangements under EMIR and MiFIR Final Report Draft regulatory technical standards on indirect clearing arrangements under EMIR and MiFIR 26 May 2016 ESMA/2016/725 Table of Contents 1 Executive Summary... 3 2 Indirect clearing arrangements...

More information

Bergen vogtwiig.no Oslo Trondheim Singapore. Advokatfirmaet Vogt & Wiig AS 11/12/09

Bergen vogtwiig.no Oslo Trondheim Singapore. Advokatfirmaet Vogt & Wiig AS 11/12/09 Bergen vogtwiig.no Oslo Trondheim Singapore 1 Termination of Shipbuilding Contracts Possibilities and pitfalls Erlend Lous, partner Advokatfirmaet Vogt & Wiig AS 2 Background Happy Go Lucky in a booming

More information

DET TEKNISK-NATURVITENSKAPELIGE FAKULTET MASTEROPPGAVE. Line Myhre, Sigurd Ur, Atle Øglend

DET TEKNISK-NATURVITENSKAPELIGE FAKULTET MASTEROPPGAVE. Line Myhre, Sigurd Ur, Atle Øglend DET TEKNISK-NATURVITENSKAPELIGE FAKULTET MASTEROPPGAVE Studieprogram/spesialisering: Masterstudium i Industriell Økonomi Spesialisering i kontraktsadministrasjon og reservoar. Forfatter: Fagansvarlig:

More information

DISCUSSION PAPER TAX IMPLICATIONS RELATED TO THE IMPLEMENTATION OF FRS 116: PROPERTY, PLANT AND EQUIPMENT

DISCUSSION PAPER TAX IMPLICATIONS RELATED TO THE IMPLEMENTATION OF FRS 116: PROPERTY, PLANT AND EQUIPMENT The Malaysian Institute of Certified Public Accountants DISCUSSION PAPER TAX IMPLICATIONS RELATED TO THE IMPLEMENTATION OF FRS 116: PROPERTY, PLANT AND EQUIPMENT Prepared by: Joint Tax Working Group on

More information

Terms & Conditions Supply of Goods or Services

Terms & Conditions Supply of Goods or Services Terms & Conditions Supply of Goods or Services 1. DEFINITIONS In these terms and conditions: Agreement means an agreement between the Purchaser and Supplier for the supply of Goods or Services constituted

More information

comments on Consultation Paper 26 Jul 2012

comments on Consultation Paper 26 Jul 2012 European Association of Co-operative Banks Groupement Européen des Banques Coopératives Europäische Vereinigung der Genossenschaftsbanken European Association of Co-operative Banks comments on Consultation

More information

Thinking about the Deffered Retirement Option Program? Read this report first!

Thinking about the Deffered Retirement Option Program? Read this report first! Thinking about the Deffered Retirement Option Program? Read this report first! The information provided herein is for general reference purposes only. It is not approved or endorsed by the Florida Retirement

More information

I N V I T A T I O N T O B I D B I D # DOOR AND WINDOW REPLACEMENT AT SOUTH PORTLAND SCHOOLS

I N V I T A T I O N T O B I D B I D # DOOR AND WINDOW REPLACEMENT AT SOUTH PORTLAND SCHOOLS I N V I T A T I O N T O B I D B I D # 1 0-17 FINANCE DEPARTMENT GREGORY N. L HEUREUX Finance Director KRISTIE BRADBURY Deputy Finance Director COLLEEN C. SELBERG Purchasing Agent DOOR AND WINDOW REPLACEMENT

More information

WARRANTY PACKAGE. The future of TERMITE PROTECTION today

WARRANTY PACKAGE. The future of TERMITE PROTECTION today WARRANTY PACKAGE The future of TERMITE PROTECTION today For BUILDERS/HOME OWNERS who have installed a Termguard Reticulation System This package includes: Your Certificates of Installation, Application

More information

Motorpal Annual Membership Subscription Promotional Media Services. Terms and Conditions. Description

Motorpal Annual Membership Subscription Promotional Media Services. Terms and Conditions. Description Motorpal Annual Membership Subscription Promotional Media Services Terms and Conditions Description The Motorpal product is owned and marketed by Promotional Media Services Limited which is a registered

More information

LABOUR AND LEGAL AFFAIRS & CORPORATE SOCIAL RESPONSIBILITY (CSR)

LABOUR AND LEGAL AFFAIRS & CORPORATE SOCIAL RESPONSIBILITY (CSR) LABOUR AND LEGAL AFFAIRS & CORPORATE SOCIAL RESPONSIBILITY (CSR) Karoline L. Bøhler Attorney-at-Law & CSR Manager 13.01.16 LABOUR AFFAIRS NSA is a major employer organisation representing shipping companies

