October 29, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

Size: px
Start display at page:

Download "October 29, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C."

Transcription

1 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C., 46 October 9, 5 Re: Southwest Power Pool, Inc., Docket No. ER6- - Submission of Tariff Amendments to Clarify Treatment of Point-To-Point Transmission Service Revenues Dear Secretary Bose: Pursuant to section 5 of the Federal Power Act ( FPA ), 6 U.S.C. 84d, and Part 35 of the Regulations of the Federal Energy Regulatory Commission ( Commission ), 8 C.F.R. Part 35, Southwest Power Pool, Inc. ( SPP ), as authorized by its Board of Directors, submits revisions to its Open Access Transmission Tariff to resolve ambiguity regarding the treatment of Point-To-Point Transmission Service ( PTP ) revenues in the calculation of a Transmission Owner s Zonal Annual Transmission Revenue Requirement ( ATRR ) for the purposes of determining Monthly Demand Charges and Base Plan Zonal and Region-wide Charges for Network Integration Transmission Service ( NITS ). SPP requests an effective date of January, 6 for the revisions proposed in this filing. In support, SPP states the following: I. BACKGROUND A. SPP SPP is a Commission-approved Regional Transmission Organization ( RTO ). 3 It is an Arkansas non-profit corporation with its principal place of business in Little 3 Southwest Power Pool, Inc., Open Access Transmission Tariff, Sixth Revised Volume No. ( Tariff ). References in this filing to Tariff refer to the version of SPP s Tariff currently in effect. Proposed Tariff refers to revisions proposed in this filing. Capitalized terms not otherwise defined herein shall have the meaning ascribed in the Tariff. Sw. Power Pool, Inc., 9 FERC 6,9 (4), order on reh g, FERC 6,37 (5).

2 The Honorable Kimberly D. Bose October 9, 5 Page Rock, Arkansas. SPP has 94 Members, including 6 investor-owned utilities, 4 municipal systems, 9 generation and transmission cooperatives, 8 state agencies, 3 independent power producers, power marketers, independent transmission companies, and federal agency. As an RTO, SPP administers open access Transmission Service over approximately 56, miles of transmission lines covering portions of Arkansas, Iowa, Kansas, Louisiana, Minnesota, Missouri, Montana, Nebraska, New Mexico, North Dakota, Oklahoma, South Dakota, Texas and Wyoming, across the facilities of SPP s Transmission Owners, 4 and administers the Integrated Marketplace, a centralized day ahead and real-time energy and operating reserve market with locational marginal pricing and market-based congestion management. 5 B. Stakeholder Process The revisions proposed in this filing were developed through the SPP stakeholder process. The process to identify the issues around the treatment of PTP revenues in the Tariff began in the Billing Determinants Task Force ( BDTF ), which is a group organized under the purview of the Regional Tariff Working Group ( RTWG ). The BDTF developed the initial draft of the Tariff revisions proposed herein and first presented them to the RTWG on November 9, 4. 6 The RTWG approved the revisions without opposition on December 7, 4. 7 The Markets and Operations Policy Committee ( MOPC ) unanimously approved the RTWG s actions on January 3, 5 8 and the Board of Directors approved the Tariff revisions for filing on January 7, See Sw. Power Pool, Inc., 89 FERC 6,84 (999); Sw. Power Pool, Inc., 86 FERC 6,9 (999); Sw. Power Pool, Inc., 8 FERC 6,67, order on reh g, 85 FERC 6,3 (998). Sw. Power Pool, Inc., 46 FERC 6,3 (4) (order approving the start-up and operation of the Integrated Marketplace effective March, 4). See RTWG Minutes, dated November 9, 4, at Agenda Item 7 posted at the following location on SPP s website: -%november%9%-%,%4%updated%-9-4.pdf. See RTWG Minutes, dated December 7, 4, at Agenda Item 4 posted at the following location on SPP s website: %9,%4%amended%-8-5.pdf. See MOPC Minutes, dated January 3-4, 5, at Agenda Item 8 posted at the following location on SPP s website: january%3-4,%5.pdf.

3 The Honorable Kimberly D. Bose October 9, 5 Page SPP recognizes that stakeholder approval does not by itself cause a filing to be just and reasonable; however, SPP requests that the Commission extend appropriate deference to the wishes of its stakeholders regarding the revisions proposed in this filing, consistent with Commission precedent. II. DESCRIPTION OF AND JUSTIFICATION FOR PROPOSED TARIFF REVISIONS A. Justification for Proposed Tariff Revisions During the BDTF discussions, SPP staff and stakeholders identified three issues regarding the treatment of PTP revenues that needed either correction or clarification in the Tariff. These three issues create ambiguity regarding the treatment and accounting for PTP revenues under the Tariff and this instant filing seeks to resolve these issues. First, current Section 34. (Monthly Demand Charge) of the Tariff is written in a manner that a Network Customer s monthly Demand Charge accounts for only Schedule 7 (Firm PTP) charges. Under Section 34. of the Tariff, a Network Customer s monthly Demand Charge is determined in part by recognizing any PTP revenues that the Transmission Owner collects. The mechanics of this process involves the reduction of the Demand Charge to the extent PTP revenues are collected by the Transmission Owner. Under Section 34., this reduction can either be accomplished by the Transmission Owner through its formula rate, or SPP settlements does the reduction to the Demand Charge for those Transmission Owners that have a stated rate or don t take PTP revenues into account in its formula rate. This process is intended to assure that the Transmission Owner doesn t over-collect its ATRR by receiving its total ATRR from NITS revenues under Schedule 9 and also additional PTP revenues that SPP collects. When Section See Board of Directors/Members Committee Meeting Minutes No. 6, dated January 7, 5, at Agenda Item 3 posted at the following location on SPP s website (approved as part of the Consent Agenda): The Commission previously has recognized that provisions approved through the stakeholder processes of RTOs are due deference. See Sw. Power Pool, Inc., 7 FERC 6,83, at P 33 (9) (noting that the Commission accord[s] an appropriate degree of deference to RTO stakeholder processes ); Policy Statement Regarding Regional Transmission Groups, FERC Stats. & Regs., Regs. Preambles 3,976, at 3,87 (993) (the Commission will afford an appropriate degree of deference to the stakeholder approval process). See Pub. Serv. Comm n of Wis. v. FERC, 545 F.3d 58, 6-63 (D.C. Cir. 8) (noting that the Commission often gives weight to RTO proposals that reflect the position of the majority of the RTO s stakeholders).

4 The Honorable Kimberly D. Bose October 9, 5 Page 4 was written SPP offered only Firm PTP under the Tariff. Subsequently, SPP has implemented schedules which also generate PTP charges for non-firm PTP (Schedule 8) and the Base Plan Zonal and Region-Wide Charge (Schedule ). However, Section 34. was not updated at the time those schedules were implemented to account the new PTP revenues in the determination of the Network Customer s monthly Demand Charge. Second, Section 34. was implemented prior to the implementation of formula rate templates for SPP Transmission Owners. Since that time, many of SPP s Transmission Owners have implemented formula rate templates that account for (i.e., reduce or credit) Schedules 7, 8, and PTP revenues in the determination of their zonal ATRR. This crediting of PTP revenues is based on the premise that Transmission Owners fully recover their Zonal and Base Plan ATRR from NITS collected pursuant to Schedules 9 and of the Tariff. As a result, Section 34. and Schedule require correction to recognize in a more transparent fashion how PTP revenues are credited in the formula rates and stated rates of Transmission Owners. Finally, the BDTF identified the need to correct provisions of the Tariff which result in the over-collection of revenues by a few Transmission Owners that were inadvertently excluded from the provisions of Section 34. due to the Transmission Owner s integration in an existing zone that was not subject to Section 34. requirements. Currently, Sections 34. and 34.3 of the Tariff provide an exemption from Section 34. for SPP pricing zones (American Electric Power ( AEP-West )) and (Southwestern Public Service Company ( SPS )). When the aforementioned Transmission Owners, were added to these zones, they inadvertently became eligible for the same exception to Section 34.. The result was that the Transmission Owners added to Zones and (and which did not account for PTP revenues in its ATRR) would over-collect its revenue requirements because it received both (i) its stated total ATRR (i.e., that is not reduced under Section 34. to account for its PTP revenues); and (ii) revenues for PTP service on its facilities. SPP did not recognize this unintended consequence when it developed zones and into multi-transmission Owner zones. Notwithstanding the over-collection described above, SPP determined the filed-rate doctrine prohibited SPP from adjusting the Transmission Owner s ATRR to account for the PTP revenues it received. Such Transmission Owners could have either a stated-rate or a formula rate that does not annually update and account for PTP revenues received by the Transmission Owner as an offset to the Transmission Owner s revenue requirements. See Oxy USA, Inc., v. FERC, 64 F.3d 679, 699 (995), quoting, Arkansas Louisiana Gas Co. v. Hall, 453 U.S. 57, 577, 69 L. Ed. d 856, S. Ct. 95 (98) ( The filed-rate doctrine forbids a regulated entity to charge rates for its services other than those properly filed with the appropriate federal regulatory authority. "); see also Cargill Power Markets, LLC., FERC P 6,5 at P 7, (continued...)

