Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

Similar documents
Teori Pengambilan Keputusan. Week 12 Project Management

IE 102 Spring Project Management

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

Project Management Chapter 13

Textbook: pp Chapter 11: Project Management

1 of 14 4/27/2009 7:45 AM

CHAPTER 9: PROJECT MANAGEMENT

CISC 322 Software Architecture

UNIT-II Project Organization and Scheduling Project Element

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

After complete studying this chapter, You should be able to

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

Project Management Fundamentals

06IP/IM74 OPERATIONS RESEARCH

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

GPE engineering project management. Project Management in an Engineering Context

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

Real-World Project Management. Chapter 15

Project Management -- Developing the Project Plan

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

SWEN 256 Software Process & Project Management

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

Project Management Techniques (PMT)

Appendix A Decision Support Analysis

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

Construction Management

Project Management and Cost Control

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan

Decision Support Tool for Project Time-Cost Trade-off

POLYTECHNIC OF NAMIBIA

CHAPTER 5. Project Scheduling Models

Management Management

Chapter 11: PERT for Project Planning and Scheduling

Chapter 2 The PERT/CPM Technique

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2

Outline. Project Management. Introduction. What is a Project?

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

ETSF01: Software Engineering Process Economy and Quality

MS Project 2007 Page 1 of 18

COPYRIGHTED MATERIAL. Index

EXERCISE Draw the network diagram. a. Activity Name A B C D E F G H


Project planning and creating a WBS

Project Management. Basic Definitions: Project and Project Plan

CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

Comparison between Deterministic and Stochastic Time Estimating Techniques

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT

Research Methods Outline

MODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT

The Project Times and Costs

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri

VALLIAMMAI ENGINEERING COLLEGE

Appendix B: Glossary of Project Management Terms

Cost Reduction: Planning & Control. Impacting the Bottom Line

Lecture 3 Project Scheduling

Project Planning. Planning is an important step in project execution. Planning means:

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD

Lecture 5: Project Management

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta

SCM 301 (Lutz) Exam 1 Practice Exam Solutions

International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN:

IP-CIS : CIS Project Management

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015

UNIVERSITY OF SWAZILAND FACULTY OF COMMERCE DEPARTMENT OF BUSINESS ADMINISTRATION FINAL EXAMINATION PAPER MAY 2016 ROJECT MANAGEMENT THREE [3] HOURS

Introduction to Project Management. Modeling after NYS ITS

Project Management. A Practitioner s Guide. Steven M. Bragg

Project Management with Brief Information regarding CPM and PERT Methods

WHY ARE PROJECTS ALWAYS LATE?

VALUE MANAGEMENT INTERNATIONAL RESEARCH JOURNAL OF ENGINEERING AND TECHNOLOGY (IRJET) E-ISSN: Snehal Salunke

Ins. Luay Dwaikat Fall 2013/2014

MnDOT use of Calendars in Primavera P6

SCM 301 (Solo) Exam 1 Practice Exam Solutions

Risk Video #1. Video 1 Recap

The Critical Path Method

Impacting the Bottom Line. Cost Reduction: Planning & Control. Bottom Line (costs) A = Costs (what we expend) B = Revenue, sales (what we generate)

Allocate and Level Project Resources

Brown hamburger and assemble tacos (including cheese)

ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

THE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

Plan Implementation. Pushpa Lal Shakya

Project Controls Expo 16 th Nov 2016

CHAPTER 5 STOCHASTIC SCHEDULING

Transcription:

Project Management

Outline Global Company Profile: Bechtel Group The Importance of Project Management Project Planning Project Scheduling Project Controlling

Outline - Continued Project Management Techniques: PERT and CPM Determining the Project Schedule Variability in Activity Times Cost-Time Trade-offs and Project Crashing 3

Outline - Continued A Critique of PERT and CPM Using Microsoft Project to Manage Projects 4

Bechtel Projects Constructing 3 high-security data centers worldwide for Equinix, Inc. ($1. billion) Building a rail line between London and the Channel Tunnel ($4.6 billion) Developing an oil pipeline from the Caspian Sea region to Russia ($85 million) Expanding the Dubai Airport in the UAE ($6 million), and the Miami Airport in Florida ($ billion) 14 Pearson Education, Inc. 5

