CHAPTER 5. Project Scheduling Models

Similar documents
Project Management Chapter 13

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

Textbook: pp Chapter 11: Project Management

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

CHAPTER 9: PROJECT MANAGEMENT

1 of 14 4/27/2009 7:45 AM

Project Management Techniques (PMT)

After complete studying this chapter, You should be able to

UNIT-II Project Organization and Scheduling Project Element

Teori Pengambilan Keputusan. Week 12 Project Management

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

CHAPTER 5 STOCHASTIC SCHEDULING

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

Allocate and Level Project Resources

CISC 322 Software Architecture

Appendix A Decision Support Analysis

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

Real-World Project Management. Chapter 15

Project Management Fundamentals

Chapter 11: PERT for Project Planning and Scheduling

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

Project Management -- Developing the Project Plan

Construction Management

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan


A Linear Programming Approach for Optimum Project Scheduling Taking Into Account Overhead Expenses and Tardiness Penalty Function

Chapter 2 The PERT/CPM Technique

ETSF01: Software Engineering Process Economy and Quality

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta

MnDOT use of Calendars in Primavera P6

IE 102 Spring Project Management

Management Management

Research Methods Outline

M G T 2251 Management Science. Exam 3

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

GPE engineering project management. Project Management in an Engineering Context

SWEN 256 Software Process & Project Management

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

Project Planning. Planning is an important step in project execution. Planning means:

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

NPV Method. Payback Period

Quantitative Risk Analysis with Microsoft Project

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

MS Project 2007 Page 1 of 18

56:171 Operations Research Midterm Examination Solutions PART ONE

u w 1.5 < 0 These two results imply that the utility function is concave.

PROJECT MANAGEMENT DIPLOMA COURSE

06IP/IM74 OPERATIONS RESEARCH

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

Appendix B: Glossary of Project Management Terms

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

Lecture 5: Project Management

POLYTECHNIC OF NAMIBIA

Handout 4: Deterministic Systems and the Shortest Path Problem

A STUDY OF THE BASIC CONCEPT OF CRASHING CPM NETWORK USING DERIVATIVE MARGINAL COST IN LINEAR PROGRAMMING

Project Management and Cost Control

WHY ARE PROJECTS ALWAYS LATE?

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL

Line Balancing S K Mondal Chapter 3

Unit 5 Slide Lectures of 04/05/06 April 2017

Chapter16Project Management and. Scheduling Project management

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule

IP-CIS : CIS Project Management

56:171 Operations Research Midterm Examination Solutions PART ONE

Lesson Plan for Simulation with Spreadsheets (8/31/11 & 9/7/11)

56:171 Operations Research Midterm Examination October 25, 1991 PART ONE

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

Lecture 3 Project Scheduling

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

Brown hamburger and assemble tacos (including cheese)

56:171 Operations Research Midterm Exam Solutions October 22, 1993

Outline. Project Management. Introduction. What is a Project?

Making sense of Schedule Risk Analysis

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

Project Controls Expo 16 th Nov 2016

How to Consider Risk Demystifying Monte Carlo Risk Analysis

Statistical Methods in Practice STAT/MATH 3379

VALLIAMMAI ENGINEERING COLLEGE

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

Poor Man s Approach to Monte Carlo

Project planning and creating a WBS

Programme Evaluation and Review Technique

SAMPLE. DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development. AACE International Recommended Practice No.

Introduction to Project Management. Modeling after NYS ITS

How to Satisfy GAO Schedule Best Practices


Transcription:

CHAPTER 5 Project Scheduling Models 1

5.1 Introduction A project is a collection of tasks that must be completed in minimum time or at minimal cost. Objectives of Project Scheduling Completing the project as early as possible by determining the earliest start and finish of each activity. Calculating the likelihood a project will be completed within a certain time period. Finding the minimum cost schedule needed to complete the project by a certain date. 2

A project is a collection of tasks that must be completed in minimum time or at minimal cost. Objectives of Project Scheduling Investigating the results of possible delays in activity s completion time. Progress control. 5.1 Introduction Smoothing out resource allocation over the duration of the project. 3

Task Designate Tasks are called activities. Estimated completion time (and sometimes costs) are associated with each activity. Activity completion time is related to the amount of resources committed to it. The degree of activity details depends on the application and the level of specificity of data. 4

5.2 Identifying the Activities of a Project To determine optimal schedules we need to Identify all the project s activities. Determine the precedence relations among activities. Based on this information we can develop managerial tools for project control. 5

Identifying Activities, Example KLONE COMPUTERS, INC. KLONE Computers manufactures personal computers. It is about to design, manufacture, and market the Klonepalm 2000 palmbook computer. 6

KLONE COMPUTERS, INC There are three major tasks to perform: Manufacture the new computer. Train staff and vendor representatives. Advertise the new computer. KLONE needs to develop a precedence relations chart. The chart gives a concise set of tasks and their immediate predecessors. 7

