Accelerated Bridge Construction Decision Making Process 2010

Similar documents
HRTPO TTAC RECOMMENDATIONS ON THE HB2 PRIORITIZATION PROCESS

Research: Research and Technology Transfer Office Sept. 1, 1996-Dec. 31, 1996 P.O. Box 5080

GLOSSARY. At-Grade Crossing: Intersection of two roadways or a highway and a railroad at the same grade.

PennDOT Rapid Bridge Replacement Project

State of Ohio. Department of Transportation ~ Innovative Contracting Manual

House Bill 20 Implementation. House Select Committee on Transportation Planning Tuesday, August 30, 2016, 1:00 P.M. Capitol Extension E2.

ALL Counties. ALL Districts

Cost-effectiveness of protection measures to mitigate terrorist attacks on bridges and tunnels

2045 Long Range Transportation

DEPARTMENT OF TRANSPORTATION STATE OF GEORGIA TIA PROJECT CONCEPT REPORT

Corridors of Commerce DRAFT Scoring and Prioritization Process. Patrick Weidemann Director of Capital Planning and Programming November 1, 2017

CHAPTER 5 INVESTMENT PLAN

I-64 Capacity Improvements Segment III Initial Financial Plan

Texas Department of Transportation Corpus Christi District

TESTIMONY. The Texas Transportation Challenge. Testimony Before the Study Commission on Transportation Financing

UNIFIED TRANSPORTATION PROGRAM

Form DOT F (8-72) 7. Author(s) Thomas L. Glenn. 10. Work Unit No. (TRAIS) 16. Abstract

Improving Bridge Risk and Deterioration Modeling

Emergency Relief Program. Ammon Heier, FHWA ER Coordinator

SOUTH CENTRAL PLANNING AND DEVELOPMENT COMMISSION. Scope of Services. Terrebonne Parish

Appendix A Decision Support Analysis

EXCELLENCE INNOVATION SERVICE VALUE

BCE Guidance. Advanced Wastewater Treatment Plant. Version 1.0

Financial Snapshot October 2014

CHAPTER 3: GROWTH OF THE REGION

Texas Department of Transportation 1

Introduction to Risk for Project Controls

Asset Inventory and Valuation. A sset Inventory

Concept Development Activity Descriptions July, 2017

Safety Target Meeting Summary 10/3/2017

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1113 VALUE ENGINEERING IN CONSTRUCTION. October 19, 2012

Economic Impacts of Road Project Timing Shifts in Sarasota County

Minimum Elements of a Local Comprehensive Plan

OHIO MPO & LARGE CITY CAPITAL PROGRAM SFY 2017 SUMMARY

Draft Environmental Impact Statement. Appendix G Economic Analysis Report

Estimating the Construction Cost Associated with Accelerated Bridge Construction

CENTRAL CITY LINE PROJECT UPDATE AND SMALL STARTS EVALUATION & RATINGS APPLICATION UPDATED & REVISED 4/20/17

Contents. Alamo Area Metropolitan Planning Organization. Introduction S. St. Mary s Street San Antonio, Texas 78205

GOLDEN EARS BRIDGE. Alternative Transportation Financing ITE Quad Conference - May Fred Cummings Vice-President, Major Construction Projects

Simsbury. Challenges Capitol Region Natural Hazards Mitigation Plan Update - Page 356

Climate Change Adaptation A Study in Risk Management. T.D. Hall AAC Conference, Halifax Session 8 September 2015

Financial. Snapshot An appendix to the Citizen s Guide to Transportation Funding in Missouri

7:00 p.m th Avenue North COUNCIL WORK SESSION AGENDA #37

FY 2011 Continuing Appropriations Act. TIGER Discretionary Grant Program

Georgia Department of Audits and Accounts Performance Audit Division

Receive and file capital works report CW providing an update on the Burloak grade separation.

US 69 Hurricane Evacuation Corridor Improvements

Volusia County Floodplain Management Plan 2012

STUDY SCHEDULE STUDY PURPOSE

32 nd Street Corridor Improvements

TIGER IV. Benefit Cost Analysis. Minot International Airport Access Road. Minot, ND

Mn/DOT Scoping Process Narrative

MEETING MINUTES SUMMARY

VALUE FOR MONEY ASSESSMENT HIGHWAY 407 EAST PHASE 1 PROJECT

Keep Wisconsin Moving Smart Investments Measurable Results

THE CORPORATION OF THE CITY OF WINDSOR POLICY

Strengthening Vermont s Economy by Integrating Transportation and Smart Growth Policy

Governor Harry W. Nice Memorial Bridge Improvement Project. Charles County Commissioners Presentation September 1, 2009

Setting Standards for Sustainable Development Update and Review of the World Bank s Safeguard Policies Case Studies in Indonesia

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

Transportation Economics and Decision Making. Lecture-11

The Cost of Pavement Ownership (Not Your Father s LCCA!)