More information

May IFRIC Interpretation. IFRIC 21 Levies

May IFRIC Interpretation. IFRIC 21 Levies May 2013 IFRIC Interpretation IFRIC 21 Levies IFRIC Interpretation 21 Levies IFRIC Interpretation 21 Levies is published by the International Accounting Standards Board (IASB). Disclaimer: the IASB, the

More information

HIPAA BUSINESS ASSOCIATE AGREEMENT BEST PRACTICES: A COMPLIANCE SOLUTION FOR THE TICKING CLOCK AND THE DRACONIAN CIVIL AND CRIMINAL PENALTIES

HIPAA BUSINESS ASSOCIATE AGREEMENT BEST PRACTICES: A COMPLIANCE SOLUTION FOR THE TICKING CLOCK AND THE DRACONIAN CIVIL AND CRIMINAL PENALTIES HIPAA BUSINESS ASSOCIATE AGREEMENT BEST PRACTICES: A COMPLIANCE SOLUTION FOR THE TICKING CLOCK AND THE DRACONIAN CIVIL AND CRIMINAL PENALTIES January 23, 2014 I. Executive Summary I: The HIPAA Final Rule

More information

WINDSOR HIGH SCHOOL POOL HOUSE HVAC UNIT REPLACEMENT PROJECT 50 SAGE PARK ROAD. WINDSOR, CT

WINDSOR HIGH SCHOOL POOL HOUSE HVAC UNIT REPLACEMENT PROJECT 50 SAGE PARK ROAD. WINDSOR, CT INVITATION TO BID Contractor Services Associated with: WINDSOR HIGH SCHOOL POOL HOUSE HVAC UNIT REPLACEMENT PROJECT 50 SAGE PARK ROAD. WINDSOR, CT 06095 THIS IS AN INVITATION FOR BIDS AND THE TOWN RESERVES

More information

Place, as part of a concurrent rulemaking proceeding to implement House Bill (HB) 2259, 81st

Place, as part of a concurrent rulemaking proceeding to implement House Bill (HB) 2259, 81st Railroad Commission of Texas Page 1 of 43 The Railroad Commission adopts the repeal of 3.15, relating to Surface Casing To Be Left in Place, as part of a concurrent rulemaking proceeding to implement House

More information

Amendments to IAS 37 Provisions, Contingent Liabilities and Contingent Assets and IAS 19 Employee Benefits

Amendments to IAS 37 Provisions, Contingent Liabilities and Contingent Assets and IAS 19 Employee Benefits Amendments to IAS 37 Provisions, Contingent Liabilities and Contingent Assets and IAS 19 Employee Benefits 30 Cannon Street, London EC4M 6XH, UK Phone: +44 (20) 7246 6410, Fax: +44 (20) 7246 6411 Email:

More information

Viking Supply Ships AB (publ.) Q August Morten G. Aggvin IR Director Ulrik Hegelund CFO

Viking Supply Ships AB (publ.) Q August Morten G. Aggvin IR Director Ulrik Hegelund CFO Viking Supply Ships AB (publ.) Q2 2017 4 August 2017 Morten G. Aggvin IR Director Ulrik Hegelund CFO VSS AB Group result Q2 Second quarter Total revenue from continuing operations was MSEK 81 (217) EBITDA

More information

Offshore Activities responses to Questionnaire.

Offshore Activities responses to Questionnaire. Offshore Activities responses to Questionnaire. 1 and 2. Regional or bi-lateral Agreements relating to compensation for pollution from offshore activities. Korea. Party to an environmental agreement with

More information

Know Your Investment Risk (KYIR) PREMIUM CURRENCY INVESTMENTS

Know Your Investment Risk (KYIR) PREMIUM CURRENCY INVESTMENTS Know Your Investment (KYIR) PREMIUM CURRENCY INVESTMENTS A currency linked structure is a principal-at-risk investment where the payoff is linked to the performance of the exchange rate of a pair of currencies.

