What is PBC and how it can help deal with the challenges of reducing NRW?

Similar documents
Designing a PBC for NRW reduction

WATERLOSS EUROPE SEPTEMBER COPENHAGEN FINANCING WATER LOSS MANAGEMENT : FINANCING SCHEMES

Performance-based contract financing options Pristina, 7 October, IFC Advisory Services in Public-Private Partnerships

Mbombela Water Indaba : April 2012

Performance Based Contracts in Non- Revenue Water Reduction Programs March Session 4: What is a PBC?

Non-Revenue Water Pre-Feasibility Assessment Tool

BEST PRACTICE 3: System Water Loss Control Overview Why a Best Practice? State Planning Requirements

Water Loss Control Tools. Software Tools for Supply Side Efficiency

Water Research Foundation 4372a

The Importance of Real Loss Component Analysis for Determining the Correct Intervention Strategy

NON REVENUE WATER INTERNATIONAL BEST PRACTICE FOR ASSESSMENT, MONITORING AND CONTROL

A FINANCIAL TURNAROUND STRATEGY FOR PUBLIC WATER AND SANITATION UTILITIES N A Macleod

Use of Operating Contracts for Managing Infrastructure Enterprises under Difficult Conditions. Office of Infrastructure and Engineering USAID

RATE STUDY. Town of Midland. HEMSON C o n s u l t i n g L t d.

Introduction. to restructure procedures and practices in a manner most appropriate for sustained NRW Control. ABSTRACT

Looking at various aspects of leakage calculations

JCI Energy Savings Performance Contract (ESPC) Services AMI System & Water Meter Replacements Water System SCADA Upgrades Acoustic Leak Survey August

MITIGATING THE IMPACT OF THE FINANCIAL CRISIS ON THE URBAN POOR USING RESULTS-BASED FINANCING SUCH AS OUTPUT-BASED AID FOR SLUM UPGRADING

Economic Level of Leakage (ELL)

360 CMR (2005)

Village of Carol Stream

Performance Audit: Department of Watershed Management Efforts to Reduce Water Loss

Understanding Public-Private Partnerships in Infrastructure

Plenary 2: Public-Private Partnerships. Monday, 12:00 to 13:00

Office of Utilities Regulation REGULATORY FRAMEWORK FOR THE NATIONAL WATER COMMISSION ( )

CASE STUDIES IN PRIVATE SECTOR PARTICIPATION: WATER SUPPLY SERVICES

Private sector participation in WATSAN services

CITY OF WATERLOO Water & Sanitary Sewer Rate Design Study Final Report & Financial Plan No

FINANCIAL ANALYSIS. A. Introduction

NARUC. Summer Committee Meetings. Committee On Gas

The challenge & solution of Sustainable Cost Recovery

Proposed Draft. Annexes DRAFT UNECE STANDARD ON PPPS IN WATER SUPPLY AND SANITATION. Water Supply and Sanitation Project Team

1. Risk of regularizing illegal connections

New Financing Trends Impact on Tunnelling Contracts

Accounting For Loss Water & Revenues

An Introduction to Strategic Water Loss Reduction

INCENTIVES & TARGETS KEY FEATURES OF SUCCESSFUL OPERATING CONTRACTS

WATER ASSET MANAGEMENT PLAN

ECONOMIC ANALYSIS. A. Introduction and Macroeconomic Context

Pipeline Regulatory Issues

EAP Task Force. EAP Task

DRM : EnergyNorth Natural Gas, Inc. dlbla Liberty Utilities Comments on Proposed Changes to Puc 500 Rules for Gas Service

MINISTRY OF FINANCE AND ECONOMIC AFFAIRS

ACHIEVEMENT OF TECHNICAL ASSISTANCE OUTCOMES

Improve Operational and Financial Performance of the PUC s

Water Research Foundation 4372a. Real Loss Component Analysis: A Tool for Economic Water Loss Control

YOUR WATER METER. 1 Your water meter

WATER. Approved.

