1 Technical Assistance TAR: PRC Technical Assistance to the People s Republic of China for Preparing the Railway Development Project September 2005

2 CURRENCY EQUIVALENTS (as of 14 August 2005) Currency Unit yuan (CNY) CNY1.00 = $ $1.00 = CNY ABBREVIATIONS ADB Asian Development Bank EIA environmental impact assessment GMS Greater Mekong Subregion MOR Ministry of Railways PRC People s Republic of China TA technical assistance YMR Yuxi Mengzi railways TECHNICAL ASSISTANCE CLASSIFICATION Targeting Classification General intervention Sector Transport and communications Subsector Railways Theme Sustainable economic growth Subthemes Promoting economic efficiency and enabling markets, fostering physical infrastructure development (i) (ii) NOTES The fiscal year (FY) of the Government and its agencies ends on 31 December. In this report, $ refers to US dollars. This report was prepared by: Mission Leader: M. Parkash, Transport and Communications Division Other Team Member: S. Ferguson, Transport and Communications Division Director: N. Rayner, Transport and Communications Division Director General: H. Satish Rao, East and Central Asia Department Vice President: J. Eichenberger, Operations Group 2

3

4 I. INTRODUCTION 1. The Government of the People s Republic of China (PRC) requested technical assistance (TA) from the Asian Development Bank (ADB) for preparing the Railway Development Project. 1 ADB conducted a fact-finding mission in June July 2005, carried out an initial poverty and social assessment and a rapid environmental assessment, and discussed technical and socioeconomic issues with representatives of the Government, Yunnan provincial and local governments, and the Ministry of Railways (MOR). An understanding was reached with the Government on the goals, purpose, scope, implementation arrangements, cost, financing arrangements, and terms of reference for the TA. The TA is included in ADB's country assistance program for The design and monitoring framework is in Appendix 1. II. ISSUES 2. The PRC has experienced sustained rapid economic growth since market-oriented economic reforms were introduced in This has resulted in a rapid increase in demand for transportation. Passenger transport grew by 9.0% per year between 1978 to 2004 and freight transport grew by 7.6% per year. Road traffic accounted for 53.7% of total passenger-kilometers (km) in 2004, followed by railways at 35.0%, civil aviation at 10.9%, and coastal and inland waterways at 0.4%. The modal split for freight ton-km was 58.4% for coastal and inland waterways, 28.9% for railways, 11.4% for roads, 1.2% for pipelines, and 0.1% for civil aviation. 3. Rapid economic growth led to high demand for railway transportation, which is the primary mode for long-distance and bulk transport. Between 1978 and 2004, railway freight grew from 535 billion ton-km to 1,929 billion ton-km, equivalent to an annual growth rate of 5.1%. Passenger traffic grew at 6.6% annually, increasing from 109 billion passenger-km to billion passenger-km. At the end of 2004, the PRC s railway system comprised 74,400 route-km. Despite such growth rates, railway capacity has lagged behind demand due to railway system constraints. Given the railway s important role in providing economic transportation, these constraints if not removed will continue to adversely affect efficient economic growth. 4. The Government adopted an aggressive plan to improve the railway, and planned network extensions and construction in underserved areas. Government policy on railway development is focused on (i) removing constraints and expanding the system, (ii) encouraging construction of joint-venture local railways to promote local economic development, (iii) improving efficiency by using new technology and modern management tools in planning and operation, (iv) reducing operating subsidies through appropriate pricing and commercialization of services, (v) initiating institutional and structural reforms to increase MOR s autonomy and accountability, and (vi) encouraging nongovernment investment in infrastructure and related services. 5. The Tenth Five-Year Plan ( ) identifies transportation including railway development as a priority. The plan envisages (i) constructing 6,000 km of new lines to provide access to unserved areas to increase the network length to 75,000 route-km by 2005; (ii) constructing 3,000 km of double lines and electrifying 5,000 km of key lines to increase capacity; and (iii) increasing operating speeds on 5,000 km to reach high speeds on the total length of 15,000 km. The plan envisages a total investment of CNY350 billion, including CNY270 billion for capital construction and CNY80 billion for rolling-stock acquisition for the 1 Formerly called Yuxi Mengzi Railway Project. 2 The TA first appeared in the ADB Business Opportunities (Internet edition) on 22 June 2005.

5 2 railway sector. Investments in capital construction for the railway are expected to reach CNY450 billion from 2003 to In 2004, the State Council approved the new railway development plan (until 2020), which seeks to expand the railway network from 72,000 km to 85,000 km by 2010 and 100,000 km by Increasing train speed is identified as a major goal. Train speeds will be raised to over 200 km per hour on the trunk network by Priority will be given to the development of railways in unserved areas and regions, which lack transport and are less developed. The route network length will increase by 16,000 km in the western region of the PRC, to reach a network length of 40,000 km by To improve operational efficiency, steps will be taken to separate passenger and freight trains on key rail corridors. 7. Japan is the major source of external financing in the PRC railway sector, followed by ADB and the World Bank. Since 1979, Japan has provided about Y558 billion for 15 railway projects to expand rail transportation capacity. Since 1984, the World Bank has provided 10 loans totaling over $2.4 billion for (i) nine national railway projects to expand railway capacity on high-priority corridors, modernize system wide technology, and strengthen institutional capabilities; and (ii) one local railway project. ADB focused on the development of railways in less-developed inland provinces, to promote growth and reduce poverty. ADB provided 13 loans, totaling about $2.6 billion, to finance the construction of about 1,921 km of provincial railways and 4,597 km of national railway projects. 8. ADB's operational strategy in the PRC focuses on (i) expanding the railway system in unserved, less-developed, and poor areas; (ii) modernizing and increasing the capacity of key national railway system routes to improve transport efficiency; (iii) commercializing railway operations to sustain efficient operations; and (iv) increasing railway competitiveness in the transport sector through restructuring and policy reform. The strategy will continue to focus on railway development in underserved areas in poor interior provinces, to link lower-income regions with growth centers and facilitate pro-poor growth. Policy issues addressed include corporatization, marketing and business development, and tariff-setting with improved cost recovery. ADB enhanced policy dialogue with MOR and is providing technical assistance support for MOR policy reforms. 3 This consultation will continue to further reforms in the sector. 9. The Project envisages the construction of 141 km of Class I electrified railway line and 13 new railway stations, with subgrades, bridges, and tunnels. Tunnels and bridges will comprise 51.5% of the route length because of hills along the Yuxi-Mengzi railway route. The railway will cross Yunnan province from Yuxi running southward through the Yuxi district and Honghe prefecture to Mengzi in the southwest. The project area includes two cities and three counties with a total population of about 3.56 million in Yuxi city, Tonghai county, Jianshui county, Geiju city, and Mengzi county. The total rural population is about 2.8 million about 0.44 million (15.7%) live below the poverty line, including inhabitants in 259 poverty villages that do not have access to highway (65 villages), electricity (17 villages), telephone (78 villages), and good drinking water (440 villages). In the project area, 34.1% of inhabitants are from ethnic minorities mainly Yi, Hani, Dai, Hui, and Meng, with smaller concentrations of Miao and Lago. The proposed railway project will directly benefit a significant number of the poor, especially through the construction of 13 new railway stations. The proposed Project will cause resettlement due to the requirements of the new alignment and construction of new railway stations. Total land acquisition area is estimated at hectares (ha) of permanent land and 3 ADB Technical Assistance to the People s Republic of China for World Trade Organization-Policy Reform Support to the Ministry of Railways. Manila.