More information

International Financial Reporting Standard [Month, year] WORKING DRAFT 19 FEBRUARY International Financial Reporting Standard [X] Liabilities

International Financial Reporting Standard [Month, year] WORKING DRAFT 19 FEBRUARY International Financial Reporting Standard [X] Liabilities International Financial Reporting Standard [Month, year] WORKING DRAFT 19 FEBRUARY 2010 International Financial Reporting Standard [X] Liabilities References Next to each paragraph in this working draft

More information

INTERIM REPORT. for the third quarter 2018

INTERIM REPORT. for the third quarter 2018 INTERIM REPORT for the third quarter 2018 Quarterly highlights Increased investment in Reach Subsea. During July and August North Energy has acquired additional shares in Reach Subsea ASA (Reach) through

More information

Council. International Seabed Authority ISBA/16/C/6

Council. International Seabed Authority ISBA/16/C/6 International Seabed Authority Council Distr.: General 5 March 2010 Original: English Sixteenth session Kingston, Jamaica 26 April-7 May 2010 Proposal to seek an advisory opinion from the Seabed Disputes

More information

We would like to thank you for the opportunity to provide feedback on the draft Code and would be happy to discuss our comments.

We would like to thank you for the opportunity to provide feedback on the draft Code and would be happy to discuss our comments. File Name: 2017/30 25 October 2017 Insurance in Superannuation Working Group Project Management Office ISWG-PMO@kpmg.com.au Dear Sir/Madam, Consultation Paper: Insurance in Superannuation Code of Practice

More information

Risks and Risk Management of Renewable Energy Projects: The Case of Onshore and Offshore Wind Parks

Risks and Risk Management of Renewable Energy Projects: The Case of Onshore and Offshore Wind Parks Risks and Risk Management of Renewable Energy Projects: The Case of Onshore and Offshore Wind Parks Nadine Gatzert and Thomas Kosub Friedrich-Alexander University Erlangen-Nürnberg (FAU) This presentation

More information

WINDSOR NORTH WEST PARK NATURE CENTER ADDITION AND STRUCTURE PROJECT 145 LANG ROAD. WINDSOR, CT

WINDSOR NORTH WEST PARK NATURE CENTER ADDITION AND STRUCTURE PROJECT 145 LANG ROAD. WINDSOR, CT INVITATION TO BID Contractor Services Associated with: WINDSOR NORTH WEST PARK NATURE CENTER ADDITION AND STRUCTURE PROJECT 145 LANG ROAD. WINDSOR, CT 06095 THIS IS AN INVITATION FOR BIDS AND THE TOWN

More information

Automatic Enrolment Threshold for 2018/19 University of Sunderland vs Drossou potential impact on calculating a week s pay

Automatic Enrolment Threshold for 2018/19 University of Sunderland vs Drossou potential impact on calculating a week s pay To: At: Salaries and Wages Human Resources Pension Contacts All Employing Authorities Circular 1/2018 15 January 2018 Dear Colleagues Automatic Enrolment Threshold for 2018/19 University of Sunderland

More information

Clearing Member Disclosure Document Relating to Clearing of Securities Transactions 1

Clearing Member Disclosure Document Relating to Clearing of Securities Transactions 1 Markets and Securities Services I Direct Custody & Clearing Dated: 13 December 2017 Citibank Europe Plc Clearing Member Disclosure Document Relating to Clearing of Securities Transactions 1 1 The Guidance

More information

Standard forms of partnering contracts The ultimate contractual commitment? Part 4

Standard forms of partnering contracts The ultimate contractual commitment? Part 4 Standard forms of partnering contracts The ultimate contractual commitment? Part 4 This is the fourth in a series of articles being published in CES comparing the terms of some of the different standard

More information

Top 11½ Mistakes in License Agreements. Top 11½ Mistakes in License Agreements. Introduction. Explanation of Title. 10. Not Conducting Due Diligence

Top 11½ Mistakes in License Agreements. Top 11½ Mistakes in License Agreements. Introduction. Explanation of Title. 10. Not Conducting Due Diligence If If it it is is the the latter, latter, then then you you should should know know that that I I am am always always joking joking when when I I talk talk on on the the phone. phone. Adam Petravicius

More information

Aalborg Universitet. The transposition of the Environmental Liability Directive Cassotta, Sandra. Publication date: 2017

Aalborg Universitet. The transposition of the Environmental Liability Directive Cassotta, Sandra. Publication date: 2017 Aalborg Universitet The transposition of the Environmental Liability Directive Cassotta, Sandra Publication date: 2017 Link to publication from Aalborg University Citation for published version (APA):

More information

Fred. Olsen Energy ASA

Fred. Olsen Energy ASA Fred. Olsen Energy ASA Report for the 2 nd quarter 2017 and the 1 st half year 2017 Figures in USD FRED. OLSEN ENERGY ASA (FOE) REPORTS AN OPERATING PROFIT BEFORE DEPRECIATION (EBITDA) OF 29 MILLION FOR

