Rayleigh Curves A Tutorial

Size: px
Start display at page:

Download "Rayleigh Curves A Tutorial"

Transcription

1 Rayleigh Curves A Tutorial Hear F. Chelson Richard L. Coleman Jessica R. Summerville Steven L. Van Drew SCEA 2004 Manhattan Beach, CA June 2004

2 Outline Background Description Application The N-R Curve Generation Tool Risk Analysis considerations Refining Rayleigh after Program Start Fitting N-R Curve in Mature Programs Conclusions

3 Background Studies done by Norden, Lee ors have shown that cumulative costs of R&D projects, derived from earned value systems, typically follow Rayleigh distribution 1 quite closely V(t) = d(1-e -at2 ) The Rayleigh distribution models buildup, peak taper of a development program s effort over time Using Rayleigh curve, forecasting EACs, given sufficient earned value data, is a matter of predicting d a variables in above equation to yield a value for V(t final ). $250,000.0 Cum Expenditures V(t) = d(1 e^(-a*t^2) ) Dollars (in $k) $200,000.0 $150,000.0 $100,000.0 $50,000.0 $ Time Rayleigh Cumulative Distribution V(t) V(t) = d(1-e d(1-e -at2 ) -at2 ) 1. Norden-Raleigh Analysis: A Useful Tool for EVM in Development Projects, David Lee, Logistics Management Institute, The Measurable News, March 2002

4 Detailed Description

5 Norden-Rayleigh Model Cumulative distribution function for Rayleigh: V(t) = d(1-e -at2 ) V(t) = Total effort expended t = Time d = Scale factor of distribution a = Shape parameter Probability density function for Rayleigh: v(t) = 2adte -at2

6 Rayleigh Curve Use in Modeling Funding Profiles Expenditures v(t) = 2adte^(-a*t^2) Dollars (in $M) Time Funding Profile Over Over Time Dollars (in $M) Cum Expenditures V(t) = d(1 e^(-a*t^2) ) Time Cumulative Funding Over Over Time

7 The Norden-Rayleigh Funding Model Models time-phasing of expenditures for Development programs Given expenditures vs. time data, useful for forecasting Cost-to-go Time-to-go Models typical programs that rapidly ramp-up labor efforts n taper off Ideally reflected in manufacturing programs as well as incremental software development efforts

8 Application

9 Application of Rayleigh Curve Valid tool for assessing funding cost of Development programs Assessing funding profiles: Rayleigh Model offers a stard of comparison for reasonableness of a project s planned funding phasing Assessing cost: An assumed scale (d) shape factor (a) can be used to build a profile But uncertainties attached to project end time, or t f means that Rayleigh Curve methodology cannot reasonably predict cost until re is sufficient earned value data to estimate d a Valid tool for generating an EAC Must have following information Computed d a from ACWP data already completed

10 When Rayleigh Model Does Not Apply When schedule contains a great deal of uncertainty When programs* are comprised of distinct sub programs with starts stops, e. g.: When a contract funds more than one development program within same funding profile Software programs that release periodic versions or upgrades within same funding profile * * If If a a program program is is an an aggregation aggregation of of subprograms, subprograms, cannot cannot be be predicted predicted in in toto, toto, it it must must be be broken broken into into independent independent component component sub-programs, sub-programs, Rayleigh Rayleigh applied applied to to each each sub-program sub-program

11 Benefits Endorsements Benefits Good cross check to EAC Fast The methodology is in use elsewhere AFCAA OSD ASC

12 The N-R Curve Generation Tool

13 N-R Curve Generation Tool This N-R Curve Generation Tool is a basic tool that can be used early in program to generate a program s total funding profile Useable at outset to develop or check planned funding profile Usable throughout a program as a cross check or early indicator Early in program (before ~20% complete) plot will provide a good cross check when plotted against immature ACWP profile, is an early indicator of trends According to Christensen, et al, it is at 20% that a program stabilizes to a degree that claim can be made that Cum CPI will not change by more than 10% from its value at 20% point. 1 The 20% point is a forward looking point actual percent complete is unclear until later, but thumb rule is still valid This tool is also useful at any point in program to provide a cross-check on EVM data that may appear suspect INPUTS Norden-Rayleigh Tool Expenditure Curves Program Estimate $ 250,000.0 Program Start Date 1-May-00 Program Completion Date 15-Jun-04 t f 50 a (Shape Parameter) d (Scale Parameter computed as a cross check of total funding) 257,732 yellow cells are for input (in $K) $300,000.0 $250,000.0 $200,000.0 $150,000.0 $100,000.0 $50,000.0 $- OUTPUT N-R Expenditure Curve Double-click on picture to launch N-R tool. Months 1. Is CPI-Based EAC a Lower Bound to Final Cost of Post A-12 Contracts?, David S. Christensen, Ph.D., David A. Rees, Ph.D., The Journal of Cost Analysis Management, Winter 2002.

14 Determining a d (Early in Program) Early in program (because ACWP is immature), pdf parameters a d can only be found from schedule variables. Below are equations for calculating a d. V(t) = d(1 e -at2 ), at t f, V(t f ) = d(1 e -at f 2 ) Given V(t f ) =.97d, solve for a Because Because V(t) V(t) does does not not reach reach v v 0 in 0 in finite finite time, time, project s project s end end time time is is usually usually 1 1 defined defined as as time time at at which: which: V(t V(t f ) f ) = = 97% 97% of of v v 0, 0, or, or, V(t V(t f ) f ) = =.97d.97d 1. Analyzing Development Programs Expenditure with 1. Norden-Rayleigh Analyzing Development Model, David Programs Lee, Expenditure 32nd ADoDCAS, with February Norden-Rayleigh 1999, p21. Model, David Lee, 32nd ADoDCAS, February 1999, p21. V(t f ) = d(1 e -at f 2 ).97d = d(1 e -at f 2 ).97 = (1 e -at f 2 ) e -at f 2 =.03 -at f2 = ln(.03) a = -ln(.03) / t f 2 V(t) = d(1 e -(-ln.03/t f 2 )t 2 ) d = V(t) / (1 e -(-ln.03/t f 2 )t 2 ), where t f is known The The authors authors recommend recommend using using this this computation computation only only as as a a rough rough cross cross check check to to program program plan, plan, particularly particularly for for curve curve generation. generation. A mismatch mismatch between between this this derivation derivation of of d d program program funding funding should should be be viewed viewed as as an an indicator indicator of of schedule schedule funding funding misalignment misalignment Warning: SDD Completion Date is difficult to estimate, refore t f is almost always unknown as is evidenced by existence (in fact commonness) of schedule growth. This limits reliability of Norden-Rayleigh method until sufficient data are available.

