EPC Contracts Key Issues to Consider. Ran Chakrabarti Partner May 2018

Similar documents
Construction and Infrastructure Contracts. 30 th August 2015, NJA, Bhopal. Sujit Ghosh Partner & National Head, Advaita Legal, New Delhi

Due Diligence checklist for [insert project name]

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management

DOUKPSC04 Rev Feb 2013

Emtelle UK Limited Conditions Of Sale Of Goods

Terms & Conditions Supply of Goods or Services

Session 3 by Zoltán Záhonyi, FIDIC AIT,

GARDEN DESIGNER / LANDSCAPER TERMS AND CONDITIONS BUSINESS CLIENTS

Sub Contract Agreement

Standard Terms & Conditions for Purchase Order

IPP s Project Risk Classification

DRAWINGS AND DESCRIPTIONS GENERAL CONDITIONS CONCLUSION OF THE CONTRACT, MINIMUM ORDER VALUE & PURCHASE ORDER CHANGES/CANCELLATION DEFINITIONS

COAA EPC Contract Philosophy

Mega Energy Projects What s in the Contract? Bali, Indonesia, October 2013 Glen Warwick, Partner, Clyde & Co Australia

VIRIDOR WASTE MANAGEMENT LIMITED TERMS AND CONDITIONS OF TRADE

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager as Owner s Agent

Subcontracting in UAE

Top Ten Tips for Negotiating an LTSA

ETTORE ZANON S.p.A. GENERAL CONDITIONS OF PURCHASE

RAIL SETTLEMENT PLAN LIMITED. [SUPPLIER or RETAILER] ACCREDITATION CONTRACT v01-00

Suspension and Termination

JC PAYNE SPECIALIST SERVICES LIMITED TERMS AND CONDITIONS FOR REPAIR AND MAINTENANCE

MT WELD MINING PTY LTD ACN Purchase Order Terms and Conditions for the Supply Of Goods and/or Services

EIMSKIP GENERAL TERMS AND CONDITIONS FOR PURCHASE OF GOODS AND/OR SERVICES

ACCEPTANCE OF CONTRACT/TERMS AND CONDITIONS

JC PAYNE SPECIALIST SERVICES LIMITED TERMS AND CONDITIONS FOR SERVICE

Subcontracting. Module 7

AIA Document B141 TM 1997 Part

Western Water Development Consultant Accreditation Deed

Fixed-to-Mobile satellite services

Atlantis Industries Corporation Terms and Conditions

SAMPLE CONTRACT BETWEEN THE BOARD OF COMMISSIONERS OF THE PORT OF NEW ORLEANS AND CONTRACTOR NAME FOR SERVICES

Copyright RBL Bank Ltd.

CONSULTING AGREEMENT STANDARD TERMS AND CONDITIONS

Comparative analysis of key issues in D&C contracts in recent social infrastructure PPPs

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk

Nutreco General Purchase Terms and Conditions

Pleece&Co LTD. Terms and Conditions +44 (0)

General Terms and Conditions of Sale

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES

AGREEMENT FOR ENGINEERING SERVICES. J.R.MacKenzie, P.Eng Goodlad Street Burnaby, BC, V5E 2H9 (herinafter called ENGINEER)

QIOPTIQ LIMITED (UK) CONDITIONS OF SALE

Conditions of Contract for PLANT and Design-Build

General Conditions for Purchase (CG-2)

Front Page. Supplier: [INSERT SUPPLIER DETAILS]

AIF GENERAL CONDITIONS (Commercial Projects)

STANDARD TERMS FOR SPARE PARTS AND/OR SITE SERVICES

GENERAL TERMS AND CONDITIONS 1 DEFINITIONS... 3

JPL Telecom Limited Conditions of Sale. The customer's attention is drawn in particular to the provisions of clause 9.

COAA EPC Contract Philosophy

SUPPLIER - TERMS AND CONDITIONS Materials and Goods

GENERAL TERMS AND CONDITIONS. Researchpark Haasrode, Romeinsestraat 10, 3001 Heverlee, Belgium VAT (BE) RLP Leuven

Contract means the contract for the purchase and/or sale and/or hire of the Goods and/or the supply of Services.

MASTER SUPPLY AND SERVICES AGREEMENT BETWEEN THE CROWN IN RIGHT OF ONTARIO AS REPRESENTED BY THE MINISTER OF TRANSPORTATION. - and - ACCENTURE INC.

CS ENERGY LIMITED SERVICE CONDITIONS

Form of Agreement Between the Client And the Quantity Surveyor

1.2 The "Supplier" shall mean the legal or natural person supplying the Works to MSD.

End User Subscription Agreement. 1. Scope; Procurement and Provisioning by Affiliates; Subscription Services Users.

