NEC3 AND NEC4: ASSESSING COMPENSATION EVENTS

Similar documents
NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage

NEC 3: How to claim as the main

Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC)

TRANSNET NATIONAL PORTS AUTHORITY RFP NUMBER TNPA 541 DESCRIPTION OF THE WORKS: PORT OF RICHARDS BAY - CONSTRUCTION OF PORT ENTRANCES AND ACCESS ROADS

Newsletter Nr. 62 (EN) Demand Guarantees and Unfair Calling of Guarantees

Exposure Draft Accounting Guideline on Merger Accounting

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong

NEC3 ECC Introductory Training

Doing Business in the UAE September Alan Wood and Nigel Wilson Pinsent Masons LLP Dubai Branch

McCarthy Tétrault Advance Building Capabilities for Growth. Group Terminations. Calgary, February 19, McCarthy Tétrault LLP / mccarthy.

The NEC Contract Key Concepts and the Proper Approach to Assessment. The proper basis of assessment of Compensation Events By Karen Gough, Barrister

CONSOLIDATED FINANCIAL STATEMENTS FOR THE YEAR ENDED 31 DECEMBER 2017

Our members. At a glance 2016

ENGINEERING AND CONSTRUCTION CONTRACT

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager

Commercial (QS) Core Competencies (Feb 17)

The Future of Retirement. Shifting sands

The Future of Retirement. Shifting sands

THE COLD WAR: JCT AND ADVERSE WEATHER CONDITIONS

Prompt Payment in Canada An Update Geza R. Banfai Thermal Insulation Association of Canada Banff, AB September 8, 2018

Contractual Awareness Introduction

COMPARISON OF ARBITRATION RULES COMPARISON OF ARBITRATION RULES ICC UNCITRAL KLRCA. HKIAC HONG KONG INTERNATIONAL

I18. Business Demography: Enterprise Births, Deaths and Survival Rates for 2016

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016)

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date

Off-Site Manufacturing

International Commercial Arbitration - An Introduction. Steven Lim Managing Partner, Singapore, Nabarro LLP 12 October 2016

Employment law update

Exposure Draft (ED) of Proposed Statement of Auditing Standards (SAS) 730 The examination of prospective financial information

The Future of Retirement. Shifting sands

All Change in the Change Clause. NEC3 to NEC4 Comparison of Core Clause 6 Compensation Events. giving priority to your commercial success

reads: ICEBERG AHEAD! (DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT)

The Future of Retirement

NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT.

PRODUCT HIGHLIGHTS SHEET

EDQ End Of Service Life Policy

BUSINESS CLASS FLYAWAY EXPERIENCE TO FASHION CITIES LUCKY DRAW PROMOTION 2018 TERMS AND CONDITIONS ( PROMOTION )

EAST AND WEST COMPARED: A CRITICAL REVIEW OF TWO ALTERNATIVE INTERIM PAYMENT SYSTEMS AS USED IN HONG KONG AND THE U.K. ON MAJOR CONSTRUCTION WORKS

Harmony CCP Connect for Equities

Shipbuilding Contracts the Value of Defence Club Cover

DGA Group. International Construction Consultants

Information regarding ISDA is set out in Annex 1 to this response.

Standard forms of partnering contracts The ultimate contractual commitment? Part 4

PROLONGATION COST CLAIMS THE BASIC PRINCIPLES

Real Estate Bulletin

Importance of the amendment to the Public Procurement Law for the expenditure of EU funds

CONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1

Brexit considerations FOR BUSINESS CONTRACTS

THE HONG KONG INSTITUTE OF SURVEYORS

NEC3 ECC target contract option principles and innovative applications

Global Depositary Receipts and the new EU regime

Leaseholder Consultation Section 20 of the Landlord and Tenant Act 1985 (as amended)

WHAT IS A TRANSACTIONAL TAX PRACTICE?

The 10 Most Important Issues General Counsel Should Know About Risk Transfer Involving Insurance

MEASURING PERFORMANCE. Member and Broker Survey 2013 UKDC IS MANAGED BY THOMAS MILLER

Auditor General s Office

INTERIM REPORT. FDM Group (Holdings) plc. For the six months ended 30 June Creating and inspiring exciting careers that shape our digital future

PROTECTING YOUR BUSINESS FROM EVERY POSSIBLE ANGLE

CHAPTER 1 25 INTRODUCTION

Prudential Unit Trusts

VAT update. News. Cases. August 2018

This form must be fully completed, signed and dated. Please delete accordingly and/ or state "N/A" if not applicable.

