19th & Barker Roundabout / Waterline Improvement Project No. 56-CP12-901(C) Cost Breakdown

Similar documents
Rock Chalk Park - Infrastructure Report. July 2013

BID TABULATION BID REQUEST NO

ITEM DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT UNIT PRICE AMOUNT

JANUARY 18, Reference Specifications, Attachment to Form 96 (BID FORM), Bid Proposal: Respectfully submitted,

BID TABULATION REPORT ABRAM STREET (SH CITY LIMITS) PROJECT No. PWST09016 BID OPENED : April 22, 2014 at 1:30 p.m.

Bid No.: PO Box Cone Rd Asphalt Ave th Ave. E. Dunedin, FL Tampa, FL Tampa, FL Palmetto, FL 34221

BIDDER'S PROPOSAL TO THE HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL

BID TAB PROJECT: REPLACEMENT OF ALBON ROAD BRIDGE NO. 606, PID NO BID OPEN: MAY 9, 2012 COMPLETION DATE: NOVEMBER 16, 2012

69889/AV/lm. Recipients of C-TRAN ITB # Fourth Plain BRT Maintenance Facility Expansion. DATE: June 25, SUBJECT: Addendum #11

CITY OF CHINO ENGINEERING COST ESTIMATE. Quantity Unit Item Unit Total Cost Price Per Item. LS Traffic Control (5% of construction cost) 5% $

2011 PUBLIC PARKING LOT & ALLEY IMPROVEMENTS Village of Whitefish Bay Project No March 17, 2011 ITEM DESCRIPTION UNIT QTY.

Certified Bid Tabulation Southeast Residential Community Parking Development South Dakota State University

FALCON FIELD RELOCATE PARALLEL TAXIWAY 'E' (B II SM.) ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST

DORAN STREET AND BROADWAY/BRAZIL SAFETY AND ACCESS PROJECT PROJECT STUDY REPORT (EQUIVALENT) Appendix I Cost Estimates

2015 Financial Assurance 8/6/2015 Estimate Form (with pre-plat construction)

LETTING : CALL : 056 COUNTIES : MILLE LACS

33 Ditch Bottom Inlet (DBI) -Type E $ 2, EA - 0 $ - 35 Ditch Bottom Inlet (DBI) -Type H (Modified) $ 5, EA $ 5,600.

ENGINEER'S ESTIMATE OF PROBABLE COST CCTA I 680 NORTH EXPRESS LANE PROJECT (SOUTHBOUND ONLY) EA 04 4H % PS&E Submittal

2012 WATER & SEWER CONSTRUCTION CONTRACT, PACKAGE IV SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B DD BID PROPOSAL

BID TABULATION. Engineer's Estmated Opinion of Costs

EST. UNIT UNIT PRICE TOTALS UNIT PRICE TOTALS UNIT PRICE TOTALS UNIT PRICE TOTALS

Crushed Surfacing Base Course, per ton. Pages 8-8, Special Provisions Section , Materials. This Section is supplemented with the following:

RANCHERO ROAD AND BNSF GRADE SEPARATION PROJECT, C.O. NO Item Description Est. Qty. Units Unit Price

Annual Services Construction Contract (ASCC) #15 Project Number: PUCN

REPLACEMENT OF MERCER COUNTY BRIDGE

CITY OF TAMPA ADDENDUM 2. April 18, 2018

PART II - Prospect Street 37. 8" Ductile Iron CL52 Water Main 614 lin. ft. $ $ 49, $ $ 43, $ $ 46,050.