KLONE COMPUTERS, INC Activity Description A Prototype model design B Purchase of materials Manufacturing C Manufacture of prototype model activities D Revision of design E Initial production run F Staff training Training activities G Staff input on prototype models H Sales training Advertising activities I Pre-production advertising campaign J Post-redesign advertising campaign 8

KLONE COMPUTERS, INC From the activity description chart, we can determine immediate predecessors for each activity. A B Activity A is an immediate predecessor of activity B, because it must be competed just prior to the commencement of B. 9

KLONE COMPUTERS, INC Precedence Relationships Chart Immediate Estimated Activity Predecessor Completion Time A None 90 B A 15 C B 5 D G 20 E D 21 F A 25 G C,F 14 H D 28 I A 30 J D,I 45 10

5.3 The PERT/CPM Approach for Project Scheduling The PERT/CPM approach to project scheduling uses network presentation of the project to Reflect activity precedence relations Activity completion time PERT/CPM is used for scheduling activities such that the project s completion time is minimized. 11

KLONE COMPUTERS, INC. - Continued Management at KLONE would like to schedule the activities so that the project is completed in minimal time. Management wishes to know: The earliest and latest start times for each activity which will not alter the earliest completion time of the project. The earliest finish times for each activity which will not alter this date. Activities with rigid schedule and activities that have slack in their schedules. 12

Earliest Start Time / Earliest Finish Time Make a forward pass through the network as follows: Evaluate all the activities which have no immediate predecessors. The earliest start for such an activity is zero ES = 0. The earliest finish is the activity duration EF = Activity duration. Evaluate the ES of all the nodes for which EF of all the immediate predecessor has been determined. ES = Max EF of all its immediate predecessors. EF = ES + Activity duration. Repeat this process until all nodes have been evaluated EF of the finish node is the earliest finish time of the project. 13

Earliest Start / Earliest Finish Forward Pass 90,105 B 15 105,110 C 5 149,170170 E 21 0,90 A 90 90,115 F 25 110,124 115,129 129,149 G D 14 20 149,177177 H 28 194 EARLIEST FINISH 90,120 I 30 120,165 149,194194 J 45 14

Latest start time / Latest finish time Make a backward pass through the network as follows: Evaluate all the activities that immediately precede the finish node. The latest finish for such an activity is LF = minimal project completion time. The latest start for such an activity is LS = LF - activity duration. Evaluate the LF of all the nodes for which LS of all the immediate successors has been determined. LF = Min LS of all its immediate successors. LS = LF - Activity duration. Repeat this process backward until all nodes have been evaluated. 15

Latest Start / Latest Finish Backward Pass 90,105 95,110 B 15 C 5 105,110 110,115 149,170 173,194 E 21 5,95 A 90 29,119 0,90 0,90 90,115 90, 115 F 25 90,120 119,149 I 30 115,129 129,149 149,177 115,129 153,173 129,149 129,149 166,194 129,149 G 129,149 D 146,166 129,149 H 14 129,149 20 28 129,149 129,149 149,194 149,194 J J 45 194 16

Slack Times Activity start time and completion time may be delayed by planned reasons as well as by unforeseen reasons. Some of these delays may affect the overall completion date. To learn about the effects of these delays, we calculate the slack time, and form the critical path. 17

Slack Times Slack time is the amount of time an activity can be delayed without delaying the project completion date, assuming no other delays are taking place in the project. Slack Time = LS - ES = LF - EF 18

Slack time in the Klonepalm 2000 Project Activity LS - ES Slack A 0-0 0 B 95-90 5 C 110-105 5 D 119-119 0 E 173-149 24 F 90-90 0 G 115-115 0 H 166-149 17 I 119-90 29 J 149-149 0 Critical activities must be rigidly scheduled 19

The Critical Path The critical path is a set of activities that have no slack, connecting the START node with the FINISH node. The critical activities (activities with 0 slack) form at least one critical path in the network. A critical path is the longest path in the network. The sum of the completion times for the activities on the critical path is the minimal completion time of the project. 20

The Critical Path 90,105 95,110 B 15 C 5 105,110 110,115 149,170 173,194 E 21 0,90 0,90 A 90 90,115 90, 115 F 25 115,129 129,149 149,177 115,129 129,149 166,194 G D 14 20 H 28 90,120 119,149 I 30 149,194 149,194 J J 45 21

Possible Delays We observe two different types of delays: Single delays. Multiple delays. Under certain conditions the overall project completion time will be delayed. The conditions that specify each case are presented next. 22

Single delays A delay of a certain amount in a critical activity, causes the entire project to be delayed by the same amount. A delay of a certain amount in a non-critical activity will delay the project by the amount the delay exceeds the slack time. When the delay is less than the slack, the entire project is not delayed. 23

Multiple delays of non critical activities: Case 1: Activities on different paths B 15 C 5 ES=149 DELAYED START=149+15=164 LS=173 E 21 A 90 F 25 I ES=90 30 DELAYED START=90+15 =105 LS =119 G 14 D 20 Activity E and I are each delayed 15 days. THE PROJECT COMPLETION TIME IS NOT DELAYED H 28 J 45 24

