UNIT-II Project Organization and Scheduling Project Element

Similar documents
Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

CISC 322 Software Architecture

After complete studying this chapter, You should be able to

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

Management Management

Textbook: pp Chapter 11: Project Management

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

CHAPTER 9: PROJECT MANAGEMENT

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Teori Pengambilan Keputusan. Week 12 Project Management

06IP/IM74 OPERATIONS RESEARCH

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Project Management Chapter 13

Project Management -- Developing the Project Plan

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

Appendix A Decision Support Analysis

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

GPE engineering project management. Project Management in an Engineering Context

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

SWEN 256 Software Process & Project Management

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

Project Management Techniques (PMT)

Real-World Project Management. Chapter 15

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

IE 102 Spring Project Management

Project Management Fundamentals

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

1 of 14 4/27/2009 7:45 AM

Construction Management

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan

MS Project 2007 Page 1 of 18

Project planning and creating a WBS

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

WHY ARE PROJECTS ALWAYS LATE?

Research Methods Outline

POLYTECHNIC OF NAMIBIA

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL

Allocate and Level Project Resources

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta

Appendix B: Glossary of Project Management Terms

ETSF01: Software Engineering Process Economy and Quality

COPYRIGHTED MATERIAL. Index

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

The Project Times and Costs

Project Management with Brief Information regarding CPM and PERT Methods

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

Outline. Project Management. Introduction. What is a Project?

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

PROJECT MANAGEMENT: PERT AMAT 167

The Critical Path Method

CHAPTER 5. Project Scheduling Models

Introduction to Project Management. Modeling after NYS ITS

VALLIAMMAI ENGINEERING COLLEGE

A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT

Cost Reduction: Planning & Control. Impacting the Bottom Line

Project Management and Cost Control

IP-CIS : CIS Project Management

Plan Implementation. Pushpa Lal Shakya

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING


MnDOT use of Calendars in Primavera P6

CHAPTER 5 STOCHASTIC SCHEDULING

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

Impacting the Bottom Line. Cost Reduction: Planning & Control. Bottom Line (costs) A = Costs (what we expend) B = Revenue, sales (what we generate)

Systems Engineering. Engineering 101 By Virgilio Gonzalez

Chapter 2 The PERT/CPM Technique

MODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT

Project Management. A Practitioner s Guide. Steven M. Bragg

MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD

u w 1.5 < 0 These two results imply that the utility function is concave.

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1

Project Management. Basic Definitions: Project and Project Plan

Programme Evaluation and Review Technique

Making sense of Schedule Risk Analysis

Chapter 11: PERT for Project Planning and Scheduling

EXERCISE Draw the network diagram. a. Activity Name A B C D E F G H

Line Balancing S K Mondal Chapter 3

VALUE MANAGEMENT INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: Snehal Salunke

Decision Support Tool for Project Time-Cost Trade-off

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri

Risk Video #1. Video 1 Recap

Chapter16Project Management and. Scheduling Project management

DC Program and Project Managers Meeting #2

International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN:

Lecture 3 Project Scheduling

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

Comparison between Deterministic and Stochastic Time Estimating Techniques

Transcription:

UNIT-II Project Organization and Scheduling Project Element Five Key Elements are Unique. Projects are unique, one-of-a-kind, never been done before. Start and Stop Date. Projects must have a definite start date and stop date. One Accountable Entity. Unlike operational work, where separate managers are accountable for different parts of the work, projects have only one accountable entity.