15 Use of Curve Generator for Risk The previous tool will produce a Norden-Rayleigh curve when program planning data are input Start date End date Total budget A cross check of total funding is available, computed from t f, or t final, but it is not considered reliable The same tool can produce useful outputs for risk estimates If a risk estimate is done, in eir cost or schedule or both, different values for end date total funding will yield an alternative profile Even if a formal risk analysis is not done, nominal (average) growth factors can be applied to yield a profile with typical growth

16 Refining Rayleigh after Program Start

17 Refining Raleigh Curve As program begins to gar stable ACWP data, Rayleigh curve should be updated to reflect improved availability of information a d can be furr refined by finding peak of funding profile Finding a d in terms of peak of pdf (t peak ) firms up value of a d Due to previously noted volatility in schedules, t final is a poor basis a d dependent on t final should only be used when t peak cannot be determined (derivation on following slide )

18 Refining a d To determine when funding is at max, we must find point (t p, or t-peak) at which first derivative of pdf is zero (stard math technique): Start with pdf v(t) = 2adte -at2 Taking first derivative v (t) = 2ad * [e -at2 * t * (-2at) + e -at2 ] = 2ad * (e -at2 * -2at 2 + e -at2 ) = 2ade -at2 * (-2at 2 + 1) Set v (t) = 0 0 = 2ade -at p 2 * (-2at p2 + 1) Solving, we get t p =1 / 2a So, a = 1 / (2t p2 ) And, d = v(t) / 2t p te -(1/ 2t p 2 )t 2 or d = V(t) / (1 e -(1/ 2t p 2 )t 2 ) Computing Computing 2 nd 2 nd derivative derivative yields yields a a negative negative number number (given (given that that a a d d are are greater greater than than 0), 0), indicating indicating that that t p t is p is at at max max point point vs. vs. a a min min point point of of curve: curve: v (t) v (t) = = a 2 dte a 2 dte -at2 -at2 (8at (8at 2-12), 2-12), substitute substitute t p t = p = 1/(sqrt(2a)) 1/(sqrt(2a)) => => v (t) v (t) = = -8a -8a 2 d/(sqrt(2ae)) 2 d/(sqrt(2ae)) By definition, time is greater than 0, so a must be greater than 0. Solving for d in terms of t p, since time is greater than 0 as is also v(t) [funding], so d must be greater than 0.

19 Fitting N-R Curve in Mature Programs

20 Fitting N-R Curve in Mature Programs After a program is 20% complete, earned value data should be sufficient to fit a Rayleigh distribution to data The 20% point is not empirically demonstrated, but authors believe that EACs are sufficiently stable at this point to use method based on work by Christle, Abba, Christensen ors The parameters a d are found by fitting a curve to data using least squares. This is difficult given that equation has two unknowns. Solutions: to best fit a Rayleigh curve to earned value data, analyst needs additional tools that will make se computations $250,000.0 Cum Expenditures v(t) = d(1 e^(-a*t^2) ) COTS COTS software software solutions: solutions: Rayleigh Rayleigh Analyzer, Analyzer, Logistics Logistics Management Management Institute Institute Premium Premium Solver Solver Platform Platform Versions Versions or or 5.5, 5.5, Frontline Frontline Systems Systems Inc. Inc. - - Used Used with with Microsoft Microsoft Excel Excel Solver Solver DLL DLL Platform, Platform, Frontline Frontline Systems Systems Inc. Inc. - - Used Used with with Visual Visual Basic Basic C++ C++ Dollars (in $k) $200,000.0 $150,000.0 $100,000.0 $50,000.0 $- t ptp N-R Curve ACWP Time Warnings: 1) Excel Solver uses an algorithm that finds local optimal solutions based on inputted start points for decision variables (changing cells) in non-linear equations. The answers provided may not be global optimal solutions. 2) The 20% point is a forward looking calculation. It may prove inexact, but is sufficient for use of thumb rule

21 Conclusions

22 Conclusions The Norden-Rayleigh model can be a valid tool for assessing performance (cost schedules) of DoD Development programs offers tests for reasonableness of a project s planned earned value phasing Caveat: reliability of model is dependent on maturity of earned value data to estimate a d ( shape scale parameters) A Summary of Different Methodologies ACWP data availablitity Basis of a d Concerns Comments Beginning of program Stabilized Program Mature Program Not available or Mature, stable Inititial data available insufficient available a is based on an a d based on a assumed schedule a d found by fitting a known curve critical critical t-final d is curve to data using t-peak to compute based on program plans least squares method curve checked with t-final Actual t-final is unknown due to reality of schedule variability Good for early planning Actual t-peak is difficult to determine until ACWP profile is well beyond peak t-peak can be sketchy if determined too early Difficult because equation has two unknowns (a d ) Needs lots of data (program past 20%)

23 References (also see footnotes) Analyzing Development Programs Expenditure with Norden- Rayleigh Model, David Lee, 32 nd ADoDCAS, February 1999 The Rayleigh Analyzer, John Dukovich, Scott Houser, David Lee, LMI Report At902C1, October 1999 Familiar Metric Management Effort, Development Time, Defects Interact, Lawrence H. Putnam, Ware Myers, Quantitative Software Management, Inc. Norden-Raleigh Analysis: A Useful Tool for EVM in Development Projects, David Lee, Logistics Management Institute, The Measurable News, March 2002 ASC/FMC Rayleigh Curve Overview, Ross Jackson, 60 th ASC Industry Cost Schedule Workshop, April 2003 Is CPI-Based EAC a Lower Bound to Final Cost of Post A- 12 Contracts?, David S. Christensen, Ph.D., David A. Rees, Ph.D., The Journal of Cost Analysis Management, Winter 2002.