1. Introduction 2. Aim & Research question 3. Method 4. Theory/Background 5. Case 6. Conclusion 7. Questions & other considerations

GUIDELINE ACTIVITY RISK MANAGEMENT GUIDELINE

PAYING OUR WAY: A NEW FRAMEWORK FOR TRANSPORTATION FINANCE

2040 Long Range Transportation Plan. Financial Summary

Examples of Decision Support Using Pavement Management Data

Chapter 8: Lifecycle Planning

WECC Criterion TPL-001-WECC-CRT-3.1

TABLE OF CONTENTS/EXECUTIVE SUMMARY

Planned Special Events: Its role in the Economy and the tools of Cost Management and Cost Recovery

Prioritization and Programming Process. NCDOT Division of Planning and Programming November 16, 2016

OHIO MPO AND LARGE CITY CAPITAL PROGRAM SFY 2015 SUMMARY

WASATCH FRONT REGIONAL TRANSPORTATION PLAN FINANCIAL PLAN. Technical Report 47 May 2007 DAVIS MORGAN SALT LAKE TOOELE WEBER

Attachment B. Project Cost Estimates. Ridge Road Extension Alternatives Analysis

Ian McKay Chair Transmission Expansion Planning and Policy Committee (204)

MONROE COUNTY 2015 LMS STEP TWO: CHARACTERIZATION FORM

LOCAL MAJOR BRIDGE PROGRAM

Texas Department of Transportation Page 1 of 42 Planning and Development of Transportation Projects

MassDOT Highway ACEC State Markets Conference April 5, Jonathan Gulliver, Highway Administrator John J. Bechard, P.E., Deputy Chief Engineer

Tampa Bay Express Planning Level Traffic and Revenue (T&R) Study

Life-Cycle Cost Analysis: A Practitioner s Approach

Impacts of 2017 Wildfires on Cariboo Chilcotin Coast Tourism Businesses

Investor Presentation. August 2016

ENVIRONMENTAL ASSESSMENT ACT SECTION 9 NOTICE OF APPROVAL TO PROCEED WITH THE UNDERTAKING

SOUTHERN BELTWAY US-22 TO I-79 PROJECT 2013 FINANCIAL PLAN. Pennsylvania Turnpike Commission Allegheny and Washington Counties, Pennsylvania

TXDOT CONGESTION RELIEF INITIATIVE, INCLUDING

Interested Parties William E. Hamilton Transportation Needs and Revenue Distribution

REQUEST FOR QUALIFICATIONS Engineering Services for Aerial Sewer Line Construction Project SOUTH GRANVILLE WATER AND SEWER AUTHORITY October 31, 2018

Military Highway Continuous Flow Intersection (CFI) Initial Financial Plan

1. Introduction 2. Model Formulation 3. Solution Approach 4. Case Study and Findings 5. On-going Research

Implementing Risk Appetite for Variable Annuities

Construction Mitigation Management

Prepared by the South East Texas Regional Planning Commission-Metropolitan Planning Organization (SETRPC-MPO) December 6, 2013

SEPTEMBER 2018 DULLES CORRIDOR ENTERPRISE REPORT OF THE FINANCIAL ADVISORS

Environmental Analysis, Chapter 4 Consequences, and Mitigation

A new highly predictive FICO Score for an uncertain world

Role of Disaster Insurance in Improving Resilience: An Expert Meeting The Resilient America Roundtable

City of Portsmouth Portsmouth, New Hampshire Department of Public Works

2016 CDM Smith All Rights Reserved July 2016 SECTION SAFETY, HEALTH, AND EMERGENCY RESPONSE

Transcription:

Accelerated Bridge Construction Decision Making Process 2010 Introduction In the past, the Department used an Accelerated Bridge Construction (ABC) Decision Chart during project scoping to determine if ABC was appropriate for the site. This chart was based on the Federal Highway Administration Manual entitled Decision-Making Framework for Prefabricated Bridge Elements and Systems (PBES), May 2006. This process was based on a set of questions regarding specific constraints of each project. If certain thresholds were met, ABC was recommended. A new approach has been developed for the decision-making process for accelerated bridge construction. This guide outlines the approach to the new process and how it is used during project development. A spreadsheet has been developed to assist project planners in the implementation of this new process. Approach ABC is standard practice for project delivery, efficiency and fast construction. The Department has recently adopted themes that are now used as the basis of all projects in Utah. The themes are as follows: Accelerate Delivery Design and Construction Decrease and Minimize MOT (Reduce user costs associated with delays) Encourage Innovation Get a good price ABC can be used as a tool for the incorporation of these themes. In an effort to make the ABC decision making process more in line with these themes, the Department has developed a new process. The previous chart was based on a series of go/no-go decisions. In reality, many of these decisions are more measured. A definitive answer on whether or not to use ABC based on individual factors is not always appropriate. In the past, one project factor out of the eleven selected factors could drive the decision process. The new approach involves measured responses to each factor. The individual factors are weighted in order to be consistent with the Department themes. The weighted factors are then used to calculate an ABC rating, which is used to provide direction on the use of ABC for the project. If the Department policies and direction change in the future, the weighting factors can be adjusted to coincide with the changes. The result of this new approach is that a bridge with one significant control factor may actually rate lower than a bridge with several moderate control factors. This approach will not change the decision-making process outcomes for projects that are on the outlying boundaries of the controls. Bridges where ABC was an Page 1