A B C 90 90 15 105 115 5 129 20 149 194 D E F G H I Gantt chart demonstration of the (no) effects on the project completion time when delaying activity I and E by 15 days. Activity I 25 30 Activity E 14 21 28 45 194 J 25

Multiple delays of non critical activities: Case 2: Activities are on the same path, separated by critical activities. ES=90 DELAYED START =94 LS =95 B 15 C 5 ES=149 DELAYED START=149+15 =164 LS =173 E 21 A 90 F 25 G 14 D 20 H 28 Activity B is delayed 4 days, activity E is delayed 15 days THE PROJECT COMPLETION TIME IS NOT DELAYED I 30 J 45 26

Multiple delays of non critical activities: Case 2: Activities are on the same path, no critical activities separating them. ES= 90 DELAYED START =94 DELAYED FINISH = 94+15=109 B 15 DELAYED START= 109 + 4 =113; C LS =110 5 3 DAYS DELAY IN THE ENTIRE PROJECT E 21 A 90 F 25 I 30 G 14 D 20 Activity B is delayed 4 days; Activity C is delayed 4 days. THE PROJECT COMPLETION TIME IS DELAYED 3 DAYS J 45 H 28 27

5.4 A Linear Programming Approach to PERT/CPM Variables X i = The start time of the activities for i=a, B, C,,J X(FIN) = Finish time of the project Objective function Complete the project in minimum time. Constraints For each arc L M a constraint states that the start time of M must not occur before the finish time of its immediate predecessor, L. 28

A Linear Programming Approach Define X(FIN) to be the finish time of the project. The objective then is Minimize X(FIN) While this objective function is intuitive other objective functions provide more information, and are presented later. 29

A Linear Programming Approach Minimize X(FIN) ST X(FIN) X E + 21 C 5 X(FIN) X H + 28 X(FIN) X J + 45 X D X G + 14 F 25 X E X D + 20 X G X C + 5 X H X D + 20 X G X F + 25 X J X D + 20 X I X D + 90 All X s are nonnegative X J X I + 30 X F X A + 90 X C X B + 15 G 30

A Linear Programming Approach Minimize X A +X B + +X J This objective function ensures that the optimal X values are the earliest start times of all the activities. The project completion time is minimized. Maximize X A +X B + +X J S.T. X(FIN) = 194 and all the other constraints as before. This objective function and the additional constraint ensure that the optimal X values are the latest start times of all the activities. 31

5.5 Obtaining Results Using Excel CRITICAL PATH ANALYSIS MEAN 194 STANDARD DEVIATION* 0 * As sumes all critical activities are on one critical path VARIANCE* 0 If not, enter in gold box, the variance on one critical path of interest. PROBABILITY COMPLETE BEFORE = Acitivty Node Critical µ σ σ 2 ES EF LS LF Slack De sign A * 90 0 90 0 90 0 Ma te ria ls B 15 90 105 95 110 5 Ma nufa cture C 5 105 110 110 115 5 De sign Revision D * 20 129 149 129 149 0 Production Run E 21 149 170 173 194 24 Staff Training F * 25 90 115 90 115 0 Staff Input G * 14 115 129 115 129 0 Sa le s Tra ining H 28 149 177 166 194 17 Preprod. Adve rtise I 30 90 120 119 149 29 Post. Advertise J * 45 149 194 149 194 0 32

5.6 Gantt Charts Gantt charts are used as a tool to monitor and control the project progress. A Gantt Chart is a graphical presentation that displays activities as follows: Time is measured on the horizontal axis. A horizontal bar is drawn proportionately to an activity s expected completion time. Each activity is listed on the vertical axis. In an earliest time Gantt chart each bar begins and ends at the earliest start/finish the activity can take place. 33

Here s how we build an Earliest Time Gantt Chart for KLONEPALM 2000 34

90 105 A 90 15 115 129 B C 5 20 149 194 D E F G H I J Immediate Estimated Activity Predecessor Completion Time A None 90 B A 15 C B 5 D G 20 E D 21 F A 25 G C,F 14 H D 28 I A 30 J D,I 45 25 30 14 21 28 45 194 35

Gantt Charts- Monitoring Project Progress Gantt chart can be used as a visual aid for tracking the progress of project activities. Appropriate percentage of a bar is shaded to document the completed work. The manager can easily see if the project is progressing on schedule (with respect to the earliest possible completion times). 36

Monitoring Project Progress A 90 15 B C D E F G H I J The shaded bars represent completed work BY DAY 135. Do not conclude that the project is behind schedule. Activity I has a slack and therefore can be delayed!!! 25 30 5 14 20 21 28 45 194 194 135 37

Gantt Charts Advantages and Disadvantages Advantages. Easy to construct Gives earliest completion date. Provides a schedule of earliest possible start and finish times of activities. Disadvantages Gives only one possible schedule (earliest). Does not show whether the project is behind schedule. Does not demonstrate the effects of delays in any one activity on the start of another activity, thus on the project completion time. 38

5.7 Resource Leveling and Resource Allocation It is desired that resources are evenly spread out throughout the life of the project. Resource leveling methods (usually heuristics) are designed to: Control resource requirements Generate relatively similar usage of resources over time. 39

