Contents. Minutes of the 32 nd Meeting of SRPC held on Page 1

Size: px
Start display at page:

Download "Contents. Minutes of the 32 nd Meeting of SRPC held on Page 1"

Transcription

1 Contents 1. INTRODUCTION CONFIRMATION OF THE MINUTES OF 31 st MEETING OF SRPC OPERATION OF HYDRO POWER PROJECTS IN PEAKING MODE MEMBERSHIP TO RPC PREPARATION FOR MEETING REVISED ENVIRONMENT NORMS AS PER ENVIRONMENT (PROTECTION) AMENDMENT RULES, RELIABLE COMMUNICATION SCHEME UNDER CENTRAL SECTOR FOR SOUTHERN REGION TECHNICAL COMMITTEE FOR IMPLEMENTATION OF FRAMEWORK ON RENEWABLE AT STATE LEVEL TECHNICAL COMMITTEE CONSTITUTED BY CEA OPTIMUM HARNESSING OF RE IN SOUTHERN REGION COMPLIANCE OF CEA REGULATIONS FOR GRID CONNECTIVITY OF RENEWABLE ENERGY SOURCES TERMS OF REFERENCE FOR RENEWABLE INTEGRATION TASK FORCE UPCOMING TRANSMISSION SYSTEM UPCOMING RENEWABLE PROJECTS AND THEIR INTEGRATION WITH TRANSMISSION NETWORK REQUEST TO ISSUE CERTIFICATE FOR CLAIMING ADDITIONAL ROE NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE & UMPP NEW PROJECTS OF STATE SECTOR & IPP ROADMAP TO OPERATIONALISE RESERVES IN THE COUNTRY INCLUSION OF DRAWAL OF MAHE IN REA ISSUES IN RESPECT OF NPCIL COMMUNICATION REQUIREMENT DURING NATURAL DISASTERS STATUS OF GENERATION IN ISGS REVIEW OF ULDC / SCADA/COMMUNICATION URTDSM (PMU) PROJECT IN SOUTHERN REGION SCHEDULING OF WIND & SOLAR GENERATING PROJECTS HAVING CAPACITY OF 500 MW AND ABOVE TTC/ATC METHODOLOGY FOR CERTIFICATION OF INTRA-STATE TRANSMISSION LINE EMERGENCY RESTORATION SYSTEM (ERS) PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR OUTSTANDING DUES BETWEEN SOUTHERN AND WESTERN REGIONS NON-AVAILING OF OCC APPROVED SHUTDOWN STATUS OF PHASE I AND PHASE II OF PROTECTION AUDIT RECOMMENDATIONS SPARE ICT AND REACTOR PLACEMENT AND USAGE PROCEDURE IEGC RELATED ISSUES REQUIRING ATTENTION/ACTION Minutes of the 32 nd Meeting of SRPC held on Page 1

2 34. IMPLEMENTATION OF PROTECTION SUITE / PROTECTION MANAGEMENT SYSTEM (PMS) FOR SR POWER SYSTEM ANALYSIS GROUP (PSAG-18) MEETING HELD ON 4 TH JULY, 2076 AT 400/ 220/ 66 KV HOODY SUBSTATION OF KPTCL IN THE CONTEXT OF FREQUENT TRIPPING OF 400/ 220 KV ICT S PROTECTION AUDIT OF SUBSTATIONS IN SR CONDUCTED DURING MARCH AUGUST, AUTO-RECLOSURE IMPLEMENTATION ON ALL 220 KV & ABOVE TRANSMISSION LINES OF SR IMPLEMENTATION OF LINE DIFFERENTIAL PROTECTION (LDP) IN NELLORE & SIMHADIRI COMPLEXES PATROLLING / MAINTENANCE OF CRITICAL LINES AND SUBSTATIONS COMPLIANCE OF ORDER OF HON BLE CERC IN PETITION NO. 420/MP/2014 IN RESPECT OF LVRT AND OTHER PROVISIONS OF CEA/CERC REGULATIONS PENDING IMPLEMENTATION OF RECOMMENDATIONS OF PCSC OF SRPC COMMERCIAL COMMITTEE ISSUES MONITORING OF SCHEMES FUNDED FROM PSDF SCHEDULING OF KAMUTHI SOLAR PARK AUGMENTATION OF TALCHER-II TRANSMISSION SYSTEM GRID OPERATION CONGESTION RELATED ISSUES REIMBURSEMENT OF SRPC EXPENDITURE STATE-WISE ALLOCATION OF 540 MW POWER FROM RGPPL TO RAILWAYS ADVANCE INTIMATION REGARDING FIRST TIME SYNCHRONIZATION OF TRANSMISSION ELEMENTS FREQUENT FAILURES OF TRANSMISSION LINE TOWER OF VOLTAGE LEVEL 220 KV & ABOVE IMPLEMENTATION OF CERC (COMMUNICATION SYSTEM FOR INTER-STATE TRANSMISSION OF ELECTRICITY) REGULATIONS, OVR GRADING OF 400 KV AND 765 KV TRANSMISSION LINES OF SOUTHERN REGION APPRAISAL REPORT ON KSEBL S REVISED PSDF PROPOSAL STUDY PROGRAMME ON THE INTEGRATION OF RENEWABLE ENERGY RESOURCES INTO THE GRID NON-ADHERENCE TO THE MAINTENANCE SCHEDULE - OVERHAULING OF TALCHER STAGE II U OUTSTANDING DUES FROM TSDISCOMS TO APGENCO URS ALLOCATION TO NON-BENEFICIARY CONCLUSION DATE & VENUE OF THE NEXT MEETING OF SRPC Minutes of the 32 nd Meeting of SRPC held on Page 2

3 1. INTRODUCTION SOUTHERN REGIONAL POWER COMMITTEE BENGALURU MINUTES OF THE 32 nd MEETING OF SRPC HELD ON AT THIRUVANANTHAPURAM 1.1 The 32 nd Meeting of the Southern Regional Power Committee (SRPC) was held on 22 nd August 2017 at Thiruvananthapuram. The list of participants is given at Annexure-I. 1.2 Team KSEBL welcomed the respected dignitaries to the 32 nd SRPC Meeting being held at Kovalam, Thiruvananthapuram, also known as Paradise of South India. 1.3 Dr K Ellangovan, CMD, KSEBL welcomed Chairperson, SRPC, Member Secretary, SRPC and distinguished delegates to the 32 nd Meeting of SRPC. He noted that the TCC Meeting had been well attended and the deliberations had been fruitful. The delegates of the TCC would acknowledge that the Meeting had been very useful in sorting out various issues of significance between member states. He stated that it was a pleasure to host this Meeting with all Members kindly accepting to come to Thiruvananthapuram. This Meeting would be discussing some vital issues which are now being faced. It was the view of KSEBL that SRPC Meetings have been extremely beneficial to place ones views on the table, so that the same get acknowledged not only in SRPC but at the highest level. SRPC has been very useful to the State of Kerala being tucked away from other states in respect of geographical location. CMD, KSEBL acknowledged the contribution of SRPC in various matters. He welcomed Shri D Prabhakar Rao, Chairperson, SRPC and stated that he has been very active, keen and methodical. He was certain that SRPC under his able Chairmanship would find solutions to some of the difficult problems being faced by the SR power sector. He welcomed the Members who had joined for the SRPC meeting - Shri Jawaid Akhtar, MD, KPTCL, Shri G Kumar Naik, MD, KPCL, Shri K Vijayanand, CMD, APTRANSCO, Shri A Gopal Rao, CMD, TSTNPDCL, Shri U K Verma, ED, NLDC, Shri V Thangapandian, Director (P), NLC and Shri R K Singh, ED (SR-II), PGCIL. This Meeting was also being attended by several important functionaries of Government, State Government, other utilities etc. He thanked his entire team for their wonderful efforts in organizing this Meeting. He hoped that all current issues would be deliberated and wished fruitful deliberations. 1.4 Shri S R Bhat, Member Secretary, SRPC welcomed all the esteemed Members to the 32 nd SRPC Meeting. He welcomed Chairperson, SRPC & CMD, TSTRANSCO to the Meeting and requested him to kindly chair the same. He also thanked CMD, KSEBL and the entire team for the outstanding arrangement made for both the Meetings. 1.5 Shri D Prabhakar Rao, Chairperson, SRPC & CMD, TSTRANSCO extended a warm greeting to all attending the 32 nd SRPC Meeting. He added that the 30 th TCC and 31 st SRPC Meetings were Minutes of the 32 nd Meeting of SRPC held on Page 3

4 conducted on and at Bengaluru and Minutes were communicated by MS, SRPC on and respectively. Southern Region has been in the forefront in maintaining grid discipline and always takes lead in implementing CERC/CEA/MoP guidelines. Main challenge confronted by SR is regarding handling of Renewable Energy. SR was leading in RE front with a target of 60 GW by 2022 as against all India target of 175 GW. It was heartening to note that SR had already achieved 22 GW of RE. To address this issue, a Special Meeting of SRPC was conducted at Hyderabad on , wherein it had been agreed in principle to go ahead with the Overarching Agreement among Southern States for mutual exchange of power for better harnessing of RE to minimize the balancing resources. Further, a Working Level Committee had been formed to work out the modalities. Accordingly, the issue of cooperation among Southern States was further discussed during the Working Level Committee Meeting through VC on and a few modifications had been incorporated in the Agreement. Finally, the Overarching Agreement for regional cooperation for better harnessing of RE without endangering the grid security had been concluded. He placed on record appreciation for concluding this outstanding concept by SR entities for harnessing maximum RE with least cost, which had also been appreciated by CEA and MoP. He added that it was time to address the Regulator to reduce clearing time for power exchange market transactions to 4 time blocks. This would help in quicker exchange of power since presently time for transacting power through exchange was around 3 hours. Another challenging issue to be stressed was readiness of downstream network by SR states to match the interstate transmission system. It was very important that state transmission utilities plan the network well in advance and complete downstream 400 kv and 220 kv sub stations and lines for evacuating the power from the ISTS projects soon after their commissioning. It was also observed that there was under utilization of inter-regional links such as 765 kv Angul-Srikakulam and 400 kv Jeypore-Gazuwaka. All concerned states and CTU should take proactive steps for utilization of inter-regional links for evacuating of bulk power to the maximum extent possible for benefit of all stakeholders. He requested all states and delegates to express their views and opinions on the agenda points which would help take timely decisions for expediting various projects/schemes in the interest of the region. He hoped that Southern Region would continue to take lead role in the country by means of more proactive initiatives for betterment of power sector in future too. On behalf of SRPC, he conveyed sincere thanks to Dr Ellangovan, CMD, Directors and other officials of KSEBL for making excellent arrangements for the Meeting. 1.6 SRPC welcomed the following new Members: Shri H Y Dora, CMD, APSPDCL Shri A Gopala Rao, CMD, TSNPDCL Ms Ruby Srivatsava, Director (F), NPCIL Shri M Prabhagar, CEO, NTPL Minutes of the 32 nd Meeting of SRPC held on Page 4

