SWEN 256 Software Process & Project Management

Similar documents
Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Project planning and creating a WBS

CISC 322 Software Architecture

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

UNIT-II Project Organization and Scheduling Project Element

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

Textbook: pp Chapter 11: Project Management

Unit 3 Research Project. Eddie S. Jackson. Kaplan University. IT511: Information Systems Project Management

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

After complete studying this chapter, You should be able to

Project Management Chapter 13

CHAPTER 9: PROJECT MANAGEMENT

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

Appendix B: Glossary of Project Management Terms

ETSF01: Software Engineering Process Economy and Quality

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

POLYTECHNIC OF NAMIBIA

The Project Times and Costs

PASS4TEST. IT Certification Guaranteed, The Easy Way! We offer free update service for one year

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

Systems Engineering. Engineering 101 By Virgilio Gonzalez

Project Management -- Developing the Project Plan

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark


Construction Management

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

Exam Questions PMI-SP

Teori Pengambilan Keputusan. Week 12 Project Management

IE 102 Spring Project Management

Real-World Project Management. Chapter 15

MS Project 2007 Page 1 of 18

Vendor: PMI. Exam Code: CA Exam Name: Certified Associate in Project Management. Version: Demo

Unit 5 Slide Lectures of 04/05/06 April 2017

Project Management. Basic Definitions: Project and Project Plan

Appendix A Decision Support Analysis

Research Methods Outline

Introduction to Project Management. Modeling after NYS ITS

JAYARAM COLLEGE OF ENGINEERING AND TECHNOLOGY DEPARTMENT OF INFORMATION TECHNOLOGY

Project Management Fundamentals

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2016

Outline. Project Management. Introduction. What is a Project?

Techniques to Assist Delivery of Projects

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri

IP-CIS : CIS Project Management

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

COPYRIGHTED MATERIAL. Index

MnDOT use of Calendars in Primavera P6

70-632_formatted. Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0

Project Controls Expo 16 th Nov 2016

1 of 14 4/27/2009 7:45 AM

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

DC Program and Project Managers Meeting #2

WHY ARE PROJECTS ALWAYS LATE?

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

Project Management. Session 5 Budgets and Estimation Andre Samuel

Project Risk Management

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

Management Management

PROJECT MANAGEMENT DIPLOMA COURSE

GPE engineering project management. Project Management in an Engineering Context

Project Planning. Planning is an important step in project execution. Planning means:

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

Project Progress HELP.PSPRG. Release 4.6C

Project Management. A Practitioner s Guide. Steven M. Bragg

PMI - Dallas Chapter. Sample Questions. March 22, 2002

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

Chapter 5: Estimating Project Times and Costs 4KF3

Chapter16Project Management and. Scheduling Project management

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan

Allocate and Level Project Resources

SCM 301 (Lutz) Exam 1 Practice Exam Solutions

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

PMI PMI-SP. PMI Scheduling Professional. Download Full Version :

Making sense of Schedule Risk Analysis

PMP032 Project Management Leadership Skills

Chapter 9: Reducing Project Duration 4KF3

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

A Project Management Guide for Researchers

MODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT

Braindumps.PMI-SP.323 questions

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

PROJECT MANAGEMENT BODY OF KNOWLEDGE

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

Project Theft Management,

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

Crashing the Schedule An Algorithmic Approach with Caveats and Comments

PROJECT COST MANAGEMENT

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2

Managing Project Risk DHY

Earned Value Management Handbook. arne. alu

Guide to Earned Value Management (EVM) Scalability for Non-Major Acquisition Implementations

Quality Project Management

Project Management with Brief Information regarding CPM and PERT Methods

Scheduling Resources and Costs

Transcription:

SWEN 256 Software Process & Project Management

Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end dates, relationships, and resources. Track: Uses monitoring and tools to determine if plans, estimates, and schedules are accurate Planning Estimating Scheduling Tracking

1. Identify what needs to be done o Work Breakdown Structure (WBS) 2. Identify how much (the size) o Size estimation techniques 3. Identify the dependency between tasks o Dependency graph, network diagram 4. Estimate total duration of the work to be done o The actual schedule

You need to decompose your project into manageable chunks ALL projects need this step Divide & Conquer Two main causes of project failure o Forgetting something critical o Ballpark estimates become targets How does partitioning help this?

A Project: functions, activities, tasks

a.k.a. WBS

Work Break Down Structure (WBS): a check list of the work that must be accomplished to meet the project objectives. The WBS lists the major project outputs and those departments or individuals primarily responsible for their completion.

