TO THE MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: DISCUSSION ITEM EXECUTIVE SUMMARY

Size: px
Start display at page:

Download "TO THE MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: DISCUSSION ITEM EXECUTIVE SUMMARY"

Transcription

1 Office of the President 107 TO THE MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: DISCUSSION ITEM For the Meeting of January 18, 2005 ENGINEERING UNIT 3, IRVINE CAMPUS EXECUTIVE SUMMARY Campus: Irvine Project: Engineering Unit 3 Committee on Finance approval of external financing in the amount of $8,591,000 to be requested at its meeting of January 20, 2005 Total Cost: $65,730,000 to be funded from a combination of State funds ($53,963,000), external financing ($8,591,000), and campus funds ($3,176,000). Previous Actions: November 2003: Approval of the project as an element of the Regents Budget for Capital Improvements. November 2004: Approval of the Project as an element of the Regents Budget for Capital Improvements, including inflationary increase for C and E portions of Engineering Unit 3 budget. Project Summary: The new 86,895 assignable square fee (asf) (149,938 gross square feet (gsf)) Engineering Unit 3 building would provide 68,795 asf for the Henry Samueli School of Engineering for instructional and research laboratories and faculty and administrative offices, 5,400 asf for a 350-seat lecture hall, and 12,700 asf for surge space. Issues: External financing of $8,591,000 Building cost/gsf: $307

2 COMMITTEE ON 107 GROUNDS AND BUILDINGS January 18, BACKGROUND In conformance with University policy that all funds be in hand at time of bid, approval of external financing in the amount of $8,591,000 for the construction of Engineering Unit 3 building, Irvine campus, will be requested from the Committee on Finance at its January 2005 meeting. As the capital project budget has been approved by The Regents, that request will seek approval only to debt-finance a portion of the project funding. The budget for this project totals $65,730,000, to be funded from a combination of State funds ($53,963,000), campus funds ($3,176,000), and external financing ($8,591,000). The Engineering Unit 3 project would construct 86,895 asf (149,938 gsf), including space for the Henry Samueli School of Engineering, a 350-seat general assignment lecture hall, and surge space to address other high-priority academic needs. The Regents Budget for Capital Improvements, which included this project, was approved by The Regents at its meeting of November The approved project budget was $63,184,000, to be supported with $51,443,000 of State funds, $3,150,000 of University funds, and $8,591,000 of external financing. In accordance with standard University procedure, this approval by The Regents authorized only the project budget and specifically did not authorize the acquisition of financing. In November 2004, The Regents approved the Regents Budget for Capital Improvements. This project was included in the budget and was allotted an additional $2,546,000 for inflationary adjustments to the C (Construction) and E (Equipment) phases of the work. The project budget is now $65,730,000, supported with State funding of $53,963,000, University funds of $3,176,000, and external financing of $8,591,000. Project Description The Engineering Unit 3 project would construct 86,895 asf of space. Of this total, 68,795 asf would be for the Henry Samueli School of Engineering to provide teaching and research laboratories and academic and administrative office space, 5,400 asf would provide a 350-seat general assignment lecture hall, and 12,700 asf would be for surge space to address other highpriority academic needs. The project site is in the Engineering-Computer Science Quadrangle, adjacent to the Computer Science Unit 3 building currently in construction. This location is occupied by two woodframed buildings that would be demolished as part of the project. The site is in conformance with the campus s revised Long Range Development Plan. The project is scheduled for award in January 2006, with completion in spring CEQA Classification In accordance with University of California guidelines for the implementation of the California Environmental Quality Act, environmental documentation will be prepared for consideration in conjunction with the project design review. (Attachments)

3 ATTACHMENT 1 PROJECT STATISTICS ENGINEERING UNIT 3 CAPITAL IMPROVEMENT BUDGET IRVINE CAMPUS CCCI 4328 Cost Category Amount % of Total Site Clearance $628, % Building 46,066, % Exterior Utilities 964, % Site Development 1,782, % A/E Fees (a) 4,137, % Campus Administration (b) 1,949, % Surveys, Tests 729, % Special Items (c ) 1,165, % Contingency 1,958, % Total $59,378, % Group 2 & 3 Equipment 6,352,000 Total Project $65,730,000 Statistics Gross Square Feet (gsf) (d) 149,938 Assignable Square Feet (asf) (d) 86,895 Ratio asf/gsf (%): 58% Building Cost/gsf (d) $307 Building Cost/asf $530 Comparable University Projects at CCCI 4328 CIB Dated Campus Project Building Cost/GSF Ratio gsf/asf (N/A) (N/A) University of California Benchmark Model $ % 03/07/01 Irvine Cal-(IT)2 Facility at Irvine $ % 07/02/03 Riverside Materials Science and Engineering Building $ % (a) A/E fees include executive architect basic services, and other professional design contract costs. (b) Campus administration includes project management and inspection. (c) Special Items include independent seismic review, value engineering/constructability review, agency review, utility infrastructure coordination, subsurface soils consultant, topographic/as-built survey, environmental impact report, and interest during construction (d) Gross square feet (gsf) is the total area, including all usable areas, stairways, and space occupied by the structure itself. Assignable square feet (asf) is the net program area.

4 ATTACHMENT 2 FINANCIAL FEASIBILITY (for information only) The total cost for the Engineering Unit 3 project is estimated at $65,730,000. The project would be funded from State funds ($53,963,000), campus funds ($3,176,000), and external financing ($8,591,000). Based on long-term debt of $8,591,000 amortized over 30 years at percent interest, the estimated average annual debt service would be $632,000. Repayment for the Engineering Unit 3 debt would be from campus Opportunity Funds. Opportunity Funds are a portion of the indirect cost recovery generated by federal contracts and grants. By University policy, up to 65 percent of the campus s total Opportunity Funds may be pledged for debt service, but only up to 33 percent of actual debt service may be paid from Opportunity Funds. In fiscal year , the second full year of occupancy and first full year of principal and interest for the project, 61.2 percent of Opportunity Funds are pledged for debt service. Inclusive of this amount for the external financing, the campus is within the prescribed Opportunity Fund pledge and payment limits. Project Title: Engineering Unit 3 SUMMARY OF FINANCIAL FEASIBILITY ANALYSIS Total Estimated Project Costs: $65,730,000 Proposed Source of Funding: State Funds $53,963,000 Campus Funds $ 3,176,000 External Financing $ 8,591,000 Total $65,730,000 Projected Financing Terms: Interest Rate: 6.125% Duration: 30 years Annual Debt Service: $632,000 Campus Opportunity Funds Information (FY ): (1) Pre-Off-the-Top Existing Garamendi Projects $ 3,570,000 Opportunity Funds Generated $14,769,000 Total Estimated Annual Revenue $18,339,000