Bechtel Projects Building liquid natural gas plants in Yemen ($ billion) and in Trinidad, West Indies ($1 billion) Building a new subway for Athens, Greece ($.6 billion) Constructing a natural gas pipeline in Thailand ($7 million) Building 3 plants for imotors.com, a company that sells refurbished autos online ($3 million) Building a highway to link the north and south of Croatia ($33 million) 14 Pearson Education, Inc. 6

Learning Objectives When you complete this chapter you should be able to: 3.1 Use a Gantt chart for scheduling 3. Draw AOA and AON networks 3.3 Complete forward and backward passes for a project 3.4 Determine a critical path 7

Learning Objectives When you complete this chapter you should be able to: 3.5 Calculate the variance of activity times 3.6 Crash a project 8

Importance of Project Management Bechtel Project Management International workforce, construction professionals, cooks, medical personnel, security Strategic value of time-based competition Quality mandate for continual improvement 9

Project Characteristics Single unit Many related activities Difficult production planning and inventory control General purpose equipment High labor skills 1

Examples of Projects Building Construction Research Project 11

Management of Projects 1. Planning - goal setting, defining the project, team organization. Scheduling - relate people, money, and supplies to specific activities and activities to each other 3. Controlling - monitor resources, costs, quality, and budgets; revise plans and shift resources to meet time and cost demands 1

Project Management Activities Planning Objectives Resources Work breakdown structure Organization Scheduling Project activities Start and end times Network Controlling Monitor, compare, revise, action 13

Project Planning, Scheduling, and Controlling Figure 3.1 14

Project Planning, Scheduling, and Controlling Figure 3.1 15

Project Planning, Scheduling, and Controlling Figure 3.1 16

Project Planning, Scheduling, and Controlling Figure 3.1 17

Project Planning, Time/cost Scheduling, estimates and Controlling Budgets Engineering diagrams Cash flow charts Material availability details CPM/PERT Gantt charts Milestone charts Cash Figure flow 3.1schedules Budgets Delayed activities report Slack activities report 18

Project Planning Establishing objectives Defining project Creating work breakdown structure Determining resources Forming organization 19

Project Organization Often temporary structure Uses specialists from entire company Headed by project manager Coordinates activities Monitors schedule and costs Permanent structure called matrix organization

Project Organization Most Helpful When: 1. Work can be defined with a specific goal and deadline. The job is unique or somewhat unfamiliar to the existing organization 3. The work contains complex interrelated tasks requiring specialized skills 4. The project is temporary but critical to the organization 5. The project cuts across organizational lines 1

A Sample Project Organization President Human Resources Marketing Finance Design Quality Mgt Production Project No. 1 Project Manager Mechanical Engineer Test Engineer Technician Project No. Project Manager Electrical Engineer Computer Engineer Technician Figure 3.

Matrix Organization Marketing Operations Engineering Finance Project 1 Project Project 3 Project 4 14 Pearson Education, Inc. 3-3

The Role of the Project Manager Highly visible Responsible for making sure that: 1) All necessary activities are finished in order and on time ) The project comes in within budget 3) The project meets quality goals 4) The people assigned to the project receive motivation, direction, and information 4

The Role of the Project Manager Highly visible Responsible for making sure that: Project managers should be: Good coaches 1) All necessary activities Good are communicators finished in order and on time Able to organize activities ) The project comes in within budget 3) The project meets quality goals 4) The people assigned to the project receive motivation, direction, and information from a variety of disciplines 5

Ethical Issues Project managers face many ethical decisions on a daily basis The Project Management Institute has established an ethical code to deal with problems such as: 1) Offers of gifts from contractors ) Pressure to alter status reports to mask delays 3) False reports for charges of time and expenses 4) Pressure to compromise quality to meet schedules 6

Work Breakdown Structure Level 1. Project. Major tasks in the project 3. Subtasks in the major tasks 4. Activities (or work packages ) to be completed 7

Work Breakdown Structure Level 1 Develop Windows 8 Operating System 1. Level Software Design 1.1 Cost Management System Plan 1. Testing 1.3 Level 3 Develop GUIs 1.1.1 Design Cost Tracking Reports 1..1 Module Testing 1.3.1 Ensure Compatibility with Earlier Versions 1.1. Develop Cost/Schedule Interface Defect 1.. Testing 1.3. Level 4 (Work packages) Compatible with Windows 7 Compatible with Windows Vista 1.1..1 1.1.. Compatible with Windows XP 1.1..3 Figure 3.3 8

