SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING MAY 15, 2018

Similar documents
SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 16, 2018

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

Ballot Measures-T Section

Status: Structural steel installation complete at primary building. Observatory construction underway. Central Plant modifications are complete.

Governing Board Bond Update. Measure G Bond Program. for. Solano Community College District

FACILITIES PLAN STATUS REPORT July 21, 2014 SADDLEBACK COLLEGE 1. SCIENCES BUILDING

Action Item. Sid Albaugh, Assistant Superintendent Business Services. Consideration of Approval of 2018 Measure A - Facilities Project List

APPENDIX A FULL TEXT OF BOND MEASURE

Contents Ballot Measure... 2 Full Text Ballot Proposition... 3 Tax Rate Statement... 7 Impartial Analysis... 8 Statement in Favor of Measure...

FACILITIES PLAN STATUS REPORT January 22, 2019 CAPITAL IMPROVEMENT PLANNING

Allan Hancock Joint Community College District

SOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S SOMIS UNION SCHOOL DISTRICT TAX RATE STATEMENT BOND MEASURE S

Status: Structural steel installation underway at primary building. Observatory construction underway.

Rockville Science Center (P036600)

Original Revision Total Project Budget: $14,530,000 $47,700,000 $62,230,000 District Funding Commitment Anticipated State Match: $14,530,000 $N/A

Original Revision Total Project Budget: $52,234,000 $8,308,000 $67,358,000 District Funding Commitment: Anticipated State Match:

Ballot Measures-N 7. Centralia Elementary School District, Building Strong Neighborhood Schools

Original Revision Total Project Budget: $52,234,000 $ 8,308,000 $67,358,000 District Funding Commitment: $15,670,000 $51,688,000 $67,358,000

Measure G Quarterly Progress Update

Progress Update Identified Needs & Capital Plan

P R E S E N T E D T O : S O L A N O C O M M U N I T Y C O L L E G E D I S T R I C T G O V E R N I N G B O A R D J U L Y

Contents. Ballot Measure Full Text Ballot Proposition Tax Rate Statement Impartial Analysis Statement in Favor of Measure...

OVERSIGHT OF MEASURE C SPENDING THE CITIZENS OVERSIGHT COMMITTEE

I. PROJECT DESCRIPTION

STATE CAPITAL OUTLAY PLANNING

Measure G Quarterly Progress Update

Santa Barbara Community College District Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2013

BERKELEY UNIFIED SCHOOL DISTRICT

October 4, 2007 Page 1 of 8

Original Revision Total Project Budget: $14,530,000 $47,700,000 $62,230,000 District Funding Commitment Anticipated State Match: $14,530,000 $N/A

Program and Project Status Update

REQUEST FOR PROPOSALS (RFP)- SCIENCES BUILDING FOR DSA INSPECTION SERVICES, SADDLEBACK COLLEGE

Bond Oversight Committee Bond program. January 7, 2016

REGISTER OF IOWA STATE UNIVERSITY CAPITAL IMPROVEMENT BUSINESS TRANSACTIONS

MT. SAN ANTONIO COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE R, NOVEMBER 2001) PERFORMANCE AUDIT.

EXHIBIT A Page 1 of 11

Original Revision Total Project Budget: $14,530,000 $47,700,000 $62,230,000 District Funding Commitment Anticipated State Match: $14,530,000 $N/A

Facility Condition Assessment Report. Coast Community College District

Allan Hancock Joint Community College District

Public Presentation Capital Bond November 27, 2017

CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5

2019 Capital Projects Plan

Santa Barbara Community College District Measure V Bond Construction Fund Financial Statements and Agreed-Upon Procedures Year Ended June 30, 2015

Measure M. Board of Trustees Study Session. January 16, 2013

University of Colorado Capital Construction Project Status SUMMARY - May 2017 (accounting noted by campus)

West Bend School District Community Survey Results. Spring 2018

CITY OF WILLIAMSBURG MEMORANDUM. Mayor and City Council Planning Commission. From: Andrew O Trivette, Assistant City Manager

Construction Workshop

Community College District. Measure M

9000 SERIES SCHOOL FACILITIES TABLE OF CONTENTS

Transportation and Parking Services

Measure RR Bond Budget by Project. Measure RR BAN Measure RR BAN Interest Measure RR Series AB Measure RR Series AB Interest

SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA

Residential Permit Fee Schedule

Physical Plant. Five-Year Capital Budget Plan. State College Area School District November Page 1 of 15

SONOMA COUNTY JUNIOR COLLEGE DISTRICT PROPOSITION 39 AND MEASURE A GENERAL OBLIGATION BONDS SANTA ROSA, CALIFORNIA

SAN MATEO COUNTY COMMUNITY COLLEGE DISTRICT Bond Oversight Committee Minutes June 7, 2018 District Office Board Room

