Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement

Similar documents
Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC)

ENGINEERING AND CONSTRUCTION CONTRACT

NEC3 ECC Introductory Training

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager

CONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1

Construction Law Update The NEC4 suite of contracts are here!

Kelvin N. F. Lau Associate Vice President. 2 Februray 2012

reads: ICEBERG AHEAD! (DEFINED COST UNDER THE NEC3 ENGINEERING AND CONSTRUCTION CONTRACT)

NEC4 Engineering and Construction Contract review of changes from NEC3

NEC4: Evolution not Revolution. Delivering distinctive, high quality projects across the construction and property industry

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong

Using a Dispute Avoidance Board for contracts covered by the Housing Grants, Construction and Regeneration Act 1996

NEC4 ENGINEERING & CONSTRUCTION CONTRACT

Standard forms of partnering contracts The ultimate contractual commitment? Part 4

Webinar - The Project Manager in the NEC4 ECC: What s new and different?

AMENDMENTS APRIL 2013

NEC 3 ABOUT US 27/06/2013 COMPANY PROFILE NEC 3 SOME PROBLEMS EXPOSED AND DISCUSSED. Gary Blackburn Michael Conway Damien Savage

Professional Services Contract

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION.

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

Unpacking framework agreements for the delivery and maintenance of infrastructure

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

2 The Contractor s main responsibilities

HKIS Resolving Disputes between Contractors

NEC: Lessons from nearly 20 years in the UK and elsewhere : implications for Hong Kong Hong Kong Institute of Surveyors, 24 April 2012

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016)

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

ICES. Narrative. Applicant s name

Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract

Framework agreements. Framework agreement. Figure 1: Call-offs over the term of a framework contract. Package / batch /

TRANSNET NATIONAL PORTS AUTHORITY RFP NUMBER TNPA 541 DESCRIPTION OF THE WORKS: PORT OF RICHARDS BAY - CONSTRUCTION OF PORT ENTRANCES AND ACCESS ROADS

The NEC 3 Engineering and Construction Contract

The New NZS 3910:2013

NEC: OPINION ON THE APPLICATION OF SUBCONTRACTED FEE PERCENTAGE UNDER THE NEW ENGINEERING CONTRACT (3RD EDITION) ENGINEERING CONSTRUCTION CONTRACT.

NEC 3: How to claim as the main

NEC3 ECC target contract option principles and innovative applications

Z-CLAUSES: FRIEND OR FOE?

MacRoberts. A law firm as individual as you.

The NEC Definitely, Maybe?

TRUSTED TRADER. Trusted Trader terms and conditions. Contents.

The NEC Contract Key Concepts and the Proper Approach to Assessment. The proper basis of assessment of Compensation Events By Karen Gough, Barrister

Section 7. General Conditions of Contract for the Procurement of Works

New Terminology. References to. The main theme of NEC4 is that it represents an evolution rather than a revolution in thinking

Contractual Awareness Introduction

Common Pitfalls and Associated Solutions with the Use of NEC for the Construction Industry Council

Implementing the Construction Supply Chain Payment Charter. January Guidance Note

Helpful instructions for webinar attendees

The Contractor s NEC3 ECC Handbook

Short Course on. Construction Law. with particular reference to the. JBCC 2000 Series of Contracts. in particular the application of

TRUSTED TRADER CONTENTS. Terms and conditions of scheme membership.

NEC3 A Practical Guide to Compensation Events. Chris Holden. LLB FRICS FBEng MCIArb.

Australian Standard. Subcontract conditions for design and construct. AS (Incorporating Amendment No. 1) AS

NEC4 Key Commercial Changes

NEC Asia Pacific Users Group Workshop 2014 Keeping the Programme Up to Date

Introduction to Construction Arbitration

Procedure for Post Contract Progress And Cost Control. Procedure No. 012

Cl Offence Individual Corporation

SCHEDULE 1 CHANGE ORDERS

MAIN CIVIL WORKS CONTRACT SCHEDULE 12 CHANGES TABLE OF CONTENTS

Subcontract conditions

Off-Site Manufacturing

Key Performance Indicators for the Provision of Medium Construction Related Works and Building Refurbishment for the University of Worcester

The Key Role of the NEC Programme and who really owns the float?