Project Scheduling Techniques 1) Ensure that all activities are planned for ) Their order of performance is accounted for 3) The activity time estimates are recorded 4) The overall project time is developed 9

Purposes of Project Scheduling 1. Shows the relationship of each activity to others and to the whole project. Identifies the precedence relationships among activities 3. Encourages the setting of realistic time and cost estimates for each activity 4. Helps make better use of people, money, and material resources by identifying critical bottlenecks in the project 3

Project Management Techniques Gantt chart Critical Path Method (CPM) Program Evaluation and Review Technique (PERT) 31

A Simple Gantt Chart Design Prototype Test Revise Production Time J F M A M J J A S 3

Service For a Delta Jet Passengers Baggage Fueling Cargo and mail Galley servicing Lavatory servicing Drinking water Cabin cleaning Cargo and mail Flight services Operating crew Baggage Passengers Figure 3.4 Deplaning Baggage claim Container offload Pumping Engine injection water Container offload Main cabin door Aft cabin door Aft, center, forward Loading First-class section Economy section Container/bulk loading Galley/cabin check Receive passengers Aircraft check Loading Boarding 1 3 4 Time, Minutes 33

Project Controlling Close monitoring of resources, costs, quality, budgets Feedback enables revising the project plan and shift resources Computerized tools produce extensive reports 34

Project Management Software There are several popular packages for managing projects Oracle Primavera MindView HP Project Fast Track Microsoft Project 35

Project Control Reports 1) Detailed cost breakdowns for each task ) Labor requirements 3) Cost and hour summaries 4) Raw materials and expenditure forecasts 5) Variance reports 6) Time analysis reports 7) Work status reports 36

PERT and CPM Network techniques Developed in 195s CPM by DuPont for chemical plants (1957) PERT by Booz, Allen & Hamilton with the U.S. Navy, for Polaris missile (1958) Consider precedence relationships and interdependencies Each uses a different estimate of activity times 37

Six Steps PERT and CPM 1. Define the project and prepare the work breakdown structure. Develop relationships among the activities decide which activities must precede and which must follow others 3. Draw the network connecting all of the activities 38

Six Steps PERT and CPM 4. Assign time and/or cost estimates to each activity 5. Compute the longest time path through the network this is called the critical path 6. Use the network to help plan, schedule, monitor, and control the project 39

Questions PERT and CPM Can Answer 1. When will the entire project be completed?. What are the critical activities or tasks in the project? 3. Which are the noncritical activities? 4. What is the probability the project will be completed by a specific date? 4

Questions PERT and CPM Can Answer 5. Is the project on schedule, behind schedule, or ahead of schedule? 6. Is the money spent equal to, less than, or greater than the budget? 7. Are there enough resources available to finish the project on time? 8. If the project must be finished in a shorter time, what is the way to accomplish this at least cost? 41

A Comparison of AON and AOA Network Conventions Activity on Activity Activity on Node (AON) Meaning Arrow (AOA) (a) A B C A comes before B, which comes before C A B C (b) A B C A and B must both be completed before C can start A B C (c) A B C B and C cannot begin until A is completed A B C 4

A Comparison of AON and AOA Network Conventions Activity on Activity Activity on Node (AON) Meaning Arrow (AOA) (d) A B C D C and D cannot begin until both A and B are completed A B C D (e) A B C D C cannot begin until both A and B are completed D cannot begin until B is completed A dummy activity is introduced in AOA A B C Dummy activity D 43

A Comparison of AON and AOA Network Conventions Activity on Activity Activity on Node (AON) Meaning Arrow (AOA) (f) A B D B and C cannot begin until A is completed D cannot begin until both B and C A B C are completed Dummy A dummy activity activity is again introduced in AOA C D 44

AON Example Table 3.1 Milwaukee Paper Manufacturing s Activities and Predecessors ACTIVITY DESCRIPTION IMMEDIATE PREDECESSORS A Build internal components B Modify roof and floor C Construct collection stack A D Pour concrete and install frame A, B E Build high-temperature burner C F Install pollution control system C G Install air pollution device D, E H Inspect and test F, G 45

AON Network for Milwaukee Paper A Activity A (Build Internal Components) Start Start Activity B Activity B (Modify Roof and Floor) Figure 3.5 46

AON Network for Milwaukee Paper Activity A Precedes Activity C A C Start B D Activities A and B Precede Activity D Figure 3.6 47