BID TABULATION PAGE 1 OF 8

ADDENDUM NO. 1 PUBLIC WORKS CONSTRUCTION PROJECT NO

ADDENDUM No. 1 January 29, Paving Program Village of Milford

Engineer's Preliminary Estimate - 100% Submittal

Addendum 1 Downtown North CRA Sidewalks

TOTAL QUANTITY UNIT COST UNIT

Addendum 1 13 TH Street Streetscape. September 1, 2017

Subject: Addendum No. 1 Project #C CCE Parking Lot Replacement Phase 2 Robert Bishop Drive 4380 Richmond Road, Highland Hills, Ohio 44122

Department of Public Works Engineering

Sunset Street West Sidewalk Projects Opinion of Anticipated Construction Costs March 12, 2012 Project Summary. Project List

CITY ENGINEER'S ESTIMATE ITEM DESCRIPTION UNIT QTY. UNIT PRICE ITEM TOTAL UNIT PRICE ITEM TOTAL UNIT PRICE ITEM TOTAL REMOVALS

2012 WATER & SEWER ALLEY CONSTRUCTION CONTRACT, PACKAGE I SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B DD

SUBDIVISION IMPROVEMENTS AGREEMENT

Reviax Constracting Corp. DeSantis Construction

OKLAHOMA TURNPIKE AUTHORITY

ADDENDUM #1 March 12, 2019 BID FORM. Moore, Oklahoma DATE: PROJECT:

Failure to acknowledge all addenda in the BID may cause rejection of the BID. See Instructions to Bidders.

AVERAGE OF BID ITEMS ENGINEERS ESTIMATE

RFB Addendum 3

OKLAHOMA TURNPIKE AUTHORITY

BID PROPOSAL ANNUAL PATHWAY & MINOR CONSTRUCTION CONTRACT PBC PROJECT #

BID TABULATION PAGE 1 OF 6


Munilla Construction HOOD RD., E. OF FLORIDA'S TURNPIKE TO W. OF CENTRAL BLVD. AND HOOD RD. & CENTRAL

North Baker Ave - City Limits to 23rd St NE CRP 949 PROPOSAL

NE WEST KINGSTON ROAD CULVERT REPLACEMENT

PART A ROADWAY - BASE BID

Sandalfoot Blvd. & SR 7 and SW 3rd St. & SR 7 Bridge Replacements WEEKLEY ASPHALT PAVING, INC. KIEWIT INFRASTRUCTURE CO. RUSSELL ENGINEERING

LETTER OF INTENT FOR: HERITAGE HILLS COMMUNITY

SUTTER BUTTER FLOOD CONTROL AGENCY FEATHER RIVER WEST LEVEE PROJECT PROJECT C, CONTRACT NO C BID TABULATION

CITY OF ELKO BID TABULATION * RE-BID* FOR Sports Complex April 4, 2018

CONTRACT TIME DETERMINATION

ALVAREZ ENGINEERS, INC. July 27, 2017 a) Evaluation Criteria PROJECT: ROADWAY IMPROVEMENTS TO DOLPHIN MALL OUTER RING ROAD for BEACON TRADEPORT COMMUN

CITY OF YUBA CITY STATE OF CALIFORNIA PUBLIC WORKS DEPARTMENT NOTICE TO CONTRACTORS

OKLAHOMA TURNPIKE AUTHORITY

1 DEPARTMENT MAKING REQUEST 2 MEETING DATE 4 AGENDA 5 IS THIS ITEM BUDGETED ( IF APPLICABLE ) -

Utility Committee Meeting AGENDA. October 3, 2017

Tabulation of Bids. Counties: ROUTE 94 BLACK CREEK TRIBUTARY CULVERT REPLACEMENT

Northumberland County County Road 2 Class Environmental Assessment Construction Cost Estimate

A DESIGN-BUILD PROJECT

Town of Middleton Salt Storage Building Pioneer Road Pioneer Lands Town of Middleton Dane County, WI 53562

BID PROPOSAL. PROPOSAL OF, a corporation, a partnership consisting of. an individual doing business as

BID PROPOSAL Mobilization for Non-Emergency Work Orders; 200 EA $ $ Mobilization for Emergency Work Orders; 2 EA $ $

Fuel Adjustment Allowance USD 50,000 $ 1.00 $ 50, $ 1.00 $ 50, $ 1.00 $ 50, $ 1.00 $ 50, $ 1.00 $

Patchogue Road Culvert Crossing IFB ADDENDUM #1 07/13/2015. Addendum #1 addresses the questions submitted by contractors.