SECTION 3 CAPITAL PLAN AND BUDGET

Overview of Public Schools CIP

DESERT COMMUNITY COLLEGE DISTRICT PROPOSITION 39, GENERAL OBLIGATION BONDS (MEASURE B, MARCH 2004) PERFORMANCE AUDIT JUNE 30, 2010

Minutes Capital Planning and Budget Committee Thursday, August 23, 2012

CERRITOS COMMUNITY COLLEGE DISTRICT

SAN FRANCISCO COMMUNITY COLLEGE DISTRICT GENERAL OBLIGATION BOND FUNDS (ELECTION OF 2001, SERIES A, B, AND C AND ELECTION OF 2005, SERIES A AND B)

2017 Bond Program Summary

CAPITAL PROJECT PROCESS

KOINONIA HOUSE (KHSE) CAMPUS PUBLIC SAFETY OFFICE (CPSO) RENOVATIONS Solicitation #1560

Minutes Capital Planning and Budget Committee Thursday, July 9, 2009

2009 Annual Report to the Board of Trustees. Bond Measure V Citizens Oversight Committee

Facilities Planning & Construction Report nd Quarter Ending December 31, 2017

Attachment FC 16 SBCC 11/17/2017. STATE BOARD OF COMMUNITY COLLEGES Construction and Property November 17, 2017

Use of State and District Construction Funds

Members Present: Gino Gasparini, Vijay Gupta, Nori Jabba, James Ruigomez, Bill Rundberg and Dennis Zheng

PROGRAM REVIEW FACILITIES PLANNING & SERVICES DIVISION

Performance Audit on 2008 and 2013 SPLOST Revenues For the Fiscal Year ended June 30, 2012

Financial Statements and Report of Independent Certified Public Accountants

Sam Houston State University A Member of The Texas State University System

Tumwater University School District Budget Myths Bond Project Update. February 2016 Mel Murray, Director of Capital Projects John Bash, Superintendent

Information. June 06, 2017 The Board awarded a contract to gkkworks/belli Architects.

BUDGET AND FINANCE COMMITTEE. March 19, Minutes

Capital Projects Completed since 1988

INVENTRUST PROPERTIES VENDOR TRADE CODES INSURANCE REQUIREMENTS

FY 2017 Capital Development Plan. Arizona State University. Revised November 2016

3. INTRODUCTION OF REAPPOINTED AND NEW MEMBERS. Heather Anderson* Barry Snell* Sonya Sultan

Los Angeles Community College District. Building Program Monthly Progress Report

MUROC JOINT UNIFIED SCHOOL DISTRICT KERN COUNTY NORTH EDWARDS, CALIFORNIA

Local ballot measure: B. Redding School District Bond Measure

Thompson Rivers University

FY2019 MEIF / Auxiliary Services / E&G Budget Discussion

Attachment FC 08 (REVISED 03/13/2018) SBCC 03/16/2018. STATE BOARD OF COMMUNITY COLLEGES Construction and Property March 16, 2018 FY

Overview of Public Schools CIP

Overview of Public Schools CIP

Lake Mills Area School District Community Survey Results. Spring 2018

CAPITAL FUNDING SUMMARY

Basic Financial Statements, Management s Discussion and Analysis and Supplementary Information. June 30, 2012 and 2011

Detailed Project Budget

ADDENDUM NUMBER 01 TO THE BID DOCUMENTS. BID NUMBER: G Math and Science Building Exterior Stair Lighting #32107 Evergreen Valley College

LEE COUNTY SCHOOL DISTRICT S CAPITAL PLANNING PROCESS

UNIVERSITY OF HOUSTON SYSTEM-WIDE Art Acquisition Policies and Procedures

Novato Unified School District

Region 5 Upcoming Projects for Summer/Fall 2018

Transcription:

FACILITIES COMMITTEE MEETING MAY 15, 2018 1

PROJECTS Dunlap Hall Renovation - Completed Central Plant & Infrastructure - Completed Johnson Student Center Johnson Demolition Science Center & Building J Demolition 17 th & Bristol Street Parking Lot 2

