Implementation of the Integrated Road Map

Similar documents
Update on the Integrated Road Map: proposed interim governance arrangements

Update on the Integrated Road Map and on proposed interim governance arrangements

Biennial Programme of Work of the Executive Board ( )

Biennial programme of work of the Executive Board ( )

Biennial programme of work of the Executive Board ( )

Supplementary Table S1 National mitigation objectives included in INDCs from Jan to Jul. 2017

Senior Leadership Programme (SLP) CATA Commonwealth Association of Tax Administrators

GEF Evaluation Office MID-TERM REVIEW OF THE GEF RESOURCE ALLOCATION FRAMEWORK. Portfolio Analysis and Historical Allocations

Hundred and Sixty-seventh Session. Rome, May 2017

Update on the Financial Framework Review. Informal Consultation 25 July 2016

Biennial programme of work of the Executive Board ( )

PROGRESS REPORT NATIONAL STRATEGIES FOR THE DEVELOPMENT OF STATISTICS. May 2010 NSDS SUMMARY TABLE FOR IDA AND LOWER MIDDLE INCOME COUNTRIES

Biennial programme of work of the Executive Board ( )

Report on Countries That Are Candidates for Millennium Challenge Account Eligibility in Fiscal

E Distribution: GENERAL ORGANIZATIONAL AND PROCEDURAL MATTERS. Agenda item 11 BIENNIAL PROGRAMME OF WORK OF THE EXECUTIVE BOARD ( )

2019 Daily Prayer for Peace Country Cycle

Annex Supporting international mobility: calculating salaries

The Budget of the International Treaty. Financial Report The Core Administrative Budget

Argentina Bahamas Barbados Bermuda Bolivia Brazil British Virgin Islands Canada Cayman Islands Chile

IBRD/IDA and Blend Countries: Per Capita Incomes, Lending Eligibility, IDA Repayment Terms

Report to Donors Sponsored Delegates to the 12th Conference of the Parties Punta del Este, Uruguay 1-9 June 2015

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT BOARD OF GOVERNORS. Resolution No. 612

Hundred and Sixty-ninth Session. Rome, 6-10 November Status of Current Assessments and Arrears as at 30 June 2017

IBRD/IDA and Blend Countries: Per Capita Incomes, Lending Eligibility, and Repayment Terms

Hundred and Seventieth Session. Rome, May Status of Current Assessments and Arrears as at 31 December 2017

United Nations Environment Programme

Hundred and Seventy-fifth Session. Rome, March Status of Current Assessments and Arrears as at 31 December 2018

NSDS STATUS IN IDA AND LOWER MIDDLE INCOME COUNTRIES

TRENDS AND MARKERS Signatories to the United Nations Convention against Transnational Organised Crime

WGI Ranking for SA8000 System

COUNCIL. Hundred and Sixtieth Session. Rome, 3-7 December Status of Current Assessments and Arrears as at 26 November 2018 EXECUTIVE SUMMARY

2 Albania Algeria , Andorra

CLEAN TECHNOLOGY FUND ELIGIBILITY OF GUARANTEES FINANCED FROM THE CLEAN TECHNOLOGY FUND FOR SCORING AS OFFICIAL DEVELOPMENT ASSISTANCE

Background Note on Prospects for IDA to Become Financially Self-Sustaining

The State of the World s Macroeconomy

ShockwatchBulletin: Monitoring the impact of the euro zone crisis, China/India slow-down, and energy price shocks on lower-income countries

E Distribution: GENERAL ORGANIZATIONAL AND PROCEDURAL MATTERS. Agenda Item 10 BIENNIAL PROGRAMME OF WORK OF THE EXECUTIVE BOARD ( )

WILLIAMS MULLEN. U.S. Trade Preference Programs & Trade Agreements

ANNEX 2. The following 2016 per capita income guidelines apply for operational purposes:

EMBARGOED UNTIL GMT 1 AUGUST

SUN Movement Meeting of the Network of Country Focal Points: Report of the 16 th Meeting- 3 rd to 6 th of November 2014

ANNEX. to the. Report from the Commission to the European Parliament and the Council

Appendix 3 Official Debt Restructuring

April Food and. Agricultura. Organization of the United Nations. Hundred and Forty-fourth Session. Rome, May 2012

