PROJECT MANAGEMENT: PERT AMAT 167

Similar documents
Real-World Project Management. Chapter 15

Risk Video #1. Video 1 Recap

CHAPTER 5 STOCHASTIC SCHEDULING

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

WHY ARE PROJECTS ALWAYS LATE?

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

UNIT-II Project Organization and Scheduling Project Element

Project Risk Management

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

Making sense of Schedule Risk Analysis

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

GPE engineering project management. Project Management in an Engineering Context

Project Management. Managing Risk. Clifford F. Gray Eric W. Larson Third Edition. Chapter 7

Project Management Techniques (PMT)

A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

Poor Man s Approach to Monte Carlo

Haeryip Sihombing 1. Risk. Risk Management

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

Formulas to Know for EXAM

Review. What is the probability of throwing two 6s in a row with a fair die? a) b) c) d) 0.333

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

Project Management Chapter 13

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule

Textbook: pp Chapter 11: Project Management

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

06IP/IM74 OPERATIONS RESEARCH

Teori Pengambilan Keputusan. Week 12 Project Management

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

About the Risk Quantification of Technical Systems

Quantitative Risk Analysis with Microsoft Project

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

Uncertainty in Economic Analysis

Using Fat Tails to Model Gray Swans

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

Program Evaluation and Review Technique (PERT) in Construction Risk Analysis Mei Liu

CHAPTER 9: PROJECT MANAGEMENT

After complete studying this chapter, You should be able to

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Section 6-1 : Numerical Summaries

Chapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO END-OF-CHAPTER QUESTIONS

Monte Carlo Simulation (General Simulation Models)

Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic methods

MONTE CARLO EXTENSIONS

Pension Drawdown Monte Carlo Simulation. for. Example Client. Created by Mark Barden Vision West and Wales

STAT Chapter 6: Sampling Distributions

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta

Moments and Measures of Skewness and Kurtosis

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

Overview. We will discuss the nature of market risk and appropriate measures

Chapter 15: Sampling distributions

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL

Section The Sampling Distribution of a Sample Mean

Chapter Seven. The Normal Distribution

Probability Distribution Unit Review

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

Programme Evaluation and Review Technique

Probability and Statistics

In a binomial experiment of n trials, where p = probability of success and q = probability of failure. mean variance standard deviation

Monte Carlo Methods in Structuring and Derivatives Pricing

PERMUTATION AND COMBINATIONS APPROACH TO PROGRAM EVALUATION AND REVIEW TECHNIQUE

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

EXERCISE Draw the network diagram. a. Activity Name A B C D E F G H

Quantitative Methods for Economics, Finance and Management (A86050 F86050)

Chapter-8 Risk Management

SAMPLE. Answer all 60 multiple choice questions sample paper contains 30 questions only Use the proforma answer sheet provided.

Mohammed Rafiuddin CEO and General Manager, BIOSI Biohazards Solutions Innovators

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

To acquaint yourself with the practical applications of simulation methods.

KARACHI UNIVERSITY BUSINESS SCHOOL UNIVERSITY OF KARACHI BS (BBA) VI

Chapter 7: SAMPLING DISTRIBUTIONS & POINT ESTIMATION OF PARAMETERS

Advanced Financial Modeling. Unit 2

Refer to Ex 3-18 on page Record the info for Brand A in a column. Allow 3 adjacent other columns to be added. Do the same for Brand B.

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

Computational Finance Improving Monte Carlo

Risk analysis in adopting FES-exoskeleton system in rehabilitation programs

Computational Finance. Computational Finance p. 1

. (i) What is the probability that X is at most 8.75? =.875

Why Pooling Works. CAJPA Spring Mujtaba Datoo Actuarial Practice Leader, Public Entities Aon Global Risk Consulting

CHAPTER 2 Describing Data: Numerical

Alpha, Beta, and Now Gamma

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

1 Sampling Distributions

Sampling Distribution of and Simulation Methods. Ontario Public Sector Salaries. Strange Sample? Lecture 11. Reading: Sections

NPV Method. Payback Period

Averages and Variability. Aplia (week 3 Measures of Central Tendency) Measures of central tendency (averages)


This item is the archived peer-reviewed author-version of:

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan

ก ก ก ก ก ก ก. ก (Food Safety Risk Assessment Workshop) 1 : Fundamental ( ก ( NAC 2010)) 2 3 : Excel and Statistics Simulation Software\


Transcription:

PROJECT MANAGEMENT: PERT AMAT 167

PROBABILISTIC TIME ESTIMATES We need three time estimates for each activity: Optimistic time (t o ): length of time required under optimum conditions; Most likely time (t m ): most probable amount of time required; and Pessimistic time (t p ): length of time required under the worst conditions;

BETA DISTRIBUTION This is used to describe the inherent variability in time estimates. 0 t o t m t e t p Activity start Optimistic time Most likely time (mode) Pessimistic time

BETA DISTRIBUTION There is no established theoretical justification for using the beta distribution. It has certain features that make it attractive in practice: ØThe distribution can be symmetrical or skewed to either the right or the left according to the nature of a particular activity; Øthe mean and variance of the distribution can be readily obtained from the three time estimates (t o, t m, t p ); and Øthe distribution is unimodal with a high concentration of probability surrounding the most likely time estimate.

AVERAGE TIME Expected time of an activity: t e t 4 t t 6 o m p Expected duration of a path: Path mean of expected times of activities on the path

Variance of an activity s time: The larger the variance, the greater the uncertainty. VARIANCE 2 2 2 ( tp to) ( tp to) or 6 36 Note: the standard deviation of each activity s time is estimated as one-sixth of the difference between the pessimistic and optimistic time estimates Variance of a path s time: (Variances of activities on path)

EXAMPLE AOA diagram 1-3-4 a Optimistic time Most likely time 2-4-6 b Pessimistic time 2-3-5 c 3-4-5 d 2-3-6 g 3-5-7 e 4-6-8 h 5-7-9 f 3-4-6 i

EXAMPLE AON diagram Start 1-3-4 2-4-6 2-3-5 a b c 3-4-5 3-5-7 5-7-9 d e f 2-3-6 4-6-8 3-4-6 g h i Finish

REMARK (TRIANGULAR DISTRIBUTION) http://www.epixanalytics.com/modelassist/atrisk/images/15/image219.gif

PATH PROBABILITY Although activity times are represented by a beta distribution, the path distribution is represented by a normal distribution. The central limit theorem tells us that the summing of activity times (random variables) results in a normal distribution. The normal tendency improves as the number of random variables increases. However, even when the number of items being summed is fairly small, the normal approximation provides a reasonable approximation to the actual distribution.

FIGURE 17.9 PATH PROBABILITY Path Activity Activity Activity Beta Beta Beta Normal Probability that a given path will be completed in a specified length of time, can be determined using: z Specified time Path mean Path standard deviation

PATH PROBABILITY Probability of completing the path by the specified time 0 Expected path duration z Specified time

PATH PROBABILITY The resulting value of z indicates how many standard deviations of the path distribution the specified time is beyond the expected path duration. The more positive the value, the better. Rule of thumb: treat the path probability as being equal to 100 percent if the value of z is +3.00 or more. Note: probability when z = +3.00 is.9987.

PATH PROBABILITY A project is not completed until all of its activities have been completed, not only those on the critical path. It sometimes happens that another path ends up taking more time to complete than the critical path. This requires determining the probability that all paths will finish by a specified time. To do that, find the probability that each path will finish by the specified time, and then multiply those probabilities. The result is the probability that the project will be completed by the specified time.

INDEPENDENCE This assumes independence of each path duration times: find the probability that each path will finish by the specified time, and then multiply those probabilities. To use this, activity times should be independent of each other, and each activity is only on one path. However, this assumption is usually considered to be met if only a few activities in a large project are on multiple paths.

REMARK (NOT INDEPENDENT) In practice, when dependent cases occur, project planners often use Monte Carlo Simulation.

EXERCISE What is the probability that the project can be completed within 17 weeks of its start? AON diagram 1-3-4 2-4-6 2-3-5 a b c 3-4-5 3-5-7 5-7-9 What is the probability that the project will not be completed within 17 weeks of its start? Start d e f 2-3-6 4-6-8 3-4-6 g h i Finish

SOLUTION Path 17 weeks 1.00 a-b-c 10.0 Weeks d-e-f 16.0 Weeks 1.00 g-h-i 13.5 Weeks

SOLUTION Path z 17 Expectedpath duration Path standarddeviation Probability of Completion in 17 Weeks a-b-c 17 10 722. 097. d-e-f 17 16 100. 100. 1.00.8413 g-h-i 17 13. 5 107. 327. 1.00 P( Finish by week 17) P( Path a-b-c finish ) P( Path d-e-f finish ) P( Path g-h-i finish) 100.. 8413 100.. 8413