Presentation to NERSA on ESKOM tariff application 5 February 2016

Size: px
Start display at page:

Download "Presentation to NERSA on ESKOM tariff application 5 February 2016"

Transcription

1 Presentation to NERSA on ESKOM tariff application 5 February 2016

2 Why all here? Will it really help? Hope Confidence that NERSA will actually consider our concerns and let it find expression in the tariff to be approved for ESKOM & Municipalities as licensed distributors, subject to license conditions Our view, experienced from perspective of electricity consumers of Rustenburg We are hoping, recently against hope! The role of NERSA versus the role of the Municipal Council is not understood by municipalities Municipalities seem to be confused Who has the final say on tariff increases? Councils say it is NERSA, as they blame NERSA when challenged by consumers

3 Our experience: Since first 35% in 2008 Increase to ESKOM: 35% Increase allowed to municipalities: 35% Was wrong implies every cost driver increased by 35% NERSA subsequently changed. 2015/16: Granted to ESKOM: 14.4% 2015/16: NERSA guideline tariff increase to municipalities: 12.2% However, 35% adjusted retrospectively? NO!

4 Rustenburg consumers - Our experience: 2012/13 Implementation of block tariffs not even tabled before Council in March or May First word after NERSA approval Reason supplied to consumers: NERSA said so! Implied tariff increase of 20.25% on 1000 kwh. Was implemented without even one budget calculation by RLM Engaged with NERSA. Did it help: NO! NERSA s plea following engagement: We will not do it again!

5 Rustenburg: Business (400 V) tariffs (Consumption based portion) (VAT exclusive) 8000 kwh in 2007 (R0.16/kWh) 8000 kwh in 2015 (summer) (R /kWh) 8000 kwh in 2015 (winter) (R1.90/kWh) 8000 kwh in 2015(average) (R0.9602/kWh) Average increase between 2015 and 2016 Increase in winter months Increase/month since 2007, based on average Increase in % Average increase/year (%) Comparison: Toll gate fees If now (2016) costs Will cost in 2024 if same trend applicable R R R R % % R % 62.47% R R107.96

6 Rustenburg: Household tariffs (VAT inclusive) 1000 kwh in kwh in 2015 Increase in R Increase in % Average increase/year Comparison: Bread If now (2016) costs Will cost in 2024 if same trend R R R % 35.24% R R 38.19

7 Rustenburg - Our experience: 2015/16 Seasonal tariff increases for business : 199% Calculated over a year: 38% Rustenburg economy: Platinum industry driven / AMCU strike / Marikana Mines shedding positions like ESKOM shedding load Local economy suffering Amidst this with the approval of NERSA: Taking two thirds of approved annual tariff increase upfront in July and August. Which business charge July/August clients the annual price increase, but the subsequent clients no increase? With NERSA approval? Does it instil confidence in NERSA NO! NERSA engagement: Reduces 27c/kWh to 0.27c/kWh Did the RLM adjust retrospectively: No Were consumers afforded an opportunity to be heard on the increase above 12.2%, as is the prescribed NERSA procedure (like this): NO! NERSA s comment: We will not do it again! Will electricity consumers have confidence in NERSA: No!

8 Process ESKOM application Public hearings NERSA consideration NERSA caps ESKOM increase NERSA determines tariff guideline increase for Municipalities Municipalities submit applications. Limited municipal capacity Municipal own calculations mostly none - just based on NERSA increase Application considered time frames important. Section 43 MFMA / NT guideline Council draft budget to public. NERSA approves different tariff. Council has to go back to public. Do they do it? Mostly NOT! NERSA should engage with public if > than tariff guideline increase

9 Debtors/municipalities not paying Media: Soweto consumers owe ESKOM R4 billion Municipalities owe ESKOM R5 billion. ESKOM providing bridging finance to non-paying municipalities? All knows: Non-collection finds expression in tariffs somebody must pay for the non-payment! Who are they? Law abiding consumers like us Municipality do not pay ESKOM. ESKOM cut supply to town. Who suffers: Law abiding consumers who paid. Are the Council dissolved? No! Are the MM and/or CFO fired: No! Are the conditions of the license agreement enforced/license of the municipality withdrawn: No! Are ESKOM allowed to cut supply to town: Yes! Who should now protect the law abiding and paying residents/electricity consumers?