THE ADVISORY CENTRE ON WTO LAW

Country Documentation Finder

The world of CARE. 2 CARE Facts & Figures

Figure 1. Exposed Countries

Hundred and Fifty-third Session. Rome, May 2014

Annex A to DP/2017/39 17 October 2017 Annex A to the UNDP integrated resources plan and integrated budget estimates for

GPEI Financing

Annual Report on Exchange Arrangements and Exchange Restrictions 2011

Charting the Diffusion of Power Sector Reform in the Developing World Vivien Foster, Samantha Witte, Sudeshna Gosh Banerjee, Alejandro Moreno

Working Party on Export Credits and Credit Guarantees

Resolution adopted by the General Assembly on 24 December [on the report of the Fifth Committee (A/67/502/Add.1)]

COUNTRY DSA(US$) MAX RES RATE MAX TRV RATE EFFECTIVE DATE OF %

SURVEY TO DETERMINE THE PERCENTAGE OF NATIONAL REVENUE REPRESENTED BY CUSTOMS DUTIES INTRODUCTION

Africa: An Emerging World Region

FAQs The DFID Impact Fund (managed by CDC)

COUNCIL. Hundred and Fifty-sixth Session. Rome, April Status of Current Assessments and Arrears as at 17 April 2017.

UPDATE ON THE INTEGRATED ROAD MAP

COUNTRY DSA(US$) MAX RES RATE MAX TRV RATE EFFECTIVE DATE OF %

FIFTH SESSION OF THE GOVERNING BODY. Muscat, Oman, September 2013 RESOLUTION 13/2013 WORK PROGRAMME AND BUDGET FOR THE 2014/2015 BIENNIUM

RESOLUTION 14/2017 WORK PROGRAMME AND BUDGET

COUNTRY DSA(US$) MAX RES RATE MAX TRV RATE EFFECTIVE DATE OF %

ANNEX 2. The applicable maturity premiums for pricing groups A, B, C and D are set forth in Tables 2, 3, 4 and 5 below, respectively

COUNTRY DSA(US$) MAX RES RATE MAX TRV RATE EFFECTIVE DATE OF %

May 2018 FC 171/3. Hundred and Seventy-first Session. Rome, May Update on the Integrated Road Map

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT BOARD OF GOVERNORS. Resolution No General Capital Increase

Report of the Executive Director on the utilization of contributions and waivers of costs (General Rules XII.4 and XIII.4 (h))

Enabling long term. finance in local currency. Enabling Long Term. Local Currency

OP 3.10 Annex D - IBRD/IDA and Blend Countries: Per Capita. Incomes, Lending Eligibility, and Repayment Terms, July 2016, updated December 2016

HIPC HEAVILY INDEBTED POOR COUNTRIES INITIATIVE MDRI MULTILATERAL DEBT RELIEF INITIATIVE

Finexpo s action focuses on financing conditions for credits granted for the supply of equipment and services.

Biennial programme of work of the Executive Board ( )

STATISTICS ON EXTERNAL INDEBTEDNESS

Afghanistan $135 $608 $911 1 March Albania $144 $2,268 $3,402 1 January Angola $286 $5,148 $7,722 1 January 2003

Afghanistan $135 $608 $911 1 March Albania $144 $2,268 $3,402 1 January Algeria $208 $624 $936 1 March 1990

( Euro) Annual & Monthly Premium Rates. International Healthcare Plan. Geographic Areas. (effective 1st July 2007) Premium Discount

Report to the Board June 2017

Why Corrupt Governments May Receive More Foreign Aid

Kentucky Cabinet for Economic Development Office of Workforce, Community Development, and Research

UPDATE ON THE INTEGRATED ROAD MAP: PROPOSED INTERIM GOVERNANCE ARRANGEMENTS

Legal Indicators for Combining work, family and personal life

World Development Indicators

IMPENDING CHANGES. Subsistence Allowances

MDRI HIPC MULTILATERAL DEBT RELIEF INITIATIVE HEAVILY INDEBTED POOR COUNTRIES INITIATIVE GOAL GOAL

PARIS CLUB RECENT ACTIVITY

Scale of Assessment of Members' Contributions for 2008

1.1 LIST OF DAILY MAXIMUM AMOUNT PER COUNTRY WHICH IS DEEMED TO BEEN EXPENDED

Lessons learnt from 20 years of debt relief

MDRI HIPC. heavily indebted poor countries initiative. To provide additional support to HIPCs to reach the MDGs.

