EDP Brasil BM&FBovespa: ENBR3. 3Q17 Results Presentation (Teleconference on November 01 st, 2017)

Similar documents
Execution Excellence. Integrated Operator/ Portfolio Optimization. Operational Efficiency

Foco nas Availability of 89%; Follow-up of Ceara s hydrological situation; EBITDA of R$ 504 million.

This presentation may include forward-looking statements of future events or results according to regulations of the Brazilian and international

EDP s Participation in the 2nd Stage of Transmission Auction 013/2015 Localization: Construction deadline: Lenght: Capex: RAP:

Highlights. Results. Indebtedness. Private Capital Increase

Release 3Q17. October 31 st, 2017 NET INCOME. Main Indicators

Release 2Q17 July 26, 2017

EDP Energias do Brasil. Investor Presentation

Release 1Q18. May 09 th, Net Income EBITDA PMTO ¹. Pecém. Commercialization. Pecém. São Manoel. Hydrological Hedge. Distributed Energy.

Novembro de EDP Energias do Brasil

4Q17 and 2017 Release

APIMEC Presentation August 2011

RESULTS RELEASE 4Q16

Investor Day -May Oporto, May 22 nd, 2012

EDP Energias do Brasil Q10 Results

EDP Energias do Brasil reports 2Q14 EBITDA of R$ 430 million

EDP - Energias do Brasil

Recurring (1) EBITDA -4% YoY to 911m Renewables and Brazil underlying growth offset by forex (-6%) and regulatory changes in Portugal (- 66m YoY)

+0.6GW additions of wind and solar capacity Efficiency savings of 141m (26% above 2017 target for OPEX IV Programme)

2Q08. Earnings Release

ELECTRICITY GENERATION

2010 Results. March, 2011

9M18 Results Presentation

Recurring EBITDA +10% to 2,832m including 2% negative impact from ForEx

RESULTS Assertive decision-making points to path of success

Agenda. About Sector About Copel Main Strategic Objectives Leverage Analysis Budget Supplementation Startup New Assets

EDP Investor Day. 5 years of IPO EDP in Brasil

-3% Recurring +5% -16% Recurring EBITDA (1) : 1,740m Sound underlying growth in Brazil & renewables

Jonel Nazareno Iurk, CEO Adriano Rudek de Moura, CFO

Light S.A. Overview & Strategy. Rio de Janeiro 3Q18

Realized. 9.86% 717 Sale completed 25% 80 Transfer, to Taesa, completed. In progress

Antonio Sergio de Souza Guetter, CEO Adriano Rudek de Moura, CFO

Institutional Presentation 4T16

9M17 RESULTS: KEY HIGHLIGHTS

Common stock prices 1. New York Stock Exchange indexes (Dec. 31,1965=50)2. Transportation. Utility 3. Finance

Neoenergia s Overview Regulatory Environment Networks (Distribution and Transmission) Contracted Generation Financial Results and Debt Profile

Recurring EBITDA: 1,902m, -5% YoY 62% decline YoY of hydro production in Iberia: 42% below historical avg. in 1H17 vs.

COMPANY OVERVIEW. US$812mn. Largest Energy Generator in Chile 5,063MW 531 MW 100% 11 Years. US$2.2bn. BBB-/Baa3 66.7% of installed capacity

Net debt of 15.1bn by Sep-17, -5% YTD Portfolio reshuffling (disposal of Naturgas & reinforecement in EDPR stake to 82.6%): - 1.

2Q15. 2Q15 Results. Conference Call 2Q15 with Simultaneous Translation. Date: 08/19/2015

Annual Public Meeting of Analysts and Investors 2011

3nd Quarter Results. November Economic - Financial Office and Investor Relations Office

2Q16 DISTRIBUTION OF R$ MILLION IN DIVIDENDS THIS QUARTER RESULTS. Results Conference Call. Table of Contents

INSTITUTIONAL PRESENTATION 2Q18

Reduction of R$177 million (2Q18/2Q17) R$649 million - Total amount. Premium of 76.8% on auction reserve price

In this material, financial amounts are in R$ million (R$ mn) unless otherwise stated. Financial data reflect the adoption of IFRS.