5 The Honorable Kimberly D. Bose October 9, 5 Page 5 To remedy these issues, this filing proposes Tariff revisions to correct the provisions related to the accounting of PTP revenues in the calculation of a Transmission Owner s Zonal ATRR for the purposes of determining monthly Demand Charges and Base Plan Zonal and Region-wide Charges for NITS. The proposed Tariff revisions clarify how SPP will properly account for all PTP revenues when the Transmission Owner s ATRR is not calculated using a formula rate that credits PTP revenues on an annual basis or is a stated-rate that is not reduced to account for PTP revenues. To the extent that a Transmission Owner s formula rate template does not include adjustments for PTP revenue to the Zonal ATRR, the Base Plan Zonal ATRR, and the Region-wide ATRR, the proposed Tariff revisions allow SPP to make such adjustments in the Settlement process accordingly. Additionally, the proposed revisions clarify the proper inclusion of PTP charges pursuant to Schedule 8 and in the accounting described above. Commission approval of the proposed Tariff revisions is warranted and justified because they result in the proper accounting for all PTP revenue distributed to the Transmission Owners. The proposed revisions are necessary to ensure that PTP revenues are properly accounted for in the Transmission Owners ATRR so that the Transmission Owners do not over-recover their revenue requirements under the Tariff. In other words, unless the state-rate or formula rate template credits PTP revenue, all PTP revenues distributed to such Transmission Owner are over and beyond the Transmission Owner s Zonal and Base Plan ATRR. Because the existing Tariff provisions do not address Non-Firm PTP revenues (Schedule 8), nor Schedule PTP revenues associated with Base Plan facilities, there is ambiguity as to how PTP revenues are calculated and distributed to Transmission Owners. Commission approval of the proposed Tariff revisions will reduce the current ambiguity existing in the Tariff and result in increased transparency in the application of the PTP revenue credits. (... continued) reh'g denied, 3 FERC P 6,33 (5) (under the filed-rate doctrine, a regulated entity must charge the rate that is on file with the Commission). The corollary to the filed-rate doctrine is the rule against retroactive ratemaking. This rule prohibits the Commission from adjusting current rates to make up for a utility s over- or under- collection in prior periods. Towns of Concord, 955 F.d 67 at 7, n. (citing Columbia Gas Transmission Corp v. FERC, 83 F.d 35, 39-4 (D.C. Cir 99).

6 The Honorable Kimberly D. Bose October 9, 5 Page 6 B. Description of Proposed Tariff Revisions. Part III- Network Integration Transmission Service, Section 34 (Rates and Charges) Section 34 of the Tariff sets forth the rates and charges that a Network Customer is required to pay for NITS as determined in accordance with Schedule 9. As relevant here, Sections 34. through 34.3 of the Tariff contain provisions regarding the Monthly Demand Charge that a Network Customer is required to pay for all Network Load served by SPP. 3 SPP proposes revisions to Sections 34. through 34.3 of the Tariff 4 to clarify that, for the purposes of calculating the Monthly Demand Charge, the Transmission Owner s Zonal ATRR 5 will be adjusted to account for both Firm PTP and Non-Firm PTP revenues collected in the prior calendar year, unless the Transmission Owner utilizes a formula rate that already offsets PTP revenues in calculating the Transmission Owner s ATRR. Specifically, SPP has revised Section 34. (Monthly Demand Charge) to provide that a Network Customer s Monthly Demand Charge will be determined by multiplying its Load Ratio Share 6 times one twelfth of the Zonal ATRR specified in Attachment H, As described in Section II.A of this transmittal letter, Section 34. governs the calculation of the Monthly Demand Charge in Zone, AEP-West. Section 34.3 governs the calculation of the Monthly Demand Charge in Zone, SPS. Both zones include the transmission facilities of multiple Transmission Owners. SPP also includes a ministerial revision to the Table of Contents of the Tariff to reflect the title change for Section 34.. The Tariff defines Zonal Annual Transmission Revenue Requirement as [t]he revenue requirements for facilities in each Zone and the Accredited Revenue Requirement(s), if any, that are allocated to the Zone in accordance with Attachment J to this Tariff as set forth in Attachment H, Table, Column (3). Tariff at Part I, Section XYZ Definitions. The Tariff defines Load Ratio Share as the: Ratio of a Transmission Customer s Network Load in a Zone to the total load in that Zone computed in accordance with Sections 34.4 and 34.5 of the Network Integration Transmission Service under Part III of this Tariff and calculated on a calendar year basis, for the prior calendar year. Customer loads used to determine the Load Ratio Share shall be adjusted for real power losses in accordance with the provisions set out in Section 8.5 of this Tariff. (continued...)

7 The Honorable Kimberly D. Bose October 9, 5 Page 7 less any amount reallocated in accordance with Section IV.A of Attachment J of the Tariff 7 and less any Schedule 7 and 8 revenues allocated to each Transmission Owner in the Zone under Attachment L for the previous calendar year. 8 In addition, Section 34.()(a) now clarifies that, [f]or each Transmission Owner utilizing a formula rate, the Transmission Provider shall not make an adjustment for Schedule 7 and 8 revenues if the Schedule 7 and 8 revenues are credited and updated on an annual basis in the Transmission Owner formula rate. 9 Conversely, to account for any PTP revenues that (i) may have been used in a determination of Transmission Owner s Zonal ATRR in a prior rate proceeding; or (ii) included as an input into the Transmission Owner s formula rate but not otherwise updated on an annual basis, Section 34.()(b) now clarifies that: For each Transmission Owner utilizing a stated rate or utilizing a formula rate without annual update of the Schedule 7 and 8 revenue credits, the Schedule 7 and 8 revenue adjustment described in this Section 34.() shall be offset by the amount of Schedule 7 and 8 revenues, if any, already credited in the calculation of the Zonal ATRR shown in Table, Section I of Attachment H. The amount of Schedule 7 and 8 revenues already credited in calculation of the Zonal ATRR shown in Table, Section I of Attachment H for such Transmission Owner is shown in Table 3, Section I of Attachment H. Furthermore, SPP has made corresponding revisions to Sections 34. (Monthly Demand Charge Zone ) and 34.3 (Monthly Demand Charge Zone ) of the Tariff. Regarding Section 34., SPP has revised the Tariff to make clear that the Network Customer shall pay a monthly Demand Charge for Network Load located within Zone and that [t]he component of such Demand Charge for American Electric Power s revenue requirement shall be calculated in accordance with Addendum of Attachment H which is consistent with the current Tariff construct in this section. Additionally, (... continued) Tariff at Part I, Section L - Definitions Section IV.A of Attachment J of the Tariff provides for the reallocation of Zonal and/or Base Plan Zonal ATRR to the Region-Wide ATRR under SPP s Balanced Portfolio construct to account for a benefit/cost deficiency in a zone. Proposed Tariff at Section 34.()-(). Proposed Tariff at Section 34.()(a). Proposed Tariff at Section 34.()(b). Proposed Tariff at Section 34..

8 The Honorable Kimberly D. Bose October 9, 5 Page 8 SPP proposes to clarify that the component of the Demand Charge for other Transmission Owners in the zone will be calculated in accordance with Section 34.. SPP has also revised Sections 34. to further provide that [a]ll components of the Demand Charge for Zone shall be adjusted as provided in Section 34. for any amount reallocated in accordance with Section IV.A of Attachment J and for any Schedule 7 and 8 revenues allocated to each Transmission Owner in the Zone under Attachment L. This added language recognizes reallocation of revenues as provided in other parts of the Tariff. SPP has made comparable revisions to Section 34.3 of the Tariff regarding the monthly Demand charge for Network Load located within Zone. 3 These revisions are just and reasonable because they clarify how SPP will account for credits for PTP revenues in determining the monthly Demand Charge if the Transmission Owner s formula rate does not already do so. In this manner, these revisions prevent a Transmission Owner from over-recovering its revenue requirements by failing to offset its Zonal ATRR by the PTP revenues it receives.. Schedule (Base Plan Zonal Charge and Region-wide Charge) With this filing, SPP also proposes to revise Schedule of the Tariff for the purpose of calculating Base Plan Zonal Charges 4 and Region-wide Charges 5 to Resident Load. 6 SPP will adjust the Base Plan Zonal ATRR and Region-wide Annual Proposed Tariff at Section 34.. See Proposed Tariff at Section In Zone, SPS component of the Monthly Demand Charge is calculated in accordance with Addendum 5 of Attachment H. Id. The Tariff defines Base Plan Zonal Charge as the Zonal component of the charge assessed by the Transmission Provider in accordance with Schedule to recover the revenue requirement of facilities classified as Base Plan Upgrades. Tariff at Part I, Section B Definitions. The Tariff defines Region-wide Charge as the Regional component of the charge assessed by the Transmission Provider in accordance with Schedule to recover the Region-wide Annual Transmission Revenue Requirement. Tariff at Part I, Section R Definitions. Resident Load includes load served by Network Customers taking Network Integration Transmission Service to serve their Network Load under the Tariff or a Transmission Owner s bundled retail load for which the Transmission Owner is not taking NITS or PTP Transmission Service and certain load being service under a Grandfathered Agreement. See Tariff at Part I, Section R Definitions (continued...)

9 The Honorable Kimberly D. Bose October 9, 5 Page 9 ATRR to account for both Base Plan Zonal and Region-wide PTP revenues collected in the prior calendar year. Specifically, SPP has added a new Section II.A to Schedule, which provides that SPP shall sum the applicable, Commission-approved annual transmission revenue requirements for upgrades eligible for cost recovery under this Schedule, as allocated in accordance with Attachment J of this Tariff. 7 Revised Section II.A further provides that a Transmission Owner s revenue requirement will be reduced by the amount of PTP revenues it receives during the previous calendar year resulting from charges under Section III of Schedule, if such revenues were not already used in calculating the Transmission Owner s revenue requirement. 8 As with SPP s proposed revisions to Section 34 of the Tariff, the proposed language in the new Section II.A. of Schedule draws a distinction between Transmission Owners that utilize a formula rate that already provides for crediting of annual PTP revenues and those that do not. For each Transmission Owner utilizing a formula rate that already provides for such updating and crediting, SPP will not make an adjustment to the Transmission Owner s revenue requirement. 9 For each Transmission Owner utilizing a stated rate or utilizing a formula rate that does not utilize Schedule PTP revenue credits in determining the Transmission Owner s revenue requirement, proposed Section II.A provides that SPP will reduce the Transmission Owner s revenue requirement by the amount of PTP revenues received by the Transmission Owner, and the reduction will be offset by the amount of PTP revenue, if any, that was already credited in the calculation of the Transmission Owner s annual revenue requirements that are included in the Base Plan Zonal ATRR and Region-wide ATRR. 3 Like the revisions discussed in Section II.B., supra, these revisions are just and reasonable because they ensure that PTP revenues received by a Transmission Owner are (... continued) (defining Resident Load as The load specified in Section 4 of the Tariff. See also id. at Section 4 (Applicability to Resident Load) Proposed Tariff at Schedule Section II.A. Proposed Tariff at Schedule Section II.A. Proposed Tariff at Schedule Section II.A.. Proposed Tariff at Schedule Section II(A)(). SPP has also included language in Section II(A)() to specify that the amount of revenue resulting from Base Plan Zonal Charges and Region-wide Charges for PTP Transmission Service that are already credited in the calculation of the Transmission Owner s ATRRs included in the Base Plan Zonal ATRR and Region-wide ATRR is shown in Table 3, Section of Attachment H. Id.

