CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

Similar documents
Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

UNIT-II Project Organization and Scheduling Project Element

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

Project Management Chapter 13

Textbook: pp Chapter 11: Project Management

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

CISC 322 Software Architecture

CHAPTER 9: PROJECT MANAGEMENT

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

1 of 14 4/27/2009 7:45 AM

Project Management Techniques (PMT)

Teori Pengambilan Keputusan. Week 12 Project Management

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

56:171 Operations Research Midterm Examination Solutions PART ONE

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015

06IP/IM74 OPERATIONS RESEARCH

CHAPTER 5 STOCHASTIC SCHEDULING

Project Management Fundamentals

Allocate and Level Project Resources

Real-World Project Management. Chapter 15

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

GPE engineering project management. Project Management in an Engineering Context

Chapter 11: PERT for Project Planning and Scheduling

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

After complete studying this chapter, You should be able to

Management Management

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

Profit Maximization and Strategic Management for Construction Projects

Appendix A Decision Support Analysis

IE 102 Spring Project Management

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

A SINGLE STEP CPM TIME-COST TRADEOFF ALGORITHM. In Mathematics and Computing. Under the guidance of Dr. Mahesh Kumar Sharma

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

An Application of Mathematical Model to Time-cost Trade off Problem (Case Study)

Handout 4: Deterministic Systems and the Shortest Path Problem

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

56:171 Operations Research Midterm Examination Solutions PART ONE

A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT

Time and Cost Optimization Techniques in Construction Project Management

CHAPTER 5. Project Scheduling Models

56:171 Operations Research Midterm Exam Solutions October 22, 1993

Project Management and Cost Control

Project Management -- Developing the Project Plan

Decision Support Tool for Project Time-Cost Trade-off

A Linear Programming Approach for Optimum Project Scheduling Taking Into Account Overhead Expenses and Tardiness Penalty Function

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD

PROJECT MANAGEMENT: PERT AMAT 167

Project Time-Cost Trade-Off

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

Chapter 2 The PERT/CPM Technique

A New Mathematical Model for Time Cost Trade-off. Problem with Budget Limitation Based on. Time Value of Money

WHY ARE PROJECTS ALWAYS LATE?

SWEN 256 Software Process & Project Management

COMPARATIVE STUDY OF TIME-COST OPTIMIZATION

Construction Management

Project planning and creating a WBS

Essays on Some Combinatorial Optimization Problems with Interval Data

Lecture 3 Project Scheduling

Comparison between Deterministic and Stochastic Time Estimating Techniques

Lecture 5: Project Management

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta

INTRODUCTION PROJECT MANAGEMENT

56:171 Operations Research Midterm Exam Solutions October 19, 1994

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

MODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

Research Methods Outline

56:171 Operations Research Midterm Exam Solutions Fall 1994

THE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION

International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN:

Indirect cost associated with project increases linearly with project duration. A typical line for indirect cost is shown in figure above.


56:171 Operations Research Midterm Examination October 28, 1997 PART ONE

56:171 Operations Research Midterm Examination October 25, 1991 PART ONE

VALLIAMMAI ENGINEERING COLLEGE

Project Management with Brief Information regarding CPM and PERT Methods

COST MANAGEMENT IN CONSTRUCTION PROJECTS WITH THE APPROACH OF COST-TIME BALANCING

u w 1.5 < 0 These two results imply that the utility function is concave.

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan

A new PDE-based approach for construction scheduling and resource allocation. Paul Gabet, Julien Nachef CE 291F Project Presentation Spring 2014

POLYTECHNIC OF NAMIBIA

Journal of Project Management

Line Balancing S K Mondal Chapter 3

Risk Video #1. Video 1 Recap

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

A STUDY OF THE BASIC CONCEPT OF CRASHING CPM NETWORK USING DERIVATIVE MARGINAL COST IN LINEAR PROGRAMMING

Homework solutions, Chapter 8

The Stochastic Time Cost Tradeoff Problem: A Robust Optimization Approach

Programme Evaluation and Review Technique

TUFTS UNIVERSITY DEPARTMENT OF CIVIL AND ENVIRONMENTAL ENGINEERING ES 152 ENGINEERING SYSTEMS Spring Lesson 16 Introduction to Game Theory