0.0 Retail Web Site 1.0 Project Management 2.0 Requirements Gathering 3.0 Analysis & Design 4.0 Site Software Development 4.1 HTML Design and Creation 4.2 Backend Software 4.2.1 Database Implementation 4.2.2 Middleware Development 4.2.3 Security Subsystems 4.2.4 Catalog Engine 4.2.5 Transaction Processing 4.3 Graphics and Interface 4.4 Content Creation 5.0 Testing and Production

From: http://www.hyperthot.com/pm_wbs.htm

Process WBS a.k.a Activity-oriented Ex: Requirements, Analysis, Design, Testing Typically used by PM Product WBS a.k.a. Entity-oriented Ex: Financial engine, Interface system, DB Typically used by engineering manager Hybrid WBS: both above This is not unusual Ex: Lifecycle phases at high level with component or featurespecifics within phases Rationale: processes produce products

List of Activities, not Things List of items can come from many sources o SOW, Proposal, brainstorming, stakeholders, team Describe activities using bullet language o Meaningful but terse labels All WBS paths do not have to go to the same level Do not plan more detail than you can manage

Generic term for discrete tasks with definable end results The one-to-two rule o Often at: 1 or 2 persons for 1 or 2 weeks Basis for monitoring and reporting progress o Can be tied to budget items (charge numbers) o Resources (personnel) assigned Ideally shorter rather than longer o Longer makes in-progress estimates needed o These are more subjective than done o 4/40 or 8/80 rule ( shortest/longest duration) o Not so small as to micro-manage

PM must map activities to chosen lifecycle Each lifecycle has different sets of activities Integral process activities occur for all o Planning, configuration, testing Operations and maintenance phases are not normally in plan (considered post-project) Some models are straightened for WBS o Spiral and other iterative models o Linear sequence several times Deliverables of tasks vary by methodology

Top-Down Bottom-Up Analogy Rolling Wave o 1 st pass: go 1-3 levels deep o Gather more requirements or data o Add more detail later Post-its on a wall All WBS Techniques rely upon Expert Judgment!

Top-down o Start at highest level o Systematically develop increasing level of detail o Best if The problem is well understood Technology and methodology are not new This is similar to an earlier project or problem o But is also applied in majority of situations

Bottom-up o Start at lowest level tasks o Aggregate into summaries and higher levels o Cons o Pros Time consuming Needs more requirements complete Detailed

Analogy o Base WBS upon that of a similar project o Use a template o Analogy also can be estimation basis o Pros Based on past actual experience o Cons Needs comparable project

Brainstorming o Generate all activities you can think of that need to be done o Group them into categories Both Top-down and Brainstorming can be used on the same WBS Remember to get the people who will be doing the work involved (buy-in matters!)

Network scheduling Costing Risk analysis Organizational structure Control Measurement

Should be easy to understand Some companies have corporate standards for these schemes Some top-level items, like Project Mgmt. are in WBS for each project o Others vary by project What often hurts most is what s missing Break down until you can generate accurate time & cost estimates Ensure each element corresponds to a deliverable

Tools and Techniques

Milestone Chart Gantt chart Network Techniques o o CPM (Critical Path Method) PERT (Program Evaluation and Review Technique)

Gantt chart is a means of displaying simple activities or events plotted against time or dollars Most commonly used for exhibiting program progress or for defining specific work required to reach an objective Gantt charts may include listing of activities, activity duration, scheduled dates, and progress-todate

Advantages: o Easy to understand o Easy to change Disadvantages: o Only a vague description of the project o Does not always show interdependency of activities o May not show results of an early or late start of an activity

A precedence network diagram is a graphic model portraying the sequential relationship between key events in a project. Initial development of the network requires that the project be defined and thought out. The network diagram clearly and precisely communicates the plan of action to the project team and the client.

Task Duration Dependencies A - Architecture & design strategy 9 start B - Decide on number of releases 5 A C - Develop acceptance test plan 7 A D - Develop customer support plan 11 B,C E - Final sizing & costing 8 D Start A 9 B 5 D 11 8 E End 9 C 7

Critical Path Method (CPM) tries to answer the following questions: What is the duration of the project? By how much (if at all) will the project be delayed if any one of the activities takes N days longer? How long can certain activities be postponed without increasing the total project duration?

