The contract will be for a period of 15 years and will be delivered by Interserve, the preferred bidder. The main highlights are as follows:

Size: px
Start display at page:

Download "The contract will be for a period of 15 years and will be delivered by Interserve, the preferred bidder. The main highlights are as follows:"

Transcription

1 Airedale NHS Foundation Trust Board of Directors: 27 March 2013 Title: Briefing Paper for Carbon Energy Fund Project Authors: Steve Blenkinsop / Mark Walsh 1. Overview In September 2012 the Board approved the business case for the upgrade of the boiler house and the implementation of energy reduction measures through the Carbon Energy Fund (CEF). The business case made the following recommendations: that the Main Scheme proceeds to contract under CEF with Interserve as preferred bidder; those elements of the main scheme that are dependent on the Board decision with respect to the laundry are finalised prior to contract completion; the STOR 1 contract is pursued with the preferred bidder MCW; the biomass boiler option is not included in the main scheme at this stage. The decision on the future provision of Laundry services has now been finalised. The option to include a biomass boiler was not pursued due to increased maintenance costs, fuel price risk, capital costs and system availability. The Trust, through CEF, has developed both the main scheme and STOR schemes. This briefing paper is seeking to provide the necessary financial and legal assurances to the Board to proceed to contract signature on the main scheme and also to provide a brief update on the progress on the STOR project. 2. Main Scheme The contract will be for a period of 15 years and will be delivered by Interserve, the preferred bidder. The main highlights are as follows: forecast NPV over 15 years to the Trust 1.159m first year saving on completion of works 86k (excludes VAT benefits) investment provided 3.461m carbon emissions reduction (36%) 2 2,597 tco 2 /year The original business case estimated a first year saving of approximately 100k per year. The final value has reduced largely due to the decisions on the Laundry and the requirement to install additional equipment to maintain steam supply to SSD sterilisers, Theatre humidification plant and main kitchen equipment. Also there are works required to the electrical interface between the Trust and electricity grid that were confirmed during the contract negotiations. The cost savings of the key elements of the scheme will be delivered through the following projects: 835kW Combined Heat and Power (CHP) plant to generate electricity and hot water 3 new hot water boilers (replacing the existing steam boilers) 2500 new high efficiency lighting fittings improvements to the building management systems reductions to heat losses from pipework 3. Programme Delivery The proposed timescales for programme delivery are as follows: 1 The STOR (Short Term Operating Reserve) scheme will provide revenue and savings from operating the new emergency generators. The generators will export electricity to the grid as part of the Short Term Operating Reserve (STOR). It is estimated that the generators would run for 30 hours per year. 2 The Trust is committed through the NHS Carbon Management Programme to target reduction of 15% in carbon emissions by 2014/2015 from a baseline year of 2007/2008. CEF has advised that the main scheme will achieve a reduction of 36%.

2 Airedale NHS Foundation Trust Board of Directors: 27 March 2013 Title: Briefing Paper for Carbon Energy Fund Project Authors: Steve Blenkinsop / Mark Walsh contract approval March 2013 commence site works April 2013 completion of site works March Implications on Contract Delay The original timetable for achieving contract approval was extended to accommodate the decision on the future provision of Laundry services. Unfortunately a technical design solution couldn t be achieved until this had been made. Both CEF and Interserve were sensitive to the Trust s position and accepted the delay. However, if the Board is unable to approve the main scheme in March, CEF has advised that there could be a potential cost increase in Interserve s bid of approximately 3% as the price quoted in the tender was fixed for a period of 4 months. This will reduce the guaranteed savings by an estimated 11% (around 9k from an estimated saving of 86k). The method for paying CEF fees may also vary. It is currently included within the unitary payment. If the scheme is to be delayed, CEF would expect advance fee payments of approximately 20k per month which would be refunded on contract signature. 5. Funding Arrangements The funding will be provided by the Cooperative Bank to Interserve. The Trust will pay Interserve a unitary payment every quarter. The Trust understands that loan is between Interserve and the Cooperative Bank (Appendix B, item3, Funding) and is therefore treated as assigned receivables with the Trust, ie. the Trust guarantees the unitary payment, not the loan. Savings will be validated by CEF. Performance of Interserve relates to the guaranteed carbon saving of 2,597 tco 2 /year which will be monitored by CEF and the Trust during the operational phase of the project. Underperformance will be penalised with reduced payment to Interserve and over performance will be shared in accordance with the performance indicators within the project agreement payment mechanism. 6. Financial Implication Included in Appendix A is a sensitivity analysis which identifies the current expected saving of 85,537 based on the expected carbon saving of 2,597 tco 2 /year. This also reflects the possible variance in Department of Energy & Climate Change (DECC) energy prices which could vary between 79,581 and 173,992 (net of VAT). Also included in Appendix A is the unitary payment (UP) & savings proforma which provides a breakdown of the annual revenue costs and a cost proforma which provides a breakdown of Interserve s investment costs. 7. Accounting Treatment Price Waterhouse Cooper (PWC) has advised that subject to the following condition the lease can be treated as an operating lease and not a finance lease: The key decision which can tip this either way is whether the risk of the CHP not delivering savings lies with the lessor, ie. if they will guarantee the savings in spite of CHP not delivering them, then overall the risk lies with lessor not the Trust, which could help tip this in favour of an operating lease. Hill Dickinson has also advised that the project agreement reflects the necessary legally binding conditions to treat this lease as an operating lease and not a finance lease.

3 Airedale NHS Foundation Trust Board of Directors: 27 March 2013 Title: Briefing Paper for Carbon Energy Fund Project Authors: Steve Blenkinsop / Mark Walsh 8. Other Source of Finance The main constraint to the Trust in achieving its carbon reduction target (through its own resources) is the lack of Trust capital in cash terms. The Trust has applied for grant funding from the Improving Energy Efficiency in the NHS, Applications for Capital Funding The application was submitted on 28 February 2013 for 1.688m; this is the capital value of the CHP plant (inclusive of VAT). The applications will be reviewed and further detail requested from selected applicants in April A final decision on whether the Trust has been successful is expected in June Provision has been made which is acceptable to the Cooperative Bank to vary the contract if the Trust is successful in its application. CEF has advised that a breakage fee of up to 50k will be payable by the Trust if the contract was to be varied to accommodate the grant funding. It should be noted that the grant will provide a cash benefit of 72k per annum based on the current figures, but unfortunately it will generate an income and expenditure loss of 39k per annum. The Trust will consider its position once the grant decision has been made. The impact of the grant will also have to be considered in line with the proposed Monitor financial risk ratings and the Trust s liquidity. 9. Legal Implication and Board Resolution Minutes The Trust has commissioned Hill Dickinson solicitors to act on its behalf to carry out a due diligence review of the project agreement. The attached letter (Appendix B) is a copy of the executive summary of their full report. Hill Dickinson has advised that the agreement is robust from a legal perspective. Interserve will occupy a specifically identified area within the boilerhouse by way of a lease agreement. Provisions have been made within the project agreement that will minimise the risk to the Trust. The lease is necessary because it will formally exclude the security of tenure provisions. If the Trust didn t have a formal lease arrangement this would give Interserve security of tenure when the contract expires or is terminated, which means Interserve would have the right to remain within the building. The lease will not be granted until the plant is installed and commissioned and the lease will be terminated if the project agreement is terminated. As part of the approvals process, the Board will need to pass certain resolutions approving the CEF main scheme (Appendix C). For reasons connected with the funding arrangements through the Cooperative Bank, these resolutions (and the accompanying minutes) are more extensive than the resolutions which the Board would conventionally pass. Hill Dickinson has advised that despite their approaches to the Cooperative Bank, there is no flexibility over their wording. Certificates of the specimen signatures of the Trust s signatories (Appendix D) and confirming which drafts of the contract and legal documents are approved for execution by the Trust (Appendix E) will also need to be issued. 10. Future Development The STOR project is being procured separately with the preferred supplier MCW. The current status is that a provision export agreement has finally been reached with the district network operator (DNO) to allow 1.5MVA export of electricity. Once the extent of the project and guaranteed savings are confirmed and identified with MCW and CEF a further briefing paper will be submitted to the Board.

4 Airedale NHS Foundation Trust Board of Directors: 27 March 2013 Title: Briefing Paper for Carbon Energy Fund Project Authors: Steve Blenkinsop / Mark Walsh 11. Recommendation The Board is asked to note the status of the STOR project and requested to proceed to contract signature on the CEF main scheme and to also pass the resolutions in Appendix C.

