Network Analysis Basic Components. The Other View. Some Applications. Continued. Goal of Network Analysis. RK Jana

Similar documents
CHAPTER 9: PROJECT MANAGEMENT

UNIT-II Project Organization and Scheduling Project Element

Project Planning. Identifying the Work to Be Done. Gantt Chart. A Gantt Chart. Given: Activity Sequencing Network Diagrams

A convenient analytical and visual technique of PERT and CPM prove extremely valuable in assisting the managers in managing the projects.

IE 102 Spring Project Management

Project Management Techniques (PMT)

1 of 14 4/27/2009 7:45 AM

EXERCISE Draw the network diagram. a. Activity Name A B C D E F G H

Lecture 3 Project Scheduling

Teori Pengambilan Keputusan. Week 12 Project Management

Project Management. Chapter 2. Copyright 2013 Pearson Education, Inc. publishing as Prentice Hall

6/7/2018. Overview PERT / CPM PERT/CPM. Project Scheduling PERT/CPM PERT/CPM

Textbook: pp Chapter 11: Project Management

Project Management Chapter 13

Lecture 5: Project Management

Outline. Global Company Profile: Bechtel Group. The Importance of Project Management Project Planning Project Scheduling Project Controlling

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

Introduction. Introduction. Six Steps of PERT/CPM. Six Steps of PERT/CPM LEARNING OBJECTIVES

PROJECT MANAGEMENT COURSE 5: PROJECT TIME MANAGEMENT. G.N. Sandhy Widyasthana

After complete studying this chapter, You should be able to

PROJECT MANAGEMENT CPM & PERT TECHNIQUES

Project Planning. Jesper Larsen. Department of Management Engineering Technical University of Denmark

06IP/IM74 OPERATIONS RESEARCH

CHAPTER 6 CRASHING STOCHASTIC PERT NETWORKS WITH RESOURCE CONSTRAINED PROJECT SCHEDULING PROBLEM

CISC 322 Software Architecture

Optimization Prof. A. Goswami Department of Mathematics Indian Institute of Technology, Kharagpur. Lecture - 18 PERT

A METHOD FOR STOCHASTIC ESTIMATION OF COST AND COMPLETION TIME OF A MINING PROJECT

CHAPTER 5 STOCHASTIC SCHEDULING

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Appendix A Decision Support Analysis

SSC-JE STAFF SELECTION COMMISSION CIVIL ENGINEERING STUDY MATERIAL ESTIMATING, COSTING AND VALUATION

WHY ARE PROJECTS ALWAYS LATE?

Project Management Fundamentals

11/1/2018. Overview PERT / CPM. Network representation. Network representation. Project Scheduling. What is a path?

Handout 4: Deterministic Systems and the Shortest Path Problem

Programme Evaluation and Review Techniques (PERT) And Critical Path Method (CPM) By K.K. Bandyopadhyay. August 2001

Construction Management

Project Management -- Developing the Project Plan

A STUDY OF THE BASIC CONCEPT OF CRASHING CPM NETWORK USING DERIVATIVE MARGINAL COST IN LINEAR PROGRAMMING

Program Evaluation and Review Techniques (PERT) Critical Path Method (CPM):

GPE engineering project management. Project Management in an Engineering Context

INSE 6230: Assignment 1 - Winter (0% of final grade) 1. The table below provides information about a short IT project.

CHAPTER 5. Project Scheduling Models

Probabilistic Completion Time in Project Scheduling Min Khee Chin 1, Sie Long Kek 2, Sy Yi Sim 3, Ta Wee Seow 4

PROJECT MANAGEMENT. Trying to manage a project without project management is like trying to play a football game without a game plan


Formulas to Know for EXAM

A UNIT BASED CRASHING PERT NETWORK FOR OPTIMIZATION OF SOFTWARE PROJECT COST PRITI SINGH, FLORENTIN SMARANDACHE, DIPTI CHAUHAN, AMIT BHAGHEL

Impacting the Bottom Line. Cost Reduction: Planning & Control. Bottom Line (costs) A = Costs (what we expend) B = Revenue, sales (what we generate)

Chapter 11: PERT for Project Planning and Scheduling

Plan Implementation. Pushpa Lal Shakya

Cost Reduction: Planning & Control. Impacting the Bottom Line

MS Project 2007 Page 1 of 18

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

Project Management. Project Mangement. ( Notes ) For Private Circulation Only. Prof. : A.A. Attarwala.

INSE 6230 Total Quality Project Management Winter 2018 Quiz I. Max : 70 points. This is a closed book exam. Answer all the questions in the booklet.