10 The Honorable Kimberly D. Bose October 9, 5 Page used to offset the Transmission Owner s revenue requirements for Base Plan Zonal and Region-wide charges to ensure Transmission Owners recover its appropriate ATRR under the Tariff Attachment H (Annual Transmission Revenue Requirement for Network Integration Transmission Service) SPP proposes to revise Attachment H of the Tariff to add a new Section I.7 and Table 3, which will set forth each Transmission Owner s PTP revenues that are accounted for in calculating the Transmission Owner s ATRR for NITS. The revisions provide that SPP will use Schedules 7, 8, and/or PTP revenues to offset the ATRRs for Transmission Owners that do not already account for such revenues under a formula rate. 3 New Section I.7 also provides that, for Transmission Owners using a formula rate that already annually updates and credits Schedules 7 and 8 revenues and/or PTP Schedule revenues, the Table 3 entries will read Not Applicable. 33 SPP has also made minor clarifying and conforming revisions to Addendum and Addendum 5 of Attachment H of the Tariff, which set forth the calculation of the Monthly Demand Charges in Zones (for AEP-West) and (for SPS), respectively. 34 Furthermore, SPP proposes to delete language in Addendum to Attachment H addressing the calculation of a Monthly Demand Charge associated with East Texas Electric Cooperative, Inc., Tex-La Electric Cooperative of Texas, Inc., and Deep East Teas Electric Cooperative, Inc. 35 SPP removes this language because it is superseded by SPP also proposes minor changes to renumber various sections of Schedule to reflect the addition of new Section II.A and to eliminate redundant and unnecessary language. See, e.g., Proposed Tariff at Schedule Sections III.A (removing Revenue Rates and Requirements File because it is defined elsewhere in the Tariff), III.C.5 (removing posted on the SPP website because it is stated elsewhere in the Tariff). SPP also proposes revisions to the definitions of Base Plan Zonal Load Ratio Share and Region-wide Load Ratio Share to reflect the renumbering of Schedule. Proposed Tariff at Part I, B Definitions and R Definitions. Proposed Tariff at Attachment H Section I.7. Schedules 7 & 8 PTP revenues will be reflected in Column 3 of Table 3, and Schedule PTP revenues will be reflected in Column 4. To the extent there are no PTP revenues the value will reflect $. Proposed Tariff at Attachment H Section I.7. Proposed Tariff at Attachment H Addendum and Addendum 5, Part. Proposed Tariff at Attachment H Addendum.

11 The Honorable Kimberly D. Bose October 9, 5 Page the revisions SPP proposes elsewhere in this filing to clarify the crediting of PTP revenues. The revisions to Attachment H are just and reasonable because they further the purposes of this filing to implement proper crediting of PTP revenues in each Transmission Owner s ATRR that is used to calculate the Monthly Demand Charge and Base Plan charges for NITS. 4. Attachment L (Treatment of Revenues) SPP proposes to revise Section II.C. of Attachment L of the Tariff (which governs PTP revenue distribution associated with Zonal revenue requirements to include language specifying that, in determining revenue distribution for PTP revenues, a Transmission Owner s owner-specific zonal annual revenue requirement is to be adjusted in accordance with the language in new Section 34.() of the Tariff. 36 In other words, this language clarifies that PTP revenues will reduce the Zonal ATRR for any amount received not already credited. The total Zonal ATRR is comprised of the individual Transmission Owner s OZRRs for multi-transmission Owner zones. SPP also proposes to revise Section III.A of Attachment L of the Tariff (which governs distribution of PTP revenues collected under Schedule ) to clarify that, when distributing revenues associated with Base Plan Zonal ATRR and with Region-wide ATRR, the revenues distributed to Transmission Owners owning Base Plan Upgrades, upgrades within approved Balanced Portfolios, or approved Interregional Projects shall be reduced to account for Schedule PTP revenue. 37 In other words, PTP revenues will be subtracted from the Base Plan, Balanced Portfolio, and Interregional ATRRs based on the calculation of PTP revenues under each individual type. 5. Attachment T (Rate Sheets for Point-to-Point Transmission Service) Attachment T of the Tariff contains the rate sheets for firm and non-firm PTP for each SPP pricing zone (Schedules 7 and 8), based on the ATRR of the Transmission Owners in the zone. SPP proposes to revise the rate sheets for each pricing zone to include language addressing PTP revenue crediting for PTP rates. The new language clarifies that, for each of the Transmission Owners in the zone, rates for PTP under Attachment T will reflect any adjustments for Schedule 7 and 8 revenues implemented in Proposed Tariff at, Attachment L Sections II.C()-(3). The owner-specific zonal annual revenue requirement is defined by the acronym OZRR in Attachment L Section B.. Proposed Tariff at Attachment L Section III(A).

12 The Honorable Kimberly D. Bose October 9, 5 Page accordance with Section 34.() of the Tariff. 38 The new language also clarifies that [t]he rates, including any applicable Schedule 7 and 8 revenue adjustment, shall be set forth in the [Revenue Requirements and Rates] File, which is posted on the SPP website. 39 [Remainder of page intentionally left blank] Proposed Tariff at Attachment T. SPP also proposes a revision in the Attachment T rate sheet for Zone, the SPS Zone, to remove references to Tri County Formula Rate and Addendum 7 of Attachment H that SPP inadvertently did not remove from the Tariff as part of its compliance filing in Docket No. ER Id.; see also Compliance Filing of Southwest Power Pool, Inc., Docket No. ER (Oct. 3, 4). Proposed Tariff at Attachment T. The Revenue Requirements and Rates File is defined as: A file posted on the SPP website as a reference to: (i) Annual Transmission Revenue Requirements (ATRRs) for Network Integration Transmission Service, as referenced in Attachment H to this Tariff; (ii) Base Plan ATRR allocation; (iii) allocation factors for Base Plan funded projects; (iv) notes on the calculation of Base Plan ATRR amounts on a Region-wide and Zonal basis; (v) ATRR reallocation for Balanced Portfolio projects; (vi) the calculation of Base Plan Point-To-Point Transmission Service rates on a Regionwide and Zonal basis in accordance with Schedule ; and (vii) the rates for Point-To-Point Transmission Service as referenced in Attachment T in accordance with Schedules 7 and 8. Tariff at Part I, Section R Definitions.

13 The Honorable Kimberly D. Bose October 9, 5 Page 3 III. EFFECTIVE DATE AND APPLICABILITY OF TARIFF REVISIONS SPP respectfully requests that the Tariff revisions proposed in this filing be made effective on January, 6, which is not less than sixty days, or more than days prior to, the submission of this filing as required by the Commission. 4 This effective date will allow SPP to implement the changes on the first day of the monthly billing cycle that commences sixty days after filing. 4 IV. ADDITIONAL INFORMATION A. Information Required by the Commission s Regulations. Documents submitted with this filing: In addition to this transmittal letter, SPP submits clean and redlined versions of the proposed Tariff revisions in electronic format.. Effective date: SPP requests that the Commission accept the proposed revisions to the Tariff effective January, 6, as discussed above. 3. Service: SPP has electronically served a copy of this filing on all its Members, Market Participants and Transmission Customers. A complete copy of this filing will be posted on the SPP web site, and is also being served on all affected state commissions. 4. Requisite agreements: There are none. 4 4 See 8 C.F.R at (a) (). An effective date of January, 6 will allow SPP to properly account for all 5 PTP revenues consistent with Section 34. of the Tariff, which provides that the Network Customers monthly Demand Charge shall be reduced by any Schedule 7 and 8 revenues allocated to each Transmission Provider in the zone pursuant to Attachment L for the previous calendar year (emphasis added)

14 The Honorable Kimberly D. Bose October 9, 5 Page 4 5. Estimate of transactions and revenues: Not applicable. 6. Basis of rates: The basis for the proposed revisions is explained above. 7. Comparison to rates for similar services: Not applicable. 8. Specifically assignable facilities installed or modified: There are none. B. Communications Correspondence and communications with respect to this filing should be sent to, and SPP requests that the Commission include on the official service list for this proceeding, the following individuals: Nicole Wagner Manager Regulatory Policy Southwest Power Pool, Inc. Worthen Drive Little Rock, AR 73 Telephone: (5) Fax: (5) 48- jwagner@spp.org Matthew Harward Attorney Southwest Power Pool, Inc. Worthen Drive Little Rock, AR 73 Telephone: (5) Fax: (5) 48- mharward@spp.org [Remainder of page intentionally left blank]

15 The Honorable Kimberly D. Bose October 9, 5 Page 5 V. CONCLUSION For all of the foregoing reasons, SPP respectfully requests that the Commission accept the Tariff revisions submitted in this filing as just and reasonable, effective January, 6. Respectfully submitted, /s/ Matthew Harward Matthew Harward Southwest Power Pool, Inc. Worthen Drive Little Rock, AR 73 Telephone: (5) mharward@spp.org Attorney for Southwest Power Pool, Inc.

16 Southwest Power Pool, Inc. Open Access Transmission Tariff Sixth Revised Volume No. Superseding Fifth Revised Volume No.