Utility Rate Public Hearing City Council Meeting

DEPARTMENT OF PUBLIC WORKS UTILITIES

Establishment of a Self- Sustaining Environmental Investment Service in the East Asian Seas Region

Public Private Partnerships

Recipe for Developing a Winning M&V Formula in Indian ESCO Projects: Balancing Rigor and Accuracy with Cost-Effectiveness and Practicality

WATER Operations in EASTERN EUROPE. Athens European Week. Jean-Patrice POIRIER November 22, 2013

BOARD OF DIRECTORS TERMS OF REFERENCE

Performance-Based Ratemaking

Reducing Non-Revenue Water: Actions to Reduce Real Losses and Improve Customer Satisfaction. June 21, 2016

BALANCED CONCESSIONS FOR THE AIRPORT INDUSTRY DELIVERING WIN-WIN OUTCOMES FOR SUCCESSFUL AIRPORT CONCESSION CONTRACTS

AMP2016. i t r i g e s t. c o w w w. p u b l i c s e c t o r d i g e s t. c o m. The 2016 Asset Management Plan for the Township of Hamilton

Guidelines For Rajasthan Infrastructure Project Development Fund (RIPDF)

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. Advantages of PPP

Public-Private Private partnerships for Urban Water Utilities in Developing Countries: A Review of Experiences in Developing Countries

Billing/Leak Adjustments Policy

Financing the Transport Infrastructure Priority Projects on the Future Trans- Mediterranean Transport Network (TMT-N):

RISK MANAGEMENT OF WEST SEMARANG WATER SUPPLY PPP PROJECT: PUBLIC SECTOR PERSPECTIVE

Status of the Liberian Power Sector & Future Plans. EG Team/Liberia December 15, 2008

Public Private Partnerships IFC s Global Experience

A. These rules and regulations are promulgated pursuant to the authority conferred by R.I. Gen. Laws

Framing and Focussing Resource Efficiency: EU Research & Innovation Policy (CSF) Horizon 2020 Hungary, 28 June 2010

TERMS OF REFERENCE FEASIBILITY STUDY FOR ENVIRONMENTAL TRUST FUND

Lima, May Prepared by Marc Robinson

Toronto Water Budget BU Recommended Operating Budget Recommended Capital Plan 2017 Recommended Water Rate

Building Systems and Performance: an Introduction to Building Operator Certification Lesson 19: Energy Audits

SIL and Functional Safety some lessons we still have to learn.

THE NARRAGANSETT ELECTRIC COMPANY TERMS AND CONDITIONS FOR DISTRIBUTION SERVICE

Stormwater System Asset Management Plan. June 2018

International Monetary and Financial Committee

LAKE WATER COMPANY, LLC AUG A WYOMING LIMITED LIABILITY COMPANY P0 BOX 453 WHEATLAND, WY Voo

Chapter 2 Department of Supply and Services Public-Private Partnership: Eleanor W. Graham Middle School and Moncton North School

This is a sample of the instructor materials for The Core Elements of Value in Healthcare, by Paveljit S. Bindra.

Water in the Green Economy in Practice Session 3: Sustainable Financing. Maria Angelica Sotomayor Senior Economist World Bank

Participant s Guide. Energy efficiency programs: Feasibility studies Implementation incentives BUSINESS CUSTOMERS

WRF Webcast. A Snapshot of Water Loss: Examining the Country s Water Audit Submissions

CONSISTENCY OF REPORTING PERFORMANCE MEASURES REPORTING GUIDANCE - LEAKAGE

Utilities - Water and Sewer Funds

Wholesale water charges scheme 2018/2019 Page 1 of 39

MMP212 PROPERTY INVESTMENT

FRAMEWORK FINANCING AGREEMENT (SRI: Colombo Water and Wastewater Management Improvement Investment Program)

HAMILTON CITY COUNCIL BYLAWS

Request for Decision. Water Wastewater 2018 Budget - Business Cases Funding Report. Relationship to the Strategic Plan / Health Impact Assessment

WATER AND SEWER RATE STUDY

Three waters A GIS-BASED METHOD FOR SUPPORTING OPERATIONAL EVENTS MANAGEMENT IN WATER SUPPLY SYSTEM

PART R RADON. Sec. R.2 - Definitions. As used in Part R, these terms have the definitions set forth below:

Picture to be changed

COLOMBIA Barranquilla Airport SUMMARY OVERVIEW SUMMARY LESSONS LEARNED BARRANQUILLA AIRPORT. Location Barranquilla, Colombia

Acquisition of Wachs Valve and Hydrant Services LLC

NAFOP CONTRIBUTION TO THE CONSULTATION PAPER

FINANCIAL ANALYSIS. Table 1: Project Outputs Output Subcomponents Type of Analysis Enshi Wastewater Enshi Hongmiao WWTP Enshi Dashaba WWTP

WATER SERVICE TARIFF RATES, TERMS AND CONDITIONS FOR WATER SERVICE WITHIN MARION COUNTY, INDIANA. Issued By The

July 9, 2014 Thurston, Grays Harbor and Mason County Community Meeting with PUD Commissioners. PUD Cost of Service Presentation