PROJECT UPDATE JOHNSON STUDENT CENTER Project Summary: Demolition of existing building. Construction of a 63,642 square foot new Johnson Student Center. Building Programs Include: Campus Store, Grab-n- Go/Coffee & Juice, DSPS, EOPS/CARE & CalWORKS, Student Financial Services, SSSP/Upward Bound, Warehouse, Reprographics, Conference Center, Financial Aid, Student Placement, Health & Wellness Center, DSPS, Office of Student Life, ASG, The Spot. Site improvements include new hardscape, landscape and shade shelter around the Johnson Center as well as renovations to the West Plaza including new landscape, hardscape, a shade structure, and a lunch serving kiosk for Middle College High School (MCHS). Current Status: Final decommissioning activities will be completed summer 2018. Increment 1 (Site Preparation) received DSA approval on February 20, 2018. Increment 2 (Building) was submitted to DSA on February 15, 2018. Increment 2 (Building) DSA approval anticipated August 2018. Target construction start Fall 2018 - Spring 2021. Target occupancy late Spring 2021. Budget: RFP for lease-leaseback construction delivery is under development. $50 million $41.95 million funded by Measure Q Note: Budget is currently deficient by $8.05 million and a new budget update is pending upon a reallocation of budgets from the Central Plant and 17 th /Bristol St. Parking Lot projects. 3

Project Summary: Construction of a new three-story, 64,785 square foot science center and 880 square foot greenhouse. Programs Include: Division Office, Faculty Offices, (2) Standard Classrooms, (1) Large Classroom, (1) Large Divisible Classroom, (1) Computer Lab, (1) Engineering Lab & Support Space, (6) Biology Labs & Support Space, (2) Geology Labs & Support Space, (5) Chemistry Labs & Support Space, (1) Physics Lab & Support Space, Student Collaboration Areas. Project includes demolition of (3) J Buildings. Current Status: Underground electrical runs underway Underground plumbing activities underway Underground site utilities underway New Foundation and pile cap installation underway New Underground infiltration system underway New Pile installation complete New Phase 1A complete including anti-graffiti on masonry wall, electrical for welding stations and hardscape improvements Target Occupancy/Completion: Summer 2020 Budget: $73.38 million PROJECT UPDATE SCIENCE CENTER & BUILDING J DEMOLITION 4

PROJECT UPDATE PARKING LOT AT 17 TH /BRISTOL ST. Project Summary: New surface parking lot. Current Status: Project is on hold. To be used as overflow parking for contractors for the Science Center and Johnson Student Center. Given the project is on hold, the budget of $2.5 million will be recommended to be reallocated to another short-funded project this Spring 2018 until there is further certainty around the future of this project. 5

2015-2016 SCHEDULED MAINTENANCE PROJECTS (SM16) PROJECT STATUS ESTIMATED BUDGET Water Conservation No change in status. A smaller scope of work has been identified to undertake an Irrigation Phase 1 project, which the scope of work is to repair and replace some of the existing landscaping and irrigation until the larger project scope of work can be identified. A mandatory job walk was held on March 14, 2018. Bids were due March 27, 2018 and the District received one bid. The award of bid was ratified by the Board of Trustees on April 23, 2018. The work is anticipated to start in April 2018 and complete in June 2018. $96,915 (under review) TOTAL ALLOCATION (active projects only) $96,915 6

2016-2017 SCHEDULED MAINTENANCE PROJECTS (SM17) PROJECT STATUS ESTIMATED BUDGET Window Replacement (H) No change in status. A pre-construction meeting was held on March 5, 2018. A DSA project inspector agreement was approved by the Board of Trustees on April 23, 2018. The project is anticipated to start construction in June 2018. $731,535* TOTAL BUDGET ALLOCATION $731,535 * Budget Breakdown: $440,000 funded by SM17 $260,000 funded by the Campus $31,535 funded by Capital Facilities Fund 7

CURRENT CAPITAL PROJECTS RELOCATIONS PROJECT STATUS ESTIMATED BUDGET Welding Relocation Relocation required due to demolition of (3) J Buildings. Window Replacement (H) Temporary Relocation to Russell Hall R-118B Temporary power was removed and the welding stations were moved back now that the new masonry wall west of the Science Center has been completed. This project will be removed from future updates. Temporary swing space/workstation furniture (6) for Summer 2018 has been setup in Russell Hall. Relocation to follow in June. $122,000 Included in SM17 Window Replacement (H) Budget 12

CURRENT CAPITAL PROJECTS RUSSELL HALL REPLACEMENT (HEALTH SCIENCES BUILDING) Project Summary: Construction of a new 55,138 square foot Health Sciences Building to include Nursing, Occupational Therapy Technology, Emergency Medical Services, Pharmacy Technology, general classrooms and computer labs. The new building will be located south of the existing library and north of the new Science Center. Demolition of existing Russell Hall Building. The District will have to adhere to a strict state process and guidelines. Current Status: The Preliminary Plan was submitted to the State on February 28, 2018 and is under review. Design development documents scheduled to be submitted to the District late May 2018. New User group meetings have been completed. New Meetings with M&O, ITS and Campus Safety are ongoing. No changes are allowed to square footage and/or programs. DSA submittal anticipated February 2019. DSA approval anticipated November 2019. New Target construction start April 2020. New Target occupancy May 2022. Budget: New $58.8 million* (District to contribute 50% - subject to change based on annual State Budget changes for inflation adjustments) $20,475,000 state funded Budget under review 13