Resource Leveling A Heuristic A heuristic approach to level expenditures Assumptions Once an activity has started it is worked on continuously until it is completed. Costs can be allocated equally throughout an activity duration. Step 1: Consider the schedule that begins each activity at its ES. Step 2: Determine which activity has slack at periods of peak spending. Step 3: Attempt to reschedule the non-critical activities performed during these peak periods to periods of less spending, but within the time period between their ES and LF. 40

Resource Leveling KLONE COMPUTERS, Inc. - continued Management wishes to schedule the project such that Completion time is 194 days. Daily expenditures are kept as constant as possible. To perform this analysis cost estimates for each activity will be needed. 41

Resource Leveling KLONE COMPUTERS, Inc. cost estimates Total Total Cost Cost Time per Activity Description (x10000) (days) Day A Prototype model design 2250 90 25 B Purchase of materials 180 15 12 C Manufacture of prototype 90 5 18 D Revision of design 300 20 15 E Initial production run 231 21 11 F Staff training 250 25 10 G Staff input on prototype 70 14 5 H Sales traini ng 392 28 14 I Pre-production advertisement 510 30 17 J Post-production advertisement 1350 45 30 Total cost = 5,623 42

55 50 45 40 35 30 25 20 15 10 5 Cumulative Daily Expenditure Earliest Times vs. Latest Times Earliest Start-Earliest Finish Budget Latest Start-Latest Finish Budget Feasible Budgets 20 40 60 80 100 120 140 160 180 200 Time 43

55 50 45 40 35 30 25 20 15 10 5 Daily Expenditure of the ES Schedule 55 A Cost Leveling ES = 90 25 39 I B F I I I I I I 45 LS = 110 I C F 27 I F 22 I G 32 I D 15 H E H E J J H E J 44 H J 30 J 20 40 60 80 100 120 140 160 180 200 44

55 Cost Leveling 55 50 45 H H 44 40 35 30 25 20 15 10 5 25 A I B F I C F 27 I F 22 I G 32 I 15 D E H E J J E J H J H 30 J 20 40 60 80 100 120 140 160 180 200 45

5.8 The Probability Approach to Project Scheduling Activity completion times are seldom known with 100% accuracy. PERT is a technique that treats activity completion times as random variables. Completion time estimates are obtained by the Three Time Estimate approach 46

The Probability Approach The Three Time Estimate approach provides completion time estimate for each activity. We use the notation: Three Time Estimates a = an optimistic time to perform the activity. m = the most likely time to perform the activity. b = a pessimistic time to perform the activity. 47

The Distribution, Mean, and Standard Deviation of an Activity Approximations for the mean and the standard deviation of activity completion time are based on the Beta distribution. µ σ = the mean completion time = a + 4m + b 6 = the standard deviation = b - a 6 48

The Project Completion Time Distribution - Assumptions To calculate the mean and standard deviation of the project completion time we make some simplifying assumptions. 49

The Project Completion Time Distribution - Assumptions Assumption 1 A critical path can be determined by using the mean completion times for the activities. The project mean completion time is determined solely by the completion time of the activities on the critical path. Assumption 2 The time to complete one activity is independent of the time to complete any other activity. Assumption 3 There are enough activities on the critical path so that the distribution of the overall project completion time can be approximated by the normal distribution. 50

The Project Completion Time Distribution The three assumptions imply that the overall project completion time is normally distributed, the following parameters: Mean = Sum of mean completion times along the critical path. Variance = Sum of completion time variances along the critical path. Standard deviation = Variance 51

The Probability Approach KLONE COMPUTERS Activity Optimistic Most Likely Pessimistic A 76 86 120 B 12 15 18 C 4 5 6 D 15 18 33 E 18 21 24 F 16 26 30 G 10 13 22 H 24 18 32 I 22 27 50 J 38 43 60 52

The Probability Approach KLONE COMPUTERS Management at KLONE is interested in information regarding the completion time of the project. The probabilistic nature of the completion time must be considered. 53

KLONE COMPUTERS Finding activities mean and variance µ A = [76+4(86)+120]/6 = 90 σ Α = (120-76)/6 = 7.33 σ 2 A = (7.33) 2 = 53.78 Activity µ σ σ 2 A 90 7.33 53.78 B 15 1.00 1.00 C 5 0.33 0.11 D 20 3.00 9.00 E 21 1.00 1.00 F 25 2.33 5.44 G 14 2.00 4.00 H 28 1.33 1.78 I 30 4.67 21.78 J 45 3.67 13.44 54

KLONE COMPUTERS Finding mean and variance for the critical path The mean times are the same as in the CPM problem, previously solved for KLONE. Thus, the critical path is A - F- G - D J. Expected completion time = µ A +µ F +µ G +µ D +µ J =194. The project variance =σ A2 +σ F 2 +σ G2 +σ D2 +σ J2 = 85.66 The standard deviation = = 9.255 σ 2 55

