Project Status Report Timeline and Budget Project Update Next Steps Key Project Dates 3
Project Timeline Go Live October 15 Implementation Phase Gate November 15 Moved to December 20 Postponed until all high-impact issues have been resolved 4
Budget Budget covers all direct project costs through implementation and close-out, plus hardware & software maintenance through the Warranty Period Required an additional $288K of costs for North Highland through February 28 Will end up with a $813K positive variance plus an additional $100-200K potential savings 5
Budget & EAC Summary Ove rall Proje ct Budge t & Estimate d Variance Rebaselined Budget Allocated Contingency & Management Reserves Supplemental Budget Requests REA Grant Updated Project Budget Estimate at Completion Project Variance Project Funding OPS 217,770 0 0 0 217,770 296,427 (78,657) Expenses 7,240,310 75,908 0 0 7,316,218 7,143,276 172,941 OCO (Hardware) 1,441,425 (905,527) 0 0 535,898 389,808 146,089 Contracted Services Project Management & Support Project Management Office 2,019,270 0 0 0 2,019,270 1,960,700 58,570 Project & Operational Support 3,694,500 (1,420,155) 648,850 119,474 3,042,669 2,882,542 160,127 Outside Legal 230,652 0 0 0 230,652 228,960 1,692 ITN Development 512,700 0 0 0 512,700 512,700 0 Business Transition 3,945,916 99,201 0 134,730 4,179,847 4,446,418 (266,572) Other Contracted Services 164,790 3,030,676 0 0 3,195,466 3,064,895 130,571 Total Project Management & Support 10,567,828 1,709,721 648,850 254,204 13,180,603 13,096,215 84,387 IV&V Services 2,019,940 0 0 0 2,019,940 2,024,565 (4,625) Benefits Realization Strategy 239,391 1,915 0 0 241,306 239,391 1,915 Organizational Change Management 467,520 8,383 0 0 475,903 467,520 8,383 System Integrator (SI) Services 28,285,557 2,936,990 761,925 1,054,586 33,039,059 32,719,377 319,682 SI Hardware & Software 9,095,608 (726,739) 0 0 8,368,869 8,328,827 40,042 Project Reserves 122,695 0 0 0 122,695 0 122,695 Project Funding Totals 59,698,044 3,100,651 1,410,775 1,308,790 65,518,259 64,705,407 812,852 Contingency/Management Reserves 3,100,651 0.00 697,460 <- Geographic Solutions, WF Integration PM Total Project Funding 62,798,694 2,006,250 & Misc. Deloitte CRs 6
Budget Tracking Project Funding - Cumulative by Quarter 70,000,000 60,000,000 50,000,000 Budgeted: $65,518,259 Forecast: 64,705,407 Variance: $ 812,852 40,000,000 30,000,000 20,000,000 10,000,000 0 FY11 Q1 FY11 Q2 FY11 Q3 FY11 Q4 FY12 Q1 FY12 Q2 FY12 Q3 FY12 Q4 FY13 Q1 FY13 Q2 FY13 Q3 FY13 Q4 FY14 Q1 FY14 Q2 FY14 Q3 FY14 Q4 FY 15 Q1 FY 15 Q2 Budget Forecast Committed 7
Current Status CONNECT is improving every day CONNECT has taken and paid claims every day since implementation Since Go Live, CONNECT has taken 1.6M claims, and paid out $443M to over 228,000 Claimants 8
Adjudication Metrics As of this week, there are less than 5,000 individuals with at least one week on hold pending adjudication and the active caseload is being processed at record levels This number represents a caseload far below what had been normal in the legacy system 9
Adjudication Metrics The decrease in the active caseload is a result of multiple factors: system fixes, DEOimplemented workarounds, increased staff productivity, and increased staff The active cases are not a backlog of cases, as there is always an active adjudication caseload because the RA system is designed to flag and investigate claims with potential eligibility issues 10
9,000 Adjudication Metrics Adjudication Performance Daily Determination Productivity 8,000 7,000 6,000 5,000 4,000 3,000 2,000 1,000-2-Dec 9-Dec 16-Dec 23-Dec 30-Dec 6-Jan 13-Jan 20-Jan 27-Jan 3-Feb 10-Feb 17-Feb Determinations Linear (Determinations) 11
Adjudication Metrics Processing more Issues than we are receiving 9,000 Issues Created v. Determined 8,000 7,000 6,000 Daily Caseload Reduction 5,000 4,000 3,000 2,000 1,000-1-Jan 8-Jan 15-Jan 22-Jan 29-Jan 5-Feb 12-Feb 19-Feb Determinations Total Issues Created 12
Claimants Issues 70,000 60,000 50,000 Adjudication Metrics Near Zero Pending Initial and Continued Caseload Claimants Awaiting Adjudication for Payment 65,127 57,097 58,229 48,692 140,000 120,000 100,000 40,000 80,000 30,000 60,000 20,000 40,000 10,000 5,663 20,000-10/15 12/11 12/30 1/16 2/21 Claimants with Issues Holding Payment Issues Holding Payment - 13
Call Volume Contact Center Metrics Call Volume Dramatically Decreased 1,400,000 Total Incoming Calls 1,200,000 1,000,000 800,000 600,000 400,000 200,000-8/31/2013 9/30/2013 10/31/2013 11/30/2013 12/31/2013 1/31/2014 14
Contract Center Metrics Handling All Calls Multiple Touches 140,000 Unique Incoming Telephone #s v. Interactions 120,000 100,000 80,000 60,000 40,000 20,000-8/31/2013 9/30/2013 10/31/2013 11/30/2013 12/31/2013 1/31/2014 Distinct Offered Total Handled 15