10 Distribution losses Distribution losses filtered into tariffs Norm set by National Treasury: 8% Electricity distribution losses exceeds norm in Rustenburg Totally unacceptable, yet 38% tariff increase approved by NERSA! What does it imply? Poor leadership and management find expression in increased tariffs Law abiding consumers pay for inefficiencies! Any repercussions: No! Who suffers?: The law abiding paying consumer

11 Conclusion Under NERSA s nose, on their watch, electricity consumers of RLM pay today between 288 & 499 % more for electricity than in 2008 and if challenged: NERSA approved! Implies: On average an increase between 35% and 63 % per year Reported inflation of between 5 & 6 % Economic growth of not even 2% predicted for 2016/17 Yet: ESKOM has the audacity to ask for 17%, blaming previous requests for increases not granted, in a market where it has no competitor Can Sunbake, who bake and sold the bread in 2013, recoup from a different consumer the increase that he could not filter into his tariffs then? We are paying for inefficient management at ESKOM and Municipalities - finding expression in tariff increases, allowed by NERSA and claimed by Municipalities as the final authority they do what NERSA say Yet: Ethekweni no block tariffs

12 Munsolve s request to NERSA Consequence management: At NERSA, at ESKOM, at Municipalities Currently only consequences for business/households they must pay, adapt lifestyles, cut back on other expenses or suffer disconnection of supply, yet senior managers at NERSA, ESKOM and Municipalities seem to be remunerated at above average salaries Every business in SA suffered the consequences of load shedding how many senior managers and Board members at ESKOM were held accountable? Do not allow the ESKOM increase applied for let them do what all of us were forced to do cut back and become more effective, efficient & economical. Review license agreements of all muni s, first non-paying municipalities. There must be consequences for a Council/Municipality that do not pay ESKOM Insist, as license condition: Municipal tariff calculation submitted with detailed working papers to Council and included as part of public participation during budget process Clear cut role differentiation between NERSA and Municipalities on tariff determination and tariff approval

13 Leaders are dealers in HOPE Munsolve call on NERSA to bring HOPE, based on integrity, to electricity consumers! Without a process that we can believe in, the integrity of the process is tarnished, which will eventually find expression in PROTEST, as the voice of the UNHEARD! Thank you Baie dankie Ke a leboga Obricado Siyabonga

Update on the Energy Conservation Scheme (ECS) proposed by the DME and Eskom. by Chris Yelland CEng Managing editor EE Publishers

Update on the Energy Conservation Scheme (ECS) proposed by the DME and Eskom. by Chris Yelland CEng Managing editor EE Publishers Update on the Energy Conservation Scheme (ECS) proposed by the DME and Eskom by Chris Yelland CEng Managing editor EE Publishers Background to the ECS The ECS is a component of the Power Conservation Programme

More information

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA. Electricity Subcommittee Public Hearing 3 June 2010

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA. Electricity Subcommittee Public Hearing 3 June 2010 Presentation ti to the NATIONAL ENERGY REGULATOR OF SOUTH AFRICA Electricity Subcommittee Public Hearing 3 June 2010 1 Content of Presentation Motivation and background of Tariff Increases proposed General

More information

ANNEXURE 1. Consultation Paper

ANNEXURE 1. Consultation Paper ANNEXURE 1 MUNICIPAL TARIFF GUIDELINE INCREASE, BENCHMARKS AND PROPOSED TIMELINES FOR MUNICIPAL TARIFF APPROVAL PROCESS FOR THE 2018/19 FINANCIAL YEAR Consultation Paper Published on 28 February 2018 Table

More information

AMEU Convention Tuesday 28 SEPTEMBER 2010 Stellenbosch

AMEU Convention Tuesday 28 SEPTEMBER 2010 Stellenbosch AMEU Convention Tuesday 28 SEPTEMBER 2010 Stellenbosch Chief Engineer: Metering, Vending and Tariffs City of Ekurhuleni Stephen Delport 28 SEPTEMBER 2010 During the Depression years, when power lines first

More information

Residential tariff increases and restructuring for MYPD3 explained. Brochure

Residential tariff increases and restructuring for MYPD3 explained. Brochure Residential tariff increases and restructuring for MYPD3 explained Brochure November 2012 Residential brochure for MYPD3 changes Page 1 PART 1: ESKOM REVENUE REQUIREMENT Introduction Eskom applies for

More information

CENTLEC HOUSEHOLD TARIFFS: 2017/2018 versus 2016/2017

CENTLEC HOUSEHOLD TARIFFS: 2017/2018 versus 2016/2017 CENTLEC HOUSEHOLD TARIFFS: /2018 versus 2016/ (including Tariff amendment of 1 July ). To explain the tariffs between the 1 July to 30 June 2018 (current Centlec Financial Year) in comparison with those

More information

NERSA Submissions ESKOM RCA

NERSA Submissions ESKOM RCA NERSA Submissions ESKOM RCA 4 February 2016 Presented by: Stefan Pieterse Armand Greyling Content 1. Who is AfriBusiness 2. RCA Methodology 3. Municipal Budget Process 4. Eskom Revenue Variance 5. OCGT

