FINANCIAL ANALYSIS. 1. Introduction and Methodology

Similar documents
FINANCIAL ANALYSIS. A. Kathmandu Upatyaka Khanepani Limited

FINANCIAL ANALYSIS. Table 1: Project Outputs Output Subcomponents Type of Analysis Enshi Wastewater Enshi Hongmiao WWTP Enshi Dashaba WWTP

ECONOMIC ANALYSIS. A. Introduction and Macroeconomic Context

FINANCIAL ANALYSIS. A. Introduction

FINANCIAL ANALYSIS. A. Background

FINANCIAL ANALYSIS. Second Greater Mekong Subregion Tourism Infrastructure for Inclusive Growth Project (RRP REG 49387)

FINANCIAL ANALYSIS. A. Financial Capacity Assessment of MWSS

ECONOMIC AND FINANCIAL ANALYSIS

FINANCIAL ANALYSIS: PROJECT 1

FINANCIAL ANALYSIS OF TRANCHE 1

South Asia Subregional Economic Cooperation Power System Expansion Project (RRP NEP 44219) FINANCIAL ANALYSIS

ECONOMIC ANALYSIS. Table 1: Total Cost Estimate (Economic Costs) (CNY million)

ECONOMIC AND FINANCIAL ANALYSIS

FINANCIAL ANALYSIS A. Introduction

FINANCIAL ANALYSIS. 2. Taking into account the financial costs, the total amount needed to finance the Padma Bridge Project is presented in Table 1.

FINANCIAL ANALYSIS. 3. Assumptions. The following assumptions were used in carrying out the financial analysis:

ECONOMIC AND FINANCIAL ANALYSIS

FINANCIAL ANALYSIS. A. Introduction

Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS. A. Introduction

ECONOMIC AND FINANCIAL ANALYSIS

Karnataka Integrated Urban Water Management Investment Program (RRP IND 43253) ECONOMIC ANALYSIS

FINANCIAL ANALYSIS. A. Methodology and Assumptions

ECONOMIC AND FINANCIAL ANALYSIS

FINANCIAL ANALYSIS. A. Introduction

FINANCIAL ANALYSIS. A. Introduction

Planning & Economic Analysis I

ASIAN DEVELOPMENT BANK PPA: PRC 25013

ECONOMIC AND FINANCIAL ANALYSIS

FINANCIAL ANALYSIS OF THE WATER SUPPLY AND SEWERAGE AUTHORITY OF ULAANBAATAR CITY

FINANCIAL ANALYSIS. A. Methodology and Major Assumptions

PREFERRED FINANCIAL PLAN SCENARIO & WATER RATE DESIGN ALTERNATIVE

Completion Report. Project Number: Loan Number: 1472 August Philippines: Small Towns Water Supply Sector Project

FINANCIAL ANALYSIS. A. Introduction

NWC Tariff Submission for the Period January 2019 to December Submission to the Office of Utilities Regulation (OUR)

India: Karnataka Urban Development and Coastal Environmental Management Project

INCENTIVES & TARGETS KEY FEATURES OF SUCCESSFUL OPERATING CONTRACTS

Report and Recommendation of the President to the Board of Directors

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

ECONOMIC AND FINANCIAL ANALYSES FOR TRANCHE 2

ASIAN DEVELOPMENT BANK

Validation Report. India: North Karnataka Urban Sector Investment Program, Tranche 1. Independent Evaluation Department

Wastewater Rate Study. Villa Park, Illinois

KEY QUESTIONS FOR CONSULTANTS ECONOMIC ANALYSIS OF PROJECTS. Project Economic Evaluation Division Economics and Development Resource Center

New Development Bank. Policy on Financial Management and Financial Analysis, and Economic Analysis of Projects

Philippines: Mindanao Basic Urban Services Sector Project

FINANCIAL ANALYSIS. For this report, common equity refers to the PKSF s capital fund as reported in its annual report. 4