5 ATTACHMENT 2 continued Estimated Average Annual Debt Service/O&M Expenditures (FY ): (1) Proposed Project Debt Service $ 632,000 Existing Garamendi Debt Service and O&M Expenditures $ 3,570,000 Pledged Expenditures Other Approved Capital Projects $ 6,720,000 Planned Projects Not Yet Approved (2) $ 306,000 Total Estimated Annual Expenses $11,228,000 Percentage of Opportunity Funds Pledged for Debt: 61.2% Debt Service Coverage: 1.63x (1) Fiscal year represents first full year of principal and interest for the project (2) This project estimate is based on the information reported in the to Five Year Non State Capital Program section for the Irvine campus and is subject to change based on campus priorities

TO THE MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM

TO THE MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM 102 TO THE MEMBERS OF THE COMMITTEE ON : For Meeting of ACTION ITEM AMENDMENT OF THE BUDGET FOR CAPITAL IMPROVEMENTS AND THE CAPITAL IMPROVEMENT PROGRAM FOR DAVIS HALL NORTH REPLACEMENT BUILDING, BERKELEY

More information

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM 104 Office of the President TO MEMBERS OF THE COMMITTEE ON : For Meeting of ACTION ITEM AMENDMENT OF THE BUDGET FOR CAPITAL IMPROVEMENTS AND THE CAPITAL IMPROVEMENT PROGRAM AND APPROVAL OF EXTERNAL FINANCING

More information

$46,400,000 to be funded from gifts ($37,400,000) and external financing ($9,000,000)

$46,400,000 to be funded from gifts ($37,400,000) and external financing ($9,000,000) 501B COMMITTEE ON FINANCE B. AMENDMENT OF THE BUDGET FOR CAPITAL IMPROVEMENTS AND THE CAPITAL IMPROVEMENT PROGRAM, AND APPROVAL OF EXTERNAL FINANCING FOR C. V. STARR EAST ASIAN LIBRARY, BERKELEY CAMPUS

More information

TO THE MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM

TO THE MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM 106 Office of the President TO THE MEMBERS OF THE COMMITTEE ON : For Meeting of ACTION ITEM AMENDMENT OF THE BUDGET FOR CAPITAL IMPROVEMENTS AND THE CAPITAL IMPROVEMENT PROGRAM, ADOPTION OF FINDINGS, AND

More information

TO THE MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM CONSENT

TO THE MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM CONSENT GB1 Office of the President TO THE MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: For Meeting of January 22, 2014 ACTION ITEM CONSENT AMENDMENT OF THE BUDGET AND APPROVAL OF EXTERNAL FINANCING, LI

More information

CHAIRMAN OF THE BOARD CHAIRMAN OF THE COMMITTEE ON GROUNDS AND BUILDINGS PRESIDENT OF THE UNIVERSITY

CHAIRMAN OF THE BOARD CHAIRMAN OF THE COMMITTEE ON GROUNDS AND BUILDINGS PRESIDENT OF THE UNIVERSITY UNIVERSITY OF CALIFORNIA BERKELEY DAVIS' IRVINE LOS ANGELES' MERCED' RlVERSIDE SAN DIEGO' SAN FRANCISCO SANTA BARBARA SANTACRUZ 1111 Franklin Street Oakland, CA 94607-5200 Phone: (510) 987-9074 Fax: (510)

More information

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM GB1A Office of the President TO MEMBERS OF THE COMMITTEE ON : For Meeting of ACTION ITEM AMENDMENT OF THE BUDGET FOR CAPITAL IMPROVEMENTS AND THE CAPITAL IMPROVEMENT PROGRAM AND APPROVAL OF EXTERNAL FINANCING,

More information

CHAIR OF THE BOARD CHAIR OF THE COMMITTEE ON GROUNDS AND BUILDINGS PRESIDENT OF THE UNIVERSITY

CHAIR OF THE BOARD CHAIR OF THE COMMITTEE ON GROUNDS AND BUILDINGS PRESIDENT OF THE UNIVERSITY UNIVERSITY OF CALIFORNIA BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANTA BARBARA SANTA CRUZ OFFICE OF THE PRESIDENT 1111 Franklin Street Oakland, CA 94607-5200 Phone: (510)

More information

VICE PRESIDENT, BUDGET AND CAPITAL RESOURCES, UNIVERSITY OF CALIFORNIA, OFFICE OF THE PRESIDENT

VICE PRESIDENT, BUDGET AND CAPITAL RESOURCES, UNIVERSITY OF CALIFORNIA, OFFICE OF THE PRESIDENT August 2014 VICE PRESIDENT, BUDGET AND CAPITAL RESOURCES, UNIVERSITY OF CALIFORNIA, OFFICE OF THE PRESIDENT AMENDMENT OF THE BUDGET, ENVIRONMENTAL HEALTH AND SAFETY EXPANSION, RIVERSIDE CAMPUS EXECUTIVE

More information

UC MERCED CAPITAL PLANNING PROCESS CAPITAL PROJECT DEVELOPMENT Issued: February 2005 TABLE OF CONTENTS. Table of Contents...1

UC MERCED CAPITAL PLANNING PROCESS CAPITAL PROJECT DEVELOPMENT Issued: February 2005 TABLE OF CONTENTS. Table of Contents...1 UC MERCED CAPITAL PLANNING PROCESS CAPITAL PROJECT DEVELOPMENT Issued: February 2005 TABLE OF CONTENTS Table of Contents...1 I. Executive Summary...2 II. III. Overview of the UC Merced Capital Planning

More information

A. Certify the UCLA Long Range Development Plan Amendment (2017) and Student Housing Projects Subsequent Environmental Impact Report.