Institutional Presentation. February 2018

1Q14 Results. May Economic - Financial Office and Investor Relations Office

Highlights 1Q16. 1) Balance of sectoral financial assets and liabilities, excluding tariff

EDP Energias do Brasil S.A. CNPJ/MF nº / NIRE Publicly Company. 36th General and Special Shareholders' Meeting

Arise Windpower AB. Company presentation February 2013

ELECTRICITY GENERATION

1Q14. 1Q14 Highlights. Conference Call 1Q14 with Simultaneous Translation. Net Operating Revenue of R$1.7 billion in 1T14, 48.9% higher than 1Q13

Successful Strategy Performance reflects balanced portfolio structure. April, 2013

1Q13 Results. Highlights

3Q17. 3Q17 Results. Conference Call 3Q17 with Simultaneous Translation. Data: 14/11/2017 Portuguese

Fiscal Year Highlights. Conference Call 2013 with Simultaneous Translation

Successful Strategy. Performance reflects balanced portfolio structure 2017

FINANCIAL RESULTS Q CFO Irene Egset 4 th May 2017

2017 Results. Net Operating Revenue of R$ 1.5 billion. Gross Operating Profit of R$ 292 million. Adjusted EBITDA of R$ 389 million e Margin of 26.

COLBÚN S PRESENTATION BICE INVERSIONES CORREDORA DE BOLSA S.A. SEPTEMBER 2015

Financial & Business Highlights For the Year Ended June 30, 2017

Successful Strategy Performance reflects balanced portfolio structure. August, 2013

Growth on renewables and Brazil balanced with value crystallisation under a controlled financial leverage

Brazilian Electricity System in the World

This document has been prepared by EDP - Energias de Portugal, S.A. (the "Company") solely for use at the presentation to be made on this date and

Copel records EBITDA of R$254.3 million in the 4Q16

Fourth quarter 2016 Presentation to analysts and preliminary results 2016

2014 Results. March Economic - Financial Office and Investor Relations Office

Fixed Income Presentation 3Q17

JUNE

EEI Conference. November 10 th, 2015

Results Presentation 1Q13. Lisbon, May 10 th, 2013

EARNINGS RELEASE 1Q18 RESULTADOS

FINANCIAL RESULTS Q CEO Christian Rynning-Tønnesen CFO Irene Egset 26 October 2017

Consolidated EBITDA reaches R$ 429 million in 2Q17, CELPA reaches the regulatory target for energy losses

XML Publisher Balance Sheet Vision Operations (USA) Feb-02

Fixed Income Presentation 1Q18

Comgás gas sales revenue moves up 24.2% and EBITDA totals R$ 1,035.0 million in 2008

Large Commercial Rate Simplification

Citi: 10th Annual Brazil Equity Conference June 2017

Results 2Q18. August 2, 2018

Jonel Nazareno Iurk, CEO Adriano Rudek de Moura, CFO

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016

Presentation to Investors May, 2006

TD Securities 2011 Calgary Unconventional Energy Conference July 7, Dawn Farrell Chief Operating Officer

2Q17 RESULTS. Conference Call: Aug/11th :00 (BZ) / 13:00 (ET) Dial-in: Portuguese: +55 (11) English: +1 (646)

Fourth Quarter 2016 Performance Summary

In this material, financial amounts are in R$ million (R$ mn) unless otherwise stated. Financial data reflect the adoption of IFRS.

Morgan Stanley B I r t iilt U uttiili o ti nes al C P o r r e p s o e ra ntte at A iocc n ess Day

Sabancı Holding Q Earnings Presentation

Corporate Presentation 2017

Statkraft Investor Update. March 2014

Results Presentation 1Q18. April 26 th, 2018

PHOENIX ENERGY MARKETING CONSULTANTS INC. HISTORICAL NATURAL GAS & CRUDE OIL PRICES UPDATED TO July, 2018

Institutional. November, 2012

AES Tietê records 14% growth in 1Q05 EBITDA

Eletropaulo Metropolitana Eletricidade de São Paulo S.A.