5 Annual discounted cashflow, /yr Annual discounted cashflow, /yr Appendix A OVERVIEW OF CEF SCHEME Proposed Scheme CHP New Boilers Lighting Improvements BMS Improvements Steam generators Electrical & Mechanical Works Non Energy Savings Replacement of Chiller Plant Description New 835kW high efficiency Combined Heat and Power plant Three new dual fuel hot water boilers to improve efficiency of heat supply and replace current boilers Major lighting upgrade of circa 3000 lights (includes fittings) Improvements to building comfort and efficiency improvements New generators to maintain supply for CSSD / Theatres / Kitchen Integrate all plant and equipment into site operations Maintenance of boilers and ancillary plant moves to Interserve and lighting replacement reduces lamp replacement on-going This is covered in Interserve scheme and so avoided capital cost (as it capital budget) Capital Investment 3,461,054 capital investment for scheme above SENSITIVITY ANALYSIS - EXCLUDES GRANT (See note on impact of grant on reducing finance repayment) Assumptions CEF Base Case used 2.5% energy price increase per annum value applied to both electricity and gas DECC Energy Price Forecasts are taken from DECC Interdepartmental Analysts' Group The public sector DECC energy prices have been used (see "Energy Price Forecast DECC" for values and graphs for energy prices) The future annual % increase from the DECC values has been calculated and applied to the current energy prices paid by Airedale in 2012/13. The tables presented are for No VAT and VAT scenarios Discount Rate is 3.5% CRC Savings included Impact of Grant Application (With VAT) Grant (No Vat) Additional Studies Cost of grant interest only repayment Total Finance Charge No Grant Total over 15 years ( simple ) Cost of Borrowing Reduction in Finance Charge Capital charges on grant if all capital Cash Release from Grant* Depreciation Charge Charge to I/E 1,668,000 inclusive of VAT 1,340,000 excluding VAT 50,000 excluding VAT 58,380 Calculated 300,696 Hard coded 4,510,440 Cost of finance 86.9 COOP (via Interserve) 130,424 /year 58,380 /year 72,044 /year 111,200 /year based on 15 year life - 39,156 /year Impact of removing energy inflation. So for DECC scenarios 1st Year 2014 Discount Energy on real price increase used Sensitivity Analysis No VAT UPS Inflation VAT NPV Non Energy Unitary Energy Saving, * Saving, Repayment, Saving, Rate Inflation Energy Inflation First Year NPV Saving, Base Case CEF Proforma Std 508,776 81, ,486 85, % 2.50% 2.50% 0% 1,159,232 0% 75, ,111 [Note: for CEF base case removing energy inflation means prices are as 2012/13 for duration] DECC Central Price Rise + Carbon (CRC) 595,092 81, , , % 2.50% 2.50% 0% 2,324,492 0% 160,520 2,130,584 [Note: for DECC scenarios inflation removed and real price increases used] DECC High Price Rise + Carbon (CRC) 598,327 81, , , % 2.50% 2.50% 0% 2,282,150 0% 120,925 2,087,295 [Note: for DECC scenarios inflation removed and real price increases used] DECC Low Price Rise + Carbon (CRC) 500,682 81, ,486 79, % 2.50% 2.50% 0% 1,951,445 0% 67,369 1,764,655 [Note: for DECC scenarios inflation removed and real price increases used] * Includes CRC saving Impact of removing energy inflation. So for DECC scenarios 1st Year 2014 Discount Energy on real price increase used Sensitivity Analysis With VAT UPS Inflation VAT NPV Non Energy Unitary Energy Saving, * Saving, Repayment, Saving, Rate Inflation Energy Inflation First Year NPV Saving, Base Case CEF Proforma Std 610,531 97, , , % 2.50% 2.50% 20% 1,391,078 0% 90, ,933 [Note: for CEF base case removing energy inflation means prices are as 2012/13 for duration] DECC Central Price Rise + Carbon (CRC) 705,560 97, , , % 2.50% 2.50% 20% 2,773,148 0% 184,074 2,540,458 [Note: for DECC scenarios inflation removed and real price increases used] DECC High Price Rise + Carbon (CRC) 709,442 81, , , % 2.50% 2.50% 20% 2,517,987 0% 128,834 2,284,160 [Note: for DECC scenarios inflation removed and real price increases used] DECC Low Price Rise + Carbon (CRC) 600,818 81, ,983 79, % 2.50% 2.50% 20% 2,121,141 0% 64,566 1,896,993 [Note: for DECC scenarios inflation removed and real price increases used] * Includes CRC saving 200, , , , , ,000 80,000 60,000 40,000 20,000 0 Discounted Annual Cash Flow Scenarios No VAT 250, , , ,000 50,000 0 Discounted Annual Cash Flow Scenarios With VAT CEF Base Case DECC High Price Scenario Years DECC Central Price Scenario DECC Low Price Scenario CEF Base Case DECC High Price Scenario Years DECC Central Price Scenario DECC Low Price Scenario

6 Carbon and Energy Fund ITT Financial model and bid proforma Airedale Core Bid 2 Decommissioned Laundry Rev 3 V22 Instructions to bidders Bidders to fill in just the cells shaded this colour. See guidance re changing cells. All calculations to be live, ie not calculations replaced by a number Where cells shaded this colour are already filled in these figures should be treated as draft figures Please add to this sheet to deal with aspects of your bid that the sheet does not anticipate Please ignore the various #div/0! messages, these should calculate correctly when the green cells are filled in VAT is generally excluded, and should not be added. There is a VAT amount that can be added to the NPV sheet, and that affects just the NPV sheet Core Energy Scheme Funding options available to the Trust CEF funded Contractor funded Trust funded Finance Rate /1000 invested /1000 invested CEF funded - Cost of finance incl capital repayment per 1000 Capital Indexation assumed in funding/ sloped finance rate 2.5% Grant - change this for the grant value to work through. Unitary Payment Breakdown year 1 p.a. Extra cash release p.a. p.a. Capital repayment element 300, , ,637 Operation and maintenance costs 189,533 Total cash release 189, ,533 Total annual unitary payment CEF funded ( incl VAT if on) 490,230 85, , ,170 Duration of contract after practical completion 15 years 15 years 15 years Amount of grant or ECA funding included Amount of capital funding required 3,461,054 3,461,054 3,561,054 Simple affordability calculations Total guaranteed savings 575, , ,767 Unitary payment 490, , ,170 Amount by which guarantee exceeds cost yr1 85,537 27, ,596 NPV of proposal over 15 years 1,159, , ,083 Investment per tonne of carbon saved Is the proposal no service no fee throughout? Yes Yes Yes

7 Test Trust Core Bid 2 Decommissioned Laundry Rev 3 V22 Carbon and Energy Fund ITT Financial model and bid proforma Bidders to fill in green shaded cells only. See guidance re changing cells, all calculations to be live, ie do not replace a calculation with a value Core Bid Decommissioned Laundry Compliant Option - 24 Hour CHP Run Description of Saving to be guaranteed Capital investment required ( non NHS ) Trust funded option capital investment required Annual OP & maintenance cost + lifecycle CHP including CHPQA compliance 1,368,533 1,368,533 80,058 Amounts for depreciation Biomass Renewables including fuel handling and emissions CHP 0 Boilers and boiler auxiliaries 398, ,500 Rest 3,561,054 Cooling and systems 114, ,696 Energy distribution systems Lighting retrofit 820, ,677 Steam system upgrade 123, ,042 Relocation steam gas main, water, condensate upgrades 43,833 43,833 Steam upgrade from 600kW to 2 x 1000kW & new gas meter 57,509 57,509 Controls BEMS 37,500 37,500 10,000 VSD's 57,500 57,500 Metering 30,000 30,000 Income generated (excl export CHP generation ) Rolled up interest Bank costs total 167, ,914 change Enhanced capital allowances ( negative sum) see Up & savings proforma cell E21-100,000 CDMC Costs 6,000 6,000 Total OPEX charges (steam generators removed) 55,737 Carbon Manager 5,000 Administration of bid and project fees recovery 77,442 77,442 Binder Points 2,500 2,500 DNO and associated works, full description TBC 78,000 78,000 Total Capital Elements before oncosts 3,283,646 3,383, ,795 Design costs as a percentage of capital cost* 0.0% 0.0% Savings risk premium as a percentage of the o&m cost* 0.0% Prelims incl insurance costs as a percentage* 0.0% 0.0% 2.5% Contribution to overheads* 0.0% 0.0% 3.5% Profit margin as a percentage of total costs* 0.0% 0.0% 4.0% Carbon and Energy Fund Admin costs ( NCIS ) 4.0% 4.0% 4.0% Cef fee Totals including all costs 3,461,054 3,561, , ,407 Notes to this section The percentages quoted in each bidders framework ITT are to be used in the yellow boxes or reduced for all projects under the framework - they may not be increased. NCIS amounts may not be changed CEF Fee NCIS payment due on contract award 131, ,407 NCIS payment due on practical completion 46,061 NCIS payment due on each anniversary of the contract 23,031 ( indexation applies in later years ) as does VAT 2.50%