NAME OF CONTRACTOR CONTRACTORS ADDRESS Buffalo Road th ave Ct SW Walcott, IA North Liberty, IA

ADDITIONS, MODIFICATIONS, AND/OR DELETIONS TO THE PROPOSAL

SECTION BID. Valley Court Force Main Replacement Contract No. BE17-029

2001 Average Bid Tabs

For Reference Only - Not for the Purpose of Bidding BP-1. Azucena Street 30-Inch Sewer Project Job No Solicitation No.

NOTICE TO BIDDERS LETTING OF NOVEMBER 9, 2018 ADDENDUM NO. 1 CHANGES TO PROPOSAL OR PLANS

CECIL COUNTY, MARYLAND. ADDENDUM #3 Bid 18-14: Bohemia Church Road Culvert Replacements XCE1073, XCE1074 & XCE1075

NOTICE OF AWARD OF CONTRACT S.R. 408/S.R.417 INTERCHANGE IMPROVEMENTS PHASE 1. Project No. 253F Contract No

REQUEST FOR PROPOSALS ADA SIDEWALK RAMP REPLACEMENT 2019 Construction Season. SUBMITTAL DUE DATE: 2:00 p.m. on Tuesday, March 19, 2019

AWARD CONSTRUCTION CONTRACT FOR NAVE DRIVE MULTI USE PATH (MUP) AND ADOPT A RESOLUTION AMENDING CIP BUDGET

The bid due date has been changed to 2:50 p.m. May 25, 2018.

8 EA $ 1, $ $ 1, $ 8, $ 1, $ 8, EA $ 6, $6, $ 7, $ 7, $ 5, $ 5,445.

ITEM ESTIMATED UNIT NO. DESCRIPTION QUANTITIES UNIT PRICE AMOUNT 1a COLD MILLING CLASS 3 (Approx.2") 7,386 S.Y. $ $ 1b COLD MILLING CLASS 3 (Approx 3-

BID FORM. PROJECT: 2017 Water line replacement

August 22, Mr. David Lobue Airport Director Hammond Northshore Regional Airport 600 Judge Leon Ford Drive Hammond, LA

CITY OF DEERFIELD BEACH Request for City Commission Agenda

ITB-PW-U Matanzas Woods Parkway Reclaimed Water Main Construction Phase 2

Job No Wastewater Collection System Small Main Rehabilitation at Focus Areas Pipebursting Method BID PROPOSAL. Dollars Cents $ $ Dollars

TABULATION OF BIDS 1 L.S. $ 5, $ 5, $ 27, $ 27,000.00

AVGPR14.Y01 2/11/2014 DOES NOT INCLUDE STATE AID PROJECTS ALL ITEMS BETWEEN 12/01/13 AND 12/31/13 BY ITEM GROUP

PROJECT COST. Prepared for City of Burlington, Iowa Downtown/Riverfront Revitalization Project

FLOOD DIVERSION AUTHORITY FINANCE COMMITTEE AGENDA FOR THURSDAY, MAY 11, Fargo City Commission Chambers 3:00 PM

Opinion of Probable Cost

CITY OF SAN MARCOS ENGINEERING DIVISION

BID TABULATION JAMES STREET TRUNK SEWER IMPROVEMENTS CORALVILLE, IOWA

2018 Road Improvements Engineer's Project Number: LK 01 Bid Deadline: May 1, 2018 at 2:00 p.m. local time

GENERAL AVIATION TERMINAL BUILDING

REPLACEMENT RESERVE REPORT FY 2010 WOODWIND ASSOCIATION. N & H Enterprises MILLER ~ DODSON ASSOCIATES. Community Management by:

Transcription:

19th & Barker Roundabout / Waterline Improvement Project No. 56CP12901(C) Cost Breakdown Engineering Fees: Original Contract $ 71,861.00 Additional Services $ 8,744.00 Waterline Contract $ 17,500.00 TOTAL $ 98,105.00 RightofWay / Easement Acquisitions $ 36,331.00 Original Construction Contract: Section 119th & Barker Roundabout $ 266,845.65 Section 217th & New Hampshire Roundabout $ 26,469.45 Section 3 Waterline Improvements $ 184,378.00 TOTAL $ 477,693.10 Change Order No. 1 (voided) $ Change Order No. 2: Section 119th & Barker Roundabout $ 21,640.00 Change Order No. 3 (proposed): Section 119th & Barker Roundabout $ 6,636.20 Section 1RightofWay Agreements $ 15,535.00 Section 3Waterline Improvements $ 10,390.00 TOTAL $ 32,561.20 Bid Item Quantity Overruns: Section 119th & Barker Roundabout $ 13,671.98 Section 217th & New Hampshire Roundabout $ 666.55 Section 3Waterline Improvements $ 11,966.40 TOTAL $ 26,304.93 Total Project Cost $ 692,635.23 Total Roundabout Cost (Sections 1 & 2) $ 468,400.83 Total Waterline Cost (Section 3) $ 224,234.40

Project No. 56CP12901(C) 19th & BARKER ROUNDABOUT SECTION 1 1 Mobilization L.S. 1 $ 10,900.00 $ 10,900.00 1 $ 10,900.00 $ 2 Demolition and Site Preparation L.S. 1 $ 14,500.00 $ 14,500.00 1 $ 14,500.00 $ 3 Clearing and Grubbing L.S. 1 $ 2,000.00 $ 2,000.00 1 $ 2,000.00 $ 4 Unclassified Excavation C.Y. 1,008 $ 20.00 $ 20,160.00 1008 $ 20,160.00 $ 5 Embankment C.Y. 167 $ 10.00 $ 1,670.00 167 $ 1,670.00 $ L.F. 6 Island Curb 272.2 $ 8.00 $ 2,177.60 272.2 $ 2,177.60 $ 7 Doweled Curb L.F. 621.1 $ 8.00 $ 4,968.80 382 $ 3,056.00 $ (1,912.80) 8 Curb and Gutter L.F. 921.1 $ 13.00 $ 11,974.30 1517 $ 19,721.00 $ 7,746.70 9 Exposed Aggregate Concrete Pavement 6" S.Y. 305.6 $ 52.00 $ 15,891.20 267.3 $ 13,899.60 $ (1,991.60) 10 Concrete Pavement 9" (Plain) S.Y. 1,761.7 $ 43.70 $ 76,986.29 1790.7 $ 78,253.59 $ 1,267.30 11 Exposed Aggregate Concrete Pavement 9" S.Y. 69.7 $ 58.00 $ 4,042.60 69.7 $ 4,042.60 $ 12 6" High Early Concrete S.Y. 123.9 $ 39.60 $ 4,906.44 351.6 $ 13,923.36 $ 9,016.92 13 9" Fly Ash Subgrade S.Y. 1,921.9 $ 4.00 $ 7,687.60 1921.9 $ 7,687.60 $ 14 2" Milling S.Y. 144.3 $ 20.00 $ 2,886.00 184.3 $ 3,686.00 $ 800.00 15 Brick Pavers S.Y. 15.9 $ 240.00 $ 3,816.00 14.8 $ 3,552.00 $ (264.00) 16 Curb Inlet 5' x 4' Each 2 $ 2,200.00 $ 4,400.00 2 $ 4,400.00 $ 17 Junction Box 7' x 4' Each 1 $ 2,400.00 $ 2,400.00 1 $ 2,400.00 $ 18 Manhole Adjustment Each 1 $ 450.00 $ 450.00 2 $ 900.00 $ 450.00 19 Storm Sewer RCP 15" L.F. 54.9 $ 40.00 $ 2,196.00 54.9 $ 2,196.00 $ 20 Block Retaining Wall S.F. 587 $ 20.00 $ 11,740.00 618.2 $ 12,364.00 $ 624.00 21 Concrete Steps C.Y. 1.5 $ 1,170.00 $ 1,755.00 7.2 $ 8,424.00 $ 6,669.00 22 Sidewalk 4" Thick S.Y. 341.4 $ 33.30 $ 11,368.62 407.6 $ 13,573.08 $ 2,204.46 23 Decorative Bollard Each 19 $ 650.00 $ 12,350.00 0 $ $ (12,350.00) 24 Chain Link Fence 48" L.F. 19.8 $ 30.00 $ 594.00 19.8 $ 594.00 $