ETSF01: Software Engineering Process Economy and Quality

Transcription:

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM 6.1 Introduction Project Management is the process of planning, controlling and monitoring the activities associated with a large complex project. The success of any project is very much dependent upon the quality of planning, scheduling and controlling of the various phases of the project. Planning and controlling projects is of paramount importance in the success of any project, because it constitutes a major part in the project management life cycle. Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT) are very common and widely adopted project management tools. CPM does not provide a measure of uncertainty and it is developed under the condition of normal working on the project duration time. PERT is an aid to management in expending and controlling the resources to meet the scheduling completion date of the projects which involve high degree of uncertainty. The project represented by networks, the network consists of number of activities. These activities are represented in a network by arrows. These activities are clearly definable task to which a known quantity of resources. The activities are represented in two ways: the AOA (activity-on-arc) or AON (activity-on-node). Event is the junction of arrow(s). It represents that point of time when all activities ending at that point are done and all succeeding activities that begin at that point can start. It is represented by a circle. The interdependency of activities indicates relationship between different activities. For any project, the first event represents the starting point and the last event represents the completion point of a project. 6.2 Crashing Crashing refers to compression project activities which is the decreasing total project schedule duration. Crashing project duration take place after analyzing all possibility activities are crashed, resource availability and least addition cost. The objective of crashing a network is to determine the trade-off between optimal project duration and minimum project cost. Each phase of the crashing project duration design to consume resources hence cost is associated with it. The cost will vary according to the amount of time consumed by the design phase. An optimum

minimum cost project schedule implies lowest possible cost and the utilization of resources associated time for project management. 6.3 Literature Review PERT problem was developed by Naval Engineers of USA Navy in charge of Polaris sub-marine missile project in 1958. Euro working group on project management and scheduling was established to assess the state of art and to emulate progress in theory and practice. Steve and Dessouky (1977) described a procedure for solving the project time/cost trade-off problem of reducing project duration at a minimum cost. The solution to the time & cost problem is achieved by locating a minimal cut in a flow network derived from the original project network. Dobin (1984) also determined the most critical paths in PERT networks. Johnson and Schon (1990) used simulation to compare three rules for crashing stochastic networks. He also made use of criticality indices. Feng et al. (2000) presented a hybrid approach that combines simulation techniques with a genetic algorithm to solve the time-cost trade-off problem under uncertainty. Pulat and Horn (1996) described efficient project schedules for a range of project realization times and resource cost per time unit for each resource. The time-cost trade off technique is extended to solve the time-resource tradeoff problem. Kelfer and Verdini (1993) gives the expediting projects in PERT with stochastic time estimation. A detailed survey of resource constrained project scheduling has been given by Ozdamar and Ulusay (1995). Cho and Yum (1997) measured an uncertainty importance of activities in PERT network. Cho and Yam (1997) developed method for Uncertain Important Measure. It has been intended to explore some of the problems for crashing stochastic networks. Sevkina and Hulya (1998) tried to analyze on project management using primal-dual relationship. Rehab and Carr (1989) described the typical approach that construction planners take in performing time-cost Trade-off (TCT). Abbasi and Mukattash (2001) developed method for crashing PERT networks. Turnquist and Nozick (2004) developed a nonlinear programming optimization model of time and resource allocation decision in project with uncertainty. Suri and Bharat (2008) used simulation for optimization of software project and scheduling.