5 SRPC placed on record the excellent services rendered by following outgoing Members: Shri M M Nayak, CMD, APEPDCL Shri G Raghuma Reddy, CMD, TSSPDCL Shri Preman Dinaraj, Director, NPCIL Shri R Parthasarathy, Head, Bangalore Office, UPCL Shri A R Neelakanta Pillai, CEO, NTPL 1.7 Agenda was taken up for discussion. 2. CONFIRMATION OF THE MINUTES OF 31 st MEETING OF SRPC 2.1 Minutes of the 31 st Meeting of SRPC held on 25 th February 2017 at Bengaluru was circulated vide letter dated 11 th May Minutes of the Meeting were confirmed. 3. OPERATION OF HYDRO POWER PROJECTS IN PEAKING MODE 3.1 POSOCO had carried out operational analysis of various hydro stations in the country. A Report on Operational Analysis for Optimization of Hydro Resources & facilitating Renewable Integration in India was also prepared. It was observed by POSOCO that a number of hydro stations particularly in the state sector are not being operated in peaking mode. MoP had constituted a Sub-Committee under Chairperson, CEA to study and recommend individual hydro power stations which can be operated to achieve peak load capacity. This Sub-Committee had held three Meetings with concerned Hydro generating stations and concluded that there was scope of about 2,000 MW additional power generations from hydro station during peak hours. CEA vide letter dated (Annexure-II) has advised that the above issue be discussed in the TCC/RPC Meeting in all the regions. CEA had also advised that the matter of utilization of hydro stations in peaking mode be made an Agenda Point for discussion in the monthly OCC Meetings while discussing operational planning for the month ahead and analyzing the operation in the previous month. 3.2 POSOCO vide letter dated (Annexure-III) had furnished an agenda item on Operational analysis of Hydro Power Stations. Issue had been discussed in detail in the 134 th Meeting of OCC held at Neyveli on 11 th August 2017 (Summary given as Annexure-IV). TCC deliberations 3.3 The issue had been deliberated in detail in the TCC and the following was summarized: Presentation made by SRLDC/NLDC is given at Annexure-V. It was felt that hydro generation is already being optimized by SLDCs. Feedback of the 134 th Meeting of OCC has been passed on to NLDC for kind consideration. NLDC stated that the feedback of these Meetings would be considered. Suitable Market mechanism/incentive scheme needed to be in place for the purpose of any hydro optimization. Minutes of the 32 nd Meeting of SRPC held on Page 5

6 SRPC deliberations 3.4 MS, SRPC informed that the issue had been deliberated at length in the TCC and the following was noted: Efforts of POSOCO in preparation of the questionnaire and analysis. POSOCO had come out with a nice report which was well appreciated. POSOCO had put in lot of effort, time and energy in preparation of this report. In a nutshell, POSOCO had analyzed peaking, ramping capacity utilization factor and also identified constraints in optimal usage with flexibility based on all India peak demand curve. On various parameters the analysis had been carried out. They had also suggested multipart tariff for hydro stations for better utilization. TSTRANSCO had stated that hydro utilization also depended on irrigation requirements and LGB management of the control area. Dispatch based on national peak, ramp rates etc may be considered only with proper market mechanism in place. Margins are kept to meet RE and load variations. KSEBL had stated that final report had not been shared and SLDC had not been consulted appropriately. Hydro in merit order is considered based on price of the replaced energy in the entire water cycle year and not merely on the basis of the cost. Hydro generation was also being modulated based on power exchange rates. TANTRANSCO had stated that this was 2 nd year of poor monsoon and storage was only %. Study based on peak for last one year data could not be conclusive. 6,000 MW of RE was to be balanced and available hydro was also limited. Operation of hydro in NR/NER cannot be compared with Hydro operation philosophy of SR. KPTCL had stated that hydro was also required for grid security, deviation management, fall in generation due to outages, RE withdrawal and was also based on seasonal requirement. Hydro generation was being maximized during the period January to April since the power rates were higher. APTRANSCO had stated that hydro generation was also based on irrigation and drinking water requirements. It was felt that hydro generation was already being optimized by SLDCs keeping in view specific requirements of the respective control areas. A clear Market Mechanism was required to be introduced which may incentivize hydro support for peaking, ancillary services etc. 3.5 CMD, TSTRANSCO pointed out that water was very precious in various aspects. Water usage was with different objectives in various states. In AP and TS, hydro projects are multipurpose projects. Though hydro generation in TS was designed for around 3,500-4,000 MUs, in there was generation of only 269 MUs. There were several uncertainties and as expressed by the states, hydro generation was already being optimized. Srisailam LB was being utilized for condenser mode, pump mode besides generation. Final decision of operating hydro should be left with the concerned States where projects are located. 3.6 ED, NLDC stated that the views of the forum are well acknowledged and hydro generation in SR was being optimized. Only requirement of NLDC was that keeping in view daily allocated quantum of energy for hydro, considering all constraints (agricultural/drinking) support could be Minutes of the 32 nd Meeting of SRPC held on Page 6

7 extended to meet peak and balance could be utilized to meet other requirements. All SR states were purchasing power through exchange. Price of power during peak was higher, and thus it made economic sense to utilize higher hydro during peak hours. Price of power was generally following the load curve, it was up to Rs 7-8 during peak and going below Rs 2 during off peak hours. All over the world similar market has evolved where peak rates are higher than off peak rates. This would contribute to economic benefits by means of saving for the states. 3.7 CMD, APTRANSCO noted that in respect of SR states, the presence of renewable was quite significant. Historically, hydro was being utilized to meet the peak while other generation such as Thermal, Solar etc was being utilized during day. Hydro optimization may not be required to be revisited for any further refinement. 3.8 ED, NLDC informed that out of 150 hydro stations (equivalent to 32 GW which is around 80 % of the total population) it was found out that there were only 43 stations where peaking optimization was required. In SR, there were around 18 stations and in these stations the generation pattern could be studied and further peaking support could be extended. 3.9 MS, SRPC stated that the suggestion appeared to be for all India peaking support while each state was an individual control area as per Grid Code. There would be reasons for specific hydro generation pattern through the day. Since hydro generation was also based on storage content, average values may not work out. Based on storage, market, RE variability, load variability, irrigation requirements etc the hydro optimization is being carried out CMD, KSEBL opined that the consultation process by POSOCO with states was not as much as it should have been. He was personally not aware of this study. Kerala s load curve was different from that of other states. KSEBL had optimized hydro power in such a manner that the cost of the overall power gets optimized. Dams were not only for hydro generation, but were also being utilized for irrigation and drinking water requirements. As noted in the Assembly, drinking water requirement was of major concern followed by that of power. The compulsions for water utilization were different from state to state. Kerala s hydro was being utilized during peak beside the must run hydro during the day. Further optimization may not be possible. State wise hydro optimization within the control area constraints was a better approach rather than painting an all India picture. POSOCO had earlier brought out analysis of demand, load curve etc for 8 years which was Volume-1. Subsequently, state specific analysis was carried out which was Volume-2 and similar approach needed to be adopted now. In the State related chapters, critical appraisal needs to be carried out MS, SRPC stated that critical state-wise analysis may bring out the real optimization. Further, in NR & NER, many of the hydro units were central sector units, while in SR all were state owned ED, NLDC stated that unit wise analysis has already been carried out and only after detailed study 43 stations had been identified. Ancillary services market for hydro was under consideration and Minutes of the 32 nd Meeting of SRPC held on Page 7

8 they had already moved the matter before Hon ble CERC. Tariff design may need to be looked into by SERCs in line with that for central hydro units MD, KPTCL stated that the crux of the issue has already been highlighted by SRPC. For the POSOCO report, a lot of statistics had been collected. But it was quite apparent that there was no detailed discussion and interaction with state utilities during finalization of the report. The report might have assumed, as evident from the deliberations the present scenario and it might not have considered requirement of the state vis-à-vis target of 175 GW of RE by Like TN, Karnataka also may find it difficult to manage the RE. In Karnataka, reserves had been declining since last three years - from 55% to 44% while this year it was at 41%. The optimization in totality could only be appreciated through extensive interactions with SLDC on a day-to-day basis. With this target it would be rather difficult to manage the grid/re in the next 2-3 years. States may not have necessary resources and thus GoI may need to step in and create a scheme at national level. POSOCO should have comprehensively discussed this matter with states before finalizing the report. The resources belonged to the states and were to be utilized by them, in tune with the federal structure MS, SRPC informed that a Committee headed by Member (Planning), CEA had been constituted by MoP and the Committee was already looking into various issues. Region wise/ joint meetings had been conducted and they are in process of finalizing the Report. Issues relating to Balancing requirement, ramps etc had been covered in the Report ED, NLDC stated that they were open to suggestions and would interact with each state individually. He added that there were three types of reserves- Primary, Secondary and Tertiary. CERC orders specified quantum to be maintained by the state utilities and at the national level. NLDC was considering monitoring of the reserves w r t the stipulated quantity Chairperson, SRPC concluded that it was almost unanimous that the final decision on hydro optimization should be left to the states. As suggested by CMD, KSEBL, state-wise analysis for hydro operation could be carried out by POSOCO in coordination and close consultation with SLDCs. 4. MEMBERSHIP TO RPC 4.1 Withdrawal of Membership from SRPC M/s Lanco Kondapalli Power Ltd (LKPL) vide letter dated (Annexure-VI) had stated that there is no power generation from their plant since last nine months and also no visibility of generating power in the near future under the present circumstances. In light of this, they would be unable to contribute in respect of expenditure of SRPC Secretariat and hence are withdrawing their Membership from SRPC. They would consider availing Membership with SRPC, as and when, their plants become operational. Minutes of the 32 nd Meeting of SRPC held on Page 8