6 ha of temporary land. In addition, the Project will displace 55,105 square meters (m 2 ) of structures and relocate 460 households The rationale for the Project reflects the need to (i) develop the railway network; (ii) enhance capacity; (iii) enhance regional cooperation; (iv) reduce energy consumption and environmental pollution; (v) meet the needs of the new railway development plan and the western region development strategy; and (vi) promote pro-poor economic growth along the line and in the region. The proposed railway line will connect with the Kunming-Chengdu, Kunming- Guiyang, Kunming-Nanning, Kunming-Neijiang main lines, and Kunming-Lijiang 5 through the Kunming-Kunyang-Yuxi railway line in the north and Mengzi-Hekou in the south, to the LaoCai- Hanoi-Ho Chi Minh city and Haiphong port in Viet Nam. This line extends northward to Chengdu and Nanning, connecting with the Chen-Kun and Nan-Kun routes; and westward to Hekou to connect with the Kun-Hue line. The existing meter gauge Kun-Hue railway line built in 1903 is in poor condition and cannot meet existing traffic demand, so capacity must be added. The existing highway runs between Kunming and Mengzi only. 11. Once completed, the connection will provide the shortest link from Kunming to Hekou and connect to the proposed pan-asian railway to Viet Nam, Cambodia, Thailand, Malaysia, and Singapore. The Project will provide access to Haiphong port in Viet Nam 6, and South and Southeast Asia promoting regional cooperation in the Greater Mekong Subregion. The railway is the most energy efficient and environmentally friendly mode of transport and is at least six times more fuel-efficient than the best mode of road transport. The electric line will have small energy requirements and cause minimal environmental pollution. The proposed Project will be a joint-venture railway project, with equity participation from MOR and Yunnan provincial government. 12. The project area has large mineral reserves and is rich in food grains and forest produce. It has chemical, engineering, cement, and manufacturing industries and a number of tourist sites. The proposed railway will pass through an alignment area that has remained cut off from mainstream development, due to lack of transportation and its remote location. Poor accessibility and lack of economic transport impeded economic growth in the resource rich area. The region has many tourist spots and potential is enormous. This can be maximized with the development of the railway line, as the line will provide much-needed economic, reliable, and safe transport. The provincial and local governments and people living in the project area view the railway as a key investment crucial to create employment and income-generating activities and a prerequisite for reducing poverty. 13. The proposed railway will carry both passenger and freight traffic and help develop the railroad network in an unserved area. It is included in MOR s updated Tenth Five-Year Plan, as well as the railway development plan, and will support the Government s western region development strategy. By the year 2012 and 2020, the project railway is expected to carry 7 million tons of freight and 1.3 million passengers, and 9 million tons of freight and 1.7 million passengers, respectively. This will facilitate economic development and integration of the poor western region; and stimulate industrial and natural resources development, and tourism and related industries. It will also increase local people s access to market and social services, and allow them to improve their standard of living. ADB-financed railway projects show that such 4 These estimates are preliminary and will be revised during the project preparatory TA. 5 Part of this is financed by ADB under ADB Report and Recommendation of the President to the Board of Directors on Proposed Loan to the People s Republic of China for the Dali-Lijiang Railway Project. Manila, which is currently under implementation. 6 ADB is supporting the development of Kunming Haiphong corridor and is considering financing improvements on the existing railway line from Lao Cai to Haiphong in Viet Nam.

7 4 projects create jobs in construction and loading and unloading operations, as well as other income-generating activities. 7 Lower transportation costs after project completion will make goods and services available at lower prices and allow local people to sell their produce to broader markets. The railway will offer more affordable, reliable, and punctual transport. The Project is consistent with ADB s country operational strategy and will support the Government s strategic policy objective of greater developmental emphasis on poor, interior, and underserved areas of the PRC by improving transport links with growth centers. 14. The National Development Reforms Commission approved the project proposal on 25 February MOR has prepared a feasibility study with cost estimates and traffic forecasts. The Yunnan provincial government has established a project leading group and confirmed that all cities/counties to be affected by resettlement have implemented locally-funded projects involving resettlement. Resettlement under the Project will be implemented according to national laws, provincial regulations, and ADB s Policy on Involuntary Resettlement. 15. ADB has pursued the introduction of operational reforms and enhanced railway safety with MOR, which is in a transition phase and is upgrading its technology and systems. It is adopting high-speed passenger train and heavy load freight train operation systems. These developments require an urgent comprehensive approach to safety development on PRC railways. ADB is supporting a separate additional project component to promote sustainable safety systems, and help MOR modernize and upgrade its existing management systems and technology to meet current and future requirements of safe, reliable train operation. MOR is preparing a draft feasibility study detailing the rationale, objective, scope and components, cost estimates, and monitoring indicators for this component. III. THE TECHNICAL ASSISTANCE A. Impact and Outcome 16. The TA aims to (i) assist the Government in reviewing and strengthening the two feasibility studies, EIA, resettlement plan, and related studies to meet ADB's financing requirements; (ii) identify policy measures and institutional development needs to improve railway safety, operational efficiency and management, and ensure financial sustainability of operations; and (iii) identify social dimensions to be incorporated in project design (including measures to enhance social development and reduce poverty in the project area). The outcome will be the design of a project suitable for ADB financing. B. Methodology and Key Activities 17. The TA will (i) review and strengthen the two feasibility studies to meet ADB requirements for (a) technical aspects (railway safety, construction, and operation); (b) economic and financial analyses (including a review of the traffic forecast and financial performance of project facility operations); and (c) financial management assessment (including a review of budgetary and planning control, financial and management accounting, and internal control and audit systems); (ii) develop a set of verifiable performance indicators (including socioeconomic and poverty) and a sustainable monitoring mechanism for during and after construction; (iii) recommend policy measures to improve railway safety, enhance operational efficiency and management, and assess specific institutional development needs to 7 In the ADB-financed Daxian Waxian Railway Project, the average net income along the proposed alignment of the railway increased by 25% in real terms during the construction period. The average real increase in Chongqing for the same period was approximately 10%. Education is often the first spending priority for families. Increased income has reportedly led some poor people out of debt for the next generation s education.

8 5 commercially operate the project facilities and ensure financial sustainability; (iv) review potential for private sector participation in construction, provision of services, and tourism development; (v) review and update EIA and prepare a summary EIA with appropriate environmental monitoring and management plans; (vi) review and refine the resettlement plan to ensure compliance with ADB s Policy on Involuntary Resettlement and relevant operations manuals; (vii) review the initial poverty and social assessment; carry out a detailed poverty, social and gender analysis (including a baseline gender-disaggregated socioeconomic profile of project area inhabitants); and prepare relevant mitigation and enhancement measures (Appendix 2); (viii) prepare a development plan for ethnic minorities, according to ADB guidelines; and (ix) undertake distribution analysis of the Project and associated developments on poverty reduction (including poverty impact). Key activities are field surveys; document review; data analysis; and consultations with stakeholders (including government officials, project beneficiaries, and project-affected people ethnic minorities, women, and the poor). C. Cost and Financing 18. The cost of the TA is estimated at $670,000 equivalent, comprising $376,000 in foreign exchange and $294,000 equivalent in local currency costs (Appendix 3). The Government requested that ADB finance $500,000 equivalent to cover the entire foreign exchange cost and $124,000 equivalent of the local currency cost. The TA will be financed on a grant basis by ADB s TA funding program. MOR will provide the remaining $170,000 equivalent in local currency cost for counterpart staff members, office facilities, support services, and local communications. The Government and MOR have been informed that approval of the TA does not commit ADB to financing any ensuing project. D. Implementation Arrangements 19. MOR will be the Executing Agency, with responsibility for supervising and monitoring TA activities. The Government and MOR agreed to provide assistance for the TA. MOR will make available (i) all relevant reports, studies, and information; (ii) suitable office accommodation and appropriate and qualified counterpart staff; (iii) local transport facilities; and (iv) any other assistance that the consultants may reasonably request (including liaison with the Government and local authorities). 20. The TA will require about 39 person-months of consulting services (16 international and about 23 domestic), including fieldwork. The TA will be implemented over 5 months from January to July ADB will engage the consultants in accordance with its Guidelines on the Use of Consultants and other arrangements satisfactory to ADB for the engagement of domestic consultants. Recruitment of consultants will follow the quality- and cost-based selection method, and simplified technical proposals will be required. The international consultants will have expertise in transport economics, financial analysis, railway safety, railway engineering and operation, institution building, environment, resettlement and social poverty analysis. Expertise required form domestic consultants will be in the fields of transport economics, railway safety, railway engineering and operation, environment, resettlement and social poverty analysis. Appendix 4 gives the outline terms of reference for consulting services. The consultants will procure equipment in accordance with ADB s Guidelines for Procurement. IV. THE PRESIDENT'S DECISION 21. The President, acting under the authority delegated by the Board, has approved the provision of technical assistance not exceeding the equivalent of $500,000 on a grant basis to the Government of the People s Republic of China for preparing the Railway Development Project, and hereby reports this action to the Board.