The project is completed when all tasks are completed. With deterministic task durations, the CPM methodology is used to determine the task start time, task finish time, and task slack time in order to find out the longest path in a project, the critical path. Also, with the help of CPM, managers can relocate resources to minimize the total project duration. The CPM methodology has its best performance when the task durations are deterministic. The PERT problem arises when task durations are modeled as random variables and the time becomes uncertain. Thus, the accuracy of the estimate of time becomes critical for the project. Therefore the time scheduling techniques are principally based upon networks analysis in CPM and PERT. In construction projects, scheduling and planning involves selection of proper methods, crew size, equipment s and technology to perform the task. The allocation of resources leads to problems like cost overrun or project delay. In general, there is a trade-off between the time and the cost to complete a task, less expensive the resources, the maximum duration to complete the activity. Each activity requires resources to allocate such a way that overall cost of the project minimum. 6.4 Problem Definition In the project management generally there is a specific date for the project completion. In order to complete the project in less than the normal time, the normal duration of the project must be reduced to the desired duration. The method of reducing the project duration by shortening time of one or more activities at a cost is called crashing. Network crashing developed in CPM for reducing duration of the project with the additional amount of money invested. It selects the lowest cost slope activities which will reduce the time in the critical path(s). The idea of crashing a project with resource constrained was not developed in PERT where probabilistic time was used. We have focused on the problem of crashing the project duration with resource constraint using PERT network. This objective of this research has two fold. First, develop a model to constructing a relationship between project duration and the cost i.e. time-cost tradeoff with resource constraint environment. Resources are available only in limited quantities and the resource demands of concurrent activities may not be satisfied. Second, network crashing is developed in CPM for reducing duration of the project with the additional amount of money invested. It selects the lowest cost slope activities which will reduce the time in the critical path(s). The idea of crashing

a project was not developed in PERT where probabilistic time was used. This research focuses on the problem of crashing the stochastic project duration using PERT network with resource constrained with additional amount of money invested in each activity. 6.5 Mathematical Formulation PERT is based on the concept that a project is divided into a number of activities which are arranged in some order according to the job requirement. A PERT network consists of a set of nodes and arcs, where a node represents the beginning or completion of one or more activities and an activity is represented by an arc (arrow) connecting two nodes-activity-on arrow (AOA) representation. PERT calculates the expected value of activity duration as an average of the three time estimations. It makes the assumption that the optimistic, most likely time and pessimistic activity times a, m and b respectively. So the average or expected time t e of an activity is determined from beta distribution. We have considered crashing of PERT network with resource constrained environment. A project consists of a set of activities which have to be processed. The activities are interrelated by two kinds of constraints. First, precedence constraints each activity can not to be started before all its immediate predecessor activities in the set have been finished. Second, performing the activities requires renewable resources with limited capacities. The activity durations are independent continuous random variables; preemption is not allowed. The objective of the problem is to crash the stochastic PERT network with renewable resources for finding minimum makespan of the project. PERT activity has three times estimation: optimistic (a), most likely (m), pessimistic (b). For commuting the expected duration of each activity the three times estimation assumes follow the beta distribution. The probability density function of a beta distribution for a random variable x is given by: F(x) = K(x-a) α (b-x) β a x b, α, β > -1

where, k is a constant which can be expressed in terms α and β. The expected time (mean time) t e is located at one third of the distance between most likely time and mid-range. So, the expected time t e of the activity will be: t e = (a + 4m + b)/6 (1) and standard deviation σ = {(b - a)/6} 2 (2) The formulas (1) and (2) are supposed to be valid for the variable t e that has a variety of distribution shapes. The project completion time can be reduced by reducing (crashing) the normal completion time of critical activities. The reducing normal time of compulsion will increase the cost of the project. However, decision maker always look for trade-off for the total cost of a project and the time required completing. It is easy to compute crash the activities and the completion time for the project with unlimited resource availability. In this research, we have developed a model for crashing stochastic PERT network with resource constrained conditions. The resources are defined for each activity. The mathematical model is: Min c i x j i = 1, 2,n Subject to x j x i t ij r t,k b k j A(t) k=1, 2,m x i = earliest even time of node i x j = earliest event time of node j t ij = time of activity i j c i = crashing cost r t,k is the resource demand of k th of activity i at the duration of t b k is the resource limit of the k th resource

m is the total number of resources type n is the total numbers of activities We have considered crashing the project activity with resource availability. The problem is defined with experimental models. 6.6 Experimental Model I The developed algorithm is evaluated using a large number of networks. A construction company wants to make a new commercial market complex and it has been contracted a time period of 300 days to complete which is a normal time period required to complete the project. The budget of the project is $7.25 million and some additional amount of money is available. But the management wants to finish before two weeks so as selling without any delay. Also, the management wants to spend some extra amount of money for the early completion of market complex. As the activities of this project are uncertain time duration and resource constrained, the project manager have constructed a PERT network model for planning and scheduling of the project with availability and the requirement of resources. But it is essential to complete the project around two weeks before the duration, so as to complete within their allotted time duration and satisfy the management. Table 34 shows the three time estimates of the activities of the project I: optimistic (a), most probable (m) and pessimistic times (b). Normal estimated durations and crashing durations are defined in table 35. In each activity requirement and availability resources are defined in table 36. Figure 18 shows the network model using activity on arrow diagram. As the activities of this project are uncertain time duration, the project manager has constructed a PERT network model for planning and scheduling of the project.

