1 Supporting and Enhancing Our Mission through the Capital Requests University of Wisconsin-Milwaukee December 13,
2 GSF FACILITIES ASSESSMENT Gross Square Feet by Decade 2,500,000 2,205,816 2,000,000 1,500,000 UWM Founded 1,181,472 1,000, , , , , , , , , , ,688 34,806 87, DECADE 2
3 FACILITIES ASSESSMENT Building Condition Analysis 3
4 PROJECT PRIORITIES AND SEQUENCE CHART UW- MILWAUKEE IN PROGRESS UNIVERSITY OF WISCONSIN SYSTEM UNIFIED CAPITAL PROJECT PRIORITY AND SEQUENCE through FUNDING NO. TYPE BIEN PROJECT TITLE GPR PR GIFT/GRANT TOTAL 1 MP 1517 Funding shortfall - NWQ Renovation - NWQD façade repair $ $ AA 1719 NLAK Roof and Masonry Repair/Replacement $ $ AA 1719 IT Infrastructure Renewal $ $ AA 1719 EMS Lab FH, Make-up Air Sys, Safety Shws, and Power Upgrd $ $ AA 1719 Kenilworth Square Chiller Replacement and Façade Repairs $ $ $ AA 1719 Continuing Education Chiller, Pump, AHU Coil Replacements $ $ $ AA 1719 Pearse Building Façade Repairs and Minor Site Work $ $ AA 1719 Multi-Bldg Central Air Handler Duct Smoke Detector Upgrades $ $ AA 1719 Mitchell Building Façade Repairs $ $ AA 1719 Vogel Building Façade Repairs and Walk Replacement $ $ AA 1719 Zelazo Electrical Service Upgrade $ $ AA 1719 Garland Building Façade Walk and Entrance Repairs $ $ AA 1719 Enderis Building Façade and Loading Dock Area Repairs $ $ AA 1719 AUP Building Façade Repairs $ $ AA 1719 CUN Heating & Cooling Sys Upgrds & Corner Window Replace $ $ AA 1719 Hefter Mechanical, Code and Envelope Repairs $ $ AA 1719 Mitchell Replacement of Building Windows $ $ AA 1719 EMS 9th Floor Lab Remodeling & Fume Hood Installations $ $ AA 1719 EMS 10th Floor Lab Remodeling & Fume Hood Installations $ $ IS 1719 CHM Instructional Labs Renovation(mechanical;fume hoods) $ $ IS 1719 HLT G86 Active Learning Classroom $ $
5 PROJECT PRIORITIES AND SEQUENCE CHART UW- MILWAUKEE IN PROGRESS UNIVERSITY OF WISCONSIN SYSTEM UNIFIED CAPITAL PROJECT PRIORITY AND SEQUENCE through FUNDING NO. TYPE BIEN PROJECT TITLE GPR PR GIFT/GRANT TOTAL 22 MP 1921 Chemistry Replacement & Central Utilities Extension $ $ $ $ MP 1921 Student Union Major Repairs Phase 1 $ $ MP 1921 Klotsche Added Recreational Space $ $ $ IS 1921 MIT B85 Active Learning Classroom $ $ IS 1921 LUB N146 Renovation $ $ IS 1921 High Use Classroom renewal LUB and EMS $ $ AA 1921 Unfunded AAPR's (or add'l AAPR's if funded) $ $ AA 1921 Garland Pearse Mechanical repairs $ $ AA 1921 Continuing Education Mechanical and Plumbing repairs $ $ AA 1921 Mitchell Hall Mechanical repairs, Controls upgrade $ $ AA 1921 PR Index projects $ $ MP 2123 STEM Renovation of old CHM Building $ $ MP 2123 GLRF dock wall $ $ IS 2123 MER 131 Active Learning Classrooom $ $ IS 2123 High Use Classroom renewal LUB and EMS $ $ AA 2123 GPR Projects on AAPR Index $ $ AA 2123 PR projects on AAPR Index $ $ MP 2325 Engineering Building (SWQ 2) $ $ MP 2325 Central Utility Extensions for Engineering (SWQ2) $ $ MP 2325 PHY Demolition $ - $ $ MP/AA 2325 NWQ site renovation (retaining walls, site stairs, roadways, terminated power plant) $ $ $ MP 2325 Student Union Major Repairs Phase 2 $ $ IS 2325 LAP 160 Renovation $ $ IS 2325 SAB G90 Renovation $ $ IS 2325 High Use Classroom renewal LUB and EMS $ $ AA 2325 GPR projects on AAPR Index $ $ AA 2325 PR projects on AAPR Index $ $
6 PROJECT PRIORITIES AND SEQUENCE CHART UNIVERSITY OF WISCONSIN SYSTEM UNIFIED CAPITAL PROJECT PRIORITY AND SEQUENCE through GPR PR GIFTS/GRANTS TOTAL $ $ - $ - $ $ $ $ - $ $ $ $ $ $ $ $ - $ $ $ $ $ TOTAL $ $ $ $
7 CAPITAL BUDGET REQUEST UWM s Most Urgent GFSB and PRSB Capital Needs for GFSB Projects: Chemistry Replacement Building facility deferred capital maintenance threatens to impact safety Extend Steam and Chilled Water to support Chemistry Replacement Building PRSB Projects: Student Union Major Maintenance a majority of the union was built between 1956 and MEP systems, building envelope and life safety systems that are beyond useful life require replacement. Klotsche Center Annex will relieve overcrowding during high use times when athletics and recreation needs coincide 7