9 6 Appendix 1 DESIGN AND MONITORING FRAMEWORK Design Summary Performance Targets/Indicators Data Sources/Reporting Mechanisms Assumptions and Risks Impact An efficient, reliable, and affordable railway transport system is developed in the region. Passenger and freight traffic volumes increased in 2012 and Travel time reduced from Kunming to Mengzi (8 to 5 hours), and Yuxi to Mengzi (5 to 3 hours) Cost of travel reduced in 2012 Accident rate reduced in 2012 and 2020 MOR statistics and operating data before and after the Project Progress reports Project administration missions and project completion report Postevaluation surveys and reports from EA Local government statistics Assumptions Forecast economic growth rates are achieved Traffic forecasts for the Yuxi-Mengzi railway are realized Users of other transport modes will change to the Yuxi-Mengzi railway Commitment of local governments for local area development is sustained Outcome Project design and feasibility study suitable for ADB financing, agreed by Government and ADB Shops, tourist centers, hotels, and businesses established near station areas by 2012 and 2020 Memorandum of understanding signed by Government and ADB during appraisal mission of October 2006 Memorandum of understanding Assumptions Government willing to address necessary changes in priorities Government obtains additional sources of funding Outputs 1. Technical assessments 2. Project design requirements Inception report submitted to Government and ADB by February 2006 Summary EIA, poverty and social analysis, resettlement plan, and ethnic minorities development plan submitted to Government and ADB by April 2006 ADB document registration Government document registration Assumption Effective stakeholder participation and ownership developed Risks Restricted availability of and access to information and government personnel Draft final report submitted to Government and ADB by May 2006

10 Appendix 1 7 Activities with Milestones 1.1 Analyze transport demand in the region (by May 2006). 1.2 Assess the adequacy of railway infrastructure (by May 2006). 1.3 Review technical aspects related to railway construction and operation (by May 2006) Develop a set of verifiable performance indicators, including socioeconomic and poverty (by May 2006). 1.5 Recommend policy reform measures and institutional development needs (by May 2006). 1.6 Review potential for private sector participation (by May 2006). Inputs ADB: $500, person-months of international and 23 person-months of domestic consulting services Government: $170, Carry out consultations with stakeholders, including government officials, project beneficiaries, and affected people ethnic minority groups, women, and the poor (February March 2006). 2.2 Undertake social and poverty assessment (by April 2006). 2.3 Complete baseline survey (by March 2006). 2.4 Carry out financial and economic analysis (by April 2006). 2.5 Undertake institutional analysis (by April 2006). 2.6 Complete summary initial environmental examination (by April 2006). 2.7 Prepare resettlement and ethnic minorities development plan, if required (by April 2006). 2.8 Finalize project design and monitoring framework (by May 2006). ADB = Asian Development Bank, EA = executing agency, EIA = environmental impact assessment, MOR = Ministry of Railways.

11 8 Appendix 2 A. Linkages to the Country Poverty Analysis INITIAL POVERTY AND SOCIAL ANALYSIS Is the sector identified as a national priority in country poverty analysis? Yes No Is the sector identified as a national priority in country poverty partnership agreement? Yes No Contribution of the sector or subsector to reduce poverty in the People s Republic of China: The transport sector and railway subsector contribute to poverty reduction directly through improved access to markets, employment opportunities, and social services, and indirectly by stimulating economic development. B. Poverty Analysis Targeting Classification: General intervention What type of poverty analysis is needed? Poverty analysis will be carried out to assess the impact of the new railway on existing railway services (passenger and freight) that currently serve the poor. The analysis will be carried out following the Asian Development Bank s Handbook on Poverty and Social Analysis and Handbook for Integrating Poverty Impact on Economic Analysis of Projects. C. Participation Process Is there a stakeholder analysis? Yes No Is there a participation strategy? Yes No To be determined D. Gender Development Strategy to maximize impacts on women: The railway project in general will provide equal opportunity to women, and past experience indicates that some of the unskilled jobs are taken by women, which will be included in the project design. Has an output been prepared? Yes No E. Social Safeguards and Other Social Risks Item Resettlement Significant/ Not Significant/ None Significant Not significant None Strategy to Address Issues A resettlement plan will be prepared following the Land Administration Law and ADB policy. The plan will be disclosed to the public and affected people. Internal and external monitoring arrangements will be put in place. Plan Required Full Short None

12 Appendix 2 9 Item Affordability Significant/ Not Significant/ None Significant Not significant Strategy to Address Issues The proposed tariffs will be lower than current service charges, as rail travel is considerably cheaper than road and other modes of transport hence, more affordable. Plan Required Yes No Labor None Significant Not significant The Project will contribute to creating employment opportunities during construction and will not have any adverse impact on labor issues. Yes No Indigenous Peoples None Significant Not significant None The project impact area includes 34.1% minority nationalities, including Dai, Hani, Yi and others who will be affected by land acquisition. Compensation is addressed in the resettlement plan and additional measures will be taken to enhance their benefits from the project. Yes No Other Risks and/or Vulnerabilities Significant Not significant None The railway will be more affordable, and no negative impacts of ADB intervention are likely. However, these will be further assessed by project preparatory technical assistance consultants. Yes No

13 10 Appendix 3 COST ESTIMATES AND FINANCING PLAN ($'000) Foreign Local Total Item Exchange Currency Cost A. Asian Development Bank Financing a 1. Consultants a. Remuneration and Per Diem i. International Consultants ii. Domestic Consultants b. International and Local Travel c. Reports and Communications Equipment b Training, Seminars, and Conferences Surveys Miscellaneous Administration and Support Costs 6. Representative for Contract Negotiations Contingencies Subtotal (A) B. Government Financing 1. Office Accommodation and Transport Remuneration and Per Diem of Counterpart Staff 3. Others Subtotal (B) Total a Financed by the Asian Development Bank s technical assistance funding program. b Including computer hardware and software, photocopier, facsimile machine, and other equipment to be procured under the consultant s contract, in accordance with procedures acceptable to the Asian Development Bank, and whose ownership will be transferred to the Government. Source: Asian Development Bank estimates.

14 Appendix 4 11 A. Scope of Services OUTLINE TERMS OF REFERENCE FOR CONSULTANTS 1. The scope of the technical assistance (TA) includes (i) railway safety, engineering, and operations; (ii) economic and financial analyses; (iii) policy measures to improve operational efficiency and management; (iv) environmental impact assessment (EIA) report with appropriate environmental monitoring and management plans; (v) resettlement plan; and (vi) poverty, social, and gender analysis, including an ethnic minorities development plan. B. Terms of Reference 2. The tasks under the TA will include, but will not necessarily be limited to, the following: 3. Railway Safety, Engineering, and Operations. The railway safety, engineering, and operations expert will undertake the following tasks: (i) (ii) (iii) (iv) (v) (vi) (vii) (viii) Review the Government s plan for development of a transportation network and other infrastructure in the project area, including the building of the Yuxi Mengzi railways (YMR), upgrading the existing Kunming-Hekou railway, complementary road network, and constructing link and access roads, other infrastructure, and social development programs. Document details of projects and/or programs, giving estimated cost, funding source, implementing agencies, schedules, and benefits envisaged. Review the Government s plan for sustainable safety development of PRC railways, including plans to modernize and upgrade technology and management. Prepare a status paper on safety, clearly identifying the issues and suggesting proposed actions. Recommend issues and actions that could be carried out under the proposed Project. Document details of ongoing and planned projects/programs giving estimated cost, funding source, implementing agency, schedule, and envisaged benefits. Analyze project and alignment alternatives to determine if the least-cost solution is proposed while minimizing environmental impact and involuntary resettlement. Review capacity of connecting railway lines, identify network constraints that may affect traffic to and from the YMR, and review plans for their mitigation. Assess how the Project will enhance regional cooperation with Greater Mekong Subregion (GMS) countries. Evaluate the regional benefits of the proposed railway and suggest options (including intermodal and facilitation measures) to maximize the traffic potential within the People s Republic of China (the PRC) and with the GMS region. Review all technical aspects presented in the two feasibility studies and preliminary designs, including safety aspects during construction and operation and maintainability of the new railway line after its completion. Review and update the cost estimates on the basis of current prices of goods and services (including the costs of environmental mitigation measures and monitoring, land acquisition, and resettlement). Prepare a list of contract packages for ADB financing that may be procured using international competitive bidding procedures, in accordance with ADB s Guidelines for Procurement. Review the implementation arrangements and organizational setup for project management and maintaining project accounts, and recommend any required changes. Prepare an implementation schedule and schedule for disbursement of loan and counterpart funds. Review requirements for tourism development (including provision of facilities and operational arrangements). Assess which of these could be offered to the