8

9

10

11

12

13

14 Appendix C AIREDALE NHS FOUNDATION TRUST EXTRACT OF THE MINUTES OF A MEETING OF THE BOARD HELD AT AIREDALE GENERAL HOSPITAL ON 27 MARCH 2013 AT 9.00 A.M. Present: Chairman and Non-Executive Directors Colin Millar, Chairman David Adam, Non Executive Director Jeff Colclough, Non Executive Director Ronald Drake, Non Executive Director Sally Houghton, Non Executive Director Anne Gregory, Non Executive Director Executive Directors Bridget Fletcher, Chief Executive Andrew Copley, Director of Finance Dr Andrew Catto, Medical Director Rob Dearden, Director of Nursing Ann Wagner, Director of Strategy and Business Development 1 NOTICE OF MEETING AND QUORUM The Chairman confirmed that: 1.1 all Directors had received notice of the meeting; and 1.2 a quorum of Directors was present, in accordance with the Trust s standing orders and standing financial instructions and other applicable governance procedures. [Other business] 2 RE-PROVISION OF ENERGY AND ENERGY MANAGEMENT FACILITIES AT AIREDALE GENERAL HOSPITAL 2.1 Declaration of interests The Chairman confirmed, as previously noted at the meeting, that the Directors had been reminded of the requirement to declare any interest (and v1 Page 1

15 none had been declared), in accordance with the Trust s standing orders and standing financial instructions and other applicable governance procedures. 2.2 Background The Chairman advised the meeting that the Trust wishes to improve the quality and efficiency of its energy infrastructure at Airedale General Hospital (the Hospital). As such, the Trust had invited tenders from suppliers approved under the Carbon and Energy Fund framework in relation to a project to re-provide energy and energy management facilities at the Hospital (the Project) Interserve Construction Limited (company number ) of 395 George Road, Erdington, Birmingham B23 7RZ had been granted preferred bidder status for the Project, following assessment during the framework procurement The Board noted that the relevant documentation relating to the Project was nearly complete. It was noted that, in order for the new energy and energy management facilities to be made available to the Hospital, the Trust is required to enter into and accede to certain documentation in relation to the above. 2.3 Project documents The Chairman produced to the meeting a paper produced by Andrew Copley, Director of Finance, and a letter report from the Trust s legal advisers, Hill Dickinson LLP, in relation to the following draft documents: a project agreement between Airedale NHS Foundation Trust and Interserve Construction Limited for the re-provision of energy and energy management facilities (the Project Agreement); a certificate confirming that Interserve Construction Limited is permitted to commence construction and/or installation works; a direct agreement between Airedale NHS Foundation Trust and Interserve Construction Limited and its funder The Cooperative Bank P.L.C.; and a lease of land at the Hospital to be granted by Airedale NHS Foundation Trust to Interserve Construction Limited, v1 Page 2

16 (together, the Documents) It was noted that the paper and the letter report referred to in paragraph confirmed that the Documents had been prepared in a way consistent with the full business case, and that the report identified the key obligations to be assumed by the Trust under the Documents Certificates requiring specimen signatures of the persons approved to execute the Documents and confirming the versions of each of the Documents approved for execution by the Trust were presented to the meeting (as appended to these minutes, as Appendices 1 and 2 respectively). 2.4 Board approval and resolutions After careful consideration, the Board: confirmed its view that the Project is within the Trust s power and authority, and that the associated full business case had been prepared in accordance with and complies with the Trust s standing orders and standing financial instructions and other applicable governance procedures; RESOLVED that the Project and the associated full business case be approved; confirmed its view that, by virtue of the scheme of delegation operated by the Trust, any of the Trust's Executive Directors is authorised to negotiate, finalise and approve on behalf of the Trust the final form of the Documents; confirmed its view that, by virtue of the Trust s standing orders and standing financial instructions, and have authority 1 to execute and deliver each of the Documents on behalf of the Trust, and each other document or notice required to be executed or signed in connection with implementation of the Project; RESOLVED that (subject to such amendments as any of the Trust s Executive Directors may in his/her absolute discretion deem necessary 1 Trust to advise as to the identity of the authorised officers or named individuals v1 Page 3

17 or desirable) each of the Documents (other than the certificate of commencement referred to in paragraph , which is to be executed under hand) be executed by the Trust as a deed under seal, and that appropriate entries be made as required in the Trust s register of sealings, and that the certificate of commencement referred to in paragraph be signed under hand, and that the same be delivered; RESOLVED that and be severally authorised 2 to sign or execute on behalf of the Trust (subject to such amendments as any of the Trust s Executive Directors may in his/her absolute discretion deem necessary or desirable) all other documents and to do all other acts and things as any of the Trust s Executive Directors may consider necessary or desirable in connection with implementation of the Project; confirmed its view that, by virtue of the Trust s standing orders and standing financial instructions, each of the Documents, and each other document required to be executed or signed in connection with implementation of the Project, would (once amended as considered necessary by any of the Trust s Executive Directors, delivered and completed) bind the Trust, Interserve Construction Limited and each other party to those agreements or other documents for the performance of the obligations stated in those agreements or other documents; and RESOLVED that: either of the persons referred to in paragraph 2.4.6, the Board secretary or another relevant Trust Officer be authorised to complete and sign a certificate of specimen signatures in the form appended to these minutes as Appendix 1; the Executive Director approving the versions of each of the Documents for execution by the Trust be authorised to complete and sign a certificate to that effect in the form appended to these minutes as Appendix 2; and either of the persons referred to in paragraph 2.4.6, the Board secretary or another relevant Trust Officer be authorised to 2 Trust to advise as to the identity of the authorised officers or named individuals v1 Page 4

18 produce to Interserve Construction Limited a certified copy of the standing orders and standing financial instructions of the Trust. Chairman v1 Page 5

19 APPENDIX 1 [ON HEADED PAPER OF AIREDALE NHS FOUNDATION TRUST] Interserve Construction Limited 395 George Road Erdington Birmingham B23 7RZ [ ] 2013 Re-provision of energy and energy management facilities at Airedale General Hospital I, [Name of officer], the [Role of relevant officer] of Airedale NHS Foundation Trust, refer to the project agreement proposed to be entered into between Airedale NHS Foundation Trust (1) and Interserve Construction Limited (2) (the Project Agreement). Terms defined in the Project Agreement shall have the same meanings in this certificate. I hereby certify that: 1 by authority conferred: 1.1 by resolutions passed by the Trust s Board at a meeting held on 27 March 2013 (the Meeting); 1.2 the Trust s standing orders and standing financial instructions; and 1.3 the scheme of delegation operated by the Trust, the persons listed below have the authority to sign the Project Agreement and the other Documents (as defined in the minutes of the Meeting) to which Airedale NHS Foundation Trust is a party: [Name of officer], [Role of officer] [Name of officer], [Role of officer] 2 the signature appearing opposite the name of such person is his/her true signature: Name Position Specimen signature Page 6

20 Name Position Specimen signature This certificate is authorised by the Trust... Name: Position/office: 2013 Page 7

21 APPENDIX 2 [ON HEADED PAPER OF AIREDALE NHS FOUNDATION TRUST] Interserve Construction Limited 395 George Road Erdington Birmingham B23 7RZ [ ] 2013 Re-provision of energy and energy management facilities at Airedale General Hospital I, [Name of officer], the [Role of relevant officer] of Airedale NHS Foundation Trust, refer to the project agreement proposed to be entered into between Airedale NHS Foundation Trust (1) and Interserve Construction Limited (2) (the Project Agreement), and to resolutions passed by the Trust s Board at a meeting held on 27 March Terms defined in the Project Agreement shall have the same meanings in this certificate. I hereby certify that the versions of each of the Documents approved for execution by the Trust are: Document Parties Draft Project Agreement Airedale NHS Foundation Trust (1) and Interserve Draft, dated [ ] 2013 Construction Limited (2) Certificate of Airedale NHS Foundation As in Schedule 28 to the Commencement Trust (1) and Interserve Construction Limited (2) above-referred draft of the Project Agreement Funder's Direct Agreement Airedale NHS Foundation As in Schedule 6 to the Trust (1), Interserve above-referred draft of the Construction Limited (2) and Project Agreement The Co-operative Bank P.L.C. Leases, of land at Airedale General Hospital Airedale NHS Foundation Trust (1) and Interserve Construction Limited (2) As in Schedule 7 to the above-referred draft of the Project Agreement This certificate is authorised by the Trust. Page 8