9 TCC deliberations This issue would be deliberated in the SRPC Meeting. SRPC deliberations SRPC agreed for withdrawal of the Membership of LKPL. 4.2 Trader Membership MS, SRPC informed that CEA vide letter dated (Annexure-VII) had communicated the Membership of JSW Power Trading as Trader Representative in SRPC for SRPC deliberations COO (Trading), JSWEL stated that JSW Power Trading had been inducted as trader representative in SRPC for the current financial year. But already half of the financial year was over and the objective of representation was lost. CEA may kindly communicate the Membership in March / April each year so that the concerned Trader is associated with respective RPC for the entire year. Since the Membership was communicated in August they are not willing to accept the Membership for the current year. It was agreed that this issue could be brought to the notice of CEA. 5. PREPARATION FOR MEETING REVISED ENVIRONMENT NORMS AS PER ENVIRONMENT (PROTECTION) AMENDMENT RULES, Revised water consumption and emission norms for existing as well as new thermal units (to be installed from onwards) as per Environment (Protection) Amendment Rules, 2015 were notified by Ministry of Environment, Forest & Climate Change (MOEF & CC) (Gazette Notification dated ). MOEF guidelines had classified thermal generators into three categories with different norms. The three classes were - prior to 31 st December 2003, 1 st Jan 2004 to 31 st December 2016 and beyond 1 st January Existing as well as new plants were required to meet standards by the stipulated time lines. Preparedness and action plan in order to comply with revised norms had been discussed in SRPC as well as Subcommittee Meetings. 5.2 CEA, New Delhi vide letter dated had intimated that a Committee headed by Chairperson, CEA had been constituted by Ministry of Power; Govt. of India for preparing phasing plan for implementation of new environmental norms issued in December 2015 by MOEF &CC with regard to SPM, SOx & NOx emissions. 1 st & 2 nd Meetings of this Committee were conducted on 21 st October 2016 and 13 th December 2016 respectively. Accordingly, a Meeting was conducted on 12 th January 2017 at SRPC, Bengaluru to (Minutes of the Meeting available on SRPC website). 5.3 The following had been noted in earlier Meetings: SRPC had noted the requirements for necessary compliance. deliberate on status and also firm up Phasing Plan. Minutes of the 32 nd Meeting of SRPC held on Page 9

10 Chairperson, SRPC had stated that most likely none of the entities may be in a position to meet time frame for compliance of new environment norms. The issue had been taken up for TN units with GoI, but response had not been very encouraging. Cost of Rs.1 to 1.5 crore per MW to take up the works was quite exorbitant. All entities could therefore suitably take the request for time extension with the concerned Authorities. It was agreed that Chairperson, SRPC may kindly take up the issue with GoI for funding to meet stipulated revised environmental norms. 5.4 Subsequently, CEA had firmed up the FGD phasing plan and uploaded the same on its website. Later, a Meeting to firm up phasing out plan for thermal unit which do not have space for FGD was held on 25 th March 2017 (Minutes available at SRPC website). Updated Plan for FGD implementation with respect to SR Units with confirmation/comments is given at Annexure-VIII. The Phasing Out Plan is given at Annexure-IX. However, confirmation/comments are awaited from most of the generators. 5.5 Chairperson, SRPC vide letter dated 24 th May 2017 (Annexure-X) addressed to Secretary-Power, MoP had brought to kind attention of MoP, the issue regarding funding either from PSDF or any other fund to meet stipulated revised environmental norms. 5.6 The following was noted in the TCC Meeting: APGENCO had informed that a Committee has been formed on FGD assessment etc and the Report would be submitted to the Board shortly. About Rs.1 Crore/MW was estimated expense for FGD and the issue would be reviewed/decided in the next Board Meeting. AP was in discussions with M/s BHEL and its team had also visited the power stations. There were issues with regard to limestone availability and also disposal of gypsum. Phasing out was also to be considered based on the commissioning of new 800 MW units at Krishnapattnam & Vijayawada (both expected in 2019) and overall energy security of the state. TSGENCO had expressed concern over space constraints for FGD installation in some of the plants and over the huge expense to GENCOs and consequent implications on tariff. NLC had informed that they had appointed M/s Mecon as Consultant and measurements had been taken at site. Based on the results, the type of FGD etc would be suggested by Consultant. NLC was seriously pursuing this matter and a decision would be taken after the Consultant s report is made available. Generators had been suggested to keep CEA kindly apprised of developments in this matter. Action was to be initiated to adhere to the FGD Plan and also Phasing Out Plan finalized by CEA/SRPC. After deliberations, TCC had recommended that Chairperson, SRPC may be kindly requested to once again take up the issue of funding (PSDF/any other fund) with Ministry of Power, for meeting the environment norms. SRPC deliberations 5.7 Director (P), NLC informed that the readings had been taken by the Consultant. Though space constraints were there, but the report was awaited. The consultant would be suggesting the way forward and a call would be taken after that. 5.8 MS, SRPC stated that the basic premise of earlier CEA report was based on inputs furnished by Minutes of the 32 nd Meeting of SRPC held on Page 10

11 generators on the space for FGD. Based on inputs furnished by NLC, the units of TS-II had been identified for phasing out. The NLC Report may need to be expedited and CEA was required to be informed accordingly. 5.9 Director (P), NLC stated that the report was expected in about 1-1½ month and the status would thereafter be communicated to CEA CMD, TSTRANSCO stated that the MOEF guideline was to be implemented but the financial support should also be considered. Some support through PSDF or special funds was required from GoI. The impact to meet norms was around Rs 1 crore/mw, it would be burden to the state utility which would have to be passed on to the consumer. Space constraints for FGD in certain cases were also to be considered MD, APGENCO noted that already thermal power was getting costly as could be seen from Kudgi. Further investment to the tune of Rs crore/mw to meet environment norms would be difficult for the State Government. The burden would automatically arise and it would thus be difficult for the generator to be economically viable. A resolution could be passed to request GoI to support the generators in meeting the environment norms. At the time when the plants were designed and constructed, the norms and costing were different and the Regulator had accordingly fixed the costs. Chairperson, SRPC could take up the issue with Secretary, MoP to consider some sort of financial support be it from PSDF, NCEF or any other fund MD, CEPL stated that from IPP point of view also, it was very necessary that some sort of funding was required. The cost would be Rs crore/mw and it could be extremely difficult to pass it on to the tariff Chairperson, SRPC stated that a specific mention of IPP cannot be made and a general appeal to GoI would be made It was agreed that Chairperson, SRPC would take up the issue of financial support through PSDF, NCEF or any other fund for the generators to meet the revised environment norms Generators were kindly suggested to keep CEA apprised of developments with regard to FGD/Phasing Out plan. Appropriate action needs to be initiated as per the FGD/Phasing Out plan finalized by CEA. 6. RELIABLE COMMUNICATION SCHEME UNDER CENTRAL SECTOR FOR SOUTHERN REGION 6.1 POWERGRID vide letter dated 4 th August 2017 (Annexure-XI) had stated that in the 31 st Meeting of SRPC, approval had been accorded for reliable communication scheme of 5,406 kms of OPGW based communication network at an estimated cost of Rs crores. It is now intimated that the estimated cost comes out to Rs crores. However, actual cost shall be discovered only after the bidding process. It had also been intimated that tender activities has been initiated as per DPR. 6.2 SRPC noted the above. Minutes of the 32 nd Meeting of SRPC held on Page 11

12 7. TECHNICAL COMMITTEE FOR IMPLEMENTATION OF FRAMEWORK ON RENEWABLE AT STATE LEVEL -FOR 7.1 FOR vide their communication dated 02 nd May 2017 had informed that a Technical Committee under the Chairmanship of Member, CERC had been formed at the direction of Forum of Regulators (FOR). This Committee comprises of Technical Members of State Commission of renewable rich States, viz. Tamil Nadu, Gujarat, Rajasthan, Maharashtra, Andhra Pradesh, Karnataka and Madhya Pradesh. The objectives of the Committee include facilitating implementation of Regulations for Forecasting, Scheduling and Deviation Settlement at the State level, implementation of ABT framework and Ancillary Services in member States, among others. The Committee in its eleventh Meeting held in Chennai on had felt that with increasing penetration of Renewable Energy (RE) in the backdrop of GoI s 175 GW RE target, increasing inter-state transmission of power and commitment of 24x7 Power to All, regional cooperation for optimum utilization of generation resources had become critical. Further, it had been decided that Sub-Groups be constituted in Northern Region, Western Region and Southern Region (three RE rich regions) headed by the Member Secretaries of the respective Regional Power Committees (RPCs) to examine this issue. This Sub-Group shall inter-alia examine feasibility and modality of cooperation among states in the respective region for ensuring optimum utilization of generation resources with least cost options for balancing across the region. 7.2 Subgroup Meeting of SR under Technical Committee for Implementation of Framework on Renewable at State Level was conducted in SRPC, Bengaluru on 07 th June Recommendations (Annexure-XII) of this Sub Group had been submitted to the Technical Committee. 7.3 TCC deliberations MS, SRPC had informed that the Sub Group had submitted certain recommendations which also included Overarching Agreement for STOA under MCP /Swap, Separate Control Area for RE and Sale of URS through Generator (for firmness) which would be examined by the Committee. Also there was another Meeting held in CERC on 18 th August 2017.There was discussion about another intra-day product through PX, which would not be as rigid as presently available products. 7.4 SRPC noted the above. 8. TECHNICAL COMMITTEE CONSTITUTED BY CEA 8.1 A Technical Committee had been constituted by CEA for study of optimal location of various types of balancing energy sources/energy storage devises to facilitate grid integration of Renewable Energy Sources and associate issues. Subsequently a Meeting of Sub- Group of Southern Region formed under the Technical Committee was conducted on 24 th March 2017 with participation from CEA and the Minutes of the Meeting issued on is at Annexure-XIII. The second Meeting of the Technical Committee was held at Chennai on The final meeting was held at New Delhi on The Minutes of the Meeting are available on website of CEA. Minutes of the 32 nd Meeting of SRPC held on Page 12

13 8.2 TCC deliberations MS, SRPC informed that in the Committee Meeting, a new concept of net DSM had been discussed through which a state may get insulated from vagaries of RE. DSM of the Control Area may be arrived excluding the Deviation of the RE generators. 8.3 SRPC noted the above. 9. OPTIMUM HARNESSING OF RE IN SOUTHERN REGION 9.1 Follow up of MoP meeting / Special TCC A Meeting was held on 10 th February 2017 in MoP on matters relating to optimum harnessing of Renewable Energy Integration in SR without endangering Grid Security. A number of actionable points had been finalized in that Meeting and time lines for compliance of the same also had been specified. SRPC vide letter dated (Annexure-XIV) had requested the concerned utilities that the matter may kindly be arranged to be reviewed and urgent action arranged wherever necessitated. A Special TCC Meeting was also convened on 20 th May 2017 (Minutes at Annexure-XV) in SRPC, Bengaluru SRLDC had conducted a Capacity Building Workshop on STOA Procedures on 19 th May 2017 in compliance. A Special Meeting of SRPC Members of the constituent states was also held on 31 st July 2017 at Hyderabad. Based on the discussions in the Hyderabad Meeting, a draft Overarching Agreement had been prepared and circulated. It had been proposed to sign the Overarching Agreement in SRPC Bengaluru on 17 th August TCC deliberations TANGEDCO vide letter dated (Annexure-XVI) had informed that rate of energy of power to be exchanged as per item no. 7 was not viable to TANGEDCO. SRPC in its reply vide letter dated (Annexure-XVII) had again requested TANGEDCO to kindly sign the Agreement. MS, SRPC had informed that the Overarching Agreement had been signed between APPCC, TSDISCOMs & KSEBL on 17 th August He had thanked the utilities for their kind cooperation in this regard. PCKL had stated that they would communicate their views in the SRPC Meeting. TANGEDCO had stated that they would consider signing the Agreement under Swap with mutually agreed rates for the residual energy. In respect of SAMAST implementation, the following had been noted: APTRANSCO had informed that they had prepared a Report and submitted it to CERC and to NLDC for funding. It was of concern that the amount approved was only about 1/5 th of the estimate. TSTRANSCO had also endorsed the views of APTRANSCO and stated that NLDC should take lead and approve higher funds. They had submitted estimate of Rs 85 crores and in case much lower funds are approved, it may not encourage entities to take up the project in a time bound manner. KPTCL had informed that they were preparing the DPR and they had also deputed a Committee to Gujarat and MP to study their proposals. The DPR would be finalized by end of the month. Minutes of the 32 nd Meeting of SRPC held on Page 13