15 12 Appendix 4 (ix) (x) public and/or private sector on a profit-sharing basis to facilitate tourism development in the project area. Review requirements and proposals for passenger stations and station facilities, industrial sidings, and marshalling yards. Make recommendations on how their construction may be facilitated to benefit the railway, passengers and/or users. Examine multimodal issues to enhance the overall positive impact of the Project. Prepare a design and monitoring framework that outlines the impact, outcome, outputs, and activities and inputs under the Project, in accordance with staff instructions on the use of logical frameworks for ADB-assisted loans and TA. 4. Economic Analysis. The transport economist will undertake the following tasks: (i) (ii) (iii) (iv) (v) Include in the economic analysis (a) economic analysis of the Project as further described in this section; (b) economic analysis of the program for development of associated transport infrastructure (such as roads and other infrastructure that would help maximize poverty reduction); (c) economic analysis taking into account items (a) and (b) combined; and (d) distribution analysis, including poverty impact ratios for items (a) and (b) taken separately and combined. All economic analyses should be carried out in accordance with ADB s Guidelines on Economic Analysis of Projects, Handbook for Integrating Poverty Impact Assessment in the Economic Analysis of Projects, and Handbook on Poverty and Social Analysis. Review the project rationale and provide a basis for ADB involvement. Assess the relevance and priority of the Project to the transport sector strategy, ADB s and the Government s development strategies, and the United Nations Millennium Development Goals. Assess service differentiation with road transportation in terms of types of transport services demanded, bus and truck service complementarity, and competition. Review demand for transport of goods by the railway based on origin-destination data and traffic forecast by commodity. Review demand for passenger traffic based on an origin-destination survey. Develop passenger profile for the railway. Subdivide forecast of freight and passengers into categories to show the source of the traffic and enable the benefits of the railway and modal competition to be estimated. Subdivide forecast into traffic diverted from roads, traffic diverted from other modes, and traffic generated. The traffic forecast should cover 25 years from the start of project operation, under basecase and low-case scenarios, which consider experiences gained and lessons learned from similar projects, in which actual traffic was less than forecasts due to delays in implementation of envisaged developmental projects that were expected to provide traffic for the Project and/or any other reasons. Identify all project costs and benefits comparing with and without project situations. Estimate economic internal rate of return on the basis of nonincremental and incremental economic benefits and economic costs (including economic capital, operation, and maintenance costs) in constant economic prices. In an economic analysis, evaluate the environmental aspects and analyze poverty reduction benefits envisaged under the Project. During project operation, include in the economic analysis the effects on poverty reduction through the provision of goods at affordable prices due to more economic and cheaper rail transportation, increased prices of goods received by rural producers at the markets in urban areas, and less costly personal travel. Also include incremental benefits related to the Project. Undertake sensitivity analysis to assess the effects of adverse changes in key assumptions that underline the economic analysis (including but not limited to project costs, traffic, and implementation delays). Express results as a sensitivity

16 Appendix 4 13 (vi) indicator and a switching value. If the Project is sensitive to the value of a key variable, recommend measures to minimize the risk. Carry out quantitative risk analysis in accordance with ADB s Handbook for Integrating Risk Analysis in the Economic Analysis of Projects. Develop for project monitoring, together with item (i), a set of performance indicators that can be verified and monitored (including operational, financial, environmental, socioeconomic, and poverty reduction parameters). Specify baseline targets for socioeconomic and poverty indicators and a sustainable mechanism for monitoring during and beyond the construction stage. Assess the developmental impact of the Project, focusing on generated economic activities. Draw up a project performance management system. 5. Financial and Institutional. The financial and institutional expert will undertake the following tasks: (i) (ii) (iii) (iv) (v) Undertake financial analysis of the Project following ADB s Guidelines for the Financial Governance and Management of Investment Projects Financed by ADB, including a financial return at constant prices and financial projections over 25 years at current prices. Calculate financial internal rate of return and weighted average cost of capital for comparison with the financial internal rate of return. Conduct sensitivity analysis (including the effects of a change in the exchange rate). Prepare the financial projections of the existing railway administration in the project area on a pro forma basis. Review the potential for private sector participation in the construction of project facilities and provision of services for operation and tourism development, and assess the financial impact. Review the status of reforms in the railway sector (since 1985). Document the status of their implementation, achievements and lessons learned, and impact of reforms on the operational efficiency and profitability of the national railway and the Project. Review Railway Development Plan (2020) and the reforms that are proposed to be implemented in the future, together with their likely impacts. The status should be reflected in a matrix, together with supporting background and description. Review and recommend additional areas for reform in the railway sector in general and the Project in particular, which could be pursued under the Project. Examine the adequacy of operational, financial, and institutional arrangements for separating freight and passenger traffic. Review the organizational structure for the proposed YMR and identify specific areas where support is required for institutional development. Review the institutional arrangements for railway safety in PRC railways and identify areas which could be supported by ADB under the proposed component on railway safety. 6. Environmental. The environmental expert will undertake the following tasks: (i) (ii) Analyze the following aspects: (a) review the EIA to ensure it conforms to ADB s Environment Policy, 2002 and Environmental Assessment Guidelines 2003 and Environmental Review Procedures; (b) assist the Ministry of Railways (MOR) (the Executing Agency) in carrying out further investigations and analyses, as required, and in finalizing the environmental impact statement, management plan, and monitoring plan by incorporating comments from ADB and provincial environmental protection bureaus; and (c) prepare summary EIA. Assess major issues in the EIA (based on a preliminary environment scoping) to include impacts on ecological resources, cultural heritage sites, tourism: (a) soil

17 14 Appendix 4 (iii) erosion, (b) noise and air quality, (c) spills of hazardous or toxic chemicals, and (d) construction activity disturbances affecting communities. The EIA will include detailed plans for (a) protection of sensitive ecological areas, (b) protection or enhancement of environmental resources that promote tourism, (c) mitigation of environmental impacts from construction activities, (d) containment and cleanup of hazardous or toxic chemical spills, and (e) health and safety for construction workers and local people. Assess potential induced impacts, if any, on environment and ecosystem and reflect in the EIA report. The consultant will (a) determine costs of the proposed environmental measures, (b) appraise the level of cost against expected environmental benefits, (c) assist MOR in incorporating appropriate mitigating measures into the project design, (d) prepare contractor specifications for environmental management and monitoring, and (e) prepare terms of reference and budget for independent environment monitoring and evaluation. The consultant will assist MOR with public consultation and EIA preparation. 7. Poverty, Social, and Gender Analysis. The poverty, social, and gender expert will undertake the following tasks: (i) (ii) (iii) Prepare socioeconomic and poverty profiles for the areas to be served by the railway and local roads. Collect data through statistical records, necessary field surveys, and key informant interviews and participatory community appraisal techniques. Conduct surveys to develop a profile of transport services and costs that are currently available in the project areas and assess whether accessibility is affordable for low-income groups. This information will also serve as a baseline for performance monitoring. Conduct a poverty, social, and gender analysis (based on the initial poverty and social assessment) in accordance with ADB s Handbook on Poverty and Social Analysis and Handbook for Integrating Poverty Impact on Economic Analysis of Projects. Assess how the proposed construction of the railway will help improve people s incomes and livelihoods. Recommend measures to enhance benefits and minimize adverse impacts, particularly for the poor and ethnic minorities. Assess other social issues (including those related to ethnic minorities, and gender and vulnerable groups) and recommend appropriate measures to address impacts and promote development opportunities during railway construction, and operation and maintenance. Prepare ethnic minorities development plan, as set out in ADB s Indigenous People s Policy Carry out a detailed gender assessment of the project area. If the Project is gender sensitive, formulate strategies and an action plan to enhance project benefits and improve the gender balance within an SDAP and EMDP. (iv) Collect official gender-disaggregated information on the prevalence of HIV/AIDS 1 and other sexually transmitted infections in the Yunnan province and in the project area. Identify ongoing programs and modalities through which the project may complement ongoing government and nongoverment-funded activities aimed at HIV/AIDS prevention, harm reduction, and anti-human trafficking in the project area. (v) Assist MOR in establishing consultative and participatory processes that will continue throughout project design, construction, and operation. Identify stakeholders and representatives to be consulted to incorporate their needs and demands into the Project. Prepare public participation and consultation status report and project implementation plan. 1 Human immunodefiniciency virus/acquired immunodeficiency syndrome.