The Probability Approach Probabilistic analysis The probability of completion in 194 days = 194 P(X 194-194 194) = P(Z ) = P( Z 0) = 0. 5 9.255 56

The Probability Approach Probabilistic analysis An interval in which we are reasonably sure the completion date lies is µ ± z 0.025 σ µ The interval is = 194 ± 1.96(9.255) [175, 213] days. The probability that the completion time lies in the interval [175,213] is 0.95..95 57

The Probability Approach The probability of completion in 180 days = 0.0655 Probabilistic analysis 180-1.51 194 0 X Z P(X 180) = P(Z -1.51) = 0.5-0.4345 = 0.0655 58

The Probability Approach Probabilistic analysis The probability that the completion time is longer than 210 days =.4582? 0.0418 194 0 210 1.73 X Z P(X 210)=P(Z 1.73)= 0.5-0.458= 0.0418 59

The Probability Approach Probabilistic analysis Provide a completion time that has only 1% chance to be exceeded. There is 99% chance that the project is completed in 215.56 days..49 0.01 194 0 P(X X 0 ) = 0.01, or P(Z [(X 0 µ)/σ] = P(Z Z 0 ) =.01 P(Z 2.33) = 0.01; X 0 =µ+z 0 σ =194 + 2.33(9.255) = 215.56 days. X 0 2.33 X Z 60

The Probability Approach Probabilistic analysis with a spreadsheet NORMDIST(194, 194, 9.255, TRUE) NORMINV(.025, 194, 9.255) NORMINV(.975, 194, 9.255) NORMDIST(180, 194, 9.255, TRUE) 1 - NORMDIST(210, 194, 9.255, TRUE) NORMINV(.99, 194, 9.255) 61

The Probability Approach Critical path spreadsheet CRITICAL PATH ANALYSIS MEAN 194 STANDARD DEVIATION* VARIANCE* PROBABILITY COMPLETE BEFORE 180 = 0.065192 9.255629 * Ass umes all critical activities are on one critical path 85.66667 If not, enter in gold box, the variance on one critical path of interest. Acitivty Node Critica l µ σ σ 2 ES EF LS LF Slack Design A * 90 7.333333 53.77778 0 90 0 90 0 Materials B 15 1 1 90 105 95 110 5 Manufa cture C 5 0.333333 0.111111 105 110 110 115 5 Design Revision D * 20 3 9 129 149 129 149 0 Production Run E 21 1 1 149 170 173 194 24 Staff Training F * 25 2.333333 5.444444 90 115 90 115 0 Staff Input G * 14 2 4 115 129 115 129 0 Sales Training H 28 1.333333 1.777778 149 177 166 194 17 Preprod. Adve rtise I 30 4.666667 21.77778 90 120 119 149 29 Post. Adve rtise J * 45 3.666667 13.44444 149 194 149 194 0 62

The Probability Approach critical path spreadsheet CRITICAL PATH ANALYSIS A comment multiple critical paths MEAN 189 STANDARD DEVIATION* 9.0185 * Ass umes all critical activities are on one critical path In the case of multiple critical paths (a not unusual situation), VARIANCE* 81.33333 If not, enter in gold box, the variance on one critical path of interes t. determine the probabilities for each critical path separately using its PROBABILITY COMPLETE BEFORE 180 = 0.159152 standard deviation. However, the probabilities of interest (for example, P(X x)) cannot be determined by each path alone. To find these probabilities, check Acitivty Node Critical µ σ σ 2 ES EF LS LF Slack Design A * 90 7.333333 53.77778 0 90 0 90 0 Materials B * 15 1 1 90 105 90 105 0 whether the paths are independent. Manufacture C * 5 0.333333 0.111111 105 110 105 110 0 Design Revision If D the paths * are 20independent 3 (no 9 common 124 activities 144 among 124 the paths), 144 0 Production Run multiply E the probabilities 21 of all 1 the paths: 1 144 165 168 189 24 Staff Training F 14 0.666667 0.444444 90 104 96 110 6 [Pr(Completion time x) = Pr(Path 1 x)p(path 2 x) Path k x)] Staff Input G * 14 2 4 110 124 110 124 0 Sales Training If Hthe paths are 28dependent, 1.333333 the 1.777778 calculations 144 might 172 become 161 very 189 17 Preprod. Advertise cumbersome, I in which 30 case 4.666667 running 21.77778 a computer 90 simulation 120 114 seems to 144 be 24 Post. Advertise J * 45 3.666667 13.44444 144 189 144 189 0 more practical. 63

5.9 Cost Analysis Using the Expected Value Approach Spending extra money, in general should decrease project duration. Is this operation cost effective? The expected value criterion is used to answer this question. 64

KLONE COMPUTERS - Cost analysis using probabilities Analysis indicated: Completion time within 180 days yields an additional profit of $1 million. Completion time between 180 days and 200 days, yields an additional profit of $400,000. Completion time reduction can be achieved by additional training. 65

KLONE COMPUTERS - Cost analysis using probabilities Two possible activities are considered for training. Sales personnel training: Cost $200,000; pursued? New time estimates are a = 19, m= 21, and b = 23 days. Technical staff training: Which option should be Cost $250,000; New time estimates are a = 12, m = 14, and b = 16. 66