More information

ANNEXURE 1. Consultation Paper

ANNEXURE 1. Consultation Paper ANNEXURE 1 MUNICIPAL TARIFF GUIDELINE INCREASE, BENCHMARKS AND PROPOSED TIMELINES FOR MUNICIPAL TARIFF APPROVAL PROCESS FOR THE 2017/18 FINANCIAL YEAR Consultation Paper 23 February 2017 TABLE OF CONTENTS

More information

THE 2010/11 TARIFF ADJUSTMENT. Standard schedule of Tariffs

THE 2010/11 TARIFF ADJUSTMENT. Standard schedule of Tariffs THE TARIFF ADJUSTMENT Standard schedule of Tariffs Scenario Modelling Tool (SMT) Tariff options Only change is to the residential Standard ' options - Urban Rural Residential Megaflex Ruraflex Inclining

More information

ESKOM One Year Application 2018/19

ESKOM One Year Application 2018/19 ESKOM One Year Application 2018/19 NERSA 1 November 2017 Nelson Mandela Bay Business Chamber Comments and Recommendations Overview The Nelson Mandela Bay Business Chamber What the application means for

More information

Eskom 2018/19 Revenue Application

Eskom 2018/19 Revenue Application Eskom 2018/19 Revenue Application Nersa Public Hearings Bloemfontein 15 November 2017 Where we are coming from This revenue application is being made for the year 2018/19, after the Energy Regulator maintained

More information

Electricity theft and non-payment: Impact and action plan. by Chris Yelland CEng Managing editor EE Publishers

Electricity theft and non-payment: Impact and action plan. by Chris Yelland CEng Managing editor EE Publishers Electricity theft and non-payment: Impact and action plan by Chris Yelland CEng Managing editor EE Publishers Outline The scale of electricity theft and non-payment The impact on the national demand The

More information

ESKOM s applications for MYPD4 and MYPD3 RCA 2017/18

ESKOM s applications for MYPD4 and MYPD3 RCA 2017/18 ESKOM s applications for MYPD4 and MYPD3 RCA 2017/18 NERSA 15 January 2019 Nelson Mandela Bay Business Chamber Comments and Recommendations Overview The Nelson Mandela Bay Business Chamber What the applications

More information

Eskom 2018/19 Revenue Application

Eskom 2018/19 Revenue Application Eskom 2018/19 Revenue Application Nersa Public Hearings 30 October 2017 Where we are coming from This revenue application is being made for the year 2018/19, after the Energy Regulator maintained its revenue

More information

Draft Eskom 2018/19 Revenue Application

Draft Eskom 2018/19 Revenue Application Draft Eskom 2018/19 Revenue Application Nersa Public Hearings Durban 2 November 2017 Where we are coming from This revenue application is being made for the year 2018/19, after the Energy Regulator maintained

More information

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA In the matter regarding NATIONAL ENERGY REGULATOR OF SOUTH AFRICA DETERMINATION OF THE MUNICIPAL TARIFF GUIDELINE FOR THE FINANCIAL YEAR 2013/14 AND THE REVISION OF MUNICIPAL TARIFF BENCHMARKS DECISION

More information

FFC Public Hearings on the LG Fiscal Framework. Comment by SALGA

FFC Public Hearings on the LG Fiscal Framework. Comment by SALGA FFC Public Hearings on the LG Fiscal Framework Comment by SALGA Leriba Lodge 4 June 2012 Overview Introduction General Comments Service Delivery Capital Investment Revenue Patterns Expenditure LGFF Proposed

More information

Demystifying Tariff Setting The tariff conundrum Lower rates now, blackouts later?

Demystifying Tariff Setting The tariff conundrum Lower rates now, blackouts later? Demystifying Tariff Setting The tariff conundrum Lower rates now, blackouts later? Does South Africa need a cost reflective tariff? For years, low electricity costs have been a driver behind South Africa

More information

SWARTLAND MUNICIPALITY

SWARTLAND MUNICIPALITY SWARTLAND MUNICIPALITY PRESENTATION AT NERSA PUBLIC HEARING 3 JUNE 2010 2010/11 ELECTRICITY TARIFF APPLICATION R DU TOIT Pr Eng 1 2 ACKNOWLEDGEMENTS Extracts and copies from public documents included in

More information

MYPD3 Application Gauteng January 2013

MYPD3 Application Gauteng January 2013 MYPD3 Application 2014-2018 Gauteng January 2013 Disclaimer This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or invitation of

More information

Eskom Revenue Application. Multi Year Price Determination. 2010/11 to 2012/13 (MYPD 2)

Eskom Revenue Application. Multi Year Price Determination. 2010/11 to 2012/13 (MYPD 2) Issues Paper Eskom Revenue Application Multi Year Price Determination 2010/11 to 2012/13 (MYPD 2) Published on 30 October 2009 1 TABLE OF CONTENTS Abbreviations... 3 Definitions... 4 1. Introduction...6