18 Appendix 4 15 (vi) (vii) Review local government policies, strategies, and programs for poverty reduction and regional economic development for the project area. Analyze how the proposed Project will complement government development programs. Consult with local governments to identify development initiatives that could complement the railway project particularly those targeted at the poor and ethnic minorities and identify possible sources of funding for these initiatives. Develop a set of verifiable and easily monitored gender-disaggregated socioeconomic and poverty indicators. Specify baseline targets and assist with the preparation of performance monitoring and evaluation systems, including a reporting format and how to measure indicators during and beyond the construction stage. 8. Resettlement. The resettlement expert will carry out the following tasks: (i) (ii) (iii) (iv) (v) (vi) Review draft resettlement plan and prepare modifications, as required, to comply with ADB s Handbook on Resettlement: A Guide to Good Practice. Conduct resettlement household surveys to ensure adequate understanding of social impacts. The resettlement plan must include a village-level impact assessment of project-affected people, land, assets, and occupations. Define categories for impact and compensation eligibility of affected people, and prepare an entitlements matrix (covering compensation and other assistance) for all types of impacts to achieve full replacement for lost assets, income, and livelihoods. Identify potential impoverishment risks and vulnerable groups, including gender analysis. Prepare village economic rehabilitation plans for seriously affected villages, which will restore incomes of affected people and host people. Identify specific measures for severely affected people, poor people, ethnic minorities, affected women, or other vulnerable households. Assist MOR and relevant local government officials in initiating and expanding consultation with affected communities, local leaders, local proponents, and local stakeholders who may be opposed to the Project. Prepare a consultation plan for MOR and a format for documenting consultation with affected people. Assist MOR in preparing a resettlement information booklet, and distribute it to affected villages and households. Assess and justify that (a) compensation standards are based on replacement value, and (b) overall resettlement budget is sufficient to acquire land and implement the resettlement plan based on the proposed entitlements and rehabilitation plans. Review the organizational structure and capacity for resettlement implementation and recommend improvements and actions required before the start of land acquisition. Assist MOR in preparing a detailed resettlement implementation schedule and a plan for external and internal monitoring and evaluation. C. Schedule and Reporting Requirements 9. Submit (i) brief monthly progress reports; (ii) an inception report (within 3 weeks of starting work); (iii) a preliminary social analysis (within 6 weeks of starting work); (iv) a draft summary EIA together with the EIA, a supplement to the EIA, a draft resettlement plan, and a draft ethnic minority peoples plan, for YMR, and an interim report for component on railway safety (within 3 months of starting work); (v) the draft final report, including a detailed social analysis (within 4 months of starting work), which will be discussed at a tripartite meeting involving the Government, ADB, and the consultant; (vi) the final report (within 2 weeks of tripartite meeting). All reports will be submitted to ADB in English (3 copies) and to the Government and MOR in English and Chinese (3 copies of each).

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:PRC 36432 TECHNICAL ASSISTANCE TO THE PEOPLE S REPUBLIC OF CHINA FOR PREPARING THE DALI-LIJIANG RAILWAY PROJECT June 2003 CURRENCY EQUIVALENTS (as of 14 May 2003) Currency Unit

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 4 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing loan project and prepared outline technical studies

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 13 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The project preparatory technical assistance (PPTA) is required to help the government of Mongolia design the Regional Road Development

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK . ASIAN DEVELOPMENT BANK TAR: BAN 35242 TECHNICAL ASSISTANCE TO THE PEOPLE S REPUBLIC OF BANGLADESH FOR PREPARING THE GAS SECTOR DEVELOPMENT PROJECT April 2004 CURRENCY EQUIVALENTS (as of 21 April 2004)

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:NEP 37266 TECHNICAL ASSISTANCE (Financed by the Japan Special Fund) TO THE KINGDOM OF NEPAL FOR PREPARING THE TRANSPORT CONNECTIVITY SECTOR PROJECT June 2004 CURRENCY EQUIVALENTS

More information

Project Administration Memorandum. People s Republic of China: Dali-Lijiang Railway Project. Project Number: Loan Number: 2116 October 2005

Project Administration Memorandum. People s Republic of China: Dali-Lijiang Railway Project. Project Number: Loan Number: 2116 October 2005 Project Administration Memorandum Project Number: 36432 Loan Number: 2116 October 2005 People s Republic of China: Dali-Lijiang Railway Project The project administration memorandum is an active document,

More information

People s Republic of China: Study on Natural Resource Asset Appraisal and Management System for the National Key Ecological Function Zones

People s Republic of China: Study on Natural Resource Asset Appraisal and Management System for the National Key Ecological Function Zones Technical Assistance Report Project Number: 50004-001 Policy and Advisory Technical Assistance (PATA) October 2016 People s Republic of China: Study on Natural Resource Asset Appraisal and Management System

More information

Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project

Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project Technical Assistance Project Number: 50098 Project Preparatory Technical Assistance (PPTA) November 2016 Socialist Republic of Viet Nam: GMS Corridor Connectivity Enhancement Project This document is being

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1

SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Country Partnership Strategy: Viet Nam, 2012 2015 SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Investment in the transport sector in Viet

More information

Periodic Financing Request Report. People s Republic of China: Railway Energy Efficiency and Safety Enhancement Investment Program (MFF): Tranche 4

Periodic Financing Request Report. People s Republic of China: Railway Energy Efficiency and Safety Enhancement Investment Program (MFF): Tranche 4 Periodic Financing Request Report Project Number: 43332 December 2013 People s Republic of China: Railway Energy Efficiency and Safety Enhancement Investment Program (MFF): Tranche 4 CURRENCY EQUIVALENTS

More information

Republic of the Maldives: Preparing Business Strategy for Port Development

Republic of the Maldives: Preparing Business Strategy for Port Development Technical Assistance Report Project Number: 47283 Capacity Development Technical Assistance (CDTA) November 2013 Republic of the Maldives: Preparing Business Strategy for Port Development The views expressed

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 9 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The PPTA will review and assess the performance of the secondary education subsector in Viet Nam and identify the challenges, which

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:INO 34147 TECHNICAL ASSISTANCE (Cofinanced by the Government of the United Kingdom) TO THE REPUBLIC OF INDONESIA FOR INTEGRATION OF POVERTY CONSIDERATIONS IN DECENTRALIZED EDUCATION

More information

Team Leader: Srinivasan Palle Venkata, Evaluation Specialist ( Contact:

Team Leader: Srinivasan Palle Venkata, Evaluation Specialist (  Contact: Asian Development Bank. 6 ADB Avenue, Mandaluyong City, 1550 Metro Manila, Philippines Tel +63 2 632 4444; Fax +63 2 636 2163; evaluation@adb.org; www.adb.org/evaluation Evaluation Approach Paper Project

More information

Republic of the Philippines: Preparing the Road Sector Improvement Project

Republic of the Philippines: Preparing the Road Sector Improvement Project Technical Assistance Report Project Number: 41076 July 2008 Republic of the Philippines: Preparing the Road Sector Improvement Project (Financed by the Japan Special Fund) The views expressed herein are

More information

Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2

Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2 Technical Assistance Report Project Number: 40345 April 2008 Republic of the Philippines: Strengthening Provincial and Local Planning and Expenditure Management Phase 2 The views expressed herein are those

More information

People's Republic of China: Ganzhou Longyan Railway Project

People's Republic of China: Ganzhou Longyan Railway Project Validation Report Reference Number: PCV: PRC 2009-22 Project Number: 33442 Loan Number: 1850 December 2009 People's Republic of China: Ganzhou Longyan Railway Project Independent Evaluation Department

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: SAM 35132 TECHNICAL ASSISTANCE (Financed by the Japan Special Fund) TO THE INDEPENDENT STATE OF SAMOA FOR PREPARING THE SAVAI I RENEWABLE ENERGY PROJECT November 2002 CURRENCY

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: NEP 37196 TECHNICAL ASSISTANCE TO THE KINGDOM OF NEPAL FOR RESTRUCTURING OF NEPAL ELECTRICITY AUTHORITY December 2004 CURRENCY EQUIVALENTS (as of 3 November 2004) Currency Unit

More information

Nepal: Preparing the North South Fast Track Road Project

Nepal: Preparing the North South Fast Track Road Project Technical Assistance Report Project Number: 40011 September 2006 Nepal: Preparing the North South Fast Track Road Project (Financed by the Japan Special Fund) CURRENCY EQUIVALENTS (as of 15 September 2006)

More information

People s Republic of Bangladesh: Updating the Road Master Plan

People s Republic of Bangladesh: Updating the Road Master Plan South Asia Subregional Economic Cooperation Dhaka Northwest Corridor Road Project, Phase 2 (RRP BAN 40540) Technical Assistance Report Project Number: 40540-016 Transaction Technical Assistance (TRTA)

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: VIE 38561 TECHNICAL ASSISTANCE (Financed by the Poverty Reduction Cooperation Fund) TO THE SOCIALIST REPUBLIC OF VIET NAM FOR DEVELOPING AGRICULTURAL INSURANCE December 2004

More information

Papua New Guinea: Preparing the Highlands Highway (Southern Highlands and Enga Provinces Network) Rehabilitation Project

Papua New Guinea: Preparing the Highlands Highway (Southern Highlands and Enga Provinces Network) Rehabilitation Project Technical Assistance Report Project Number: 40173 June 2007 Papua New Guinea: Preparing the Highlands Highway (Southern Highlands and Enga Provinces Network) Rehabilitation Project (Financed by the Japan

More information

People s Republic of China: Promotion of a Legal Framework for Financial Consumer Protection

People s Republic of China: Promotion of a Legal Framework for Financial Consumer Protection Technical Assistance Report Project Number: 47042-001 Policy and Advisory Technical Assistance (PATA) October 2013 People s Republic of China: Promotion of a Legal Framework for Financial Consumer Protection