A. Certify the UCLA Long Range Development Plan Amendment (2017) and Student Housing Projects Subsequent Environmental Impact Report. FINANCE AND CAPITAL STRATEGIES COMMITTEE January 25, 2018 TO THE REGENTS OF THE UNIVERSITY OF CALIFORNIA 1. APPROVAL OF AMENDMENT #6 TO THE UCLA 2002 LONG RANGE DEVELOPMENT PLAN FOR ADDITIONAL ON-CAMPUS

More information

Georgia Institute of Technology Advanced Computing Technology Building. Draft Program. Mission Model Initial Program Development

Georgia Institute of Technology Advanced Computing Technology Building. Draft Program. Mission Model Initial Program Development Georgia Institute of Technology Advanced Computing Technology Building Draft Program Initial Program Development Issued April 2, 2001 Introduction Scope This document is a summary of the Session for the

More information

ACTION ITEM APPROVAL OF EXTERNAL FINANCING, SANTA MONICA ORTHOPEDIC HOSPITAL LEGAL SETTLEMENT, LOS ANGELES CAMPUS EXECUTIVE SUMMARY

ACTION ITEM APPROVAL OF EXTERNAL FINANCING, SANTA MONICA ORTHOPEDIC HOSPITAL LEGAL SETTLEMENT, LOS ANGELES CAMPUS EXECUTIVE SUMMARY F2 Office of the President TO MEMBERS OF THE COMMITTEE ON FINANCE For Meeting of March 23, 2016 ACTION ITEM APPROVAL OF EXTERNAL FINANCING, SANTA MONICA ORTHOPEDIC HOSPITAL LEGAL SETTLEMENT, LOS ANGELES

More information

Agenda Item No. 3.2 AGENDA ITEM BRIEFING

Agenda Item No. 3.2 AGENDA ITEM BRIEFING Agenda Item No. 3.2 AGENDA ITEM BRIEFING Submitted by: Billy Hamilton, Executive Vice Chancellor and Chief Financial Officer The Texas A&M University System Subject: Approval of the Project Scope and Budget,

More information

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: ACTION ITEM TO MEMBERS OF THE COMMITTEE ON : For Meeting of January 19, 2010 ACTION ITEM GB3 ACCEPTANCE OF 2009-19 CAPITAL FINANCIAL PLAN AND PHYSICAL DESIGN FRAMEWORK AND AUTHORIZATION TO PARTICIPATE IN THE PILOT

More information

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: 1 ACTION ITEM

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: 1 ACTION ITEM GB3 Office of the President TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: 1 For Meeting of January 22, 2015 ACTION ITEM AMENDMENT OF POLICY ON APPROVAL OF DESIGN, LONG RANGE DEVELOPMENT PLANS,

More information

Agenda Item No. 3.2 AGENDA ITEM BRIEFING

Agenda Item No. 3.2 AGENDA ITEM BRIEFING Agenda Item No. 3.2 AGENDA ITEM BRIEFING Submitted by: Billy Hamilton, Executive Vice Chancellor and Chief Financial Officer The Texas A&M University System Subject: Approval of the Revised Project Scope

More information

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: DISCUSSION ITEM

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: DISCUSSION ITEM GB3 Office of the President TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: For Meeting of DISCUSSION ITEM STATUS OF THE PILOT PHASE OF THE DELEGATED PROCESS FOR CAPITAL IMPROVEMENT PROJECTS EXECUTIVE

More information

The Regents of the University of California. COMMITTEE ON GROUNDS AND BUILDINGS COMMITTEE ON FINANCE January 14, 2004

The Regents of the University of California. COMMITTEE ON GROUNDS AND BUILDINGS COMMITTEE ON FINANCE January 14, 2004 The Regents of the University of California COMMITTEE ON GROUNDS AND BUILDINGS COMMITTEE ON FINANCE January 14, 2004 The Committees on Grounds and Buildings and Finance met jointly on the above date at

More information

CALIFORNIA POLYTECHNIC STATE UNIVERSITY, SAN LUIS OBISPO. Financial Statements. June 30, 2009

CALIFORNIA POLYTECHNIC STATE UNIVERSITY, SAN LUIS OBISPO. Financial Statements. June 30, 2009 Financial Statements (With Independent Auditors Report Thereon) Table of Contents Page Independent Auditors Report 1 Management s Discussion and Analysis 3 Financial Statements: Statement of Net Assets

More information

UCM DA 176. September 7, 2018 VICE CHANCELLOR AND CHIEF FINANCIAL OFFICER

UCM DA 176. September 7, 2018 VICE CHANCELLOR AND CHIEF FINANCIAL OFFICER UCM DA 176 September 7, 2018 VICE CHANCELLOR AND CHIEF FINANCIAL OFFICER RE: Delegation of - Appointment of and Execution of Agreements for Executive Architects, Executive Landscape Architects, and Executive

More information

RECOMMENDATION. c. Approve a total project cost of $3,300,000

RECOMMENDATION. c. Approve a total project cost of $3,300,000 1. U. T. Arlington - Intramural and Recreation Complex - Phase I: Request for Approval to Amend the FY 2002-2007 Capital Improvement Program and the FY 2002-2003 Capital Budget to Include Project; Authorization

More information

UNC System Building Reserve Model Instructions

UNC System Building Reserve Model Instructions Instructions Introduction: These are instructions for filling out the two building reserve templates. One template is for new buildings - UNC System Building Reserve Model for New Buildings; and one template

More information

TO MEMBERS OF THE FINANCE AND CAPITAL STRATEGIES COMMITTEE: ACTION ITEM

TO MEMBERS OF THE FINANCE AND CAPITAL STRATEGIES COMMITTEE: ACTION ITEM F4 Office of the President TO MEMBERS OF THE FINANCE AND CAPITAL STRATEGIES COMMITTEE: For Meeting of March 15, 2017 ACTION ITEM APPROVAL OF BUDGET AND DESIGN FOLLOWING ACTION PURSUANT TO THE CALIFORNIA

More information

State Capital Outlay Program Overview

State Capital Outlay Program Overview State Capital Outlay Program Overview CCC Chancellor s Office ACBO Institute, February 2017 Fred Harris Carlos Montoya Agenda Chancellor s Office Role CCC Facilities Overview Capital Outlay Planning Capital

More information

CALIFORNIA POLYTECHNIC STATE UNIVERSITY, SAN LUIS OBISPO. Financial Statements. June 30, (With Independent Auditors Report Thereon)