More information

GUIDELINE DOCUMENT TO MUNICIPALITIES ON THE DESIGN OF A DOMESTIC INCLINING BLOCK RATE TARIFF

GUIDELINE DOCUMENT TO MUNICIPALITIES ON THE DESIGN OF A DOMESTIC INCLINING BLOCK RATE TARIFF GUIDELINE DOCUMENT TO MUNICIPALITIES ON THE DESIGN OF A DOMESTIC INCLINING BLOCK RATE TARIFF 1. BACKGROUND AND APPROACH 1.1. During the National Energy Regulator of South Africa (NERSA) stakeholder consultation

More information

COMPANY OVERVIEW ABOUT PEC METERING. Background

COMPANY OVERVIEW ABOUT PEC METERING. Background COMPANY OVERVIEW ABOUT PEC METERING Background PEC Metering (Pty) Ltd is a private professional company established in 1994, specialising in utility management services and energy management with operations

More information

SETSOTO LOCALL MUNICIPALITY

SETSOTO LOCALL MUNICIPALITY ANNUAL BUDGET OF SETSOTO LOCALL MUNICIPALITY Page 1 TABLE OF CONTENTS 2013/14 TO 2015/16 MEDIUM TERM REVENUE AND EXPENDITURE FORECASTS PART 1: ANNUAL BUDGET 6 1.1 MAYOR S REPORT 6 (REFER TO THE ATTACHMENT)

More information

(011) (fax) Department:

(011) (fax) Department: Telephone: (011) 999-5263 (work) Ekurhuleni Metropolitan Municipality (011) 917-1634 (fax) Department: e-mail: stephen.delport@ekurhuleni.gov.za Electricity and Energy PO Box 215 Boksburg 1460 62 nd AMEU(SA)

More information

ESKOM RCA APPLICATION TO NERSA: MINING SECTOR RESPONSE

ESKOM RCA APPLICATION TO NERSA: MINING SECTOR RESPONSE ESKOM RCA APPLICATION TO NERSA: MINING SECTOR RESPONSE Henk Langenhoven Chief Economist: Chamber of Mines Midrand 14 May 2018 PAGE CONTENTS Mining Sector CONTRIBUTION, and Conclusions re 20% Tariff Application

More information

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA

NATIONAL ENERGY REGULATOR OF SOUTH AFRICA NATIONAL ENERGY REGULATOR OF SOUTH AFRICA In the matter regarding DETERMINATION OF THE MUNICIPAL TARIFF GUIDELINE AND THE REVISION OF MUNICIPAL TARIFF BENCHMARKS FOR THE FINANCIAL YEAR 2011/12 DECISION

More information

Approved New Tariffs & Rates for City of Johannesburg Effective 1 July 2011 Principally Residential / Domestic Tariffs Prepared 30 th August 2011

Approved New Tariffs & Rates for City of Johannesburg Effective 1 July 2011 Principally Residential / Domestic Tariffs Prepared 30 th August 2011 Approved New Tariffs & Rates for City of Johannesburg Effective 1 July 2011 Principally Residential / Domestic Tariffs Prepared 30 th August 2011 This document has been prepared by the DA caucus of the

More information

RCAs submitted for FY2014/15, FY 2015/16 and FY 2016/17. NERSA Public Hearings 17 April 2018

RCAs submitted for FY2014/15, FY 2015/16 and FY 2016/17. NERSA Public Hearings 17 April 2018 RCAs submitted for FY2014/15, FY 2015/16 and FY 2016/17 NERSA Public Hearings 17 April 2018 Regulator members requests Eskom has taken note of all requests made by Regulator members of the panel for :

More information

PRESENTATION AT NERSA PUBLIC HEARINGS FOR ESKOM S MYPD3 RCA FOR YEAR 5 RONALD CHAUKE 14 JANUARY 2019

PRESENTATION AT NERSA PUBLIC HEARINGS FOR ESKOM S MYPD3 RCA FOR YEAR 5 RONALD CHAUKE 14 JANUARY 2019 PRESENTATION AT NERSA PUBLIC HEARINGS FOR ESKOM S MYPD3 RCA FOR YEAR 5 RONALD CHAUKE 14 JANUARY 2019 1 CONTENT Introduction Context Operating Costs Reporting Best Practice Primary Energy World Bank Report

More information

Eskom 2018/19 Revenue Application

Eskom 2018/19 Revenue Application Eskom 2018/19 Revenue Application Nersa Public Hearings Klerksdorp 13 November 2017 Where we are coming from This revenue application is being made for the year 2018/19, after the Energy Regulator maintained

More information

BUSA presentation to NERSA on Eskom s RCA Application Multi Year Price Determination (MYPD3) Year 1 (2013/2014) 5 February 2016