Contractor and subcontractor insolvency January 2010

COMPLIANCE GUIDELINES

SCHEDULE 1 CHANGE ORDERS

General Conditions of Purchase Current: July 2009

A Simple Guide to applying the Security of Payments Act 2009 (Vic)

Waste Treatment Plant Project Supply Chain Collaboration Event WTP - EQUITABLE ADJUSTMENT MANAGEMENT (Changes, REAs, Claims)

NEC: AN EARLY WARNING OF NEC4 S CHANGES TO THE EARLY WARNING CLAUSE

STANDARD TERMS & CONDITIONS for Construction, Engineering & Electrical Works

PHO Services Agreement

CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND

Appendix K Model Letters for Use by the Engineer

Conditions of Contract for PLANT and Design-Build

The NEC3. The Unknowns

DOWN THE RABBIT HOLE WITH THE TAKING-OVER PROCEDURE UNDER FIDIC

PROJECT BANK ACCOUNTS

SURCO TRAINING. presents a series of AND CONTRACT MANAGEMENT TRAINING SEMINARS. for CONSTRUCTION PROFESSIONALSS

Purchase Order general terms and conditions for the supply of goods and services

Conditions of Contract

Consultancy Services Contract

C O N T R A C T. between

Comparison between the Red Book 1999 and the MDB Harmonised Edition 2010

Do your. homework. A contractor s guide to rights and obligations when contracting with homeowners

Whereas the Contractor has entered into an agreement (the "Prime Contract") dated the, 20 with:

(Revised March 3, 2008) ADVANCE PAYMENT POOL (DEC 1991)

GENERAL CONDITIONS OF ELECTRICAL INSTALLATION CONTRACT

Repair Authority - Terms of Authority

1 In these Domestic Sub-Contract Conditions the following expressions and terms shall have the meanings given below:

Tender Terms and Conditions: 1. This invitation of bid is open to contractors, Class-Small registered with the Construction Development Board.

Cosmos Projects - Standard Terms and Conditions of Sub-Contract

Limitations on Pass-Through Charges. Government Contracts Update Volume 2, Nov. 2011

ENFORCEMENT (PACKAGED RETAIL AND INSURANCE-BASED INVESTMENT PRODUCTS REGULATIONS 2017) INSTRUMENT 2018

Ref P BLACKHALL LTD (PBL) CONDITIONS OF TRADING 2018/ 19

NZS 3915:2005 AMENDMENTS. No. Date of issue Description Entered by, and date

Terms and Conditions

PLANNING SUPERVISOR'S APPOINTMENT

COMPENSATION & PAYMENT PROVISIONS (COST REIMBURSABLE)

Transcription:

Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement Technical Forum on NEC3 Collaborative Contracts 7 March 2012 Ir Ken W. N. Ko 1

Agenda Subletting Early Warning Notification Compensation Event Payment 2

Spirit of the NEC Contract 3

Partnering Partnering ECC Clause 10.1 The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract and in a spirit of mutual trust and co-operation. = REAL PARTNERING 4

Subletting 5

Subletting (1/3) Contractor shall prepare a Subletting Procedures for subletting works Subletting Procedures shall be commented and accepted by Project Manager and ICAC before subcontract tendering process carried out The Contractor shall propose a subcontractor tenderer list and the list shall be approved by the Project Manager 6

Subletting (2/3) Join tender opening will be carried out by Project Manager s, Supervisor s and Contractor s staff Project Manager or his representative should attend the Tender Interviews with the potential tenderers Recommendation of tenderer should get Project Manager s approval before awarding to proposed tenderer 7