14 TCC had urged concerned entities to initiate action to complete pending points as noted in the Special TCC Meeting held on Implementation of SAMAST was targeted to be completed by December NLDC was requested to kindly look into the possibility of higher fund approval for the proposals under SAMAST. Demand and RE forecasting / scheduling was also to be undertaken by states on a priority basis. SRPC deliberations MS, SRPC thanked Chairperson, SRPC for his proactive leadership in enabling conclusion of the Overarching Agreement in the Meeting held on Chairperson, SRPC requested KPTCL & TANGEDCO to also sign the Overarching Agreement. In this Agreement there was no commitment on any state. This Agreement could be more advantageous to TN on account of the high RE penetration MD, KPTCL informed that they were ready to sign the Agreement CMD, KSEBL enquired about the mutually agreed rates being requested by TN. He added that KSEBL had been of the view that TN would participate and surplus power would be availed. He requested TN to kindly consider signing the Agreement. Since monsoon was below par, RE potential in the region should be exploited to the maximum. TN could weigh the cost of RE absorption and the likely benefits of trade and take a judicious decision MS, SRPC clarified that the option of mutually agreed rate under swapping was only in respect of residual energy under swap. He suggested that states could kindly use the mechanism for RE Integration and other contingencies and put the system in place. He noted that initially all initiatives were with the premise that TN was having constraints at times, for absorption of RE power in full Director (O), TANTRANSCO informed that within one weeks time they may sign the Agreement. Approval of State Government/ Management was required for this purpose. They would consider signing the agreement under Option 2 (swap) CMD, APTRANSCO stated that TN should also come forward to sign this Agreement, especially since there were no commercial implications NLDC was kindly requested to favorably consider approval of the SAMAST DPRs APTRANSCO informed that while DPR of Rs 57 crores, only Rs 11 crores had been approved. The component relating to metering and CT/PT had not been approved and revised DPR had been requested CMD, TSTRANSCO also raised concern and stated that releases are relatively very less and requested NLDC to look into this aspect favorably ED, NLDC assured that the DPRs under SAMAST would be possibly relooked. For reliable communication the grant has been raised to 50% which was earlier 30%. Many schemes had been approved by Monitoring Committee, but the utilities had not come forward to sign the Agreement MS, SRPC observed that pace of utilization of funds of sanctioned schemes may need acceleration. Minutes of the 32 nd Meeting of SRPC held on Page 14

15 NLDC had been regularly taking review meetings for appraising Ministry. There was a general perception that utilization was not taking place as desired Chief Engineer, NPC stated that utilization was an area of concern. Out of Rs 421 Crores for Kerala only Rs 23 Crores had been availed. For Karnataka out of Rs 17.9 Crores only Rs 8.7 Crores has been availed, Out of Rs 255 Crores for AP, only Rs 11 Crores had been availed while in case of Telangana out of Rs 108 Crores only Rs 24 Crores had been availed. In case of Tamil Nadu out of Rs 304 Crores Rs 12 Crores only had been availed. This had been noted with concern at higher levels. Out of more than Rs 9,000 Crores total sanctioned amount, about Rs. 600 crores only had been utilized so far Director (G&TM), APTRANSCO that project schedule was of two years but they were expediting to complete 1-2 months earlier. The tendering process needed to be followed, and since it included both replacement and new procurement, tendering process was getting delayed. However, within 9-10 months from Zero date all material would be procured. Any nonperformance could only be reviewed at the end of the project that is 2 years. The projects would be however completed within the stipulated time period. 9.2 Assessment of lift irrigation loads and necessary planning for using as demand response In the Sub Committee /Special Meetings, states had been suggested look into optimizing lift irrigation/other pumping schemes existing in their system for Load Generation Management/RE issues/load change over. Running these loads at different times could help in improved load generation management In the Meetings, it had been noted that TS was considering utilization of the lift irrigation loads for better RE integration States had been requested to kindly study this aspect and interact with Government Bodies/irrigation department to utilize these schemes for improved flexing of the loads SRPC suggested constituents to kindly consider the possibility of using lift irrigation loads also as part of demand response. 9.3 Operation of existing units in pump mode A Special Meeting had been convened at SLDC, TSTRANSCO with participation from AP, TS, SRLDC & SRPC Secretariat. Recommendations finalized w.r.t pump mode operations of Nagarjunasagar are given below: TSGENCO to address issues for filling up the Tail Pond Reservoir i.e. legal issues, elevating the lift irrigation schemes etc. Also, TSGENCO to test pump mode operation through their OEM M/s Hitachi. Issue of discharges (quantum / time duration) / mechanism for enabling pump mode operation/utilization of the water pumped back could be referred to CEA /MoP for further guidance and suitable directions. This could help in utilization of Nagarjunasagar units in pump mode in an optimal manner especially with higher renewable integration. Minutes of the 32 nd Meeting of SRPC held on Page 15

16 Following were the recommendation finalized w.r.t Srisailam pump mode operation: Issue regarding weir could be taken up with CEA /MoP for further advice/guidance/funding. Though it could take 2-3 years for completion but with high targets of renewables addition, this would be useful in pump mode operation at Srisailam and balancing of RE. Issue regarding discharges (quantum/time duration) / mechanism for enabling pump mode operation/utilization of the water pumped back could be referred to CEA /MoP for further guidance and suitable directions. This could help in utilization of Srisailam units in pump mode in an optimal manner TCC deliberations TSGENCO had informed that lift irrigation scheme between N Sagar and Tail Pond were getting submerged and needed to be elevated. Shifting of the lift irrigation scheme (under private sector) is under progress. OEM M/s Hitachi had visited in July 2017 and approved operation of N Sagar units in pump mode. Once lift irrigation scheme gets elevated and with sufficient available water, units can be operated in pump mode. With regard to Srisailam / N Sagar pump mode operation, TSGENCO was suggested to kindly take up issues, requiring attention of CEA. SRPC deliberations CMD, TSTRANSCO & TSGENCO informed that the Tail Pond reservoir is ready and was to be handed over to TS. Recently OEM, M/s Hitachi had inspected all the units and they had approved the commissioning MD, APGENCO informed that the proposal for handing over of the dam has been submitted to Government and was under consideration. The views expressed in SRPC Meeting would also be communicated to Government to take the decision at the earliest. Being an interlinked issue with Puluchintala, the handing over was awaiting formalization CMD, TSGENCO said that the Tail Pond was for pump mode and due to some administrative reasons there had been some delay MS, SRPC stated that in the CEA Meeting, Member (Planning), CEA had suggested that issues with regard to pump mode could be taken up with MoP/ Member (Hydro) by TSGENCO MD, APGENCO noted that Tail Pond dam was constructed with the intention of utilizing the N sagar units in pump mode and also the Tail Pond units were constructed to utilize 50 MW power Regarding Srisailam, CMD, TSGENCO said that 540 feet level was required to be maintained at N sagar for pumping operations. The weir had been washed out and would have to be re-planned. For weir construction they had already approached the concerned Central body. With good release from Almatti, pump operation at Srisailam may be possible. If any issue is perceived, it would be taken up with MoP/CEA. 9.4 Pump Storage Plants A Meeting had been convened by CEA on 28 th June 2017 (MoM dated enclosed as Annexure-XVIII) regarding utilization of existing pumps in the country. CEA had informed the Minutes of the 32 nd Meeting of SRPC held on Page 16

17 following about upcoming Pump Storage Plants in SR: State PSP Scheme Status Andhra Pradesh Upper Sileru (1000 MW) DPR being prepared Tamil Nadu Kundah (500 MW) DPR prepared 5 projects on existing sites Karnataka Sharavathy (2000 MW) PFR submitted to MoEF Varahi Kerala Sholayar-I (810 MW) Survey and investigation Sholayar-II (390 MW) (S&I)/implementation could Poringalkuthu (80 MW) not be taken up for want of forest clearance Issues in this regard, as also noted in the Hyderabad Meeting, had been taken up by SRPC with Member (Hydro), CEA vide letter dated (Annexure-XIX). SRPC deliberations SRPC suggested the constituents to follow the pumping schemes with concerted efforts. 9.5 Power Flow Analysis under high RE scenario SRLDC vide dated had informed that a project had been undertaken jointly by POSOCO, USAID and NREL for power flow analysis under high RE scenario. This study would look into reliability and security issues with high RE penetration. As a part of Phase-I of this work, studies are proposed to be conducted for 2018 grid scenario. For this purpose, States were kindly requested to share details of existing wind & Solar generator details and Wind and Solar expected to be commissioned by July 2018 with details of planned transmission system. It had also been requested to kindly fill in details sought as per the attached format. A sample wind station diagram was also attached for reference The following had been noted in the TCC Meeting: TSTRANSCO, TANTRANSCO & KPTCL had already furnished the relevant information. APTRANSCO informed that system study group had carried out Analysis with Spanish Consultant around two weeks back and report was awaited. SRLDC requested APTRANSCO & KSEBL to kindly furnish the information at the earliest SRPC noted the above. 9.6 Typical ramps of Solar Typical ramps for the 250 MW NP Kunta solar plant are given in Table below: Ramp No. Time blocks Approx. Time (Hrs.) Average ramp (MW/ block) Ram rate % installed capacity Remarks 1 26 to 27 6:15 to 6: % Slow ramp up 2 28 to 38 6:46 to 9: % Steep ramp up 3 39 to 45 9:31 to 11: % Slow ramp up 4 46 to 53 11:16 to 13:15 2 to 3 1% to 1.5% Generation more or less Minutes of the 32 nd Meeting of SRPC held on Page 17

