Delay In Start-Up Insurance. A Primer Based on Lessons Learned Houston Marine Insurance Seminar September 21, 2015

Similar documents
The Navigators Group, Inc.

Delay in Start Up Insurance Understanding & Controlling Risk

between the financial and insurance viewpoint DSU WORKING PARTY CONCLUSIONS IMIA Conference 2013 New Delhi

GAP INSURANCE When It Is Needed Why Adding it to a Personal Auto Policy Often is the Better Choice. Example of New Vehicle Pricing - from TRUECar.

ALOP Advance Loss of Profits. SwissRe ALOP

Builder s Risk. Introduction and Coverages. March 9, 2018

Business Interruption Policy

Advance Loss of Profits Insurance A knowledge share initiative of Salasar Services (Insurance Brokers) Pvt. Ltd.

Damage to Existing Property Coverage Property Damage or Third Party Liability?

REAL ESTATE INDUSTRY SESSION IND010

IMIA Engineering Underwriting Training Course

MITIGATION OF HYDRO PROJECT DEVELOPMENT RISK - INSURANCE NEED

Business Continuity Planning. A guide to loss prevention

INSURING DELAY IN OPENING AND ASSOCIATED COSTS

Recent Trends in California Indemnity and Additional Insured Law Impacting Construction Disputes

Worldwide Financed Projects Middle East, SE Asia and Latin America Key Developing Insurance Markets

Demystifying Business Interruption in Mining:

A Perfect Storm: Hurricanes and Construction Defect Claims

Insurance for the construction industry an overview of core products, coverage and claims

Elements of Contractual Risk Transfer

THE 24TH ANNUAL INSURANCE SYMPOSIUM: ALLOCATION & OTHER INSURANCE ROBERT J. WITMEYER & KATYA G. LONG

Business Interruption! Best Practice:! A Forensic Accounting Perspective!

Recent Developments in Construction Coverage

Table of Contents. The Builders Risk Book

COVERAGE FOR THE COST OF MITIGATING DAMAGE

Risk Control and Claims Handling on Advanced Loss of Profits Insurance (ALOP) (WGP63 (2009))

CONTRACTUAL RISK TRANSFER SPONSORED BY

James K. Ruble MEGA Seminar Topic Descriptions Lake Buena Vista, Florida June 4-7, 2018

The Navigators Group, Inc.

Jujitsu Techniques for Enforcing & Defending Contract Liability Claims

Additional Insured Coverage under Excess Policies

Contractual Breaches & Termination

Selected Insurance Issues in Commercial Real Estate Transactions Understanding the Nuances

MACHINERY BREAKDOWN LOSS OF PROFITS- Absa Select

Insurances. National Certificates of Currency

ALLOCATION AMONG MULTIPLE CARRIERS IN CONSTRUCTION DEFECT LITIGATION

Introduction to Business Interruption Insurance. Uninsured Expenses in BI Policies

Where Builders Risk Meets Personal Lines

Coverage for Contractual Risk Transfer and Additional Insured Issues

Business Interruption Insurance

Understanding Mortgages

Bookkeepers are the accountant s eyes and ears. Few accountants actually take the time

Zurich Canada Builders Risk. New Forms and Enhancements

Paul May LLB, MBA, FCII, FCILA, ADipC, DipAIS, ELAE, MAE, MCIArb FIFAA. Chairman Concordia Consultancy Ltd

2018 Cyber & Tech Liability Risk Transfer Update Part 2

American Bar Association Forum on Construction Law. Writing Outside the Lines: Changes to Contract Clauses (From the Contractor s Perspective)

Construction Project Management from the Owner s Perspective

Alternative business entities: liability and insurance issues

Insurer v. Insurer: The Bases of an Insurer s Right to Recover Payment From Another Insurer*

FINANCIAL SERVICES GUIDE

Holden Motor Equity Insurance. Policy Document and Product Disclosure Statement

IMIA Working Group Paper WG 92 (15) IMIA Conference Merida, Mexico Sep Engineering Insurance: Best Practice - Claims Protocol

Allocating Risk in Real Estate Leases: Contractual Indemnities, Additional Insured Endorsements and Waivers of Subrogation

INSURANCE AND INDEMNIFICATION MANUAL. Supplement to Policy 560 i

Session of HOUSE BILL No By Committee on Insurance 1-19

Keeping Finances Under Control. How to Manage Debt so it Doesn t Manage You

Construction Insurance 2018 Construction Certification Review Course. Christopher Mueller Taylor, Day, Grimm & Boyd

Waiver of Subrogation:

Practical Tips for Pursuing Additional Insured Coverage

Contractual Risk Transfer in Construction Contracts

WHAT DOES IT MEAN TO EXHAUST AN UNDERLYING LAYER OF INSURANCE?

