Comparison between the Red Book 1999 and the MDB Harmonised Edition 2010

Similar documents
1.5 Priority of Documents

Conditions of Contract for Construction

MDB Harmonised Particular Conditions

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M.

Conditions of Contract for PLANT and Design-Build

MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015)

(1) In these sub-contract conditions of agreement, the following words and phrases shall have the following meanings:-

Terms and Conditions Applicable to the Model Contract for Consulting Services

Section 7. General Conditions of Contract for the Procurement of Works

2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals

DOUKPSC04 Rev Feb 2013

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC)

Supply Contract Channel and Pipeline Standard Conditions Schedule 3. Version 2

A. Letter of Acceptance

Standard Supply Contract Mary Valley Water Supply Scheme (Distribution)

Design and Build of Passenger Terminal Building North Extension At Macau International Airport (RFQ-198) Section 2 Terms and Conditions of Contract

Bulk Water Supply Contract LMA Scheme. Version 1

MINISTRY OF FINANCE Procurement Policy Unit (Established under section 6 of the Public Procurement Act, 2015)

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management

Consultancy Services Contract

STANDARD PROFESSIONAL SERVICES CONTRACT. July, 2009: Edition 3 of CIDB document 1015

AIRPORT AUTHORITY HONG KONG

Amendments to Core Clauses

1 In these Domestic Sub-Contract Conditions the following expressions and terms shall have the meanings given below:

Insert Project Title Here Reference Version. Insert Title of Works Here. United Nations Office for Project Services ( UNOPS ) -and-

CS ENERGY LIMITED SERVICE CONDITIONS

Terms and Conditions Applicable to the Model Contract for Consulting Services

GCC: The GCC 2015 (3 rd Edition) Welcomed with Open Arms

CONDITIONS OF CONTRACT. The Builder must execute and complete the Works in a workmanlike manner and ensure the Works are adequately supervised.

GENERAL CONDITIONS OF CONTRACT

Suspension and Termination

CIlent/ConsuItant MODEL SERVICES AGREEMENT

Moxtra, Inc. DATA PROCESSING ADDENDUM

BETWEEN name. address. AND name (hereinafter called the Subcontractor ) address

AGREEMENT between The United Nations and

Scottish Conditions of Appointment of an Architect SCA/2014 (Apr 2015)

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

STANDARD BIDDING DOCUMENTS UNDER JAPANESE ODA LOANS

CONCODE Agreement for the appointment of project managers for commissions for construction projects in the NHS STATUS IN WALES ARCHIVED

CONDITIONS OF CONTRACT FOR QUOTATION

Danida Business Finance. Rules for Procurement

SECURITIES (COLLECTIVE INVESTMENT SCHEMES) REGULATIONS 2001 ARRANGEMENT OF REGULATIONS PART I PRELIMINARY

Veolia Group - General Conditions of Supply

GENERAL TERMS & CONDITIONS

AMENDMENTS TO GDLA 82 (re-printed 18 th June 2003) REVISED FAIR WAGES CLAUSE AND RELEVANT COMPLIANCE CERTIFICATES. Contents. - Clause 39 Fair Wages

Form of Agreement Between the Client And the Quantity Surveyor

HOW TO EXECUTE THIS DPA:

SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS

Appendix K Model Letters for Use by the Engineer

Contractual Awareness Introduction

Conditions of Appointment for an Architect for a Domestic Project 2010 (2012 revision) Incorporating Amendment 1, September 2011

CONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1

Workshop 4 FIDIC Contracts (Update on New Documents)

STANDARD TERMS FOR SPARE PARTS AND/OR SITE SERVICES

In every contract over $10,000, the provisions in A. and B. below apply: A. During the performance of this contract, the vendor agrees as follows:

Electronic & Mechanical Calibrations Pty Ltd Terms & Conditions of Trade Definitions Acceptance Change in Control 4.

