Teori Pengambilan Keputusan. Week 12 Project Management

Similar documents
Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

IE 102 Spring Project Management

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Project Management Chapter 13

1 of 14 4/27/2009 7:45 AM

Textbook: pp Chapter 11: Project Management

CHAPTER 9: PROJECT MANAGEMENT

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

UNIT-II Project Organization and Scheduling Project Element

CISC 322 Software Architecture

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

Real-World Project Management. Chapter 15

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

Project Management Techniques (PMT)

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

GPE engineering project management. Project Management in an Engineering Context

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

06IP/IM74 OPERATIONS RESEARCH

Project Management -- Developing the Project Plan

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

Appendix A Decision Support Analysis

After complete studying this chapter, You should be able to

Project Management and Cost Control

Project Management Fundamentals

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

CHAPTER 5. Project Scheduling Models

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

Construction Management

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

Lecture 3 Project Scheduling

SWEN 256 Software Process & Project Management

Comparison between Deterministic and Stochastic Time Estimating Techniques

Chapter 2 The PERT/CPM Technique

Chapter 11: PERT for Project Planning and Scheduling

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015

Management Management

POLYTECHNIC OF NAMIBIA

CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING

MODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT

WHY ARE PROJECTS ALWAYS LATE?

Project Management with Brief Information regarding CPM and PERT Methods

The Critical Path Method

THE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

Research Methods Outline


Allocate and Level Project Resources

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri

MS Project 2007 Page 1 of 18

MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD

EXERCISE Draw the network diagram. a. Activity Name A B C D E F G H

Outline. Project Management. Introduction. What is a Project?

PROJECT MANAGEMENT: PERT AMAT 167

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL

Decision Support Tool for Project Time-Cost Trade-off

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta

CHAPTER 5 STOCHASTIC SCHEDULING

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2

Formulas to Know for EXAM

SCM 301 (Lutz) Exam 1 Practice Exam Solutions

Plan Implementation. Pushpa Lal Shakya

Project planning and creating a WBS

Project Management. Basic Definitions: Project and Project Plan

ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING

NPV Method. Payback Period


International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN:

Line Balancing S K Mondal Chapter 3

Ins. Luay Dwaikat Fall 2013/2014

SCM 301 (Solo) Exam 1 Practice Exam Solutions

VALUE MANAGEMENT INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: Snehal Salunke

Project Network Analysis Model to Dredging Operations In Niger Delta

Lecture 5: Project Management

Project orie:nta.teci pla.:n:ni:ng, scheduling a.:nci controlling technique

56:171 Operations Research Midterm Examination Solutions PART ONE

ETSF01: Software Engineering Process Economy and Quality

Programme Evaluation and Review Technique

Cost Reduction: Planning & Control. Impacting the Bottom Line

Brown hamburger and assemble tacos (including cheese)

VALLIAMMAI ENGINEERING COLLEGE

A SINGLE STEP CPM TIME-COST TRADEOFF ALGORITHM. In Mathematics and Computing. Under the guidance of Dr. Mahesh Kumar Sharma

PROJECT MANAGEMENT DIPLOMA COURSE

M G T 2251 Management Science. Exam 3

Final: Total 200 points (3-hour exam)

MnDOT use of Calendars in Primavera P6

IP-CIS : CIS Project Management

Transcription:

Teori Pengambilan Keputusan Week 1 Project Management

Project Management Program Evaluation and Review Technique (PERT) Critical Path Method (CPM)

PERT and CPM Network techniques Developed in 195 s CPM by DuPont for chemical plants (1957) PERT by Booz, Allen & Hamilton with the U.S. Navy, for Polaris missile (1958) Consider precedence relationships and interdependencies Each uses a different estimate of activity times

PERT/CPM 1.. Define the project and all of its significant activities or tasks. Develop the relationships among the activities. Decide which activities must precede others. 3. Draw the network connecting all of the activities. 4. Assign time and/or cost estimates to each activity. 5. Compute the longest time path through the network; this is called the critical path. 6. Use the network to help plan, schedule, monitor, and control the project.

Questions PERT & CPM Can Answer 1. When will the entire project be completed?. What are the critical activities or tasks in the project? 3. Which are the noncritical activities? 4. What is the probability the project will be completed by a specific date?

Questions PERT & CPM Can Answer 5. Is the project on schedule, behind schedule, or ahead of schedule? 6. Is the money spent equal to, less than, or greater than the budget? 7. Are there enough resources available to finish the project on time? 8. If the project must be finished in a shorter time, what is the way to accomplish this at least cost?