Other Operational Stats Appeals and other business units continue to stay up with open caseloads Due to decreased call volume, the Contact Center is no longer open on Sundays And we will continue to align hours to expected claimant services demand 16
Technical Issues There have been, and will be, one-off technical and data conversion errors that are tracked and resolved through warranty maintenance 17
Continuing Claimant Issues Have a special team in place to aggressively resolve any claimant payment delays due to technical issues These tend to be data conversions related Most claimant technical issues are resolved within 24 hours of detection 18
Claimant Communications As Claimant issues are identified and resolved, an aggressive outreach program continues in place to reach affected Claimants, including: Individual calls to known claimants And as needed going forward: Posting of FAQs to social media and DEO s website Robocalls Emails IVR Messaging 19
Recent Contract Activity The Implementation Phase Gate (acceptance of the system) was postponed from November 15 until December 20 On December 20, DEO documented 102 (ultimately 133) operational gaps (High- Impact Issues) to be addressed 20
Recent Contract Activity There are currently 4 open high-impact issues that have been addressed by Deloitte and DEO is carefully reviewing those to determine if they can be closed or are no longer highimpact 21
Questions? 22
Agenda Introduction Meeting Minutes Approval Project Status Report Other Business Public Comments Review of Actions from Meeting Scheduling of Next Meeting March 12 Adjourn 23
Attachments FY13/14 + Spend Plan Graph FY13/14 + Spend Plan Details 24
Millions FY13/14 + Spend Plan Graph 30 FY 2013-2014 + Project Funding - Cumulative by Month to End of Warranty Period 25 20 Budgeted: $ 25,067,802 Forecast: 24,254,949 Variance: $ 812,853 } KPI payments 15 10 5 Warranty Period Begins 0 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 FY Budget Forecast Committed 25
FY13/14 + Spend Plan Details FY 2013-2014+ Budget Allocation and Spend by Month - Q1 & Q2 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Budget Committed Budget Committed Budget Committed Budget Committed Budget Committed Budget Committed OPS Funding 3,800 14,735 3,800 16,427 3,800 13,832 3,800 17,853 3,800 5,680 3,800 2,135 Expenses Funding 66,284 65,174 139,584 229,373 129,865 110,892 66,865 64,307 67,104 47,666 132,104 48,218 OCO Funding 0 0 0 0 0 0 0 0 0 0 0 0 Contracted Services Project Management & Support 226,279 311,553 184,029 281,447 184,029 305,031 184,029 348,881 196,704 140,845 184,029 1,000,363 IV&V Services 77,762 44,206 0 2,750 46,456 44,206 0 75,512 0 2,750 46,456 1,250 Benefits Realization Strategy 0 11,385 0 8,415 0 12,375 0 3,960 0 0 0 0 Organizational Change Management 0 0 0 0 0 0 0 0 0 0 0 0 System Integrator (SI) Services 4,039,600 4,015,719 0 742,667 0 3,237,664 2,725,233 0 2,480,471 0 203,628 203,628 SI Hardware & Maintenance 0 0 0 0 0 8,188 0 0 0 0 0 0 SI Software & Maintenance 0 0 0 0 0 93,636 0 0 0 0 0 0 Project Reserves 0 0 0 0 0 0 0 0 0 0 0 0 Total Contracted Services 4,343,641 4,382,863 184,029 1,035,279 230,485 3,701,099 2,909,262 428,353 2,677,175 143,595 434,113 1,205,241 Total Budget Allocation & Spend 4,413,725 4,462,772 327,413 1,281,079 364,149 3,825,823 2,979,927 510,513 2,748,078 196,942 570,016 1,255,595 26
FY13/14 + Spend Plan Details FY 2013-2014+ Budget Allocation and Spend by Month - Q3 & Q4 Jan-14 Feb-14 Mar-14 Apr-14 May-14 Jun-14 to Dec-14 Budget Committed Budget Forecast Budget Forecast Budget Forecast Budget Forecast Budget Forecast OPS Funding 3,800 1,517 2,600 1,000 1,000 0 2,600 0 0 0 0 0 Expenses Funding 66,911 80,793 58,473 59,354 34,049 34,930 34,049 34,930 21,500 21,500 107,500 107,500 OCO Funding 0 0 0 0 0 0 0 0 0 0 0 0 Contracted Services Project Management & Support 184,029 1,007,569 16,000 152,901 16,000 191,703 16,000 118,805 0 223,824 0 453,689 IV&V Services 0 0 0 0 0 0 0 0 0 0 0 0 Benefits Realization Strategy 0 8,580 0 0 0 0 0 0 0 0 0 0 Organizational Change Management 0 0 0 0 0 0 0 0 0 0 0 0 System Integrator (SI) Services 203,628 203,628 203,628 6,157,677 203,628 964,365 203,628 708,283 203,628 817,991 3,712,292 1,353,417 SI Hardware & Maintenance 0 0 0 0 0 0 0 0 0 0 0 0 SI Software & Maintenance 0 0 0 23,508 0 0 0 0 0 0 0 0 Project Reserves 0 0 0 0 0 0 0 0 0 0 0 0 Total Contracted Services 387,657 1,219,777 219,628 6,334,086 219,628 1,156,068 219,628 827,088 203,628 1,041,815 3,712,292 1,807,106 Total Budget Allocation & Spend 458,368 1,302,086 280,701 6,394,440 254,677 1,190,999 256,277 862,018 225,128 1,063,315 3,819,792 1,914,606 27