CALIFORNIA POLYTECHNIC STATE UNIVERSITY, SAN LUIS OBISPO. Financial Statements. June 30, (With Independent Auditors Report Thereon) Financial Statements (With Independent Auditors Report Thereon) Table of Contents Page Independent Auditors Report 1 Management s Discussion and Analysis 3 Financial Statements: Statement of Net Assets

More information

FY 2017 Capital Development Plan. Arizona State University. Revised November 2016

FY 2017 Capital Development Plan. Arizona State University. Revised November 2016 FY 2017 Capital Development Plan Arizona State University Revised November 2016 EXECUTIVE SUMMARY Page 1 of 17 Item Name: Revised FY 2017 Capital Development Plan (ASU) Action Item Committee Recommendation

More information

Presentation to the University Committee on Planning and Budget

Presentation to the University Committee on Planning and Budget Presentation to the University Committee on Planning and Budget by Peter J. Taylor, Executive Vice President & Chief Financial Officer Sandra Kim, Executive Director, External Finance October 6, 2009 y

More information

DA2598 UNIVERSITY OF CALIFORNIA. April 19, 2016

DA2598 UNIVERSITY OF CALIFORNIA. April 19, 2016 UNIVERSITY OF CALIFORNIA DA2598 BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANTA BARBARA SANTA CRUZ CHANCELLORS DIRECTOR LAWRENCE BERKELEY NATIONAL LABORATORY EXECUTIVE

More information

FY 2016 Capital Development Plan. Arizona State University

FY 2016 Capital Development Plan. Arizona State University FY 2016 Capital Development Plan Arizona State University EXECUTIVE SUMMARY Page 3 of 19 Project Name Approval Date Occupancy Date Project Cost Gift Target Current Gifts (Cash/ Pledges) College Avenue

More information

CHAPTER 3: PROJECT PRIORITIES AND SELECTION

CHAPTER 3: PROJECT PRIORITIES AND SELECTION CHAPTER 3: PROJECT PRIORITIES AND SELECTION 3.1 Overview 3.2 Steps in the Capital Outlay Process 3.3 State Funding Configurations 3.4 Priority Criteria for Capital Outlay 3.5 Types of Projects 3.6 Community

More information

In accordance with authority previously delegated by the Regents, interim or concurrence action was taken on routine or emergency matters as follows:

In accordance with authority previously delegated by the Regents, interim or concurrence action was taken on routine or emergency matters as follows: REPORT OF INTERIM Office of the Secretary and Chief of Staff November 15, 2012 TO THE REGENTS OF THE UNIVERSITY OF CALIFORNIA: INFORMATION ITEM Report of Actions Taken Between Meetings In accordance with

More information

ARKANSAS DEPARTMENT OF HIGHER EDUCATION ADHE 17-1 SUMMARY OF INCOME FOR ALL FUND GROUPS (SEE INSTRUCTIONS)

ARKANSAS DEPARTMENT OF HIGHER EDUCATION ADHE 17-1 SUMMARY OF INCOME FOR ALL FUND GROUPS (SEE INSTRUCTIONS) ADHE 17-1 SUMMARY OF INCOME FOR ALL FUND GROUPS FICE CODE 12105 COMPLETED BY: Susan Holsomback INSTITUTION DATE COMPLETED: 9/13/2013 FISCAL YEAR ended June 30,2013 TELEPHONE NO. 501-760-4216 INCOME (and

More information

SONOMA STATE UNIVERSITY. Financial Statements. June 30, (With Independent Auditors Report Thereon)

SONOMA STATE UNIVERSITY. Financial Statements. June 30, (With Independent Auditors Report Thereon) Financial Statements (With Independent Auditors Report Thereon) Table of Contents Page Independent Auditors Report 1 Management s Discussion and Analysis 3 Financial Statements: Statement of Net Assets

More information

Scott A. Jordan Executive Vice President for Administration and Chief Financial Officer

Scott A. Jordan Executive Vice President for Administration and Chief Financial Officer April 26, 2017 TO: FROM: Members of the Board of Trustees Scott A. Jordan Executive Vice President for Administration and Chief Financial Officer Jeremy Teitelbaum Interim Provost and Executive Vice President

More information

The California State University - OFFICE OF THE CHANCELLOR

The California State University - OFFICE OF THE CHANCELLOR The California State University - OFFICE OF THE CHANCELLOR MEMORANDUM To: Vice Presidents, Finance I Administration From: Elvyra F. San Ju~ C;-n~or Assistant Vice Capital Planning, Design and Construction

More information

TABLE 4A UNIVERSITY OF CALIFORNIA

TABLE 4A UNIVERSITY OF CALIFORNIA Net-New Research in the Building $1,285,726 $53,832 $1,324,000 1) $1,364,000 Rate Inc. Resulting From New Buildings $64,137 $67,000 $70,000 INCREASE OF OVERHEAD $1,349,863 $53,832 $1,391,000 $0 $1,434,000

More information

REQUEST FOR PROPOSALS (RFP)- SCIENCES BUILDING FOR DSA INSPECTION SERVICES, SADDLEBACK COLLEGE

REQUEST FOR PROPOSALS (RFP)- SCIENCES BUILDING FOR DSA INSPECTION SERVICES, SADDLEBACK COLLEGE REQUEST FOR PROPOSALS (RFP)- SCIENCES BUILDING FOR DSA INSPECTION SERVICES, SADDLEBACK COLLEGE INTRODUCTION South Orange County Community College District is requesting proposals from interested, qualified

More information

University of California Current Funds Revenues By Source by Campus Schedule 12-A

University of California Current Funds Revenues By Source by Campus Schedule 12-A Current Funds Revenues By Source by Campus 2015-16 Schedule 12-A Berkeley Davis Irvine Los Angeles Merced Riverside San Diego San Francisco Santa Barbara Systemwide Programs & Santa Cruz Administration

More information

Facilities Planning (Revised 2016)

Facilities Planning (Revised 2016) Facilities Planning (Revised 2016) Chapter 7830 Draft Revision November 2016 Table of Contents.010 Campus Planning & Project Management.020 Definitions.030 Small/Medium Projects Project Decision Process

More information

THE COOPER UNION FOR THE ADVANCEMENT OF SCIENCE AND ART. Consolidated Financial Statements. June 30, 2011 and 2010