Draft Design and Monitoring Framework

Bangladesh: Urban Governance and Infrastructure Improvement (Sector) Project

ECONOMIC ANALYSIS. A. Economic Analysis

TOWN OF ORO VALLEY WATER UTILITY COMMISSION WATER RATES ANALYSIS REPORT OCTOBER 7, 2009

ECONOMIC ANALYSIS. Table 1: Economic costs by project component

Report and Recommendation of the President to the Board of Directors

The San Jose Del Monte Water Supply Expansion Project

ASIAN DEVELOPMENT BANK

Trung Son Hydropower Project. Financial Analysis

ECONOMIC AND FINANCIAL ANALYSIS

Periodic Financing Request Report. India: Karnataka Integrated Urban Water Management Investment Program (Tranche 2)

ECONOMIC ANALYSIS. A. Introduction

Town of Perth Water Ontario Regulation 453/07 Financial Plan. Financial Plan #

Independent Electricity System Operator Statement of Financial Position Unaudited

Section 3.07 is deleted and the following is substituted therefor:

150. PROFILE ON THE PRODUCTION OF AC MOTORS

116. PROFILE ON THE PRODUCTION OF CHIP BOARD

PUBLIC UTILITIES BOARD OF MANITOBA. For use by utilities in preparing submissions for approval of Water and Sewer Rates.

Pricing and cost recovery of urban services: issues in the context of decentralized urban governance in India

CITY OF WATERLOO Water & Sanitary Sewer Rate Design Study Final Report & Financial Plan No

V. Consolidated Financial Statements and Key Notes on Financial Statements (1) Consolidated Balance Sheet

ECONOMIC AND FINANCIAL ANALYSIS

FUNDING & RESERVES POLICY

Capital Region Water. Water and Wastewater Rate Study Report. November 22, Capital Region Water Water and Wastewater Rate Study

Summary of fiscal principles, practices and policies

Republic of Azerbaijan: Water Supply and Sanitation Investment Program Tranche 4

Periodic Financing Request Report. India: Kolkata Environmental Improvement Investment Program (Tranche 2)

City of Cornwall Water and Wastewater Ontario Regulation 453/07 Financial Plans. Financial Plan #

Enercare Inc. Condensed Interim Consolidated Financial Statements. For the three and six months ended June 30, 2018 and June 30, 2017

La Cañada Irrigation District

ES.1 Findings and Recommendations... ES Overview Current Rates Rate Making Objectives

Bangladesh: Second Urban Governance and Infrastructure Improvement (Sector) Project

(A CALIFORNIA NONPROFIT CORPORATION) FINANCIAL STATEMENTS AND INDEPENDENT AUDITORS REPORT

Project Completion Report

EX26.2. Financial Sustainability of Toronto Community Housing Corporation Prepared for the City of Toronto. Appendix 4. Summary Report.

From: Lex Warmath and Elaine Conti, Raftelis Financial Consultants, Inc.

Kyrgyz Republic: Emergency Assistance for Recovery and Reconstruction

PROJECT PREPARATORY TECHNICAL ASSISTANCE

Preiss-Steele Place Housing, Inc. Annual Financial Report

SCIENCE FOR DEVELOPMENT

RATE STUDY. Town of Midland. HEMSON C o n s u l t i n g L t d.

City and Borough of Juneau, AK WATER UTILITY AND WASTEWATER UTILITY RATE STUDY

M A N I T O B A ) Order No. 136/11 ) THE PUBLIC UTILITIES BOARD ACT ) October 6, 2011

Honolulu High-Capacity Transit Corridor Project Alternatives Analysis

Economics Training Series Introductory Course. Benefit Estimation

Cambodia: Second Power Transmission and Distribution Project

FINANCIAL ANALYSIS. A. Financial Analysis

YORK COUNTY, SOUTH CAROLINA

REPORT ACCOMPANYING THE SECOND AMENDMENT TO THE RIVER DISTRICT URBAN RENEWAL PLAN

Biennial Budget Section II: Process/Policies

City of Norco WATER AND SEWER RATES Frequently Asked Questions

STAFF REPORT. ITEM NO. 1 MEETING DATE: September 27, 2018 MEETING: Board of Directors / Finance Committee SUBJECT:

2016 WCGFOA Conference

Study Workshops are designed to be both educational and to seek broad direction from the Board

Transcription:

Third Urban Governance and Infrastructure Improvement (Sector) Project (RRP BAN 39295) 1. Introduction and Methodology FINANCIAL ANALYSIS 1. The project finances basic urban services improvements and aims to improve the capacity of pourashavas (municipalities) for sustainable administrative and financial management in accordance with the Local Government (Pourashava) Act, 2009. Thirty pourashavas will receive finance under the project, and will receive investments in three phases. The total project amount is estimated to be $236 million, and the implementation period is 6 years. This financial analysis appraises the financial sustainability and viability of the subproject investments for three sample pourashavas Lalmonirhat, Magura, and Naogaon. The financial analysis was prepared in accordance with the Asian Development Bank (ADB) Financial Management and Analysis of Projects. 1 2. Financial sustainability and viability analysis of subprojects assesses the capacity of each pourashava to meet future costs including capital expenditures, operation and maintenance (O&M) costs, debt service, and provision for uncollectable debt. A financial discounted cash flow analysis was conducted in real terms to determine the weighted average cost of capital (WACC), financial internal rate of return (FIRR) for revenue-generating subprojects, and financial net present value (where applicable) to assess the financial viability of each subproject and incremental tariffs required. For non-revenue-generating subprojects, the financial analysis focused on the pourashavas financial capacity to meet recurrent costs. Financial projections for sample pourashavas were conducted to assess their overall financial capacity to sustain and provide urban services and provide for incremental costs associated with project investments. 2. Discounted Cash Flow Analysis and Subproject Viability 3. The discounted cash flow analysis was conducted on a with- and without-project basis by estimating incremental costs and revenues over a 20-year period. Subproject capital and O&M costs were derived from the engineers estimates, including (i) capital expenditures under the project including physical contingencies and tax and duties, (ii) O&M expenditures, and (iii) additional capital expenditures to repair and rehabilitate the assets developed under the project. The FIRR is then compared to the WACC and is computed in real terms over a 20-year period, including all capital and operating cash flow and physical but not price contingencies. 2 4. The WACC calculation considers various funding sources and their relending terms between the government and pourashavas. Although ADB loan terms are lower, the relending rate from the government to pourashavas is expected to be 6%. The loan grant ratio of the pourashavas is expected to be 15:85. The equity return rate is considered at the 13% that is currently given on bonds issued by the government. A domestic inflation rate of 7.2% 3 is assumed to convert nominal rates into real rates. The WACC is computed for the project to be 4.6% in real terms (Table 1). 1 ADB. 2005. Financial Management and Analysis of Projects. Manila. 2 Interest and other financing charges during construction are excluded from the costs. 3 Consumer price index inflation is used as the domestic cost escalation factor in Bangladesh.

2 Table 1: Weighted Average Cost of Capital Calculation for Pourashavas (Municipalities) Financing Arrangements (%) Item Equity Debt Weightage 85.00 15.00 Nominal rate 13.00 6.00 Tax rate (no tax implication for 0.00 0.00 pourashava) Tax adjusted rate 13.00 6.00 Inflation 7.20 7.20 Real cost 5.41 (1.12) Weighted component 4.60 0.00 WACC 4.60 ( ) = negative, ADB = Asian Development Bank, WACC = weighted average cost of capital. Source: ADB Estimates 3. Direct Revenue-Generating Components 5. The following are the project assumptions: (i) The value of benefits arising from water sales was calculated by multiplying the volume of water sold each year by the proposed tariffs used for each year in constant prices. The revenues and receipts for other revenue-generating components are conservatively estimated at the rates prevailing in the respective towns. (ii) Water losses, or nonrevenue water, in the project pourashavas are identified to be 35% 40% in the without-project situation and are projected to gradually reduce to 20% by 2030 with the project. (iii) The implementation period of the project is 6 years (2014 2020). Phase-wise implementation is planned, with the first phase of 18 months, second phase of 30 months, and third phase of 24 months. The implementation period for the water supply component is 48 months; for other components it is 24 30 months. The year-wise project implementation for revenue-generating components is assumed as 20%, 30%, 30%, and 20% for water; and 30%, 40%, and 30% for others if in the second phase or 40% and 60% if in the third phase. (iv) Collection efficiency has been assumed to be 95% of current demand and 85% of arrears demand. 6. Water supply system. The financial analysis of water supply subprojects assumes that 26% of the population of Lalmonirhat, 35% of the population of Magura, and 37% of the population of Naogaon are presently served and connected to the system. It is projected that by 2030, 90% of the population of Lalmonirhat and Magura and 95% of the population of Naogaon will be served and connected to the system. Revenue projections are based on the proposed volumetric water tariff, water demand and consumption, 4 number of connections, continual nonrevenue water reduction, and the collection efficiency mentioned above. A tariff revision is proposed to recover full O&M costs, debt service, and a provision for uncollectible debt for water supply systems. This tariff proposal includes (i) determining effective water tariffs per cubic meter under existing fixed rate tariffs for calculating revenue until introduction of metered volumetric tariffs; (ii) introducing volumetric tariffs in all towns; (iii) setting initial volumetric tariffs for all towns; and (iv) a gradual tariff increase in subsequent years to cover O&M costs, 4 Water demand has been projected on the basis of population projection of the respective towns.