BUSA presentation to NERSA on Eskom s RCA Application Multi Year Price Determination (MYPD3) Year 1 (2013/2014) 5 February 2016 BUSA presentation to NERSA on Eskom s RCA Application Multi Year Price Determination (MYPD3) Year 1 (2013/2014) 5 February 2016 Martin Kingston Chair: BUSA Standing Committee on Economic & Trade Policy

More information

Energy and Climate Change Programme P O Box 106 Office Tel: (+27) (0) Fax:

Energy and Climate Change Programme P O Box 106 Office Tel: (+27) (0) Fax: SAFCEI is a company not for profit Reg No 2006/014388/08 NPO 053498 PBO 930024255 Faith communities committed to cherishing living earth. www.safcei.org.za Energy and Climate Change Programme P O Box 106

More information

Tariffs and Tariff Design Promoting Access to the Poor

Tariffs and Tariff Design Promoting Access to the Poor Regulation for Practitioners Building Capacity through Participation Tariffs and Tariff Design Promoting Access to the Poor Gloria Magombo Energy Advisor gmagombo@satradehub.org July 27-31, Eskom Convention

More information

MYPD3 Application January 2013

MYPD3 Application January 2013 MYPD3 Application 2014-2018 January 2013 Disclaimer This presentation does not constitute or form part of and should not be construed as, an offer to sell, or the solicitation or invitation of any offer

More information

Low-Income Customers and Role of the Regulator in Energy Affordability

Low-Income Customers and Role of the Regulator in Energy Affordability Energy Regulatory Partnership Program Low-Income Customers and Role of the Regulator in Energy Affordability Svetla Todorova, Commissioner State Energy and Water Regulatory Commission of Bulgaria stodorova@dker.bg

More information

SALGA Position on Eskom Revenue Proposal 2018/19 Cllr M. Mfikoe Nhlanhla L Ngidi Lonwabo Magida 16 November 2017

SALGA Position on Eskom Revenue Proposal 2018/19 Cllr M. Mfikoe Nhlanhla L Ngidi Lonwabo Magida 16 November 2017 SALGA Position on Eskom Revenue Proposal 2018/19 Cllr M. Mfikoe Nhlanhla L Ngidi Lonwabo Magida 16 November 2017 www.salga.org.za Content Introduction Cllr Matshidiso Mfikoe SALGA Summary of Observations

More information

Cover slide (same as IR cover)

Cover slide (same as IR cover) Integrated results for the year ended 31 March 2015 Cover slide (same as IR cover) 11 August 2015 This presentation is available at www.eskom.co.za/ir2015 Contents Overview of the year Financial review

More information

RAINMAKER ENERGY. Comments to 2011 NERSA REFIT Review Tariffs

RAINMAKER ENERGY. Comments to 2011 NERSA REFIT Review Tariffs RAINMAKER ENERGY Comments to 2011 NERSA REFIT Review Tariffs 1 About Rainmaker Rainmaker Energy is developing Wind projects within South Africa Two flagship projects are in final stage of development,

More information

ESKOM S FINANCIAL CRISES AND CONTINUING TARIFF INCREASES

ESKOM S FINANCIAL CRISES AND CONTINUING TARIFF INCREASES ESKOM S FINANCIAL CRISES AND CONTINUING TARIFF INCREASES Strategies for containing costs and stabilising its financial position. NERSA Public hearing on Eskom s revenue application for 2018/19 Cape Town,

More information

retail SNAPSHOT the impact of price hikes on retail spend Has the high cost of living impacted spending habits?

retail SNAPSHOT the impact of price hikes on retail spend Has the high cost of living impacted spending habits? retail SNAPSHOT the impact of price hikes on retail spend Has the high cost of living impacted spending habits? Q2 www.broll.com THE IMPACT OF PRICE HIKES ON RETAIL SPEND With continuous increases in petrol

More information

POST-CABINET MEDIA BRIEFING

POST-CABINET MEDIA BRIEFING POST-CABINET MEDIA BRIEFING By Phindile Nzimande CEO Holdings (Pty) Ltd 31 October 2006 Summary of Who We Are EDI HOLDINGS is a 100% state owned company We were established in 2003 to restructure the electricity

More information

Dr Willem J. De Beer, Chief Operations Officer, EDI Holdings (Pty) Ltd, South Africa 23November 2010

Dr Willem J. De Beer, Chief Operations Officer, EDI Holdings (Pty) Ltd, South Africa 23November 2010 Dr Willem J. De Beer, Chief Operations Officer, EDI Holdings (Pty) Ltd, South Africa 23November 2010 The process of dealing with the EDI maintenance backlog: Can we catch up? Electricity Supply Chain GENERATION

More information

29 March 2012 MBOMBELA LOCAL MUNICIPALITY DRAFT 2012/ /2015 ANNUAL BUDGET AND MEDIUM- TERM REVENUE AND EXPENDITURE FRAMEWORK