A Comparison of AON and AOA Network Conventions Activity on Activity Activity on Node (AON) Meaning Arrow (AOA) (a) A B C A comes before B, which comes before C A B C (b) A B C A and B must both be completed before C can start A B C (c) A B C B and C cannot begin until A is completed A C B

A Comparison of AON and AOA Network Conventions Activity on Activity Activity on Node (AON) Meaning Arrow (AOA) (d) A B C D C and D cannot begin until both A and B are completed A B C D (e) A B C D C cannot begin until both A and B are completed; D cannot begin until B is completed. A dummy activity is introduced in AOA A B C Dummy activity D

A Comparison of AON and AOA Network Conventions Activity on Activity Activity on Node (AON) Meaning Arrow (AOA) (f) A B and C cannot begin until A is B D completed. D A B C cannot begin until both B and C are completed. A dummy activity is again introduced in AOA. Dummy activity C D

Activity AON Example Milwaukee Paper Manufacturing's Activities and Predecessors Description Immediate Predecessors A Build internal components B Modify roof and floor C Construct collection stack A D Pour concrete and install frame A, B E Build high-temperature burner C F Install pollution control system C G Install air pollution device D, E H Inspect and test F, G

AON Network for Milwaukee Paper A Activity A (Build Internal Components) Start Start Activity B Activity B (Modify Roof and Floor)

AON Network for Milwaukee Paper Activity A Precedes Activity C A C Start B D Activities A and B Precede Activity D

AON Network for Milwaukee Paper A C F Start E H B D G Arrows Show Precedence Relationships Figure 3.8

Determining the Project Schedule Perform a Critical Path Analysis The critical path is the longest path through the network The critical path is the shortest time in which the project can be completed Any delay in critical path activities delays the project Critical path activities have no slack time

Determining the Project Schedule Perform a Critical Path Analysis Activity Description Time (weeks) A Build internal components B Modify roof and floor 3 C Construct collection stack D Pour concrete and install frame 4 E Build high-temperature burner 4 F Install pollution control system 3 G Install air pollution device 5 H Inspect and test Total Time (weeks) 5

Determining the Project Schedule Perform a Critical Path Analysis Earliest start (ES) = earliest time at which an activity can start, assuming all predecessors have been completed Earliest finish (EF) = earliest time at which an activity can be finished Latest start (LS) = latest time at which an activity can start so as to not delay the completion time of the entire project Latest finish (LF) = latest time by which an activity has to be finished so as to not delay the completion time of the entire project

Determining the Project Schedule Perform a Critical Path Analysis Activity Name or Symbol Earliest Start ES A EF Earliest Finish Latest Start LS LF Latest Finish Activity Duration

Forward Pass Begin at starting event and work forward Earliest Start Time Rule: If an activity has only a single immediate predecessor, its ES equals the EF of the predecessor If an activity has multiple immediate predecessors, its ES is the maximum of all the EF values of its predecessors ES = Max {EF of all immediate predecessors}

Forward Pass Begin at starting event and work forward Earliest Finish Time Rule: The earliest finish time (EF) of an activity is the sum of its earliest start time (ES) and its activity time EF = ES + Activity time

ES/EF Network for Milwaukee Paper ES Start EF = ES + Activity time

ES/EF Network for Milwaukee Paper Start ES of A A EF of A = ES of A +

ES/EF Network for Milwaukee Paper A Start ES of B B 3 EF of B = ES of B + 3 3

ES/EF Network for Milwaukee Paper A C 4 Start B 3 3

ES/EF Network for Milwaukee Paper A C 4 Start B 3 = Max (, 3) 3 D 7 3 4

ES/EF Network for Milwaukee Paper A C 4 Start B 3 D 3 7 3 4

ES/EF Network for Milwaukee Paper A C 4 4 F 7 3 Start E H 4 8 13 15 4 B 3 3 D 3 7 4 G 8 13 5 Figure 3.11

Backward Pass Begin with the last event and work backwards Latest Finish Time Rule: If an activity is an immediate predecessor for just a single activity, its LF equals the LS of the activity that immediately follows it If an activity is an immediate predecessor to more than one activity, its LF is the minimum of all LS values of all activities that immediately follow it LF = Min {LS of all immediate following activities}

Backward Pass Begin with the last event and work backwards Latest Start Time Rule: The latest start time (LS) of an activity is the difference of its latest finish time (LF) and its activity time LS = LF Activity time