18 same 5 54 to 58 13:16 to 14: % Slow ramp Down 6 59 to 69 14:31 to 17: % Steep ramp Down 7 70 to 73 17:16 to 18: % Slow ramp Down These Ramps could be used for balancing/reserve planning by entities. The installed capacity could be scaled suitably for this purpose. This exercise assumes significant importance in view of the fact that Solar trajectory is quite high and would form large component of the RE / installed capacity of the states. This would be an apt time to use such tools for better load generation, balancing / reserve assessment / planning. SRPC deliberations Constituents were kindly requested to consider this aspect for better reserve planning, balancing etc. 10. COMPLIANCE OF CEA REGULATIONS FOR GRID CONNECTIVITY OF RENEWABLE ENERGY SOURCES 10.1 CEA vide letter dated (Annexure-XX) had stated that in compliance of Clauses 6(3) and 6(4)(b) of CEA (Technical Standards for Connectivity to Grid) Regulations 2007 and CEA (Technical Standards for Connectivity of the Distributed Generation Resources) Regulations 2013 notified on 30 th September 2013, it is obligatory for all grid connected renewable generators to provide necessary facilities for data-communication and data-storage and other parameters as may be stipulated. The said CEA Regulations also place onus on the generating plants including renewable, to coordinate with appropriate licensees on issues including, but not limited to protection safety and metering With the above perspective emerging from the CEA Regulations, SLDCs had been kindly requested to take up the matter with all renewable generators to ensure transfer of data to the appropriate Load Despatch Centre, so that real time generation data is available with them for centralized monitoring. It was also requested to indicate present status in this regard and the action plan with definite time frame to ensure real time data telemetry from the entire grid connected Renewable Generators/Plants to SLDCs. CEA had requested SRPC to take up this issue with concerned SLDC/utility operating the SLDC Subsequently, CEA vide letter dated (Annexure-XXI) had conveyed contents of MoP letter dated The same are given below : CEA to ensure that necessary rules and regulations regarding generation data communication including RE generators are in place and being implemented in true spirit along with the suitable monitoring mechanism/penal mechanism for non-compliance. National level Registry to be maintained by Central Electricity Authority (CEA), where generation capacity data of all kind of Generators (Conventional, Non-conventional, Non-captive, Captive ISGS or ISGS) would be available. State level Registry shall be maintained at the respective SLDCs also where generation capacity data of all kind of Generators (Conventional, Non-conventional, Non-captive, Captive) in the respective States will be available. State level Minutes of the 32 nd Meeting of SRPC held on Page 18

CONTENTS. Minutes of the 31 st Meeting of TCC held on Page 1

CONTENTS. Minutes of the 31 st Meeting of TCC held on Page 1 CONTENTS 1. INTRODUCTION... 3 2. CONFIRMATION OF THE MINUTES OF THE 30 th MEETING OF TCC... 7 3. OPERATION OF HYDRO POWER PROJECTS IN PEAKING MODE... 7 4. MEMBERSHIP TO RPC... 11 5. PREPARATION FOR MEETING

More information

SOUTHERN REGIONAL POWER COMMITTEE BANGALORE MINUTES OF THE 22 ND MEETING OF COMMERCIAL SUB-COMMITTEE OF SRPC HELD AT BANGALORE ON

SOUTHERN REGIONAL POWER COMMITTEE BANGALORE MINUTES OF THE 22 ND MEETING OF COMMERCIAL SUB-COMMITTEE OF SRPC HELD AT BANGALORE ON SOUTHERN REGIONAL POWER COMMITTEE BANGALORE MINUTES OF THE 22 ND MEETING OF COMMERCIAL SUB-COMMITTEE OF SRPC HELD AT BANGALORE ON 31.07.2013 1. INTRODUCTION 1.1 The 22 nd Meeting of the Commercial Sub-

More information

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU. Record Notes of the Meeting regarding issues pertaining to Tamil Nadu

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU. Record Notes of the Meeting regarding issues pertaining to Tamil Nadu SOUTHERN REGIONAL POWER COMMITTEE BENGALURU Record Notes of the Meeting regarding issues pertaining to Tamil Nadu A Meeting on issues pertaining to Tamil Nadu was held on 25 th TANTRANSCO, Chennai. The

More information

SOUTHERN REGIONAL POWER COMMITTEE BANGALORE MINUTES OF THE 19 TH MEETING OF TECHNICAL COORDINATION COMMITTEE OF SRPC HELD AT HYDERABAD ON

SOUTHERN REGIONAL POWER COMMITTEE BANGALORE MINUTES OF THE 19 TH MEETING OF TECHNICAL COORDINATION COMMITTEE OF SRPC HELD AT HYDERABAD ON SOUTHERN REGIONAL POWER COMMITTEE BANGALORE MINUTES OF THE 19 TH MEETING OF TECHNICAL COORDINATION COMMITTEE OF SRPC HELD AT HYDERABAD ON 27.09.2012 1. INTRODUCTION 1.1 The 19 th meeting of Technical Coordination

More information

Uttar Pradesh Electricity Regulatory Commission

Uttar Pradesh Electricity Regulatory Commission Uttar Pradesh Electricity Regulatory Commission Notification no. UPERC / Secy / CNCE Regulation, 2009/ 696 Dated: 22.3.2010 In exercise of powers conferred under section 181 read with section 9, 61, 86

More information

Contents. Minutes of the 34 th Meeting of SRPC held on Page 1

Contents. Minutes of the 34 th Meeting of SRPC held on Page 1 Contents 1. INTRODUCTION...3 2. CONFIRMATION OF THE MINUTES OF THE 33 rd MEETING OF SRPC...7 3. SUPPORT OF RE GENERATORS FOR REACTIVE COMPENSATION...7 4. RAMP RATES... 11 5. PROCUREMENT OF POC SOFTWARE

More information

31 NON-AVAILING OF OCC APPROVED SHUTDOWN GRID STUDY COMMITTEE (TASK- 2) AUDIT PROGRESS DETAILS STATUS OF PHASE I AND PHASE II OF

31 NON-AVAILING OF OCC APPROVED SHUTDOWN GRID STUDY COMMITTEE (TASK- 2) AUDIT PROGRESS DETAILS STATUS OF PHASE I AND PHASE II OF CONTENTS 1. INTRODUCTION... 4 2. CONFIRMATION OF THE MINUTES OF THE 30 th SRPC MEETING... 7 3. MEMBERSHIP TO RPC... 7 4. PREPARATION FOR MEETING REVISED ENVIRONMENT NORMS AS PER ENVIRONMENT (PROTECTION)

More information

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU SOUTHERN REGIONAL POWER COMMITTEE BENGALURU Minutes of the 30 th Meeting of Commercial Sub Committee of SRPC held at Bengaluru on 4 th February 2016 1. Introduction The 30 th Meeting of Commercial Sub-Committee

More information

Contents. Minutes of the 33 rd Meeting of SRPC held on Page 1

Contents. Minutes of the 33 rd Meeting of SRPC held on Page 1 Contents 1. INTRODUCTION... 3 2. CONFIRMATION OF THE MINUTES OF THE 32 nd MEETING OF SRPC... 7 3. MEMBERSHIP TO RPC... 7 4. COAL ISSUES... 8 5. 400 kv NPS NELLORE TRANSMISSION LINES LOADING... 15 6. CYBER

More information

31 NON-AVAILING OF OCC APPROVED SHUTDOWN GRID STUDY COMMITTEE (TASK- 2) AUDIT PROGRESS DETAILS STATUS OF PHASE I AND PHASE II OF

31 NON-AVAILING OF OCC APPROVED SHUTDOWN GRID STUDY COMMITTEE (TASK- 2) AUDIT PROGRESS DETAILS STATUS OF PHASE I AND PHASE II OF CONTENTS 1. INTRODUCTION... 4 2. CONFIRMATION OF THE MINUTES OF THE 29 th TCC & 30 th SRPC MEETINGS... 4 3. MEMBERSHIP TO RPC... 4 4. PREPARATION FOR MEETING REVISED ENVIRONMENT NORMS AS PER ENVIRONMENT

More information

POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT. Energy Department Government of Bihar

POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT. Energy Department Government of Bihar POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT Energy Department Government of Bihar 2012 ( 1 ) Table of Content 1. Objective 2. Title and Enforcement 3. Scope and Coverage 4. Nodal Agency 5. Classification

More information

CIN No. U40105DL2009GOI प वर स टम ऑपर शन क रप र शन ल मट ड (प वर ड क रप र शन ऑफ इ डय ल मट ड क एक प ण व म व व ल सह यक क पन ) POWER SYSTEM OPERATIO

CIN No. U40105DL2009GOI प वर स टम ऑपर शन क रप र शन ल मट ड (प वर ड क रप र शन ऑफ इ डय ल मट ड क एक प ण व म व व ल सह यक क पन ) POWER SYSTEM OPERATIO CIN No. U40105DL2009GOI188682 प वर स टम ऑपर शन क रप र शन ल मट ड (प वर ड क रप र शन ऑफ इ डय ल मट ड क एक प ण व म व व ल सह यक क पन ) POWER SYSTEM OPERATION CORPORATION LIMITED (A wholly owned subsidiary of

More information

Maharashtra Electricity Regulatory Commission (Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation) Regulations, 2018

Maharashtra Electricity Regulatory Commission (Forecasting, Scheduling and Deviation Settlement for Solar and Wind Generation) Regulations, 2018 MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website: www.mercindia.org.in;

More information

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU SOUTHERN REGIONAL POWER COMMITTEE BENGALURU AGENDA FOR THE 30 th MEETING OF COMMERCIAL SUB - COMMITTEE OF SRPC TO BE HELD AT BENGALURU ON 4 th FEBRUARY 2016 1. Confirmation of the Minutes of 29 th Commercial

More information

25 AUGMENTATION OF TALCHER-II TRANSMISSION SYSTEM.67

25 AUGMENTATION OF TALCHER-II TRANSMISSION SYSTEM.67 CONTENTS 1. INTRODUCTION... 4 2. CONFIRMATION OF THE MINUTES OF 28 th MEETING OF TCC... 6 3. FLEXIBILITY IN UTILIZATION OF DOMESTIC COAL FOR REDUCING COST OF POWER GENERATION... 6 4. TERMS OF REFERENCE

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM. PRESENT: Sri.T.M. Manoharan, Chairman

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM. PRESENT: Sri.T.M. Manoharan, Chairman KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM PRESENT: Sri.T.M. Manoharan, Chairman Petition No. 1893/DD (T)/Jhabua/2016/KSERC in OP No. 13/2015 In the matter of Procurement of 865

More information

GUJARAT ELECTRICITY REGULATORY COMMISSION 1st Floor, Neptune Tower, Ashram Road, Ahmedabad

GUJARAT ELECTRICITY REGULATORY COMMISSION 1st Floor, Neptune Tower, Ashram Road, Ahmedabad GUJARAT ELECTRICITY REGULATORY COMMISSION 1st Floor, Neptune Tower, Ashram Road, Ahmedabad-380009 Minutes of the meeting of the Coordination Forum held on 29 th July,2006 in Hotel hider Residency, Ahmedabad.