29 March 2012 MBOMBELA LOCAL MUNICIPALITY DRAFT 2012/ /2015 ANNUAL BUDGET AND MEDIUM- TERM REVENUE AND EXPENDITURE FRAMEWORK 29 March 2012 MBOMBELA LOCAL MUNICIPALITY DRAFT 2012/2013 2014/2015 ANNUAL BUDGET AND MEDIUM- TERM REVENUE AND EXPENDITURE FRAMEWORK MBOMBELA LOCAL MUNICIPALITY 2012/13 TO 2014/15 DRAFT ANNUAL BUDGET AND

More information

SANCO FREE STATE PROVINCE

SANCO FREE STATE PROVINCE Cnr Charles & Fichardt Streets P.O. Box 4447 Kaizer Sebothelo Building Bloemfontein 9300 Date: 21 January 2013 SANCO FREE STATE PROVINCE PRESENTATION ON ESKOM PROPOSED TARIFFS INCREASE VENUE: MANGAUNG

More information

09 MAY 2017 MEDIA STATEMENT NAMPOWER TARIFF ADJUSTMENT FOR THE FINANCIAL PERIOD 2017/2018

09 MAY 2017 MEDIA STATEMENT NAMPOWER TARIFF ADJUSTMENT FOR THE FINANCIAL PERIOD 2017/2018 09 MAY 2017 MEDIA STATEMENT NAMPOWER TARIFF ADJUSTMENT FOR THE FINANCIAL PERIOD 2017/2018 MEMBERS OF THE MEDIA, COLLEAGUES, LADIES & GENTLEMEN It is my honour to announce that the Board of Directors of

More information

Brochure on Eskom s Policy for granting the benefit of diversity. July 2013

Brochure on Eskom s Policy for granting the benefit of diversity. July 2013 Brochure on Eskom s Policy for granting the benefit of diversity July 2013 Brochure on Eskom s policy for Granting the benefit of diversity 2 Contents Eskom Policy on granting the benefit of diversity...

More information

A Rational Price Path for South Africa

A Rational Price Path for South Africa A Rational Price Path for South Africa Finding the Balance Nersa s task in MYPD3 Serious Imbalance Not in Balance Balanced c. Contain taxes and levies A Balanced Solution Set Business, Eskom, NERSA and

More information

Submission to SALGA and National Treasury

Submission to SALGA and National Treasury MYPD 3 Re-opener for selective items (2015/16~2017/18) o OCGTs and o STPPP Including the Submission to SALGA and National Treasury In terms of the Municipal Finance Management Act (MFMA) 16 March 2015

More information

AMEU CONVENTION 2010 MUNICIPAL TARIFF CHALLENGES

AMEU CONVENTION 2010 MUNICIPAL TARIFF CHALLENGES AMEU CONVENTION 2010 MUNICIPAL TARIFF CHALLENGES Ir Leon Kritzinger 28 September 2010 What lies behind us and what lies before us are tiny matters compared to what lies within us. Walt Emerson Challenges

More information

THE JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION, RANCHI. Case No. 25 of JHARKHAND BIJLI VITRAN NIGAM LIMITED Petitioner P R E S E N T

THE JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION, RANCHI. Case No. 25 of JHARKHAND BIJLI VITRAN NIGAM LIMITED Petitioner P R E S E N T THE JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION, RANCHI. Case No. 25 of 2015. JHARKHAND BIJLI VITRAN NIGAM LIMITED Petitioner P R E S E N T Hon ble Mr. Justice N.N. Tiwari, Chairperson Hon ble Mr.

More information

The South African Grid Code. Transmission Tariff Code. Version 9.0

The South African Grid Code. Transmission Tariff Code. Version 9.0 The South African Grid Code Transmission Tariff Code Version 9.0 This document is approved by the National Energy Regulator of South Africa (NERSA) Issued by: RSA Grid Code Secretariat Contact: Mr. Bernard

More information

Eskom s Draft Application to NERSA for Price. Increase in 2008/9

Eskom s Draft Application to NERSA for Price. Increase in 2008/9 Eskom s Draft Application to NERSA for Price Increase in 2008/9 Submitted to NERSA on 17 March 2008 Table of Contents Executive Summary... 4 1 Background and Introduction... 12 2 Primary Energy... 20 3

More information

AND NOTICE OF HEARING REVIEW OF NON-PAYMENT OF ACCOUNT SERVICE CHARGES FOR ELECTRCITY AND NATURAL GAS DISTRIBUTORS BOARD FILE NO.