22 .. Name: Position/office: 2013 Page 9

23 Appendix D [ON HEADED PAPER OF AIREDALE NHS FOUNDATION TRUST] Interserve Construction Limited 395 George Road Erdington Birmingham B23 7RZ [ ] 2013 Re-provision of energy and energy management facilities at Airedale General Hospital I, [Name of officer], the [Role of relevant officer] of Airedale NHS Foundation Trust, refer to the project agreement proposed to be entered into between Airedale NHS Foundation Trust (1) and Interserve Construction Limited (2) (the Project Agreement). Terms defined in the Project Agreement shall have the same meanings in this certificate. I hereby certify that: 1 by authority conferred: 1.1 by resolutions passed by the Trust s Board at a meeting held on 27 March 2013 (the Meeting); 1.2 the Trust s standing orders and standing financial instructions; and 1.3 the scheme of delegation operated by the Trust, the persons listed below have the authority to sign the Project Agreement and the other Documents (as defined in the minutes of the Meeting) to which Airedale NHS Foundation Trust is a party: [Name of officer], [Role of officer] [Name of officer], [Role of officer] 2 the signature appearing opposite the name of such person is his/her true signature: Name Position Specimen signature Page 1

24 Name Position Specimen signature This certificate is authorised by the Trust... Name: Position/office: 2013 Page 2

25 Appendix E [ON HEADED PAPER OF AIREDALE NHS FOUNDATION TRUST] Interserve Construction Limited 395 George Road Erdington Birmingham B23 7RZ [ ] 2013 Re-provision of energy and energy management facilities at Airedale General Hospital I, [Name of officer], the [Role of relevant officer] of Airedale NHS Foundation Trust, refer to the project agreement proposed to be entered into between Airedale NHS Foundation Trust (1) and Interserve Construction Limited (2) (the Project Agreement), and to resolutions passed by the Trust s Board at a meeting held on 27 March Terms defined in the Project Agreement shall have the same meanings in this certificate. I hereby certify that the versions of each of the Documents approved for execution by the Trust are: Document Parties Draft Project Agreement Airedale NHS Foundation Trust (1) and Interserve Draft, dated [ ] 2013 Construction Limited (2) Certificate of Airedale NHS Foundation As in Schedule 28 to the Commencement Trust (1) and Interserve Construction Limited (2) above-referred draft of the Project Agreement Funder's Direct Agreement Airedale NHS Foundation As in Schedule 6 to the Trust (1), Interserve above-referred draft of the Construction Limited (2) and Project Agreement The Co-operative Bank P.L.C. Leases, of land at Airedale General Hospital Airedale NHS Foundation Trust (1) and Interserve Construction Limited (2) As in Schedule 7 to the above-referred draft of the Project Agreement This certificate is authorised by the Trust. Page 1

26 .. Name: Position/office: 2013 Page 2

2 BUSINESS OF THE MEETING

2 BUSINESS OF THE MEETING (the "Company") Minutes of a meeting of the board of directors of the Company held at "Meeting"). Present on (the ("Chairman") In attendance 1 QUORUM AND NOTICE 1.1 It was resolved to appoint as Chairman

More information

NHS Carbon and Energy Fund ( CEF ) Outline for Trusts wishing to consider using the CEF

NHS Carbon and Energy Fund ( CEF ) Outline for Trusts wishing to consider using the CEF NHS Carbon and Energy Fund ( CEF ) Outline for Trusts wishing to consider using the CEF November 2012 Page 1 Introduction The Carbon and Energy Fund is a NHS initiative to make it easier for Trusts to

More information

This annexure should be completed and signed by the Bidder s authorised personnel as indicated below:

This annexure should be completed and signed by the Bidder s authorised personnel as indicated below: ANNEXURE I: PRICING SCHEDULE This annexure should be completed and signed by the Bidder s authorised personnel as indicated below: 1 Please indicate your total bid price in Table 1.1 below (compulsory)

More information

Haringey Green Deal Pilot

Haringey Green Deal Pilot Haringey Green Deal Pilot Background Investment in energy efficiency can provide long term cost savings to householders, as well as increased thermal comfort. However, many people lack the up front capital

More information

SHORT TERM OPERATING RESERVE. General Description of the Service. 14 th April 2017

SHORT TERM OPERATING RESERVE. General Description of the Service. 14 th April 2017 SHORT TERM OPERATING RESERVE General Description of the Service 14 th April 2017 1. Introduction This document provides a summary of the service of Short Term Operating Reserve (STOR) as set out in detail

More information

A Guide to: The Green Deal and The Energy Company Obligation

A Guide to: The Green Deal and The Energy Company Obligation A Guide to: The Green Deal and The Energy Company Obligation This Guide is based on the November 2011 consultation documents and will be updated as the details are finalised. PART 1 - The Green Deal What

More information

Impact Assessment (IA)

Impact Assessment (IA) Title: : AMENDMENTS TO PART 3, CHAPTER 1 OF THE ENERGY ACT 2008 (as amended): NUCLEAR SITES: DECOMMISSIONING AND COST RECOVERY IA No: DECC0089 Lead department or agency: DECC Other departments or agencies:

More information

Introduction to RELCOST. Carolyn Roos, Ph.D. Northwest CHP Technical Assistance Partnerships Washington State University Energy Program

Introduction to RELCOST. Carolyn Roos, Ph.D. Northwest CHP Technical Assistance Partnerships Washington State University Energy Program Introduction to RELCOST Carolyn Roos, Ph.D. Northwest CHP Technical Assistance Partnerships Washington State University Energy Program 1 Overview of RELCOST Presentation Outline Program use Results A review

More information

UK EE Financing Programmes: An Update

UK EE Financing Programmes: An Update UK EE Financing Programmes: An Update Dr. Steven Fawkes ACEEE Financing Forum 15 th May 2013 Agenda Update on: Green Deal ECO Green Investment Bank Other programmes, projects and initiatives 2 Green Deal

More information

The Clatterbridge Cancer Centre NHS Foundation Trust Business Implementation Plan. Prop Co (NO APPENDICES)

The Clatterbridge Cancer Centre NHS Foundation Trust Business Implementation Plan. Prop Co (NO APPENDICES) Prop Co (NO APPENDICES) 1 CONTENTS 1 Context 4 2 Overview of PropCo 5 2.1 Form of PropCo 5 2.2 Scope of PropCo 5 2.3 Included services 6 2.4 Excluded services 6 2.5 Services to be included subject to confirming

More information

Board Meeting Tuesday, 20th September 2005 Board Paper No. 05/62

Board Meeting Tuesday, 20th September 2005 Board Paper No. 05/62 Greater Glasgow Health Board Board Meeting Tuesday, 20th September 2005 Board Paper No. 05/62 Acting Chief Executive, Primary Care Division The NHS Board is asked to :- Gartnavel Royal Hospital Contract

More information

A guaranteed savings case study. Fixing the NHS estate in a broken economy

A guaranteed savings case study. Fixing the NHS estate in a broken economy A guaranteed savings case study Fixing the NHS estate in a broken economy Schneider Electric, The global specialist in energy management Making energy: Energy production & transmission > Safe > Reliable

More information

Hansard Global plc. (incorporated in the Isle of Man with company number C) Mr G S Marr Box 192

Hansard Global plc. (incorporated in the Isle of Man with company number C) Mr G S Marr Box 192 THIS DOCUMENT IS IMPORTANT AND REQUIRES YOUR IMMEDIATE ATTENTION. If you are in any doubt about the contents of this document, you should consult a person authorised under the Financial Services and Markets

More information

The Energiesprong concept is based on the assumption that the capital investment required to deliver net-zero-energy refurbishments is covered by:

The Energiesprong concept is based on the assumption that the capital investment required to deliver net-zero-energy refurbishments is covered by: Energiesprong UK Limited National Energy Centre Davy Avenue, Knowlhill Milton Keynes MK5 8NG 30 November 2015 Energiesprong UK finance model London Introduction The purpose of the financial model is to

More information

VAT Considerations For District Heating Scottish Futures Trust

VAT Considerations For District Heating Scottish Futures Trust www.pwc.co.uk VAT Considerations For District Heating Scottish Futures Trust October 2014 Important notice This report is provided solely in connection with our advice to Scottish Futures Trust on VAT

More information

THAMESWEY CENTRAL MILTON KEYNES LIMITED. BUSINESS PLAN 2018 Covering the period

THAMESWEY CENTRAL MILTON KEYNES LIMITED. BUSINESS PLAN 2018 Covering the period THAMESWEY CENTRAL MILTON KEYNES LIMITED BUSINESS PLAN 2018 Covering the period 2018-2021 Address: 2 nd Floor, Gloucester Chambers, Jubilee Square, Woking, Surrey GU21 6GA Registered Address: The St Botolph

More information

Responsible Property Investment (RPI) Summary Policy

Responsible Property Investment (RPI) Summary Policy Responsible Property Investment (RPI) Summary Policy Introduction DTZ Investors is a full service vertically integrated real estate manager. We have been operating in the UK since 1968 and in Continental

More information

SPECIAL CONDITIONS OF TENDER

SPECIAL CONDITIONS OF TENDER Page 1 SPECIAL CONDITIONS OF TENDER A. INTRODUCTION The following documents are available on http://emits.esa.int/ under "Reference Documentation" --> "Administrative Documents": ESA Procurement Regulations

More information

Title of report: Leeds City Region Energy Saving Scheme

Title of report: Leeds City Region Energy Saving Scheme Name of meeting: CABINET Date: 9 APRIL 2013 Title of report: Leeds City Region Energy Saving Scheme Providing Energy Efficiency Green Deal Loans and Energy Company Obligation Grants for Private Sector

More information

Rethinking Repairs. A New Approach to Gas Procurement. Jerry Austin Executive Director for Property Sutton Housing Partnership

Rethinking Repairs. A New Approach to Gas Procurement. Jerry Austin Executive Director for Property Sutton Housing Partnership Rethinking Repairs A New Approach to Gas Procurement Jerry Austin Executive Director for Property Sutton Housing Partnership 07500 550 211 Agenda Guide to today s presentation 1. Traditional approach has

More information

Procurement models for District Energy System Projects

Procurement models for District Energy System Projects Procurement models for District Energy System Projects IDEA Conference Presented by Tomasz Smetny-Sowa, Senior Director Energy Services Acquisition Program June 13, 2018 Real Property Services Branch Public

More information

What s in the EESSH? Jonathan Grant Scottish Government

What s in the EESSH? Jonathan Grant Scottish Government What s in the EESSH? Jonathan Grant Scottish Government Background Sustainable Housing Strategy tackling fuel poverty and climate change. 2012 consultation. Stakeholder working group. Case study research

More information

TENDER NUMBER: PH. NO

TENDER NUMBER: PH. NO TENDER NUMBER: PH. NO. 09.04.2018 INSPECTION AND MAINTENANCE OF THE SECURITY FENCE FOR THE HOMEOWNERS ASSOCIATION OF PINEHAVEN COUNTRY ESTATE Contact Person: Beverley Venter Contact Number: (011) 662-1709

More information

FIRM FAST RESERVE EXPLANATION AND TENDER GUIDANCE DOCUMENT

FIRM FAST RESERVE EXPLANATION AND TENDER GUIDANCE DOCUMENT FIRM FAST RESERVE EXPLANATION AND TENDER GUIDANCE DOCUMENT Issue #2 1 April 2013 National Grid Electricity Transmission plc National Grid House Warwick Technology Park Gallows Hill Warwick CV34 6DA Website:

More information

Cabinet. 27 July Classification: Part Exempt (Appendix 1 Exempt) Report of: Corporate Director Place. Housing Capital Projects: Pipeline schemes

Cabinet. 27 July Classification: Part Exempt (Appendix 1 Exempt) Report of: Corporate Director Place. Housing Capital Projects: Pipeline schemes Cabinet 27 July 2017 Report of: Corporate Director Place Classification: Part Exempt (Appendix 1 Exempt) Housing Capital Projects: Pipeline schemes Lead Member Originating Officer(s) Wards affected Community

More information

Finance, Performance and Strategic Planning Committee Terms of Reference

Finance, Performance and Strategic Planning Committee Terms of Reference Finance, Performance and Strategic Planning Committee Terms of Reference Document Control: Document Document Owner: Board of Directors JPUH Finance, Performance and Strategic Planning Electronic File Name:

More information

Case-study location: Battaglia Terme\Galzignano Terme

Case-study location: Battaglia Terme\Galzignano Terme Economic modelling of low-temperature geothermal energy Case-study location: Battaglia Terme\Galzignano Terme Activity 4.3 in WP 4 Partner: PADUA Coordinated by: UM Index 1. INTRODUCTION... 3 2. ASSESSMENT

More information

The Warm Front Scheme

The Warm Front Scheme The Warm Front Scheme LONDON: The Stationery Office 14.35 Ordered by the House of Commons to be printed on 2 February 2009 REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 126 Session 2008-2009 4 February

More information

Authorised Officer is any officer permitted by an Appropriate Officer to authorise orders and contracts as per clause 2.5.

Authorised Officer is any officer permitted by an Appropriate Officer to authorise orders and contracts as per clause 2.5. PART 3G Contracts Standing Orders 2018/19 Definitions Aggregation is the combining together of the total contract valuespend from separate contracts where they meet a single requirement for works, goods

More information

THAMESWEY SOLAR LIMITED

THAMESWEY SOLAR LIMITED THAMESWEY SOLAR LIMITED BUSINESS PLAN 2017-19 Address: 2 nd Floor, Gloucester Chambers, Jubilee Square, Woking, Surrey GU21 6GA Registered Address: The St Botolph Building, 138 Houndsditch, London, EC3A

More information

INVITATION FOR QUOTATION. TEQIP-III/2018/mntj/Shopping/6

INVITATION FOR QUOTATION. TEQIP-III/2018/mntj/Shopping/6 INVITATION FOR QUOTATION TEQIP-III/2018/mntj/Shopping/6 22-Jan-2018 To,.. Sub: Invitation for Quotations for supply of Goods Dear Sir, 1. You are invited to submit your most competitive quotation for the

More information

REQUEST FOR PROPOSAL RFP-RCU2012Q2/1

REQUEST FOR PROPOSAL RFP-RCU2012Q2/1 GOVERNMENT OF THE TURKS AND CAICOS ISLANDS Government House Grand Turk Telephone: (649) 941 2801 Fax: (649) 946 1648 REQUEST FOR PROPOSAL RFP-RCU2012Q2/1 FOR THE PROVISION OF INFORMATION TECHNOLOGY SERVICES

More information

PROCUREMENT BUSINESS CASE

PROCUREMENT BUSINESS CASE PROCUREMENT BUSINESS CASE In accordance with the Procurement and Contracts Rules and Procedures (PCRP) (see section 3.1.1): a formal business case is required for any procurement with a total value above

More information

Profit from early action with the Carbon Trust Standard

Profit from early action with the Carbon Trust Standard Profit from early action with the Carbon Trust Standard A Financial Director s guide to the Carbon Reduction Commitment Energy Efficiency Scheme Last updated: October 2009 2 03 Introduction Click on the

More information

STANDARD CVA CONDITIONS

STANDARD CVA CONDITIONS STANDARD CVA CONDITIONS Introduction 1. These standard CVA conditions should be read together with the Proposal to which they are Appended ( the Proposal ) and the definitions set out in the Proposal will

More information

ScottishPower Consolidated Segmental Statement for the year ended 31 December 2017

ScottishPower Consolidated Segmental Statement for the year ended 31 December 2017 ScottishPower Consolidated Segmental Statement for the year ended 31 December 2017 Required under Standard Condition 16B of Electricity Generation Licences and Standard Condition 19A of Electricity and

More information

Relocation Expenses Policy and Procedure

Relocation Expenses Policy and Procedure Relocation Expenses Policy and Procedure Ratification Process Lead Author: Developed by: Approved by: Ratified on and by: Senior OD & HR Manager, C&P CCG Senior OD & HR Manager, C&P CCG Joint Consultation

More information

Lecture in Energy Economics: Life Cycle Cost Analysis for Bankable Projects in Sustainable Energy

Lecture in Energy Economics: Life Cycle Cost Analysis for Bankable Projects in Sustainable Energy Lecture in Energy Economics: Life Cycle Cost Analysis for Bankable Projects in Sustainable Energy INOGATE Programme New ITS Project, Ad Hoc Expert Facility (AHEF) Task AM-54-55-56 Slides prepared by: Ali

More information

THIS DOCUMENT IS IMPORTANT AND REQUIRES YOUR IMMEDIATE ATTENTION.