More information

1.1 These regulations shall extend to whole of the State of Punjab.

1.1 These regulations shall extend to whole of the State of Punjab. THE PUNJAB STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION The, 2018 No.PSERC/Secy/Regu. - In exercise of the powers conferred under Section 181of the Electricity Act, 2003 (36 of 2003), and all other

More information

पत स च/ Address List

पत स च/ Address List पत स च/ Address List 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. म य अ भय त (व ण य), एप प स स, ह दर ब द Chief Engineer (Comml.), APPCC, Hyderabad. अपर नद शक (प रय जन ),प स क ल, क व र भवन,

More information

BEFORE THE HON BLE MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION (MPERC) BHOPAL

BEFORE THE HON BLE MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION (MPERC) BHOPAL BEFORE THE HON BLE MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION (MPERC) BHOPAL IN THE MATTER OF Provisional approval of Generation tariff of M.P. s 57% share of power in Sardar Sarovar Project (6x200+5x50

More information

BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION AT GANDHINAGAR PETITION NO OF 2016

BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION AT GANDHINAGAR PETITION NO OF 2016 1 BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION AT GANDHINAGAR PETITION NO OF 2016 IN THE MATTER OF: Petition under Section 86 read with Section 181 of the Electricity Act, 2003 for amendment of

More information

Draft MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION

Draft MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION Draft MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION No. / /2017/MPERC.- In exercise of the powers conferred under Section 181of the Electricity Act, 2003 (36 of 2003), and all other powers enabling

More information

CONTENTS 1.0 INTRODUCTION CONFIRMATION OF THE MINUTESOF 27 th TCC MEETING IMPLEMENTATION OF SPS FOR CONTINGENCY OF 400 kv NELLORE -

CONTENTS 1.0 INTRODUCTION CONFIRMATION OF THE MINUTESOF 27 th TCC MEETING IMPLEMENTATION OF SPS FOR CONTINGENCY OF 400 kv NELLORE - CONTENTS 1.0 INTRODUCTION... 1 2.0 CONFIRMATION OF THE MINUTESOF 27 th TCC MEETING... 5 3.0 IMPLEMENTATION OF SPS FOR CONTINGENCY OF 400 kv NELLORE - NELLORE PS LINES AND DIFFERENTIAL PROTECTION... 5 4.0

More information

Scanned by CamScanner

Scanned by CamScanner Scanned by CamScanner Maharashtra Electricity Regulatory Commission intends to enact MERC (Forecasting, Scheduling and Deviation. Accordingly, the Hon ble Commission has circulated the draft of the proposedmerc

More information

TELANGANA STATE POWER COORDINATION COMMITTEE Request for Proposal (RfP) NOTICE No. TSPCC (Commercial)/02/15-16

TELANGANA STATE POWER COORDINATION COMMITTEE Request for Proposal (RfP) NOTICE No. TSPCC (Commercial)/02/15-16 1 TELANGANA STATE POWER COORDINATION COMMITTEE Request for Proposal (RfP) NOTICE No. TSPCC (Commercial)/02/15-16 TSPCC on behalf of TSDISCOMs (TSSPDCL & TSNPDCL) intends to purchase 2000 MW power for the

More information

Rajasthan Electricity Regulatory Commission

Rajasthan Electricity Regulatory Commission Rajasthan Electricity Regulatory Commission Vidyut Viniyamak Bhawan, Near State Motor Garage, Sahkar Marg, JAIPUR -302001 Phone: EPBX 0141-2741299, Fax: 0141-2741018 Website: www.rerc.rajasthan.gov.in

More information

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION 5 th Floor, "Metro Plaza", Bittan Market, Bhopal - 462 016 Petition No.55 of 2012 PRESENT: Rakesh Sahni, Chairman IN THE MATTER OF: C.S. Sharma, Member

More information

GUJARAT ELECTRICITY REGULATORY COMMISSION. Notification No. 13 of 2005

GUJARAT ELECTRICITY REGULATORY COMMISSION. Notification No. 13 of 2005 GUJARAT ELECTRICITY REGULATORY COMMISSION OPEN ACCESS REGULATION Notification No. 13 of 2005 In exercise of the powers conferred on it by Section 181 read with Sections 39(2)(d), 40(c), 42 (2)(3)(4), 86(1)(c)

More information

Bhopal, Dated:

Bhopal, Dated: Bhopal, Dated: 08.12.2015 No. /MPERC /2015 - In exercise of powers conferred under sub-section zp of Section 181 of the Electricity Act, 2003 (36 of 2003), and all other powers enabling it in this behalf,

More information

Power Procurement Strategy

Power Procurement Strategy Power Procurement Strategy 01.03.16 IIT-Kanpur For Public Use POWER SECTOR OVERVIEW Source: Executive Summary of October 2015, CEA *including renewable generation Installed Capacity (All) Category Installed

More information

Chhattisgarh State Electricity Regulatory Commission

Chhattisgarh State Electricity Regulatory Commission Øekad 62] jk;iqj]] 'kqøokj] fnukad 4 ekpz 2011 & QkYxqu 13] 'kd 1932 Chhattisgarh State Electricity Regulatory Commission Irrigation Colony, Shanti Nagar, Raipur Raipur, Dated March 04, 2011 No. 36/CSERC/2011

More information

CHAPTER I: PRELIMINARY Short title, commencement and interpretation

CHAPTER I: PRELIMINARY Short title, commencement and interpretation Notification dated 20.2.2009 Bhopal: dated 31 st January, 2009 No. 254-MPERC-2009. In exercise of the powers conferred by Section 181 read with Subsection (b) of Section 86 of the Electricity Act 2003

More information

BEFORE THE KARNATAKA ELECTRICITY REGULATORY COMMISSION, BENGALURU. Dated 16 th, May,2018

BEFORE THE KARNATAKA ELECTRICITY REGULATORY COMMISSION, BENGALURU. Dated 16 th, May,2018 No. S/01/18 BEFORE THE KARNATAKA ELECTRICITY REGULATORY COMMISSION, BENGALURU Present: Dated 16 th, May,2018 Sri. M.K. Shankaralinge Gowda - Chairman Sri. H.D. Arun Kumar - Member Sri. D.B. Manival Raju

More information

GOVERNMENT OF KERALA

GOVERNMENT OF KERALA 183 GOVERNMENT OF KERALA Kerala Small Hydro Power Policy 2012 1. Order G.O.(P) 25/2012/PD Dated: Thiruvananthapuram, 03.10.2012 2. Title Kerala Small Hydro Power Policy 2012 3. Objective To increase the

More information

Case No. 85 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.

Case No. 85 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

(Collective Transaction) Procedure for Scheduling

(Collective Transaction) Procedure for Scheduling Annexure-II Short-Term Open Access in Inter-State Transmission (Collective Transaction) Procedure for Scheduling [As per CERC Open Access Regulations, 2008 (dated 25.01.2008) & subsequent (Amendment) Regulations,

More information

CENTRAL ELECTRICITY AUTHORITY Power Communication Development Division

CENTRAL ELECTRICITY AUTHORITY Power Communication Development Division CENTRAL ELECTRICITY AUTHORITY Power Communication Development Division AGENDA FOR THE 106 th CENTRAL PTCC MEETING Date: 25 th May 2018 Venue: Evershine Keys Prima Resort, C.T.S. No. 182, Gautam Road, Mahabaleshwar,

More information

KARNATAKA ELECTRICITY REGULATORY COMMISSION TARIFF ORDER 2017 HESCOM ANNUAL PERFORMANCE REVIEW FOR FY16

KARNATAKA ELECTRICITY REGULATORY COMMISSION TARIFF ORDER 2017 HESCOM ANNUAL PERFORMANCE REVIEW FOR FY16 KARNATAKA ELECTRICITY REGULATORY COMMISSION TARIFF ORDER 2017 OF HESCOM ANNUAL PERFORMANCE REVIEW FOR FY16 & REVISION OF ANNUAL REVENUE REQUIREMENT FOR FY18 & REVISION OF RETAIL SUPPLY TARIFF FOR FY18

More information

TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Tariff Order No 1 of 2010 dated

TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Tariff Order No 1 of 2010 dated TAMIL NADU ELECTRICITY REGULATORY COMMISSION Tariff Order No 1 of 2010 dated 27.05.2010 Sl.No Description Summary of Regulations 1 Title Tariff order for projects covered by Jawaharlal Nehru National Solar

More information

KARNATAKA ELECTRICITY REGULATORY COMMISSION TARIFF ORDER 2018 BESCOM ANNUAL PERFORMANCE REVIEW FOR FY17

KARNATAKA ELECTRICITY REGULATORY COMMISSION TARIFF ORDER 2018 BESCOM ANNUAL PERFORMANCE REVIEW FOR FY17 KARNATAKA ELECTRICITY REGULATORY COMMISSION TARIFF ORDER 2018 OF BESCOM ANNUAL PERFORMANCE REVIEW FOR FY17 & REVISION OF ANNUAL REVENUE REQUIREMENT FOR FY19 & REVISION OF RETAIL SUPPLY TARIFF FOR FY19

More information

BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL)

BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL) BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL) REVISED PETITION FOR APPROVAL OF TRUE UP OF FY 2015-16 & FY 2016 17 AND PROVISIONAL TRUE UP of FY 2017-18

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3rd & 4th Floor, Chandralok Building, 36, Janpath, New Delhi : /

CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3rd & 4th Floor, Chandralok Building, 36, Janpath, New Delhi : / CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3rd & 4th Floor, Chandralok Building, 36, Janpath, New Delhi 110 001 : 011-23353503/23752958 Public Notice No. : L-1/94/CERC/2011 Dated: 26 th June, 2015

More information

Central Transmission Utility

Central Transmission Utility Central Transmission Utility Grant of long Term Access from NEW Grid to Southern Region Dat e: 22 September 2014 Subje ct : Grant of Long Term Access fo r th e eligible ap plicatio ns received in t he

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (RENEWABLE PURCHASE OBLIGATION, ITS COMPLIANCE AND IMPLEMENTATION OF RENEWABLE ENERGY CERTIFICATE FRAMEWORK)