DATA PROCESSING ADDENDUM

Insert heading depending. Insert heading depending on line on line length; please delete cover options once

PART TWO GENERAL CONDITIONS CHAPTER I. Application of the General Conditions CHAPTER II. Definitions

GENERAL TERMS AND CONDITIONS FOR THE SUPPLY OF GRAPHIC PRODUCTS 2010 (ALG 10)

Key Performance Indicators for the Provision of Medium Construction Related Works and Building Refurbishment for the University of Worcester

ROUGH DIAMOND SUPPLY AGREEMENT 1

INTERNATIONAL. Plant and Design - Build TRAINING PROGRAMME DECEMBER Conditions of Contract for EPC/Turnkey Projects

The terms and conditions of delivery stated below apply in full to contracts with

JAPAN INTERNATIONAL COOPERATION AGENCY. General Terms and Conditions for Japanese ODA Loans

FIDIC WORKSHOP 2016 GROUP 6

AGR Enterprises Pty Ltd T/A All About Cabinets Terms & Conditions of Trade

Client Quantity Surveyor Agreement 1998

ICE CLEAR US, INC. RULES

GENERAL TERMS AND CONDITIONS FOR SERVICES THE SWEDISH ARMED FORCES / FÖRSVARSMAKTEN

ISDA. International Swaps and Derivatives Association, Inc. U.S. EMISSIONS ALLOWANCE TRANSACTION ANNEX. to the Schedule to the ISDA Master Agreement

NZS 3915:2005 AMENDMENTS. No. Date of issue Description Entered by, and date

Session 3 by Zoltán Záhonyi, FIDIC AIT,

DATA PROCESSING ADENDUM

W-5 PROCUREMENT OF CIVIL WORKS UNDER SHOPPING PROCEDURES

Australian Standard. Subcontract conditions for design and construct. AS (Incorporating Amendment No. 1) AS

SECTION - IX FORMS AND PROCEDURES

Whereas the Contractor has entered into an agreement (the "Prime Contract") dated the, 20 with:

Heads of Terms of the Design Agreement for the Moscow Kazan Section of the Moscow Kazan Ekaterinburg High-Speed Railway Line

ETTORE ZANON S.p.A. GENERAL CONDITIONS OF PURCHASE

NHS Standard Contract 2016/17 General Conditions (full length)

The Standard Form of Minor Works Building Contract Edition. Issued by

STANDARD TRADING CONDITIONS

AGREEMENT ON SOCIAL SECURITY BETWEEN THE REPUBLIC OF THE PHILIPPINES AND THE SWISS CONFEDERATION

Townsville Office Furniture Pty Ltd Terms & Conditions of Trade Definitions Acceptance Change in Control 4. Price and Payment Delivery of Goods

DATA PROCESSING ADDENDUM

Document A Exhibit A

General Terms and Conditions of Verbrugge Terminals B.V. and Verbrugge Internationale Wegtransporten B.V. for provision of logistic and other services

First Source Hiring and Local Business Enterprise Policy

CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND

Terms of Business for Intermediaries. Effective from 17 May 2018

SDS ITA Registration Application Pack 2017

TRANSNET NATIONAL PORTS AUTHORITY RFP NUMBER TNPA 541 DESCRIPTION OF THE WORKS: PORT OF RICHARDS BAY - CONSTRUCTION OF PORT ENTRANCES AND ACCESS ROADS

General Conditions for Consultancy Services Agreements

FINANCIAL MANAGEMENT OF PARLIAMENT BILL

MANITOBA HOUSING SUPPLEMENTAL CONDITIONS CONTRACT #: XXXX GENERAL

Standard Form of Agreement Between. Owner and Design-Builder Cost Plus Fee with an Option for a Guaranteed Maximum Price

EMP Commercial Terms and Conditions AS AT DECEMBER 2015 ENERGY DONE BRIGHT

Transcription:

Comparison between the Red Book 1999 and the MDB Harmonised Edition 2010 Please note that this comparison is for guidance only and does not purport to be complete and exhaustive. All corrections and improvements would be welcomed via email to info@corbett.co.uk MDB 2010 Clause Nature of change 1.1.1.2 (if any) phrase taken out 1.1.1.4 Letter of Tender definition now includes or letter of bid 1.1.1.8-1.1.1.10 Appendix to Tender sub-clause taken out 1.1.1.9 Schedule of Payment Currencies title added to Bill of Quantities and Day work Schedule sub-clause 1.1.1.10 Contract Data sub-clause added Appendix to Tender changed to Contract Data 1.1.2.2 Appendix to Tender changed to Contract Data 1.1.2.4 Appendix to Tender changed to Contract Data 1.1.2.9 DAB changed to DB so named in the Contract, or other persons(s) appointed changed to appointed under sub-clause 20.2 1.1.2.11 Bank sub-clause added 1.1.2.12 Borrower sub-clause added 1.1.3.3 Appendix to Tender changed to Contract Data 1.1.3.6 provisions of the Particular Conditions replaced with Specification