Table 34: Three time estimation of activity duration of the project I Activity No. a, m, b Activity No. a, m, b Activity No. a, m, b A1 16,18,25 A15 9,16,19 A29 16,18,23 A2 10,12,18 A16 12,14,16 A30 12,14,16 A3 12,14,18 A17 8,10,13 A31 3,7,19 A4 9,12,16 A18 10,15,18 A32 5,11,14 A5 5,8,18 A19 10,12,15 A33 6,10,16 A6 13,14,18 A20 7,13,16 A34 7,12,15 A7 12,13,15 A21 4,6,9 A35 18,20,25 A8 8,11,16 A22 9,12,16 A36 10,14,16 A9 10,12,17 A23 21,22,25 A37 9,12,16 A10 9,10,12 A24 8,12,14 A38 11,13,16 A11 8,13,17 A25 9,12,17 A39 16,19,24 A12 6,12,28 A26 15,17,20 A40 12,18,21 A13 12,15,17 A27 11,16,18 A14 5,7,11 A28 8,13,17 Table 35: Normal estimated duration and crash duration for project I Node Normal time Crash time Cost/unit crash ($) Node Normal time Crash time Cost/unit crash ($) 1 0 0 0 15 12.17 3.04 3500 2 18.83 4.71 6000 16 12.50 3.13 2000 3 12.67 3.17 4500 17 22.33 5.58 5000 4 14.33 3.58 5000 18 12.00 3.00 1500 5 12.17 3.04 4000 19 12.33 3.08 2000 6 13.17 3.29 3000 20 17.17 4.24 2500 7 12.50 3.13 3000 21 12.83 3.21 1500 8 14.50 3.63 3500 22 18.50 4.63 4000 9 12.84 3.21 3700 23 10.33 2.58 1000 10 14.83 3.71 4000 24 14.00 3.50 1700 11 10.17 2.54 2500 25 11.67 2.92 1500 12 13.67 3.42 3500 26 20.50 5.13 3700 13 14.67 3.67 4000 27 19.33 4.83 4000 14 15.33 3.83 5500 28 17.50 4.38 3500

Table 36: Resource availability and resource required for project I Nodes Resource required Resource availability Nodes Resource required Resource availability 1 0 0 15 35 30 2 34 30 16 34 30 3 35 30 17 32 30 4 32 30 18 24 30 5 34 30 19 43 20 6 25 30 20 24 40 7 32 20 21 35 20 8 35 30 22 24 30 9 35 30 23 35 20 10 24 30 24 33 30 11 23 20 25 34 30 12 35 20 26 34 30 13 43 30 27 34 30 14 36 40 28 34 30 A6 A10 A15 A19 A24 A25 A33 A4 A11 A16 A20 A26 A36 A37 A1 A2 A3 A12 A21 A27 A32 A35 A39 A40 A7 A5 A8 A13 A17 A22 A31 A34 A38 A9 A14 A18 A23 A28 A29 A30 Figure 19: Activity on Arrow (AOA) network for Project I Activity Event Event

Notation: i - Start event ' i' for an activity j - End event 'j' for an activity ES - Earliest Start time EF - Earliest Finish time LS - Latest Start time LF - Latest Finish time x i = earliest even time of node i x j = earliest event time of node j resave- resource availability for activity resreq- resource required for activity xrand- Random number Activity Cost Linear cost-time relationship Crash cost Normal cost Crash time Normal time Activity duration Figure 20: Linear time and cost trade-off for an activity