More information

No. 14/1/2016-Trans Government of India Ministry of Power. Office Memorandum

No. 14/1/2016-Trans Government of India Ministry of Power. Office Memorandum No. 14/1/2016-Trans Government of India Ministry of Power Shram Shakti Bhawan, Rafi Marg, New Delhi, dated s" December, 2016 Office Memorandum Subject: Guidelines on Cross Border Trade of Electricity At

More information

Uttar Pradesh Electricity Regulatory Commission

Uttar Pradesh Electricity Regulatory Commission Uttar Pradesh Electricity Regulatory Commission In exercise of the powers conferred under Section 181 of the Electricity Act, 2003 and all powers enabling it in this behalf, the Uttar Pradesh Electricity

More information

Trading at Power Exchange - IEX

Trading at Power Exchange - IEX Trading at Power Exchange - IEX February 2016 Prasanna Rao Market Operations In this presentation Product Portfolio Trading Mechanism & Process Flow- Day-Ahead Market Trading Mechanism-Term-Ahead Market

More information

Key Processes in Power Exchange Presented By: Prasanna Rao Shalabh Shrivastava

Key Processes in Power Exchange Presented By: Prasanna Rao Shalabh Shrivastava Key Processes in Power Exchange Presented By: Prasanna Rao Shalabh Shrivastava www.iexindia.com Day Ahead Market-Collective Transaction Features A closed double-sided anonymous auction for each 15-min

More information

Procedure for Scheduling

Procedure for Scheduling Short-Term Open Access in Inter-State Transmission (Bilateral Transaction) Procedure for Scheduling (As per CERC Open Access Regulations, 2008 (dated 25.01.2008) & subsequent (Amendment) Regulations, 2009

More information

Rs Billion Short Term Debt Programme. (Series IX & X)

Rs Billion Short Term Debt Programme. (Series IX & X) CRISIL Limited CRISIL s RatingRationale Power Grid Corporation of India Limited OCTOBER 2005 Rs. 20 Billion Bonds Programme Rs. 6.50 Billion Short Term Debt Programme (Enhanced from Rs. 6 Billion) Rs.

More information

Power Market, Power Trading and Power Exchange

Power Market, Power Trading and Power Exchange Power Market, Power Trading and Power Exchange National Seminar Challenges & Opportunities in Power Generation, Transmission & Distribution 23-03-12 Power System Operation Corporation Ltd. Eastern Regional

More information

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU

SOUTHERN REGIONAL POWER COMMITTEE BENGALURU SOUTHERN REGIONAL POWER COMMITTEE BENGALURU AGENDA NOTES FOR THE 29 th MEETING OF COMMERCIAL SUB- COMMITTEE OF SRPC TO BE HELD AT BENGALURU ON 29 th SEPTEMBER 2015 1. CONFIRMATION OF THE MINUTES OF THE

More information

North Eastern Regional Power Committee Agenda For

North Eastern Regional Power Committee Agenda For North Eastern Regional Power Committee Agenda For 33 rd Commercial Sub-Committee Meeting Time Date Venue Host : 10:30 Hrs. : 25 th August 2017 (Friday) : Spring Valley Resort, Sonapur, Guwahati : NEEPCO

More information

Green Day Ahead Market (Petition no. 187/MP/2016) CERC Hearing I December 1, 2016

Green Day Ahead Market (Petition no. 187/MP/2016) CERC Hearing I December 1, 2016 Green Day Ahead Market (Petition no. 187/MP/2016) CERC Hearing I December 1, 2016 Brief Introduction IEX since last 8 years has been successfully operating markets in: Day Ahead Market (DAM) [based on

More information

GUJARAT ELECTRICITY REGULATORY COMMISSION No. ---/---/---/GERC Dated: 13/01/2017. NOTIFICATION No. of 2017

GUJARAT ELECTRICITY REGULATORY COMMISSION No. ---/---/---/GERC Dated: 13/01/2017. NOTIFICATION No. of 2017 GUJARAT ELECTRICITY REGULATORY COMMISSION -------- No. ---/---/---/GERC Dated: 13/01/2017 NOTIFICATION No. of 2017 In exercise of the powers conferred under Section 181 of the Electricity Act, 2003 (36

More information

Tariff Filing. Sri Damodaram Sanjeevaiah Thermal Power Station (2 x 800 MW)

Tariff Filing. Sri Damodaram Sanjeevaiah Thermal Power Station (2 x 800 MW) Tariff Filing Sri Damodaram Sanjeevaiah Thermal Power Station (2 x 800 MW) For the control period 2014-2019 INDEX Annex Description Page Application with supporting affidavit 1-16 A-1 Capital Cost 17-19

More information

F. No. 53/15/2016 -WE Ministry of New & Renewable Energy. Evaluation of Generation Based Incentives Scheme for Wind Power Projects

F. No. 53/15/2016 -WE Ministry of New & Renewable Energy. Evaluation of Generation Based Incentives Scheme for Wind Power Projects F. No. 53/15/2016 -WE Ministry of New & Renewable Energy Evaluation of Generation Based Incentives Scheme for Wind Power Projects The GBI scheme was initially introduced in 11th Plan on 17.12.2009 with

More information

Leading Renewable Energy Generation Company

Leading Renewable Energy Generation Company Leading Renewable Energy Generation Company Disclaimer Certain statements in this presentation concerning our future growth prospects are forward looking statements, which involve a number of risks and

More information

GOVERNMENT OF PUNJAB DEPARTMENT OF POWER (Power Reforms Wing) NOTIFICATION The 21 st June, 2010

GOVERNMENT OF PUNJAB DEPARTMENT OF POWER (Power Reforms Wing) NOTIFICATION The 21 st June, 2010 GOVERNMENT OF PUNJAB DEPARTMENT OF POWER (Power Reforms Wing) NOTIFICATION The 21 st June, 2010 No. 1/17/09-EB(PR)/450.- Whereas the State of Punjab is presently facing acute power shortages. And therefore,

More information

By S K Agrawal ED (Commercial) NHPC Ltd.1

By S K Agrawal ED (Commercial) NHPC Ltd.1 By S K Agrawal ED (Commercial) NHPC Ltd.1 Need for Renovation & Modernisation of HEPs Advantages of R&M of old Power Stations Govt. policies on R&M Regulatory Provisions & Commercial aspects Overview of

More information

PORTFOLIO OPTIMIZATION FOR OPEN ACCESS CONSUMERS/DISCOMS

PORTFOLIO OPTIMIZATION FOR OPEN ACCESS CONSUMERS/DISCOMS PORTFOLIO OPTIMIZATION FOR OPEN ACCESS CONSUMERS/DISCOMS By Dr. PARUL MATHURIA POST DOCTORAL FELLOW DEPARTMENT OF INDUSTRIAL AND MANAGEMENT ENGINEERING INDIAN INSTITUTE OF TECHNOLOGY KANPUR 2017 15-05-2017

More information

दव ण त र य व द य त सवमवत

दव ण त र य व द य त सवमवत भ रत सरक र GOVERNMENT OF INDIA व द य त म त र लय MINISTRY OF POWER क द र य व द य त प र व करण CENTRAL ELECTRICITY AUTHORITY दव ण त र य व द य त सवमवत SOUTHERN REGIONAL POWER COMMITTEE व ण ज य उप सम त क उन

More information

Distribution Tariff Determination and Rationalization

Distribution Tariff Determination and Rationalization Department of Industrial and Management Engineering Indian Institute of Technology Kanpur 3 rd Capacity Building Programme for Officers of Electricity Regulatory Commissions 23 28 August, 2010 Forum of

More information

Case No. 27 of In the matter of

Case No. 27 of In the matter of Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

M.P. Electricity Regulatory Commission Bhopal

M.P. Electricity Regulatory Commission Bhopal SMP-20/2010 M.P. Electricity Regulatory Commission Bhopal Tariff Order for procurement of power from Wind Electric Generators 1. LEGISLATIVE PROVISIONS 1.1 Section 86(1) (e) of the Electricity Act 2003

More information

BEFORE THE KERALA STATE ELECTRICITY REGULATORY COMMISSION

BEFORE THE KERALA STATE ELECTRICITY REGULATORY COMMISSION BEFORE THE KERALA STATE ELECTRICITY REGULATORY COMMISSION IN THE MATTER OF: Proposals to introduce Fuel Price Adjustment Charges on all consumers including Bulk Consumers/ Other Licensees to recover the

More information

OFFICE MEMORANDUM. Subject:- Administrative Approval of Central Sector Scheme "National Dairy Plan Phase-1 (NDP-1)"

OFFICE MEMORANDUM. Subject:- Administrative Approval of Central Sector Scheme National Dairy Plan Phase-1 (NDP-1) F. No.22-23l2011-DP Government of lrdia Ministry of ft{jrirulture Department of Animal Husbandry, Dairying & Fisheries Krishi Bhawan, New Delhi-11 0001 Dated the 16th March, 2012 OFFICE MEMORANDUM Subject:-

More information

BRIEF ANALYSIS ON NEW OPEN ACCESS REGULATIONS IN THE STATE OF MAHARASHTRA

BRIEF ANALYSIS ON NEW OPEN ACCESS REGULATIONS IN THE STATE OF MAHARASHTRA BRIEF ANALYSIS ON NEW OPEN ACCESS REGULATIONS IN THE STATE OF MAHARASHTRA ETERNITY LEGAL 1207, Dalamal Tower, Free Press Journal Road, Nariman Point, Mumbai 400021 Tel: +91 22 6747 9001 Email: legalupdates@eternitylegal.com

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. 94/2010 Coram: Dr. Pramod Deo, Chairperson Shri S.Jayaraman, Member Shri V.S.Verma, Member Shri M.Deena Dayalan, Member Date of Hearing:

More information

CONDUCT OF BUSINESS RULES (CBR) THE DESIGNATED AUTHORITY FOR FACILITATING CROSS BORDER TRANSACTION AND TRADE IN ELECTRICITY

CONDUCT OF BUSINESS RULES (CBR) THE DESIGNATED AUTHORITY FOR FACILITATING CROSS BORDER TRANSACTION AND TRADE IN ELECTRICITY CONDUCT OF BUSINESS RULES (CBR) OF THE DESIGNATED AUTHORITY FOR FACILITATING CROSS BORDER TRANSACTION AND TRADE IN ELECTRICITY Central Electricity Authority Ministry of Power Government of India April

More information

2 EXECUTIVE SUMMARY. 1. This Licence may be called the Distribution Licence for The Tata Power Company Ltd. (Distribution Licence No.