More information

slaughter and may The matching premium

slaughter and may The matching premium slaughter and may BRIEFING MARCH 2012 Introduction Solvency II is intended to introduce greater levels of harmonisation in the prudential regulation of insurers across Europe. This includes greater harmonisation

More information

Landscape Construction. For Hard & Soft Landscaping. Standard Terms and Conditions of Contract. Artisan Hardscape Solutions Ltd

Landscape Construction. For Hard & Soft Landscaping. Standard Terms and Conditions of Contract. Artisan Hardscape Solutions Ltd Landscape Construction For Hard & Soft Landscaping Standard Terms and Conditions of Contract Artisan Hardscape Solutions Ltd 1.0 DEFINITIONS 1.1 Client means the individual or organisation who buys or

More information

ProMinent Verder B.V.

ProMinent Verder B.V. Terms & Conditions ProMinent Verder B.V. (30100444) Filed at the Chamber of Commerce on 29-01-2015 1. General 1.1 These terms and conditions use the following terms and definitions: Product: items, as

More information

Revenue recognition: Key considerations for the construction industry

Revenue recognition: Key considerations for the construction industry Revenue recognition: Key considerations for the construction industry November 9, 2017 Your instructors Brandon Maves Partner, National Construction Industry Leader Minneapolis, Minnesota Your instructors

More information

THE COLD WAR: JCT AND ADVERSE WEATHER CONDITIONS

THE COLD WAR: JCT AND ADVERSE WEATHER CONDITIONS Date Posted: 02 December 2011 ramskill martin s previous article The Cold War: NEC and Adverse Weather Conditions explained the NEC s strict contractual rules for assessing when adverse weather is a Compensation

More information

slaughter and may REVERSE TAKEOVERS INTRODUCTION

slaughter and may REVERSE TAKEOVERS INTRODUCTION slaughter and may The Financial S ervices Authority: Consultation Paper CP12/2 Amendments to the Listing Rules, Prospectus Rules, Disclosure Rules and Transparency Rules ( UKLA Rules or Rules ) BRIEFING

More information

Boa Offshore 12 September 2018 Pareto Oil & Offshore Conference Helge Kvalvik, CEO

Boa Offshore 12 September 2018 Pareto Oil & Offshore Conference Helge Kvalvik, CEO Boa Offshore 12 September 2018 Pareto Oil & Offshore Conference Helge Kvalvik, CEO Disclaimer This presentation is made by Boa Offshore (or the Company ). The information contained herein include statements

More information

Negotiating aims for drilling contractors following Transocean Drilling UK Limited v Providence Resources plc [2014] EWHC 4260 (Comm.

Negotiating aims for drilling contractors following Transocean Drilling UK Limited v Providence Resources plc [2014] EWHC 4260 (Comm. . Presentation to Negotiating aims for drilling contractors following Transocean Drilling UK Limited v Providence Resources plc [2014] EWHC 4260 (Comm.) Arctic III Glenn Kangisser & William Cecil Curtis

More information

LANE RENTAL: CREATING INCENTIVES FOR EARLY COMPLETION OF ROAD WORK. Michele Cyna

LANE RENTAL: CREATING INCENTIVES FOR EARLY COMPLETION OF ROAD WORK. Michele Cyna October I992 Transport No. RD-12 TRANSPORTATION, WATER AND URBAN DEVELOPMENT DEPARTMENT THE WORLD BANK LANE RENTAL: CREATING INCENTIVES FOR EARLY COMPLETION OF ROAD WORK Michele Cyna Delays in the completion

More information

OFFSHORE SAFETY REGULATIONS The European Perspective

OFFSHORE SAFETY REGULATIONS The European Perspective OFFSHORE SAFETY REGULATIONS The European Perspective University of Oslo Faculty of Law Candidate number: 5513 Supervisor: Mette Gravdahl-Agerup Submission deadline: 05.11.2012 Word count: 17,933 (max.18,

More information

HOFFMAN ESTATES PARK DISTRICT Hoffman Estates, Illinois FORM OF PROPOSAL. Proposal of, hereinafter

HOFFMAN ESTATES PARK DISTRICT Hoffman Estates, Illinois FORM OF PROPOSAL. Proposal of, hereinafter HOFFMAN ESTATES PARK DISTRICT Hoffman Estates, Illinois FORM OF PROPOSAL Proposal of, hereinafter called the "BIDDER", (a) / (an), (Corporation, Partnership, individual) doing business as, to Hoffman Estates

More information