KLONE COMPUTERS - Cost analysis using probabilities Evaluation of spending on sales personnel training. This activity (H) is not critical. Under the assumption that the project completion time is determined solely by critical activities, this option should not be considered further. Evaluation of spending on technical staff training. This activity (F) is critical. This option should be further studied as follows: Calculate expected profit when not spending $250,000. Calculate expected profit when spending $250,000. Select the decision with a higher expected profit. 67

KLONE COMPUTERS - Cost analysis using probabilities Case 1: Do not spend $250,000 on training. Let X represent the project s completion time. Expected gross additional profit = E(GP) = P(X<180)($1 million) + P(180<X<200)($400,000) + P(X>200)(0). Use Excel to find the required probabilities: P(X<180) =.065192; P(180<X<200) =.676398; P(X>200) =.25841 Expected gross additional profit =..065192(1M)+.676398(400K)+.25841(0) = $335,751.20 68

KLONE COMPUTERS - Cost analysis using probabilities Case 2: Spend $250,000 on training. The revised mean time and standard deviation estimates for activity F are: µ F = (12 + 4 (14) + 16)/6 = 14 σ F = (16-12)/6 =0.67 σ F2 = 0(.67) 2 =0.44 Using the Excel PERT-CPM template we find a new critical path (A-B-C-G-D-J), with a mean time = 189 days, and a standard deviation of = 9.0185 days. 69

KLONE COMPUTERS - Cost analysis using probabilities The probabilities of interest need to be recalculated. From Excel we find: P(X < 180) =.159152; P(180 < X < 200) =.729561 P(X > 200) =.111287 Expected Gross Additional Revenue = P( X<180)(1M)+P(180<X<200)(400K)+P(X>200)(0) =.159152(!M)+.729561(400K)+.111287(0) = $450,976.40 70

KLONE COMPUTERS - Cost analysis using probabilities The expected net additional profit = 450,976-250,000 = $200,976 < $335,751 Expected additional net profit when spending $250,000 on training Expected profit without spending $250,000 on training Conclusion: Management should not spend money on additional training of technical personnel. 71

5.10 Cost Analyses Using The Critical Path Method (CPM) The critical path method (CPM) is a deterministic approach to project planning. Completion time depends only on the amount of money allocated to activities. Reducing an activity s completion time is called crashing. 72

Crash time/crash cost There are two crucial completion times to consider for each activity. Normal completion time (T N ). Crash completion time (T C ), the minimum possible completion time. The cost spent on an activity varies between Normal cost (C N ). The activity is completed in T N. Crash cost (C C ). The activity is completed in T C. 73

Crash time/crash cost The Linearity Assumption The maximum crashing of activity completion time is T C T N. This can be achieved when spending C N C C. Any percentage of the maximum extra cost (C N C C ) spent to crash an activity, yields the same percentage reduction of the maximum time savings (T C T N ). 74

Time 20 18 16 14 12 10 8 6 4 2 Normal C N = $2000 T N = 20 days and save on and completion save more time on completion time Add more Add to the normal normal cost... cost... to save 25% of the max. time reduction Total Cost = $2600 Job time = 18 days A demonstration of the Linearity Assumption Add 25% of the extra cost... Crashing C C = $4400 T C = 12 days 5 10 15 20 25 30 35 40 45 Cost ($100) 75

Crash time/ Crash cost - The Linearity Assumption Marginal Cost = Additional Cost to get Max. Time Reduction Maximum Time reduction = (4400-2000)/(20-12) = $300 per day M = E R 76

Crashing activities Meeting a Deadline at Minimum Cost If the deadline to complete a project cannot be met using normal times, additional resources must be spent on crashing activities. The objective is to meet the deadline at minimal additional cost. 77

Baja Burrito Restaurants Meeting a Deadline at Minimum Cost Baja Burrito (BB) is a chain of Mexican-style fast food restaurants. It is planning to open a new restaurant in 19 weeks. Management wants to Study the feasibility of this plan, Study suggestions in case the plan cannot be finished by the deadline. 78

Baja Burrito Restaurants Without spending any extra money, the restaurant will open in 29 weeks at a normal cost of $200,000. When all the activities are crashed to the maximum, the restaurant will open in 17 weeks at crash cost of $300,000. Determined by the PERT.xls template 79

Baja Burrito Restaurants Network presentation E O B I K A C D F G H J L M N P 80

Baja Burrito Restaurants Marginal costs R = T N T C = 5 3 = 2 E = C C C N = 36 25 = 11 M = E/R = 11/2 = 5.5 81

Baja Burrito Restaurants Heuristic Solution Small crashing problems can be solved heuristically. Three observations lead to the heuristic. The project completion time is reduced only when critical activity times are reduced. The maximum time reduction for each activity is limited. The amount of time a critical activity can be reduced before another path becomes critical is limited. 82