obvious choice before will remain as such. Conversely, bridges where ABC was not appropriate before will also remain as such. This new process will be helpful for bridges between these extremes where the use of ABC is in question. ABC Measures Eight measures of project constraints have been identified as being applicable to the ABC decision process. The following is a brief description of each measure and how they apply to the current Department themes: Average daily traffic: This is a measure of the amount of traffic traversing the bridge site. Use a value equal to the total number of vehicles on the bridge and on the roadway under the bridge (if applicable). The value of maintaining the interstate highway network is accounted for in this measure by assigning the maximum score for this situation. This measure addresses the Department theme of Decrease and Minimize MOT. Delay/Detour time: This is a measure of the time impact that a project has on vehicles passing through the construction site. Account for the construction time delays due to detours and congestion caused by construction. If delays are anticipated for both the roadway on and under the bridge, enter the worst case scenario. This measure addresses the Department theme of Decrease and Minimize MOT. Bridge classification: This measure is used to account for bridges that are on or over a designated evacuation route or part of a critical lifeline route that will be used in an emergency such as a major earthquake. Accelerated bridge construction can be used to minimize time of impact for these important roadways. This measure addresses the Department themes of Decrease and Minimize MOT and Accelerate Delivery. User costs: This is a measure of the financial impact of a construction project on the traveling public. The major contributing factors in calculating user costs are the delay time and ADT, but the duration of the impact to users is the key component in measuring the encumbrance to the traveling public. The Department has instituted standard methods for calculating user costs. Calculate the user costs in coordination with the Structures Division Project Manager and the TOC and determine the total project cost for each construction option that is being evaluated (SPMT bridge move, prefabricated elements, conventional construction, etc.). This measure addresses the Department themes of Decrease and Minimize MOT, Get a Good Price and Encourage Innovation. Economy of scale: This measure accounts for the repetition of the elements and processes, and how they relate to the overall cost of a project, as well as the possible savings to future projects. The total number of spans is used in order to account for Page 2

repetition of substructure elements as well as superstructure elements. This measure addresses the Department theme of Get a Good Price. Use of typical details: This is a measure of the potential to make use of Department typical details that have been developed for ABC. Most bridges can be successfully built using ABC; however there are instances where the complexity of the bridge geometry makes use of typical details impractical and costly. Contact the Structures Division Project Manager to evaluate the bridge site and determine the level of complexity as it relates to various ABC techniques. The use of typical details will lead to more repetition of elements, faster construction times, higher quality, and reduced prices. This measure addresses the Department themes of Get a Good Price and Accelerate Delivery. Safety: This is a measure of the relative safety provided to the traveling public and the work force at the construction site. Accelerated bridge construction and the use of prefabricated elements will reduce the exposure time of travelers and workers to these dangerous environments. Project sites that require complex MOT schemes for extended periods of time are undesirable. The goal of ABC is to minimize this exposure to both the traveling public and the workers on site. This measure addresses the Department themes of Decrease and Minimize MOT and Accelerate Delivery. Environmental issues: This is a measure of the project s impact to the surrounding environment. The presence of endangered species or annual spawning seasons can lead to short construction windows. In other cases, projects may have limitations due to wetlands, air quality, extreme weather or noise. Accelerated bridge construction may be necessary to accomplish an acceptable level of impact on the surrounding environment. This measure does not specifically address a department theme and is not a weighted factor; rather, it is included in the ABC Decision Flowchart to evaluate if ABC can provide appropriate mitigation to an environmental commitment or requirement. Railroad impacts: This is a measure of the impact of the project on railroad traffic. The number of trains and type of train are used to measure this impact. This measure addresses the Department themes of Decrease and Minimize MOT and Accelerate Delivery. The ABC measures described above have been incorporated into an ABC Rating Procedure to help determine where the use of ABC is appropriate. This procedure is described on the next page. The range of scores to be used with the ABC Decision Flowchart has been set to ensure that accelerated construction will be commonplace when the measured benefit is more significant than the measured cost with respect to accomplishing Department themes and project goals. Page 3