THE COOPER UNION FOR THE ADVANCEMENT OF SCIENCE AND ART. Consolidated Financial Statements. June 30, 2011 and 2010 Consolidated Financial Statements (With Independent Auditors Report Thereon) KPMG LLP 345 Park Avenue New York, NY 10154 Independent Auditors Report The Board of Trustees The Cooper Union for the Advancement

More information

July 2011 Review Lander Schematic. Design. Presentation. Pre-design / Design / Construction

July 2011 Review Lander Schematic. Design. Presentation. Pre-design / Design / Construction F 6 Phase, Reduce Project Budget and Reduce Debt Funding Regents Action and Information Timeline November 2009 HFS Master Plan Phase II & III Update Mercer Site 30W Project Concept March 2011 Mercer Presentation

More information

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: INFORMATION ITEM ANNUAL REPORT ON MAJOR CAPITAL PROJECTS IMPLEMENTATION FISCAL YEAR

TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: INFORMATION ITEM ANNUAL REPORT ON MAJOR CAPITAL PROJECTS IMPLEMENTATION FISCAL YEAR Office of the President November 2008 Mailing between Meetings TO MEMBERS OF THE COMMITTEE ON GROUNDS AND BUILDINGS: INFORMATION ITEM ANNUAL REPORT ON MAJOR CAPITAL PROJECTS IMPLEMENTATION FISCAL YEAR

More information

C. ESTIMATED COSTS OF LRDP PROPOSALS

C. ESTIMATED COSTS OF LRDP PROPOSALS EXISTING SITES With these historical references in mind, it is possible to examine the set of future projects for each campus site set out in Chapter 5, Plans for Existing Sites. Table 37 displays the

More information

CP DC MASTERING THE 2-7. Presented by CPDC Facilities Planning. Systemwide Professional Development

CP DC MASTERING THE 2-7. Presented by CPDC Facilities Planning. Systemwide Professional Development CP DC MASTERING THE 2-7 Presented by CPDC Facilities Planning Produced by Systemwide Professional Development Mastering Facilities Planning Series of six sessions Mastering Feasibility Studies May 17,

More information

UNIVERSITY OF CALIFORNIA, BERKELEY. Annual Financial Report

UNIVERSITY OF CALIFORNIA, BERKELEY. Annual Financial Report UNIVERSITY OF CALIFORNIA, BERKELEY Annual Financial Report 2006-07 TABLE OF CONTENTS Fiscal Year 2006-07 Management's Discussion and Analysis 3 Letter from the Associate Vice Chancellor Finance and Controller

More information

Faculty Senate Fiscal Committee February 24, 2015

Faculty Senate Fiscal Committee February 24, 2015 Faculty Senate Fiscal Committee February 24, 2015 TOPIC: Overhead Rates for FY 2016 CONTEXT: This is the annual calculation of overhead rates charged by the University to non-general Fund (earnings) units

More information

ANNUAL DISCLOSURE REPORT OF THE BOARD OF TRUSTEES OF THE LELAND STANFORD JUNIOR UNIVERSITY FOR THE FISCAL YEAR ENDED AUGUST 31, 2017

ANNUAL DISCLOSURE REPORT OF THE BOARD OF TRUSTEES OF THE LELAND STANFORD JUNIOR UNIVERSITY FOR THE FISCAL YEAR ENDED AUGUST 31, 2017 ANNUAL DISCLOSURE REPORT OF THE BOARD OF TRUSTEES OF THE LELAND STANFORD JUNIOR UNIVERSITY FOR THE FISCAL YEAR ENDED AUGUST 31, 2017 DATED JANUARY 26, 2018 ANNUAL DISCLOSURE REPORT OF THE BOARD OF TRUSTEES

More information

FY 2016 BUDGET RUTGERS NEWARK

FY 2016 BUDGET RUTGERS NEWARK RUTGERS SCHOOLS Office of Budget and Resource Studies January 29, 2016 Office of Budget and Resource Studies 33 Knightsbridge Road Piscataway, NJ 08854 budget.rutgers.edu p. 848-932-7472 f. 732-445-3579

More information

Oakland University. Annual Financial Report. Years ended June 30, 2003 and 2002 with Report of Independent Auditors

Oakland University. Annual Financial Report. Years ended June 30, 2003 and 2002 with Report of Independent Auditors Annual Financial Report Years ended June 30, 2003 and 2002 with Report of Independent Auditors Annual Financial Statements Years ended June 30, 2003 and 2002 Contents Management s Discussion and Analysis...

More information

CAPITAL PROJECT PROCESS

CAPITAL PROJECT PROCESS CAPITAL PROJECT PROCESS May 2009 GETTING STARTED What is a project? A project is defined as all work (maintenance & repair or renovation) that requires 5,000 or more in time and materials and/or is sufficiently

More information

Final Project Proposal 20 -

Final Project Proposal 20 - APPENDIX E: FINAL PROJECT PROPOSAL Final Project Proposal 20 - Community College Construction Act of 1980 Capital Outlay Budget Change Proposal Proposal Name Community College District College or Center

More information

FINAL PROJECT REPORT

FINAL PROJECT REPORT FINAL PROJECT REPORT TO: FROM: DATE: Pat Gamble President Kit Duke AVP Facilities and Land Management Chancellor Vice Chancellor Associate Vice Chancellor Director Project Manager (insert ) SUBJECT: Project

More information

FLORIDA DEPARTMENT OF TRANSPORTATION ADDENDUM NO. 2 DATE: September 13, 2013

FLORIDA DEPARTMENT OF TRANSPORTATION ADDENDUM NO. 2 DATE: September 13, 2013 ADDENDUM NO. 2 FLORIDA DEPARTMENT OF TRANSPORTATION ADDENDUM NO. 2 DATE: September 13, 2013 RE: RFP Number: Description: Districtwide Right of Way Asbestos Consulting Services. CHANGE: Removes Section

More information

Case Western Reserve University Consolidated Financial Statements for the Year Ending June 30, 2002

Case Western Reserve University Consolidated Financial Statements for the Year Ending June 30, 2002 Contents Report of Independent Accountants 1 Part 1 Consolidated Financial Statements Consolidated Balance Sheet 2 Consolidated Statement of Activities 3 Consolidated Statement of Cash Flows 4 Part 2 Summary

More information

RESOLUTION OF THE BOARD OF TRUSTEES OF THE TRUSTEES OF PURDUE UNIVERSITY (THE CORPORATION )