Presented at the 2003 SCEA-ISPA Joint Annual Conference and Training Workshop -

Presented at the 2003 SCEA-ISPA Joint Annual Conference and Training Workshop - Predicting Final CPI Estimating the EAC based on current performance has traditionally been a point estimate or, at best, a range based on different EAC calculations (CPI, SPI, CPI*SPI, etc.). NAVAIR is

More information

Weibull Analysis Method

Weibull Analysis Method Weibull Analysis Method Presented to the ICEAA Annual Symposium Denver, CO June 2014 Erik Burgess, Burgess Consulting James Smirnoff, Wyle Brianne Wong, Booz Allen Hamilton 1 Topics Analytical Basis Accuracy

More information

Early Warning Model for Acquisition Program Cost and Schedule Growth

Early Warning Model for Acquisition Program Cost and Schedule Growth Early Warning Model for Acquisition Program Cost and Schedule Growth 15 April 28 Dan Davis Agenda Background Approach Results Way ahead 5/9/28 3:51 PM 2 Background Prior related studies The Rayleigh Analyzer,

More information

Ground Radar Expenditure Phasing Analysis

Ground Radar Expenditure Phasing Analysis Ground Radar Expenditure Phasing Analysis ICEAA June 18 2103 Rick Garcia MCR, LLC 360 N Sepulveda Blvd, Suite 2000 El Segundo, CA 90245 424.218.1631 2012 MCR, LLC Distribution prohibited without expressed

More information

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM presented by: (C)2011 MCR, LLC Dr. Roy Smoker MCR LLC rsmoker@mcri.com (C)2011 MCR, LLC 2 OVERVIEW Introduction EVM Trend

More information

Do Not Sum Earned-Value-Based WBS-Element Estimates-at-Completion

Do Not Sum Earned-Value-Based WBS-Element Estimates-at-Completion Do Not Sum Earned-Value-Based WBS-Element Estimates-at-Completion Stephen A. Book The Aerospace Corporation P.O. Box 92957 Los Angeles, CA 90009-2957 (310) 336-8655 stephen.a.book@aero.org Society of Cost

More information

Cost Estimation as a Linear Programming Problem ISPA/SCEA Annual Conference St. Louis, Missouri

Cost Estimation as a Linear Programming Problem ISPA/SCEA Annual Conference St. Louis, Missouri Cost Estimation as a Linear Programming Problem 2009 ISPA/SCEA Annual Conference St. Louis, Missouri Kevin Cincotta Andrew Busick Acknowledgments The author wishes to recognize and thank the following

More information

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005 PMP Preparation Training Your key in Successful Project Management Akram Al-Najjar, PMP Cost Management Processes Chapter 7 Cost Management Slide 2 1 AGENDA What is Cost Management? Cost Management Processes

More information

EARNED VALUE AS A RISK ASSESSMENT TOOL

EARNED VALUE AS A RISK ASSESSMENT TOOL EARNED VALUE AS A RISK ASSESSMENT TOOL Introduction Earned Value Definition: Employment of a Single Management Control System Providing Accurate, Consistent, Reliable, and Timely Data That Management at

More information

USING PERFORMANCE INDICES TO EVALUATE THE ESTIMATE AT COMPLETION 1. David S. Christensen Southern Utah University

USING PERFORMANCE INDICES TO EVALUATE THE ESTIMATE AT COMPLETION 1. David S. Christensen Southern Utah University USING PERFORMANCE INDICES TO EVALUATE THE ESTIMATE AT COMPLETION 1 David S. Christensen Southern Utah University Christensend@suu.edu ABSTRACT The estimated final cost of a defense contract, termed the

More information

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter: NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Jim Anderson, PMP 1 Goal of the Presentation A presentation ti on earned value that t allows PM

More information

Connecting Earned Value to the Schedule

Connecting Earned Value to the Schedule Connecting Earned Value to the Schedule PMI-CPM Conference Long Beach, California May 11-13, 2005 Walt Lipke Tinker AFB walter.lipke@tinker.af.mil (405) 736-3341 Purpose To discuss the application of Earned

More information

Jacob: What data do we use? Do we compile paid loss triangles for a line of business?

Jacob: What data do we use? Do we compile paid loss triangles for a line of business? PROJECT TEMPLATES FOR REGRESSION ANALYSIS APPLIED TO LOSS RESERVING BACKGROUND ON PAID LOSS TRIANGLES (The attached PDF file has better formatting.) {The paid loss triangle helps you! distinguish between

More information

Presented at the 2012 SCEA/ISPA Joint Annual Conference and Training Workshop -

Presented at the 2012 SCEA/ISPA Joint Annual Conference and Training Workshop - Applying the Pareto Principle to Distribution Assignment in Cost Risk and Uncertainty Analysis James Glenn, Computer Sciences Corporation Christian Smart, Missile Defense Agency Hetal Patel, Missile Defense

More information

The First Steps in Implementing a Simplified Earned Value Management System

The First Steps in Implementing a Simplified Earned Value Management System 2007 Joint ISPA/SCEA National Conference & Workshop June 12-15, 2007 The First Steps in Implementing a Simplified Earned Value Management System Dorothy Tiffany, CPA, PMP NASA/GSFC EVM System Interface

More information

Presented at the ICEAA 2016 Professional Development & Training Workshop

Presented at the ICEAA 2016 Professional Development & Training Workshop Presented at the ICEAA 2016 Professional Development & Training Workshop 1 Visualization of Process History Ground Rules / Modifications PMMS Set Up Model Execution Case Study Future Development / Ideas

More information

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327 Integrated Project Performance Management.EMERGING PRACTICE. Earned Schedule Eleanor Haupt ASC/FMCE Wright-Patterson AFB OH eleanor.haupt@wpafb.af.mil 937-656-5482 ANL327 1 Required Legal Notices ***CAUTION***.EMERGING

More information

Developing Optimized Maintenance Work Programs for an Urban Roadway Network using Pavement Management System