ABC Rating Procedure This procedure has been developed to calculate an ABC rating score that accounts for all of the project measures defined in the previous section (except environmental issues). Weighting factors have been assigned to each measure to coincide with the current Department themes. Do not change the weighting factors for individual projects. The values assigned to each project decision measure are multiplied by the corresponding weight factor. The weighted values are then totaled and divided by the maximum possible score for each measure. The rating scores have been categorized into three ranges. Each of the three rating ranges lead to a different entry point on the corresponding ABC Decision Flowchart. Use the ABC rating score to enter the flowchart and work toward a conclusion. ABC Decision Flowchart The ABC Rating Procedure is the first step in the determination of whether accelerated bridge construction is appropriate for each project. The ABC Decision Flowchart uses the ABC rating score and then addresses yes/no factors that need to be considered prior to making a final decision on construction approach. These factors include project schedule, environmental issues, total project cost, site conditions and high-level indirect costs such as political capital, safety or possible impacts to stakeholders. Together, the ABC Rating Procedure and ABC Decision Flowchart can be used to make a final determination on the appropriate construction methods for each project. The following pages depict the ABC Rating Procedure and the ABC Decision Flowchart. Page 4

Utah Department of Transportation Project: Hypothetical Bridge Project 4501 South 2700 West By: MPC Checked: BLB Salt Lake City, UT 84114 Date: 8/30/2010 8/30/2010 Sheet. 1 of 3 ABC Rating Procedure June 2010 Enter values for each aspect of the project. Attach applicable supporting data. Average Daily Traffic 5 0 traffic impacts Combined on and under 1 Less than 5000 Enter 5 for Interstate Highways 2 5000 to 10000 3 10000 to 15000 4 15000 to 20000 5 More than 20000 Delay/Detour Time 2 0 delays 1 Less than 5 minutes 2 5-10 minutes 3 10-15 minutes 4 15-20 minutes 5 More than 20 minutes Bridge Classification 1 1 rmal Bridge 3 Essential Bridge 5 Critical Bridge User Costs 4 0 user costs 1 Less than $10,000 2 $10,000 to $50,000 3 $50,000 to $75,000 4 $75,000 to $100,000 5 More than $100,000 Economy of Scale 2 0 1 span (total number of spans) 1 2 to 3 spans 2 4 to 5 spans 3 More than 5 spans Use of Typical Details 1 1 Complex geometry or unfavorable site conditions 3 Some complexity, but favorable site conditions 5 Simple geometry and favorable site conditions Safety 5 1 Short duration impact with simple MOT scheme 2 Short duration impact with multiple traffic shifts 3 rmal duration impact with multiple traffic shifts 4 Extended duration impact with multiple traffic shifts 5 Extended duration impact with complex MOT scheme Railroad Impacts 0 0 railroad or minor railroad spur 3 One mainline railroad track 5 Multiple mainline railroad tracks

Utah Department of Transportation Project: Hypothetical Bridge Project 4501 South 2700 West By: MPC Checked: BLB Salt Lake City, UT 84114 Date: 8/30/2010 8/30/2010 Sheet. 2 of 3 ABC Rating Procedure June 2010 te: Do not adjust weight factors without prior consultation with UDOT Structures Division Project Manager ABC RATING SCORE FACTORS AND WEIGHTS Weight Adjusted Maximum Adjusted Score Factor Score Score Score Average Daily Traffic 5 10 50 5 50 Delay/Detour Time 2 10 20 5 50 Bridge Classification 1 5 5 5 25 User Costs 4 10 40 5 50 Economy of Scale 2 3 6 3 9 Use of Typical Details 1 3 3 5 15 Safety 5 10 50 5 50 Railroad Impacts 0 5 0 5 25 Total Score 174 Max. Score 274 ABC Rating Score: 64 Cost Considerations: Calculate the following costs for use in determining the lowest total project cost TOTAL PROJECT COST EVALUATION Alternative #1 Alternative #2 Construction Costs User Costs Total Project Cost $2,500,000 $1,000,000 $3,500,000 $3,000,000 $250,000 $3,250,000

Utah Department of Transportation Project: Hypothetical Bridge Project 4501 South 2700 West By: MPC Checked: BLB Salt Lake City, UT 84114 Date: 8/30/2010 8/30/2010 Sheet. 3 of 3 ABC Decision Flowchart June 2010 * Region Director or Project Development Director to evaluate possible indirect benefits ABC Rating 0 to 20 ABC Rating 20 to 40 ABC Rating 40+ Can project delivery be accelerated with ABC? Does ABC mitigate a critical environmental issue? Director Decision* Does ABC provide the lowest total project cost? Do the existing site conditions support an ABC approach? Use Traditional Construction Develop an ABC approach that accomplishes project goals