RESOLUTION OF THE BOARD OF TRUSTEES OF THE TRUSTEES OF PURDUE UNIVERSITY (THE CORPORATION ) PFC 5/15/14 Action Item 4 BT 5/16/14 IV-7 RESOLUTION OF THE BOARD OF TRUSTEES OF THE TRUSTEES OF PURDUE UNIVERSITY (THE CORPORATION ) 1. DECLARING THE NECESSITY FOR THREE ENGINEERING RESEARCH LAB PROJECTS

More information

PROCESS IMPROVEMENT INITIATIVE

PROCESS IMPROVEMENT INITIATIVE FACILITIES SERVICES / DISTRICT & SCHOOL SECURITY PROCESS IMPROVEMENT INITIATIVE Work System Owner Ed Curry Work System Enabling Leader Dane Theodore, Director 5/1/09 1 INITIATIVE CATEGORIES Facilities

More information

Civic Center Facilities Master Plan

Civic Center Facilities Master Plan Agenda Item #26 Attachment A Civic Center Facilities Master Plan Presentation to the Board of Supervisors February 23, 2016 - C o u n t y O c c u p a n c y i n C i v i c C e n t e r 10 County-owned Buildings

More information

Members Present: Gino Gasparini, Vijay Gupta, Nori Jabba, James Ruigomez, Bill Rundberg and Dennis Zheng

Members Present: Gino Gasparini, Vijay Gupta, Nori Jabba, James Ruigomez, Bill Rundberg and Dennis Zheng SAN MATEO COUNTY COMMUNITY COLLEGE DISTRICT Bond Oversight Committee Minutes of June 1, 2017 Meeting District Office Board Room Members Present: Gino Gasparini, Vijay Gupta, Nori Jabba, James Ruigomez,

More information

CSUCI FINANCING AUTHORITY (A Discretely Presented Component Unit of California State University, Channel Islands)

CSUCI FINANCING AUTHORITY (A Discretely Presented Component Unit of California State University, Channel Islands) Financial Statements and Supplementary Information (With Independent Auditors Report Thereon) Table of Contents Independent Auditors Report 1 Financial Statements: Statements of Net Assets 2 Statements

More information

Budget Planning Update. Academic and Business Administrators

Budget Planning Update. Academic and Business Administrators Budget Planning Update Academic and Business Administrators March 5, 2013 Budget Planning Updates State and UC Budget UCSD Budget and Planning Sources & Uses Budget Planning Process for 2013/14 Assumptions

More information

TABLE 4A UNIVERSITY OF CALIFORNIA

TABLE 4A UNIVERSITY OF CALIFORNIA TABLE 4A PROJECT: Institute for Geophysics and Planetary Physics - Unit 2 Net-New Research in the Building $1,476,561 $193,682 $1,521,000 1) $1,567,000 Rate Inc. Resulting From New Buildings $253,099 $266,000

More information

Minutes Capital Planning and Budget Committee Thursday, July 9, 2009

Minutes Capital Planning and Budget Committee Thursday, July 9, 2009 Minutes Capital Planning and Budget Committee Thursday, July 9, 2009 Committee Chair Regent Bartell convened the meeting of the Capital Planning and Budget Committee at 9:08 a.m. in Room 1820 of Van Hise

More information

THE COOPER UNION FOR THE ADVANCEMENT OF SCIENCE AND ART. Consolidated Financial Statements. June 30, 2013 and 2012

THE COOPER UNION FOR THE ADVANCEMENT OF SCIENCE AND ART. Consolidated Financial Statements. June 30, 2013 and 2012 Consolidated Financial Statements (With Independent Auditors Report Thereon) KPMG LLP 345 Park Avenue New York, NY 10154 Independent Auditors Report The Board of Trustees The Cooper Union for the Advancement

More information

Asset Liability Management Semi-Annual Borrower Reports (SABRe)

Asset Liability Management Semi-Annual Borrower Reports (SABRe) STANDING COMMITTEES F 4 Finance and Asset Management Committee Asset Liability Management Semi-Annual Borrower Reports (SABRe) INFORMATION For information only. BACKGROUND The Semi-Annual Borrower Reports

More information

California State University, Long Beach Annual Management Report A Supplement to the Annual Audited Financial Report

California State University, Long Beach Annual Management Report A Supplement to the Annual Audited Financial Report California State University, Long Beach 2009-2010 Annual Management Report A Supplement to the Annual Audited Financial Report Foreword August 9, 2010 Dr. F. King Alexander President The Annual Management

More information

OPERATING BUDGET

OPERATING BUDGET 2018 19 OPERATING BUDGET May 10, 2018 Table of Contents 2018-19 Operating Budget at a Glance... 1 Introduction... 2 Key Components of the 2018-19 Budget... 3 Revenue... 3 Expenditures... 6 Appendices...

More information

FY 2018 Capital Development Plan University of Arizona

FY 2018 Capital Development Plan University of Arizona FY 2018 Capital Development Plan University of Arizona Revised November 2017 EXECUTIVE SUMMARY Page 1 of 34 Item Name: Revised FY 2018 Capital Development Plan (UA) Action Item Committee Recommendation

More information

14 Capital Improvements

14 Capital Improvements Capital Improvements Supporting Data The purpose of the Capital Improvements element is to evaluate the need for public facilities as identified in other campus master plan elements; to estimate the cost

More information

CALIFORNIA STATE UNIVERSITY, CHICO. Financial Statements. June 30, (With Independent Auditors Report Thereon)

CALIFORNIA STATE UNIVERSITY, CHICO. Financial Statements. June 30, (With Independent Auditors Report Thereon) Financial Statements (With Independent Auditors Report Thereon) Table of Contents Page Independent Auditors Report 1 Management s Discussion and Analysis (unaudited) 3 Financial Statements: Statement of

More information

CALIFORNIA STATE UNIVERSITY, NORTHRIDGE. Financial Statements. June 30, (With Independent Auditors Report Thereon)

CALIFORNIA STATE UNIVERSITY, NORTHRIDGE. Financial Statements. June 30, (With Independent Auditors Report Thereon) Financial Statements (With Independent Auditors Report Thereon) Table of Contents Page Independent Auditors Report 1 Management s Discussion and Analysis 3 Basic Financial Statements: Statement of Net