Subletting (3/3) Project Manager, Supervisor, and Contractor involve in the entire subletting process, to urge Contractor to select most competent subcontractor and competitive offer 8

Early Warning Notification 9

Early Warning Notification (1/4) The purpose of the Early Warning Notification is to raise the risk at the early stage solving the problems together rather than against each other 10

Early Warning Notification (2/4) Contractor and the Project Manager can give an Early Warning by notifying the others as soon as either becomes aware of any matter could increase the project price delay completion delay meeting a Key Date or affect works quality 11

Early Warning Notification (3/4) Following the Early Warning Notification, a Risk Reduction Meeting amongst Project Manager, Supervisor and Contractor will be conducted. It may be agreed that other people attend according to particular circumstances. All parties will discuss to find out the root problem and solution for eliminating / reducing the risk together. Risk is owned by All Parties 12

Early Warning Notification (4/4) ECC+ACC Risk Register (ECC16.1-16.4) Following the Risk Reduction Meeting, Risk Register shall be revised by Project Manager to record the actions taken for avoiding or reducing the risk. 13

Compensation Event 14

Compensation Event (1/3) An event to be a Compensation Event, it must be specifically listed Core Clause 60.1 Events added by Secondary Options Additional events included in Contract Data part 1 Fair risk sharing: Any variation works and unforeseen matters will be covered by Compensation Event Time and cost will be dealt together 15 15

Compensation Event (2/3) Typically each compensation event is dealt with independently Ideally the Compensation Event estimation shall be agreed prior to work (avoid future dispute) Once Compensation Event has been agreed by Project Manager for the cost, the Target Price will be adjusted and it will not be reassessed on the actual expenses 16 16

Compensation Event (3/3) Key Points: CE Quotation = Estimated Cost + Fee Agreed price for Compensation Events based on agreed Quotation 50% Client 50% Contractor Actual Final Cost Target Price (Tender Price) 17

Payment 18

Payment (1/7) Payment Amount Due: Price for Work Done to Date (PWDD) plus other amounts to be paid to the Contractor less amounts to be paid by or retained from the Contractor * Contractor shall present the proof of the payments which have been paid 19 19

Payment (2/7) Price for Work Done to Date (PWDD) PWDD = total Defined Cost + Fee Defined Cost ECC Clause 11.2(23) payments due to subcontractor cost components in ECC including People, Equipment, Plant and Materials less Disallowed Cost Fee fee percentage tenderer shall be specified in the Contract Data The Fee includes all the costs of the Contractor that are not included in Defined Cost, together with his profit and any allowance for his risks. 20

Payment (3/7) ECC+ACC Disallowed Cost ECC Clause 11.2(25) Should not have been paid to a Subcontractor or Supplier in accordance with his contract Correcting defects after completion Correcting defects caused by the Contractor not complying with constraints in Works Information Surplus resources, plant & materials etc The cost of preparation for and conduct of an adjudication or proceedings of the tribunal 21

Payment (4/7) Assessment of Payment Project Manager / Supervisor can access to Contractor s account records (i.e. Open Account) which is transparency and subject to audit by Project Manager auditor team Project Manager / Supervisor can monitor the overall financial arrangement of the Contractor for the project 22 22

Payment (5/7) ECC + ACC Pain / Gain Sharing (Option C): - Actual Cost < Contract Price (Y) Contractor and Client share 50% of gain value. Actual Cost 110% Contract Price (Y) Contractor and Client share 50% of pain value. i.e. The maximum of the Final Amount will be ($Y x 1.05 = $1.05Y) Actual Cost > 110% Contract Price (Y) Contractor will share 100% of pain value i.e. the ceiling of the Final Amount is $1.05Y only for Client 23

Payment (6/7) Pain / Gain Sharing (ECC Option C): Encourage joint problem solving Incentive to Contractor to save Cost Gain 50% / 50% share saved Cost 24

Payment (7/7) Target The final payment should be the FINAL ACCOUNT once the contract completion 25

END 26