Developing Optimized Maintenance Work Programs for an Urban Roadway Network using Pavement Management System Developing Optimized Maintenance Work Programs for an Urban Roadway Network using Pavement Management System M. Arif Beg, PhD Principal Consultant, AgileAssets Inc. Ambarish Banerjee, PhD Consultant, AgileAssets

More information

Chapter 6 Analyzing Accumulated Change: Integrals in Action

Chapter 6 Analyzing Accumulated Change: Integrals in Action Chapter 6 Analyzing Accumulated Change: Integrals in Action 6. Streams in Business and Biology You will find Excel very helpful when dealing with streams that are accumulated over finite intervals. Finding

More information

for 9 Sep 15 SoCal ICEAA Workshop

for 9 Sep 15 SoCal ICEAA Workshop Two Complementary EVM Cost-Risk Models Part 2 1. Use of EVM Trend Tool (EVMTT) to Forecast Cost Risks with 4 Case Study Examples 2. Integrated Cost-Risk Model (ICRM) Utilizing ACEIT for 9 Sep 15 SoCal

More information

Earned Value Management (EVM) and the Acquisition Program

Earned Value Management (EVM) and the Acquisition Program American Society of Military Comptrollers Professional Development Institute May 31 June 2, 2017 Earned Value Management (EVM) and the Acquisition Program Workshop #102 R o b e r t L. G u s t a v u s.

More information

Modeling R&D Budget Profiles

Modeling R&D Budget Profiles Modeling R&D Budget Profiles SCEA/ISPA Joint Annual Conference Orlando, FL June 2012 Erik Burgess erik@burgess-consulting.net Background Agenda Key findings from 2004 put into practice Link between schedule

More information

chapter 2-3 Normal Positive Skewness Negative Skewness

chapter 2-3 Normal Positive Skewness Negative Skewness chapter 2-3 Testing Normality Introduction In the previous chapters we discussed a variety of descriptive statistics which assume that the data are normally distributed. This chapter focuses upon testing

More information

The Not-So-Geeky World of Statistics

The Not-So-Geeky World of Statistics FEBRUARY 3 5, 2015 / THE HILTON NEW YORK The Not-So-Geeky World of Statistics Chris Emerson Chris Sweet (a/k/a Chris 2 ) 2 Who We Are Chris Sweet JPMorgan Chase VP, Outside Counsel & Engagement Management

More information

RISK BASED LIFE CYCLE COST ANALYSIS FOR PROJECT LEVEL PAVEMENT MANAGEMENT. Eric Perrone, Dick Clark, Quinn Ness, Xin Chen, Ph.D, Stuart Hudson, P.E.

RISK BASED LIFE CYCLE COST ANALYSIS FOR PROJECT LEVEL PAVEMENT MANAGEMENT. Eric Perrone, Dick Clark, Quinn Ness, Xin Chen, Ph.D, Stuart Hudson, P.E. RISK BASED LIFE CYCLE COST ANALYSIS FOR PROJECT LEVEL PAVEMENT MANAGEMENT Eric Perrone, Dick Clark, Quinn Ness, Xin Chen, Ph.D, Stuart Hudson, P.E. Texas Research and Development Inc. 2602 Dellana Lane,

More information

Risk classification of projects in EU operational programmes according to their S-curve characteristics: A case study approach.

Risk classification of projects in EU operational programmes according to their S-curve characteristics: A case study approach. Risk classification of projects in EU operational programmes according to their S-curve characteristics: A case study approach. P. G. Ipsilandis Department of Project Management, Technological Education

More information

BASIC COST RISK ANALYSIS: USING CRYSTAL BALL ON GOVERNMENT LIFE CYCLE COST ESTIMATES

BASIC COST RISK ANALYSIS: USING CRYSTAL BALL ON GOVERNMENT LIFE CYCLE COST ESTIMATES Proceedings of the 2007 Crystal Ball User Conference BASIC COST RISK ANALYSIS: USING CRYSTAL BALL ON GOVERNMENT LIFE CYCLE COST ESTIMATES ABSTRACT R. Kim Clark Booz Allen Hamilton 700 N. Saint Mary s St.,

More information

Estimating Cost-To-Go Without Stable EVM Data

Estimating Cost-To-Go Without Stable EVM Data PR-158 Estimating Cost-To-Go Without Stable EVM Data Peter C. Frederic, Tecolote Research Inc. Ronald K. Larson, NASA 20 March 2013 2013 Professional Development & Training Workshop New Orleans, LA June

More information

Schedule Analysis and Predictive Techniques Using Earned Schedule. 16 th IPM Conference Tysons Corner, Virginia

Schedule Analysis and Predictive Techniques Using Earned Schedule. 16 th IPM Conference Tysons Corner, Virginia Schedule Analysis and Predictive Techniques Using Earned Schedule 16 th IPM Conference Tysons Corner, Virginia 17 th November 2004 Walt Lipke OC-ALC/MAS Tinker AFB OK walter.lipke@tinker.af.mil 405-736-3341

More information

Maximum Likelihood Estimates for Alpha and Beta With Zero SAIDI Days

Maximum Likelihood Estimates for Alpha and Beta With Zero SAIDI Days Maximum Likelihood Estimates for Alpha and Beta With Zero SAIDI Days 1. Introduction Richard D. Christie Department of Electrical Engineering Box 35500 University of Washington Seattle, WA 98195-500 christie@ee.washington.edu

More information

RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1

RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1 RETURN TO ROME Project Management Fundamentals 1 Work - Milestones Plan: MS 4 Four Day Rome Project S-Curve Work vs Time Actual vs. Plan MS 3 MS 2 MS 1 = Plan = Actual Cumulative Milestones Completed 0

More information

Making Risk Management Tools More Credible: Calibrating the Risk Cube

Making Risk Management Tools More Credible: Calibrating the Risk Cube Making Risk Management Tools More Credible: Calibrating the Risk Cube SCEA 2006 Washington, DC Richard L. Coleman, Jessica R. Summerville, Megan E. Dameron Northrop Grumman Corporation 0 Outline! The General

More information

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: Project Control 1 Project Control Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities: 1. Planning performance Software Development Plan, schedule,