LS/LF Times for Milwaukee Paper A C 4 4 F 7 3 Start E H 4 8 13 15 B 3 3 LS = LF Activity time D 3 7 4 4 G 8 13 5 13 LF = EF of Project 15

LS/LF Times for Milwaukee Paper A C 4 4 F 7 1 13 3 Start E H LF = Min(LS 4 of following 8 13 15 activity) 13 15 4 B 3 3 D 3 7 4 G 8 13 5

LS/LF Times for Milwaukee Paper LF = Min(4, 1) A C 4 4 F 7 4 1 13 3 Start E H 4 8 13 15 4 8 4 13 15 B 3 3 D 3 7 4 G 8 13 8 5 13

LS/LF Times for Milwaukee Paper A C 4 4 F 7 4 1 13 3 Start E H 4 8 13 15 4 8 4 13 15 B 3 1 3 4 3 D 7 4 4 8 G 8 13 8 5 13

Computing Slack Time After computing the ES, EF, LS, and LF times for all activities, compute the slack or free time for each activity Slack is the length of time an activity can be delayed without delaying the entire project Slack = LS ES or Slack = LF EF

Computing Slack Time Earliest Earliest Latest Latest On Start Finish Start Finish Slack Critical Activity ES EF LS LF LS ES Path A Yes B 3 1 4 1 No C 4 4 Yes D 3 7 4 8 1 No E 4 8 4 8 Yes F 4 7 1 13 6 No G 8 13 8 13 Yes H 13 15 13 15 Yes

Critical Path for Milwaukee Paper A C 4 4 F 7 4 1 13 3 Start E H 4 8 13 15 4 8 4 13 15 B 3 1 3 4 3 D 7 4 4 8 G 8 13 8 5 13

ES EF Gantt Chart for Milwaukee Paper A Build internal components B Modify roof and floor C Construct collection stack D Pour concrete and install frame E Build high-temperature burner F Install pollution control system G Install air pollution device H Inspect and test 1 3 4 5 6 7 8 9 1 11 1 13 14 15 16

LS LF Gantt Chart for Milwaukee Paper A Build internal components B Modify roof and floor C Construct collection stack D Pour concrete and install frame E Build high-temperature burner F Install pollution control system G Install air pollution device H Inspect and test 1 3 4 5 6 7 8 9 1 11 1 13 14 15 16

Variability in Activity Times CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times PERT uses a probability distribution for activity times to allow for variability

Variability in Activity Times Three time estimates are required Optimistic time (a) if everything goes according to plan Pessimistic time (b) assuming very unfavorable conditions Most likely time (m) most realistic estimate

Variability in Activity Times Estimate follows beta distribution Expected time: t = (a + 4m + b)/6 Variance of times: v = [(b a)/6]

Probability Variability in Activity Times Estimate follows beta distribution Expected time: t = (a + 4m + b)/6 Variance Probability of of times: 1 in 1 of < a occurring v = [(b a)/6] Probability of 1 in 1 of > b occurring Activity Time Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b)

Computing Variance Most Expected Optimistic Likely Pessimistic Time Variance Activity a m b t = (a + 4m + b)/6 [(b a)/6] A 1 3.11 B 3 4 3.11 C 1 3.11 D 4 6 4.44 E 1 4 7 4 1. F 1 9 3 1.78 G 3 4 11 5 1.78 H 1 3.11 Table 3.4

Probability of Project Completion Project variance is computed by summing the variances of critical activities s = Project variance p = (variances of activities on critical path)

Probability of Project Completion Project variance is computed by summing the variances of critical activities Project variance s =.11 +.11 + 1. + 1.78 +.11 = 3.11 p Project standard deviation s p = Project variance = 3.11 = 1.76 weeks

Probability of Project Completion PERT makes two more assumptions: Total project completion times follow a normal probability distribution Activity times are statistically independent

Probability of Project Completion Standard deviation = 1.76 weeks 15 Weeks (Expected Completion Time)

Probability of Project Completion What is the probability this project can be completed on or before the 16 week deadline? due date expected date of completion Z = /s p = (16 wks 15 wks)/1.76 =.57 Where Z is the number of standard deviations the due date or target date lies from the mean or expected date

Probability of Project Completion From Appendix I What is the probability this project can be completed on or. before.1 the 16.7 week deadline?.8.1.5.5399.579.53188..53983.5438.56749.5714 due date expected date of completion Z = /s p.5.69146.69497.71566.7194.6.7575.797.74857.75175 = (16 wks 15 wks)/1.76 =.57 Where Z is the number of standard deviations the due date or target date lies from the mean or expected date