IBRD/IDA and Blend Countries: Per Capita Incomes, Lending Eligibility, and Repayment Terms

Convention on the Conservation of Migratory Species of Wild Animals

The Changing Wealth of Nations 2018

Food and. Agricultura. Organization of the United Nations COUNCIL. Hundred and Forty-fourth Session. Rome, June 2012

The world of CARE. CARE International Member Countries A Australia B Austria C Canada D Denmark. E France F Germany/Luxemburg G Japan H Netherlands

Statistics Luigi Scarpa de Masellis

The world of CARE. CARE International Member Countries A Australia B Austria C Canada D Denmark. E France F Germany/Luxemburg G Japan H Netherlands

Global Total Compensation Measurement (TCM ) 2012

Transcription:

Integrated Road Map Implementation of the Integrated Road Map 7 February 2018

2018 Informal Consultations 13 17 November 2017 Second Regular Session [Approval of Update on the Integrated Road Map: interim governance arrangements for 2018; Approval of CSPs and ICSPs] 7 March Informal Consultation Update on the Integrated Road Map; Proposed amendments to the General Rules and Financial Regulations Additional Informal Consultation: 7 February Implementation of the Integrated Road Map 3 May Informal Consultation Update on the Integrated Road Map; Proposed amendments to the General Rules and Financial Regulations 13 July Informal Consultation Update on the Integrated Road Map; Proposed amendments to the General Rules and Financial Regulations 29 31 May FAO Finance Committee 28 September Informal Consultation On CSPs and ICSPs (TBC) October TBC ACABQ 26 30 November Second Regular Session [Update on the Integrated Road Map: Amendments to the General Rules and Financial Regulations for approval; CSPs and ICSPs for approval] 16 January Informal Consultation On CSPs and ICSPs Honduras, Pakistan, Timor- Leste, Tunisia, Burundi Afghanistan, Bolivia, Egypt, Kenya, Philippines (concept notes) 26 28 February First Regular Session [CSPs and ICSPs for approval] May TBC ACABQ 11 April Informal Consultation On CSPs and ICSPs (TBC) 18 22 June Annual Session [Update on the Integrated Road Map: Proposed amendments to the General Rules and Financial Regulations; CSPs and ICSPs for approval] 6 September Informal Consultation Update on the Integrated Road Map; Proposed amendments to the General Rules and Financial Regulations 5 7 November FAO Finance Committee 5 October Informal Consultation On CSPs and ICSPs (TBC) 1

Agenda Integrated Road Map 1. Progress update Update on implementation Resource migration and cutover update Board s oversight of budget revisions, including crisis response Contributions received to date 2. Lessons learned: Focus on Sudan 3. Proposal for the CSP/ICSP review process 4. Open for discussion 5. Update on the CRF 6. Open for discussion 2

Agenda Integrated Road Map 1. Progress update Update on implementation Resource migration and cutover update Board s oversight of budget revisions, including crisis response Contributions received to date 2. Lessons learned: Focus on Sudan 3. Proposal for the CSP/ICSP review process 4. Open for discussion 5. Update on the CRF 6. Open for discussion 3

PROGRESS TO DATE and TRANSITION OUTLOOK Integrated Road Map 2017 2018 2019 12 live of 14 approved CSPs 11 ICSPs Core business of crisis response: Sudan ICSP (complex operation) Bangladesh CSP (Rohingya crisis) 1 January: 53 live T-ICSPs 37 CSPs 12 ICSPs 4 April: 2 live CSPs 1 ICSPs 1 July: 3 live CSPs 3 January: 11 live CSPs 7 ICSPs 3 T-ICSP 1 All 81 countries under the IRM framework 4 Total: 12 Total: 58 Total: 11 Resource Management Department