THIS DOCUMENT IS IMPORTANT AND REQUIRES YOUR IMMEDIATE ATTENTION. THIS DOCUMENT IS IMPORTANT AND REQUIRES YOUR IMMEDIATE ATTENTION. If you are in any doubt as to what action you should take, you are recommended to seek your own personal financial advice immediately from

More information

Energy Efficiency. Green Deal was No deal for social housing. So how do you maximise the funding for social housing energy efficiency works?

Energy Efficiency. Green Deal was No deal for social housing. So how do you maximise the funding for social housing energy efficiency works? Energy Efficiency Green Deal was No deal for social housing. So how do you maximise the funding for social housing energy efficiency works? Farooq Mohammed, Director 22 May 2013 CIH Conference / Nottingham

More information

Energy Company Obligation (ECO): Help to Heat ( )

Energy Company Obligation (ECO): Help to Heat ( ) Energy Company Obligation (ECO): Help to Heat (2017-2018) Government Response - SEA Briefing The consultation on the ECO: Help to Heat ran between 29 th June 2016 and 17 th August 2016. The consultation

More information

Multifamily Buildings (5 or more units)

Multifamily Buildings (5 or more units) May 2017 Multifamily Buildings (5 or more units) Full-Service Energy Efficient Building Services Authorization and Agreement for Multifamily Rental Building Energy Assessment Building Contact Information

More information

(CALL FOR PROPOSALS) FAST TRACK FEASIBILITY STUDIES

(CALL FOR PROPOSALS) FAST TRACK FEASIBILITY STUDIES Page 1 SPECIAL CONDITIONS OF TENDER FOR THE Integrated Applications Promotion (IAP) Programme (CALL FOR PROPOSALS) FAST TRACK FEASIBILITY STUDIES Page 2 INTRODUCTION For the purposes of this Call for Proposals

More information

FINANCE AND TREASURY COMMITTEE TERMS OF REFERENCE

FINANCE AND TREASURY COMMITTEE TERMS OF REFERENCE 1. Purpose FINANCE AND TREASURY COMMITTEE TERMS OF REFERENCE 1.1 The purpose of the Finance and Treasury Committee ( the Committee ) is to exercise delegated authority in relation to certain finance and

More information

BID DOCUMENT (DNIT) FOR ASSIGNING THE CONTRACT FOR SALE OF UNUSED AND USED QUESTION PAPER BOOKLET/LAST PACKET OF THE EXAMINATIONS

BID DOCUMENT (DNIT) FOR ASSIGNING THE CONTRACT FOR SALE OF UNUSED AND USED QUESTION PAPER BOOKLET/LAST PACKET OF THE EXAMINATIONS BID DOCUMENT (DNIT) FOR ASSIGNING THE CONTRACT FOR SALE OF UNUSED AND USED QUESTION PAPER BOOKLET/LAST PACKET OF THE EXAMINATIONS BOARD OF SCHOOL EDUCATION HARYANA, BHIWANI 1 BRIEF INFORMATION ON BID DOCUMENT

More information

ECMWF Copernicus Procurement

ECMWF Copernicus Procurement ECMWF Copernicus Procurement Invitation to Tender CLARIFICATIONS Clarifications issued 28 November 2017 ITT Ref: COP_031 ISSUED BY: ECMWF Administration Department Procurement Section We are pleased to

More information

Policy and Procedures

Policy and Procedures Procurement Policy and Procedures Page 1 of 23 Document Version Control Version Description Date Approval Number 0.1 for Discussion to P&R 01/04/2003 P&R noted 0.2 for Discussion to P&R 30/04/2003 P&R

More information

Promoting Energy Efficiency in the UK Landscape and Considerations

Promoting Energy Efficiency in the UK Landscape and Considerations EXTERNAL Promoting Energy Efficiency in the UK Landscape and Considerations Sustainable Energy Investment Forum, Dublin Ioannis Orfanos Business Partner, Commercial & Corporate Finance Advisory Sounding

More information

Facilities & Property Capital Expenditure

Facilities & Property Capital Expenditure Irish Water Facilities & Property Capital Expenditure Interim Price Control Submission 2014-2016 Document No: IW-IPC-004 Contents 1 Executive Summary 1 2 Assumptions 2 2.1 Activity Metrics 2 2.2 LA Legacy

More information

The Green Deal Finance Company Briefing Pack

The Green Deal Finance Company Briefing Pack The Green Deal Finance Company Briefing Pack The Green Deal Finance Company The Green Deal Finance Company (TGDFC) is a not-for-profit company set up to provide the lowest cost finance to the Green Deal,

More information

Cab O1 3/7 BARNSLEY METROPOLITAN BOROUGH COUNCIL. This matter is a Key Decision within the Council s definition and has not

Cab O1 3/7 BARNSLEY METROPOLITAN BOROUGH COUNCIL. This matter is a Key Decision within the Council s definition and has not Services Finance Property & Information and Assistant Chief Executive, Executive, Legal & Governance Report of the Assistant Chief been included in the relevant Forward Plan This matter is a Key Decision

More information

DRAFT STCP 18-1 Issue 004 Connection and Modification Application

DRAFT STCP 18-1 Issue 004 Connection and Modification Application STCP 18-1 Connection and Modification Application Draft Issue 004 - June 2014 DRAFT STCP 18-1 Issue 004 Connection and Modification Application STC Procedure Document Authorisation Party Name of Party

More information

Yanino Waste Processing Plant City of St. Petersburg

Yanino Waste Processing Plant City of St. Petersburg Yanino Waste Processing Plant City of St. Petersburg Project Briefing 26 October 2009 Page 1 Table of Contents Sections 1. Executive Summary. 3 2. Waste Processing Industry in St. Petersburg.....4 3. Project

More information

Guidance on the development of Heat Supply Agreements for District Heating schemes

Guidance on the development of Heat Supply Agreements for District Heating schemes Guidance on the development of Heat Supply Agreements for District Heating schemes February 2018 CONTENTS Executive Summary... 3 1. Introduction... 4 1.1. Scope of guidance... 4 2. Overview of heat supply

More information

HomeServices Terms and Conditions

HomeServices Terms and Conditions HomeServices Terms and Conditions Contents Definitions 03 The Contract 04 Start date 04 Payment 14 Cancellation 14 Appointments 16 Product Renewal 16 Changes to contract 16 Safety Recommendations 17 Property

More information

YOUR QUESTIONS ABOUT HEATING AT DERWENTHORPE

YOUR QUESTIONS ABOUT HEATING AT DERWENTHORPE YOUR QUESTIONS ABOUT HEATING AT DERWENTHORPE This document sets out questions received from Derwenthorpe Residents Association about the communal heating system at Derwenthorpe and provides responses from

More information

sustainable finance for sustainable change picking up where we left off in 2010: Financing the Community

sustainable finance for sustainable change picking up where we left off in 2010: Financing the Community sustainable finance for sustainable change west midlands finance model for energy efficiency retrofit SHAP conference may 2018 picking up where we left off in 2010: Financing the Community 13% reductions

More information

Save Money by Saving Carbon

Save Money by Saving Carbon Save Money by Saving Carbon Decision Making in the NHS using Marginal Abatement Cost Curves Contents Background 2 What is a Marginal Abatement Cost (MAC) Curve? 2 Purpose of this document 3 Why would you

More information

Notice Inviting Tender for Printing of Accounts Manual of APDCL

Notice Inviting Tender for Printing of Accounts Manual of APDCL Tender for Printing of Accounts Manual of APDCL ASSAM POWER DISTRIBUTION COMPANY LTD Single Stage Two Envelope Procedure Tender No: APDCL/CGM(F&A)/PRN/Accounts Manual/2014/3 Date 11.6.2014 Notice Inviting

