GPE engineering project management. Project Management in an Engineering Context

Similar documents
Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

UNIT-II Project Organization and Scheduling Project Element

Project Management Techniques (PMT)

Textbook: pp Chapter 11: Project Management

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

CHAPTER 9: PROJECT MANAGEMENT

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

CISC 322 Software Architecture

Project Management -- Developing the Project Plan

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

IE 102 Spring Project Management

Teori Pengambilan Keputusan. Week 12 Project Management

u w 1.5 < 0 These two results imply that the utility function is concave.

Real-World Project Management. Chapter 15

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

Project Management with Brief Information regarding CPM and PERT Methods

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

Project Management Chapter 13

After complete studying this chapter, You should be able to

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Management Management

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

Plan Implementation. Pushpa Lal Shakya

06IP/IM74 OPERATIONS RESEARCH

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

Comparison between Deterministic and Stochastic Time Estimating Techniques

PROJECT MANAGEMENT: PERT AMAT 167

Project Management and Cost Control

MS Project 2007 Page 1 of 18

WHY ARE PROJECTS ALWAYS LATE?

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

COPYRIGHTED MATERIAL. Index

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri

Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

Project planning and creating a WBS

Construction Management

Appendix A Decision Support Analysis

Chapter 11: PERT for Project Planning and Scheduling

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

SAMPLE. DETERMINING ACTIVITY DURATIONS TCM Framework: 7.2 Schedule Planning and Development. AACE International Recommended Practice No.

NETWORK ANALYSIS QUESTION BANK

CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING

POLYTECHNIC OF NAMIBIA

Decision Support Tool for Project Time-Cost Trade-off

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2

SWEN 256 Software Process & Project Management

Project Management Fundamentals

1 of 14 4/27/2009 7:45 AM

Lecture 3 Project Scheduling

CHAPTER 5 STOCHASTIC SCHEDULING

Project Planning. Planning is an important step in project execution. Planning means:

Chapter 2 The PERT/CPM Technique

ETSF01: Software Engineering Process Economy and Quality

Programme Evaluation and Review Technique

International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN:

Project Risk Management

MnDOT use of Calendars in Primavera P6

MODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

Line Balancing S K Mondal Chapter 3

Ins. Luay Dwaikat Fall 2013/2014

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

A SINGLE STEP CPM TIME-COST TRADEOFF ALGORITHM. In Mathematics and Computing. Under the guidance of Dr. Mahesh Kumar Sharma

The Project Times and Costs

Introduction to Project Management. Modeling after NYS ITS

Outline. Project Management. Introduction. What is a Project?

Appendix B: Glossary of Project Management Terms

Chapter16Project Management and. Scheduling Project management

Quality Project Management

A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT

PASS4TEST. IT Certification Guaranteed, The Easy Way! We offer free update service for one year

Research Methods Outline

Poor Man s Approach to Monte Carlo

Making sense of Schedule Risk Analysis

Project Network Analysis Model to Dredging Operations In Niger Delta

THE ACCELERATING OF DURATION AND CHANGE OF COST ON CONSTRUCTION PROJECT IMPLEMENTATION

Cost Reduction: Planning & Control. Impacting the Bottom Line

If you have a question during any portion of this exam, raise your hand and speak to the proctor. Write legibly.

Exam Questions PMI-SP

BTech: Operations Management

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015

Systems Engineering. Engineering 101 By Virgilio Gonzalez

JAYARAM COLLEGE OF ENGINEERING AND TECHNOLOGY DEPARTMENT OF INFORMATION TECHNOLOGY

MINIMIZE TIME AND COST FOR SUCCESSFUL COMPLETION OF A LARGE SCALE PROJECT APPLYING PROJECT CRASHING METHOD

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

CHAPTER 5. Project Scheduling Models

Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique

Transcription:

GPE engineering project management Project Management in an Engineering Context

Network diagrams in context PM SOW CHARTER SCOPE DEFINITION WBS circulation, negotiation, translation WBS WP à activities ----- estimation Time AOA GANTT Cost PERT AON ----------- planning, resource allocation, cost allocation, control ---------Mainly PMBOK chapter 6

Network diagrams WBS

PERT Program Evaluation & Review Technique

WBS GANTT PERT

Network Analysis (PERT Program Evaluation & Review Technique; CPM Critical Path Method) Network modulation approach used in planning, scheduling and controlling projects. Beyond the analysis they facilitate, they represent a common ground to discuss options so they are excellent communication tools. They facilitate thematic brain-storming analysis Network diagrams are entity/relationship models (interrelations among instances of resources) usually used in project planning, namely on scheduling and time management Using these models we need to take into account: interrelation of activities (sequencing relations) and relations among activities and resources (allocation) There are more complex models, using statistics but we will eventually address them later

Critical Path Method (CPM) (deterministic) A schedule network analysis technique used to determine the amount of scheduling flexibility (the amount of float) on various logical network paths in the project schedule network, and to determine the minimum total project duration. Early dates are calculated by means of a forward pass, using a specified start date. Late dates are calculated by means of a backward pass, starting from a specified completion date, which sometimes is the project early finish date calculated during the forward pass calculation. Program Evaluation and Review Technique (PERT) (probabilistic) A technique used to improve the accuracy of the cost or duration estimates of project components when there is uncertainty. PERT uses weighted averages of optimistic, pessimistic, and most likely estimates (the well-known three-point estimates) of the components' cost or duration. Different weighting schemes represent different probability distributions of the possible cost or duration of a component. For instance, the typical formula is [(optimistic + 4 times the most likely + pessimistic) divided by 6], approximates a beta distribution.