Transcription:

Joint DWP ARA Regional Workshop on Performance Based Contracting for Non-Revenue Water Reduction What is PBC and how it can help deal with the challenges of reducing NRW? Bambos Charalambous World Bank Consultant Bucharest February 12, 2018

Business as Usual 1

N R W Result of Business as Usual High Passive Approach NRW Increases with Time Low 0 NRW= Water supplied in to a system but does not produce revenue 0 TIME - Years 2

A Vicious NRW Cycle NRW Increases Low willingness to Pay Inefficient Operations Customer Dissatisfaction Low Investments Poor Service 3 The Challenge: How to turn the vicious cycle into virtuous cycle

N R W Moving away from Business as Usual High NRW increases with Time Passive Approach Business as Usual HIGH NRW NON-REVENUE WATER MANAGEMENT LONG TERM STRATEGIC ACTION PLAN Low 0 LOW NRW ECONOMIC NRW 0 TIME - Years 4

The Centrality of Water Loss Management 5 Source: McCormack, 2005

Water Losses in a Supply System 6

NRW Constituent Components System Input Volume Authorized Consumption Water Losses Billed Authorized Consumption Unbilled Authorized Consumption Commercial Losses Physical Losses Revenue Water Non Revenue Water 7

Non Revenue Water Key Message REDUCTION IN: Unbilled Authorized Consumption will generate more revenues Commercial Losses will generate more revenues Physical Losses will: result in more water being available for consumption or reduction in operating costs delay the need for investments in source development 8

Steps towards NRW Sustainability Recognize the importance and centrality of NRW including its relation with operation efficiency and asset management Commitment at all levels in NRW reduction program Establish and operationalize cross-departmental NRW unit Strategic and business planning, with realistic phasing and target setting Improvement in the operational efficiency of the utility based on a long term NRW strategy Measurable efforts in NRW reduction Validated base lining, water audits and target setting linked to priority investments of network Structure long term performance-based PPP contracts to reduce NRW to accelerate NRW reduction and capacity building process 9

Why Performance Based Contracting? Despite huge investments by utility companies, IFIs and donors, most of the presently applied NRW reduction measures are often not effective in the medium to long term Technical assistance projects anchored within the utilities rigid, bureaucratic institutional framework, have low impact on efficiency and sustainable improvement of service delivery A paradigm change is needed, concentrating on delivering sustainable results based on performance and being output oriented 10

What are the Key Features of a PBC? Defines desired outputs and outcomes within a given time frame Links the achievement of set targets to relevant remuneration Focuses on results and thus provides the contractor with some flexibility on deciding how it will achieve its targets, it is not prescriptive Applies to a wide variety of services and contracts 11

Increasing operator s responsibilities and /or increasing value creation for the client PBCs: Applicable in a wide variety of services and contracts Consulting engineering Technical assistance Misc. services CONSULTING Management contract Lease / affermage contract DBO contract O&M contract Concession contract BOT contract PUBLIC-PRIVATE PARTNERSHIP Privatization ASSET OWNERSHIP Legend: Service contracts Infrastructure contracts Source: Suez Environmental Increasing operator s time commitment and / or conducive context for PPP 12

Key Features that differentiate PBCs (from more Traditional Service Contracts) Increased value for money Performance risk lies with the contractor and full remuneration is contingent upon verifiable performance improvements Greater flexibility for the contractor Decides on measures to undertake to achieve targets, applying innovation and creative solutions Increased emphasis on accountability The contractor s remuneration is tied to verifiable progress visà-vis its targets Support to long-term improvements Efficiency gains through a PBC can help support long-term improvements 13

PBCs have the potential to be more efficient contracts (than the traditional, input-based contracts) While the contractor is required to take more risks, it has also more incentives to deliver tangible results For the water utility, a well-designed PBC is less risky since it will pay the full price of the contract only if targeted performance improvements are achieved Contractor comes for limited time to carry out additional tasks not done by the utility does not have an effect on utility staffing (No staff layoffs) A well-designed PBC is a Win-Win solution for both the utility and the contractor 14

NRW Reduction using PBC Performance Based Contracts between water utilities and private contractors can be focused on reducing: physical losses, commercial losses, or both 15

Typical reduction activities relating to the Water Losses are the following: Treatment works, trunk mains and reservoirs: SCADA installation, leak detection and repair, pipe / valve replacement, pressure management Distribution System: Establishment of District Metered Areas, pressure management, measurement and monitoring system, data recording and transfer, leak detection and repair, pipe and service connection replacement, removal of illegal connections Meters: Customer surveys, removal of illegal connections, meter installation, calibration, rehabilitation, replacement Billing: Meter reader training, improved customer accounting, internal auditing Collections: Controlled procedures and accountability 16