More information

CHAPTER 5: CAPITAL OUTLAY PROJECT PROPOSALS

CHAPTER 5: CAPITAL OUTLAY PROJECT PROPOSALS CHAPTER 5: CAPITAL OUTLAY PROJECT PROPOSALS 5.1 Overview 5.2 Preparation of Capital Outlay Project Proposals 5.3 Initial Project Proposal 5.4 Final Project Proposal 5.5 Chancellor s Office Project Design

More information

University of Colorado Capital Construction Project Status SUMMARY - May 2017 (accounting noted by campus)

University of Colorado Capital Construction Project Status SUMMARY - May 2017 (accounting noted by campus) of Colorado Capital Project Status SUMMARY - May (accounting noted by campus) Legend On-Track Risks Approved - Adjustments Needed Awaiting $ Start-Up Phase In Bidding Phase In Closeout Project Completed

More information

Honors College and Residences Request BOT Approval to Finance, Construct and Award Construction Contract

Honors College and Residences Request BOT Approval to Finance, Construct and Award Construction Contract Honors College and Residences Request BOT Approval to Finance, Construct and Award Construction Contract PFC 9/25/14 BT 9/26/14 Campus: Project Description: Architect/Engineer: West Lafayette This project

More information

Bruce McPheron, Interim Executive Vice President and Provost Geoff Chatas, Senior Vice President and Chief Financial Officer

Bruce McPheron, Interim Executive Vice President and Provost Geoff Chatas, Senior Vice President and Chief Financial Officer Department of Accounting and MIS 400 Fisher Hall 2100 Neil Avenue Columbus, OH 43210 614-247-6299 Phone 614-292-2118 Fax dietrich@fisher.osu.edu February 29, 2016 To: Bruce McPheron, Interim Executive

More information

TOTAL COST OF OWNERSHIP Planning and Budget Counsel November 4, 2015 P E R A L TA COMMUNITY COLLEGE DISTRICT

TOTAL COST OF OWNERSHIP Planning and Budget Counsel November 4, 2015 P E R A L TA COMMUNITY COLLEGE DISTRICT P E R A L TA COMMUNITY COLLEGE DISTRICT TOTAL COST OF OWNERSHIP 2014 Planning and Budget Counsel November 4, 2015 D E P A R T M E N T O F G E N E R A L S E R V I C E S Table of Contents INTRODUCTION 1

More information

Guidelines for Space Needs Studies

Guidelines for Space Needs Studies Guidelines for Space Needs Studies Approved by the Space Use Advisory Committee 1 ; 3/28/19 INTENT Develop a standard process, including standardized documentation, to assess existing space utilization

More information

Approve a project to construct the Sports Performance Center

Approve a project to construct the Sports Performance Center Facilities Committee Michael S. Molina Vice Chancellor - Facilities Planning & Construction December 10-11, 2015 Texas Tech University Item 1 Approve a project to construct the Sports Performance Center

More information

Northern Branch Jail Project

Northern Branch Jail Project BUDGET & FULL-TIME EQUIVALENTS SUMMARY & BUDGET PROGRAMS CHART Operating $ 24,071,489 Capital $ - FTEs - Northern Branch Jail Team (General Services and Sheriff's Office) Northern Branch Jail Project (AB900)

More information

Campus Planning Committee September 25, :00-4:00 p.m. Minutes

Campus Planning Committee September 25, :00-4:00 p.m. Minutes Campus Planning Committee September 25, 2012 2:00-4:00 p.m. Minutes Members Present: Todd Lee, John Foran, Gene Lucas, Kum-Kum Bhavnani, Marc Fisher, Jan Frodesen, Melvin Oliver, Rod Alferness, Beverly

More information

TABLE 4A UNIVERSITY OF CALIFORNIA

TABLE 4A UNIVERSITY OF CALIFORNIA PROJECT: Institute for Geophysics and Planetary Physics - Unit 2 Net-New Research in the Building $1,115,199 $1,171,000 $1,230,000 Project Related Rate Increase Recovery $89,977 $94,000 $99,000 TOTAL INCREASE

More information

University of California, Riverside

University of California, Riverside Capital Asset Strategies UNIVERSITY OF CALIFORNIA, RIVERSIDE 1223 University Ave Suite 240 Riverside CA 92507 University of California, Riverside Request for Qualifications (RFQ) for Developer and Project

More information

Prepared by the Office of the Treasurer

Prepared by the Office of the Treasurer Prepared by the Office of the Treasurer 0 February 24, 2015 Agenda 1. Budget Principles & Model 2. Operating Budget Highlights 3. Enrollment & Housing 4. Investments & Reserves Overview 5. Debt & Capital

More information

June 10, VIA & U.S. MAIL

June 10, VIA  & U.S. MAIL UNIVERSITY OF CALIFORNIA OFFICE OF THE GENERAL COUNSEL 1111 FRANKLIN STREET, 8th FLOOR OAKLAND, CALIFORNIA 94607-5200 (510) 987-9800 FAX (510) 987-9757 Writer's direct line: (510) 987-9744 E-mail: stephen.morrell@ucop.edu

More information

Highlights financial report. June 30 June (in thousands)

Highlights financial report. June 30 June (in thousands) Highlights FINANCIAL (in thousands) June 30 June 30 2000 1999 Total revenues $1,680,943 $1,367,175 Total cash gifts and equipment gifts $220,642 $211,215 Capital expenditures $118,799 $94,896 Total assets

More information

California Institute of Technology Financial Statements For the Years Ended September 30, 2013 and 2012

California Institute of Technology Financial Statements For the Years Ended September 30, 2013 and 2012 Financial Statements For the Years Ended Index to the Financial Statements For the Years Ended Page(s) Independent Auditor s Report 1 Balance Sheets 2 Statements of Activities 3 Statements of Cash Flows

More information

Management s Discussion and Analysis. Statement of Net Assets. Statement of Revenues, Expenses and Changes in Net Assets. Statement of Cash Flows

Management s Discussion and Analysis. Statement of Net Assets. Statement of Revenues, Expenses and Changes in Net Assets. Statement of Cash Flows 2 0 0 6 f i n a n c i a l r e p o r t UC DAV I S 2 0 0 6 FINANCIAL REPORT TA B LE OF CONTENT S Management s Discussion and Analysis 2 Statement of Net Assets 14 Statement of Revenues, Expenses and Changes