Management Management

SWEN 256 Software Process & Project Management

Real-World Project Management. Chapter 15

Project planning and creating a WBS

UNIVERSITY OF BOLTON SCHOOL OF ENGINEERING. MSc CIVIL ENGINEERING MSc CONSTRUCTION PROJECT MANAGEMENT SEMESTER ONE EXAMINATION 2017/2018

ETSF01: Software Engineering Process Economy and Quality

Risk Video #1. Video 1 Recap

UNIT 5 PROJECT ANALYSIS PERT/CPM MODULE - 2

Programme Evaluation and Review Technique

Homework solutions, Chapter 8

CONSTRUCTION MANAGEMENT CHAPTER 3 PLANNING

POLYTECHNIC OF NAMIBIA

Chapter 2 The PERT/CPM Technique

MnDOT use of Calendars in Primavera P6


IP-CIS : CIS Project Management

Project Management. Managing Risk. Clifford F. Gray Eric W. Larson Third Edition. Chapter 7

Line Balancing S K Mondal Chapter 3

Project Management. Chapter 2 DISCUSSION QUESTIONS

NETWORK ANALYSIS QUESTION BANK

56:171 Operations Research Midterm Examination Solutions PART ONE

PROJECT MANAGEMENT: PERT AMAT 167

Decision Support Tool for Project Time-Cost Trade-off

Logistics. Lecture notes. Maria Grazia Scutellà. Dipartimento di Informatica Università di Pisa. September 2015

Haeryip Sihombing 1. Risk. Risk Management

Project Management with Brief Information regarding CPM and PERT Methods

56:171 Operations Research Midterm Examination Solutions PART ONE

MODULE: INTRODUCTION TO PROJECT MANAGEMENT / PROJECT MANAGEMENT

56:171 Operations Research Midterm Exam Solutions October 22, 1993

Allocate and Level Project Resources

NPV Method. Payback Period

ECSE 321: INTRODUCTION TO SOFTWARE ENGINEERING

Project Time-Cost Trade-Off

Optimization of Rescheduling and Economy. Analysis of the Implementation of Kwitang Office. Park Building Construction Project in Jakarta

A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling. By Gunnar Lucko 1

Roll No. :... Invigilator s Signature :.. CS/B.TECH(IT)/SEM-5/M(CS)-511/ OPERATIONS RESEARCH AND OPTIMIZATION TECHNIQUES

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.

IEOR E4004: Introduction to OR: Deterministic Models

MnDOT Project Management Office Presents: Project Reporting. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

A Linear Programming Approach for Optimum Project Scheduling Taking Into Account Overhead Expenses and Tardiness Penalty Function

CHAPTER 5 SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT. UWB10202 Effective Communication by Norazmi Danuri

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

Outline. Project Management. Introduction. What is a Project?

Advanced Operations Research Prof. G. Srinivasan Dept of Management Studies Indian Institute of Technology, Madras

Transcription:

Network nalysis RK Jana asic omponents ollections of interconnected linear forms: Lines Intersections Regions (created by the partitioning of space by the lines) Planar (streets, all on same level, vertices at every intersection of edges) Non-planar (airline routes, highways with bridges/flyovers, electronic circuits) 2 Some pplications Shortest path between vertices Shortest route visiting all locations once and returning to start point (Travelling Salesman Problem) Minimum cost of constructing a network Identification of zones within specified travel time/cost The Other View Network: It is the graphical representation of a project and is composed of activities that must be completed to reach the end objective of a project, showing the planning sequence of their activities, their dependence and inter-relationships. Event: n event is a specific physical or intellectual accomplishment in a project plan. ctivity: n activity is a task that consumes resources (time, money etc). It lies between two events. 3 4 ontinued Dummy ctivity: Without using any resources, some activities are used to represent a connection between events. This type of activity is known as a dummy activity. D E F Goal of Network nalysis Solving problems involving networks Objectives Maximize efficiency Minimizing time Minimizing expenditure Dummy Purpose of a dummy activity To maintain the proper logic in a network To maintain uniqueness in the numbering system 5 1

Rules of Network onstruction 1. No event can occur until every activity preceding it has been completed. 2. n activity succeeding an event cannot start until that event has occurred. 3. n event cannot occur more than once. 4. Each activity must start and terminate in an event. 5. Time flows from left to right.. n activity must be completed in order to reach the end event. 7. Dummy activities should be used if absolutely necessary. 7 Situations in Network Diagram Dummy D D must finish before either or can start both and must finish before can start both and must finish before either of or D can start must finish before can start both and must finish before D can start 8 Network onstruction (Ex 1) Earliest Start & Finish Times Draw a network diagram for the following set of activities: <, ; < D, E; < E; E < F; D, F < G; G < H The notation X < Y implies that the activity X must be finished before Y begins. Earliest Start Time Earliest time an activity can start For an activity (i, j) it is denoted by ES i Earliest Finish Time Earliest time an activity can finish For an activity (i, j) it is denoted by ES j For the activity (i, j), ES j = ES i + t ij If more than one activity end at the node (j) then ES j = max{es i + t ij }, for all i For the initial activity ES 1 = 0 9 10 Latest Start & Finish Times Starting from the last node, we proceed backward to calculate the latest times. Latest Start Time Latest time at which an activity can start For an activity (i, j) it is denoted by LS i Latest Finish Time Latest time by which an activity can be completed For an activity (i, j) it is denoted by LS j For the activity (i, j), LS i = LS j t ij If more than one activity start from the node (i) then LS i = min{ls j -t ij }, for all j For the last node ES n = LS n Total, Free, and Independent Float Total Float : Total float of an activity (i, j) is the difference between the maximum time available to finish the activity and the time required to complete it. It is calculated as: Total Float = LS j ES i t ij Free Float : Free float is the time by which an activity can be delayed beyond its earliest finish without affecting the earliest start time of a succeeding activity. Therefore, Free Float = Total Float (LS j ES j ) Independent Float : The time by which an activity can be rescheduled without affecting the preceding or the succeeding activities is known as independent float. Independent Float = Total Float (LS i ES i ) 11 12 2