Baja Burrito Restaurants Linear Programming Linear Programming Approach Variables X j = start time for activity j. Y j = the amount of crash in activity j. Objective Function Minimize the total additional funds spent on crashing activities. Constraints No activity can be reduced more than its Max. time reduction. Start time of an activity takes place not before the finish time of all its immediate predecessors. The project must be completed by the deadline date D. 83

Baja Burrito Restaurants Linear Programming Min 5.5Y A +10Y B +2.67Y C +4Y D +2.8Y E +6Y F +6.67Y G +10Y H + 5.33Y I +12Y J +4Y K +5.33Y L +1.5Y N +4Y O +5.33Y P Minimize total crashing costs 84

Linear Programming Min 5.5Y A +10Y B +2.67Y C +4Y D +2.8Y E +6Y F +6.67Y G +10Y H + 5.33Y I +12Y J +4Y K +5.33Y L +1.5Y N +4Y O +5.33Y P ST X ( FIN ) 19 Meet the deadline Y A 2.0 YB 0.5 YC 1.5 YD 1.0 YE 2.5 YF 0.5 Y G 1.5 Y H 0.5.. Maximum time-reduction constraints 85

Linear Programming Min 5.5Y A +10Y B +2.67Y C +4Y D +2.8Y E +6Y F +6.67Y G +10Y H + 5.33Y I +12Y J +4Y K +5.33Y L +1.5Y N +4Y O +5.33Y P Baja Burrito Restaurants Network presentation X B X A +(5 Y A ) -Y A E O X A A A X A +5-Y A X A +5 A B C D F G I H J K L M 84 N P B BB X BB X BB X B Activity can start only after all the Predecessors are completed. 86

Linear Programming Min 5.5Y A +10Y B +2.67Y C +4Y D +2.8Y E +6Y F +6.67Y G +10Y H + 5.33Y I +12Y J +4Y K +5.33Y L +1.5Y N +4Y O +5.33Y P A Baja Burrito Restaurants Network presentation E B C D F G I H J K L M 84 O N P X B X A +(5 Y A ) X C X A +(5 Y A ) X D X A +(5 Y A ) X e X A +(5 Y A ) X F X A +(5 Y A ) X B X B +(1 Y B ) X F X C +(3 Y C ) X G X F +(1 Y F ).. X(FIN) X N +(3 Y N ) X(FIN) X O +(4 Y O ) X(FIN) X P +(4 Y P ) Activity can start only after all the predecessors are completed. 87

Baja Burrito Restaurants Deadline Spreadsheet TOTAL PROJECT COST 248.75 PROJECT NORMAL COST 200 COMPLETION TIME 19 PROJECT CRASH COST 300 ACTIVITY CRASHING ANALYSIS NODE Completion Time Start Time Finish Time Amount Crashed Cost of Crashing Total Cost Revisions/Approvals A 3 0 3 2 11 36 Grade Land B 1 3 4 0 0 10 Purchase Materials C 1.5 3 4.5 1.5 4 22 Order Equipment D 2 3 5 0 0 8 Order Furniture E 4 12.5 16.5 0 0 8 Concrete Floor F 0.5 4.5 5 0.5 3 15 Erect Frame G 4 5 9 0 7.87637E-11 20 Install Electrical H 2 9 11 0 0 12 Install Plumbing I 2.5 9 11.5 1.5 8 21 Install Drywall/Roof J 2 11.5 13.5 0 0 10 Bathrooms K 2 13 15 0 0 8 Install Equipment L 1.5 13.5 15 1.5 8 22 Finish/Paint Inside M 1.5 15 16.5 1.5 8 18 Tile Floors N 2.5 16.5 19 0.5 0.75 6.75 Install Furniture O 2.5 16.5 19 1.5 6 14 Finish/Paint Outside P 4 13.5 17.5 0 0 18 88

Baja Burrito Restaurants Operating within a fixed budget Baja Burrito has the policy of not funding more than 12.5% above the normal cost projection. Crash budget = (12.5%)(200,000) = 25,000 Management wants to minimize the project completion time under the budget constraint. 89

The crash funds become a constraint Minimize X(FIN) 5.5Y A + 10Y B + 2.67Y C + 4Y D + 2.8Y E + 6Y F + 6.67Y G + 10Y H + 5.33Y I + 12Y J + 4Y K + 5.33Y L + 1.5Y N + 4Y O + 5.33Y P The completion time becomes the objective function X(FIN) 19 Baja Burrito Restaurants Operating within a fixed budget 5.5Y A + 10Y B + 2.67Y C + 4Y D + 2.8Y E + 6Y F + 6.67Y G + 10Y H + 5.33Y I + 12Y J + 4Y K + 5.33Y L + 1.5Y N + 4Y O + 5.33Y P 25 The other constraints of the crashing model remain the same. 90