Project Element Definitive Prioritization of the TradeOffs When doing the work of projects most people are aware of what has been termed the "triple constraints" of project management.(time, quality, and resource expenditures) Agreement The final element is having agreement between the sponsor and the project manager 2

Types of WBS Process WBS It partitions a large process into smaller & smaller processes. Each process is eventually decomposed into tasks that can be assigned to individuals for accomplishment. Product WBS It partitions a large entity into its components. Each component & interfaces are identified, resulting in a clearer identification of the larger system. Hybrid WBS A WBS that includes both process & product elements of a project into one WBS. Project Life Cycle Project Life Cycle ModelsWaterfall model Prototyping Model Spiral Model 7

Product Life cycle Product development. Product Introduction. Product Growth. Product Maturity. Product Decline. Ways To Organize Personnel Flat Staffing Some of the developers can be assigned to the analysis activities with system analysts. While others may already start other activities such as technology review & trainings. Gradual Staffing The project work is gradually carried out by hiring people as required. It is motivated by saving resources in the early part of the project. 8

What should be the Team Size??? Team Size (n) Positive Impact. Three Members 2. Four Members Even if one member leaves, others continues to work.. Five & Six Members It is an ideal size for a team. Single roles may be given to each member. Members meet face to face. Every member has chance to speak. Negative Impact One member can dominate the other two. One member may perform many roles. Resolving issues like tie during voting can be more time consuming. No negative effects.. Seven Members Effective team size. Team meetings tend to become long. Sub teams formation is necessary. Reviewing the status requires more than half an hour.. Eight & more members Results are usually satisfactory. Too difficult to manage. More competition rather than cooperation of team members. Internal structure starts to break down into sub teams. Stages of Team Development Forming Storming These conflicts are settled & a group feeling should emerge. Performing Various team members try to show their leadership that may result in conflicts. Norming Introduction between team members. Some rules are also setup about behavior. Tasks are decided finally. Adjourning The group is dispersed. 9

Project Scheduling and Control Techniques Gantt Chart Critical Path Method (CPM) Program Evaluation and Review Technique (PERT) Gantt Chart Graph or bar chart with a bar for each project activity that shows passage of time Provides visual display of project schedule 0

History of CPM/PERT Critical Path Method (CPM) E I Du Pont de Nemours & Co. (97) for construction of new chemical plant and maintenance shut-down Deterministic task times Activity-on-node network construction Repetitive nature of jobs Project Evaluation and Review Technique (PERT) U S Navy (98) for the POLARIS missile program Multiple task time estimates (probabilistic nature) Activity-on-arrow network construction Non-repetitive jobs (R & D work) Project Network Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects Use of nodes and arrows Arrows An arrow leads from tail to head directionally Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work. Nodes A node is represented by a circle Indicate EVENT, a point in time where one or more activities start and/or finish. Activity A task or a certain amount of work required in the project Requires time to complete Represented by an arrow Dummy Activity Indicates only precedence relationships Does not require any time of effort

Event Project Network Signals the beginning or ending of an activity Designates a point in time Represented by a circle (node) Network Shows the sequential relationships among activities using nodes and arrows Activity-on-node (AON) nodes represent activities, and arrows show precedence relationships Activity-on-arrow (AOA) arrows represent activities and nodes are events for points in time AOA Project Network for House Lay foundation 2 Design house and obtain financing 2 Dummy 0 Order and receive materials Select paint Build house Finish work 7 Select carpet AON Project Network for House Lay foundations Build house 2 2 Start Finish work 7 Design house and obtain financing Order and receive materials Select carpet Select paint 2

Situations in network diagram B A A must finish before either B or C can start C A C both A and B must finish before C can start B A C B A D B both A and C must finish before either of B or D can start A must finish before B can start Dummy both A and C must finish before D can start C D Network example Illustration of network analysis of a minor redesign of a product and its associated packaging. The key question is: How long will it take to complete this project?

For clarity, this list is kept to a minimum by specifying only immediate relationships, that is relationships involving activities that "occur near to each other in time". Questions to prepare activity network Is this a Start Activity? Is this a Finish Activity? What Activity Precedes this? What Activity Follows this? What Activity is Concurrent with this?