RESULTS 2Q16. Investor Relations Telefônica Brasil S.A. July, 2016

ADMIE (IPTO) Holding S.A. 1H 17 earnings presentation September 2017

Transcription:

EDP Brasil BM&FBovespa: ENBR3 3Q17 Results Presentation (Teleconference on November 01 st, 2017)

Disclaimer This presentation may include forward-looking statements of future events or results according to regulations of the Brazilian and international securities and exchange commissions. These statements are based on certain assumptions and analysis by the company that reflect its experience, the economic environment and future market conditions and expected events, many of which are beyond the control of the company. Important factors that may lead to significant differences between the actual results and the statements of expectations about future events or results include the company s business strategy, Brazilian and international economic conditions, technology, financial strategy, public service industry developments, hydrological conditions, financial market conditions, uncertainty of the results of future operations, plans, objectives, expectations and intentions, among others. Considering these factors, the actual results of the company may be significantly different from those shown or implicit in the statement of expectations about future events or results. The information and opinions contained in this presentation should not be understood as a recommendation to potential investors and no investment decision is to be based on the veracity, current events or completeness of this information or these opinions. No advisors to the company or parties related to them or their representatives shall have any responsibility for whatever losses that may result from the use or contents of this presentation. This material includes forward-looking statements subject to risks and uncertainties, which are based on current expectations and projections about future events and trends that may affect the company s business. These statements include projections of economic growth and energy demand and supply, as well as information about the competitive position, the regulatory environment, potential opportunities for growth and other matters. Several factors may adversely affect the estimates and assumptions on which these statements are based. 2

Transmission Distribution Generation 3Q17 Operational Highlights Energetic Risk Protection Total energy hedge of 18% (184 average MW) Impact of +R$ 278 Million (Hydro+Com.) and +R$ 29 Million (Pecém) Construction of São Manoel 97.2% of physical work completion and the Operation License granted Uptime of Pecém 91% (9M17) higher than contracted (90%) Volume increase Total distributed energy growth of 2.3%, with highlight to EDP SP (+4.4%) Reduction of Total Losses -1.12 p.p. at EDP ES and -0.04 p.p. at EDP SP compared to Sep/16 (positive impact of R$ 25.2 million/year) Effectiveness in bad debt control R$ 21 million reduction compared to 2Q17 Bad Debt Provision/Gross Revenue of 0.6%, in 3Q17 (vs. 1.4% in 2Q17) CAPEX + 19.3% compared to 9M16 Environmental Licensing Early delivery of the licensing schedule for Lot 24 (Auction of Oct/16) 3

Sold Energy Generation Volume (GWh) Commercialization Volume (GWh) -2.9% 3,608 3,505 5,093 351 336 1,358 1,358 3,313 +53.7% 1,899 1,811 3Q16 3Q17 3Q16 Total Hydro Total Thermal 3Q17 Jari and Cachoeira Caldeirão HPPs Total Volume Distribution Volume (GWh) EDP São Paulo EDP Espírito Santo +4.4% 3,552 3,708 1,474 1,750 2,066 1,944-0.9% 2,326 2,306 143 116 801 941 1,383 1,249 Increase of 1.5% in industrial production in the state of São Paulo; Extraction industries; Auto-vehicles. 3Q16 3Q17 3Q16 3Q17 Captive Market Free Market Supply/Own Consumption 4

GENERATION São Manoel HPP 5

2017 PLD* e GSF Scenario Average PLD 1 - Southeast R$ 436.2 R$ 116.0 R$ 162.8 R$ 155.4 R$ 302.6 + 276% Growth vs 3Q16 3Q16 4Q16 1Q17 2Q17 3Q17 GSF PLD Southeast 110% 83% 88% 84% - 21 p.p. Decrease 62% vs 3Q16 3Q16 4Q16 1Q17 2Q17 3Q17 GSF 1) Price of Settlement of Differences Spot Price 6

Risk Management of the Generation Portfolio Initial Hedge Acquisition of 70 avg. MW Decont. on MCSD¹ + Reduction of Bilateral Contracts % hedge 9% 16% +92% 166 18% 184 18 Optimized long position for hydro and spot prices scenarios risk mitigation Hedged Energy 96 70 70 Average MW 96 96 1Q17 2Q17 3Q17 MCSD + Reduction of Bilateral contracts Additional Hedge Initial Hedge ² 1) Leveraging and Deficit Compensation Mechanism MSCD 2) Considering the proportion in Santo Antonio do Jari (50%) and Cachoeira Caldeirão (50%) HPPs. 7