CHINA TAIPING INSURANCE (UK) CO LTD LIABILITY POLICY SUMMARY

Exposure Draft ED/2009/4 Prepayments of a Minimum Funding Requirement, Proposed amendments to IFRIC 14

September 24, 2010 SUBMITTED BY

PRODUCT HIGHLIGHTS SHEET

The New NZS 3910:2013

life protection I want substantial life protection at an affordable premium smart elite term smart term

IS Prime Limited BEST EXECUTION REPORT FOR 2017 APRIL 2018

New MAS Outsourcing Guidelines for Fund Managers and Other Financial Institutions

BK SURCO TRAINING. presents a series of COMMERCIAL AND CONTRACT MANAGEMENT TRAINING SEMINARS. for CONSTRUCTION PROFESSIONALS

Supplemental Information Memorandum

INTERACT POLICY

Response to Exposure Draft Recognition of Deferred Tax Assets for Unrealised Losses

Why is the IFoA launching a new curriculum? Personal and Professional Development (PPD) Transferring from Core Technical to Core Principles

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION.

Miller Insurance Services (Singapore) Pte Ltd. Terms of Business Agreement ( TOBA )

b) by extending the relief to voluntary novations and making it clear that it can be applied retrospectively to past novations to CCPs.

10 THINGS TO KNOW ABOUT PROFESSIONAL INDEMNITY INSURANCE A GUIDE TO PROTECTING YOUR BUSINESS

FUND PROTECT INNOVATION IN THE PROTECTION OF FUND DIRECTORS PERSONAL LIABILITY

Certificate and Warrant Programme

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

ABN AMRO (Channel Islands) Limited Order Execution Policy

Project Procedures. That Will Ensure Payment In Difficult Economic Times. By Neil Sinclair and Daniel Louw DMS International, Inc.

Personal and Executive Income Protection from Aviva

How Do I Wire My Stock Plan Proceeds?

TIME IS MONEY OR IS IT? (PART 2)

LITIGATION FUNDING CLARITY I FOCUS I RESOLUTION

Negotiating the ISDA Master Agreement

ESTABLISHING A MANUFACTURING PLANT IN ASIA

IASB Exposure Draft on Classification and Measurement: Limited Amendments to IFRS 9

HONG KONG SCIENCE AND TECHNOLOGY PARKS CORPORATION

Tax update. News items. Case reports. October 2018

PRODUCT HIGHLIGHTS SHEET

Dated 2015 THE MAYOR AND BURGESSES OF THE LONDON BOROUGH OF BARNET (EMPLOYER) -and- [ ] LIMITED (CONTRACTOR)

Less is More: Private Equity Investments` Benefits

Title Aggregated Procurement

Conflict of Interest Directors and prescribed officers

This Presentation is for information purposes in connection with Leed Resources PLC (the Company ). While the information contained herein has been

Transcription:

NEC3 AND NEC4: ASSESSING COMPENSATION EVENTS IAN PARKINSON Senior Consultant, Manchester The NEC3 suite of contracts were first published in 2005, meaning that the industry has had 13 years getting to grips with this family of contracts and specifically the provisions relating to the assessment of compensation events. However, I still come across cases/examples where the Parties, when assessing compensation events, fail to follow the contract. This short article is drafted to detail some of the key points to consider when assessing compensation events. DEFINED COST The assessment of compensation events is based upon the event s effect on the Defined Cost. The principle behind this is that a contractor should not unfairly gain or lose as a result of the compensation event. This is different from other standard forms of contract, which use the rates and prices included in the contract as a basis for assessment, where a contractor can potentially make significant gains or a significant loss as a result of a change. However, I continue to see examples of contractor s using their rates to price compensation events rather than the Defined Cost. This can mean the contractor is taking on more risk than they should and subsequently they under recover their full entitlement. Clause 63.1 states: The changes to the Prices are assessed as the effect of the compensation event upon: - the actual Defined Cost of the work already done; the forecast Defined Cost of the work not yet done and; the resulting Fee. 1

So, the contractor is entitled to assess the impact of the compensation event on their Defined Cost. The most frequently used contract options to calculate Defined Cost are either the Schedule of Cost Components (SCC) or the Shorter Schedule of Cost Components (SSCC). The cost components in the schedules include people; equipment; plant and materials; charges; manufacture and fabrication; design and insurance. If a cost item is not listed in the schedules, then it is deemed included in the Fee. Under the NEC3, the cut-off point between whether the contractor uses actual or forecast cost to assess the impact, is the date when the Project Manager instructed, or should have instructed, the Contractor to submit quotations. When making their assessment, contractors need to ensure that they account for not only the direct cost of doing the work, but the prolongation and disruption including any inefficient use of labour and plant as a result of the event. I often see assessments where the direct costs are included, but the contractor has not accounted for the disruption caused by the event, thus affecting their level of recovery and ultimately. If a compensation event occurs and, as a result of the event, there are labour and plant (Equipment under NEC3) resources not fully utilised, then this needs to be included in the assessment. A contractor would not be entitled to submit a separate claim for delay and disruption under an NEC3 form of contract. TIME Clause 62.2 of the NEC3 contract states Quotations for compensation events comprise proposed changes to the Prices and any delay to the Completion Date and Key Dates assessed by the Contractor. This means, that contractor must ensure they include any time impact within their quotations. Failure to do so may result in them not being entitled to an extension of time under the contract. Obtaining an extension of time is a precursor to recovering time-relating costs on the project. Failure to assess and include the time impact of the compensation event, will result in the contractor being unable to recover the time-related costs and could also make them liable for damages. On previous projects, I have seen contractors failing to 2