More information

UNIVERSITY OF CALIFORNIA, BERKELEY. Annual Financial Report

UNIVERSITY OF CALIFORNIA, BERKELEY. Annual Financial Report UNIVERSITY OF CALIFORNIA, BERKELEY Annual Financial Report 2008-09 TABLE OF CONTENTS Management's Discussion and Analysis 1 Financial Statements: Statements of Net Assets at June 30, 2009 and 2008 11 Statements

More information

University of Maine System Supplementary Requirements to AIA Document B Standard Form of Agreement Between Owner and Architect

University of Maine System Supplementary Requirements to AIA Document B Standard Form of Agreement Between Owner and Architect APPENDIX A University of Maine System Supplementary Requirements to AIA Document B102 2007 Standard Form of Agreement Between Owner and Architect NOTE: B102 2007 AS MODIFIED WITH UNIVERSITY OF MAINE SYSTEM

More information

F 2 STANDING COMMITTEES. Finance and Asset Management Committee. Capital and Debt Update INFORMATION ITEM

F 2 STANDING COMMITTEES. Finance and Asset Management Committee. Capital and Debt Update INFORMATION ITEM STANDING COMMITTEES F 2 Finance and Asset Management Committee Capital and Debt Update INFORMATION ITEM This item is being presented for information only. BACKGROUND This is a standing agenda item. The

More information

Finance, Capital, and Resources Committee September 13, 2018 Item # EXECUTIVE SUMMARY Page 1 of 7

Finance, Capital, and Resources Committee September 13, 2018 Item # EXECUTIVE SUMMARY Page 1 of 7 EXECUTIVE SUMMARY Page 1 of 7 Item Name: Capital Development Plan (NAU) Action Item Committee Recommendation to Full Board First Read of Proposed Policy Change Information or Discussion Item Issue: Northern

More information

Deferred Maintenance and Renewal Program Briefing

Deferred Maintenance and Renewal Program Briefing Deferred Maintenance and Renewal Program Briefing Business and Finance December 2007 1 Briefing Overview Nature of the challenge How we compare Progress to date Remaining barriers What s next? 2 Context

More information

ACTION ITEM APPROVAL OF UNIVERSITY OF CALIFORNIA BUDGET FOR CURRENT OPERATIONS AND AND BUDGETS FOR STATE CAPITAL IMPROVEMENTS

ACTION ITEM APPROVAL OF UNIVERSITY OF CALIFORNIA BUDGET FOR CURRENT OPERATIONS AND AND BUDGETS FOR STATE CAPITAL IMPROVEMENTS F6 Office of the President TO MEMBERS OF THE COMMITTEE ON FINANCE: For Meeting of ACTION ITEM APPROVAL OF UNIVERSITY OF CALIFORNIA 2014-15 BUDGET FOR CURRENT OPERATIONS AND 2013-14 AND 2014-15 BUDGETS

More information

SAMPLE PRIVATE USE ANALYSIS. UW Sample Building

SAMPLE PRIVATE USE ANALYSIS. UW Sample Building 1 SAMPLE PRIVATE USE ANALYSIS UW Sample Building 2 UW Sample Building Project The UW Building is a 4-story research facility located in UW Medicine s South Lake Union campus. It was developed by a 501(c)(3)

More information

150 E. Eighth Street Claremont, CA AUDITED FINANCIAL STATEMENTS FOR THE YEAR ENDED JUNE 30, 2016

150 E. Eighth Street Claremont, CA AUDITED FINANCIAL STATEMENTS FOR THE YEAR ENDED JUNE 30, 2016 150 E. Eighth Street Claremont, CA 91711 AUDITED FINANCIAL STATEMENTS FOR THE YEAR ENDED JUNE 30, 2016 Financial Statements (With Independent Auditors Report Thereon) KPMG LLP Suite 700 20 Pacifica Irvine,

More information

STATE OF NORTH CAROLINA

STATE OF NORTH CAROLINA STATE OF NORTH CAROLINA WESTERN CAROLINA UNIVERSITY CULLOWHEE, NORTH CAROLINA FINANCIAL STATEMENT AUDIT REPORT FOR THE YEAR ENDED JUNE 30, 2006 OFFICE OF THE STATE AUDITOR LESLIE W. MERRITT, JR., CPA,

More information

ARKANSAS DEPARTMENT OF HIGHER EDUCATION ADHE 17-1 SUMMARY OF INCOME FOR ALL FUND GROUPS (SEE INSTRUCTIONS)

ARKANSAS DEPARTMENT OF HIGHER EDUCATION ADHE 17-1 SUMMARY OF INCOME FOR ALL FUND GROUPS (SEE INSTRUCTIONS) ADHE 17-1 SUMMARY OF INCOME FOR ALL FUND GROUPS FICE CODE 1104 COMPLETED BY: Stan Sullivant INSTITUTION DATE COMPLETED: September 13, 2013 FISCAL YEAR 2013 TELEPHONE NO. 870-816-1274 INCOME (and other

More information

Original Revision Total Project Budget: $14,530,000 $47,700,000 $62,230,000 District Funding Commitment Anticipated State Match: $14,530,000 $N/A

Original Revision Total Project Budget: $14,530,000 $47,700,000 $62,230,000 District Funding Commitment Anticipated State Match: $14,530,000 $N/A Page 1 of 14 FACILITIES PLAN STATUS REPORT April 30, 2018 CAPITAL IMPROVEMENT PLANNING The decision to design and construct capital improvement projects begins with the Education and Facilities Master

More information

California Institute of Technology Financial Statements For the Years Ended September 30, 2011 and 2010

California Institute of Technology Financial Statements For the Years Ended September 30, 2011 and 2010 Financial Statements For the Years Ended Index to the Financial Statements For the Years Ended Page(s) Report of Independent Auditors 1 Balance Sheets 2 Statements of Activities 3 Statements of Cash Flows

More information

BRANDEIS UNIVERSITY. Financial Statements. June 30, 2013 (with summarized comparative information for June 30, 2012)

BRANDEIS UNIVERSITY. Financial Statements. June 30, 2013 (with summarized comparative information for June 30, 2012) Financial Statements (with summarized comparative information for June 30, 2012) (With Independent Auditors Report Thereon) KPMG LLP Two Financial Center 60 South Street Boston, MA 02111 Independent Auditors

More information