Project No. 56CP12901(C) 25 4" Steel Conduit L.F. 189 $ 22.00 $ 4,158.00 239 $ 5,258.00 $ 1,100.00 26 Street Lighting L.S. 1 $ 0 $ $ 27 Pavement Marking L.S. 1 $ 8,300.00 $ 8,300.00 1 $ 8,300.00 $ 28 Signing L.S. 1 $ 6,000.00 $ 6,000.00 1 $ 6,000.00 $ 29 Traffic Control L.S. 1 $ 10,380.00 $ 10,380.00 1 $ 10,380.00 $ 30 Seeding L.S. 1 $ 1,500.00 $ 1,500.00 1 $ 1,500.00 $ 31 Sodding L.S. 1 $ 0 $ $ 32 Monument Box Each 1 $ 850.00 $ 850.00 1 $ 850.00 $ 33 Contractor Construction Staking L.S. 1 $ 3,000.00 $ 3,000.00 1 $ 3,000.00 $ 34 Flowable Mortar C.Y. 16.1 $ 52.00 $ 837.20 22.1 $ 1,149.20 $ 312.00 35 Island Modifications (C.O. #2) L.S. 1 $ 18,600.00 1 $ 18,600.00 $ 18,600.00 36 Concrete Barriers (C.O. #2) L.S. 1 $ 480.00 1 $ 480.00 $ 480.00 37 Additional Traffic Control (C.O. #2) L.S. 1 $ 2,020.00 1 $ 2,020.00 $ 2,020.00 38 Adjust Sanitary Manhole (C.O.#2) Each 1 $ 540.00 1 $ 540.00 $ 540.00 *39 Install 24" #4 Dowels (Proposed C.O.) Each 480 $ 2.00 480 $ 960.00 $ 960.00 *40 Joints Sealant (Proposed C.O.) L.S. 1 $ 2,981.00 1 $ 2,981.00 $ 2,981.00 *41 Retaining Wall Color (Proposed C.O.) L.S. 1 $ 450.00 1 $ 450.00 $ 450.00 *42 Barker Islands Pvmt. Mrkg. (Proposed C.O.) L.S. 1 $ 1,795.20 1 $ 1,795.20 $ 1,795.20 *43 Storm Sewer Modfications (Propsesed C.O.) L.S. 1 $ 450.00 1 $ 450.00 $ 450.00 *44 Laundry Mat Improvements (Proposed C.O.) L.S. 1 $ 12,815.00 1 $ 12,815.00 $ 12,815.00 *45 Sauny Scott Improvements (Proposed C.O.) L.S. 1 $ 2,720.00 1 $ 2,720.00 $ 2,720.00 TOTAL SECTION 1 $ 266,845.65 $ 324,328.83 $ 57,483.18