More information

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh 2 S.Sowmya 1. Research Associate, Indian Institute of Management Ahmedabad, 2. SDE, ACS

More information

Sample Size Calculations for Odds Ratio in presence of misclassification (SSCOR Version 1.8, September 2017)

Sample Size Calculations for Odds Ratio in presence of misclassification (SSCOR Version 1.8, September 2017) Sample Size Calculations for Odds Ratio in presence of misclassification (SSCOR Version 1.8, September 2017) 1. Introduction The program SSCOR available for Windows only calculates sample size requirements

More information

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved Project Cost Management 1 Project Cost Management Processes 1. Estimate Costs 2. Determine Budget 3. Control Costs In some projects, especially with smaller scope, cost estimation and cost budgeting are

More information

Crashing the Schedule An Algorithmic Approach with Caveats and Comments

Crashing the Schedule An Algorithmic Approach with Caveats and Comments ing the Schedule An Algorithmic Approach with Caveats and Comments Gilbert C. Brunnhoeffer, III PhD, P.E. and B. Gokhan Celik PhD LEED AP Roger Williams University Bristol, Rhode Island and Providence

More information

Capturing Risk Interdependencies: The CONVOI Method

Capturing Risk Interdependencies: The CONVOI Method Capturing Risk Interdependencies: The CONVOI Method Blake Boswell Mike Manchisi Eric Druker 1 Table Of Contents Introduction The CONVOI Process Case Study Consistency Verification Conditional Odds Integration

More information

Crediting Wind and Solar Renewables in Electricity Capacity Markets: The Effects of Alternative Definitions upon Market Efficiency. The Energy Journal

Crediting Wind and Solar Renewables in Electricity Capacity Markets: The Effects of Alternative Definitions upon Market Efficiency. The Energy Journal Crediting Wind and Solar Renewables in Electricity Capacity Markets: The Effects of Alternative Definitions upon Market Efficiency The Energy Journal On-Line Appendix A: Supporting proofs of social cost

More information

Predicting Project Completion Date Using Earned Value Management

Predicting Project Completion Date Using Earned Value Management Predicting Project Completion Date Using Earned Value Management A New Tradition in EVM Analysis! AACE International 2009 Spring Symposium February 28 Long Beach, CA Ray W. Stratton, PMP, EVP 714-318-2231

More information

Cost Estimate at Completion Methods in Construction Projects

Cost Estimate at Completion Methods in Construction Projects 2011 2 nd International Conference on Construction and Project Management IPEDR vol.15 (2011) (2011) IACSIT Press, Singapore Cost Estimate at Completion Methods in Construction Projects Timur Narbaev 1

More information

Does Project Performance Stability Exist? a re-examination of CPI and evaluation of SPI(t) stability

Does Project Performance Stability Exist? a re-examination of CPI and evaluation of SPI(t) stability Does Project Performance Stability Exist? a re-examination of CPI and evaluation of SPI(t) stability Kym Henderson Vice President, Research and Standards PMI College of Performance Management * Dr. Ofer

More information

Introducing Uncertainty in Brazil's Oil Supply Chain

Introducing Uncertainty in Brazil's Oil Supply Chain R&D Project IMPA-Petrobras Introducing Uncertainty in Brazil's Oil Supply Chain Juan Pablo Luna (UFRJ) Claudia Sagastizábal (IMPA visiting researcher) on behalf of OTIM-PBR team Workshop AASS, April 1st

More information

Comparison of Development Test and Evaluation and Overall Program Estimate at Completion

Comparison of Development Test and Evaluation and Overall Program Estimate at Completion Air Force Institute of Technology AFIT Scholar Theses and Dissertations 3-11-2011 Comparison of Development Test and Evaluation and Overall Program Estimate at Completion William R. Rosado Follow this

More information

Three Numbers to Measure Project Performance

Three Numbers to Measure Project Performance Dr. Thomas Liedtke Alcatel D 70435 Stuttgart (Germany) Peter Paetzold Alcatel D 70435 Stuttgart (Germany) e_mail: TLiedtke@alcatel.de phone: +49 711 821 40346 fax.: +49 711 821 42230 e_mail: Peter.Paetzold@alcatel.de

More information

GPE engineering project management. Project Management in an Engineering Context

GPE engineering project management. Project Management in an Engineering Context GPE engineering project management Project Management in an Engineering Context Earned Value Management System Is a system to MANAGE --- and help resolve control problems in running projects difficulties

More information

DETERMINING AN ACCURATE ESTIMATE AT COMPLETION. 1. David S. Christensen, Ph.D. Southern Utah University

DETERMINING AN ACCURATE ESTIMATE AT COMPLETION. 1. David S. Christensen, Ph.D. Southern Utah University DETERMINING AN ACCURATE ESTIMATE AT COMPLETION. 1 David S. Christensen, Ph.D. Southern Utah University Christensend@suu.edu ABSTRACT The estimated completion cost of a defense acquisition contract is termed

More information

Integrating Business and Financial Management Functions

Integrating Business and Financial Management Functions PROGRAM OFFICE MANAGEMENT Integrating Business and Financial Management Functions A program executive officer once said, You can t be effective in the world of acquisition management unless you have an

More information

PART II A MACRO-ECONOMIC METHODOLOGY FOR THE APPRAISAL OF THE EFFECTS OF PRI V A TE FOREIGN INVESTMENTS IN LESS DEVELOPED COUNTRIES

PART II A MACRO-ECONOMIC METHODOLOGY FOR THE APPRAISAL OF THE EFFECTS OF PRI V A TE FOREIGN INVESTMENTS IN LESS DEVELOPED COUNTRIES PART II A MACRO-ECONOMIC METHODOLOGY FOR THE APPRAISAL OF THE EFFECTS OF PRI V A TE FOREIGN INVESTMENTS IN LESS DEVELOPED COUNTRIES TABLE OF CONTENTS SUMMARY OF PART II 53 CHAPTER I. GENERAL INTRODUCTION

More information

Maximum Likelihood Estimation

Maximum Likelihood Estimation Maximum Likelihood Estimation EPSY 905: Fundamentals of Multivariate Modeling Online Lecture #6 EPSY 905: Maximum Likelihood In This Lecture The basics of maximum likelihood estimation Ø The engine that