17 I. COMMON SERVICE PROVISIONS Definitions A - Definitions B - Definitions C - Definitions D - Definitions E - Definitions F - Definitions G - Definitions H - Definitions I - Definitions J - Definitions K - Definitions L - Definitions M - Definitions N - Definitions O - Definitions P - Definitions Q - Definitions R - Definitions S - Definitions T - Definitions U - Definitions V - Definitions W - Definitions XYZ - Definitions Initial Allocation and Renewal Procedures. Initial Allocation of Available Transfer Capability. Reservation Priority For Existing Firm Service Customers 3 Ancillary Services 4 Open Access Same-Time Information System (OASIS) 5 Local Furnishing Bonds 5. Transmission Owners That Own Facilities Financed by Local Furnishing Bonds or that are Tax Exempt Entities 5. Alternative Procedures for Requesting Transmission Service 6 Reciprocity 7 Billing and Payment 7. Billing Procedure 7. Interest on Unpaid Balances 7.3 Financial Security Held By SPP 7.4 Customer Default 8 Accounting for Use of the Tariff 8. Study Costs and Revenues 9 Regulatory Filings Force Majeure and Indemnification. Force Majeure

18 II.. Liability.3 Indemnification.4 Further Limitation of Liability.5 Transmission Provider Recovery Creditworthiness Dispute Resolution Procedures. Internal Dispute Resolution Procedures. External Arbitration Procedures.3 Arbitration Decisions.4 Costs.5 Rights Under The Federal Power Act POINT-TO-POINT TRANSMISSION SERVICE 3 Nature of Firm Point-To-Point Transmission Service 3. Term 3. Reservation Priority 3.3 Use of Firm Transmission Service by the Transmission Owners 3.4 Service Agreements 3.5 Transmission Customer Obligations for Facility Additions or Redispatch Costs 3.6 Curtailment of Firm Transmission Service 3.7 Classification of Firm Transmission Service 3.8 Scheduling of Firm Point-To-Point Transmission Service 4 Nature of Non-Firm Point-To-Point Transmission Service 4. Term 4. Reservation Priority 4.3 Use of Non-Firm Point-To-Point Transmission Service by the Transmission Owner(s) 4.4 Service Agreements 4.5 Classification of Non-Firm Point-To-Point Transmission Service 4.6 Scheduling of Non-Firm Point-To-Point Transmission Service 4.7 Curtailment or Interruption of Service 5 Service Availability 5. General Conditions 5. Determination of Available Transfer Capability 5.3 Initiating Service in the Absence of an Executed Service Agreement 5.4 Obligation to Provide Transmission Service that Requires Expansion or Modification of the Transmission System 5.5 Deferral of Service 5.6 Other Transmission Service Schedules 5.7 Real Power Losses 6 Transmission Customer Responsibilities 6. Conditions Required of Transmission Customers 6. Transmission Customer Responsibility for Third-Party Arrangements 7 Procedures for Arranging Firm Point-To-Point Transmission Service 7. Application 7.a Time Requirements

19 7. Completed Application 7.3 Credit Arrangements 7.4 Notice of Deficient Application 7.5 Response to a Completed Application 7.6 Execution of Service Agreement 7.7 Extensions for Commencement of Service 7.8 Designated Resources Using Long-Term Point-To-Point Transmission Service 7.9 Interconnection of Delivery Points 8 Procedures for Arranging Non-Firm Point-To-Point Transmission Service 8. Application 8. Completed Application 8.3 Timing of Requests and Responses Regarding Reservation of Non-Firm Point-To-Point Transmission Service 8.4 Determination of Available Transfer Capability 9 Additional Study Procedures For Firm Point-To-Point Transmission Service Requests 9. Notice of Need for System Impact Study 9. System Impact Study Agreement and Cost Reimbursement 9.3 System Impact Study Procedures 9.4 Facilities Study Procedures 9.5 Facilities Study Modifications 9.6 Due Diligence in Completing New Facilities 9.7 Partial Interim Service 9.8 Expedited Procedures for New Facilities 9.9 Reporting Failure to Meet Study Deadlines Procedures if The Transmission Provider is Unable to Complete New Transmission Facilities for Firm Point-To-Point Transmission Service. Delays in Construction of New Facilities. Alternatives to the Original Facility Additions.3 Refund Obligation for Unfinished Facility Additions Provisions Relating to Transmission Construction and Services on the Systems of Other Utilities. Responsibility for Third-Party System Additions. Coordination of Third-Party System Additions Changes in Service Specifications. Modifications On a Non-Firm Basis. Additional Charge To Prevent Abuse.3 Modification On a Firm Basis 3 Sale or Assignment of Transmission Service 3. Procedures for Assignment or Transfer of Service 3. Limitations on Assignment or Transfer of Service 3.3 Information on Assignment or Transfer of Service 4 Metering and Power Factor Correction at Receipt and Delivery Points(s) 4. Transmission Customer Obligations 4. Transmission Provider Access to Metering Data

20 III. 4.3 Power Factor 5 Compensation for Transmission Service 6 Stranded Cost Recovery 7 Compensation for New Facilities and Redispatch Costs NETWORK INTEGRATION TRANSMISSION SERVICE 8 Nature of Network Integration Transmission Service 8. Scope of Service 8. Transmission Provider and Transmission Owners Responsibilities 8.3 Network Integration Transmission Service 8.4 Secondary Service 8.5 Real Power Losses 8.6 Restrictions on Use of Service 9 Initiating Service 9. Condition Precedent for Receiving Service 9. Application Procedures 9.3 Technical Arrangements to be Completed Prior to Commencement of Service 9.4 Network Customer Facilities 9.5 Filing of Service Agreement 3 Network Resources 3. Designation of Network Resources 3. Designation of New Network Resources 3.3 Termination of Network Resources 3.4 Operation of Network Resources 3.5 Network Customer Redispatch Obligation 3.6 Transmission Arrangements for Network Resources Not Physically Interconnected With The Transmission Provider 3.7 Limitation on Designation of Network Resources 3.8 Use of Interface Capacity by the Network Customer 3.9 Network Customer Owned Transmission Facilities 3 Designation of Network Load 3. Network Load 3. New Network Loads Connected With the Transmission Provider 3.3 Network Load Not Physically Interconnected with the Transmission Provider 3.4 New Interconnection Points 3.5 Changes in Service Requests 3.6 Annual Load and Resource Information Updates 3 Additional Study Procedures For Network Integration Transmission Service Requests 3. Notice of Need for System Impact Study 3. System Impact Study Agreement and Cost Reimbursement 3.3 System Impact Study Procedures 3.4 Facilities Study Procedures 3.5 Penalties for Failure to Meet Study Deadlines 3.6 Facilities Study Modifications

21 IV. 3.7 Due Diligence in Completing New Facilities 3.8 Partial Interim Service 3.9 Expedited Procedures for New Facilities 3. Delays in Construction of New Facilities 3. Alternatives to the Original Facility Additions 33 Load Shedding and Curtailments 33. Procedures 33. Transmission Constraints 33.3 Cost Responsibility for Relieving Transmission Constraints 33.4 Curtailments of Scheduled Deliveries 33.5 Allocation of Curtailments 33.6 Load Shedding 33.7 System Reliability 34 Rates and Charges 34. Monthly Demand Charge 34. Monthly Demand Charge Zone 34.3 Monthly Demand Change Zone 34.4 Determination of Network Customer's Monthly Network Load 34.5 Determination of Transmission Provider's Monthly Zone Transmission Load 34.6 Redispatch Charge 34.7 Stranded Cost Recovery 34.8 SPP Costs 34.9 Monthly Demand Charge Zone 35 Operating Arrangements 35. Operation under the Network Operating Agreement 35. Network Operating Agreement 36 Scheduling SPECIAL RULES ON USE OF TARIFF 37 During Transition Period 37. Service Not Required for Bundled Customers or Customers Under Retail Access Programs 37. Availability of Network Integration Transmission Service 37.3 Unbundled Wholesale 37.4 Grandfathered Transactions 38 After Transition Period 38. Applicability to Retail Load Having Choice 38. Applicability to All Retail Load Not Having Choice 38.3 Grandfathered Agreements 39 Applicability of Non-Rate Terms and Conditions 39. Subject to State Laws and Regulations and Public Power Rate Schedules 39. Bundled Retail and Grandfathered Load 39.3 Participation by Western Area Power Administration Subject to Federal Laws and Regulations 39.4 Applicability to Rural Electric Cooperatives

22 V. RECOVERY OF COSTS FOR BASE PLAN UPGRADES AND APPROVED BALANCED PORTFOLIOS 4 Base Plan Zonal Charge and Region-wide Charge 4 Applicability to Resident Load 4 Applicability to Point-To-Point Transmission Service SCHEDULE Scheduling, System Control and Dispatch Service SCHEDULE -A Tariff Administration Service SCHEDULE Reactive Supply and Voltage Control from Generation or Other Sources Service SCHEDULE 3 Regulation and Frequency Response Service SCHEDULE 4 Energy Imbalance Service SCHEDULE 5 Operating Reserve - Spinning Reserve Service SCHEDULE 6 Operating Reserve - Supplemental Reserve Service SCHEDULE 7 Long-Term Firm and Short-Term Firm Point-To-Point Transmission Service SCHEDULE 8 Non-Firm Point-To-Point Transmission Service SCHEDULE 9 Network Integration Transmission Service SCHEDULE Wholesale Distribution Service SCHEDULE Base Plan Zonal Charge and Region-wide Charge SCHEDULE FERC Assessment Charge ATTACHMENT A Form Of Service Agreement For Firm Point-To-Point Transmission Service ATTACHMENT A- Form Of Service Agreement For The Resale, Reassignment Or Transfer Of Point-To- Point Transmission Service ATTACHMENT B Form Of Service Agreement For Non-Firm Point-To-Point Transmission Service ATTACHMENT C Methodology To Assess Available Transfer Capability ATTACHMENT D Methodology for Completing a System Impact Study ATTACHMENT E Index Of Point-To-Point Transmission Service Customers ATTACHMENT F Service Agreement For Network Integration Transmission Service