More information

DUKE ENERGY OHIO REQUEST FOR PROPOSALS FOR PEAKING/INTERMEDIATE POWER SUPPLY IN RESPONSE TO OHIO SENATE BILL 221

DUKE ENERGY OHIO REQUEST FOR PROPOSALS FOR PEAKING/INTERMEDIATE POWER SUPPLY IN RESPONSE TO OHIO SENATE BILL 221 DUKE ENERGY OHIO REQUEST FOR PROPOSALS FOR PEAKING/INTERMEDIATE POWER SUPPLY IN RESPONSE TO OHIO SENATE BILL 221 DUKE ENERGY OHIO Table of Contents Section Description Page 1.0 Purpose of Request for Proposals

More information

Terms of Reference Annex: Green Deal

Terms of Reference Annex: Green Deal Terms of Reference Annex: Green Deal 1. Interpretation 1.1 The definitions, below, apply to both this Annex and the Terms of Reference in relation to complaints brought to Ombudsman Services: against Participating

More information

OFFER. 1. Business name, name and address of precontractual parties

OFFER. 1. Business name, name and address of precontractual parties Form 1а Basic data on deposit Annex 1 OFFER 1. Business name, name and address of precontractual parties 1.1. Business name of bank 1.3. Name of consumer 1.2. Address of bank head office 1.4. Address of

More information

ARCHIVED DOCUMENT. Energy services at Hemel Hempstead General Hospital BEST PRACTICE PROGRAMME

ARCHIVED DOCUMENT. Energy services at Hemel Hempstead General Hospital BEST PRACTICE PROGRAMME Energy services at Hemel Hempstead General Hospital Energy services contract financed under the Private Finance Initiative Energy costs reduced by 12% Carbon dioxide emissions reduced by 33% I ENERGY EFFICIENCY

More information

Zero Waste: Edinburgh and Midlothian - Award of Food Waste Treatment Contract

Zero Waste: Edinburgh and Midlothian - Award of Food Waste Treatment Contract The City of Edinburgh Council 10.00 am, Thursday 13 December 2012 Zero Waste: Edinburgh and Midlothian - Award of Food Waste Treatment Contract Item number Report number Wards City wide Links Coalition

More information

Thank you for your Official Information Act request, received on 22 November You requested the following:

Thank you for your Official Information Act request, received on 22 November You requested the following: Reference: 20170386 20 December 2017 Thank you for your Official Information Act request, received on 22 November 2017. You requested the following: I request a copy all advice provided to either the Minister

More information

Energy Efficiency (EE) Financing Strategies and Considerations in Commercial Real Estate

Energy Efficiency (EE) Financing Strategies and Considerations in Commercial Real Estate Energy Efficiency (EE) Financing Strategies and Considerations in Commercial Real Estate Ioannis Orfanos Director, Green Value Associates Head of ULI Greece & Cyprus Sustainability Council 25 OCTOBER 2018

More information

We would welcome the opportunity to discuss any of these points in further detail.

We would welcome the opportunity to discuss any of these points in further detail. REA response - CfD Contract Terms Consultation The REA represents a wide variety of organisations, including generators, project developers, fuel and power suppliers, investors, equipment producers and

More information

Invitation to Tender

Invitation to Tender Invitation to Tender November 2016 BRIEF FOR CONSULTANT TO CARRY OUT A NETWORK ANALYSIS OF THE WESTERN ISLES GRID, A REVIEW OF BUDGET ESTIMATES RECEIVED AND A STUDY ON FUTURE INNOVATIVE CONNECTION OPTIONS

More information

STCP 16-1 Issue 005 Investment Planning

STCP 16-1 Issue 005 Investment Planning STCP 16-1 Issue 005 Investment Planning STC Procedure Document Authorisation Company Name of Party Representative Signature Date National Grid Electricity Transmission plc SP Transmission plc Scottish

More information

LOCAL GOVERNMENT FINANCE SETTLEMENT 2018/19

LOCAL GOVERNMENT FINANCE SETTLEMENT 2018/19 LOCAL GOVERNMENT FINANCE SETTLEMENT 2018/19 Report by Chief Financial Officer SCOTTISH BORDERS COUNCIL 21 December 2017 1 PURPOSE AND SUMMARY 1.1 This report provides an update to members on the contents

More information

UNIVERSITY OF PERADENIYA

UNIVERSITY OF PERADENIYA UNIVERSITY OF PERADENIYA INVITATION FOR BIDS (IFB) PURCHASING OF PHOTOCOPY PAPERS 1. The Chairman, University Procurement Committee on behalf of the University of Peradeniya now invites sealed bids from

More information

Changing FiT Payment Details

Changing FiT Payment Details Changing FiT Payment Details In order for us to deliver a quick and effective service that is simple for you, our FiT scheme will make payments directly into your bank account. Using the boxes below, please

More information

PROCUREMENT OF GOODS & SERVICES POLICY

PROCUREMENT OF GOODS & SERVICES POLICY ARK HOUSING ASSOCIATION LTD. [ARK] POLICY REF: F02 Version 2.1 November 2016 PROCUREMENT OF GOODS & SERVICES POLICY 1.0 INTRODUCTION 1.1 This policy describes how we will purchase, or procure, goods and

More information

VALUE FOR MONEY. Self-assessment statement for financial year

VALUE FOR MONEY. Self-assessment statement for financial year VALUE FOR MONEY Self-assessment statement for 2016-17 financial year WELCOME TO OUR REPORT This statement sets out how we ensure Yorkshire Housing is delivering value for money (VfM) and why it remains

More information

DATED [ ] 200[ ] NATIONAL GRID ELECTRICITY TRANSMISSION PLC (1) and [ ] (2) FAST RESERVE FRAMEWORK AGREEMENT

DATED [ ] 200[ ] NATIONAL GRID ELECTRICITY TRANSMISSION PLC (1) and [ ] (2) FAST RESERVE FRAMEWORK AGREEMENT DATED [ ] 200[ ] NATIONAL GRID ELECTRICITY TRANSMISSION PLC (1) and [ ] (2) FAST RESERVE FRAMEWORK AGREEMENT CONTRACT LOG NO: [NOTE Where Provider has an existing Fast Reserve clause in its CSA, Framework

More information

Boiler Care Products. Terms and Conditions

Boiler Care Products. Terms and Conditions Boiler Care Products Terms and Conditions Contents Definitions 03 The Contract 04 Start date 04 Exclusions 11 Payment 12 Cancellation 13 Appointments 16 Product Renewal 16 Changes to contract 16 Safety

More information

Bank s Mandate form. For companies, corporate entities, partnerships and unincorporated associations

Bank s Mandate form. For companies, corporate entities, partnerships and unincorporated associations About this form Bank s Mandate form For companies, corporate entities, partnerships and unincorporated associations This form: is an important part of our process in connection with the products and services

More information

Bank of Baroda inviting tenders from Gujarat Based Reputed Printers for F.Y with BOB Zonal Stationery Cell, Baroda. Ph.

Bank of Baroda inviting tenders from Gujarat Based Reputed Printers for F.Y with BOB Zonal Stationery Cell, Baroda. Ph. Bank of Baroda inviting tenders from Gujarat Based Reputed Printers for F.Y. 2013-14 with BOB Zonal Stationery Cell, Baroda. Ph. : 0265-2481717 Dear Sir, Sub. : Procurement of Printed Stationery Bank of

More information

DIRECTIVE This Directive Replaces Directive H

DIRECTIVE This Directive Replaces Directive H City of Kingston Community and Family Services A Department of Community Development Services Group Housing Programs Tel: 613-546-2695 ext. 4806 362 Montreal Street Fax: 613-546-9658 Kingston, ON K7K 3H5

More information

The Chartered Tax Adviser Examination

The Chartered Tax Adviser Examination The Chartered Tax Adviser Examination November 06 Suggested solutions Application and Interaction QUESTION 4 - VAT AND OTHER INDIRECT TAXES Peter Smith A&B Care Ltd First Street AD 4FG Dear Peter Northern

More information

REPORT ON STEAM PLANT CONTRACT UNIVERSITY OF RHODE ISLAND

REPORT ON STEAM PLANT CONTRACT UNIVERSITY OF RHODE ISLAND REPORT ON STEAM PLANT CONTRACT UNIVERSITY OF RHODE ISLAND EXECUTIVE SUMMARY The Office of Higher Education (OHE) Internal Audit Department (IAD) reviewed the steam services contract between the University

More information

Staff Car Lease Scheme

Staff Car Lease Scheme Staff Car Lease Scheme Under 100g/km C0 2 = Zero Road Tax Electric and Hybrid cars included Contact Staff Travel stafftravel@fhft.nhs.uk http://stafftravel.co/fph How to apply The Trust objectives are