Project No. 56CP12901(C) 17th AND NEW HAMPSHIRE MINIROUNDABOUT SECTION 2 1 Mobilization L.S. 1 $ 500.00 $ 500.00 1 $ 500.00 $ 2 Demolition and Site Preparation L.S. 1 $ 5,500.00 $ 5,500.00 1 $ 5,500.00 $ 3 Clearing and Grubbing L.S. 1 $ 250.00 $ 250.00 1 $ 250.00 $ 4 Straight Curb L.F. 59.7 $ 26.00 $ 1,552.20 60 $ 1,560.00 $ 7.80 5 Curb and Gutter L.F. 145.5 $ 13.50 $ 1,964.25 152 $ 2,052.00 $ 87.75 6 Exposed Aggregate Concrete Pavement 5" S.Y. 43.6 $ 50.00 $ 2,180.00 44 $ 2,200.00 $ 20.00 7 Concrete Pavement 7" (Reinforced) S.Y. 86.6 $ 40.00 $ 3,464.00 103.8 $ 4,152.00 $ 688.00 8 2" Asphalt Pavement Surface S.Y. 86.7 $ 20.00 $ 1,734.00 103.8 $ 2,076.00 $ 342.00 9 2" Milling S.Y. 43.6 $ 20.00 $ 872.00 43.6 $ 872.00 $ 10 Brick Pavers S.Y. 10.7 $ 190.00 $ 2,033.00 5 $ 950.00 $ (1,083.00) 11 Modify Existing Curb Inlet to Junction Box Each 1 $ 1,000.00 $ 1,000.00 1 $ 1,000.00 $ 12 Sidewalk 4" Thick S.Y. 26 $ 40.00 $ 1,040.00 41.1 $ 1,644.00 $ 604.00 13 Signing L.S. 1 $ 1,870.00 $ 1,870.00 1 $ 1,870.00 $ 14 Traffic Control L.S. 1 Inlcude in Item 29, Section 1 $ 15 Seeding L.S. 1 $ 350.00 $ 350.00 1 $ 350.00 $ 16 Sodding L.S. 1 $ 0 $ $ 17 Contractor Construction Staking L.S. 1 $ 900.00 $ 900.00 1 $ 900.00 $ 18 Relocate Existing Fire Hydrant Assembly Each 1 $ 700.00 $ 700.00 1 $ 700.00 $ 19 Replace Existing Valve Box with Ametek Type Each 2 $ 280.00 $ 560.00 2 $ 560.00 $ TOTAL SECTION 2 $ 26,469.45 $ 27,136.00 $ 666.55 WATERLINE SECTION 3 1 8" D.I.P. Waterline L.F. 1,464.5 $ 56.00 $ 82,012.00 1464.5 $ 82,012.00 $ 2 8" 11 1/4 o Bend Each 4 $ 170.00 $ 680.00 4 $ 680.00 $ 3 8" Gate Valve Each 6 $ 570.00 $ 3,420.00 6 $ 3,420.00 $ 4 8" Cross Each 2 $ 250.00 $ 500.00 2 $ 500.00 $ 5 8" Cast Iron Plug Each 1 $ 240.00 $ 240.00 1 $ 240.00 $

Project No. 56CP12901(C) 6 Water Meter Each 31 $ 500.00 $ 15,500.00 31 $ 15,500.00 $ 7 3/4" Service Connection L.F. 535 $ 30.00 $ 16,050.00 535 $ 16,050.00 $ 8 Connect to Existing Waterline Each 6 $ 1,150.00 $ 6,900.00 6 $ 6,900.00 $ 9 Relocate Fire Hydrant Each 1 $ 620.00 $ 620.00 1 $ 620.00 $ 10 Water Valve Box Adjustment Each 2 $ 100.00 $ 200.00 2 $ 200.00 $ 11 Sidewalk and Pavement Replacement S.Y. 858 $ 36.00 $ 30,888.00 1190.4 $ 42,854.40 $ 11,966.40 12 Roundabout Irrigation Hydrant L.S. 1 $ 900.00 $ 900.00 1 $ 900.00 $ 13 Flowable Mortar C.Y. 509 $ 52.00 $ 26,468.00 509 $ 26,468.00 $ 14 Paver Block Out (C.O.#2) Each 1 $ 250.00 0 $ $ *15 Water Meter Lids (Proposed C.O.) L.S. 1 $ 737.50 1 $ 737.50 $ 737.50 *16 Additional Demolition(Proposed C.O.) L.S. 1 $ 9,652.50 1 $ 9,652.50 $ 9,652.50 TOTAL SECTION 3 $ 184,378.00 $ 206,734.40 $ 22,356.40 GRAND TOTAL OF ALL SECTIONS * Proposed C.O. $ 477,693.10 $ 558,199.23 $ 80,506.13