More information

OUTLINE TERMS OF REFERENCE FOR CONSULTANTS

OUTLINE TERMS OF REFERENCE FOR CONSULTANTS Strengthening Public Financial Resource Management through Information and Communication Systems Technology Systems (TRTA MON 51084) OUTLINE TERMS OF REFERENCE FOR CONSULTANTS 1. The transaction technical

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:CAM 36593 TECHNICAL ASSISTANCE TO THE KINGDOM OF CAMBODIA FOR IMPROVING INSURANCE SUPERVISION December 2002 CURRENCY EQUIVALENTS (as of 3 December 2002) Currency Unit riel (KR)

More information

PROJECT PREPARATION TECHNICAL ASSISTANCE

PROJECT PREPARATION TECHNICAL ASSISTANCE 12 Appendix 4 A. Justification PROJECT PREPARATION TECHNICAL ASSISTANCE 1. A regional project preparatory technical assistance (R-PPTA) is required to prepare the Pacific Renewable Energy Investment Facility

More information

Mongolia: Development of State Audit Capacity

Mongolia: Development of State Audit Capacity Technical Assistance Report Project Number: 47198-001 Capacity Development Technical Assistance (CDTA) November 2013 Mongolia: Development of State Audit Capacity The views expressed herein are those of

More information

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT A. Sector Road Map Road Improvement and Institutional Development Project (RRP PHI 41076) SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT 1. Sector Performance, Problems and Opportunities 1. Roads provide

More information

Republic of the Philippines: Supporting Capacity Development for the Bureau of Internal Revenue

Republic of the Philippines: Supporting Capacity Development for the Bureau of Internal Revenue Technical Assistance Report Project Number: 46429-001 Capacity Development Technical Assistance (CDTA) April 2013 Republic of the Philippines: Supporting Capacity Development for the Bureau of Internal

More information

Socialist Republic of Viet Nam: Preparing the Hai Phong Water Supply Project

Socialist Republic of Viet Nam: Preparing the Hai Phong Water Supply Project Technical Assistance Report Project Number: 41425 October 2008 Socialist Republic of Viet Nam: Preparing the Hai Phong Water Supply Project (Financed by the Netherlands Trust Fund for the Water Financing

More information

TECHNICAL ASSISTANCE: HIMACHAL PRADESH POWER SECTOR CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT

TECHNICAL ASSISTANCE: HIMACHAL PRADESH POWER SECTOR CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT Himachal Pradesh Clean Energy Transmission Investment Program (RRP IND 43464) TECHNICAL ASSISTANCE: HIMACHAL PRADESH POWER SECTOR CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT A. INTRODUCTION 1. The

More information

Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project

Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project Project Design Advance Project Number: 47279-003 September 2016 Islamic Republic of Pakistan: Karachi Bus Rapid Transit Project This document is being disclosed to the public in accordance with ADB's Public

More information

Technical Assistance Report

Technical Assistance Report Technical Assistance Report Project Number: 40280 September 2007 Islamic Republic of Afghanistan: Technical Assistance for Support for Economic Policy Management (Cofinanced by the Government of Australia

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK TAR:LAO 29284 ASIAN DEVELOPMENT BANK TECHNICAL ASSISTANCE TO ThE LAO PEOPLE'S DEMOCRATIC REPUBLIC FOR ThE CORPORATE AND FINANCIAL DEVELOPMENT OF ELECTRICIT DU LAO LI LI May 1996 - -I CURRENCY EQUIVALENTS

More information

Policy Coordination and Planning of Border Economic Zones of the People's Republic of China and Viet Nam

Policy Coordination and Planning of Border Economic Zones of the People's Republic of China and Viet Nam Technical Assistance Report Project Number: 49400-001 Policy and Advisory Technical Assistance (PATA) January 2017 Policy Coordination and Planning of Border Economic Zones of the People's Republic of

More information

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN)

SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN) Second Jharkhand State Road Project (RRP IND 49125) SECTOR ASSESSMENT (SUMMARY): ROAD TRANSPORT (NON-URBAN) A. Sector Performance, Problems, and Opportunities 1. State context. The state of Jharkhand was

More information

Viet Nam: Ho Chi Minh City Long Thanh DauGiay Expressway Technical Assistance Project

Viet Nam: Ho Chi Minh City Long Thanh DauGiay Expressway Technical Assistance Project Validation Report Reference Number: PVR-360 Project Number: 40198 Loan Number: 2374 December 2014* Viet Nam: Ho Chi Minh CityLong ThanhDauGiay Expressway Technical Assistance Project Independent Evaluation

More information

Technical Assistance Report

Technical Assistance Report Technical Assistance Report Project Number: 51360-002 Transaction Technical Assistance Facility (F-TRTA) April 2018 Turkmenistan: Preparing the Central Asia Regional Economic Cooperation Corridors 2, 3

More information

Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved Project Performance

Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved Project Performance Technical Assistance Report Project Number: 47287-001 Capacity Development Technical Assistance (CDTA) December 2013 Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved

More information

People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project

People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project Validation Report Reference Number: PVR-462 Project Number: 42496-013 Loan Number: 2508 December 2016 People s Republic of China: Emergency Assistance for Wenchuan Earthquake Reconstruction Project Independent

More information

Project Administration Memorandum. Project Number: Loan Number: 2181 July PRC: Central Sichuan Roads Development Project

Project Administration Memorandum. Project Number: Loan Number: 2181 July PRC: Central Sichuan Roads Development Project Project Administration Memorandum Project Number: 34174 Loan Number: 2181 July 2006 PRC: Central Sichuan Roads Development Project CURRENCY EQUIVALENTS (as of 31 August 2005) Currency Unit yuan (CNY) CNY1.00

More information

Socialist Republic of Viet Nam: Preparing the Ho Chi Minh City Metro Rail System Project

Socialist Republic of Viet Nam: Preparing the Ho Chi Minh City Metro Rail System Project Technical Assistance Report Project Number: 39500 October 2006 Socialist Republic of Viet Nam: Preparing the Ho Chi Minh City Metro Rail System Project (Financed by the Japan Special Fund) The views expressed

More information

Institutional Strengthening for Aviation Regulation

Institutional Strengthening for Aviation Regulation Technical Assistance Report Project Number: 43429 Regional capacity development technical assistance (R-CDTA) December 2010 Institutional Strengthening for Aviation Regulation The views expressed herein

More information

Technical Assistance to the Islamic Republic of Pakistan for the Developing Social Health Insurance Project

Technical Assistance to the Islamic Republic of Pakistan for the Developing Social Health Insurance Project Technical Assistance TAR: PAK 37359 Technical Assistance to the Islamic Republic of Pakistan for the Developing Social Health Insurance Project July 2005 CURRENCY EQUIVALENTS (as of 7 July 2005) Currency

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT

SECTOR ASSESSMENT (SUMMARY): TRANSPORT SECTOR ASSESSMENT (SUMMARY): TRANSPORT 1 Sector Road Map 1. Sector Performance, Problems, and Opportunities 1. Myanmar is the largest country in the Greater Mekong Subregion (GMS) with a total land area

More information

SECTOR ASSESSMENT (SUMMARY): CHHATTISGARH ROAD SECTOR. 1. Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): CHHATTISGARH ROAD SECTOR. 1. Sector Performance, Problems, and Opportunities Chhattisgarh State Road Sector Project (RRP IND 44427) Sector Road Map SECTOR ASSESSMENT (SUMMARY): CHHATTISGARH ROAD SECTOR 1. Sector Performance, Problems, and Opportunities 1. The state of Chhattisgarh

More information

Armenia: Infrastructure Sustainability Support Program

Armenia: Infrastructure Sustainability Support Program Technical Assistance Report Project Number: 46220 Policy and Advisory Technical Assistance (PATA) December 2012 Armenia: Infrastructure Sustainability Support Program The views expressed herein are those

More information

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. OM Section F1/BP Page 1 of 3 OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. A. Introduction ENVIRONMENTAL

More information

Socialist Republic of Viet Nam: Preparing the Hue Water Supply Project

Socialist Republic of Viet Nam: Preparing the Hue Water Supply Project Technical Assistance Report Project Number: 41071 May 2008 Socialist Republic of Viet Nam: Preparing the Hue Water Supply Project (Financed by the Netherlands Trust Fund for the Water Financing Partnership

More information

Report and Recommendation of the President to the Board of Directors

Report and Recommendation of the President to the Board of Directors Report and Recommendation of the President to the Board of Directors Project Number: 40626-01 November 2010 Proposed Loan People s Republic of China: Yunnan Integrated Road Network Development Project

More information

Tuvalu: Outer Island Maritime Infrastructure Project

Tuvalu: Outer Island Maritime Infrastructure Project Project Design Advance Project Number: 48484-003 November 2015 Tuvalu: Outer Island Maritime Infrastructure Project This document is being disclosed to the public in accordance with ADB s Public Communications