More information

A Linear Programming Approach for Optimum Project Scheduling Taking Into Account Overhead Expenses and Tardiness Penalty Function

A Linear Programming Approach for Optimum Project Scheduling Taking Into Account Overhead Expenses and Tardiness Penalty Function A Linear Programming Approach for Optimum Project Scheduling Taking Into Account Overhead Expenses and Tardiness Penalty Function Mohammed Woyeso Geda, Industrial Engineering Department Ethiopian Institute

More information

Evaluating the Accuracy of the Estimate At Completion

Evaluating the Accuracy of the Estimate At Completion Evaluating the Accuracy of the Estimate At Completion David S. Christensen, Ph.D. Southern Utah University (435)865-8058 ChristensenD@suu.edu 2001 College of Performance Management Conference 21-24 May

More information

Comprehensive Assessment of Contract Performance Using Earned Value Management (EVM) Data

Comprehensive Assessment of Contract Performance Using Earned Value Management (EVM) Data Comprehensive Assessment of Contract Performance Using Earned Value Management (EVM) Data William Laing Technomics, Inc. wlaing@technomics.net 2011 ISPA/SCEA Joint Annual Conference & Training Workshop

More information

Flexible Budgeting Variance Analysis Excel

Flexible Budgeting Variance Analysis Excel Flexible Budgeting Variance Excel Free PDF ebook Download: Flexible Budgeting Variance Excel Download or Read Online ebook flexible budgeting variance analysis excel in PDF Format From The Best User Guide

More information

ESTIMATING THE DISTRIBUTION OF DEMAND USING BOUNDED SALES DATA

ESTIMATING THE DISTRIBUTION OF DEMAND USING BOUNDED SALES DATA ESTIMATING THE DISTRIBUTION OF DEMAND USING BOUNDED SALES DATA Michael R. Middleton, McLaren School of Business, University of San Francisco 0 Fulton Street, San Francisco, CA -00 -- middleton@usfca.edu

More information

Traditional Optimization is Not Optimal for Leverage-Averse Investors

Traditional Optimization is Not Optimal for Leverage-Averse Investors Posted SSRN 10/1/2013 Traditional Optimization is Not Optimal for Leverage-Averse Investors Bruce I. Jacobs and Kenneth N. Levy forthcoming The Journal of Portfolio Management, Winter 2014 Bruce I. Jacobs

More information

Risk vs. Uncertainty: What s the difference?

Risk vs. Uncertainty: What s the difference? Risk vs. Uncertainty: What s the difference? 2016 ICEAA Professional Development and Training Workshop Mel Etheridge, CCEA 2013 MCR, LLC Distribution prohibited without express written consent of MCR,

More information

February 2010 Office of the Deputy Assistant Secretary of the Army for Cost & Economics (ODASA-CE)

February 2010 Office of the Deputy Assistant Secretary of the Army for Cost & Economics (ODASA-CE) U.S. ARMY COST ANALYSIS HANDBOOK SECTION 12 COST RISK AND UNCERTAINTY ANALYSIS February 2010 Office of the Deputy Assistant Secretary of the Army for Cost & Economics (ODASA-CE) TABLE OF CONTENTS 12.1

More information

An Analysis of Stability Properties in Earned Value Management s Cost Performance Index and Earned Schedule s Schedule Performance Index

An Analysis of Stability Properties in Earned Value Management s Cost Performance Index and Earned Schedule s Schedule Performance Index Air Force Institute of Technology AFIT Scholar Theses and Dissertations 3-14-2014 An Analysis of Stability Properties in Earned Value Management s Cost Performance Index and Earned Schedule s Schedule

More information

PM World Today March 2011 (Vol XIII, Issue III) PM WORLD TODAY FEATURED PAPER MARCH Why Should CPI = 1? By Walt Lipke PMI Oklahoma City Chapter

PM World Today March 2011 (Vol XIII, Issue III) PM WORLD TODAY FEATURED PAPER MARCH Why Should CPI = 1? By Walt Lipke PMI Oklahoma City Chapter PM WORLD TODAY FEATURED PAPER MARCH 2011 Why Should CPI = 1? By Walt Lipke PMI Oklahoma City Chapter Abstract The expectation when applying Earned Value Management is to control performance such that CPI

More information

Economics II - Exercise Session, December 3, Suggested Solution

Economics II - Exercise Session, December 3, Suggested Solution Economics II - Exercise Session, December 3, 008 - Suggested Solution Problem 1: A firm is on a competitive market, i.e. takes price of the output as given. Production function is given b f(x 1, x ) =

More information

Application of Data Mining Tools to Predicate Completion Time of a Project

Application of Data Mining Tools to Predicate Completion Time of a Project Application of Data Mining Tools to Predicate Completion Time of a Project Seyed Hossein Iranmanesh, and Zahra Mokhtari Abstract Estimation time and cost of work completion in a project and follow up them

More information

Improving Returns-Based Style Analysis

Improving Returns-Based Style Analysis Improving Returns-Based Style Analysis Autumn, 2007 Daniel Mostovoy Northfield Information Services Daniel@northinfo.com Main Points For Today Over the past 15 years, Returns-Based Style Analysis become

More information

Expected Return Methodologies in Morningstar Direct Asset Allocation

Expected Return Methodologies in Morningstar Direct Asset Allocation Expected Return Methodologies in Morningstar Direct Asset Allocation I. Introduction to expected return II. The short version III. Detailed methodologies 1. Building Blocks methodology i. Methodology ii.