3 replacement costs, and debt service. Based on these assumptions, the proposed tariff structure estimated for three sample towns is shown in Table 2. Table 2: Proposed Estimated Water Tariff Structure for Sample Pourashavas (Municipalities) Water Tariff per Cubic Meter (Tk) Lalmonirhat Magura Naogaon Proposed Water Tariff in Nominal Terms Domestic Other Domestic Other Domestic Other Effective rate under existing fixed tariff 8.00 10.00 7.50 10.00 7.00 10.00 From the year of completion of investment 12.00 15.00 10.50 13.00 10.00 13.00 From the 5th year of completion of investment 15.00 18.00 12.50 16.00 13.00 16.00 20% increase at 5-year intervals (FY2029 18.00 21.00 15.00 19.00 15.00 18.00 FY2030) FY = financial year. Source: Asian Development Bank Estimates 7. Affordability of proposed water tariff. It is estimated that, with the proposed volumetric tariff, the average domestic monthly water bill 5 for a household would be Tk195 for Lalmonirhat, Tk170 for Magura, and Tk162 for Naogaon, which is about 3% of the average household income of the poorest 10% of the population. Therefore, this is considered affordable even for the poor. The socioeconomic survey also revealed that they showed willingness to pay more than the estimated bill amount for uninterrupted supply of good potable water. 8. The base O&M costs for water supply are estimated by engineers considering full recovery of O&M costs. The FIRR of water supply subprojects is 4.98% in Lalmonirhat, 6.75% in Magura, and 4.67% in Naogaon. 9. Market development and community centers. It is projected that the market and community halls fetch one-time possession money and monthly rentals. The rates of one-time fee and rent vary from town to town with the location of the markets, and are conservatively estimated. The increase in monthly rent is projected at 10% with 3-year intervals. The base O&M costs are estimated by engineers considering full recovery of costs. 10. Bus truck terminal. The financial analysis of the bus truck terminal covers facilities available in the terminal such as rentals from ticket counters, shops, public toilets, and parking fees from vehicles. The number of vehicles that will use the terminal per day has conservatively been estimated on the basis of available information. For calculating parking fees, 300 days are considered per year. In all cases the increase in rent and fees is projected at 2% per annum. The base O&M costs for the bus truck terminal are estimated by engineers considering full recovery of costs. 11. Consolidated analysis. Based on the above parameters and assumptions, the FIRRs of the respective direct revenue-generating subprojects have been calculated. The project O&M costs and debt service are fully recovered as per the projections for the three sample pourashavas. Sensitivity analysis shows that FIRRs are generally robust but most sensitive to revenue and costs fluctuation. The analysis also shows that the subprojects are financially viable and sustainable as the revenue account will be in surplus for the years of analysis. 5 Monthly water bill based on 80 liters per capita per day consumption.