TO THE MEMBERS OF THE COMMITTEES ON GROUNDS AND BUILDINGS AND FINANCE: DISCUSSION ITEM EXECUTIVE SUMMARY

PERMIT TO ENTER YOU ARE REQUIRED TO COMPLY WITH THE ENDORSEMENTS AND DETAILS SHOWN ON THIS PERMIT

C O N T R A C T. between

SAFETY FIRST GRANT CONTRACT

GENERAL PURCHASE CONDITIONS. entered into as defined in 1751 subpar. 1, Act No. 89/2012 Coll., Civil Code, as amended (the Civil Code" hereinafter)

ACA UNIFORM TERMS AND CONDITIONS

INTRODUCTORY NOTE ORGALIME GENERAL CONDITIONS FOR MAINTENANCE - M Scope of use. No guarantee as to results. Contents of the individual contract

General Conditions of Purchase of BASF Holdings South Africa (Pty) Ltd and its Affiliated Companies Located in South Africa

GENERAL TERMS AND CONDITIONS FOR PURCHASE OF GOODS AND SERVICES. MSD Polska sp. z o.o. MSD Polska Dystrybucja Sp. z o.o.

High Court rules that in-transit sale in turnkey contracts not eligible for exemption under Section 6(2) of the Central Sales Tax Act

Standard Form of Agreement Between. Owner and Design-Builder Cost Plus Fee with an Option for a Guaranteed Maximum Price

CONSULTING SERVICES AGREEMENT [Lump Sum]

MIX ENERGY IN MOROCCO. Prospects for the development of ENR. Amman 08/09 October 2017

Dickinson College Purchase Order Terms and Conditions

2018 Limelight Networks, Inc. All Rights Reserved

AKD TIMBER TRADING PTY LTD ACN TERMS OF SALE

Implementation Planning

SOUTHERN COMMUNICATIONS LIMITED TELEPHONE SYSTEMS - TERMS AND CONDITIONS OF SALE

Proposal and Agreement for Construction on Purchaser s Lot

MULTI PACKAGING SOLUTIONS CONDITIONS OF SALE (IRELAND)

SHORT FORM STANDARD SUBCONTRACT. This Agreement is made this day of, 20, between

Web-1 Hosting Service Agreement

FATIGUE TECHNOLOGY INC. PURCHASE ORDER TERMS AND CONDITIONS DATED JANUARY 4, 2006

BAR PROCESSING CORPORATION ( BPC ) TERMS AND CONDITIONS FOR SERVICES

SUMMARY OF ENGINEERING SERVICES MASTER SERVICES AGREEMENT

Fan and Ventilation Ltd, Terms & Conditions

2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals

Terms & Conditions of Business

SOUTHERN RESPONSE CANTERBURY EARTHQUAKE RECONSTRUCTION PROJECT GENERAL CONDITIONS OF CONTRACT FOR HOUSING REBUILD AND REPAIRS

Document A SP General Conditions of the Contract for Construction, for use on a Sustainable Project, Construction Manager as Adviser Edition

Purchase Order Terms and Conditions

TERMS OF BUSINESS. Any Enquiry or Application will be processed accordance with these Terms which you agree to these Terms.

Uncontrolled If Printed

General Terms and Conditions of A1 Telekom Austria AG for Training Services. Version January 2018

THIS CONSTRUCTION CONTRACT ( Contract ) dated as of ( Owner ) and ( Contractor ) having a principal place of business at.

Public Private Partnerships (PPPs) Projects

DESERT COMMUNITY COLLEGE DISTRICT General Terms and Conditions

ConsensusDocs 751 STANDARD SHORT FORM AGREEMENT BETWEEN CONSTRUCTOR AND SUBCONTRACTOR

Contract Administration Final Exam

VALDOSTA STATE UNIVERSITY STANDARD PURCHASE ORDER TERMS AND CONDITIONS

Document A201 TM 2007 SP

REGIONAL TRANSPORTATION COMMISSION OF SOUTHERN NEVADA. JARC and NEW FREEDOM PROJECTS SUBRECIPIENT AGREEMENT #, 2013

Transcription:

EPC Contracts Key Issues to Consider Ran Chakrabarti Partner May 2018

OVERVIEW Model Documents Scope of Work & Technical Specifications Acceptance & Testing Price & Payment Delay & Defects Suspension & Termination Force Majeure Performance Security Other Considerations