More information

INSTITUTIONAL BIDDING PROCESS No. UNDPGCCA/SUR/IICA/02/2017

INSTITUTIONAL BIDDING PROCESS No. UNDPGCCA/SUR/IICA/02/2017 INSTITUTIONAL BIDDING PROCESS No. UNDPGCCA/SUR/IICA/02/207 I. GENERAL CONDITIONS. The Inter-American Institute for Cooperation on Agriculture (IICA) is the contracting party for this contract and in no

More information

INVITATION FOR QUOTATION. TEQIP-III/2017/uiet/Shopping/39

INVITATION FOR QUOTATION. TEQIP-III/2017/uiet/Shopping/39 INVITATION FOR QUOTATION TEQIP-III/2017/uiet/Shopping/39 29-Nov-2017 To, Sub: Invitation for Quotations for supply of Goods Dear Sir, 1. You are invited to submit your most competitive quotation for the

More information

Richmond Building Energy Challenge

Richmond Building Energy Challenge Richmond Building Energy Challenge Robert Greenwald, P.Eng., MBA, President (Principal) Robert Greenwald has 25 years of energy management experience including developing energy plans, determining opportunities,

More information

Steps to Success. Energy Efficiency Loans in Wales Applicant Supporting Information. Updated May 2018

Steps to Success. Energy Efficiency Loans in Wales Applicant Supporting Information. Updated May 2018 Steps to Success Energy Efficiency Loans in Wales Applicant Supporting Information Updated May 2018 Energy Efficiency Loans in Wales Congratulations! You re taking the first step towards saving your business

More information

Trust Board Meeting in Public: Wednesday 13 January 2016 TB Title Draft Accounts for Six Months Ended 30 September 2015

Trust Board Meeting in Public: Wednesday 13 January 2016 TB Title Draft Accounts for Six Months Ended 30 September 2015 Trust Board Meeting in Public: Wednesday 13 January 2016 Title Draft Accounts for Six Months Ended 30 September 2015 Status History For information This report allows the Trust Board to receive a progress

More information

INTERNAL CONTROLS, SYSTEMS AND PROCEDURES. Direct Lending Post Approval Amendments & Pre- Disbursement Process

INTERNAL CONTROLS, SYSTEMS AND PROCEDURES. Direct Lending Post Approval Amendments & Pre- Disbursement Process INTERNAL CONTROLS, SYSTEMS AND PROCEDURES Direct Lending Post Approval Amendments & Pre- Disbursement Process 1 TABLE OF CONTENTS 1. DEFINITIONS AND ABBREVIATIONS... 3 2. GUIDING PRINCIPLES... 4 3. POST

More information

ESA TENDERING STANDARDS FOR EXPRESS PROCUREMENT ( EXPRO & EXPRO+ ) PROPOSAL TEMPLATE V5

ESA TENDERING STANDARDS FOR EXPRESS PROCUREMENT ( EXPRO & EXPRO+ ) PROPOSAL TEMPLATE V5 Appendix 4 to ESA ITT AO/1-8266/15/NL/MP Page 1/15 ESA TENDERING STANDARDS FOR EXPRESS PROCUREMENT ( EXPRO & EXPRO+ ) PROPOSAL TEMPLATE V5 [COVER LETTER] From:... (Tenderer to insert name of the company/institute

More information

The Annual Audit Letter for Plymouth City Council

The Annual Audit Letter for Plymouth City Council The Annual Audit Letter for Plymouth City Council Year ended 31 March 2015 October 2015 John Golding Partner T 0117 305 7802 E john.golding@uk.gt.com David Bray Senior Manager T 0117 305 7889 E david.bray@uk.gt.com

More information

TENDER FOR SALE OF OLD/CONDEMNED VEHICLE OF CENTRE FOR DEVELOPMENT OF ADVANCED COMPUTING

TENDER FOR SALE OF OLD/CONDEMNED VEHICLE OF CENTRE FOR DEVELOPMENT OF ADVANCED COMPUTING CENTRE FOR DEVELOPMENT OF ADVANCED COMPUTING No. 68, Electronics City, Bangalore 560100 Phone No.080-28523300. Tender No.: C-DACB/R&D/029/16-17 Date: 21.09.2016 Due date: 20.10.2016: Time: 3.00 PM Tender

More information

2018 NEW HAMPSHIRE ELECTRIC COOPERATIVE (NHEC) COMMERCIAL HEATING EQUIPMENT INCENTIVE PROGRAM

2018 NEW HAMPSHIRE ELECTRIC COOPERATIVE (NHEC) COMMERCIAL HEATING EQUIPMENT INCENTIVE PROGRAM 2018 NEW HAMPSHIRE ELECTRIC COOPERATIVE (NHEC) Applications must be fully completed, submitted and pre approved for incentives by NHEC before installation of your system begins. Incentives will not be

More information

(Incorporated in England and Wales under the Companies Act 2006 with registered number )

(Incorporated in England and Wales under the Companies Act 2006 with registered number ) THIS DOCUMENT IS IMPORTANT AND REQUIRES YOUR IMMEDIATE ATTENTION. IF YOU ARE IN ANY DOUBT ABOUT THE CONTENTS OF THIS DOCUMENT OR THE ACTION YOU SHOULD TAKE, YOU ARE RECOMMENDED TO SEEK YOUR OWN FINANCIAL

More information

MEMORANDUM OF UNDERSTANDING

MEMORANDUM OF UNDERSTANDING MEMORANDUM OF UNDERSTANDING 1 THE AGREEMENT This Memorandum of Understanding ( MoU ) is entered into by City Hospitals Sunderland NHS Foundation Trust and South Tyneside NHS Foundation Trust, collectively

More information

Morgan Sindall plc. (incorporated and registered in England and Wales under number ) Notice of Annual General Meeting

Morgan Sindall plc. (incorporated and registered in England and Wales under number ) Notice of Annual General Meeting This document is important and requires your immediate attention. If you are in any doubt as to any aspect of the proposals referred to in this document or as to the action you should take, you should

More information

(1) Standby Commercial Drive Sewer Lift Station Sealed Bid (Bid ) Town of Salem, NH

(1) Standby Commercial Drive Sewer Lift Station Sealed Bid (Bid ) Town of Salem, NH ` (1) Standby Generator @ Commercial Drive Sewer Lift Station Sealed Bid (Bid-2017-025) Town of Salem, NH August 4, 2017 SALEM PURCHASING Christine Wholley, Purchasing Agent 603-890-2090 fax 603-890-2091

More information

St Minver Lowlands Parish Council

St Minver Lowlands Parish Council INDEX to FINANCIAL REGULATIONS Section No Heading Sub-Heading 1 General 2 Accounting and Audit Internal and External 3 Annual Estimates Budget and Forward Planning 4 Budgetary Control Incl. Authority to

More information

OFFICIAL. Date and Time 15 th May 2018 SPA Boardroom, Pacific Quay Forensic Services Budget Management and Month End Guidelines Item Number 10.

OFFICIAL. Date and Time 15 th May 2018 SPA Boardroom, Pacific Quay Forensic Services Budget Management and Month End Guidelines Item Number 10. Meeting Finance Committee Date and Time 15 th May 2018 Location SPA Boardroom, Pacific Quay Title of Paper Forensic Services Budget Management and Month End Guidelines Item Number 10.2 Presented By Amy

More information

Standard Form Project Agreement (hub DBFM Projects)

Standard Form Project Agreement (hub DBFM Projects) Standard Form Project Agreement (hub DBFM Projects) Version 2: June 20122.1: October 2013 . THIS STANDARD FORM PROJECT AGREEMENT MUST BE USED IN CONJUNCTION WITH THE STANDARD PROJECT AGREEMENTS USER S

More information

ESA TENDERING STANDARDS FOR EXPRESS PROCUREMENT ( EXPRO & EXPRO+ ) PROPOSAL TEMPLATE V5

ESA TENDERING STANDARDS FOR EXPRESS PROCUREMENT ( EXPRO & EXPRO+ ) PROPOSAL TEMPLATE V5 Page 1 ESA TENDERING STANDARDS FOR EXPRESS PROCUREMENT ( EXPRO & EXPRO+ ) PROPOSAL TEMPLATE V5 [COVER LETTER] From:... (Tenderer to insert name of the company/institute submitting the tender) Date:...

More information