1.1.3.7 as stated in the Appendix of Tender replaced with which extends over 365 days except if otherwise stated in the Contract Data 1.1.5.5 including vehicles purchased for the Employer and relating to the construction or operation of the works 1.1.5.6 Appendix to Tender changed to Contract Data 1.1.6.7 and to which Plant and Materials are to be delivered added 1.1.6.10 Notice of Dissatisfaction sub-clause added 1.2 (e) the word tender is synonymous added to Interpretation sub-clause Extra sentence is added at end: In these Conditions, provisions including 1.3 discharges added Appendix to Tender changed to Contract Data in both (a) and (b) 1.4 or other jurisdiction taken out of brackets Appendix to Tender changed to Contract Data x2 Sentence re: multiple languages replaced with the ruling language of the Contract shall be stated in the Contract Data language in which the Contract (or most of it) is written replaced with language for communications shall be the ruling language of the Contract 1.5 Particular conditions subdivided into two bullet points: part A (d) and part B (e)

1.6 unless they agree otherwise changed to unless the Particular Conditions establish otherwise 1.8 of a technical nature taken out of final sentence 1.9 reasonable profit changed to profit in point (b) 1.12 Contractor becomes Contractor s and Employer s Personnel included in sub-clause as the Engineer may reasonably require in order to verify the Contractor s compliance with the Contract changed to as may be reasonably required in order to verify compliance with the Contract and allow its proper implementation Extra paragraph added re: privacy and disclosure 1.13 building permit included in point (a) (or being) changed to (or to be) in point (a) Final sentence added re: unless Contractor is impeded 1.15 Addition of Inspections and Audit by the Bank subclause 2.1 Appendix to Tender changed to Contract Data in para 1 and 2 without disruption added to para 2 reasonable profit changed to profit 2.2 (where he is in a position to do so) changed to at the request of the Contractor Assistance to the Contractor at the request of the Contractor changed to: assistance as to allow the Contractor to obtain properly

2.4 before Commencement Date and thereafter added in para 1 punctually added to pay Contract price in para 1 if the Employer intends to make any material changes to his financial arrangements changed to: before the Employer makes any material change to his financial arrangements Addition of new para re: giving notice to Contractor re bank loans/suspensions 2.5 and no longer than 28 days added to para 2 or should have become aware added to para 2 3.1 the Employer undertakes not to impose further constraints on the Engineer s authority, expect as agreed with the Contractor changed to: the Employer shall promptly inform the Contractor of any change to the authority attributed to the Engineer in para 2 Addition of point (d) re: Conditions regarding an Engineers response to a Contractor s request Paragraph added re: Engineer obtaining approval from the Employer regarding certain sub-clauses 3.4 Replacement of Engineer changed from 42 days to 21 days Employer to give full and fair consideration to this [replacing Engineer] objection rather than Employer shall not replace Engineer with a person against whom the Contractor 3.5 28 day time-limit added to para 2 4.1 3 rd para added re: origin of equipment, material and services

4.2 Appendix to Tender changed to Contract Data in para 1 and includes added ref to currencies Para 2 change: performance security now issued by a reputable bank or financial institution selected by Contractor Performance security claim conditions (a)-(d) removed Extra final para added re: amendment of Contract Price in relation to performance security 4.3 Ref to sub-clause 6.9 added re: consent withheld or revoked 6 th para added re: delegation by Contractor s Representative New sentence added on final para: if Contractor s Representative is not fluent in languages and communications defined in sub clause 1.4 4.4 solely of added to point (a) Encourages use of sub-contractors from country where project is being constructed 4.6 to suffer delay and/or added to 2 nd para 4.7 reasonable profit changed to profit in point (b) 4.12 Para 6 changed to upon receiving Para 8: shall not be bound by the Contractor s interpretation of any such evidence added 4.13 First sentence changed from The Contractor shall bear all costs and charges for special and/or temporary rights-of-way which he may require, including those for access to the Site. To Unless otherwise specified in the Contract the Employer shall provide effective access to and possession of the Site including special