5 Integrated Road Map: Indicative Cutover Timeline 2017 2019 (as of 8 January 2018) CSPs Bangladesh China Colombia Ecuador El Salvador Indonesia Lao PDR Zimbabwe 2017 2018 Apr 2017 Jul 2017 8 CSPs Jordan Mozambique 3 T-ICSPs* Algeria Lesotho 37 Namibia Armenia Liberia Tanzania Benin Madagascar Bhutan Mali Bolivia Mauritania $170m (2%) Burkina Faso Morocco ICSP Cambodia Nepal 1 Côte d Ivoire Nicaragua Sudan Cuba Sao Tome Djibouti Senegal Dominican Sierra Leone Republic Swaziland $573m (6%) DPRK Syria Egypt Tajikistan Budget released Ghana The Gambia in system Guinea Togo 12 MAY 2017 Guinea-Bissau Turkey Haiti Zambia Iraq $2.7b (30%) $233m (3%) $403m (4%) $233m (3%) Budget released in system 1 MAR 2017 Estimated annual Programme of Work T-ICSP Budget released in system JUL MID-OCT 2017 Budget released in system AUG OCT 2017 Estimated Annual Programme of Work: US$9 billion (100%) APR & JUL 2017: 12 LIVE CSPs 12 Cameroon Guatemala Honduras Kyrgyzstan Lebanon Myanmar Pakistan Palestine Peru Sri Lanka Timor-Leste Uganda $0.9b (10%) TO DATE (JAN 2018): 65 LIVE Jan 2018 Apr 2018 Jul 2018 ICSPs 4 CAR DRC Iran South Sudan $1.3b (15%) $5.0b (55%) JAN 2018: 53 LIVE CSPs P Tunisia $1m (0%) ICSPs P Burundi $58m (1%) $59m (1%) Legend: P X $X (%) 1 1 CSPs 3 P Afghanistan P Kenya P Philippines $339m (4%) $339m (4%) Jan 2019 CSPs P Chad P Congo (Rep of) P Ethiopia India P Malawi P Nigeria P Rwanda $1.1b (13%) 2019 7 ICSP 3 P Libya P Somalia P Yemen $2.8b (31%) $1.5b (16%) T-ICSP P Niger $227m (2%) Anticipate 16 country offices will continue with the current framework from 1 January 2018. These country offices will work towards moving to the IRM framework by no later than January 2019.** Proposed to continue with projects from 1 January 2018; these country offices will work towards moving to the IRM framework by no later than January 2019 Number of countries Estimated annual Programme of Work of countries (and as percentage of total annual Programme of Work), based on the 2018 Programme of Work under the latest draft of the Management Plan (2018 2020) * Country offices implementing a T-ICSP will submit a CSP or ICSP to the Board for approval by no later than the 2019 Annual Session. ** Ukraine not included in the list of 16 countries as no CSP/ICSP is planned, but will also continue with the current framework from 1 January 2018. 1

Agenda Integrated Road Map 1. Progress update Update on implementation Resource migration and cutover update Board s oversight of budget revisions, including crisis response Contributions received to date 2. Lessons learned: Focus on Sudan 3. Proposal for the CSP/ICSP review process 4. Open for discussion 5. Update on the CRF 6. Open for discussion 6

Resource migration and cutover: Update on Wave 2 53 countries which commenced a CSP, ICSP or T-ICSP in January 2018 15% remaining USD 83,900,250 Grant balances 85% migrated USD 471,600,885 19% remaining* 53,925 MT Stock balances 81% migrated 224,733 MT Migrated To be migrated Migrated To be migrated Target for 15 January: 50% of USD value migrated 91% of the countries reached the target Target for 31 January: 80% of MT migrated 70% of the countries reached the target 7 Data as of 02/02/2018 11:02AM * Commodities not yet transferred are in transit.