23 ATTACHMENT G Network Operating Agreement ATTACHMENT H Annual Transmission Revenue Requirement for Network Integration Transmission Service ATTACHMENT I Index Of Network Integration Transmission Service Customers ATTACHMENT J Recovery Of Costs Associated With New Facilities ATTACHMENT K Redispatch Procedures and Redispatch Costs ATTACHMENT L Treatment Of Revenues ATTACHMENT M Loss Compensation Procedure ATTACHMENT N [Reserved for Future Use] ATTACHMENT O Transmission Planning Process ATTACHMENT P Transmission Service Timing Requirements ATTACHMENT Q Form of Application For Short-Term Firm and Non-Firm Transmission Service ATTACHMENT R North American Electric Reliability Council Transmission Loading Relief ( TLR ) Procedure ATTACHMENT R- North American Energy Standards Board Business Practices ATTACHMENT S Procedure for Calculation of MW-Mile Impacts for Use in Revenue Requirements, Revenue Allocation and Determination of Losses ATTACHMENT T Rate Sheets For Point-To-Point Transmission Service ATTACHMENT U Rate Schedule For Compensation For Rescheduled Maintenance Costs ATTACHMENT V Coordinated Generation Interconnection Procedures ATTACHMENT W Index of Grandfathered Agreements ATTACHMENT X Credit Policy ATTACHMENT Y Transmission Owner Designation Process ATTACHMENT Z Aggregate Transmission Service Study Procedures and Cost Allocation and Recovery for Service Upgrades

24 ATTACHMENT Z Compensation for Upgrade Sponsors ATTACHMENT AA Reserved for Future Use ATTACHMENT AB Reserved For Future Use ATTACHMENT AC Reservation Processing Method For Short Term Firm Transmission Service ATTACHMENT AD Southwestern Power Administration Agreement Between United States Of America and Southwest Power Pool, Inc. ATTACHMENT AE Integrated Marketplace ATTACHMENT AF Market Power Mitigation Plan ATTACHMENT AG Market Monitoring Plan ATTACHMENT AH Market Participant Service Agreement ATTACHMENT AI Transmission Definition ATTACHMENT AJ Reserved for Future Use ATTACHMENT AK Treatment of Reserve Sharing Charges and Revenues ATTACHMENT AL Form of Non-Disclosure Agreement for Authorized Requestors ATTACHMENT AM Meter Agent Services Agreement ATTACHMENT AN Balancing Authorities Agreement ATTACHMENT AO Agreement Establishing External Generation Non-Physical Electrical Interconnection Point ATTACHMENT AP Allocation of Cost Associated with Reliability Penalty Assessments ATTACHMENT AQ Delivery Point Addition Process ATTACHMENT AR Screening Study

25 B - Definitions Balanced Portfolio: A set of transmission upgrades that provides economic benefits across the SPP Region that meet the requirements in Sections IV.3 and IV.4 of Attachment O. Balanced Portfolio Region-wide Annual Transmission Revenue Requirement: The annual transmission revenue requirement for an approved Balanced Portfolio determined in accordance with Attachment J to this Tariff. Balancing Authority: The responsible entity that integrates resource plans ahead of time, maintains load-interchange-generation balance within a Balancing Authority Area, and supports Interconnection frequency in real time in order to: () Match, at all times, the power output of the generators within the electric power system(s) and capacity and energy purchased from entities outside the electric power system(s), with the load within the electric power system(s); () Maintain scheduled interchange with other Balancing Authority Areas, within the limits of Good Utility Practice; (3) Maintain the frequency of the electric power system(s) within reasonable limits in accordance with Good Utility Practice; and (4) Provide for sufficient generating capacity to maintain operating reserves in accordance with Good Utility Practice. Balancing Authority Area: The collection of generation, transmission, and loads within the metered boundaries of the Balancing Authority. The Balancing Authority maintains load-resource balance within this area. Base Plan Region-wide Annual Transmission Revenue Requirement: The sum of the annual transmission revenue requirement for each Base Plan Upgrade and of the Accredited Revenue Requirement(s), if any, that are allocated to the SPP Region in accordance with Attachment J to this Tariff.

26 Base Plan Upgrades: Those upgrades included in and constructed pursuant to the SPP Transmission Expansion Plan in order to ensure the reliability of the Transmission System. Base Plan Upgrades shall also include: (i) those Service Upgrades required for new or changed Designated Resources to the extent allowed for in Attachment J to this Tariff, (ii) ITP Upgrades that are approved for construction by the SPP Board of Directors, and (iii) high priority upgrades, excluding Balanced Portfolios, that are approved for construction by the SPP Board of Directors. For Zones through 5, all such upgrades shall specifically exclude planned Transmission System facilities identified in the SPP Transmission Expansion Plan that are: (i) placed in service during the 5 calendar year or (ii) required to be in service to meet the SPP Criteria and the NERC Reliability Standards for the summer of 5. For Zones 6, 7, and 8, all such upgrades shall specifically exclude planned Transmission System facilities in those zones identified in the SPP Transmission Expansion Plan Report (9 8) that are required to be in service to meet the SPP Criteria and the NERC Reliability Standards for the summer of 8 or which are in operation prior to January, 9, except for those upgrades that are in service prior to January, 9 and are components of Phase of the NPPD 345kV Norfolk to Lincoln (ETR) project or OPPD Sub 55/3455 Transformer project. Network Upgrades that are components of Phase of the NPPD 345kV Norfolk to Lincoln (ETR) project or OPPD Sub 55/3455 Transformer project that are in service prior to January, 9 will be Base Plan Upgrades, however, the Zonal component of the costs shall be % allocated to the respective host zone. The Base Plan Upgrades in Zones through 8 identified by the Transmission Provider with a need date prior to October, 5 shall not be allocable to Zone 9. The upgrades in Zone 9 identified by the Transmission Provider with a need date prior to October, 5, shall not constitute Base Plan Upgrades. The facilities identified in Schedule to Attachment J are expressly deemed to be Base Plan Upgrades pursuant to Attachment J, Section III.A.. Base Plan Zonal Annual Transmission Revenue Requirement: For each Zone, the sum of the annual transmission revenue requirement for each Base Plan Upgrade and of the Accredited Revenue Requirement(s), if any, that are allocated to the Zone in accordance with Attachments J and S to this Tariff.

27 Base Plan Zonal Charge: Zonal component of the charge assessed by the Transmission Provider in accordance with Schedule to recover the revenue requirement of facilities classified as Base Plan Upgrades. Base Plan Zonal Load Ratio Share: Ratio of a Network Customer's or Transmission Owner s Resident Load in a Zone to the total load in that Zone computed in accordance with Section II.B to Schedule of this Tariff and calculated on a calendar year basis, for the prior calendar year. Customer loads used to determine the Base Plan Zonal Load Ratio Share shall be adjusted for real power losses in accordance with the provisions set out in Section 8.5 of this Tariff. Base Plan Zonal Rate: Zonal component of the rate (per kw of Reserved Capacity for Point-To-Point Transmission Service) assessed by the Transmission Provider in accordance with Schedule to recover the revenue requirement of facilities classified as Base Plan Upgrades. Business Day: A day on which the Federal Reserve System is open for business.

September 30, 2016 VIA ELECTRONIC FILING

September 30, 2016 VIA ELECTRONIC FILING September 30, 2016 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20246 Re: Southwest Power Pool, Inc., Docket

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Southwest Power Pool, Inc. ) Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Southwest Power Pool, Inc. ) Docket No. ER UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southwest Power Pool, Inc. ) Docket No. ER16- -000 PETITION OF SOUTHWEST POWER POOL, INC. FOR TARIFF WAIVER Pursuant to Rule 207(a)(5)

More information

July 15, 2015 VIA ELECTRONIC FILING

July 15, 2015 VIA ELECTRONIC FILING July 15, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20246 Re: Southwest Power Pool, Inc., Docket No.

More information

April 28, Southwest Power Pool, Inc., Docket No. ER11- Submission of Formula Rate Template

April 28, Southwest Power Pool, Inc., Docket No. ER11- Submission of Formula Rate Template Secretary Federal Energy Regulatory Commission 888 First Street NE Washington, DC 20426 Re: Southwest Power Pool, Inc., Docket No. ER11- Submission of Formula Rate Template Honorable Secretary Bose: Pursuant

More information

July 21, Southwest Power Pool, Inc., Docket No. ER Submission of Response to Request for Additional Information

July 21, Southwest Power Pool, Inc., Docket No. ER Submission of Response to Request for Additional Information July 21, 2016 VIA ELECTRONIC FILING Penny Murrell Director, Division of Electric Power Regulation-Central Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest

More information

UNITED STATES OF AMERICA BERFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BERFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BERFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southwestern Public Service Company, ) v. ) Docket No. EL13-15-000 Southwest Power Pool, Inc. ) ) Southwestern Public Service Company,

More information

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP New Member Cost Allocation Review Process Prepared by: COST ALLOCATION WORKING GROUP TABLE OF CONTENTS 1. HISTORY AND BACKGROUND... 1 2. PURPOSE / GOAL STATEMENT... 3 3. OVERVIEW OF PROCESS... 3 4. NEW

More information

April 24, 2015 VIA ELECTRONIC FILING

April 24, 2015 VIA ELECTRONIC FILING April 24, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket No.

More information

February 23, 2015 VIA ELECTRONIC FILING

February 23, 2015 VIA ELECTRONIC FILING February 23, 2015 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket

More information

April 29, 2016 VIA ELECTRONIC FILING

April 29, 2016 VIA ELECTRONIC FILING April 29, 2016 VIA ELECTRONIC FILING The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Southwest Power Pool, Inc., Docket No.