8 CAPITAL BUDGET REQUEST CHM Replacement Building Current Chemistry facility threatened by catastrophic failure All STEM fields served by CHM 1800 UWM students/year Impacts Chemistry accreditation Existing floor load capacity doesn t meet new code requirements, requiring a replacement building 8
9 CAPITAL BUDGET REQUEST #1 Request: Chemistry Replacement Building (SWQ1) SWQ 1 9
10 CAPITAL BUDGET REQUEST 10
11 CAPITAL BUDGET REQUEST #1 Request: Chemistry Replacement Building Preliminary Concepts 11
12 Union Major Maintenance Phase 1 UWM Student Union is BIG 328,072 GSF Built between 1956 and 1987 Main provider of: Community Gathering Student Organizations Food/Retail/Convenience Conference/Events Serves 22,000 people per day CAPITAL BUDGET
13 Milwaukee Eau Claire Green Bay CAPITAL BUDGET La Crosse Madison Oshkosh Parkside Platteville River Falls Stevens Point Stout Superior Whitewater Union Major Maintenance Phase 1 Union Building Analyses Functional D A A A A A A B B A A A A Physical v i ii i i i i i ii i i i i (new union recently opened)
14 Klotsche Center Annex Adds court/gymnasium space Two locations will be evaluated CAPITAL BUDGET
CAPITAL PLANNING and BUDGET AUGUST 18, 2016 ALEXANDRIA C. ROE, ASSOCIATE VICE PRESIDENT
CAPITAL PLANNING and BUDGET AUGUST 18, 2016 ALEXANDRIA C. ROE, ASSOCIATE VICE PRESIDENT BIENNIAL CAPITAL BUDGET REQUEST CONTEXT 2017-19 GENERAL FUND AND PROGRAM REVENUE SUPPORTED BORROWING General Fund
More informationPreliminary Program Revenue Budget Building Cost Factors and Timeline
Budget & Planning 780 Regent Street Suite 241 PO Box 8010 Madison, WI 53708-8010 608/262-1544 608/265-2090 Fax e-mail: budget@uwsa.edu website: http://www.uwsa.edu October 26, 2015 Via e-mail only To:
More informationPreliminary Program Revenue Budget Building Cost Factors and Timeline
Budget & Planning 780 Regent Street Suite 241 PO Box 8010 Madison, WI 53708-8010 608/263-4422 e-mail: budget@uwsa.edu website: http://www.uwsa.edu November 21, 2017 Via e-mail only To: From: Subject: Auxiliary
More informationCapital Planning and Budget. University of Wisconsin System Administration. All Agency Projects Program
University of Wisconsin System Administration All Agency Projects Program OVERVIEW All Agency Projects Program A targeted program addressing the maintenance, repair, renovation, and minor remodeling needs
More informationMinutes Capital Planning and Budget Committee Thursday, July 9, 2009
Minutes Capital Planning and Budget Committee Thursday, July 9, 2009 Committee Chair Regent Bartell convened the meeting of the Capital Planning and Budget Committee at 9:08 a.m. in Room 1820 of Van Hise
More informationWest Bend School District Community Survey Results. Spring 2018
West Bend School District Community Survey Results Spring 2018 Survey Summary The survey was conducted in June of 2018. Residents within the District were mailed a paper survey. Each survey included a
More informationANNUAL FINANCIAL REPORT
ANNUAL FINANCIAL REPORT 2017 UNIVERSITY OF WISCONSIN SYSTEM Published by the Office of Finance University of Wisconsin System 1220 Linden Drive Madison, WI 53706 Editor: Lana Becker Cover Photo: University
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - April 26, 2017
Project Name by Construction Project # Planning Academic & Research Facilities - Homer 300008 $1,850,000 $0 P UCONN 2000 Bond Funds 03/29/17 2020 Babbidge Library Renovations Stamford Campus Improvements/Housing
More informationBOARD OF REGENTS OF THE UNIVERSITY OF WISCONSIN SYSTEM
1/28/2019 BOARD OF REGENTS OF THE UNIVERSITY OF WISCONSIN SYSTEM I.3. Capital Planning and Budget Committee Thursday, February 7, 2019 10:45 a.m. 12:00 p.m. UW-Madison, Union South, 2 nd floor Varsity
More informationBOARD OF REGENTS OF THE UNIVERSITY OF WISCONSIN SYSTEM. I.6. Joint Meeting of the Business and Finance and Audit Committees
2/1/2018 BOARD OF REGENTS OF THE UNIVERSITY OF WISCONSIN SYSTEM I.6. Joint Meeting of the Business and Finance and Audit Committees Thursday, February 8, 2018 8:15 a.m. 9:00 a.m. Union South 2 nd Floor,
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - June 28, 2017
Planning Budget Phase Academic & Research Facilities - Homer 300008 $1,850,000 $0 P UCONN 2000 Bond Funds 03/29/17 2020 Babbidge Library Renovations Main Campus Parking Replacements 300023 $500,000 $0