Agenda Integrated Road Map 1. Progress update Update on implementation Resource migration and cutover update Board s oversight of budget revisions, including crisis response Contributions received to date 2. Lessons learned: Focus on Sudan 3. Proposal for the CSP/ICSP review process 4. Open for discussion 5. Update on the CRF 6. Open for discussion 8

Board s oversight of budget revisions, including crisis response Summary of work ongoing in revisions Approximately 12 T-ICSPs are working on extensions in time, which would be shared with the Board for approval by correspondence. Work is also ongoing on approximately 6 additional revisions to accommodate changes to requirements for emergencies or to reflect resources that had not been anticipated. While budgets are still being developed, most changes are anticipated to be small and within the Delegated Authority of the ED, in line with the interim delegation of authority approved by the Board. 9

Learnings identified thus far with respect to ongoing work on revisions and Delegations of Authority 1. Threshold for Board approval of revisions linked to root causes and resilience building (over 25% of CSP or USD 150 million) Without a minimum threshold, there may be a disproportionate impact on smaller CSPs. Example: A small revision of USD 85,000 for the Morocco T-ICSP is expected to require Board approval, as it accounts for more than 25% of the T-ICSP value. 2. Threshold for sharing crisis response revisions with Member States prior to approval (above 25% of the overall CSP budget or more than USD 150 million) The current threshold for sharing crisis-response-related revisions with the Member States for a comment period will include low-value revisions for small operations. Example: Approval of a small revision of USD 7 million for Zambia (which is well within the delegated authority to the Executive Director) may be delayed to accommodate the review process. 10

Agenda Integrated Road Map 1. Progress update Update on implementation Resource migration and cutover update Board s oversight of budget revisions, including crisis response Contributions received to date 2. Lessons learned: Focus on Sudan 3. Proposal for the CSP/ICSP review process 4. Open for discussion 5. Update on the CRF 6. Open for discussion 11

Contributions received to date (new) CSPs, ICSPs and T-ICSPs (as of 31 January 2018) In 2017 and 2018, 429 new grants totalling USD 2.0 billion have been confirmed to 54 countries, 90 percent of which were directed to the activity level. USD millions USD 2.0b 429 grants (2017-2018 total) 1,400 1,200 USD 1.3b 234 grants USD 1.5b 370 grants (2017 total) 1,000 800 600 400 200 USD 83m 69 grants USD 3m 2 grants USD 25m 18 grants USD 0.1m 2 grants USD 63m 49 grants USD 41m 15 grants USD 410m 40 grants USD 454m 59 grants (2018 total) 12 0 Country Level Strategic Result Level Strategic Outcome Level Activity Level 2017 NEW 2018 NEW TOTAL (NEW) 2017-2018

Agenda Integrated Road Map 1. Progress update Update on implementation Resource migration and cutover update Board s oversight of budget revisions, including crisis response Contributions received to date 2. Lessons learned: Focus on Sudan 3. Proposal for the CSP/ICSP review process 4. Open for discussion 5. Update on the CRF 6. Open for discussion 13

Lessons learned: Implementation of the IRM in Sudan With four Area Offices each the size of most Country Offices in WFP 16 Field Offices, and more than 1,100 staff, the pioneering of the Integrated Road Map framework in Sudan was recognised early on as critical to the success of WFP s global transformation. The approval of Sudan s Interim Country Strategic Plan in June 2017 represented the first approval of an ICSP in a complex setting to i. ensure that the organisation would benefit from lessons during the 2017 pilot phase; and ii. allow solutions to be adjusted where necessary. Sudan s US$600 million ICSP went live on 1 July 2017 with six Strategic Outcomes and 15 activities for a duration of 18 months (July 2017 December 2018). Sudan additionally adopted a dual structure approach, maintaining the PRRO alongside its ICSP. 14

Lessons learned: Implementation challenges identified by the Sudan Country Office I. Added complexity of the budgetary structure resulting in increased transactions across functions resulting in increased workload II. Limitations on flexibility resulting from transparency afforded by the budget structure due to increased levels of earmarking, as well as increased management of donor restrictions within activities III. Increased centralization of fund allocations, leading to operational level frustration at the field and delays in decision-making IV. Impact of the current and revised CRF on performance measurement V. Staffing, capacity, and reassignment issues 15

Lessons learned: Underlying causes and way forward A Underlying causes Organisational readiness, funds management and monitoring Way forward Adjustments to Sudan organizational structure Development of additional tools and guidance B Impact of donor earmarking Donor engagement strategy to ease earmarking, and move towards outcome-based funding over time C Complexity brought on by the vertical and horizontal fragmentation of the budget structure Cost structure management simplifications More streamlined CSP for Sudan 16 Sudan-specific actions Corporate solutions