More information

May 8, Response to Show Cause Order, Filing of Revised Tariff Sheet And Request for Any Necessary Waivers. The Dayton Power and Light Company

May 8, Response to Show Cause Order, Filing of Revised Tariff Sheet And Request for Any Necessary Waivers. The Dayton Power and Light Company The Dayton Power and Light Company 1065 Woodman Drive, Dayton Ohio 45458 May 8, 2018 Via etariff Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER REJECTING TARIFF REVISIONS. (Issued November 30, 2015)

153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER REJECTING TARIFF REVISIONS. (Issued November 30, 2015) 153 FERC 61,249 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable. Southwest Power Pool,

More information

March 7, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

March 7, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 March 7, 2012 Re: California Independent

More information

Relationship-Based Member-Driven Independence Through Diversity Evolutionary vs. Revolutionary Reliability & Economics Inseparable

Relationship-Based Member-Driven Independence Through Diversity Evolutionary vs. Revolutionary Reliability & Economics Inseparable Southwest Power Pool, Inc. CORPORATE GOVERNANCE COMMITTEE MEETING December 7, 2011 Teleconference AGENDA 1:00 p.m. 3:00 p.m. CST 1. Call to Order and Administrative Items... Nick Brown 2. Vacancies...

More information

May 28, Southwest Power Pool, Inc., Docket No. ER15- Submission of Notice of Cancellation of Interconnection Agreement

May 28, Southwest Power Pool, Inc., Docket No. ER15- Submission of Notice of Cancellation of Interconnection Agreement May 28, 2015 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street NE Washington, DC 20426 RE: Southwest Power Pool, Inc., Docket No. ER15- Submission of Notice

More information

ALSTON&BIRD LLP. The Atlantic Building 950 F Street, NW Washington, DC Fax:

ALSTON&BIRD LLP. The Atlantic Building 950 F Street, NW Washington, DC Fax: ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404 202-756-3300 Fax: 202-756-3333 Bradley R. Miliauskas Direct Dial: 202-756-3405 Email: bradley.miliauskas@alston.com December

More information

February 29, Southwest Power Pool, Inc., Docket No. ER16- Submission of Meter Agent Services Agreement

February 29, Southwest Power Pool, Inc., Docket No. ER16- Submission of Meter Agent Services Agreement February 29, 2016 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street NE Washington, DC 20426 RE: Southwest Power Pool, Inc., Docket No. ER16- Submission of Meter

More information

SPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017

SPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017 1 SPP New Member Communication and Integration Process Mountain West Transmission Group Background Information October 2017 Contents Introduction... 2 1. Westside Tariff Design... 2 2. Operational Provisions...

More information

N. Am. Elec. Reliability Corp., 119 FERC 61,060, order on reh g, 120 FERC 61,260 (2007).

N. Am. Elec. Reliability Corp., 119 FERC 61,060, order on reh g, 120 FERC 61,260 (2007). The Honorable Kimberly D. Bose Secretary November 7, 2008 Page 2 Arkansas. SPP currently has 50 Members, serving more than 4 million customers in a 255,000 square-mile area covering all or part of eight

More information

SOUTHERN CALIFORNIA EDISON COMPANY TRANSMISSION OWNER TARIFF

SOUTHERN CALIFORNIA EDISON COMPANY TRANSMISSION OWNER TARIFF Southern California Edison Company FERC Electric Tariff, Second Revised Volume No. 6 Title Page SOUTHERN CALIFORNIA EDISON COMPANY TRANSMISSION OWNER TARIFF Issued on: December 23, 2002 Effective: January

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY WILLIAM A. GRANT. on behalf of

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY WILLIAM A. GRANT. on behalf of BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S APPLICATION FOR REVISION OF ITS RETAIL RATES UNDER ADVICE NOTICE NO., SOUTHWESTERN PUBLIC SERVICE

More information

December 23, By etariff Filing Hon. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426

December 23, By etariff Filing Hon. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 December 23, 2014 By etariff Filing Hon. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: Nevada Power Company and Sierra Pacific Power Company,

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY RUTH M. SAKYA. on behalf of.

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION ) ) ) ) ) ) ) ) ) ) ) DIRECT TESTIMONY RUTH M. SAKYA. on behalf of. BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN PUBLIC SERVICE COMPANY S INTERIM REPORT ON ITS PARTICIPATION IN THE SOUTHWEST POWER POOL REGIONAL TRANSMISSION ORGANIZATION,

More information

130 FERC 61,033 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. [Docket No. RM ]

130 FERC 61,033 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. [Docket No. RM ] 130 FERC 61,033 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION [Docket No. RM10-9-000] Transmission Loading Relief Reliability Standard and Curtailment Priorities (Issued January 21, 2010)

More information

RR16 - Page 1 of

RR16 - Page 1 of DOCKET NO. APPLICATION OF SOUTHWESTERN PUBLIC SERVICE COMPANY FOR AUTHORITY TO CHANGE RATES PUBLIC UTILITY COMMISSION OF TEXAS DIRECT TESTIMONY of ARTHUR P. FREITAS on behalf of SOUTHWESTERN PUBLIC SERVICE

More information

December 7, Compliance with Order No. 844 Response to Deficiency Letter

December 7, Compliance with Order No. 844 Response to Deficiency Letter California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California Independent System

More information

PJM Interconnection, L.L.C. ( PJM ), under Section 205 of the Federal Power Act

PJM Interconnection, L.L.C. ( PJM ), under Section 205 of the Federal Power Act PJM Interconnection, L.L.C. 2750 Monroe Boulevard Audubon, PA 19403 March 30, 2018 Elizabeth P. Trinkle Counsel T: (610) 666-4707 F: (610) 666-8211 Elizabeth.Trinkle@pjm.com The Honorable Kimberly D. Bose

More information

December 10, Southwest Power Pool, Inc., Docket No. ER15- Submission of Meter Agent Services Agreement

December 10, Southwest Power Pool, Inc., Docket No. ER15- Submission of Meter Agent Services Agreement The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street NE Washington, DC 20426 December 10, 2014 RE: Southwest Power Pool, Inc., Docket No. ER15- Submission of Meter

More information

American Electric Power Service Corporation Docket No. ER10- -

American Electric Power Service Corporation Docket No. ER10- - American Electric Power 801 Pennsylvania Avenue N.W. Suite 320 Washington, DC 20004 AEP.com May 3, 2010 Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E.

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION New York Independent System Operator, Inc. ) PJM Interconnection, L.L.C. ) Docket Nos. ER17-905-002 ) MOTION FOR LEAVE TO ANSWER

More information

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION IN THE MATTER OF SOUTHWESTERN ) PUBLIC SERVICE COMPANY S 2018 ) INTEGRATED RESOURCE PLAN FOR ) NEW MEXICO. ) CASE NO. 18-00215-UT ) SOUTHWESTERN PUBLIC

More information

161 FERC 61,004 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

161 FERC 61,004 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 161 FERC 61,004 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Neil Chatterjee, Chairman; Cheryl A. LaFleur, and Robert F. Powelson. Midcontinent Independent System

More information

May 18, Black Hills Power, Inc. Docket Nos. ER and EL Compliance Filing Revising Attachment H Formula Rate Protocols

May 18, Black Hills Power, Inc. Docket Nos. ER and EL Compliance Filing Revising Attachment H Formula Rate Protocols Texas New York Washington, DC Connecticut Seattle Dubai London Blake R. Urban Attorney 202.828.5868 Office 800.404.3970 Fax Blake.Urban@bgllp.com Bracewell & Giuliani LLP 2000 K Street NW Suite 500 Washington,

More information

151 FERC 61,045 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

151 FERC 61,045 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 151 FERC 61,045 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Philip D. Moeller, Cheryl A. LaFleur, Tony Clark, and Colette D. Honorable.

More information

BY ELECTRONIC FILING Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

BY ELECTRONIC FILING Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. ANDREW W. TUNNELL t: (205) 226-3439 f: (205) 488-5858 e: atunnell@balch.com BY ELECTRONIC FILING Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington,

More information

PACIFIC GAS AND ELECTRIC COMPANY. TRANSMISSION OWNER TARIFF Sixth Revised Volume 5

PACIFIC GAS AND ELECTRIC COMPANY. TRANSMISSION OWNER TARIFF Sixth Revised Volume 5 TRANSMISSION OWNER TARIFF Sixth Revised Volume 5 First Revised Sheet No. 1 Superseding Original Sheet No. 1 TABLE OF CONTENTS 1. PREAMBLE.... 4 1.1 Transmission Access for Self-Sufficient Participating

More information

Mountain West Transmission Group (MWTG) Introduction and Process

Mountain West Transmission Group (MWTG) Introduction and Process Mountain West Transmission Group (MWTG) Introduction and Process October 13 Denver, CO October 16 Little Rock, AR 2 Agenda Overview of SPP Overview of the MWTG Members SPP Process New Member Integration

More information

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS TRANSMISSION OWNER ZONAL PLACEMENT PROCESS Published July 2017 CONTENTS Section 1: Introduction, Scope & Steps... 1 Subsection A: Introduction To Zonal Placement... 1 Subsection B: Scope... 1 Subsection

More information

9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the

9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the First Revised Sheet No. 121 ORIGINAL VOLUME NO. I Replacing Original Sheet No. 121 9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. 9.1 Nature of Relationship. Each Participating TO shall enter into

More information

November 29, RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO2019)

November 29, RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO2019) Jeffrey L. Nelson Director FERC Rates & Market Integration Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Southern California Edison Company s Formula Transmission Rate

More information

October 8, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

October 8, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. October 8, 2012 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Duke Energy Carolinas, LLC; Carolina Power & Light Company;

More information

144 FERC 61,198 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER GRANTING IN PART AND DENYING IN PART REQUESTS FOR CLARIFICATION