Probability of Project Completion Probability (T 16 weeks) is 71.57%.57 Standard deviations 15 16 Weeks Weeks Time

Determining Project Completion Time Probability of.99 Probability of.1 From Appendix I.33 Standard deviations.33 Z

Variability of Completion Time for Noncritical Paths Variability of times for activities on noncritical paths must be considered when finding the probability of finishing in a specified time Variation in noncritical activity may cause change in critical path

What Project Management Has Provided So Far The project s expected completion time is 15 weeks There is a 71.57% chance the equipment will be in place by the 16 week deadline Five activities (A, C, E, G, and H) are on the critical path Three activities (B, D, F) are not on the critical path and have slack time A detailed schedule is available

Trade-Offs And Project Crashing It is not uncommon to face the following situations: The project is behind schedule The completion time has been moved forward Shortening the duration of the project is called project crashing

Factors to Consider When Crashing A Project The amount by which an activity is crashed is, in fact, permissible Taken together, the shortened activity durations will enable us to finish the project by the due date The total cost of crashing is as small as possible

Steps in Project Crashing 1. Compute the crash cost per time period. If crash costs are linear over time: Crash cost per period = (Crash cost Normal cost) (Normal time Crash time). Using current activity times, find the critical path and identify the critical activities

Steps in Project Crashing If there is only one critical path, then select the activity on this critical path that (a) can still be crashed, and (b) has the smallest crash cost per period. If there is more than one critical path, then select one activity from each critical path such that (a) each selected activity can still be crashed, and (b) the total crash cost of all selected activities is the smallest. Note that the same activity may be common to more than one critical path.

Steps in Project Crashing Update all activity times. If the desired due date has been reached, stop. If not, return to Step.

Crashing The Project Time (Wks) Cost ($) Crash Cost Critical Activity Normal Crash Normal Crash Per Wk ($) Path? A 1,,75 75 Yes B 3 1 3, 34,, No C 1 6, 7, 1, Yes D 4 48, 49, 1, No E 4 56, 58, 1, Yes F 3 3, 3,5 5 No G 5 8, 84,5 1,5 Yes H 1 16, 19, 3, Yes

Crash and Normal Times and Costs for Activity B Activity Cost Crash Crash Cost $34, $33, $3, $31, Crash Cost/Wk = Crash Cost Normal Cost Normal Time Crash Time $34, $3, = 3 1 $4, = = $,/Wk Wks Normal Cost $3, Normal 1 3 Time (Weeks) Crash Time Normal Time

Critical Path And Slack Times For Milwaukee Paper A C 4 4 F 7 4 1 13 3 Start Slack = Slack = E Slack = 6 H 4 8 13 15 4 8 4 13 15 B 3 D 3 7 Slack = G 8 13 Slack = 1 3 4 4 4 8 8 13 5 Slack = 1 Slack = 1 Slack =

Advantages of PERT/CPM Especially useful when scheduling and controlling large projects Straightforward concept and not mathematically complex Graphical networks help highlight relationships among project activities Critical path and slack time analyses help pinpoint activities that need to be closely watched

Advantages of PERT/CPM Project documentation and graphics point out who is responsible for various activities Applicable to a wide variety of projects Useful in monitoring not only schedules but costs as well

Limitations of PERT/CPM Project activities have to be clearly defined, independent, and stable in their relationships Precedence relationships must be specified and networked together Time estimates tend to be subjective and are subject to fudging by managers There is an inherent danger of too much emphasis being placed on the longest, or critical, path

EXERCISE

1 Berikut aktivitas pada sebuah proyek. Waktu yang tercantum adalah dalam minggu. Aktivitas Aktivitas Waktu Pendahulu A -- 8 B -- 3 C A 7 D A, B 3 E C 4 F D 6

1 a. Gambarkan diagram jaringannya. b. Hitunglah ES, EF, LS, LF, dan Slack untuk masing-masing aktivitas. c. Berapakah waktu penyelesaian proyek tersebut?

Berikut aktivitas pada sebuah proyek. Waktu yang tercantum adalah dalam minggu. Aktivitas Aktivitas Waktu/Durasi Pendahulu A -- 9 B A C A 1 D A 5 E B 6 F B 8 G C, F 3 H D I H 8 J G, I 6 K E, J

a. Buatlah diagram jaringannya. b. Aktivitas manakah yang membentuk jalur kritis (critical path)? c. Berapakah slack pada aktivitas A dan F? d. Berapakah durasi dari jalur kritisnya?

THANK YOU