Result of Energy Management in Gross Margin (3Q17) Hydro and Commercialization (R$ Million) 3Q17 Positive Impact of R$ 278 Million 93 44-59 71 70-337 GSF/PLD Impact Reimbursement Referring to GSF Renegotiation Additional Hedge Margin Revenue - Uncontracted Energy Settlement Commerc. Gross Margin Net impact of GSF 8

Pecém I TPP Uptime (%) GU01 Scheduled Maintenance GU02 Scheduled Maintenance Accumulated Uptime Above to the Auction Parameter 64% 76% 88% 89% 94% 94% 98% 81% 94% 99% 81% 89% 90% 91% 91% 91% 2013 2014 2015 2016 1Q17 2Q17 3Q17 9M17 GU01 GU02 Average TPP ADOMP Hedge 2017 54 MWm PLD - CVU Savings of R$ 29.3 Million in 3Q17 9

DISTRIBUTION 10

Quality Indicators EDP São Paulo DEC (hours) FEC (times) 8.71 8.61 8.61 8.47 8.41 8.41 8.41 7.15 7.15 6.59 6.59 6.59 8.31 8.13 8.22 5.28 5.42 5.29 5.23 3 Q 1 6 4 Q 1 6 1 Q 1 7 2 Q 1 7 3 Q 1 7 5.06 3 Q 1 6 4 Q 1 6 1 Q 1 7 2 Q 1 7 3 Q 1 7 EDP Aneel EDP Aneel EDP Espírito Santo DEC (hours) FEC (times) 9.93 9.93 9.81 9.81 9.81 7.65 7.65 7.65 7.65 7.65 8.84 8.80 8.64 8.83 8.78 5.37 5.40 5.31 5.24 5.17 3 Q 1 6 4 Q 1 6 1 Q 1 7 2 Q 1 7 3 Q 1 7 3 Q 1 6 4 Q 1 6 1 Q 1 7 2 Q 1 7 3 Q 1 7 EDP Aneel EDP Aneel 11

Reduction of the gap between Real and Regulatory Losses Total Losses EDP Espírito Santo (%) 14,00% 13,68% 13,88% 13,50% 13,50% 13,11% 14,21% 13,09% 13,71% 13,62% 13,58% 13,18% 11,77% 11,75% 11,75% 9,99% Var. 3Q17 vs 3Q16-1.12 p.p. Gain of + R$ 24.0 Million per year 9,63% 9,63% Aneel Target EDP ES Aneel's Target Total Losses EDP São Paulo (%) 9,48% 9,35% 8,96% 8,95% 8,40% 8,40% 9,35% 9,16% 8,97% 8,77% 8,89% 8,75% 8,73% 8,73% 7,86% 7,86% 7,88% 7,88% Var. 3Q17 vs 3Q16-0.04 p.p. Gain of + R$ 1.2 Million per year EDP SP Aneel's Target 12

EBITDA vs Regulatory EBITDA 9M17 Consolidated Distribution (R$ Million) 4% 37 23 586 564 46-28 4-60 Regulatory¹ EBITDA Losses Market Variation Over Cont. (105%) OPEX PDD Others EBITDA Reduction of the Losses gap 2 Reduction of R$ 3 Million versus 6M17 PDD of 0.6% in 3Q and 1% in 9M 1) Regulatory EBITDA = Remuneration of Capital + Reintegration Quota (QRR) Informations from 9M17, consolidated EDP São Paulo and EDP Espírito Santo 2) Total of Losses in 1H17 = R$ 48 million 13

Change in Investment Profile 1.7x Capex Breakdown (R$ Million) Capex/QRR 1 +58% 305 54% 320 44% 481 45% 24% 413 52% Increase in Recurring Investments above Depreciation 23% 13% 24% 13% 19% 16% 15% 24% 13% 10% 11% 2014 2015 2016 9M17 Network Expansion Network Improvement Losses Reduction Strategies Others 1) Consolidated Reintegration Quota (EDP São Paulo and EDP Espírito Santo) 14