include the time impact of the event within the quotation, resulting in under recovery of costs and potential liability for damages. It should not be assumed that the impact of time on the project can be assessed globally. There is no scope for global claims under the NEC3 contract. The contract is clear, in that each event is assessed individually and in sequence. It is also worth remembering that delays to the Completion Date, are assessed as the length of time that, due to the compensation event, actual planned Completion is later than the planned Completion as shown on the Accepted Programme i, under clause 63.3. Therefore, the Contractor is entitled to additional time and cost if the compensation event delays the planned Completion date, not the contractual Completion Date. RISK Clause 63.6 entitles the Contractor to include within their assessment, risk allowances for cost and time to cover matters which have a significant chance of occurring and are at the Contractor s risk under the contract. This is probably one of the main areas where contractors are under recovering their full entitlement on NEC3 contracts. As we all know, when pricing any construction work, assumptions have to be made for unknown elements that may or may not affect the works. Under the NEC3 form of contract it would be naïve to assume that by including your own assumptions within the quotation as to how you have assessed the event, you are protected if those assumptions turn out to be incorrect. The only contract provision entitling the contractor to additional time and/or cost is the compensation event provisions in clause 60.1. Clause 60.1(17) entitles the contractor to a compensation event if the project manager (the contractor under the subcontract) notifies a correction to an assumption which he had stated i Last Accepted Programme if NEC4 applies 3

within his compensation event. Therefore, it is important to obtain the assumption from the project manager in accordance with clause 61.6, thus giving the contractor peace of mind that they will be entitled to an additional compensation event if those assumptions turn out to be incorrect. If an assumption is not forthcoming from the project manager then the contractor would be well advised to include risk allowances for any unknown/undefined factors, which may affect the works. I often find that this then prompts the project manager to provide the relevant assumption(s). In order to clearly explain pricing risk under the NEC3 contract I will give an example below based on the risk of weather events affecting the works. In this scenario clause 60.1(13) has been deleted from the contract, meaning the contractor carries the risk for all delays resulting from weather events. A compensation event occurs (a change to the Works Information) and a significant amount of rainfall is forecast in the month that the event is to occur. When making the assessment, should the contractor assume that all days will be affected, resulting in significant downtime or just a few days affected with little or no downtime? Taking this scenario back to the contract, the risk must have a significant chance of occurring, otherwise it is not a valid allowance in accordance with clause 63.6. Therefore, the contractor must make a reasonable assessment of the likelihood of the rainfall causing downtime and make their allowance based on that assessment. The next threshold is that the risk must be with the contractor s under the contract. In this scenario the clause entitling the contractor to a compensation event due to a weather event, 60.1(13), has been deleted, meaning that any time and cost impact caused by weather events is at the contractor s risk under the contract. If this clause had not been omitted then the calculation would be completely different. Assessing risk in compensation events is akin to the way in which a contractor would assess the risk inherent in pricing a tender. If they get it right, they will maximise their return on investment, however if they get it wrong, they could stand to lose a significant amount of money on the project. If contractors adhere to the provisions of the contract relating to the assessment of compensation events, they will ensure that they maximise their returns on a project, thus maximising the bottom line. If you are having problems on an NEC3 or NEC4 contract regarding the assessment of compensation events, or any other matter, please do not hesitate to contact your nearest DGA office. 4

MORE INFORMATION If you would like to find out more details about any of the subjects covered in this Ebriefing please contact DGA Group through the contact details below or at DGAGroup@dga-group.com DGA GROUP HEADQUARTERS 25 Eastcheap BIRMINGHAM Tel: +44 (0)121 698 2148 London MANCHESTER Tel: +44 (0)161 932 1222 United Kingdom NOTTINGHAM Tel: +44 (0)1332 638 061 EC3M 1DE LEEDS Tel: +44 (0)113 251 5017 BRISTOL Tel: +44 (0)117 344 5023 Tel: +44 (0)203 961 5340 MAIDSTONE Tel: +44 (0)1622 673 021 UNITED ARAB EMIRATES SINGAPORE CANADA Office 615 20 Anson Road 160 Quarry Park Boulevard SE Park Lane Tower #19-02 Suite 300 Al A amal Street Twenty Anson Calgary Business Bay Singapore 079912 Alberta United Arab Emirates Singapore Canada T2C 3G3 Tel: +971 4 437 2470 Tel: +65 6291 2482 Tel: +1(403) 279-1603 Tel: +65 62916208 HONG KONG AFRICA Suite 2802 Building 2 Lippo Centre Tower 2 Country Club Estate 89 Queensway 21 Woodmead Admiralty Sandton Hong Kong South Africa 2054 Tel: +852 2295 2678 5