6.7 Proposed Algorithms for Crashing Stochastic PERT Networks with Resource Constrained (1) Input data for the project i.e. duration, cost, resource availability, resource requirement. (2) Calculate earliest time estimates for all the activities. ES j = max (ES i + duration i ) for all x j, j 1 (3) Calculate latest time estimates for all the activities. LS i = min ( LS j - duration) for all x i, i x j where i = n (4) Calculation of slack: slack i =LS i ES j for all x n (5) Initialization ES(1) = 0 (6) Calculation of early finish time: EF j EF i + duration j + ( duration j /resave j )*resf j - crash j (7) Resource reserved: resf j = resreq j - resava j for all x j (8) Generating the random number for unit cost for unit resource: xrand j = rand (resf j ) for all x j (9) Is early finish time is less than equal to due date then calculate minimum cost Min = sum ( ccost*crash*xrandom j *resf j ) Otherwise go to step 6 6.8 Computational Results of Experimental Model I The critical path of the project and the starting and finishing times of the individual activities, ES, EF, LS, LF are calculated. The project activities are schedule in resource constrained conditions. The project is crashed according to cost slope. The program is looking for the resources availability and cheeks each activity s resource requirement. If the required resource is more than the availability, the program delayed the activity to the following day. The process continued until the calculation of the finish time of the last activity. The lower bound of the project (critical path method) of the project without resource constrained condition is calculated. The project completion time without resource constrain is 251 days. The resource requirements for the project activities depend on the availability daily total resources. We have developed an algorithm which is coded in LINGO 11.0 software for crashing project network with activity duration and resource constrained condition. The program is tested on Pentium 4 CPU 2.53 GHz processor under the Windows 7 operating system. Additional amount of money is assigned for each activity for the project. The crashing time of each activity is

uniformly taken as 25% of the original duration. The optimal duration with resource constrained is obtained 294.15 days. The optimal duration obtained after crashing the network with resource constrained condition is 282 days with addition amount of money $ 58,884.92. The relative percentage of deviation from the original critical path (CPM) duration is calculated. The optimal solution of the model is evaluated in PERT network without resource constrained is 251 days. Relative deviation for the project is calculated by: RD (%) = (RCD - d) / d x 100 Where RD = relative deviation of resource constraint duration from CPM duration in percentage; RCD = resource constraint duration d = original CPM duration without resource constraint In this model relative deviation from CPM is calculated by using above formula. The relative deviation of resource constraint duration from original CPM is 17%. The relative deviation after crashing the project with resource constrained condition from original CPM is 12%. The objective of this model is to compute the minimum project completion duration with resource constrained condition. The optimal solution shows that duration increase 17% more with resource constrained condition from original CPM duration. 6.9 Experimental Model II Resource management is a most important part of project management and it involves the allocation of resources to the different activities that need timely completion of project. The most important resource that has to consider in information systems project is human resources that is, the trained professionals. The success or failure of projects largely depends on the peoples who working on the project. The job of the project manager is to efficiently assign resources so that the project team is working on time and complete the project in time. A project management team wants to develop an e-commerce project. It is expected that the project will finish a time period of 149 days in a normal time period. The budget of the project is $2.75 million and some additional amount of money is available. But the project manager wants to finish before 20 days because to lunch the e-commerce project early. The company wants spend some extra amount of money for the completion of the project early. As the activities are

uncertain and resource constrained, the project manager have construct PERT network for planning and scheduling the project with resource constrained. Table 37 shows the three time estimates of the activities of the project: optimistic (a), most probable (m) and pessimistic times (b). In each activity requirement and availability resources are defined in table 38. Table 39 shows the normal estimated duration and crash duration of the project. Figure 20 shows the network model using activity on arrow diagram. This is an experimental model for e-commerce project and objective is to decrease the time duration with resource constrained environment with some additional amount of money. S19 S20 S7 S11 S12 S22 S21 S2 S17 S18 S1 S4 S9 S10 S16 S15 S25 S26 S27 S3 S5 S8 S13 S14 S23 S24 S6 Activit Figure 21: Activity on arrow (AOA) for project II Event Event