More information

MATH4143: Scientific Computations for Finance Applications Final exam Time: 9:00 am - 12:00 noon, April 18, Student Name (print):

MATH4143: Scientific Computations for Finance Applications Final exam Time: 9:00 am - 12:00 noon, April 18, Student Name (print): MATH4143 Page 1 of 17 Winter 2007 MATH4143: Scientific Computations for Finance Applications Final exam Time: 9:00 am - 12:00 noon, April 18, 2007 Student Name (print): Student Signature: Student ID: Question

More information

Web Extension: Continuous Distributions and Estimating Beta with a Calculator

Web Extension: Continuous Distributions and Estimating Beta with a Calculator 19878_02W_p001-008.qxd 3/10/06 9:51 AM Page 1 C H A P T E R 2 Web Extension: Continuous Distributions and Estimating Beta with a Calculator This extension explains continuous probability distributions

More information

Outline. Introduction. Nicholas C. Romano, Jr., Ph.D. Project Management Graphics: An Experimental Comparison Nicholas C. Romano

Outline. Introduction. Nicholas C. Romano, Jr., Ph.D. Project Management Graphics: An Experimental Comparison Nicholas C. Romano Project Management Graphics: An Experimental Comparison Nicholas C. Romano William S. Spears School of Business Management Science and Information Systems Oklahoma State University - Tulsa Nicholas.Romano@okstate.edu

More information

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,

More information

Earned Schedule in Action

Earned Schedule in Action Earned Schedule in Action Earned Value Analysis - 11 Conference London, United Kingdom 12-17 June 2006 Kym Henderson Education Director PMI Sydney Australia Chapter Kym.Henderson@froggy.com.au EVM Schedule

More information

Characterization of the Optimum

Characterization of the Optimum ECO 317 Economics of Uncertainty Fall Term 2009 Notes for lectures 5. Portfolio Allocation with One Riskless, One Risky Asset Characterization of the Optimum Consider a risk-averse, expected-utility-maximizing

More information

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities presented by Harry Sparrow for THE SOCIETY OF COST ESTIMATING & ANALYSIS 2004 NATIONAL CONFERENCE & TRAINING WORKSHOP

More information

EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY INTRODUCTION

EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY INTRODUCTION EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY Dr David Hillson PMP FAPM FIRM, Director, Risk Doctor & Partners david@risk-doctor.com www.risk-doctor.com INTRODUCTION In today s uncertain

More information

DOWNLOAD PDF ANALYZING CAPITAL EXPENDITURES

DOWNLOAD PDF ANALYZING CAPITAL EXPENDITURES Chapter 1 : Capital Expenditure (Capex) - Guide, Examples of Capital Investment The first step in a capital expenditure analysis is a factual evaluation of the current situation. It can be a simple presentation

More information

Estimating Maximum Smoothness and Maximum. Flatness Forward Rate Curve

Estimating Maximum Smoothness and Maximum. Flatness Forward Rate Curve Estimating Maximum Smoothness and Maximum Flatness Forward Rate Curve Lim Kian Guan & Qin Xiao 1 January 21, 22 1 Both authors are from the National University of Singapore, Centre for Financial Engineering.

More information

The Equal Time Weighted Constant Portfolio Methodology

The Equal Time Weighted Constant Portfolio Methodology The Equal Time Weighted Constant Portfolio Methodology At AltFi Data we believe that both investors and originators benefit from metrics that capture the entire track record of an originator rather than

More information

MATH6911: Numerical Methods in Finance. Final exam Time: 2:00pm - 5:00pm, April 11, Student Name (print): Student Signature: Student ID:

MATH6911: Numerical Methods in Finance. Final exam Time: 2:00pm - 5:00pm, April 11, Student Name (print): Student Signature: Student ID: MATH6911 Page 1 of 16 Winter 2007 MATH6911: Numerical Methods in Finance Final exam Time: 2:00pm - 5:00pm, April 11, 2007 Student Name (print): Student Signature: Student ID: Question Full Mark Mark 1

More information

PROJECT COST MANAGEMENT

PROJECT COST MANAGEMENT PROJECT COST MANAGEMENT Planning DETERMINE BUDGET PROCESSES BY PROCESS GROUP Monitoring and Controlling 7.1 Plan Costs Management 7.4 Control Costs 7.2 Estimate Costs 7.3 Determine Budget DETERMINE BUDGET

More information

Optimizing Modular Expansions in an Industrial Setting Using Real Options

Optimizing Modular Expansions in an Industrial Setting Using Real Options Optimizing Modular Expansions in an Industrial Setting Using Real Options Abstract Matt Davison Yuri Lawryshyn Biyun Zhang The optimization of a modular expansion strategy, while extremely relevant in

More information

Author: David S. Christensen, Ph.D. David A. Rces, Ph.D.

Author: David S. Christensen, Ph.D. David A. Rces, Ph.D. Author: David S. Christensen, Ph.D. David A. Rces, Ph.D. Mailing address: College of Business College of Business Southern Utah University Southern Utah University 351 West Center Street 351 West Center

More information

Most Critical Factors Impacting Cost-Effectiveness of Feedback Programs

Most Critical Factors Impacting Cost-Effectiveness of Feedback Programs Most Critical Factors Impacting Cost-Effectiveness of Feedback Programs Behavior, Energy and Climate Change (BECC) Conference Washington, DC December, 2014 Ali Bozorgi, PhD, CDSM Senior Associate Energy

More information

AIR FORCE INSTITUTE OF TECHNOLOGY

AIR FORCE INSTITUTE OF TECHNOLOGY ACCURACY OF TIME PHASING AIRCRAFT DEVELOPMENT USING THE CONTINUOUS DISTRIBUTION FUNCTION THESIS MARCH 2015 Gregory E. Brown, Captain, USAF AFIT-ENC-MS-15-M-173 DEPARTMENT OF THE AIR FORCE AIR UNIVERSITY

More information

Reinforcement Learning (1): Discrete MDP, Value Iteration, Policy Iteration

Reinforcement Learning (1): Discrete MDP, Value Iteration, Policy Iteration Reinforcement Learning (1): Discrete MDP, Value Iteration, Policy Iteration Piyush Rai CS5350/6350: Machine Learning November 29, 2011 Reinforcement Learning Supervised Learning: Uses explicit supervision

More information

Lattice Model of System Evolution. Outline

Lattice Model of System Evolution. Outline Lattice Model of System Evolution Richard de Neufville Professor of Engineering Systems and of Civil and Environmental Engineering MIT Massachusetts Institute of Technology Lattice Model Slide 1 of 48