AND NOTICE OF HEARING REVIEW OF NON-PAYMENT OF ACCOUNT SERVICE CHARGES FOR ELECTRCITY AND NATURAL GAS DISTRIBUTORS BOARD FILE NO. Ontario Energy Board P.O. Box 2319 27th Floor 2300 Yonge Street Toronto ON M4P 1E4 Telephone: 416-481-1967 Facsimile: 416-440-7656 Toll free: 1-888-632-6273 Commission de l énergie de l Ontario C.P. 2319

More information

GUIDE TO PROPERTY TAXES

GUIDE TO PROPERTY TAXES NEW JERSEY HOMEOWNER S GUIDE TO PROPERTY TAXES ASSOCIATION OF MUNICIPAL ASSESSORS OF NEW JERSEY Property taxes are top of mind for many New Jersey homeowners. The state has the highest property taxes in

More information

Portfolio Committee on Energy

Portfolio Committee on Energy Portfolio Committee on Energy Briefing Integrated National Electrification Programme (INEP) 26 August 2014 Context & Purpose Previous briefings to PC on INEP DoE in September 2013 Salga and DoE in February

More information

CONSULTATION PAPER ON THE REVIEW OF INCLINING BLOCK TARIFFS FOR ELECTRICITY DISTRIBUTORS

CONSULTATION PAPER ON THE REVIEW OF INCLINING BLOCK TARIFFS FOR ELECTRICITY DISTRIBUTORS CONSULTATION PAPER ON THE REVIEW OF INCLINING BLOCK TARIFFS FOR ELECTRICITY DISTRIBUTORS Published on 21 September 2012 Page 1 of 41 TABLE OF CONTENTS 1. Introduction... 4 2. NERSA Mandate... 5 3. Background...

More information

PRESENTATION TO NERSA BY Mr WH BOSHOFF

PRESENTATION TO NERSA BY Mr WH BOSHOFF PRESENTATION TO NERSA BY Mr WH BOSHOFF The presenter has been in property and development for over 20 years. He is the owner of numerous commercial developments and various other properties. He is paying

More information

OUTA Presentation to NERSA Eskom s 2018/19 application NOVEMBER 2017

OUTA Presentation to NERSA Eskom s 2018/19 application NOVEMBER 2017 OUTA Presentation to NERSA Eskom s 2018/19 application NOVEMBER 2017 1 TABLE OF CONTENTS Introduction Our Requests Our Concerns Declining Corporate Governance Lack of Transparency Regulatory Decision Making

More information

A study into approaches to minimise the impact of electricity price increases on the poor

A study into approaches to minimise the impact of electricity price increases on the poor TRADE AND INDUSTRY CHAMBER FUND FOR RESEARCH INTO INDUSTRIAL DEVELOPMENT, GROWTH AND EQUITY (FRIDGE) A study into approaches to minimise the impact of electricity price increases on the poor Final Report

More information

NERSA to consider public opinion on the ESKOM proposed revenue application multi-year price determination 2013/14 to 2017/18 (MYPD 3)

NERSA to consider public opinion on the ESKOM proposed revenue application multi-year price determination 2013/14 to 2017/18 (MYPD 3) NERSA to consider public opinion on the ESKOM proposed revenue application multi-year price determination 2013/14 to 2017/18 (MYPD 3) MMC presentation to NERSA on 25 January 2013 to illustrate what the

More information

Foreign Affairs and International Development Committee. Appearance regarding Bill C-300, November 17, Opening Statement

Foreign Affairs and International Development Committee. Appearance regarding Bill C-300, November 17, Opening Statement Foreign Affairs and International Development Committee Appearance regarding Bill C-300, November 17, 2009 Opening Statement My name is Donald Raymond and I am Senior Vice President of Public Market Investments

More information

ACER 2 nd Annual Conference Roundtable: The infrastructure challenge 17 May, 14:00 15:10 Grand Union Hotel, Ljubljana

ACER 2 nd Annual Conference Roundtable: The infrastructure challenge 17 May, 14:00 15:10 Grand Union Hotel, Ljubljana Ref.: 13GIE076 May 2013 ACER 2 nd Annual Conference Roundtable: The infrastructure challenge 17 May, 14:00 15:10 Grand Union Hotel, Ljubljana Roundtable: The Infrastructure Challenge Moderator: Piotr Wozniak

More information

Eskom Regulatory Clearing Account (RCA) year 5 of MYPD 3. Public Hearings- Port Elizabeth Date: 16 January 2019

Eskom Regulatory Clearing Account (RCA) year 5 of MYPD 3. Public Hearings- Port Elizabeth Date: 16 January 2019 Eskom Regulatory Clearing Account (RCA) year 5 of MYPD 3 Public Hearings- Port Elizabeth Date: 16 January 2019 RCA (Yr 5, MYPD3) Timeline RCAs require 3 decisions: 1 Balance decision 2 Liquidation decision

More information

BC HYDRO S RATE DESIGN APPLICATION FARM AND IRRIGATION CUSTOMER ISSUES. Presentation to the BC Cranberry Marketing Commission (BCCMC) June 15, 2015

BC HYDRO S RATE DESIGN APPLICATION FARM AND IRRIGATION CUSTOMER ISSUES. Presentation to the BC Cranberry Marketing Commission (BCCMC) June 15, 2015 BC HYDRO S RATE DESIGN APPLICATION FARM AND IRRIGATION CUSTOMER ISSUES Presentation to the BC Cranberry Marketing Commission (BCCMC) June 15, 2015 AGENDA Background on BC Hydro s 2015 Rate Design Application

More information

SAWEA submission to the public hearing relating to the NERSA review of the REFIT tariffs. By: Johan van den Berg, CEO.