Lessons learned: Underlying causes and way forward D Underlying causes Continued adoption of the dual structure approach Way forward Review potential of closing the PRRO by 30 June 2018 to end the dual structure E More robust, clear and coherent guidance from HQ Development of additional tools & guidance with alignment across HQ 17 Sudan-specific actions Corporate solutions

Lessons learned: Underlying causes and way forward F Underlying causes Impact of the current and revised CRF on performance management Way forward Progress on Corporate Results Framework G New internal processes leading to additional complexity Simplification of internal review processes Simplification of budget revision processes Review of budget revision authorities (2019) 18 Sudan-specific actions Corporate solutions

Cost structure refinements limited to level 4 & 5 only, respecting the four high level cost categories Level 1: High-level cost category NO IMPACT ON LEVELS 1, 2, 3 Level 2: Modality Level 3: Transfer value vs transfer cost Level 4: Roll-up of cost planning categories Level 5: Cost planning items Transfer Food Cash-based transfers (CBT) Transfer value Transfer cost Transfer value Transfer cost Food Other food-related costs Transport Storage Port Supply chain management costs Cooperating partner costs CBT and commodity vouchers Delivery costs CBT and commodity vouchers management costs Cooperating partner costs 19 Capacity strengthening Implementation Service delivery Adjusted direct support costs (DSC) (%) Indirect support costs (ISC) Capacity strengthening Cooperating partner costs Service delivery Cooperating partner costs Activity management costs Assessments costs Evaluation costs Monitoring costs WFP staff and staff-related costs Other adjusted DSC costs Assessments & evaluation costs Indirect support costs

Maximizing operational effectiveness with underlying principles of simplicity, flexibility, transparency, and accountability 1. Great strides achieved in transparency 2. Focus in 2018 i. Simplicity and flexibility to maximize internal efficiency within the Integrated Road Map ii. Refinements can be categorized into three areas of focus: Internal alignment and simplification, focused on maximizing efficiency [most] Donor alignment, focusing on impact of restrictions and move towards outcome-based funding [some] EB governance [less, but Board needs visibility on all] 20

Agenda Integrated Road Map 1. Progress update Update on implementation Resource migration and cutover update Board s oversight of budget revisions, including crisis response Contributions received to date 2. Lessons learned: Focus on Sudan 3. Proposal for the CSP/ICSP review process 4. Open for discussion 5. Update on the CRF 6. Open for discussion 21

Background: CSP/ICSP review process to date Nov 2016: CSP Policy introduced the 20 day electronic review process 2017 Wave 1A Wave 1B EB.2 2017 CSPs/ICSPs Jan 2017: Informal consultations on Wave 1A CSPs Feb 2017: EB approval of Wave 1A CSPs May 2017: Informal consultations on Wave 1B CSPs/ICSP June 2017: EB approval of Wave 1A CSPs Aug-Sep 2017: 20 day review process for CSPs/ICSPs to be submitted to EB.2/2017 4 Oct 2017: Informal consultations for CSPs/ICSPs to be submitted to EB.2/2017 Nov 2017: EB approval of CSPs and ICSPs 2018 Dec 2017: 20 day review process for CSPs/ICSPs to be submitted to EB.1/2018 16 Jan 2018: Trial Basis Informal consultations on Concept Notes for CSPs/ICSPs to be submitted to EB.A/2018 16 Jan 2018: Informal consultations for CSPs/ ICSPs to be submitted to EB.1/2018 Review process going forward to be discussed Feb 2018: EB approval of CSPs and ICSPs EB.1 2018 CSPs/ICSPs 22 Key: IC on Concept Notes on a trial basis Electronic review of CSP/ICSP IC on draft CSP/ICSP EB Approval

Current CSP/ICSP review process At the 16 January Informal Consultation, we flagged that the current CSP/ICSP review process, which involves three different steps prior to formal Board approval is probably not an efficient use of the Board s time: 1. Informal consultations on the Concept Notes 2. 20 day electronic written review process 3. Informal consultation on the draft CSPs/ICSPs 4. EB approval of CSPs and ICSPs Current process: IC on Concept Notes on a trial basis Electronic Review of CSP/ICSP EB Approval IC on Draft CSP/ICSP 23