More information

Empirical Tools of Public Economics. Part-2

Empirical Tools of Public Economics. Part-2 Empirical Tools of Public Economics Part-2 Outline 3.1. Correlation vs. Causality 3.2. Ideal case: Randomized Trials 3.3. Reality: Observational Data Observational data: Data generated by individual behavior

More information

Self-Assessment Questions for Module 07 Project Cost Management

Self-Assessment Questions for Module 07 Project Cost Management Self-Assessment Questions for Module 07 Project Cost Management Question 1: Which of the following regarding Analogous Estimating and Parametric Estimating is incorrect? A.) Parametric Estimating uses

More information

Reinforcement Learning (1): Discrete MDP, Value Iteration, Policy Iteration

Reinforcement Learning (1): Discrete MDP, Value Iteration, Policy Iteration Reinforcement Learning (1): Discrete MDP, Value Iteration, Policy Iteration Piyush Rai CS5350/6350: Machine Learning November 29, 2011 Reinforcement Learning Supervised Learning: Uses explicit supervision

More information

Lecture 2 Describing Data

Lecture 2 Describing Data Lecture 2 Describing Data Thais Paiva STA 111 - Summer 2013 Term II July 2, 2013 Lecture Plan 1 Types of data 2 Describing the data with plots 3 Summary statistics for central tendency and spread 4 Histograms

More information

A Skewed Truncated Cauchy Logistic. Distribution and its Moments

A Skewed Truncated Cauchy Logistic. Distribution and its Moments International Mathematical Forum, Vol. 11, 2016, no. 20, 975-988 HIKARI Ltd, www.m-hikari.com http://dx.doi.org/10.12988/imf.2016.6791 A Skewed Truncated Cauchy Logistic Distribution and its Moments Zahra

More information

Department of Economics ECO 204 Microeconomic Theory for Commerce Test 2

Department of Economics ECO 204 Microeconomic Theory for Commerce Test 2 Department of Economics ECO 204 Microeconomic Theory for Commerce 2013-2014 Test 2 IMPORTANT NOTES: Proceed with this exam only after getting the go-ahead from the Instructor or the proctor Do not leave

More information

FAV i R This paper is produced mechanically as part of FAViR. See for more information.

FAV i R This paper is produced mechanically as part of FAViR. See  for more information. The POT package By Avraham Adler FAV i R This paper is produced mechanically as part of FAViR. See http://www.favir.net for more information. Abstract This paper is intended to briefly demonstrate the

More information

EVM s Potential for Enabling Effective Integrated Cost-Risk Management

EVM s Potential for Enabling Effective Integrated Cost-Risk Management EVM s Potential for Enabling Effective Integrated Cost-Risk Management by David R. Graham (dgmogul1@verizon.net; 703-489-6048) Galorath Federal Systems Stove-pipe cost-risk chaos is the term I think most

More information

Sensitivity Analysis with Data Tables. 10% annual interest now =$110 one year later. 10% annual interest now =$121 one year later

Sensitivity Analysis with Data Tables. 10% annual interest now =$110 one year later. 10% annual interest now =$121 one year later Sensitivity Analysis with Data Tables Time Value of Money: A Special kind of Trade-Off: $100 @ 10% annual interest now =$110 one year later $110 @ 10% annual interest now =$121 one year later $100 @ 10%

More information

Transition from Manual to Automated Pavement Distress Data Collection and Performance Modelling in the Pavement Management System

Transition from Manual to Automated Pavement Distress Data Collection and Performance Modelling in the Pavement Management System Transition from Manual to Automated Pavement Distress Data Collection and Performance Modelling in the Pavement Management System Susanne Chan Pavement Design Engineer, M.A.Sc, P.Eng. Ministry of Transportation

More information

Value And Earned Schedule Management

Value And Earned Schedule Management EVM World 2013 Conference IPMC 2013 Title: An Analytical Utility For Earned Value And Earned Schedule Management Gary L. Richardson and Saranya Lakshmikanthan May 29, 2013 The popular technical literature

More information

Intro to GLM Day 2: GLM and Maximum Likelihood

Intro to GLM Day 2: GLM and Maximum Likelihood Intro to GLM Day 2: GLM and Maximum Likelihood Federico Vegetti Central European University ECPR Summer School in Methods and Techniques 1 / 32 Generalized Linear Modeling 3 steps of GLM 1. Specify the

More information

THE VALUE OF EARNED VALUE MANAGEMENT

THE VALUE OF EARNED VALUE MANAGEMENT THE VALUE OF EARNED VALUE MANAGEMENT PMI Pittsburgh Chapter Meeting February 8, 2001 Marilyn McCauley McManagement Group 703-455-0602 703-455-0598 (f) McMgtGrp@aol.com AGENDA Twelve Reasons Why Programs

More information

Predictive Model Learning of Stochastic Simulations. John Hegstrom, FSA, MAAA

Predictive Model Learning of Stochastic Simulations. John Hegstrom, FSA, MAAA Predictive Model Learning of Stochastic Simulations John Hegstrom, FSA, MAAA Table of Contents Executive Summary... 3 Choice of Predictive Modeling Techniques... 4 Neural Network Basics... 4 Financial

More information

Fatness of Tails in Risk Models

Fatness of Tails in Risk Models Fatness of Tails in Risk Models By David Ingram ALMOST EVERY BUSINESS DECISION MAKER IS FAMILIAR WITH THE MEANING OF AVERAGE AND STANDARD DEVIATION WHEN APPLIED TO BUSINESS STATISTICS. These commonly used

More information

Earned Value Management

Earned Value Management Earned Value Management Reading the Roadmap to Project Success (or, Are We There Yet?) Steve Margolis, PMP, CISSP smargolis@us.ibm.com September 5, 2018 Overview EVM Background EVM Basics and Standards

More information

A Study of the Efficiency of Polish Foundries Using Data Envelopment Analysis

A Study of the Efficiency of Polish Foundries Using Data Envelopment Analysis A R C H I V E S of F O U N D R Y E N G I N E E R I N G DOI: 10.1515/afe-2017-0039 Published quarterly as the organ of the Foundry Commission of the Polish Academy of Sciences ISSN (2299-2944) Volume 17

More information