CPM/PERT Critical Path Method (CPM) DuPont & Remington-Rand (1956) Deterministic task times Activity-on-node network construction Project Evaluation and Review Technique (PERT) US Navy, Booz, Allen & Hamilton Multiple task time estimates (probabilistic) Activity-on-arrow network construction

PERT elements Events (states), activities (nature and time), preceding, allocation, context (context must always be defined and clarified) Some examples of PERT representation - AOA activity on arrow, or ADM - arrow diagramming method; and AON activity on node A,3 B,5 C,7 D,2 E,6 F,3 G,10

PERT elements Events (states), activities (nature and time), preceding, allocation, context (context must always be defined and clarified) Some examples of PERT representation - AOA activity on arrow, or ADM - arrow diagramming method; and AON activity on node A,3 B,5 C,7 D,2 E,6 F,3 G,10 17 19

Examplesof different notations

Parallel activities signaled as we exemplify are not allowed A B A,B A B dummy If you fail this notation in the exam you will have 0 in the entire question

Task B can only be started after activity A is completed. The same with D and C A,3 B,7 C,4 D,6 10 10

Network Analysis example AOA A,3 B,7 C,4 D,6 There is a dummy activity duration 0 (only a logical dependency)

Network Analysis example AOA A,3 B,7 C,4 D,6 10 10 Are all paths identified?

Network Analysis example AOA A,3 B,7 C,4 D,6 10 10 11 No, there are three paths, not two! And that makes quite a difference!!

Network Analysis example AOA A,3 B,7 C,4 D,6 10 10 11 (A,B) (C,B) (C,D) Instant time - 5 Time interval - 6

Network Analysis example AOA A,3 B,7 C,4 D,6 10 10 11 Activity Duration Early St Early Fi Latest St Lat. Fi. Float A B C D Dummy

Network Analysis example AOA A,3 B,7 C,4 D,6 10 10 11 Activity Duration Early St Early Fi Latest St Lat. Fi. Float A 3 0 3 1 4 1 B 7 4 11 4 11 0 C 4 0 4 0 4 0 D 6 4 10 5 11 1 Dummy 0 4 4 4 4 0 Instant times

PERTS, and projects 1. Define the project and all its activities. The project is made of tasks and all tasks should have a single start and a single finish 2. Develop the relationships among the activities. Decide which activities must precede, which must follow others, and the ones that can be executed in parallel. If you are short in time try to put in parallel as much activities as you can 3. Draw the network diagram connecting all the activities. Each activity is unique. Dummy activities are immaterial in time but relevant in sequence, they impose logical dependences 4. You can assign time and cost to each activity Preceded by a planning effort by the project management team. This planning effort is part of the Develop Project Management Plan process 5. Compute the longest time path through the network. This path is called the Critical Path 6. Use the network to help plan, schedule, monitor and control the project and also as a communication tool documented in the schedule management plan

PERTS, and projects

PERTS, and projects

WBS GANTT PERT

Late start and backward path backward pass Early dates are calculated forwards, using the forward path. Late dates are calculated in reverse direction, starting at the date of the finishing of the project this is the backward path In this example one backward path leads us to event 3 through activity B. So we have: Total project time (critical path) = 11 11-7 = 4. This means that the late start for activity B is 4 Relating to event 2 we have to evaluate two paths, Dummy and D. Through Dummy we have 4-0 = 4, this means that Dummy late start is 4 and through D we have 11-6 = 5, so activity D late start is 5 Activ ity Dura tion Early St Early Fi Lates t St Lat. Fi. Float A,3 3 B,7 A 3 0 3 1 4 1 B 7 4 11 4 11 0 C 4 0 4 0 4 0 D 6 4 10 5 11 1 Dum my 0 4 4 4 4 0 DUMMY,0 C,4 D,6 2 4

So you already have the rule to compute early starts and late starts. Early starts are computed in the forward path from the beginning to the end, adding duration and late starts are computed in the backwards path, subtracting duration from the end Project management tools compute this for you, you just have to manage according to situated conditions (environment, resources, risk, )

Your project is to design and develop an electric motor. Activity durations and predecessors are identified at the following table. A) construct a PERT AOA; B) Which is the duration of every path? Which path is the critical one? C) What happens if activity E duration becomes 8? Activity duration predecessor A 10 - B 20 - C 4 - D 2 A E 10 B,C F 8 B,C G 4 B,C H 2 C I 6 G,H J 2 D,E

Network Analysis example AOA Activity duration predecessor A 10 - B 20 - C 4 - D 2 A E 10 B,C F 8 B,C G 4 B,C H 2 C I 6 G,H J 2 D,E

Network Analysis example AOA Activity duration predecessor A 10 - B 20 - C 4 - D 2 A E 10 B,C F 8 B,C G 4 B,C H 2 C I 6 G,H J 2 D,E 8 paths CP

Network Analysis example AOA Activity duration predecessor A 10 - B 20 - C 4 - D 2 A E 10 B,C F 8 B,C G 4 B,C H 2 C I 6 G,H J 2 D,E 8 paths E from 10 to 8: 30 CP CP 14

Network Analysis example AOA à AON A,3 AOA AON C,4 A,3 B,7 D,6 B,7 END BEGIN C,4 D,6 With AON you don t have dummies

Network Analysis example AON A,10 Activity duration predecessor A 10 - B 20 - C 4 - D 2 A E 10 B,C F 8 B,C G 4 B,C H 2 C I 6 G,H J 2 D,E D,2 J,2 B B,20 C,4 E,10 END F,8 G,4 H,2 I,6 ADJ 14 BEJ 32 BF 28 BGI 30 CEJ 16 CF 12 CGI 14 CHI 12