AON Network for Milwaukee Paper A C F Start E H B D G Arrows Show Precedence Relationships Figure 3.7 48

AOA Network for Milwaukee Paper C (Construct Stack) 4 1 Dummy Activity 6 H (Inspect/ Test) 7 D 3 (Pour Concrete/ Install Frame) 5 Figure 3.8 49

Determining the Project Schedule Perform a Critical Path Analysis The critical path is the longest path through the network The critical path is the shortest time in which the project can be completed Any delay in critical path activities delays the project Critical path activities have no slack time 5

Determining the Project Schedule Table 3. Time Estimates for Milwaukee Paper Manufacturing ACTIVITY DESCRIPTION TIME (WEEKS) A Build internal components B Modify roof and floor 3 C Construct collection stack D Pour concrete and install frame 4 E Build high-temperature burner 4 F Install pollution control system 3 G Install air pollution device 5 H Inspect and test Total time (weeks) 5 51

Determining the Project Schedule Perform a Critical Path Analysis Earliest start (ES) = earliest time at which an activity can start, assuming all predecessors have been completed Earliest finish (EF) = earliest time at which an activity can be finished Latest start (LS) = latest time at which an activity can start so as to not delay the completion time of the entire project Latest finish (LF) = latest time by which an activity has to be finished so as to not delay the completion time of the entire project 5

Determining the Project Schedule Activity Format Figure 3.9 Activity Name or Symbol Earliest Start ES A EF Earliest Finish Latest Start LS LF Latest Finish Activity Duration 53

Forward Pass Begin at starting event and work forward Earliest Start Time Rule: If an activity has only a single immediate predecessor, its ES equals the EF of the predecessor If an activity has multiple immediate predecessors, its ES is the maximum of all the EF values of its predecessors ES = Max {EF of all immediate predecessors} 54

Forward Pass Begin at starting event and work forward Earliest Finish Time Rule: The earliest finish time (EF) of an activity is the sum of its earliest start time (ES) and its activity time EF = ES + Activity time 55

ES/EF Network for Milwaukee Paper ES Start EF = ES + Activity time 56

ES/EF Network for Milwaukee Paper Start ES of A A EF of A = ES of A + 57

ES/EF Network for Milwaukee Paper A Start ES of B B 3 EF of B = ES of B + 3 3 58

ES/EF Network for Milwaukee Paper A C 4 Start B 3 3 59

ES/EF Network for Milwaukee Paper A C 4 Start B 3 = Max (, 3) 3 D 7 3 4 6

ES/EF Network for Milwaukee Paper A C 4 Start B 3 D 3 7 3 4 61

ES/EF Network for Milwaukee Paper A C 4 4 F 7 3 Start E H 4 8 13 15 4 B 3 3 D 3 7 4 G 8 13 5 Figure 3.1 6

Backward Pass Begin with the last event and work backwards Latest Finish Time Rule: If an activity is an immediate predecessor for just a single activity, its LF equals the LS of the activity that immediately follows it If an activity is an immediate predecessor to more than one activity, its LF is the minimum of all LS values of all activities that immediately follow it LF = Min {LS of all immediate following activities} 63

Backward Pass Begin with the last event and work backwards Latest Start Time Rule: The latest start time (LS) of an activity is the difference of its latest finish time (LF) and its activity time LS = LF Activity time 64

LS/LF Times for Milwaukee Paper A C 4 4 F 7 3 Start E H 4 8 13 15 B 3 3 LS = LF Activity time D 3 7 4 4 G 8 13 5 13 15 LF = EF of Project 65

LS/LF Times for Milwaukee Paper A C 4 4 F 7 1 13 3 Start E H 4 8 13 15 LF = Min(LS of following activity) 4 13 15 B 3 3 D 3 7 4 G 8 13 5 66

LS/LF Times for LF = Min(4, 1) Milwaukee Paper A C 4 4 F 7 4 1 13 3 Start E H 4 8 13 15 4 8 4 13 15 B 3 3 D 3 7 4 8 G 13 8 5 13 67

LS/LF Times for Milwaukee Paper A C 4 4 F 7 4 1 13 3 Start E H 4 8 13 15 4 8 4 13 15 B 3 1 3 4 3 D 7 4 4 8 8 G 13 8 5 13 68

Computing Slack Time After computing the ES, EF, LS, and LF times for all activities, compute the slack or free time for each activity Slack is the length of time an activity can be delayed without delaying the entire project Slack = LS ES or Slack = LF EF 69