More informationMinutes Physical Planning and Funding Committee Thursday, December 8, 2005
Minutes Physical Planning and Funding Committee Thursday, December 8, 2005 Committee Vice Chair Regent Gracz convened the joint meeting of the Physical Planning and Funding Committee and the Business,
More informationHRS Coordinators. September 10, :00 p.m. Room 1106/1108, 21 N. Park UNIVERSITY OF WISCONSIN MADISON
HRS Coordinators September 10, 2015 1 2:00 p.m. Room 1106/1108, 21 N. Park Agenda Introductions HR Design FLSA Choice Leave Balances Lump Sum Codes HRS Duplicate Employee IDs Order of Terminations Missed
More informationUSE OF FACILITIES POLICIES AND PROCEDURES
USE OF FACILITIES POLICIES AND PROCEDURES No: S-23 Date: September 2016 (revised-3) October 2015 (revised-2) Authority: Wis. Admin. Code UWS Ch. 18, 21 October 2003 (revised-1) Regent Policy 12-1 Competition
More informationAnnual Financial Report
Annual Financial Report 2011 Published by the Office of Finance University of Wisconsin System 1220 Linden Drive Madison, WI 53706 Editor: Laurie Grams Cover Photo: Enjoying a clear September morning,
More informationBOARD OF REGENTS OF THE UNIVERSITY OF WISCONSIN SYSTEM
3/27/2017 BOARD OF REGENTS OF THE UNIVERSITY OF WISCONSIN SYSTEM I.2. Business and Finance Committee Thursday, April 6, 2017 9:00 a.m. 10:30 a.m. UW-Platteville Ullsvik Hall, Nohr Art Gallery Platteville,
More informationMinutes Capital Planning and Budget Committee Thursday, August 23, 2012
Minutes Capital Planning and Budget Committee Thursday, August 23, 2012 The meeting of the Capital Planning and Budget Committee was called to order at 1:00 pm by Committee Chair Regent Jeffrey Bartell
More informationCapital Maintenance. 2. Deferred Maintenance, May 18, 2009 <http://en.wikipedia.org/wiki/deferred_maintenance>
Capital Maintenance Capital Maintenance Capital maintenance has previously been known as deferred maintenance, the act of postponing maintenance in order to save money or avoid costs. 2 At NYU, the term
More informationUWM Parking Budget Proposal FY
UWM Parking Budget Proposal FY 2015-2016 Parking & Transit Revenue Sources (FY1314) Current Status Auxiliary Unit Self Funded Restricted Revenues Segregated Fees (UPASS) 28% $2.2 Million Segregated Fees
More informationBOARD OF REGENTS OF THE UNIVERSITY OF WISCONSIN SYSTEM. I.6. Joint Meeting of the Business and Finance and Audit Committees
5/22/2018 BOARD OF REGENTS OF THE UNIVERSITY OF WISCONSIN SYSTEM I.6. Joint Meeting of the Business and Finance and Audit Committees a. Plante Moran External Financial Audit Engagement b. Information Security
More informationLos Angeles Unified School District Page 1 of 3
Los Angeles Unified School District 333 South Beaudry Ave, Los Angeles, CA 90017 Board of Education Report File #: Rep-201-16/17, Version: 1 Amendment to the Facilities Services Division Strategic Execution
More informationBoard of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019
Board of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019 PRESENTED BY Finance and Administration Florida Agricultural and Mechanical University 1 ACTION ITEM IV: Approval of
More informationFacility Condition Assessment Report. Coast Community College District
Facility Condition Assessment Report Coast Community College District February 28, 2003 Introduction To help document the need for funding the necessary replacement and upgrading of facilities within California
More informationMeasure RR Bond Budget by Project. Measure RR BAN Measure RR BAN Interest Measure RR Series AB Measure RR Series AB Interest
6/30/15 15/16 Thru 6/30/15 15/16 Thru 6/30/15 15/16 Thru 6/30/15 15/16 A Library, Learning Resources and Campus Center 217,200 GSF; State Funding component; begin design est. 2015/16 771120 $ 197,529.21
More informationFacility Condition Assessment. Facility Condition Assessment 8/13/2013 AGENDA
AGENDA benefits & limitations Rod Moore, RA, LEED AP, PMP Georgia Tech Benjamin Dutton, FFB, MCIOB, MRICS Faithful+Gould GT Facilities GT Program What is GT FCA Deliverables How GT uses FCA Information
More informationUse of State and District Construction Funds