144 FERC 61,198 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER GRANTING IN PART AND DENYING IN PART REQUESTS FOR CLARIFICATION 144 FERC 61,198 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Philip D. Moeller, John R. Norris, Cheryl A. LaFleur, and Tony Clark. Puget

More information

Regulatory Status Report

Regulatory Status Report FERC or State Jurisdiction: FERC 10-1227 SPP Filing of FERC Form 1 and 3-Q AD11-9 On November 25, 2014, SPP submitted its FERC Form 3-Q, Quarterly Financial Report, for the third quarter of 2014. Inquiry

More information

January 3, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

January 3, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. January 3, 2018 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Columbia Gas Transmission, LLC 700 Louisiana Street, Suite 700 Houston,

More information

Southwest Power Pool, Inc. Policy Recommendation for the SPP Board of Directors and Members Committee. March 6, 2018 Mountain West Transmission Group

Southwest Power Pool, Inc. Policy Recommendation for the SPP Board of Directors and Members Committee. March 6, 2018 Mountain West Transmission Group Southwest Power Pool, Inc. Policy for the SPP Board of Directors and Members Committee Policy Area #1 DC Ties March 6, 2018 Mountain West Transmission Group SPP and MWTG anticipate that incorporating the

More information

September 2, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

September 2, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 California Independent System Operator Corporation September 2, 2014 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426 Re: California

More information

June 25, Southwest Power Pool, Inc., Docket No. ER13- Submission of Meter Agent Services Agreement

June 25, Southwest Power Pool, Inc., Docket No. ER13- Submission of Meter Agent Services Agreement The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street NE Washington, DC 20426 June 25, 2013 RE: Southwest Power Pool, Inc., Docket No. ER13- Submission of Meter

More information

PacifiCorp Transmission Rate Case

PacifiCorp Transmission Rate Case PacifiCorp Transmission Rate Case Customer & Stakeholder Meetings Portland, March 10, 2011 & Salt Lake City, March 16, 2011 2000 PACIFICORP PAGE 2 Agenda Welcome and Introduction Purpose of Meeting and

More information

Southwestern Public Service Company Attachment O SPS Transmission Formula 2017 Projection Material Accounting Changes since January 1, 2016

Southwestern Public Service Company Attachment O SPS Transmission Formula 2017 Projection Material Accounting Changes since January 1, 2016 1 The Company has listed below any material changes that have taken effect since January 1, 2016. For additional information, please refer to the Southwestern Public Service Company FERC Form 1 for Q4

More information

Regional Cost Allocation Review (RCAR II) July 11, 2016 SPP Regional Cost Allocation Review Report for RCAR II

Regional Cost Allocation Review (RCAR II) July 11, 2016 SPP Regional Cost Allocation Review Report for RCAR II Regional Cost Allocation Review (RCAR II) July 11, 2016 SPP Regional Cost Allocation Review Report for RCAR II 1 Table of Contents EXECUTIVE SUMMARY...5 BACKGROUND...7 SECTION 1: OVERVIEW OF THE RARTF

More information

165 FERC 61,140 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ACCEPTING COMPLIANCE FILING SUBJECT TO CONDITION

165 FERC 61,140 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION ORDER ACCEPTING COMPLIANCE FILING SUBJECT TO CONDITION 165 FERC 61,140 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Neil Chatterjee, Chairman; Cheryl A. LaFleur and Richard Glick. California Independent System Operator

More information

158 FERC 61,044 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

158 FERC 61,044 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 158 FERC 61,044 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, and Colette D. Honorable. Natural Gas Pipeline Company of

More information

Statement of Chairman Cheryl A. LaFleur on Forward Capacity Auction 8 Results Proceeding

Statement of Chairman Cheryl A. LaFleur on Forward Capacity Auction 8 Results Proceeding September 16, 2014 Chairman Cheryl A. LaFleur Docket No. ER14-1409-000 Statement of Chairman Cheryl A. LaFleur on Forward Capacity Auction 8 Results Proceeding The ISO-New England (ISO-NE) Forward Capacity

More information

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $60,516,589

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $60,516,589 Page 1 Formula-based Rate Template Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff Line No. Acct Description Notes Total Transmission A. Zonal Net ATRR 1 Gross ATRR

More information

145 FERC 61,141 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 40. [Docket No. RM ; Order No.

145 FERC 61,141 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. 18 CFR Part 40. [Docket No. RM ; Order No. 145 FERC 61,141 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 18 CFR Part 40 [Docket No. RM13-13-000; Order No. 789] Regional Reliability Standard BAL-002-WECC-2 Contingency Reserve (Issued

More information

August 16, Attachment 1 to the Formula Rate is the Formula Protocols, and Attachment 2 is the Formula Spreadsheet. 2

August 16, Attachment 1 to the Formula Rate is the Formula Protocols, and Attachment 2 is the Formula Spreadsheet. 2 Karen Koyano Principle Manager FERC Rates and Compliance Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 Dear Ms. Bose: Pursuant to Section 205 of the Federal Power Act and

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION California Independent System Operator Corporation Docket No. ER14-1386- REQUEST FOR REHEARING OR, IN THE ALTERNATIVE, MOTION FOR

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404

More information

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC

ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC ALSTON&BIRD LLP The Atlantic Building 950 F Street, NW Washington, DC 20004-1404 202-756-3300 Fax: 202-756-3333 March 2, 2011 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission

More information

Southwestern Public Service Company Attachment O SPS Transmission Formula Annual True-up for 2016 Material Accounting Changes since January 1, 2016

Southwestern Public Service Company Attachment O SPS Transmission Formula Annual True-up for 2016 Material Accounting Changes since January 1, 2016 1 The Company has listed below any material changes that have taken effect since January 1, 2016. For additional information, please refer to the Southwestern Public Service Company FERC Form 1 for Q4

More information

Energy Bar Association

Energy Bar Association Energy Bar Association EBA Energizer: Section 205/206 Fundamentals and Insights November 17, 2016 David DesLauriers, Director Black & Veatch Management Consulting, LLC Jason T. Gray Esq., Shareholder Duncan,

More information

May 15, Duke Energy Ohio, Inc., and Duke Energy Kentucky, Inc. Formula Rate Annual Update Docket No. ER

May 15, Duke Energy Ohio, Inc., and Duke Energy Kentucky, Inc. Formula Rate Annual Update Docket No. ER Gary A. Morgans 202 429 6234 gmorgans@steptoe.com 1330 Connecticut Avenue, NW Washington, DC 20036-1795 202 429 3000 main www.steptoe.com The Hon. Kimberly D. Bose Secretary Federal Energy Regulatory Commission

More information

Informational Filing of Midwest Independent Transmission System Operator, Inc. s Independent Market Monitor

Informational Filing of Midwest Independent Transmission System Operator, Inc. s Independent Market Monitor Potomac Economics, Ltd. 9990 Fairfax Boulevard, Suite 560 Telephone: 703-383-0720 Fairfax, Virginia 22030 Facsimile: 703-383-0796 Honorable Kimberly D. Bose, Secretary Federal Energy Regulatory Commission

More information

Regulatory Status Report

Regulatory Status Report FERC or State Jurisdiction: FERC EL13-88 EL16-91 Northern Indiana Public Service Company's ("NIPSCO") Complaint Against the Midcontinent Independent System Operator, Inc. ("MISO") and PJM Interconnection,

More information

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $48,861,618

Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff. Total Transmission A. Zonal Net ATRR 1 Gross ATRR $48,861,618 Page 1 Formula-based Rate Template Calculate Net Annual Transmission Revenue Requirements (ATRR) and Rates for SPP Tariff Line Acct Description Notes Total Transmission A. Zonal Net ATRR 1 Gross ATRR $48,861,618

More information

transmission system. This project is referred to in the Transition Agreement as the Transmission Interconnection.

transmission system. This project is referred to in the Transition Agreement as the Transmission Interconnection. 2 Application of Valley Electric Association, Inc. to the California Independent System Operator Corporation to Become a Participating Transmission Owner June 21, 2012 Valley Electric Association, Inc.

More information

Interconnection and Local Delivery Service Agreement. between. Host Transmission Owner, Transmission Service Customer. Southwest Power Pool

Interconnection and Local Delivery Service Agreement. between. Host Transmission Owner, Transmission Service Customer. Southwest Power Pool Original Sheet No.1 Interconnection and Local Delivery Service Agreement between Host Transmission Owner, and Transmission Service Customer and Southwest Power Pool Note: Comments reflected in brackets

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Southwest Power Pool, Inc., ) Complainant, ) ) v. ) Docket No. EL14-21-000 ) Midcontinent Independent System ) Operator, Inc. )

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION U.S. Department of Energy, Portsmouth/Paducah Project Office Docket No. RC08-5- REQUEST FOR REHEARING AND CLARIFICATION OF THE NORTH

More information

August 1, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

August 1, Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C August 1, 2018 Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 700 Louisiana Street, Suite 700 Houston, Texas 77002-2700 John A. Roscher

More information

CONTROL AREA SERVICES AND OPERATIONS TARIFF OTTER TAIL POWER COMPANY

CONTROL AREA SERVICES AND OPERATIONS TARIFF OTTER TAIL POWER COMPANY Otter Tail Power Company Original Sheet No. 1 CONTROL AREA SERVICES AND OPERATIONS TARIFF OTTER TAIL POWER COMPANY Otter Tail Power Company Substitute Original Sheet No. 2 Superseding Original Volume No.