TRANSMISSION 15

Early Delivery of the Environmental Licensing Schedule Lot 24* Schedule of the Concession Contract 2016 2017 2018 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Step 1 Step 3 Step 1 Area Study and Basic Engineering Project Early Delivery 6 Months Area Study and Basic Engineering Project DPU - Declaration of Public Utility Step 3 DPU - Declaration of Public Utility Step 2 Early Delivery 13 Months Step 2 Submission of EIA/RIMA¹ and Preliminary License Request *Lot 24 Auction n13/2015 Submission of EIA/RIMA¹ and Preliminary License Request Early Delivery 8 Months 16

FINANCIAL PERFORMANCE Cachoeira Caldeirão HPP 17

3Q17 vs 3Q16 Financial Highlights 43.5 Million Gross Margin of R$ 176.5 Million Growth of 264.0% compared to 3Q16 Growth of 74.2% compared to 3Q16 PMTO Evolution Below Inflation +0.2% compared to 9M16 Adjusted EBITDA 1 of R$ 535.1 Million Increase of 14.3% compared to 3Q16 Adjusted Net Income of R$ 129.2 Million Increase of 2.4% compared to 3Q16 Controlled Leverage 1.9x (Net Debt/EBITDA) in September, 2017 1) Excluding non-recurring effects: Non-indemnified Financial Asset (VNR), Provision for the Reimbursement of the Water Charge, Sale of Pantanal Energética, Insurance Recoveries at Pecém 18

Hydro Generation Pecém Distribution Commercialization+ GRID Elimination Gross Margin 3Q17 Gross Margin Breakdown (R$ Million) 935 158 1-33 75-151 38 0 864 777 9% 849 16 2 Margin 3Q16 Margin 3Q17 1) R$ 158 million refers to Non-indemnified Financial Asset (VNR) 2) R$ 7.4 million refers to Non-indemnified Financial Asset (VNR) 19

Results Adjusted EBITDA 1 (R$ Million) PMTO (R$ Million) + 14.3% 535 468 Growth 43 5 65 131 191 192 + 0.2% Growth 293 294 16 13 34 29 20 13 107 114 227 195 117 124 3Q16 Hydro Generation Thermal Generation Others/Eliminations 3Q17 Distribution Commerc. + GRID 3Q16 3Q17 Third Party Services Personnel Provisions Others Material Adjusted Net Income (R$ Million) 126 + 2.4% Growth 129 231 140 Note 1: Excluding non-recurring effects: Nonindemnified Financial Asset (VNR), Provision for the Reimbursement of the Water Charge, Sale of Pantanal Energética, Insurance Recoveries at Pecém -105-6 3Q16 3Q17 Non-indemnified Financial Asset (VNR) (-) TPP Pecém Insurance Reimbursement Income 20

Debt Net Debt/EBITDA (R$ Million) 1.5 1.8 1.7 1.9 Net Debt/EBITDA (X) 1.3 3,397 3,553 3,582 3,563 3,908 Covenant: Up to 3.5x Net Debt Sep/16 Dec/16 Mar/17 Jun/17 Sep/17 Debt Maturity Schedule (R$ Million) Gross Debt per Indexer 1,454 1,015 1,436 1,512 IPCA; 13.0% Fixed Rate; 4.7% US$; 4.3% 699 700 TJLP; 22.8% CDI; 55.1% Availabilities 2017 2018 2019 2020 After 2021 21

2018 Preparation Generation Anticipation of São Manoel Operation Active management of energy risk Cost with coal logistics reduction Distribution Narrowing the gap for regulatory losses Strengthening the Regulatory Remuneration Base Transmission Beginning of Lot 24 construction works (Auction nº 013/2015) Obtaining the Installation License for Lots 7,11,18 and 21 (Auction # 05/2016) Commercialization and Services Consistent presentation of Commercialization results Expand market participation in Distributed Solar Energy and Efficiency Services Finance Cost Control through the continuity of ZBB* Continuity of the digitalization agenda Optimization of the Company's Capital Structure Fundraising for Transmission (Lots 7,11,18 and 21) *ZBB = Zero Base Budget 22

Investor Relations E-mail: ri@edpbr.com.br Phone: +55 (11) 2185-5907 www.edp.com.br/ri