8 Use of State and District Construction Funds Through its long-range planning process, the district has met its facilities needs without issuing significant debt. To improve cost efficiency, however,
More informationPriority #1 Request for Construction FY Priority #2 Anticipated Request for Planning FY 2019
V. IMPLEMENTATION PLAN a) Prioritize major capital projects requested from the State, including a brief project description and estimated cost, in the format provided. (Adjust previously developed or prior
More informationGov's Planning Estimates Project Title Rank Fund Project Requests for State Funds
This document is made available electronically by the Minnesota Legislative Reference Library as part of an ongoing digital archiving project. http://www.leg.state.mn.us/lrl/lrl.asp State Academies Projects
More informationContents Capital and Debt
Contents Capital and Debt Capital Expenditures and the Construction Fund... 6-3 Routine Capital Spending... 6-3 Non-routine Capital Spending... 6-3 Impact of Capital Spending on Annual Budget... 6-4 Capital
More informationAnnual Financial Report
Annual Financial Report 2013 Published by the Office of Finance University of Wisconsin System 1220 Linden Drive Madison, WI 53706 Editor: Laurie Grams Cover Photo: With a backdrop of blue skies and greenery,
More informationReserve Analysis Report
Reserve Analysis Report Parkway Towers 1155 Ash St Denver, CO 80220 Level I Study with Site Inspection Fiscal Year End Date: 12/31/2014 8597 Via Mallorca Suite E La Jolla, CA 92037 Phone: 858-764-1895
More informationCapital Projects Completed since 1988
Projects Completed since 1988 Project Cost FY1988 ICCB Building Illinois Repair & Renovation - Replace Carpet in Classroom Buildings, Library and Lobby of Admin $ 51,901.00 $ 51,901.00 $ 51,901.00 FY1990
More informationCentral Michigan University Capital Budget
Central Michigan University Capital Budget 1999-2000 Table of Contents Central Michigan University Capital Budget Table of Contents I. Narrative A. Overview and Process...1 B. Funding Sources...2 C. Capital
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - August 2, 2017
Planning Academic & Research Facilities - Homer 300008 $1,850,000 $128 P UCONN 2000 Bond Funds 03/29/17 2020 Babbidge Library Renovations Main Campus Parking Replacements 300023 $500,000 $0 P 06/28/17
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - September 27, 2017
Planning Budget Phase Academic & Research Facilities - Homer 300008 $1,850,000 $391 P UCONN 2000 Bond Funds 03/29/17 2020 Babbidge Library Renovations Main Campus Parking Replacements 300023 $500,000 $32,640
More informationSchool Referendum Results School Amount Type of Debt Description Arrowhead UHS Failed
School Referendum Results School Amount Type of Debt Description Arrowhead UHS Arrowhead UHS Baraboo Beaver Dam Belleville Cambridge Campbellsport Chippewa Falls Chippewa Falls $64,700,000.00 Issue Debt
More informationBUILDING PERMIT FEES
BUILDING PERMIT FEES 1. Building Permit Fee Based on the Construction Valuation of the project excluding site work. Refer to Fee Charts below. Electrical, Mechanical and Plumbing permits are not included
More informationUniversity of Virginia Status Report on the Plan to Address Deferred Maintenance
Executive Summary University of Virginia Status Report on the Plan to Address Deferred Maintenance The University of Virginia s facilities portfolio includes 540 buildings and related infrastructure, encompassing
More informationPage Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182
Page Item 174 Overview 175 Revenue 177 Expenditures 178 Elementary School Allocation 180 Middle School Allocation 181 High School Allocation 182 Operational Services/Central Services/Axtell Park School
More informationUNIVERSITY OF WISCONSIN SYSTEM TRUST FUNDS
UNIVERSITY OF WISCONSIN SYSTEM TRUST FUNDS ANNUAL REPORT 2016 To the UW System Board of Regents, Donors and Friends, UW Campuses and Departments The University of Wisconsin System Trust Funds is composed
More informationOur Focus: Your Future
Town of Fort Erie Infrastructure Services Our Focus: Your Future Prepared for Council-in-Committee Report No. IS-53-07 Agenda Date November 19, 2007 File No. 220102 Subject 5 YEAR FACILITY CONDITION STATUS