More information

Re: Rockland Electric Company, Docket No. EL18-111

Re: Rockland Electric Company, Docket No. EL18-111 Margaret Comes Associate Counsel Rockland Electric Company 4 Irving Place, Room 1815-S, New York, NY 10003 Tel.: 212-460-3013 Email: comesm@coned.com May 14, 2018 Hon. Kimberly D. Bose Secretary Federal

More information

Entergy Services, Inc., Docket No. ER Informational Filing of Annual Transmission Formula Rate Update

Entergy Services, Inc., Docket No. ER Informational Filing of Annual Transmission Formula Rate Update Entergy Services, Inc. 101 Constitution Ave., N.W. Suite 200 East Washington, DC 20001 Tel: 202 530 7323 Fax: 202 530 7350 E-mail: mgriffe@entergy.com Michael C. Griffen Assistant General Counsel Federal

More information

Application For Certain Authorizations Under Section 204 of the Federal Power Act

Application For Certain Authorizations Under Section 204 of the Federal Power Act UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION GridLiance West Transco LLC Docket No. ES17- -000 Application For Certain Authorizations Under Section 204 of the Federal Power

More information

Midcontinent Independent System Operator, Inc., Docket No. EL , et al., Offer of Settlement

Midcontinent Independent System Operator, Inc., Docket No. EL , et al., Offer of Settlement THE WARNER 1299 PENNSYLVANIA AVE., NW WASHINGTON, D.C. 20004-2400 TEL +1 202.639.7700 FAX +1 202.639.7890 BakerBotts.com AUSTIN BEIJING BRUSSELS DALLAS DUBAI HONG KONG HOUSTON LONDON MOSCOW NEW YORK PALO

More information

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11)

RE: Southern California Edison Company s Formula Transmission Rate Annual Update Filing in Docket No. ER (TO11) Jeffrey L. Nelson Director FERC Rates & Market Integration Ms. Kimberly D. Bose, Secretary 888 First Street, N.E. Washington, DC 20426 RE: Southern California Edison Company s Formula Transmission Rate

More information

133 FERC 61,062 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. North American Electric Reliability Corporation

133 FERC 61,062 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. North American Electric Reliability Corporation 133 FERC 61,062 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Jon Wellinghoff, Chairman; Marc Spitzer, Philip D. Moeller, John R. Norris, and Cheryl A. LaFleur. North

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Arizona Public Service Company ) Docket No. ER

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Arizona Public Service Company ) Docket No. ER UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Arizona Public Service Company ) Docket No. ER16-1342- MOTION FOR CLARIFICATION OR, IN THE ALTERNATIVE, REQUEST FOR REHEARING OF

More information

April 6, 2018 VIA OVERNIGHT MAIL. Sheri Young, Secretary of the Board National Energy Board th Avenue SW Calgary, Alberta T2R 0A8

April 6, 2018 VIA OVERNIGHT MAIL. Sheri Young, Secretary of the Board National Energy Board th Avenue SW Calgary, Alberta T2R 0A8 !! April 6, 2018 VIA OVERNIGHT MAIL Sheri Young, Secretary of the Board National Energy Board 517 10 th Avenue SW Calgary, Alberta T2R 0A8 Re: North American Electric Reliability Corporation Dear Ms. Young:

More information

150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 150 FERC 61,116 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Cheryl A. LaFleur, Chairman; Philip D. Moeller, Tony Clark, Norman C. Bay, and Colette D. Honorable.

More information

Transmission System Expansion Cost Allocation Alternatives for Renewable Resources. Cost Allocation Working Group March 26, 2008 OG&E Ver 2 3/20/8

Transmission System Expansion Cost Allocation Alternatives for Renewable Resources. Cost Allocation Working Group March 26, 2008 OG&E Ver 2 3/20/8 Transmission System Expansion Cost Allocation Alternatives for Renewable Resources Cost Allocation Working Group March 26, 2008 OG&E Ver 2 3/20/8 Page 1 Why Page 2 Page 1 of 11 Basic Principles Wind generation

More information

June 20, Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C

June 20, Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C McGuireWoods LLP 2001 K Street N.W. Suite 400 Washington, DC 20006-1040 Phone: 202.857.1700 Fax: 202.857.1737 www.mcguirewoods.com Julia Dryden English Direct: 202.857.1706 jenglish@mcguirewoods.com Fax:

More information

Regulatory Status Report

Regulatory Status Report FERC or State Jurisdiction: FERC AD10-12 AD12-12 Increasing Market and Planning Efficiency through Improved Software A technical conference was held on June 24-26, 2013 to discuss opportunities for increasing

More information

THE UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

THE UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION THE UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Inquiry Regarding the Effect of the Tax Cuts ) and Jobs Act on Commission-Jurisdictional ) Docket No. RM18-12-000 Rates ) MOTION

More information

December 19, Cal. Indep. Sys. Operator Corp., 165 FERC 61,140 (2018) (November 19 Order).

December 19, Cal. Indep. Sys. Operator Corp., 165 FERC 61,140 (2018) (November 19 Order). California Independent System Operator Corporation The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 December 19, 2018 Re: California

More information

Appendix B-2. Term Sheet for Tolling Agreements. for For

Appendix B-2. Term Sheet for Tolling Agreements. for For Appendix B-2 Term Sheet for Tolling Agreements for For 2015 Request For Proposals For Long-Term Developmental Combined-Cycle Gas Turbineand Existing Capacity and Energy Resources in WOTAB DRAFT Entergy

More information

Summary of Prior CAISO Filings and Commission Orders Concerning CAISO Market Redesign Efforts

Summary of Prior CAISO Filings and Commission Orders Concerning CAISO Market Redesign Efforts Summary of Prior CAISO Filings and Commission Orders Concerning CAISO Market Redesign Efforts 1. Commission Directives to Submit a Market Redesign Plan The direct origin of the requirement that the CAISO

More information

January 31, Ms. Kimberly Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426

January 31, Ms. Kimberly Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 January 31, 2011 Ms. Kimberly Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, DC 20426 Re: NERC Abbreviated Notice of Penalty regarding Sharyland Utilities, LP, as

More information

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) California Independent System ) Docket No. ER99-3339-000 Operator Corporation ) ) REQUEST FOR REHEARING OF THE CALIFORNIA INDEPENDENT

More information

January 17, via etariff

January 17, via etariff CLIFFORD S. SIKORA 202.274.2950 telephone Clifford.Sikora@troutmansanders.com TROUTMAN SANDERS LLP Attorneys at Law 401 9th Street, N. W., Suite 1000 Washington, D.C. 20004-2134 202.274.2950 telephone

More information

January 25, By Electronic Filing

January 25, By Electronic Filing Gary J. Newell P 202.370.0137 F 202.370.0143 gnewell@jsslaw.com Jennings, Strouss & Salmon, P.L.C. 1350 I Street, NW Suite 810 Washington, D.C. 200053305 jsslaw.com January 25, 2019 By Electronic Filing

More information

NV Energy, Inc. Operating Companies Open Access Transmission Tariff History of OATT Changes and Filings

NV Energy, Inc. Operating Companies Open Access Transmission Tariff History of OATT Changes and Filings Early 2014 NAESB-WEQ Standards for Section 4.2 RM05-5-022 The Notice of Proposed Rulemaking in this docket was issued on July 18, 2013. Approximate Business Practices and Communication Comments have been

More information

Major FERC Initiatives

Major FERC Initiatives Major FERC Initiatives 2006-2011 BUSINESS PRACTICE STANDARDS FOR ELECTRIC UTILITIES MAJOR PROPOSALS: RM05-5-000 FERC proposed to incorporate by reference the first set of standards for business practice

More information

City of Los Angeles Department of Water and Power Reform of Electric Transmission Tariff and Electric Transmission Rates

City of Los Angeles Department of Water and Power Reform of Electric Transmission Tariff and Electric Transmission Rates City of Los Angeles Department of Water and Power 2017 Reform of Electric Transmission Tariff and Electric Transmission Rates General Manager s Certificate May 4, 2017 TABLE OF CONTENTS Executive summary...

More information

Rate Schedules and Seams Agreements Tariff

Rate Schedules and Seams Agreements Tariff Rate Schedules and Seams Agreements Tariff Southwest Power Pool Rate Schedules and Seams Agreements Tariff Document Generated On: 8/20/2015 Southwest Power Pool - Rate Schedules and Seams Agreements Tariff

More information

COMMENTS OF TROUTMAN SANDERS LLP ON THE EUROPEAN REGULATORS GROUP FOR ELECTRICITY AND GAS DRAFT PROPOSAL ON GUIDELINES ON INTER-TSO COMPENSATION

COMMENTS OF TROUTMAN SANDERS LLP ON THE EUROPEAN REGULATORS GROUP FOR ELECTRICITY AND GAS DRAFT PROPOSAL ON GUIDELINES ON INTER-TSO COMPENSATION DRAFT COMMENTS OF TROUTMAN SANDERS LLP ON THE EUROPEAN REGULATORS GROUP FOR ELECTRICITY AND GAS DRAFT PROPOSAL ON GUIDELINES ON INTER-TSO COMPENSATION In response to the ERGEG Draft Proposal on Guidelines

More information

March 19, MidAmerican Central California Transco, LLC Docket No. ER

March 19, MidAmerican Central California Transco, LLC Docket No. ER 1050 Thomas Jefferson Street, NW Seventh Floor Washington, DC 20007 (202) 298-1800 Phone (202) 338-2416 Fax Douglas W. Smith (202) 298-1902 dws@vnf.com March 19, 2019 Via e-filing Kimberly D. Bose Secretary

More information

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426

FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426 FEDERAL ENERGY REGULATORY COMMISSION WASHINGTON, DC 20426 OFFICE OF ENERGY MARKET REGULATION Sidley Austin LLP 701 Fifth Avenue, Suite 4200 Seattle, WA 98104 Baltimore Gas and Electric Company Suite 1301,

More information

153 FERC 61,248 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

153 FERC 61,248 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 153 FERC 61,248 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Norman C. Bay, Chairman; Cheryl A. LaFleur, and Tony Clark, Tilden Mining Company L.C. and Empire Iron

More information

BES Definition Implementation Guidance

BES Definition Implementation Guidance BES Definition Implementation Guidance August 25, 2014 3353 Peachtree Road NE Suite 600, North Tower Atlanta, GA 30326 NERC BES Definition Implementation Guidance June 23, 2014 404-446-2560 www.nerc.com

More information