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR: INO 34149 TECHNICAL ASSISTANCE (Financed from the Japan Special Fund) TO THE REPUBLIC OF INDONESIA FOR PREPARING THE SECOND DECENTRALIZED HEALTH SERVICES PROJECT November 2001

More information

Cook Islands: Preparing the Infrastructure Development Project (Cofinanced by the Japan Special Fund and Government of New Zealand)

Cook Islands: Preparing the Infrastructure Development Project (Cofinanced by the Japan Special Fund and Government of New Zealand) Technical Assistance Report Project Number: 40287 December 2007 Cook Islands: Preparing the Infrastructure Development Project (Cofinanced by the Japan Special Fund and Government of New Zealand) The views

More information

India: Preparing for the Ara Canal Water Productivity Improvement Project

India: Preparing for the Ara Canal Water Productivity Improvement Project Technical Assistance Report Project Number: 52153-002 Transaction Technical Assistance (TRTA) June 2018 India: Preparing for the Ara Canal Water Productivity Improvement Project This document is being

More information

Technical Assistance Republic of Indonesia: Secondary Mortgage Facility

Technical Assistance Republic of Indonesia: Secondary Mortgage Facility Technical Assistance Report Project Number: 39427 December 2005 Technical Assistance Republic of Indonesia: Secondary Mortgage Facility (Financed by the Japan Special Fund) CURRENCY EQUIVALENTS (as of

More information

People s Republic of China: Supporting the Reform of the Role of the People s Bank of China

People s Republic of China: Supporting the Reform of the Role of the People s Bank of China Technical Assistance Report Project Number: 49401-001 Policy and Advisory Technical Assistance (PATA) April 2016 People s Republic of China: Supporting the Reform of the Role of the People s Bank of China

More information

Socialist Republic of Viet Nam: Preparing the Ho Chi Minh City Water Supply Project

Socialist Republic of Viet Nam: Preparing the Ho Chi Minh City Water Supply Project Technical Assistance Report Project Number: 41070 June 2008 Socialist Republic of Viet Nam: Preparing the Ho Chi Minh City Water Supply Project (Financed by the Government of France) The views expressed

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK RRP: PRC 33470 REPORT AND RECOMMENDATION OF THE PRESIDENT TO THE BOARD OF DIRECTORS ON A PROPOSED LOAN TO THE PEOPLE S REPUBLIC OF CHINA FOR THE GANSU ROADS DEVELOPMENT PROJECT November

More information

Democratic Socialist Republic of Sri Lanka: Preparing the Health System Enhancement Project

Democratic Socialist Republic of Sri Lanka: Preparing the Health System Enhancement Project Technical Assistance Report Project Number: 51107-001 Transaction Technical Assistance (TRTA) October 2017 Democratic Socialist Republic of Sri Lanka: Preparing the Health System Enhancement Project This

More information

ASIAN DEVELOPMENT BANK TAR:PRC

ASIAN DEVELOPMENT BANK TAR:PRC ASIAN DEVELOPMENT BANK TAR:PRC 34096-03 TECHNICAL ASSISTANCE TO THE PEOPLE'S REPUBLIC OF CHINA FOR ADVISORY SUPPORT FOR THE NATIONAL COUNCIL FOR THE SOCIAL SECURITY FUND October 2003 CURRENCY EQUIVALENTS

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK TAR:PHI 29226 ASIAN DEVELOPMENT BANK Li TECHNICAL ASSISTANCE TO THE REPUBLIC OF ThE PHILIPPINES FOR PREPARATION OF A NATIONAL TRANSPORT STRATEGY November 1995 CURRENCY EQUIVALENTS (as of 15 October 1995)

More information

Republic of the Philippines: Government-Owned and -Controlled Corporations Reform

Republic of the Philippines: Government-Owned and -Controlled Corporations Reform Technical Assistance Report Project Number: 39606 June 2006 Republic of the Philippines: Government-Owned and -Controlled Corporations Reform The views expressed herein are those of the consultant and

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS South Asia Subregional Economic Cooperation Chittagong-Cox s Bazar Railway Project, Phase 1 (RRP BAN 46452-002) A. Introduction ECONOMIC AND FINANCIAL ANALYSIS 1. The proposed project will construct 102

More information

HO CHI MINH CITY LONG THANH DAU GIAY EXPRESSWAY PROJECT

HO CHI MINH CITY LONG THANH DAU GIAY EXPRESSWAY PROJECT HO CHI MINH CITY LONG THANH DAU GIAY EXPRESSWAY PROJECT 1. Terms of Reference 1. The consulting services under the PPTA will follow the terms of reference set out below. These terms of reference have been

More information

LOAN AGREEMENT (Ordinary Operations) (Ho Chi Minh City Urban Mass Rapid Transit Line 2 Investment Program Loan 2) between

LOAN AGREEMENT (Ordinary Operations) (Ho Chi Minh City Urban Mass Rapid Transit Line 2 Investment Program Loan 2) between LOAN NUMBER 2956-VIE LOAN AGREEMENT (Ordinary Operations) (Ho Chi Minh City Urban Mass Rapid Transit Line 2 Investment Program Loan 2) between SOCIALIST REPUBLIC OF VIET NAM and ASIAN DEVELOPMENT BANK

More information

Mongolia: Developing an Information System for Development Policy and Planning

Mongolia: Developing an Information System for Development Policy and Planning Technical Assistance Report Project Number: 51136-001 Knowledge and Support Technical Assistance (KSTA) September 2017 Mongolia: Developing an Information System for Development Policy and Planning This

More information

SECTOR ASSESSMENT (SUMMARY): TRANSPORT (ROAD TRANSPORT [NONURBAN])

SECTOR ASSESSMENT (SUMMARY): TRANSPORT (ROAD TRANSPORT [NONURBAN]) CAREC Corridors 1 and 6 Connector Road (Aktobe Makat) Reconstruction Project (RRP KAZ 48424) SECTOR ASSESSMENT (SUMMARY): TRANSPORT (ROAD TRANSPORT [NONURBAN]) 1. Sector Performance, Problems, and Opportunities

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE (Preparing the Gujarat Solar and Smart Grid Development Investment Program)

PROJECT PREPARATORY TECHNICAL ASSISTANCE (Preparing the Gujarat Solar and Smart Grid Development Investment Program) PROJECT PREPARATORY TECHNICAL ASSISTANCE (Preparing the Gujarat Solar and Smart Grid Development Investment Program) 1. A project preparatory technical assistance (PPTA) for $700,000 in grant funds is

More information

ATTACHED TECHNICAL ASSISTANCE

ATTACHED TECHNICAL ASSISTANCE Third Capital Market Development Program (RRP BAN 45253) ATTACHED TECHNICAL ASSISTANCE A. Introduction 1. The attached technical assistance (TA) of $700,000 will support implementation of the proposed

More information

Islamic Republic of Pakistan National Motorway M-4 (Shorkot-Khanewal Section) Project

Islamic Republic of Pakistan National Motorway M-4 (Shorkot-Khanewal Section) Project PD 00001-PAK June 6, 2016 PROJECT DOCUMENT Islamic Republic of Pakistan National Motorway M-4 (Shorkot-Khanewal Section) Project This document has a restricted distribution and may be used by recipients

More information

People s Republic of China: Provincial Development Strategies for Chongqing Municipality and Guizhou Province

People s Republic of China: Provincial Development Strategies for Chongqing Municipality and Guizhou Province Attachment 1 Technical Assistance Report Project Number: 42139 Policy and Advisory Technical Assistance (PATA) September 2009 People s Republic of China: Provincial Development Strategies for Chongqing

More information

Integrated Safeguards Data Sheet (Initial)

Integrated Safeguards Data Sheet (Initial) Integrated Safeguards Data Sheet (Initial) Section I - Basic Information Date Prepared/Updated: 06/16/2003 A. Basic Project Data (from PDS) I.A.1. Project Statistics Country: EGYPT, ARAB REPUBLIC OF Project

More information

Environmental Assessment and Review Framework. Mongolia: Western Regional Road Corridor Investment Program

Environmental Assessment and Review Framework. Mongolia: Western Regional Road Corridor Investment Program Western Regional Road Corridor Investment Program (RRP MON 41193) Environmental Assessment and Review Framework September 2011 Mongolia: Western Regional Road Corridor Investment Program Prepared by the

More information

Mongolia: Regional Road Development Project

Mongolia: Regional Road Development Project Validation Report Reference Number: PVR-481 Project Numbers: 35377-013 and 35377-023 Loan/Grant Numbers: 2087, 2621, and 0199 December 2016 Mongolia: Regional Road Development Project Independent Evaluation

More information

ECONOMIC ANALYSIS. Table 1: Total Cost Estimate (Economic Costs) (CNY million)