More informationGeorgia Institute of Technology Advanced Computing Technology Building. Draft Program. Mission Model Initial Program Development
Georgia Institute of Technology Advanced Computing Technology Building Draft Program Initial Program Development Issued April 2, 2001 Introduction Scope This document is a summary of the Session for the
More information1. Program & Planning Adjustments: 2. Cash flow: 3. Indenture Amendments:
The key elements underlying the revisions to the phasing outline are detailed below. These changes are driven by academic priorities, economic realities and the importance of spending bond proceeds in
More informationCAPITAL FUNDING SUMMARY
CAPITAL SUMMARY SCC (School Consolidation Capital ) CAPITAL : B19 -December 1, Specifically to address a school board s excess capacity : B11 -May 26, Opportunity to identify most urgent & pressing accommodations
More informationBacklog Reduction Plan
2003-2013 Executive Summary proposes to achieve reductions in our facilities maintenance backlog by documenting and completing backlog projects on a priority basis and by minimizing or eliminating future
More informationBoard of Regents Biennial Budget Request. August 22, 2002
Board of Regents 2003-05 Biennial Budget Request August 22, 2002 The 2001-03 Budget Process 2001-03 Budget Bill $40 million for ongoing resources Economic development, increased enrollment 2001-03 Budget
More informationGoverning Board Bond Update. Measure G Bond Program. for. Solano Community College District
Governing Board Bond Update for Measure G Bond Program prepared by Kitchell for the Solano Community College District Included in Booklet: Board Update Bond Financial Summary Completed Projects Projects
More informationHayfield Community Schools Bond Referendum. Vote Monday, September 11, Our Schools Our Communities Our Future
Hayfield Community Schools 2017 Bond Referendum Vote Monday, September 11, 2017 Our Schools Our Communities Our Future 2017 Bond Referendum What s Already Been Done? Studies and Meetings and Meetings 2014-15
More informationCIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5
CIP FY2015 FY2019 Requests SCH-1, SCH-2 and SCH-5 Edwin Ataide Deputy Director Plant & Facilities SCH-1 School Projects All Schools Priority FY15 FY16 FY17 FY18 FY19 ADA Compliance (Handicap Accessibility)
More informationBallot Measures-N 7. Centralia Elementary School District, Building Strong Neighborhood Schools
Section Ballot Measures-N N Centralia Elementary School District, Building Strong Neighborhood Schools To repair/modernize aging classrooms, science labs/school facilities to keep pace with technology,
More informationResidential Permit Fee Schedule
City of Port St Lucie Department Residential Permit Schedule Effective October 15, 2015 - Revised July 12, 2017 Notice - Schedule is for reference only. All fees are subject to change. Please check wit
More informationSOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S SOMIS UNION SCHOOL DISTRICT TAX RATE STATEMENT BOND MEASURE S
SOMIS UNION SCHOOL DISTRICT IMPARTIAL ANALYSIS BY COUNTY COUNSEL* BOND MEASURE S Under this measure, the Somis Union School District ( District ) is submitting a bond measure, described below, to the voters
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING December 12, 2012
Project Name by Phase Project # Current BOT Approved Budget Encumbrances (As of 11/28/12) Budget Phase Budgeted Funding Source(s) (s) Planning Budget Phase Ecology and Evolutionary Biology (EEB) 201583
More informationSummary of Capital Budget Request Tennessee Board of Regents. of the. September 21, 2017
Summary of Capital Budget Request 2018-2019 of the Tennessee Board of Regents September 21, 2017 1 This is the Summary of the Capital Budget Request for Fiscal Year 2018-2019 for the Finance and Business
More informationHarnett Central High
NC School District/430 Harnett County/High School Harnett Central High Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 6 Campus
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING - October 31, 2018
Planning Academic & Research Facilities - Homer 300008 $1,850,000 $1,603,349 P UCONN 2000 Bond Funds 03/29/17 2022 Babbidge Library Renovations Northwest Science Quad Infrastucture- 3 300103 $700,000 P