CPM calculation Path Critical Path A connected sequence of activities leading from the starting event to the ending event The longest path (time); determines the project duration Critical Activities All of the activities that make up the critical path Forward Pass Earliest Start Time (ES) earliest time an activity can start ES = maximum EF of immediate predecessors Earliest finish time (EF) earliest time an activity can finish earliest start time plus activity time EF= ES + t Backward Pass Latest Start Time (LS) Latest time an activity can start without delaying critical path time LS= LF - t Latest finish time (LF) latest time an activity can be completed without delaying critical path time LS = minimum LS of immediate predecessors

CPM analysis Draw the CPM network Analyze the paths through the network Determine the float for each activity Compute the activity s float float = LS - ES = LF - EF Find the critical path is that the sequence of activities and events where there is no slack i.e.. Zero slack Float is the maximum amount of time that this activity can be delay in its completion before it becomes a critical activity, i.e., delays completion of the project Longest path through a network Find the project duration is minimum project completion time CPM Example: CPM Network f, h, 9 g, 7 a, i, b, 8 d, j, 2 c, e, 9

CPM Example ES and EF Times f, h, 9 g, 7 a, 0 i, b, 8 0 8 d, j, 2 c, 0 e, 9 CPM Example ES and EF Times f, 2 h, 9 g, 7 a, 0 2 i, b, 8 0 8 c, 0 d, j, 2 8 2 e, 9 7

CPM Example ES and EF Times f, 2 g, 7 a, 0 2 i, 2 29 h, 9 2 0 b, 8 0 8 d, 8 2 c, e, 9 0 j, 2 2 Project s EF = CPM Example LS and LF Times a, 0 b, 8 0 8 c, 0 f, 2 g, 7 2 d, 8 2 i, 2 29 27 h, 9 2 0 2 j, 2 2 2 e, 9 8

CPM Example LS and LF Times a, 0 0 b, 8 0 8 0 8 c, 0 7 2 Float f, 2 9 2 g, 7 2 0 27 d, 8 2 8 2 i, 2 29 27 h, 9 2 0 2 j, 2 2 2 e, 9 2 2 CPM Example a, 0 0 b, 8 0 0 8 0 8 c, 7 0 7 2 f, 2 9 2 g, 7 2 0 27 d, 0 8 2 8 2 h, 9 2 0 2 i, 2 29 27 j, 2 0 2 2 e, 9 7 2 2 9

CPM Example Critical Path f, h, 9 g, 7 a, i, b, 8 d, j, 2 c, e, 9 PERT PERT is based on the assumption that an activity s duration follows a probability distribution instead of being a single value Three time estimates are required to compute the parameters of an activity s duration distribution: pessimistic time (tp ) - the time the activity would take if things did not go well most likely time (tm ) - the consensus best estimate of the activity s duration optimistic time (to ) - the time the activity would take if things did go well t + tm + to Mean (expected time): te = p 2 Variance: Vt = 2 = tp - to 20

PERT analysis Draw the network. Analyze the paths through the network and find the critical path. The length of the critical path is the mean of the project duration probability distribution which is assumed to be normal The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum Probability computations can now be made using the normal distribution table. Probability computation Determine probability that project is completed within specified time x- Z= where = tp = project mean time = project standard mean time x = (proposed ) specified time 2

PERT Example Immed. Optimistic Most Likely Pessimistic Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) A - 8 B -. C A D A E A 0.. F B,C G B,C. H E,F 7 I E,F 2 8 J D,H 2. 2.7. K G,I 7 PERT Example PERT Network D A E H J C B I F K G 22

PERT Example Activity A B C D E F G H I J K Expected Time 2 Variance /9 /9 0 /9 / /9 /9 /9 /9 /9 PERT Example Activity ES EF LS LF A B C D E F G H I J K 0 0 9 9 9 7 8 22 2 0 2 9 9 20 8 9 9 20 8 8 2 2 9 8 Slack 0 *critical 0* 9 0* 7 20 0* 0* 2

PERT Example.7 Vpath = VA + VC + VF + VI + VK = /9 + 0 + /9 + + /9 = 2 path =. z = (2-2)/ (2-2)/. = From the Standard Normal Distribution table: P(z <.7) =. +.22 =.72 PROJECT COST 2