NRW Reduction using PBC Commercial Losses Principally involves improving the metering accuracy and water sales accounting and typically includes the following components: Surveys to identify missing or unmetered connections Installation, replacing, repairing or recalibrating water meters Improvement of water meter reading and data transfer to customer accounting systems, using handheld meter reading devices or Automatic Metering Reading (AMR) methods, meter reader training, changing meter locations to reduce the frequency of unread meters and estimated sales Improving customer data base and accounting systems Institutional support for a period of time and training of utility staff 17

NRW Reduction using PBC Physical Losses 18 Contracts focused on reducing physical water losses, typically include the following components: Establishing District Metered Areas (DMAs), which isolates water supply to a small sub-set of the utility s customers, improving water inflow and pressure measurement and facilitating leakage detection Leak detection and repair Pressure management Replacing service connections Replacing leaking pipes, valves, hydrants, etc. Maintenance of water savings achieved for a period of time Training of utility staff

Designing the contract and incentives framework:.the devil is in the detail. Achieving efficient incentives is dependent on factors including: Ring Fencing interface between the contractor and utility s operations needs to be carefully considered Remuneration/Risk striking a proper balance between fixed and variable payment, fair sharing of risk NRW indicators are used a good baseline is critical Contractual targets / performance need to strike a balance between being achievable (i.e. realistic) and sufficiently ambitious Level of flexibility left to the contractor allow the contractor some flexibility in achieving the overall goal Sustainability ensuring that the gains achieved can be made sustainable, substantial operating period after the NRW reduction to sustain the gains of efficiency There is no blueprint: well designed PBCs are heavily customized contractual PPP instruments 19

Ring Fencing The interface between the contractor and utility s operations needs to be carefully analyzed and appropriate steps taken to separate them: Network sectorization: how many? Which size? Divide the city network between the utility and the private partner How the utility staff will operate in areas where the private partner is carrying out NRW activities? Even with good ring-fencing, the outcome will still usually depend upon the collaboration of the utility s staff Capacity building is needed so that they fully understand the contractual approach: Include training and knowledge transfer into the PBC contract The management and staff must understand the benefits for them and be willing to cooperate with private partner Mutual commitment is essential for success 20

A Good Baseline is Critical Any agreement to pay based on performance requires a good baseline to measure improvement against. The baseline must be acceptable to both parties to the contract. It should ideally be stated in units that tie directly to the performance objective. Thus, if the objective is to reduce water leakage then the baseline should be defined in units of water, e.g., cubic meters per day and should cover only the network under the control of the contractor. 21

Targets Are Important Setting targets are important to achieving minimum performance. Most contracts include minimum annual targets indicating their perceived usefulness. When projects are intended to reduce both physical and commercial losses, it makes sense to have targets for both, plus an overall target; but to allow the contractor some flexibility in achieving the overall goal. 22

Setting targets For incentives to work, performance targets need to strike a balance between being achievable (i.e. realistic) and sufficiently ambitious. They may also need some degree of flexibility, to adjust to unpredictable conditions A good understanding of the NRW situation is critical: Physical vs. Commercial losses (IWA water balance) Choosing the right NRW indicator: e.g. m3 reduction per day instead of % losses 23

Sustainability The challenge for a successful PBC : ensuring that the gains achieved can be made sustainable: Include a substantial operating period after the NRW reduction to sustain the gains of efficiency (normally 3-5 years) Knowledge transfer activities during the contract should be included Maintaining NRW level and even improving it after the contractor leaves is the foundation of sustainable management 24

Successful PBCs for NRW reduction have high financial return Typical cost for reducing physical losses is 500 700 Euros per m 3 saved per day. Much lower for commercial losses Project return depends inter alia on levels of O&M cost and tariff, relative proportion of physical vs commercial losses, and the efficiency of NRW reduction program Some indicative payback periods: O&M cost, tariff 1 0.5 0.35 0.2 Euro/m 3 Euro/m 3 Euro/m 3 Euro/m 3 Euro/m 3 Payback period 3-5 years 4-8 years 6-12 years 9-15 years 25

Thank You For your Attention!! Bambos Charalambous Fellow of the International Water Association Tel.: +357 99 612 109 Email: bcharalambous@cytanet.com.cy Website: www.hydrocontrolltd.com 26