More informationComprehensive Facilities Assessment School Committee
C A N T O N P U B L I C S C H O O L S Comprehensive Facilities Assessment 3.23.2017 School Committee A g e n d a Introductions Schedule & Process Overview Progress Update Enrollment Targets Facilities
More informationAttachment FC 08 (REVISED 03/13/2018) SBCC 03/16/2018. STATE BOARD OF COMMUNITY COLLEGES Construction and Property March 16, 2018 FY
A. Approval New (Non State and Other Name (Other State) (Other State) 1 N/A B. Approval Amended (Non State and Other Name 1 N/A C. Approval New ( Bond Funds) Name 1 Alamance Main Campus 2400 A Building
More informationRichland School District
Richland School District April 5, 2016 Referendum Ballot and Cost Impact Presentation Presented by: Carol Wirth, President 1020 N. Broadway, Suite G-9 Milwaukee, WI 53202 Phone 414/434-9644 Question 1
More informationSOUTH DAKOTA BOARD OF REGENTS. Policy Manual
SOUTH DAKOTA BOARD OF REGENTS Policy Manual SUBJECT: NUMBER: A. PURPOSE To provide guidance on what constitutes maintenance and repair and the process used to document and approve projects. B. DEFINITIONS
More informationPRELIMINARY RESOLUTION THE CULINARY INSTITUTE OF AMERICA SERIES 2016 BONDS
PRELIMINARY RESOLUTION THE CULINARY INSTITUTE OF AMERICA SERIES 2016 BONDS A special meeting of the Dutchess County Local Development Corporation (the Issuer ) was convened in public session on June 3,
More informationFY 2017 Stockton University Expenditure Report as of May 31, 2017
FY 2017 Stockton University Expenditure Report Table of Contents Page Operational Budgets 1-2 Internal Capital Projects Summary 3 FY17 Internal Capital Projects 4 State Bond/Grants 5 STOCKTON UNIVERSITY
More informationSalt Lake City Area Office 8722 S. Harrison St. Sandy, UT P.O. Box 4439 Sandy, UT Fax
Salt Lake City Area Office 8722 S. Harrison St. Sandy, UT 84070 P.O. Box 4439 Sandy, UT 84091 800-257-5590 Fax 800-478-9880 Chicago Office 303 W. Madison Street Suite 2075 Chicago, IL 60606 800-456-4576
More informationNUNAVUT HOUSING CORPORATION. Home Renovation Program (HRP)
NUNAVUT HOUSING CORPORATION Home Renovation (HRP) October 2014 Date October 201 TABLE OF CONTENTS OBJECTIVE... 1 SUMMARY... 1 ENABLING LEGISLATION... 1 ELIGIBLE CLIENTS... 1 PRIORITY OF APPLICANTS...
More informationDeferred Maintenance Phase I Report
Ohio University Deferred Maintenance Phase I Report A Case for Addressing Deferred Maintenance Needs at Ohio University Prepared by: University Planning and Implementation and Facilities Management Ohio
More informationREQUEST FOR QUALIFICATIONS ARCHITECTURAL SERVICES FOR DOUGLAS CITY HALL RENOVATIONS DOUGLAS, WYOMING
REQUEST FOR QUALIFICATIONS ARCHITECTURAL SERVICES FOR DOUGLAS CITY HALL RENOVATIONS DOUGLAS, WYOMING Request for Qualifications (RFQ) due: 3:00pm local time, August 17, 2018 Page 1 of 8 Section One Introduction
More information6.0 Support Facilities Element
6.0 PURPOSE The purpose of this element is to ensure the provision of support facilities to meet University needs during the planning period. (1) DATA REQUIREMENTS. This element shall be based on the following
More informationLarkspur-Corte Madera School District: 2014 Bond Feasibility Survey
Larkspur-Corte Madera School District: 2014 Bond Feasibility Survey Overview and Research Objectives Larkspur-Corte Madera School District commissioned TBWB and Godbe Research to conduct a survey of local
More informationORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 02/08/2013 BUILDING SURVEY DATE
0171 1503 SOUTH MARYLAND DRIVE URBANA, ILLINOIS 61801 SYSTEM CONDITION INDEX.770 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 2,686,100 LABORATORY BUILDING GROSS SQUARE
More informationSCHOOL BOARD ACTION REPORT
SCHOOL BOARD ACTION REPORT DATE: March 15, 2018 FROM: Dr. Larry Nyland, Superintendent LEAD STAFF: Dr. Lester Herndon, Associate Superintendent, Facilities and Operations (206) 252-0644 ltherndon@seattleschools.org
More informationSubject: Capital Reserve Expenditure Guidelines. *incl. former OCHAP/CSHP Peel Access to Housing (PATH)