and/or temporary rights-of-way which are necessary for the Works. rights of way added in final sentence 4.15 at base date added to 1 st para 4.18 and shall not exceed the values replaced by or in 2 nd para 4.19 for his construction activities tests added in para 1 5.1 subject to sub clause 5.2 added to point (b) 5.2 in writing added to end of para 1 Start of point (b) changed from the subcontract does not specify that the nominated Subcontractor shall to the nominated Subcontractor does not accept to Start of point (c) changed from the subcontract does not specify that to the nominated Subcontractor does not accept to enter into a subcontract which specifies that Point (c) (iii) added - introduction of pay-when-paid clause for nominated subcontractors 5.3 amounts shown on the nominated subcontractor s invoice approved by the Contractor added in 6.1 Additional para re: employing staff from sources within the Country 6.2 Additional para re: income tax 6.7 3 substantial paras added re: HIV-AIDS and STIs 6.12-6.24 13 new sub clauses added:

Foreign personnel, supply of foodstuffs, Supply of water, measures against insect and pest nuisance, alcohol liquor or drugs, arms and ammunition, festivals and religious customs, funeral arrangements, forced labour, child labour, employment records of workers, workers organisations, non-discrimination and equal opportunity 7.4 except as otherwise specified in the Contract added to 2 nd para reasonable profit changed to profit in point (b) 7.7 Except as otherwise specified in the Contract added to 1st para Point (a) changed from when it is delivered to the Site to when it is incorporated in the works Point (b) changed from when the contractor is entitled to payment of the value to when the contractor is paid the corresponding value 8.1 Sub-clause re: commencement of works changed from: Engineering giving Contractor no less than 7 days notice of Commencement Date/Commencement Date being within 42 days after the Contractor receives the Letter of Acceptance, to fulfilment of specific precedent conditions (see below) and Contractor receiving Engineer s notification recording the agreement Points (a) to (d) added re: precedent conditions that need to be fulfilled before Commencement of Works: (a) Signature of the Contract Agreement (b) Evidence of Employer s Financial arrangements (c) Access to a possession of the Site (d) Receipt by the Contractor of the Advance Payment Penultimate para added re: termination if Engineer s instructions are not received within 180 days from receipt of the Letter of Acceptance 8.6 Final para added re: additional costs

8.7 Appendix to Tender changed to Contract Data in para 1 8.12 after receiving from the Engineer an instruction to this effect under clause 13 added at end of para 10.2 reasonable profit changed to profit 10.3 reasonable profit changed to profit in point (b) 11.3 defect or damage changed to defect or by reason of damage attributable to the Contractor 11.8 reasonable profit changed to profit 11.11 after the Employer receives a copy of changed to after receipt by the Contractor of the Performance Certificate 12.1 Addition to first para: The Contractor shall show in each application entitled under the Contract and certify the payment of the undisputed part added in final para 12.3 New para added: Any item of work included in the bill of quantities Point (i) 10% changed to 25% Point (ii) 0.01% changed to 0.25% reasonable profit changed to profit as soon as the concerned work commences added to end of final para 13.1 (i) and (ii) added substantial changes in the sequence or progress of the Works 13.5 Appendix to Tender changed to Contract Data in (ii)

13.7 Extra para added: Notwithstanding the foregoing re: extension of time 14.1 Extra para added at end re: Contractor s equipment 14.2 and cash flow support added into first para Appendix to Tender changed to Contract Data end of paras 1 and 2 3 rd para: The Engineer shall issue an Interim Payment Certificate changed to The Engineer shall deliver to the Employer and to the Contractor an Interim Payment Certificate entity and from within a country (or other jurisdiction) approved by the Employer replaced by reputable bank or financial institution selected by the Contractor 5 th para changed to advance payment repaid through percentage deductions from the interim payments determined by the Engineer Point (a) changed from deductions shall commence in the Payment Certificate to deductions shall commencement in the next interim Payment Certificate following that in which and exceeds ten percent changed to exceeds thirty percent Point (b) of one quarter (25%) changed to stated in the Contract Data and and repayments of retention changed to for its repayments as well as deductions for retention money and additional final sentence added re: repayment of advance payment End of final para adapted to include ref to clause 15 and exception to sub-clause 15.5 14.3 Appendix to Tender changed to Contract Data in point (c) x2