ECONOMIC ANALYSIS. Table 1: Total Cost Estimate (Economic Costs) (CNY million) Jiangxi Ji an Sustainable Urban Transport Project (RRP PRC 45022) ECONOMIC ANALYSIS A. Project Costs 1. This chapter outlines the methodology and results of the economic analysis for the project, comprising

More information

THE ROAD TO ECONOMIC GROWTH

THE ROAD TO ECONOMIC GROWTH THE ROAD TO ECONOMIC GROWTH Introduction 1. As in many countries, the road sector accounts for the major share of domestic freight and inter-urban passenger land travel in Indonesia, playing a crucial

More information

People s Republic of China: Yunnan Integrated Road Network Development Project

People s Republic of China: Yunnan Integrated Road Network Development Project Validation Report December 2017 People s Republic of China: Yunnan Integrated Road Network Development Project Reference Number: PVR-541 Project Number: 40626-013 Loan Number: 2709 ABBREVIATIONS ADB Asian

More information

People s Republic of China: Preparing Yangtze River Economic Belt Projects

People s Republic of China: Preparing Yangtze River Economic Belt Projects Technical Assistance Report Project Number: 50343-001 Transaction Technical Assistance Facility (F-TRTA) April 2017 People s Republic of China: Preparing Yangtze River Economic Belt Projects Cofinanced

More information

Nepal: Road Connectivity Sector I Project

Nepal: Road Connectivity Sector I Project Validation Report October 2017 Nepal: Road Connectivity Sector I Project Reference Number: PVR-523 Project Number: 37266-032 Grant Number: 0051 ABBREVIATIONS ADB Asian Development Bank DOR Department of

More information

Periodic Financing Request Report. India: Railway Sector Investment Program (Tranche 3)

Periodic Financing Request Report. India: Railway Sector Investment Program (Tranche 3) Periodic Financing Request Report Project Number: 36330-043 MFF Number: 0060 November 2017 India: Railway Sector Investment Program (Tranche 3) Distribution of this document is restricted until it has

More information

Republic of Indonesia: Strengthening National Public Procurement Processes

Republic of Indonesia: Strengthening National Public Procurement Processes Technical Assistance Report Project Number: 43219-01 Capacity Development Technical Assistance (CDTA) November 2010 Republic of Indonesia: Strengthening National Public Procurement Processes (Financed

More information

(i) Loan Disbursement Handbook means ADB s Loan Disbursement Handbook (2012, as amended from time to time);

(i) Loan Disbursement Handbook means ADB s Loan Disbursement Handbook (2012, as amended from time to time); 2 (f) Goods means equipment and materials to be financed out of the proceeds of the Loan, including related services such as transportation, insurance, installation, commissioning, training, and initial

More information

ASIAN DEVELOPMENT BANK TAR: MLD 30026

ASIAN DEVELOPMENT BANK TAR: MLD 30026 ASIAN DEVELOPMENT BANK TAR: MLD 30026 TECHNICAL ASSISTANCE (Financed from the Japan Special Fund) TO THE REPUBLIC OF MALDIVES FOR PRIVATE SECTOR PARTICIPATION IN THE MALDIVES' PORTS November 1998 CURRENCY

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE 8 Appendix 3 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The Government of the Republic of the Union of Myanmar has requested the Asian Development Bank (ADB) to provide a project preparatory

More information

EAST ASIA AND PACIFIC. Investment Project Financing P People's Republic of China

EAST ASIA AND PACIFIC. Investment Project Financing P People's Republic of China Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: PIDA31584 Project Name

More information

Viet Nam: Microfinance Development Program (Subprograms 1 and 2)

Viet Nam: Microfinance Development Program (Subprograms 1 and 2) Validation Report Reference Number: PVR-478 Project Numbers: 42235-013 and 42235-023 Loan Numbers: 2877 and 3213 December 2016 Viet Nam: Microfinance Development Program (Subprograms 1 and 2) Independent

More information

ECONOMIC AND FINANCIAL ANALYSIS

ECONOMIC AND FINANCIAL ANALYSIS Bihar New Ganga Bridge Project (RRP IND 48373) ECONOMIC AND FINANCIAL ANALYSIS A. Introduction 1. The proposed project is to build a new six-lane bridge across the Ganges River near Patna in the state

More information

Report and Recommendation of the President to the Board of Directors

Report and Recommendation of the President to the Board of Directors Report and Recommendation of the President to the Board of Directors Project Number: 43309-015 Loan Number: 2839-CAM September 2016 Proposed Loan for Additional Financing Kingdom of Cambodia: Provincial

More information

Improving the Financial Management Capacity of Executing Agencies in Afghanistan and Pakistan

Improving the Financial Management Capacity of Executing Agencies in Afghanistan and Pakistan Technical Assistance Report Project Number: 46539 Regional Capacity Development Technical Assistance (R CDTA) August 2014 Improving the Financial Management Capacity of Executing Agencies in Afghanistan

More information

Evaluation Study. Midterm Review Process. Operations Evaluation Department

Evaluation Study. Midterm Review Process. Operations Evaluation Department Evaluation Study Reference Number: SES:REG 2008-78 Special Evaluation Study Update December 2008 Midterm Review Process Operations Evaluation Department ABBREVIATIONS ADB Asian Development Bank BTOR back-to-office

More information

Technical Assistance Republic of the Philippines: Harmonization and Managing for Results

Technical Assistance Republic of the Philippines: Harmonization and Managing for Results Technical Assistance Report Project Number: 35166 November 2005 Technical Assistance Republic of the Philippines: Harmonization and Managing for Results The views expressed herein are those of the consultant

More information

People s Republic of China: Preparing the Chongqing Urban Rural Infrastructure Development Demonstration Project

People s Republic of China: Preparing the Chongqing Urban Rural Infrastructure Development Demonstration Project Technical Assistance Report Project Number: 42012 July 2008 People s Republic of China: Preparing the Chongqing Urban Rural Infrastructure Development Demonstration Project CURRENCY EQUIVALENTS (as of

More information

LOAN AGREEMENT (Special Operations) (Greater Mekong Subregion Southern Coastal Corridor Project) between KINGDOM OF CAMBODIA. and

LOAN AGREEMENT (Special Operations) (Greater Mekong Subregion Southern Coastal Corridor Project) between KINGDOM OF CAMBODIA. and LOAN NUMBER 2373-CAM(SF) LOAN AGREEMENT (Special Operations) (Greater Mekong Subregion Southern Coastal Corridor Project) between KINGDOM OF CAMBODIA and ASIAN DEVELOPMENT BANK DATED 18 FEBRUARY 2008 LAS:CAM

More information

Cambodia: Second Power Transmission and Distribution Project

Cambodia: Second Power Transmission and Distribution Project Validation Report Reference Number: PVR-464 Project Number: 37041-013 Loan Number: 2261 December 2016 Cambodia: Second Power Transmission and Distribution Project Independent Evaluation Department ABBREVIATIONS

More information

Islamic Republic of Afghanistan: Preparing the Horticulture Value Chain Development Sector Project

Islamic Republic of Afghanistan: Preparing the Horticulture Value Chain Development Sector Project Technical Assistance Report Project Number: 51039-001 Transaction Technical Assistance (TRTA) September 2017 Islamic Republic of Afghanistan: Preparing the Horticulture Value Chain Development Sector Project

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:ETM 34402 TECHNICAL ASSISTANCE (Financed from the Japan Special Fund) TO EAST TIMOR FOR TRANSPORT SECTOR IMPROVEMENT October 2001 ABBREVIATIONS ADB Asian Development Bank ETTA

More information

PRC: Inner Mongolia Road Development Project Project Preparatory Technical Assistance Concept Paper

PRC: Inner Mongolia Road Development Project Project Preparatory Technical Assistance Concept Paper PRC: Inner Mongolia Road Development Project Project Preparatory Technical Assistance Concept Paper Date: 13 October 2009 1. Country partnership strategy (CPS) / Regional cooperation strategy (RCS): The

More information

Islamic Republic of Pakistan: Update on Energy Sector Plan

Islamic Republic of Pakistan: Update on Energy Sector Plan Technical Assistance Report Project Number: 50081-001 Knowledge and Support Technical Assistance (KSTA) August 2017 Islamic Republic of Pakistan: Update on Energy Sector Plan This The views document expressed

More information

INDIA: Preparing the Rajasthan Secondary Towns Development Investment Program

INDIA: Preparing the Rajasthan Secondary Towns Development Investment Program Appendix 3 9 Technical Assistance Report Project Number: 42267-027 Transaction Technical Assistance (TRTA) June 2017 INDIA: Preparing the Rajasthan Secondary Towns Development Investment Program This document

More information