MODEL DOCUMENTS International engineering, procurement and construction contracts ( EPC Contracts ) are generally based upon the FIDIC series FIDIC has a range of off-the-peg standard forms for the construction of major civil engineering projects (the Works ) Red, Silver and Yellow books, depend on the scope of the Works to be carried out by the Contractor In India, there is generally, no accepted standard form contract and the choice of precedent is often determined by the Contractor It is imperative that your construction contract contains provisions which cover - design and construction responsibility - construction milestones - acceptance testing - remedies for delay and non performance, suspension, variation and termination It is essential that the technical specifications and performance criteria in the schedules are checked and confirmed by your client s technical adviser

SCOPE OF WORK & TECHNICAL SPECIFICATIONS Who has design responsibility? Is there a definition of Good Industry Practice benchmarking the performance of the obligations of the contractor? What responsibility does the Employer assume in relation to the plans, designs or technical information provided to the Contractor? Does the contract require the Contractor to take responsibility for those plans, designs or technical information provided by the Employer? If so, has the Contractor confirmed that those plans, designs and technical information are within its capability? Indemnity in the event that those plans, designs and technical information belong to a third party? Will the Technical Specifications and the Performance Criteria meet third party requirements?

CONSTRUCTION, ACCEPTANCE & TESTING Does the contract contain clear construction milestones, do they make sense? Do timelines for subcontracted portions of the works (for example, civil, electrical, mechanical) dovetail with each other? Sections of the Works and overall completion of the Works? Is their a regime for the acceptance testing process? What happens if the Project fails the performance tests? - Unlimited remedy of defects by the Contractor? - Termination and recovery of damages? - Take over by the Employer and Contractor to pay liquidated damages? Termination options should be controlled under the Finance Documents What is the effect of the Project passing the performance tests? Does passing the performance tests exclude the Contractor from future liability for defects?

PAYMENT & PRICE Is the Contract Price a fixed lump sum amount? Are there clearly identified additional payments and hidden costs? Does the Contract Price include all contingencies or is it subject to revision to account for fluctuations? How are payments to be structured? Is it payable up-front and in advance? If so, there should be an Advance Payment Bond to mitigate the risk of Contractor breach or insolvency What are the penalties for delay in making payments? Does the contract drip feed the payment of the Contract Price in accordance with the achievement of certain Milestones and are they achievable in the opinion of the Technical Advisers?

DELAY & DEFECTS What happens when the Project is delayed? What is the reason for delay? What happens if the Project doesn t meet the Performance Criteria? Are there delay liquidated damages provisions? Are there performance liquidated damages provisions? Are liquidated damages capped? What losses are foreseeable as a result of breach? What about consequential losses? Should they be included? Consider whether recovered sums will meet third party liabilities How long is the defects liability period?

SUSPENSION & TERMINATION In what circumstances can the Works be suspended? Can the Contractor terminate following prolonged suspension? What is the cost to the Employer for suspending the Contractor? Can the Employer terminate for: - Convenience - Contractor s breach (subject to cure periods) - Prolonged delay - Prolonged force majeure - Contractor Insolvency Can the Employer take over any subcontract to continue execution of the Works?

SUSPENSION & TERMINATION Can the Contractor terminate for: - Employer s breach (subject to cure periods) - Prolonged force majeure - Employer Insolvency Is there a Tripartite or Direct Agreement with the Lenders suspending the ability of the Contractor to terminate while the Lenders consider substitution of the contract? If the contract is terminated, in what circumstances is the Contractor entitled to claim loss of profits on outstanding work? Are there any limits on what the Contractor can claim for termination in these circumstances?

FORCE MAJEURE How broad is the force majeure clause? Does it include events which are within the reasonable control of either party? What is the consequence of an event of force majeure? Is the Contractor entitled to an extension of time? Can the Employer or the Contractor terminate the agreement for pro-longed force majeure? Does prolonged force majeure need to be continuous (or an aggregation of time)? When can a party terminate for prolonged force majeure and what are the consequences? Does the force majeure provision in other related contracts dovetail? Will an event of force majeure under the contract constitute an event of force under any related off-take agreement or supply agreement?

PERFORMANCE SECURITY Is the Employer comfortable with the balance sheet of the Contractor? Does the contract anticipate the provision of a Performance Bond by the Contractor? Is the Performance Bond payable on demand (essentially for Employers and Lenders) or does fault need to be established? Is Performance Bond Issuer acceptable to the Employer and the Lenders? Are the terms of the Performance Bond satisfactory to the Employer and is it assignable to the Lenders? When does the Performance Bond lapse? Does it coincide with the end of the Defects Liability Period? Can the value of the Performance Bond be adjusted in accordance with any change in the Contract Price? Is there an additional Parent Company Guarantee and is it assignable?