ritical Path Procedure to Find ritical Path ritical ctivity: n activity is said to be critical if a delay in its start will cause a further delay in the completion of the entire project. lternate Definition: n activity is said to be critical if its total float is zero. ritical Path: The path formed by all the critical activities is called the critical path. For the activity (i, j) to lie on the critical path, the following conditions must satisfy: 1. ES i = LS i 2. ES j = LS j 3. ES j - ES i = LS j LS i = t ij 13 14 Example 1 Solution (Ex 1) 15 1 Earliest Start Time alculation (Ex 1) Latest Start Time alculation (Ex 1) 17 18 3

Float & ritical Path alculation (Ex 1) ritical activities: (1, 2), (2, 3), (3, ), (, 7) Example 2 ritical Path: 1-2-3--7 Project ompletion time: 23+1+18+10 = 7 days 19 20 Solution (Ex 2) Earliest Start Times (Ex 2) 21 22 Float & ritical Path alculation (Ex 2) ritical Path: 1-2-3--7 Project Evaluation and Review Technique (PERT) Project ompletion time = 44 units 23 24 4

Project Planning Resource vailability and/or Limits Due date, late penalties, early completion incentives udget ctivity Information Identify all required activities Estimate the resources required (time) to complete each activity Immediate predecessor(s) to each activity needed to create interrelationships 25 PERT PERT is based on the assumption that an activity s duration follows a probability distribution instead of being a single value Three time estimates are required to compute the parameters of an activity s duration distribution: pessimistic time (t p ) - the time the activity would take if things did not go well most likely time (t m ) - the consensus best estimate of the activity s duration (assumed to follow eta distribution) optimistic time (t o ) - the time the activity would take if things did go well Mean (expected time): Variance: V t =σ 2 = t e = t p + 4 t m + t o t p - t o 2 2 PERT nalysis Draw the network. nalyze the paths through the network and find the critical path. The length of the critical path is the mean of the project duration probability distribution which is assumed to be normal. The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum. Probability computations can now be made using the normal distribution table. Probability omputation Determine probability that project is completed within specified time x - µ Z = σ where µ = t p = project mean time σ = project standard mean time x = (proposed ) specified time 27 28 Normal Distribution of Project Time Zσ Probability µ = t p x Time 29 PERT lgorithm Step 1: List all activities and the draw a network diagram. Step 2: Denote the most likely time by t m, optimistic time by t 0, pessimistic time by t p, and compute the expected time as: t e = (t m + t 0 + t p )/ Step 3: Tabulate expected activity times, ES time, LF time for each event. Step 4: Determine the total float (ES - LF) for each activity. Step 5: Identify the critical path & calculate the project duration. Step : ompute variance of each activity using t p, and t 0. Step 7: alculate the standard normal variate : z 0 = (Due date Expected completion date)/project s.d. Step 8: Use standard normal table to compute the probability of completing the project within the scheduled time. 30 5

Example Solution (EX ) Find the critical path of the project given by the following network diagram: 31 32 Example 7 Solution (EX 7) 33 34 Solution (EX 7) enefits of PM/PERT Useful at many stages of project management Mathematically simple Give critical path and slack time Provide project documentation Useful in monitoring costs 35 3

ontinued PM/PERT can answer the following important questions: How long will the entire project take to be completed? What are the risks involved? Which are the critical activities or tasks in the project which could delay the entire project if they were not completed on time? Is the project on schedule, behind schedule or ahead of schedule? If the project has to be finished earlier than planned, what is the best way to do this at the least cost? Limitations of PM/PERT learly defined, independent and stable activities Specified precedence relationships Over emphasis on critical paths Deterministic PM model ctivity time estimates are subjective and depend on judgment PERT assumes a beta distribution for these time estimates, but the actual distribution may be different PERT consistently underestimates the expected project completion time due to alternate paths becoming critical 37 38 omputer Software for Project Management Microsoft Project (Microsoft orp.) MacProject (laris orp.) PowerProject (ST Development Inc.) Primavera Project Planner (Primavera) Project Scheduler (Scitor orp.) Project Workbench (T orp.) 39 7