HIP Housing In Peel Subject: Capital Reserve Expenditure Guidelines Date: August 1, 2012 Applicable To The information contained in this document applies to the following: Municipal & Private Non- Federal
More informationSchool District of Horicon Community Survey Results. Fall 2017
School District of Horicon Community Survey Results Fall 2017 Survey Summary The survey was conducted in November December of 2017. Residents within the District were mailed a paper survey. Each survey
More informationTHE FLORIDA INTERNATIONAL UNIVERSITY BOARD OF TRUSTEES December 5, 2018
Consent Agenda FF2 THE FLORIDA INTERNATIONAL UNIVERSITY BOARD OF TRUSTEES December 5, 2018 Subject: Approval of Carryforward Funds Proposed Board Action: Approve the Florida International University (FIU)
More informationCONSTRUCTION PROJECTS STATUS REPORT BOARD OF TRUSTEES MEETING March 25, 2015
Project Name by Phase Project # Current BOT Approved Budget Encumbrances (As of 3/10/15) Budget Phase Budgeted Funding Source(s) (s) Planning Budget Phase Academic and Research Facilities STEM 901802 $1,000,000
More informationCAPITAL IMPROVEMENT PLAN OVERVIEW
CAPITAL IMPROVEMENT PLAN OVERVIEW January 15, 2015 AGENDA Capital Improvement Planning overall methodology The FY 2015 CIP process and resulting project commitments Request for new projects and project
More informationAdopted Tentative Budget. Final Public Hearing
2013-14 Adopted Tentative Budget Final Public Hearing September 5, 2013 Presentation Outline Proposed Millage Budget Information Enrollment Projections vs. State Recalibration Proposed Employee Positions
More informationCH-UH Board of Education Meeting. June 27, 2017
CH-UH Board of Education Meeting June 27, 2017 Tonight s Agenda Purpose of this work session Current status of the Master Facilities Plan Phase 1 Factors that led us to this point Current path for middle
More informationAPPENDIX E ALLOWABLE CAPITAL EXPENDITURE GUIDELINES
APPENDIX E ALLOWABLE CAPITAL EXPENDITURE GUIDELINES Introduction State capital appropriations are funded primarily through the issuance of State bonds. State bonds must be authorized by Ohio voters via
More informationORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 2/13/2013 BUILDING SURVEY DATE
0197 1102 SOUTH GOODWIN AVENUE URBANA, ILLINOIS 61801 SYSTEM CONDITION INDEX.644 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 11,554,400 LABORATORY BUILDING GROSS SQUARE
More informationFY2013 Annual Capital Improvement Budget. Board of Regents Facilities Committee May 2012
FY2013 Annual Capital Improvement Budget Board of Regents Facilities Committee May 2012 Capital Plan Board of Regents Policy directs the administration to develop a capital budget with a 6-year time horizon,
More informationProgram: Facilities and Construction Management. Program Based Budget Page 117
Program: Facilities and Construction Management Program Based Budget 2014-2016 Page 117 Program: Facilities and Construction Management Vision: To develop and maintain town buildings that is safe, comfortable
More informationFreedom Area School District Community Survey Results. Fall 2018
Freedom Area School District Community Survey Results Fall 2018 Survey Summary The survey was conducted in late October/early November of 2018. Residents within the District were mailed a paper survey.
More informationBUILD NYC RESOURCE CORPORATION PROJECT COST/BENEFIT ANALYSIS June 7, 2018
BUILD NYC RESOURCE CORPORATION PROJECT COST/BENEFIT ANALYSIS June 7, 2018 APPLICANT Blue School and Blue School Real Estate, LLC 241 Water Street New York, NY 10038 PROJECT LOCATION 156 William Street
More informationNC School District/430 Harnett County/Middle School Highland Middle Final Campus Assessment Report March 11, 2017
NC School District/430 Harnett County/Middle School Highland Middle Final Campus Assessment Report March 11, 2017 PARSONS Campus Assessment Report Table of Contents Campus Executive Summary 5 Campus Dashboard
More informationSummary Report - Texas A&M University (010366)
Page 1 of 6 Summary Report - Texas A&M University (010366) MP2&3 - Assesment of Deferred Maintenance and Demolition Needs Building Proj. Desc. Type Pri Crit? Arch HVAC P&E Safety L&M Other Project Cost
More informationJACKSON-MADISON COUNTY SCHOOL SYSTEM FUND #177 EDUCATION CAPITAL 5-YEAR PLAN (WORKING COPY)