2 EXECUTIVE SUMMARY. 1. This Licence may be called the Distribution Licence for The Tata Power Company Ltd. (Distribution Licence No. 2 EXECUTIVE SUMMARY The Tata Power Company Limited ( Tata Power ) is a company established in 1919. On April 1, 2000, The Tata Hydro-Electric Power Supply Company Limited (established in 1910) and The

More information

59 th Annual Report

59 th Annual Report Significant Accounting Policies I. Basis of Accounting The financial statements are prepared on accrual basis of accounting under historical cost convention, in accordance with Generally Accepted Accounting

More information

Procedure for Scheduling

Procedure for Scheduling Short-Term Open Access in Inter-State Transmission (Collective Transaction) Procedure for Scheduling (As per CERC Open Access Regulations, 2008 (dated 25.01.2008) & subsequent(amendment) Regulations, 2009

More information

Leading Diversified Renewable Energy Generation Company

Leading Diversified Renewable Energy Generation Company Leading Diversified Renewable Energy Generation Company Disclaimer Certain statements in this presentation concerning our future growth prospects areforward looking statements, which involve a number of

More information

Multi Year Tariff Order For Himachal Pradesh State Electricity Board Limited (HPSEBL) For the period FY to FY

Multi Year Tariff Order For Himachal Pradesh State Electricity Board Limited (HPSEBL) For the period FY to FY Multi Year Tariff Order For Himachal Pradesh State Electricity Board Limited (HPSEBL) For the period FY 2014-15 to FY 2018-19 Himachal Pradesh Electricity Regulatory Commission June 12, 2014 BEFORE THE

More information

The DSM account for the following weeks have been revised, based on the revised data furnished by SRLDC, and attached:

The DSM account for the following weeks have been revised, based on the revised data furnished by SRLDC, and attached: त स क क न र य व द य त प र वधक ण दवक षण क ष त र य व द य त सव वत 29, स क स क र स ड ब गल :-560 009 Government of India Central Electricity Authority Southern al Power Committee 29, Race Course Cross Road

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 242/TT/2015

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. 242/TT/2015 CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. 242/TT/2015 In the matter of: Coram: Shri Gireesh B. Pradhan, Chairperson Shri A.K. Singhal, Member Shri A.S. Bakshi, Member Dr. M.K. Iyer,

More information

दव ण त र य व द य त सवमवत

दव ण त र य व द य त सवमवत भ रत सरक र GOVERNMENT OF INDIA व द य त म त र लय MINISTRY OF POWER क द र य व द य त प र व करण CENTRAL ELECTRICITY AUTHORITY दव ण त र य व द य त सवमवत SOUTHERN REGIONAL POWER COMMITTEE ददन क 26 ज ल ई 2014

More information

Case No. 56 of In the matter of

Case No. 56 of In the matter of Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 22163964/ 65/ 69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Vidarbha Industries Power Limited - Transmission

Vidarbha Industries Power Limited - Transmission Vidarbha Industries Power Limited - Transmission Revised Petition towards: Approval of Capital Cost and Determination of Aggregate Revenue Requirement ( ARR ) for the period FY 14-15 to FY 15-16 Filed

More information

Bhopal: Dated 5 th May 2006

Bhopal: Dated 5 th May 2006 Bhopal: Dated 5 th May 2006 No. 1192/MPERC/2006. In exercise of the powers conferred by section 181 (g) read with section 32(3) of the Electricity Act, 2003 enacted by the parliament, the Madhya Pradesh

More information

Executive Summary of Tata Power Generation True up Petition for FY as well as MYT Petition for FY to FY

Executive Summary of Tata Power Generation True up Petition for FY as well as MYT Petition for FY to FY Executive Summary of Tata Power Generation True up Petition for FY 2011-12 as well as MYT Petition for FY 2012-13 to FY 2015-16 Tata Power G Page 1 TABLE OF CONTENTS TABLE OF CONTENTS... 2 LIST OF TABLES...

More information

Replies to objections raised by

Replies to objections raised by O.P..8 & 9 of 2016 on PPA Between M/s Singareni Colliers Company Ltd(SCCL) & Telangana State DISCOMs for supply of power for a period of 25 years from Singareni Thermal Power Project Phase-I (2x600 MW)

More information

दव ण त र य व द य त सवमवत

दव ण त र य व द य त सवमवत भ रत सरक र GOVERNMENT OF INDIA व द य त म त र लय MINISTRY OF POWER क द र य व द य त प र व करण CENTRAL ELECTRICITY AUTHORITY दव ण त र य व द य त सवमवत SOUTHERN REGIONAL POWER COMMITTEE छब ब सव ब ठक क क र यव

More information

Karnataka Power Sector Reforms -Overview of Restructuring and Lessons Learnt-

Karnataka Power Sector Reforms -Overview of Restructuring and Lessons Learnt- Karnataka Power Sector Reforms -Overview of Restructuring and Lessons Learnt- Resource persons: Tetra Tech and Dhiya Consulting Pvt. Ltd., August 23, 2010 Bengaluru Contents Reform background Reform drivers

More information

Evolution of Power Exchange. S. C. Saxena National Load Despatch Center Power System Operation Corporation Ltd.

Evolution of Power Exchange. S. C. Saxena National Load Despatch Center Power System Operation Corporation Ltd. Evolution of Power Exchange S. C. Saxena National Load Despatch Center Power System Operation Corporation Ltd. Market Design Four Pillars of Market Design ELECTRICITY MARKET SCHEDULING & DISPATCH CONGESTION

More information

Case No. 24 of In the matter of Application of Reliance Infrastructure Ltd. for Amendment of Transmission Licence No.

Case No. 24 of In the matter of Application of Reliance Infrastructure Ltd. for Amendment of Transmission Licence No. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13 th Floor, Cuffe Parade, Mumbai 400005. Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

GOVERNMENT OF MADHYA PRADESH

GOVERNMENT OF MADHYA PRADESH 206 Compendium of State Government Policies on Renewable Energy Sector in India GOVERNMENT OF MADHYA PRADESH Wind Power Project Policy of Madhya Pradesh, 2012 (As Amended on 21 st February 2013) 1. Order

More information

Karnataka Electricity Regulatory Commission Tariff Order 2018 BESCOM CHAPTER 5 REVISED ANNUAL REVENUE REQUIREMENT FOR FY19

Karnataka Electricity Regulatory Commission Tariff Order 2018 BESCOM CHAPTER 5 REVISED ANNUAL REVENUE REQUIREMENT FOR FY19 CHAPTER 5 REVISED ANNUAL REVENUE REQUIREMENT FOR FY19 5.0 Revised Annual Revenue Requirement (ARR) for FY19 BESCOM s Application: BESCOM in its application dated 30 th November, 2017, has sought the approval

More information

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. No. UPERC/Secy/Regulation/ Lucknow : Dated, 17 th August, 2010

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. No. UPERC/Secy/Regulation/ Lucknow : Dated, 17 th August, 2010 UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION No. UPERC/Secy/Regulation/10-787 Lucknow : Dated, 17 th August, 2010 In exercise of powers conferred under sections 61, 66, 86(1)(e) and 181 of the Electricity

More information

Opinion. Accounting treatment for the project assets under construction

Opinion. Accounting treatment for the project assets under construction 116 Accounting treatment for the project assets under construction The following is the opinion given by the Expert Advisory Committee of the Institute in response to a query sent by a member. This is

More information

Electricity Market. July 15.

Electricity Market.   July 15. Electricity Market Email: info@iexindia.com July 15 www.iexindia.com In this presentation Introduction to Indian Power Market Product Portfolio Trading Mechanism Market Snapshot Participation Volume Price

More information

New and Renewable Energy Department Vallabh Bhavan, Bhopal

New and Renewable Energy Department Vallabh Bhavan, Bhopal New and Renewable Energy Department Vallabh Bhavan, Bhopal English Translation of Policy for implementation of Small Hydel-Power based Electricity Projects in Madhya Pradesh, 2011 (As Amended on 15th February

More information

Mending Power Sector Finances PPP as the Way Forward. Energy Market Forum

Mending Power Sector Finances PPP as the Way Forward. Energy Market Forum Mending Power Sector Finances PPP as the Way Forward Energy Market Forum AF Mercados EMI 11 th February 2011 Structure of the Presentation Current Status of Power Sector Generation Transmission Distribution

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION (DRAFT)

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION (DRAFT) CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI New Delhi, the 20 th of June 2013 NOTIFICATION (DRAFT) No.L-1/132/2013/CERC.- In exercise of the powers conferred under Section 178 of the Electricity

More information

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (LEVY AND COLLECTION OF FEES AND CHARGES BY STATE LOAD DESPATCH CENTRE) REGULATIONS,

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (LEVY AND COLLECTION OF FEES AND CHARGES BY STATE LOAD DESPATCH CENTRE) REGULATIONS, Approach Paper for MAHARASHTRA ELECTRICITY REGULATORY COMMISSION (LEVY AND COLLECTION OF FEES AND CHARGES BY STATE LOAD DESPATCH CENTRE) REGULATIONS, 2014 Issued By: Maharashtra Electricity Regulatory

More information

June 08, 2017 Ratings

June 08, 2017 Ratings POWER Solar Parks: A new Sunrise? Contact: Sanjay Agarwal Senior Director sanjay.agarwal@careratings.com 91-22- 6754 3582 Rajashree Murkute Associate Director rajashree.murkute@careratings.com 91-22-6754

More information

Key 21 suggestions on Draft GST Return Formats

Key 21 suggestions on Draft GST Return Formats Key 21 suggestions on Draft GST Return Formats The GST Council in its 28 th GST Council Meeting held on July 21, 2018 under the Chairmanship of Shri Piyush Goyal, Union Minister for Railways, Coal, Finance

More information

IN THE JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION AT RANCHI. Case No. 12 of 2018, 13 of 2018, 14 of 2018 & 15 of 2018

IN THE JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION AT RANCHI. Case No. 12 of 2018, 13 of 2018, 14 of 2018 & 15 of 2018 IN THE JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION AT RANCHI Case No. 12 of 2018, 13 of 2018, 14 of 2018 & 15 of 2018 Jharkhand Bijli Vitran Nigam Limited...... Petitioner CORAM: HON BLE MR. (DR)

More information

MINISTRY OF PETROLEUM AND NATURAL GAS GOVERNMENT OF INDIA GUIDELINES FOR SELECTION OF CUSTOMERS FOR DOMESTIC GAS FIELDS

MINISTRY OF PETROLEUM AND NATURAL GAS GOVERNMENT OF INDIA GUIDELINES FOR SELECTION OF CUSTOMERS FOR DOMESTIC GAS FIELDS MINISTRY OF PETROLEUM AND NATURAL GAS GOVERNMENT OF INDIA GUIDELINES FOR SELECTION OF CUSTOMERS FOR DOMESTIC GAS AVAILABLE FROM SMALL/ ISOLATED FIELDS 1. Background on allocation of non-apm gas from nominated

More information