4 12. Taking all income-generating components into account, a consolidated FIRR combining the three pourashavas as well as a combined FIRR for each pourashava has been calculated (Table 3). Table 3: Consolidated and Individual Financial Internal Rate of Return of Three Sample Pourashavas (Municipalities) Sl. No. Level of FIRR Consolidated for 3 Towns FIRR in Percentage Combined Lalmonirhat Magura Naogaon 1 Base case 5.06 4.76 5.41 5.00 2 Sensitivity: Cost increase by 10% 2.17 2.33 2.72 1.68 3 Sensitivity: Benefits decrease by 10% 1.86 2.07 2.43 1.32 4 Sensitivity: Cost benefit increasedecrease (1.20) (0.42) (0.41) (2.31) by 10% 5 Cost Benefit Ratio 1.02 1.01 1.03 1.01 ( ) = negative, FIRR = financial internal rate of return. Source: Asian Development Bank estimates. 13. Financial projections. The projections for the sample pourashavas demonstrate that the pourashavas from their operating surplus can sustain the non-revenue-generating components by maintaining the assets, paying arrears, providing the improved services, and meeting the debt service payment obligations to the government. Table 4 shows a summary of the projections for Magura pourashava. Financial projection statements for the remaining sample towns indicate similar trends.

5 Table 4: Summary of the Financial Projections for Magura Pourashava (Municipality) (Tk million) Actual Projection Head of Accounts 2012 2013 2013 2014 2014 2015 2019 2020 2024 2025 2029 2030 2034 2035 2039 2040 2040 2041 Own-Source Revenue Income Collection of holding tax 13.757 17.666 18.675 20.826 26.710 35.960 48.412 65.178 67.450 Collection of fees and property 27.437 27.270 28.600 36.305 46.118 58.620 74.550 94.855 99.542 income Income from income-generating 0 0 0 12.249 13.802 15.289 17.179 19.414 19.700 components of the project Water supply 5.125 6.802 9.381 24.838 39.311 56.607 64.618 75.629 76.120 Total Own-Source Income 46.319 51.739 56.656 94.219 125.941 166.475 204.760 255.075 262.812 Revenue grants from government 0.216 0.210 0.214 0.236 0.261 0.288 0.318 0.351 0.358 and others Total Revenue Income 46.535 51.949 56.870 94.455 126.202 166.763 205.078 255.426 263.170 Expenditure General establishment expenses 38.091 42.060 47.836 54.123 67.067 83.379 103.968 129.991 135.941 Repairs and maintenance of 2.506 3.000 3.150 4.020 5.131 6.549 8.358 10.667 11.200 infrastructure O&M of Infrastructure components 0 0 0 6.467 19.580 26.826 36.754 50.356 53.629 under the project O&M of income-generating 0 0 0 2.653 3.635 4.980 6.823 9.349 9.956 components under the project Water supply O&M costs 5.560 6.900 9.876 13.531 18.539 25.400 34.800 47.678 50.777 Total Operating Expenses 46.157 51.960 60.862 80.794 113.951 147.133 190.703 248.041 261.505 Repayment of Loan (Debt service) 0 0.520 0.500 0 2.090 1.731 1.373 0 0 Total Expenses including Debt 46.157 52.480 61.362 80.794 116.041 148.865 192.076 248.041 261.505 Service Payment Revenue Cash Surplus / (Deficit) 0.378 (0.531) (4.492) 13.661 10.161 17.898 13.002 7.385 1.665 Cumulative Cash Balance 0.378 (0.153) (4.645) 16.776 50.884 98.468 47.979 159.713 161.378 Operating Ratio 99% 101% 108% 86% 92% 89% 94% 97% 99% O&M = operation and maintenance. Assumptions (i) Arrears of electricity dues up to June 2013 considered to be repaid in 3 years from 2014 2015; (ii) Debt service from other loans have been included; (iii) holding tax assumed to increase by 2% on interim assessment and changes in properties and overall demand will increase by 25% at 5-year intervals; and (iv) nontax revenue and other O&M increase at 5% per annum, other income and expenditure by 2%. Source: Asian Development Bank estimates.