19th & Barker Roundabout Project No. 56CP12901(C) Additional Work / Change Order No. 2 Section 1 Item #35 Island Noses This work shall include the construction of 12 each mountable island noses, pavement markings and delineator signs for the 6 proposed islands on Barker Ave. $ 18,600.00 Section 1 Item #36 Concrete Barriers This price shall include the installation and removal of concrete barriers on Johnson Dr. as directed by the City. $ 480.00 Section 1Item #37 Additional Traffic Control Add 8 each Type III Barricades with 4 each "Road Closed To Through Traffic" signs on Forrest Ave. and Johnson Ave. as directed by the City. $ 2,020.00 Section 1 Item #38 Adjust Sanitary Manhole This work shall include lowering and installing a new flat top to the existing brick manhole and adjusting the new ring and cover to the proposed street elevation. This manhole was not shown on the plans. $ 540.00 TOTAL $ 21,640.00

19th & Barker Roundabout Project No. 56CP12901(C) Additional Work / Change Order No. 3 Section 3 Item #15 Section 3 Item # 16 Section 1Item #39 Section 1 Item #40 Section 1 Item #41 Section 1 Item # 42 Section 1 Item #43 Section 1 Item # 44 Section 1 Item #45 Water Meter Lids for meters in sidewalk Price reflects the difference between the standard lids as shown on the plans and the special lids required by the Water Dept. $ 737.50 Additional Demolition This reflects the removal and regrading of the driveways replaced due to the steep grades created when the waterline was installed. 3861 s.f. @ $2.50/s.f. $ 9,652.50 Install 24" #4 Dowels Plans did not show any dowels tying the curb and gutter to the 9" pavement. Contractor install 480ea, 24" # 4 bars at $2.00 ea. as directed by the City. $ 960.00 Joint Sealant The plans did not call out for the joints in the 9" concrete pavement to be sealed. The price reflects the cost to seal those joints with a Hot Type Joint Sealant $ 2,981.00 Retaining Wall Color Color of the retaining wall block was not specified in the plans. The City decided on a Buff color which was an additional cost over the basic concrete color $ 450.00 Barker St. Median Islands Pavement Marking Per the City's direction the pavement markings to the Barker Islands were exteneded further than the original proposal. The amount reflects 690 l.f. of 4" yellow preformed plastic @ $2.20 per l.f. and 42 l.f. 6" yellow preformed plastic @ $6.60 per l.f. $ 1,795.20 Storm Sewer Modifications Due to the existing flow line elevations being lower than shown on the plans the proposed storm sewer junction box @ sta. 11+28 had to be modified to fit existing conditions. $ 450.00 Laundry Mat Improvements Improvments to the laundry mat @ 1900 Baker per agreement with the City Remove Tree $ 1,760.00 Survey and Design $ 1,100.00 Grading and Backfill $ 3,550.00 Asphalt Base (59 tons @ $60.00 per) $ 3,540.00 Asphalt Surface (42 tons @ $68.00 per) $ 2,865.00 $ 12,815.00 Sauny Scott Improvements Improvements to Sauney Scott's property per agreement with the City Clear Trees $ 350.00 Excavation and Backfill $ 1,870.00 Handrail $ 500.00 $ 2,720.00 TOTAL $ 32,561.20