Supply Chain Risk Management. Willis Latin America Energy Conference October 10, 2012

TRENDS INVOLVING ALL RISKS COVERAGE & CLAIMS POLICYHOLDER S PERSPECTIVE. William Chip Merlin, Jr., Esq. President, Merlin Law Group.

M&A Transaction Insurance: An Overview

Financial Services Guide

Tipsheet 2 Insurance Clauses Pitfalls for brokers

LOSS OF PROFITS (MACHINERY) SECTION

EXHIBIT C PROFESSIONAL SERVICES CONTRACT TEMPLATE

Maintenance Covers. SwissRe Techsem Poland

LEG Defect Exclusions and Project Delays

Y063202QBE0116A - PL Y063202QBE0116A - EL FI & FI & FI PI. Date for Renewal: 1 September 2017

GENESIS LAND DEVELOPMENT CORP.

Navigators Group Inc. Insuring a World in Motion

Mitigating Risk through Construction Contracts and Claims Avoidance

Condensed Consolidated Interim Financial Statements For the three and nine months ended September 30, 2012 and 2011 (Unaudited)

15 of the 30 costliest hurricanes in US history have occurred in the last 10 years. Each of the 15 storms caused more than $1 billion in damages

Builders Risk. David G. Jordan November 20, 2009

2018 Risk Transfer Update Part 1

Contractor Financing Plan

Business Interruption Training Series

Insurance Checklist - Explanatory Note [1]

Excess Layers of D&O Insurance: Peeling the Onion

Coverage for Contractual Risk Transfer and Additional Insured Issues. Jeffrey J. Vita and Edwin L. Doernberger Saxe, Doernberger & Vita, P.C.

Construction Risk in P3 Projects. Timothy J. Murphy Partner McMillan LLP

Allocating Risk in Real Estate Leases: Contractual Indemnities, Additional Insured Endorsements and Waivers of Subrogation

Consequential Loss (Machinery) Insurance A knowledge share initiative of Salasar Services (Insurance Brokers) Pvt. Ltd.

Rail Owner Controlled Insurance Program Manual

Builders Risk. Above and Below Ground

PAYPROP DEPOSITGUARANTEE FREQUENTLY ASKED QUESTIONS

Warranties, Surety Bonds and Correction Periods: How To Get Defects Repaired

LOSS OF PROFITS (MACHINERY BREAKDOWN) SECTION

Workshop D Builder s Risk: From the Basics to the Best Practices

Wednesday, March 5, 2014 Houston, TX. 1:30 2:45 p.m. OEE ISSUES AND ANSWERS

CONTRACT REVIEWS THE GOOD, THE BAD AND THE UGLY

Administrative Simplification Operational Guidelines. Submitting Supporting Documentation

SASRIA LTD. BUSINESS INTERRUPTION SECTION (STANDING CHARGES / WORKING EXPENSES AND/OR NET PROFIT ONLY) CONTENTS

Debbie Sines Crockett CHEFFY PASSIDOMO ATTORNEYS AT LAW Tampa & Naples, Florida

A Tailored Approach to Risk Management GALLAGHER ENERGY PRACTICE

Will Deepwater Horizon Change a Long Standing Rule of Law? ACCIDENT. Insurance Provisions in the Drilling Contract

General Terms and Conditions, Gerritsen Projects B.V.

Transcription:

Delay In Start-Up Insurance A Primer Based on Lessons Learned Houston Marine Insurance Seminar September 21, 2015

What is DSU?