CURRENT CAPITAL PROJECTS PROJECT STATUS ESTIMATED BUDGET Barrier Removal Exterior (Parking Lot 9 Stalls) This is a new project to address the accessible stalls and path of travel repairs needed to restore a portion of parking lot 9 after the McCarthy Construction team vacates the space. The construction fencing will be reconfigured for future construction team trailers for Johnson demolition and Science Center projects. Minor modifications, re-striping and resurfacing work needs to occur in this lot as there is a transition from one construction project to the next. DSA approved the plans on May 4, 2018. The project went out to bid on May 9, 2018 with a due date of May 22, 2018. Construction is anticipated to start in the summer. $275,000 (under review) 10

CURRENT CAPITAL PROJECTS PROJECT STATUS ESTIMATED BUDGET Barrier Removal Signage/Wayfinding Campus Directory (Electronic) Chavez Hall Renovation A kick-off meeting with the architect was held on March 16, 2018 with each campus to discuss the architect s observations and assessment. The next meeting was held at the college to review site locations, further recommendations, options, locations and types of signage and wayfinding monuments on May 2, 2018. A scope of work is under development. A kick-off meeting with the architect was held on March 16, 2018 with each campus to discuss the architect s observations and assessment. The next meeting was held at the college to review site locations, further recommendations, options, locations and software requirements on May 2, 2018. A scope of work is under development. The contract has been awarded and the next phase of work in the Business Development department is anticipated to start in the summer. $115,000 $82,500 $267,246 (under review) 11

REQUESTED PROJECTS PROJECT STATUS ESTIMATED BUDGET Campus Security Storage Work commenced on May 11, 2018 to allow for the installation of the Keytrak system and lockers. $75,000 Building K Welding Ventilation No change in status. This is a campus requested project to replace the aging ventilation system in Building K (Welding Program). The architect has commenced the investigation to assess the condition of the building to determine what upgrades can be undertaken. $242,691 (under review) Infinite Spirit Sculpture No change in status. The sculpture was installed on February 9, 2018 and the bronze plaques were attached to the pedestals on March 7, 2018. Mulch was placed around the sculpture on March 19, 2018. This project is in the close-out phase. $18,050 12

YEAR FIVE PROP 39 PROJECTS, SANTIAGO CANYON COLLEGE, DIGITAL MEDIA CENTER, ORANGE COUNTY SHERIFF S REGIONAL TRAINING ACADEMY Project Summary: LED lighting conversion at Santa Ana College, Santiago Canyon College, Digital Media Center and Orange County Sheriff s Regional Training Academy. Current Status: No change in status. Contract preconstruction has started and coordination with the colleges has begun. Construction is anticipated to start at SCC in June 2018 and at SAC in July 2018. Budget: $993,328 13

CURRENT PROJECTS DISTRICT-WIDE PROJECT STATUS ESTIMATED BUDGET Emergency Door Lockdown Campus Safety has been providing training and deployed the various lockdown devices. Going forward other devices may be acquired but the training will remain consistent. Facilities will continue to support Safety and Security with respect to other lockdown device options. The District s Working Group on this project started with the objective to provide an interim lockdown device based on compliance guidelines with SB 211 where there are classrooms or locations that have occupancies of 5 or more persons. There are certain doors that do not fit a lock down device and would need more significant work and assessment. This is why there is an RFP process concurrently underway to address a long term solution due to secondary impacts related to lockdown capability associated with hardware and potential for access control (electrified or not) systems. $16,000 14

CURRENT PROJECTS DISTRICT-WIDE PROJECT STATUS ESTIMATED BUDGET District-Wide Access Control & Door Hardware Based on the responses received for the Door Access Control RFQ/RFP, the District has requested supplemental pricing to add a complete door and door hardware assessment to the scope of work for the RFQ/RFP. The screening panel has completed their review and a recommendation for a consultant contract is being prepared for the Board of Trustees at an upcoming June meeting. $62,800 District-Wide Emergency Blue Phone & ADA Path of Travel (SAC, SCC, CEC, DO, OCSRTA, DMC) No change in status. There is ongoing review regarding the 46 blue phones to be installed and therefore the development of contract documents is on-going. Staff continues working with the Purchasing department on the procurement of phones. The architect is working on coordinating drawing and project scope with the concrete/asphalt work throughout the District on different projects to minimize the impact to the campuses. The architect anticipates completing this coordination work in April and then preparing to advertise for bidding of the project thereafter. $1.9 Million 15

EMERGENCY BLUE PHONE LOCATIONS MAP 16

QUESTIONS 17