Proposal for the CSP/ICSP review process Options for consideration: Option 1 IC on Concept Notes EB Approval Option 2 Electronic Review of CSP/ICSP EB Approval Option 3 IC on Draft CSP/ICSP EB Approval Option 4 (current process) IC on Concept Notes Electronic Review of CSP/ICSP IC on Draft CSP/ICSP EB Approval 24

25 Discussion

Agenda Integrated Road Map 1. Progress update Update on implementation Resource migration and cutover update Board s oversight of budget revisions, including crisis response Contributions received to date 2. Lessons learned: Focus on Sudan 3. Proposal for the CSP/ICSP review process 4. Open for discussion 5. Update on the CRF 6. Open for discussion 26

IRM PERFORMANCE MANAGEMENT UPDATES Performance Management and Monitoring Division 27

AGENDA 1. Update on the Revised Results Framework 2. Highlights from the new Corporate Monitoring Strategy 28

UN-WIDE DEVELOPMENTS CRF revision will need to take into account: UNDAF guidelines and UNDG guidance on joint monitoring QCPR recommendations Development of UN online platform for joint monitoring of UNDAF progress: UNINFO UNSD first progress reports on global targets and indicators Full system (global targets and indicators) review scheduled for 2020 and 2025 29

INTERAGENCY COORDINATION Consultation with Rome-Based Agencies on monitoring contributions to SDGs Ongoing review of approaches and opportunities for partnership with UNICEF, FAO, IFAD,UNFPA, UNDP Participation in the Inter-agency Joint Outcomes working group in New York Ongoing liaison with New York Office and outreach to Humanitarian World Summit Secretariat, UNDG/DOCO on QCPR decisions for joint reporting and UN system approaches 30

ELEMENTS OF THE NEW RESULTS FRAMEWORK WHAT WE DO MEASURING PROGRESS AGAINST THE STRATEGIC PLAN Compendium of indicators and methodologies used to plan programmes, monitor and report progress against the organization s goals LINK to SDGs SUPPORTING UNDAF and NATIONAL REPORTING ON SDGS Methodologies and guidance to build national capacity and support governments to report on national SDGs targets CORPORATE MANAGEMENT PERFORMANCE New structure applied to the Annual Performance Plans and Management Plan Key Performance Indicators to measure effectiveness, efficiency and economy HOW WE DO IT 31

RESULTS FRAMEWORK REVISIONS TIMELINE March Pilots Results Pilots in selected country offices are completed and experiences documented June UNDG guidance Analysis of implication of UNDG guidance on joint outcome monitoring in WFP results framework August Endorsement by EMG New Proposed Results framework is endorsed by the EMG. Advisory Board ends. January New Framework is implemented 2017 2018 2019 November CRF Advisory Board Advisory group starts meetings to receive recommendations of working groups and oversee review, evidence and proposal of enhanced CRF May Performance Management Strategy First outline is presented to the Advisory Board July CSPs evaluation Analyse and incorporate recommendations from OEV evaluation of CSP wave 1a countries initial report into the new proposed results framework November Executive board New Results Framework is approved by the Executive Board 32

NEW CORPORATE MONITORING STRATEGY VISION FOR 2021 Relevance Monitoring Information Reflects use of appropriate indicators Credibility Data Collection & Analysis Rigorous Transparent Aligned with WFP s MMRs 33 Support management, design and implementation of operational activities Is owned, meaningful and reflects end user needs (advocacy accountability and learning) Use Monitoring Information Easy to access and userfriendly Provokes reflection Tied to actions, recommendations and follow up

PRIORITY AREAS OF WORK & EXPECTED OUTCOMES 1 Workforce planning Analyze SKILLS Attract & Retain TALENT Boost EXPERTISE Sensitize SENIOR MANAGEMENT 2 Financial Commitment Ensure ADEQUATE FUNDING for monitoring 3 Functional Capacity STANDARDIZE monitoring systems and procedures AUTOMATE data collection, management, analysis ENHANCE use, credibility and relevance of data Workforce Review FIT pool M&E Roster Updated Trainings Key Performance Indicators Review of CO budgeting practices Monitoring Contingency Fund Normative Framework Indicator compendium Increase Monitoring Functionalities in COMET Invest in MDCA trainings 34

35 Discussion