Elementary & K-8 Campuses Alexander 6 8 Guttering replacement 2 $ 20,000 HVAC replacement 1 $ 800,000 Remove and replace old glass block windows 3 Total for Alexander $ - $ 20,000 $ 800,000 $ - $ - $ -
More informationMontclair Public Schools
Montclair Public Schools Budget Presentation 2014-2015 March 3, 2014 Dr. Penny MacCormack Superintendent of Schools Mr. Brian Fleischer Chief Operations Officer Budget Sources and Uses 2008-2013 Budget
More informationIntermediate & Middle Schools
Intermediate & Middle Schools BUILDING ANALYSIS MATRIX Weighting Sakai Woodward Program Assessment Core Instruction 24 20 16 Special Education 5 5 5 Functional Skills 5 5 5 Science 3 3 3 Arts/Performance
More informationWashingtonville Central School District Building Condition Survey Five Year Plan
Building Condition Survey Five Year Plan Project Cost Summary Building 2011 2012 2013 2014 2015 Totals 0001 Washingtonville Jr High School $38,759 $325,990 $1,882,653 $1,417,341 $1,025,559 $4,690,302 0002
More informationORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 2/4/2013 BUILDING SURVEY DATE
0156 504 EAST PENNSYLVANIA AVENUE CHAMPAIGN, ILLINOIS 61820 SYSTEM CONDITION INDEX.461 PRIMARY BUILDING USE BUILDING SURVEY TEAM BUILDING SYSTEM REPLACEMENT COST $ 16,618,500 CLASSROOMS / LIBRARY BUILDING
More informationUnderstanding the Costs: Frequently Asked Questions
Understanding the Costs: Frequently Asked Questions As of 9/6/2016 What is the total proposed project cost? The total project cost is $54.9 M and cannot, by state law, exceed that amount if approved by
More informationBUILDING CONDITION ASSESSMENT. A Comprehensive Approach in Energy and Facility Management
BUILDING CONDITION ASSESSMENT A Comprehensive Approach in Energy and Facility Management Presentation Outline Page Nadine International Company Profile.. 3 FCI -Industry Preferred Formula.... 4 FCI -Other
More informationBERKELEY UNIFIED SCHOOL DISTRICT Berkeley, California. MEASURE I GENERAL OBLIGATION BONDS PERFORMANCE AUDIT June 30, 2013
PERFORMANCE AUDIT June 30, 2013 PERFORMANCE AUDIT June 30, 2013 CONTENTS INDEPENDENT AUDITOR S REPORT... 1 BACKGROUND: LEGISLATIVE HISTORY... 2... 2 PERFORMANCE AUDIT: OBJECTIVES... 3 SCOPE... 3 METHODOLOGY...
More informationUCLA DEEP ENERGY EFFICIENCY PROGRAM - ENGINEERING & DESIGN SERVICES
Energy Services UCLA DEEP ENERGY EFFICIENCY PROGRAM - ENGINEERING & DESIGN SERVICES GONDA NEUROSCIENCE AND GENETICS RESEARCH CENTER PROJECT NUMBER: 4953345 MACDONALD MEDICAL RESEARCH LABORATORY BUILDING
More informationWelcome Colome Consolidated School Public Meeting. January 17, 2019 January 21, 2019
Welcome School Public Meeting January 17, 2019 January 21, 2019 How Did We Get Here? August 2017 started talking to Architects and Construction Managers We retained an architectural firm to design a Conceptual
More informationEngineering - Facilities Management
Engineering - Facilities Management Capital Improvement Plan Project Summary Agency Priority # CCB Improvements 8 00,000 00,000 00,000 00,000 00,000 00,000 # CCB Tenant Improvements 2,000,000 200,000 2,000,000
More informationUniversity of Wisconsin Tax-Sheltered Annuity (TSA) 403(b) Program 2017 Annual Report
University of Wisconsin Tax-Sheltered Annuity (TSA) 403(b) Program 2017 Annual Report Table of Contents Program Overview 3 Executive Summary 4 Program Assets 5 Plan Assets 6 Account Balances 7 Investments
More informationThe Real Meaning of Total Cost of Ownership (TCO)
The Real Meaning of Total Cost of Ownership (TCO) Presented by David Patnaude Director of Plant and Sustainability Riverdale Country School Lawrence Eighmy Managing Principle 1 The Real Meaning of Total
More informationRockville Science Center (P036600)
Rockville Science Center (P036600) (AAGE15) Rockville Date Last Modified 2/26/14 N/A-PS Planning, Design and Supervision 6,492 6,477 15 0 0 0 0 0 0 0 0 Construction 56,300 56,272 28 0 0 0 0 0 0 0 0 6,598
More informationSpringfield High School
5.1 Springfield High School Springfield School District Delaware County - Pennsylvania Master Plan Presentation Town Hall Meeting 5 Project Cost Estimates/ Project Financing Strategy / Tax Impact February
More information