Wording changed in point (d) re: repayments 14.4 less or more added to (c) 14.5 Appendix to tender changed to Schedules in (b)(i) and (c)(i) 14.6 Para 1 issue to the Employer changed to deliver to the Employer and Contractor Addition to end of para 1 re: supporting particulars Appendix to Tender changed to Contract Data in para 2 14.7 Addition to point (b) re: suspension of bank loan/credit and interim payment certificate Addition to point (c) re: suspension of bank loan/credit and final payment certificate 14.8 if not available, the interbank offered rate added to para 2 14.9 Proportion percentage in para 1 and 2 changed from 40% to 50% Final two paras added re retention money guarantee 14.11 28 days from receipt of said draft added to para 3 14.13 and to the Contractor added to para 1 issue changed to deliver in first para amount which he fairly determines added to (a) 14.15 Appendix to tender changed to Schedule of Payment Currencies in para 1 and unless otherwise stated in the Particular Conditions removed

Appendix to Tender changed to Schedule of Payment Currencies in (a)(i) Appendix to Tender changed to Contract Data and Appendix to tender changed to Schedule of Payment Currencies in (b) Appendix to Tender changed to Schedule of Payment Currencies in (e) 15.5 or to avoid a termination of the Contract by the Contractor under clause 16.2 added to para 1 Paid in accordance with changed from sub-clause 19.6 to sub-clause 16.4 para 2 African Development Bank 15.6 New sub-clause added re: corruption or fraudulent practices incl. country-specific definitions of practices 16.1 New 2 nd para added re: if bank has suspended disbursements under the loan or credit reasonable profit changed to profit in point (b) 16.2 Addition to (d) re: adverse effects to economic balance (h) added re: Contractor doesn t receive Engineers instruction recording agreement. Extra para added re: bank suspends loan/credit from which part or whole of the payments to the Contractor are being made Asian Development Bank 15.6 New sub-clause added re: corruption or fraudulent practices incl. country-specific definitions of practices

16.1 New 2 nd para added re: if bank has suspended disbursements under the loan or credit reasonable profit changed to profit in point (b) 16.2 Addition to (d) re: adverse effects to economic balance (h) added re: Contractor doesn t receive Engineers instruction recording agreement. Extra para added re: bank suspends loan/credit from which part or whole of the payments to the Contractor are being made Black Sea Trade and Development Bank or by the European Bank for Reconstruction and Development 15.6 New sub-clause added re: corruption or fraudulent practices incl. incl. country-specific definitions of practices 16.1 New 2 nd para added re: if bank has suspended disbursements under the loan or credit reasonable profit changed to profit in point (b) 16.2 Addition to (d) re: adverse effects to economic balance (h) added re: Contractor doesn t receive Engineers instruction recording agreement. Extra para added re: bank suspends loan/credit from which part or whole of the payments to the Contractor are being made Caribbean Development Bank 15.6 New sub-clause added re: corruption or fraudulent practices incl. country-specific definitions of practices

16.1 New 2 nd para added re: if bank has suspended disbursements under the loan or credit reasonable profit changed to profit in point (b) 16.2 Addition to (d) re: adverse effects to economic balance (h) added re: Contractor doesn t receive Engineers instruction recording agreement. Extra para added re: bank suspends loan/credit from which part or whole of the payments to the Contractor are being made Inter-American Development Bank 15.6 New sub-clause added re: corruption or fraudulent practices incl. country-specific definitions of practices, adherence to Bank s Policies for the Procurement of Works and Goods and the Bank s rights 16.1 New 2 nd para added re: if bank has suspended disbursements under the loan or credit reasonable profit changed to profit in point (b) 16.2 Addition to (d) re: adverse effects to economic balance (h) added re: Contractor doesn t receive Engineers instruction recording agreement. Extra para added re: bank suspends loan/credit from which part or whole of the payments to the Contractor are being made The World Bank 15.6 New sub-clause added re: corruption or fraudulent practices incl. specific definitions of practices