Baja Burrito Restaurants Budget Spreadsheet CRASHING ANALYSIS TOTAL PROJECT COST 225 PROJECT NORMAL COST 200 COMPLETION TIME 23.3125 PROJECT CRASH COST 300 ACTIVITY NODE Completion Time Start Time Finish Time Amount Crashe d Cost of Crashing Revisions/Approva ls A 5 0 5 0 0 25 Grade Land B 1 5 6 0 0 10 Purchase Materials C 1.5 5 6.5 1.5 4 22 Order Equipment D 2 5 7 0 0 8 Order Furniture E 4 16.3125 20.3125 0 0 8 Concrete Floor F 1 6.5 7.5 0 0 12 Erect Frame G 4 7.5 11.5 0 0 20 Install Electrical H 2 12 14 0 0 12 Install Plumbing I 2.5 11.5 14 1.5 8 21 Install Drywall/Roof J 2 14 16 0 0 10 Bathrooms K 2 14 16 0 0 8 Install Equipment L 1.5 16 17.5 1.5 8 22 Finish/Paint Inside M 2.8125 17.5 20.3125 0.1875 1 11 Tile Floors N 3 20.3125 23.3125 0 0 6 Install Furniture O 3 20.3125 23.3125 1 4 12 Finish/Paint Outside P 4 19.3125 23.3125 0 0 18 Total Cost 91

7.11 PERT/COST PERT/Cost helps management gauge progress against scheduled time and cost estimates. PERT/Cost is based on analyzing a segmented project. Each segment is a collection of work packages. PROJECT Work Package 1 Activity 1 Activity 2 Work Package 2 Activity 3 Activity 5 Work Package 3 Activity 4 Activity 6 92

Work Package - Assumptions Once started, a work package is performed continuously until it is finished. The costs associated with a work package are spread evenly throughout its duration. 93

Monitoring Project progress For each work package determine: Work Package Forecasted Weekly cost = Budgeted Total Cost for Work Package Expected Completion Time for Work Package (weeks) Value of Work to date = p(budget for the work package) where p is the estimated percentage of the work package completed. Expected remaining completion time = (1 p)(original Expected Completion Time) 94

Monitoring Project progress Completion Time Analysis Use the expected remaining completion time estimates, to revise the project completion time. Cost Overrun/Underrun Analysis For each work package (completed or in progress) calculate Cost overrun = [Actual Expenditures to Date] - [Value of Work to Date]. 95

Monitoring Project Progress Corrective Actions A project may be found to be behind schedule, and or experiencing cost overruns. Management seeks out causes such as: Mistaken project completion time and cost estimates. Mistaken work package completion times estimates and cost estimates. Problematic departments or contractors that cause delays. 96

Monitoring Project Progress Corrective Actions Possible Corrective actions, to be taken whenever needed. Focus on uncompleted activities. Determine whether crashing activities is desirable. In the case of cost underrun, channel more resources to problem activities. Reduce resource allocation to non-critical activities. 97

TOM LARKIN s MAYORAL CAMPAIGN Tom Larkin is running for Mayor. Twenty weeks before the election the campaign remaining activities need to be assessed. If the campaign is not on target or not within budget, recommendations for corrective actions are required. 98

MAYORAL CAMPAIGN Status Report Work Package Expenditures ($) Status A Hire campaign staff 2,600 Finish B Prepare position paper 5,000 Finish C Recruit volunteers 3,000 Finish D Raise funds 5,000 Finish E File candidacy papers 700 Finish F Prepare campaign material 5,600 40% complete G Locate/staff headquarter 700 Finish H Run personal campaign 2,000 25% complete I Run media campaign 0 0% complete Work packages to focus on 99

MAYORAL CAMPAIGN Completion Time Analysis The remaining network at the end of week 20. F 7.8 H 15 (1-p)(original expected completion time)=(1-0.25)(20)=15 I 9 20+7.8=27.8 20+15=35 Finish 27.8+9=36.8.8 The remaining activities are expected to take 0.8 weeks longer than the deadline of 36 weeks. 100

MAYORAL CAMPAIGN Project Cost Control Budgeted Values Work Total Total Percent EstimateActual Cost Package Time Cost Completed Value Value Ocerrun A 4 2000 100% 2,000 2,600 600 B 6 3,000 100% 3,000 5,000 2000 C 4 4,500 100% 4,500 3,000-1500 D 6 2,500 100% 2,500 5,000 2,500 E 2 500 100% 500 700 200 F 13 13,000 40% 5200 5,600 400 G 1 1,500 100% 1,500 700-800 H 20 6,000 25% 1,500 2,000-500 I 9 7,000 0% 0 0 0 Total 40,000 20,700 24,600 1013,900

MAYORAL CAMPAIGN Results Summary The project is currently.8 weeks behind schedule There is a cost over-run of $3900. The remaining completion time for uncompleted work packages is: Work package F: 7.8 weeks, Work package H: 15 weeks, Work package I: 9 weeks. Cost over-run is observed in Work package F: $400, Work package H: $500. 102

Copyright 2002 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that named in Section 117 of the United States Copyright Act without the express written consent of the copyright owner is unlawful. Requests for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. Adopters of the textbook are granted permission to make back-up copies for their own use only, to make copies for distribution to students of the course the textbook is used in, and to modify this material to best suit their instructional needs. Under no circumstances can copies be made for resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information contained herein. 103