OTHER CONSIDERATIONS Assignability & Subcontracting - The rights of the Employer should be assignable as part of the Lender s security package - Is assignment subject to consent from any third party? - The Contractor should not be able to subcontract or assign his obligations without the prior written consent of the Employer and then only to a subcontractor that has the particular skill and expertise to execute the Works - The identity of all subcontractors should be subject to the approval of the Employer (and the Lenders) - Subcontracting should not release the Contractor from its liabilities under the contract to execute the Works in accordance with the Technical Specifications and the Performance Criteria - Consider whether sub-contracts should be in place to essentially reflect the obligations to construct the Works that are subcontracted and consider whether Tripartite or Direct Agreements are necessary

OTHER CONSIDERATIONS Dispute Resolution - Consider carefully the dispute resolution clause and consider whether it should mirror the provisions of other related agreements - If arbitration is specified, consider whether it is effective and consider in the context of cross border Projects whether relevant jurisdictions are New York Convention signatories and the Official Gazette notifying those jurisdictions who s awards that the Government of India recognizes - Can the award be enforced against the assets of the other party effectively? Confidentiality - Do confidentiality restrictions imposed on the parties enable them to pass on information to legal, technical, financial and insurance advisers?

OTHER CONSIDERATIONS Environmental Regulations - Consider to what environmental regulations are applicable to the Project at a local level, and, to the extent that the Lenders are foreign, to what extent local Contractors must comply with the environmental regulations that foreign Lenders are subject to Final Acceptance Certificate - Consider to what extent the issuance of a Final Acceptance Certificate binds the Employer from bringing future claims against the Contractor? Variations - Does the contract provide a mechanism for variations to the Works (a Variation ) - If so, consider whether the contract contains provisions providing for cost escalations or cost savings as a result of a Variation

OTHER CONSIDERATIONS Variations - Does the contract provide for an extension of time in the event that a Variation is instructed by the Employer? - Consider what extent a Variation under the construction contract will impact the obligations of the Employer under other related Project Agreements? - For example, should a Variation be instructed, it is highly likely that the completion timetable will need to be extended - Therefore, the obligation to deliver pursuant to any third party off-take agreement will need to be extended to avoid the risk of the Employer being liable for delay liquidated damages thereunder - A material Variation should require Lender consent under the related Finance Documents

OTHER CONSIDERATIONS Reporting - Does the contract provide obligations on the Contractor to provide regular construction progress reports to the Employer - Do those reports contain information relating to events which could affect the progress of the Works? - Can the Employer and the Lenders inspect the Project during construction? - Do the reporting requirements and the timelines for reporting dovetail with obligations that the Employer has to the Lenders under the Finance Documents?

OTHER CONSIDERATIONS Project Specific Risk - Has the nature of the site of the Project been thoroughly analyzed by the Employer s technical advisers and the Lender s Technical Advisers? - Are there access issues relating to the Project site which indicate the likelihood of delay? - Has the land necessary for the construction of the Project been transferred to the Employer? Is compulsory land acquisition necessary? Are there occupants on the land? - To what extent are atmospheric, meteorological, topographical, hydrological, geological and subsurface conditions relevant to the particular Project? - If so, have relevant technical advisers been appointed to advise the Employer and the Lenders in relation thereto? - To what extent has the availability of plant, equipment, natural resources, parts, consumables, fuel, water, power and other utilities been assessed? - Have local applicable laws and regulations been reviewed in relation to the Project? - What is the impact of a change in law relating to a cost escalation, a nationalization or an expropriation?

CONTACT BANGALORE DELHI 101, 1 st Floor, Embassy Classic 2nd Floor, Block D, The Mira #11, Vittal Mallya Road Mathura Road, Ishwar Nagar Bangalore, 560 001 New Delhi 110 065 T: +91 80 4072 6600 T: +91 120 472 8100 E: bangalore@induslaw.com E: delhi@induslaw.com HYDERABAD MUMBAI 204, Ashoka Capitol 1002A, Tower 2, Indiabulls Financial Center Road No.2, Banjara Hills Senapati Bapat Marg, Lower Parel (W) Hyderabad, 500 034 Mumbai, 400 013 T: +91 40 4026 4624 T: +91 22 4920 7200 E: hyderabad@induslaw.com E: mumbai@induslaw.com DISCLAIMER This presentation is for information purposes only. Nothing contained herein is, purports to be, or is intended as legal advice and you should seek legal advice before you act on any information or view expressed herein. Although we have endeavored to accurately reflect the subject matter of this presentation, we make no representation or warranty, express or implied, in any manner whatsoever in connection with its contents. No recipient of this presentation should construe it as an attempt to solicit business in any manner whatsoever.