Computing Slack Time TABLE 3.3 ACTIVITY Milwaukee Paper s Schedule and Slack Times EARLIEST START ES EARLIEST FINISH EF LATEST START LS LATEST FINISH LF SLACK LS ES ON CRITICAL PATH A Yes B 3 1 4 1 No C 4 4 Yes D 3 7 4 8 1 No E 4 8 4 8 Yes F 4 7 1 13 6 No G 8 13 8 13 Yes H 13 15 13 15 Yes 7

Activities with zero slack are on the critical path. It: Starts at the first activity in the project Terminates at the last activity in the project Includes only critical activities TABLE 3.3 ACTIVITY Computing Slack Time Milwaukee Paper s Schedule and Slack Times EARLIEST START ES EARLIEST FINISH EF LATEST START LS LATEST FINISH LF SLACK LS ES ON CRITICAL PATH A Yes B 3 1 4 1 No C 4 4 Yes D 3 7 4 8 1 No E 4 8 4 8 Yes F 4 7 1 13 6 No G 8 13 8 13 Yes H 13 15 13 15 Yes 71

Critical Path for Milwaukee Paper A C 4 4 F 7 4 1 13 3 Start E H 4 8 13 15 4 8 4 13 15 B 3 1 3 4 3 D 7 4 4 8 8 G 13 8 5 13 7

ES EF Gantt Chart for Milwaukee Paper A Build internal components B Modify roof and floor C Construct collection stack D Pour concrete and install frame E Build high-temperature burner F Install pollution control system G Install air pollution device H Inspect and test 1 3 4 5 6 7 8 9 1 11 1 13 14 15 16 73

LS LF Gantt Chart for Milwaukee Paper A Build internal components B Modify roof and floor C Construct collection stack D Pour concrete and install frame E Build high-temperature burner F Install pollution control system G Install air pollution device H Inspect and test 1 3 4 5 6 7 8 9 1 11 1 13 14 15 16 74

Variability in Activity Times CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times PERT uses a probability distribution for activity times to allow for variability 75

Variability in Activity Times Three time estimates are required Optimistic time (a) if everything goes according to plan Pessimistic time (b) assuming very unfavorable conditions Most likely time (m) most realistic estimate 76

Variability in Activity Times Estimate follows beta distribution Expected activity time: t = (a + 4m + b)/6 Variance of activity completion times: v = [(b a)/6] 77

Variability in Activity Times Estimate follows beta distribution Expected activity time: t = (a + 4m + b)/6 Probability of 1 t in = 1 (a + 4m + b)/6 of < a occurring Variance of activity v = [(b completion a)/6]probability of 1 in 1 of > times: b occurring Probability v = [(b a)/6] Figure 3.11 Activity Time Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) 78

Computing Variance TABLE 3.4 Time Estimates (in weeks) for Milwaukee Paper's Project ACTIVITY OPTIMISTIC a MOST LIKELY m PESSIMISTIC b EXPECTED TIME t = (a + 4m + b)/6 VARIANCE [(b a)/6] A 1 3.11 B 3 4 3.11 C 1 3.11 D 4 6 4.44 E 1 4 7 4 1. F 1 9 3 1.78 G 3 4 11 5 1.78 H 1 3.11 79

Probability of Project Completion Project variance is computed by summing the variances of critical activities p = Project variance = (variances of activities on critical path) 8

Probability of Project Completion Project variance is computed by summing the variances of critical activities Project variance =.11 +.11 + 1. + 1.78 +.11 = 3.11 p Project standard deviation p = Project variance = 3.11 = 1.76 weeks 81

Probability of Project Completion PERT makes two more assumptions: Total project completion times follow a normal probability distribution Activity times are statistically independent 8

Probability of Project Completion Figure 3.1 Standard deviation = 1.76 weeks 15 Weeks (Expected Completion Time) 83

Probability of Project Completion What is the probability this project can be completed on or before the 16 week deadline? Due date Expected date of completion Z= / p = (16 weeks 15 weeks)/1.76 =.57 Where Z is the number of standard deviations the due date or target date lies from the mean or expected date 84

Probability of Project Completion From Appendix I What is the probability..1 this project.7 can.8 be completed on or before the 16 week.1.5.5399.579.53188 deadline?..53983.5438.56749.5714 due date expected date of completion Z= / p.5.69146.69497.71566.7194.6.7575.797.74857.75175 = (16 wks 15 wks)/1.76 =.57 Where Z is the number of standard deviations the due date or target date lies from the mean or expected date 85