16.1 New 2 nd para added re: if bank has suspended disbursements under the loan or credit reasonable profit changed to profit in point (b) 16.2 Addition to (d) re: adverse effects to economic balance (h) added re: Contractor doesn t receive Engineers instruction recording agreement. Extra para added re: bank suspends loan/credit from which part or whole of the payments to the Contractor are being made All Banks 17.1 Point (b) no longer divided into (i) and (ii) 17.3 [Consequences of Employer s Risks] and insofar as they directly affect the execution of the works in the Country added to para 1 and other employees of the Contractor and Subcontractors taken out of point (c) 17.4 Point (b) reasonable profit on the Cost shall also be included changed to Cost plus profit shall be payable 17.6 Para 1: other than under Sub-Clause 16.4 [Payment on Termination] and Sub-Clause 17.1 [Indemnities]. Changed to other than as specifically provided in Sub- Clause 8.7 [Delay Damages] continues to list clauses that include: 11.2, 15.4, 16.4, 17.1, 17.4, 17.5 Para 2: stated in the Particular Conditions or (if a sum is not so stated) the Accepted Contract Amount. Changed to resulting from the application of a multiplier (less or greater than one) to the Accepted Contract Amount, as stated in the Contract Data, or (if such multiplier or other sum is not stated), the Accepted Contract Amount

17.7 New sub-clause re: Use of Employer s Accommodation/Facilities 18.1 Para 3: terms consistent with the details annexed to the Particular Conditions changed to terms acceptable to the Contractor and addition of final sentence re: consistency of terms with Letter of Acceptance Final para added re: Contractors entitlement to place insurances relating to the Contract with insurers from any eligible source country. 18.2 Point (b) between the Parties for the sole purpose of changed to to the Party actually bearing the costs of Point (d) to the extent specifically required in the bidding documents of the Contract added and Appendix to Tender changed to Contract Data 18.3 Appendix to Tender changed to Contract Data in para 2 18.4 Start of para 2 changed re: insurance cover for Employer and Engineer at event of claims/damages/losses/expenses/injury/sickness/death 19.1 sabotage by persons other than the Contractor s Personnel added to (ii) Point (iii) and other employees of the Contractor and Subcontractors taken out 19.4 Addition to (b) including costs of rectifying or replacing the Works and/or Goods damaged or destroyed by Force Majeure 19.6 and necessarily added to (c) 20.1 Para 7 and 8 swapped ( Within the above defined period of 42 days and Each Payment Certificate )

Extra para added re: If Engineer does not respond within the timeframe 20.2 DAB changed to DB jointly removed from para 1 Appendix to Tender changed to Contract Data in para 1 and 2 Additions to para 2 re: qualifications of the members Para 3 altered re: If the Parties have not jointly appointed the DB 21 days before the date stated in Contract Data agreed by the parties included in para 4 Paras 8 and 9 replaced by single paragraph: If at any time and If any of these circumstances replaced by If a member declines. 20.3 or fails to approve a member nominated by the other party added to (b) Appendix to Tender changed to Contract Data in final para 20.4 Para 5: give notice to the other Party of its dissatisfaction changed to give a Notice of Dissatisfaction to the other Party indicating its dissatisfaction and intention to commence arbitration 20.5 In final para should move to commence arbitration added 20.6 Arbitration procedure re-worded see points (a)(i) and (ii) and (b) 20.7 Points (a) (c) condensed into one para

APPENDIX 1. Dispute Adjudication Agreement changed to Dispute Board Agreement (continued in the rest of appendix) 2. Paras 2 and 4 removed: ( When the Dispute Adjudication Agreement has taken affect and No assignment or subcontracting ) 6. Retainer fee reduction changed from 50% to a third. necessary travel expenses added to (c) New para added re: If parties fail to agree on the retainer fee or the daily fee 8. Final para added re: If the member fails to comply with any of his obligations 9. settled under the rules of arbitration changed to settled by institutional arbitration Addition of if no other arbitration institute is agreed, the arbitration shall be conducted under the rules of arbitration PROCEDURAL RULES 2. Addition of sentence re: preventing problems from becoming disputes