Sequence of activities that have to be executed one after another Duration times of these activities will determine the overall project time, because there is no slack/float time for these activities If any of the activities on the critical path takes longer than projected, the entire project will be delayed by that same amount Critical path = Longest path in the precedence network (generally, the longest in time)

Start A 9 B 5 D 11 8 E End 9 C 7 Critical Path = A C D E (35 time units) Critical Tasks = A,C,D,E Non-Critical Path = A-B-D-E Non-Critical Tasks = B (only)

Task Duration Depend Earliest Start Earliest Finish Latest Start Latest Finish A 9 none 0 9 0 9 B 5 A 9 14 11 16 C 7 A 9 16 9 16 D 11 B,C 16 27 16 27 E 8 D 27 35 27 35 Start A 9 B 5 D 11 8 E End Slack time maximum allowable delay for a noncritical activity. 9 C 7 Task slack time = LS ES - or - Task slack time = LF - EF Task B has 2 time units of slack time

Move Obstacles Sweep Floor Sweep Debris into Dustpan Empty Dustpan in Garbage Put Broom & Dustpan Away 4 Min 8 Min 2 Min 1 Min 2 Min Start Find Broom & Dustpan 3 Min End Find Mop & Bucket Pour Soap into Bucket Fill Bucket with Water Mop Floor Clean Used Mop & Bucket 3 Min 1 Min 2 Min 15 Min 4 Min Choose Soap 4 Min What is the Critical Path? What is the Near Critical Path? What is the Float/Slack of Choose Soap? What is the float of Mop Floor?

Move Obstacles Sweep Floor Sweep Debris into Dustpan Empty Dustpan in Garbage Put Broom & Dustpan Away 4 Min 8 Min 2 Min 1 Min 2 Min 0 Early 4 4 Early 12 12 Early 14 14 Early 15 15 Early 17 0 Late 4 4 Late 12 12 Late 14 30 Late 31 31 Late 33 Start Find Broom & Dustpan 3 Min 0 Early 3 1 Late 4 End Find Mop & Bucket Pour Soap into Bucket Fill Bucket with Water Mop Floor Clean Used Mop & Bucket 3 Min 1 Min 2 Min 15 Min 4 Min 0 Early 3 4 Early 5 5 Early 7 14 Early 29 29 Early 33 8 Late 11 11 Late 12 12 Late 14 14 Late 29 29 Late 33 Choose Soap 4 Min 0 Early 4 7 Late 11 Calculate Float Late Start Early Start or Late Finish Early Finish Time Start-Early-Finish Start-Late-Finish

Fast Tracking Work critical path activities in parallel, instead of sequentially. Sweep Floor 8 Min Sweep Debris into Dustpan 2 Min Becomes Sweep Floor 9 Min Sweep Debris into Dustpan Crashing Cost and schedule tradeoffs (Time Money) with the end result of reducing overall time to completion Other Ways (Less preferred but sometimes needed) o Reduce Scope/Quality of product o Increase resources, Reduce risks o Say no: Sometimes schedule compression just isn t an option 9 Min

A Most optimistic time M Most likely time B Most pessimistic time R 2, 4, 5 S Expected Time = (a + 4m + b)/6 Expected Time = 3.8

Task Conceptual Design Program Specification Coding Documentation User Manual Production Testing Complete? Complete Complete In Progress In Progress Not Started Not Started

Task How Complete? Conceptual Design 200/200 Program Specification 300/300 Coding 150/600 Documentation 10/100 User Manual Production 0/400 Testing 0/500 660 / 2100 * 100 = 31.4% complete

Earned Value (EV) is a methodology used to control a project It provides a uniform measure for project progress for the entire project or any sub-element Provides a consistent method of project progress and performance Provides a basis for cost performance analysis of a project

1. Establish a WBS to divide the project into manageable parts 2. Identify the activities required for the current project 3. Allocate the effort required for each activity 4. Schedule the activities over time and resources 5. Analyze/review the schedule (continued)

6. Update the schedule by reporting activity progress 7. Enter the actual cost on the activities 8. Execute the Earned Value calculations 9. Analyze the data and make course corrections as necessary

Establish a common value scale for every task, regardless of the type of work involved (software projects use effort) Total effort for the entire project is estimated Every task is given a planned value based on its estimated percentage of the total project effort Completion of a task results in a credit, or an earned value, of the value allocated to the task

Total Project Effort: 1000 person hours Task A Estimate: 15 person hours Planned Value: 1.5 Completing task A contributes 1.5 to the cumulative earned value total for the project

Earned value credit is given only when the task is 100% complete Partially completed tasks are NOT given partial credit (in most software projects) Large tasks can/must be broken into subtasks Size tasks up to 80 person-hours; aim for 2 to 4 task completions per week

Planning, Estimating, Scheduling, and Tracking are a continuum Projects need to be partitioned for manageability o Work Breakdown Structures are a great way to do this Sequencing Tasks & Activities is vital o Gantt Charts allow quick reference o Network Techniques such as Precedence Network Diagrams, the Critical Path Method, and PERT Charts are useful tools Project Tracking is important for project visibility o The Earned Value Technique is a key tool in this