Probability of Project Completion Probability (T 16 weeks) is 71.57%.57 Standard deviations Figure 3.13 15 16 Weeks Weeks Time 86

Determining Project Completion Time Probability of.99 Probability of.1 Figure 3.14 From Appendix I.33 Standard deviations.33 Z 87

Variability of Completion Time for Noncritical Paths Variability of times for activities on noncritical paths must be considered when finding the probability of finishing in a specified time Variation in noncritical activity may cause change in critical path 88

What Project Management Has Provided So Far 1. The project s expected completion time is 15 weeks. There is a 71.57% chance the equipment will be in place by the 16 week deadline 3. Five activities (A, C, E, G, and H) are on the critical path 4. Three activities (B, D, F) are not on the critical path and have slack time 5. A detailed schedule is available 89

Cost Time Trade-Offs and Project Crashing It is not uncommon to face the following situations: The project is behind schedule The completion time has been moved forward Shortening the duration of the project is called project crashing 9

Factors to Consider When Crashing a Project The amount by which an activity is crashed is, in fact, permissible Taken together, the shortened activity durations will enable us to finish the project by the due date The total cost of crashing is as small as possible 91

Steps in Project Crashing Step 1: Compute the crash cost per time period. If crash costs are linear over time: Crash cost per period = (Crash cost Normal cost) (Normal time Crash time) Step : Using current activity times, find the critical path and identify the critical activities 9

Steps in Project Crashing Step 3: If there is only one critical path, then select the activity on this critical path that (a) can still be crashed, and (b) has the smallest crash cost per period. If there is more than one critical path, then select one activity from each critical path such that (a) each selected activity can still be crashed, and (b) the total crash cost of all selected activities is the smallest. Note that the same activity may be common to more than one critical path. 93

Steps in Project Crashing Step 4: Update all activity times. If the desired due date has been reached, stop. If not, return to Step. 94

Crashing The Project TABLE 3.5 Normal and Crash Data for Milwaukee Paper Manufacturing ACTIVITY TIME (WEEKS) COST ($) NORMAL CRASH NORMAL CRASH CRASH COST PER WEEK ($) CRITICAL PATH? A 1,,75 75 Yes B 3 1 3, 34,, No C 1 6, 7, 1, Yes D 4 3 48, 49, 1, No E 4 56, 58, 1, Yes F 3 3, 3,5 5 No G 5 8, 84,5 1,5 Yes H 1 16, 19, 3, Yes 95

Crash and Normal Times and Costs for Activity B Activity Cost Crash Crash Cost $34, $33, $3, $31, Crash Cost/Wk = Crash Cost Normal Cost Normal Time Crash Time $34, $3, = 3 1 $4, = = $,/Week Wks Normal Cost Figure 3.15 $3, Normal 1 3 Time (Weeks) Crash Time Normal Time 96

Critical Path and Slack Times for Milwaukee Paper Figure 3.16 A C 4 4 F 7 4 1 13 3 Start Slack = Slack = E Slack = 6 H 4 8 13 15 4 8 4 13 15 B 3 D 3 7 Slack = G 8 13 Slack = 1 3 4 4 4 8 8 13 5 Slack = 1 Slack = 1 Slack = 97

Advantages of PERT/CPM 1. Especially useful when scheduling and controlling large projects. Straightforward concept and not mathematically complex 3. Graphical networks help highlight relationships among project activities 4. Critical path and slack time analyses help pinpoint activities that need to be closely watched 98

Advantages of PERT/CPM 5. Project documentation and graphics point out who is responsible for various activities 6. Applicable to a wide variety of projects 7. Useful in monitoring not only schedules but costs as well 99

Limitations of PERT/CPM 1. Project activities have to be clearly defined, independent, and stable in their relationships. Precedence relationships must be specified and networked together 3. Time estimates tend to be subjective and are subject to fudging by managers 4. There is an inherent danger of too much emphasis being placed on the longest, or critical, path 1

Using Microsoft Project Program 3.1 11

Using Microsoft Project Program 3. 1

Using Microsoft Project Pollution Project Percentage Completed on Aug. 1 ACTIVITY COMPLETED A 1 B 1 C 1 D 1 E F G H Program 3.3 13