Cost consideration in project Project managers may have the option or requirement to crash the project, or accelerate the completion of the project. This is accomplished by reducing the length of the critical path(s). The length of the critical path is reduced by reducing the duration of the activities on the critical path. If each activity requires the expenditure of an amount of money to reduce its duration by one unit of time, then the project manager selects the least cost critical activity, reduces it by one time unit, and traces that change through the remainder of the network. As a result of a reduction in an activity s time, a new critical path may be created. When there is more than one critical path, each of the critical paths must be reduced. If the length of the project needs to be reduced further, the process is repeated. Project Crashing Crashing Crash time an amount of time an activity is reduced Crash cost reducing project time by expending additional resources cost of reducing activity time Goal reduce project duration at minimum cost 2

Activity crashing Crash cost Crashing activity Slope = crash cost per unit time Normal Activity Normal cost Normal time Crash time Activity time Time-Cost Relationship Crashing costs increase as project duration decreases Indirect costs increase as project duration increases Reduce project length as long as crashing costs are less than indirect costs Time-Cost Tradeoff Min total cost = optimal project time Total project cost Indirect cost Direct cost time 2

Project Crashing example 2 8 2 7 2 Time Cost data Activit Norm Norm y al time al cost Rs 2 000 2 8 2000 000 2 0000 00 00 7 00 7000 Crash Crash Allowabl time cost e crash Rs time 7 000 00 7000 9 7000 00 00 22000 070 0 slope 00 00 000 7000 200 200 7000 27

R00 R7000 2 8 2 Project duration = R700 7 2 R00 To.. R000 From.. R200 R200 R00 R7000 2 8 2 R700 7 7 Project duration = Additional cost = R2000 R00 R000 R200 R200 Benefits of CPM/PERT Useful at many stages of project management Mathematically simple Give critical path and slack time Provide project documentation Useful in monitoring costs CPM/PERT can answer the following important questions: How long will the entire project take to be completed? What are the risks involved? Which are the critical activities or tasks in the project which could delay the entire project if they were not completed on time? Is the project on schedule, behind schedule or ahead of schedule? If the project has to be finished earlier than planned, what is the best way to do this at the least cost? 28

Limitations to CPM/PERT Clearly defined, independent and stable activities Specified precedence relationships Over emphasis on critical paths Deterministic CPM model Activity time estimates are subjective and depend on judgment PERT assumes a beta distribution for these time estimates, but the actual distribution may be different PERT consistently underestimates the expected project completion time due to alternate paths becoming critical To overcome the limitation, Monte Carlo simulations can be performed on the network to eliminate the optimistic bias Computer Software for Project Management Microsoft Project (Microsoft Corp.) MacProject (Claris Corp.) PowerProject (ASTA Development Inc.) Primavera Project Planner (Primavera) Project Scheduler (Scitor Corp.) Project Workbench (ABT Corp.) 29

Practice Example A social project manager is faced with a project with the following activities: Activity Description Duratio n w 2w w w Social work team to live in village Social research team to do survey Analyse results of survey Establish mother & child health program Establish rural credit program w Carry out immunization of under fives w Draw network diagram and show the critical path. Calculate project duration. Practice problem Activit y -2 - - 2- - - Description Social work team to live in village Social research team to do survey Analyse results of survey Establish mother & child health program Establish rural credit programme Carry out immunization of under fives Duratio n w 2w w w w w 2 0

Project Scheduling and Tracking What does the customer want to know? Do you understand my needs? Can you design a system to help me? How long will it take? How much will it cost?

Scheduling Principles - Compartmentalization Interdependency the product and process must be decomposed into a manageable number of activities and tasks tasks that can be completed in parallel must be separated from those that must completed serially Time allocation every task has start and completion dates that take the task interdependencies into account Scheduling Principles - 2 Effort validation project manager must ensure that on any given day there are enough staff members assigned to completed the tasks within the time estimated in the project plan Defined Responsibilities every scheduled task needs to be assigned to a specific team member 2

Scheduling Principles - Defined outcomes every task in the schedule needs to have a defined outcome (usually a work product or deliverable) Defined milestones a milestone is accomplished when one or more work products from an engineering task have passed quality review Total Float Time

QUESTIONS-

What do you mean by a dummy activity? Why it is used in networking?

Pert Question- Pert Question 7