DSU on the Rise Number of policies involving DSU cover DOUBLED over the last 10-12 years. The frequency of DSU claims are increasing with approximately 6.5% of all DSU risks encountering a loss.* From 1980 to 2008, majority of DSU losses involved: power plants (27%); building and construction (27%); and industrial process plants (13%).* In recent years, some very large DSU claims have been encountered which led to the formation of the London Market Working Party in 2012. * Topics Risk Solutions (Munich Re) (February 2013)

ALOP Advanced Loss of Profits Anticipated Profits Delayed Earnings Delayed Profits Delayed Completion Insurance Delayed Opening DSU Can Also Be Referred To As:

The Basics of DSU Generally, DSU coverage is not considered without concurrent contract works insurance such as builder s risk, contractor s all risk (CAR), or erection all risk (EAR). The key here is to tie any DSU cover to material damage cover afforded by another type of insurance. There is cover under other policy forms that might address project delay without a material damage trigger but such coverage is outside the scope of DSU and our discussion today.

Before coverage under the DSU endorsement can attach, there must be what? A) A delay caused by property damage covered by the corresponding PD policy. B) A loss caused by the contractor. C) A delay caused by the late arrival of necessary materials for the project. D) Any delay to the project schedule that is greater than the time element deductible.

Before coverage under the DSU endorsement can attach, there must be what? A) A delay caused by property damage covered by the corresponding PD policy.

Covered Property Damage Must Cause the Delay It is generally accepted that if there are concurrent insured and uninsured losses that cause a delay in the project schedule, this does not extend the indemnity period. There may be a specific exclusion in the DSU endorsement for concurrent insured and uninsured delays. Of course, policy language and relevant case law, if any, should be reviewed.

Covered Property Damage Must Cause the Delay Issues that are unrelated to the covered property damage, such as manpower shortages caused by damages to uncovered property or delays in having the undamaged portion of the project approved by local officials, have been found to not be a valid basis for extending the DSU indemnity period. See Diamond Beach, VP, L.P. v. Lexington Ins. Co., 748 F. Supp. 2d 648, 655 (S.D. Tex. 2010); Tocci Building Corp. v. Zurich Am. Ins. Co., 659 F. Supp. 2d 251, 259-61 (D. Mass. 2009).

Covered Property Damage Must Cause the Delay An example from the London Market Working Party:

DSU is similar to BI cover in some respects, but different in important ways On the legal side, this is problematic because there is a large body of case law on business interruption cover, but very little case law on DSU. At the same time, even the case law on business interruption can be confusing and contradictory.

DSU vs. Business Interruption DSU coverage typically obtained with builder s risk policies and before operational insurance. DSU insurance typically covers the loan for the project and other fixed costs (this coverage is often required by loan covenants). Only 1 period of delay and 1 time excess deductible. This is irrespective of the number of covered PD losses. If there is a delay in the scheduled completion of the project, there are no historical sales that can be analyzed after loss/delay in completion.

Policy Language is Important and Brokers and Underwriters Must Communicate Clearly

Policy Language is Important As our friends at JLT have said, the time to realize that you have a bad wording is not when the claim occurs. JLT Article; Delay in Start-Up, It s Time for a Consistent Approach, at p. 6 (February 2008).

Should a contractor be listed as an insured under the DSU endorsement? No. The contractor should not be an additional insured under the DSU endorsement. The contractor will have to seek coverage for soft costs under a contractor s extra expense endorsement.

Contractor and ICOW Provision An example of an ICOW provision: The Increased Cost of Working being defined as the expenditure necessarily and reasonably incurred by the Owner or any other party on its behalf for the sole purpose of avoiding or diminishing the amount which the Insurer would have been liable to pay as Fixed Costs under the policy, but not exceeding the sum by which the amount otherwise payable is reduced.

Mitigation Efforts Result In No Delay Under DSU Endorsement Must an insurer pay under the ICOW provision? - Yes. Even if there is no delay, an insurer may have to make a payment to the insured or the contractor under a loss mitigation provision or the DSU endorsement s ICOW provision, if expenses are incurred to avoid a loss recoverable under the DSU cover. See Assicurazioni Generali S.P.A. v. Black & Veatch Corp., 362 F.3d 1108, 1115-16 (8th Cir. 2004).

Clear Language is Key Who are the Insureds? Owner or owners actual entity that will own and operate the facility/project. Not a distant parent company. Bank or lender may be an additional insured. The contractor should never be an additional insured. Be specific regarding additional insureds, don t use the typical list of generic affiliates.

Clear Language is Key What is the project? The project should be well defined. No cover if no delay to the project, even if a portion of project is damaged prior to completion date. If it is repaired and doesn t cause delay to the project as a whole, then no cover. Phased handover should be addressed if cover is intended.