Table 37: Three time estimation of activity duration of the project II Activity No. a, m, b Activity No. a, m, b S1 6,12,14 S15 15,18,22 S2 8,10,14 S16 14,18,20 S3 12,14,17 S17 11,15,17 S4 10,14,18 S18 9,12,16 S5 13,15,18 S19 10,15,19 S6 10,12,16 S20 7,11,14 S7 11,15,17 S21 9,13,16 S8 14,18,21 S22 10,14,18 S9 10,14,17 S23 14,18,20 S10 7,10,14 S24 12,16,20 S11 6,11,14 S25 8,12,16 S12 15,18,23 S26 15,19,21 S13 10,14,16 S27 17,19,23 S14 16,18,20 Table 38: Resource availability and resource required for project II Nodes Resource Resource Nodes Resource Resource required availability required availability 1 0 0 12 26 20 2 18 15 13 32 30 3 20 15 14 33 30 4 23 20 15 30 25 5 29 25 16 24 20 6 35 30 17 28 25 7 25 20 18 24 20 8 26 15 19 25 20 9 28 20 20 35 25 10 31 20 21 26 20 11 29 25

Node Normal Crash Cost/unit Node Normal Crash Cost/unit time time crash ($) time time crash ($) 1 0 0 0 12 12.17 3.04 425 2 11.33 2.85 450 13 18.33 4.58 350 3 14.17 3.54 400 14 13.67 3.42 275 4 10.33 2.58 425 15 14.83 3.71 325 5 15.17 3.79 350 16 10.83 2.71 300 6 12.33 3.08 300 17 12.00 3.42 400 7 14.67 3.67 375 18 13.67 4.50 375 8 13.85 3.47 300 19 18.00 4.00 425 9 10.67 2.67 425 20 16.00 4.83 450 10 10.17 2.54 400 21 19.33 3.21 375 11 12.83 3.21 375 Table 39: Normal estimated duration and crash duration for Project II 6.10 Computational Results of Experimental Model II The critical path of the project and the starting and finishing times of the individual activities, ES, EF, LS, LF are calculated. The project activities are schedule in resource constrained conditions. The project is crashed according to cost slope. The program is looking for the resources availability and cheeks each activity s resource requirement. If the required resource is more than the availability, the program delayed the activity to the following day. The process continued until the calculation of the finish time of the last activity. The lower bound of the project (critical path method) of the project without resource constrained condition is calculated. The optimal solution of the model is evaluated in PERT network without resource constrained is 148.68 days. The resource requirements for the project activities depend on the availability daily total resources. The project completion time with resource constrained is 192 days.

The developed algorithm is run in LINGO 11.0 software for crashing network with activity duration and resource constrained condition. Additional amount of money is assigned for each activity for the project. The crashing time of each activity is uniformly taken as 25% of the original duration. The algorithm runs 44 iterations with Pentium 4 processor. The optimal duration obtained for crashing the network with resource constrained is 176 days with addition amount of money $ 12451.23. The relative percentage of deviation from the original critical path (CPM) duration is calculated. The relative deviation of resource constraint project duration from original CPM is 29%. The relative deviation with crashing the project with resource constrained from original CPM is 18%. The objective of this model is to compute the minimum project completion duration with resource constrained condition with cashing the project with additional amount of money. The optimal solution shows that duration increase 29% more with resource constrained condition after cashing the network with additional amount of money $ 12451.23 from original CPM duration. 6.11 Summary and Conclusions The concept of crashing in PERT networks can be applied on several networks by investing additional amount of money and resources. The objective of this constructed model is to increase the realizing the last node by minimizing pessimistic time, which lead to decrease in project duration with resource constrained environment. This model is tested by investing addition amount of money with limited resources. In experimental model I, the completing time is reducing to 282 days after cashing the project with resource constrained condition. Moreover, the schedule time decreased from 294.15 to 282 days after crashing the project for the additional amount of money $ 58,884.92 with the availability of resources. The optimal solution shows that crashing duration increase 12% more with resource constrained condition. So it is not possible for the company to complete the project before 282 days with the availability of resources. In the experimental model II, the completing time is reducing to 176 days after cashing the project with resource constrained condition. Moreover, the schedule time decreased from 192 to 176 days after crashing the project for the additional amount of money $ 12451.23 with the availability of resources. The optimal solution shows that crashing duration increase 15% more

with resource constrained condition. So it is not possible for the company to complete the project before 176 days with the availability of resources. Comparing these two different types of project, experimental models shows that the crashing duration increase around 12-15% more in resource constrained condition with additional amount of money. This algorithm will help project planners to investigate crash duration and cost in resource constrained condition in PERT network