Clear Language is Key How is DSU indemnity period defined? Begins at scheduled date of completion as per policy unless changed. Float or creep issue can arise. Project monitoring is recommended. Substantial completion or commercial operation? How are those terms defined? Sample policy language provides that the DSU indemnity period ends and the business shall be deemed to have commenced as of: the issue date of the certificate of completion, acceptance/takeover by the principal, the date of operation start-up or the date operation could have started but for the delay, whichever occurs first. Provides insurers with potential actual and theoretical dates for conclusion. Phased handover?

ANOTHER QUESTION ON DSU COVERAGE! DSU endorsement generally defines fixed costs as costs of the insured business which continue to be payable throughout the indemnity period. Which of the following does not come within this definition?

Which one is not a fixed cost? A) Principal payments. B) Property taxes. C) Amortization of finance costs. D) Fees under a take-or-pay water contract.

Which one is not a fixed cost? C) Amortization of finance costs.

Clear Language is Key What costs are covered? Depending on policy language sum insured could include: Gross profit (expected revenues less variable costs) Debt service Fixed operating costs

Clear Language is Key What costs are covered? Gross profit (expected revenues less variable costs) Fixed costs? How are those defined? What is included or excluded such as debt service and fixed operating costs. If fixed costs refers to a schedule, make sure that all owners interests are accounted for and that covered fixed costs are defined in the schedule. For example, DSU may insure principal payments on loans, interest on loans, additional insurance premiums, and property taxes, but not amortization of finance costs. The definition of fixed costs in the DSU cover may also cover the fees associated with take-or-pay contracts with suppliers.

Review the Sum Insured The key regarding covered costs is that the underwriter should closely review the submitted business plan, projected revenues and costs to substantiate the accuracy of the sum insured put forth by the insured. Insured will probably paint a rosy outlook of projected earnings.

What about liquidated damages? Who should have to pay first? The insurer providing the DSU cover or the contractor owing LDs?

What about liquidated damages? Shouldn t the DSU recovery be offset by the owner s recovery of LDs from the contractor? - Offset language should be included if intended.

Clear Language is Key Offset language concerning LDs should be included if intended. This contractual limitation may avoid the issue of an insured claiming that it was not made whole by the DSU recovery and that offset is inappropriate. The policy language should also make clear who should pay first, the contractor or the DSU insurer. Typically, the parties will want the insurer to pay first. The offset language in the DSU cover should also include language that the insurer can recover or recoup money paid to the owner. There should also be a provision in the policy that requires the owner to enforce its various rights under the contract, including the recovery of liquidated damages from the contractor. These provisions may get the insurer around subrogation complexities.

Monitoring Methods & Strategies Obtain Contractor s Monthly/ Weekly/Daily Reports. Site Visits by Representatives of the Insurer. Remote Monitoring of Schedule. Obtain Schedule in Native Format. Mitigate Costs Through Arrangement With Financiers of Project.

Who owns the float in the schedule? Suppose the substantial completion date set forth in the DSU policy is May 25, 2015; however, at the time of an indemnifiable loss, the contractor was ahead of schedule and was set to complete the project on March 25, 2015. Due to the PD loss, the new substantial completion date is February 15, 2016. Who gets to benefit from the contractor being 2 months ahead of schedule? Who owns the float?

Who owns the float in the schedule? If a loss occurs and the DSU endorsement s scheduled date of completion has not been revised, any float in the schedule should go to the insurer s benefit.

Reasons for Program Monitoring Owner may want to monitor, because contractor likely built a lot of float into its schedule. The float issue. Insurer may want to monitor, because it will be in a position to determine the actual cause of the delay or if the scheduled completion date should be moved back. The creep issue.

When a DSU Claim Occurs, Avoid the DSU Blues! B.B. King Muddy Waters

Unexpected Issues Can Arise...

Things Can Happen Quickly!

If there is an indemnifiable DSU claim, it is important to get the money flowing ASAP.

Actions to Take After the Loss Get adjustment team assembled quickly. Determine the cause of the loss/delay and make sure delay was solely caused by a covered cause of loss. Attempt to reach a written agreement with the owner on a scheduled payment plan that the adjustment team can abide by. Attempt to reach a written agreement with contractor and owner on an expedited reinstatement agreement. Adjustment team should confirm that the project would have generated enough turnover to cover its fixed costs.

During the indemnity period/after the original substantial completion date, the insured will have to obtain new DSU coverage.

Questions or comments?