SAWEA submission to the public hearing relating to the NERSA review of the REFIT tariffs. By: Johan van den Berg, CEO. SAWEA submission to the public hearing relating to the NERSA review of the REFIT tariffs By: Johan van den Berg, CEO Date: May 2011 Overview 1. Who we are and our vision 2. Some history of our engagement

More information

Department of Energy South Africa

Department of Energy South Africa Department of Energy South Africa Policy to support the Energy Efficiency and Demand Side Management Program for the Electricity Sector through the Standard Offer Incentive Scheme Draft: March 2010 1 TABLE

More information

South Africa s Platinum Mining Crisis

South Africa s Platinum Mining Crisis South Africa s Platinum Mining Crisis Presentation : 30 January 2014. Roger Baxter Chief Operating Officer Presentation Outline The Global Platinum Environment The South African Platinum Mining Industry

More information

Standard Domestic Contractual Terms & Conditions

Standard Domestic Contractual Terms & Conditions Standard Domestic Contractual Terms & Conditions T&C-DOM-v.0.1 These are the terms and conditions for the supply of electricity and/or gas to your domestic property. First, here is some basic information

More information

Registration application fee to be paid by Small-Scale Embedded Generator Applicants

Registration application fee to be paid by Small-Scale Embedded Generator Applicants Consultation Paper: Registration application fee to be paid by Small-Scale Embedded Generator Applicants Published 16 December 2018 Version 1 December 2018 Issued by The National Energy Regulator of South

More information

FUNDING & RESERVES POLICY

FUNDING & RESERVES POLICY FUNDING & RESERVES POLICY UNCHANGED 1 JULY 2016 STEVE TSHWETE LOCAL MUNICIPALITY MP 313 Approved May 2016 C36/05/2016 1. INTRODUCTION The funding and reserves policy is aimed to ensure that the municipality

More information

Eskom s revenue application for 2018/19. Presentation to NERSA public hearings 30 October 2017

Eskom s revenue application for 2018/19. Presentation to NERSA public hearings 30 October 2017 Eskom s revenue application for 2018/19 Presentation to NERSA public hearings 30 October 2017 SACTWU & CTFL Sector Organises clothing, textile, footwear, leather and related workers +100 000 members Black,

More information

SOLUTION. [?]Adoption by all stakeholders of a vision document for the ESI

SOLUTION. [?]Adoption by all stakeholders of a vision document for the ESI 18 June 2014 Ms Trudi Mcloughlin, BUSA By email Dear Ms Mcloughlin ENERGY SECURITY WORKSHOP 5 JUNE 2014 Please find below our response to your recent survey request. KEY CHALLENGES IN THE POWER / ELECTRICITY

More information

PRESENTATION TO SABOA CONFERENCE

PRESENTATION TO SABOA CONFERENCE PRESENTATION TO SABOA CONFERENCE THE DEVELOPMENT OF PERFORMANCE BASED GROSS NEGOTIATED MODEL CONTRACT DOCUMENT FOR THE ROLL-OUT OF IPTNs 23 FEBRUARY 2012 1 CONTENTS PURPOSE OF THE PRESENTATION CURRENT

More information

NATIONAL ENERGY REGULATOR. Eskom MYPD2 Regulatory Clearing Account (RCA) and RCA Balance THE DECISION

NATIONAL ENERGY REGULATOR. Eskom MYPD2 Regulatory Clearing Account (RCA) and RCA Balance THE DECISION Eskom Holdings Limited: Regulatory Clearing Account Application - Multi Year Price Determination 2010/11 to 2012/13 (MYPD2). NATIONAL ENERGY REGULATOR In the matter regarding Eskom MYPD2 Regulatory Clearing

More information

Tucson Electric Power Company Rules and Regulations

Tucson Electric Power Company Rules and Regulations Original Sheet No.: 911 A. Frequency and Estimated Bills 1. The Company will bill monthly for services rendered. Meter readings will be scheduled for periods of not less than twenty-five (25) days or more

More information

1.1 Executive Mayor s Report Council Resolutions Executive Summary Operating Expenditure Framework Capital Expenditure 22

1.1 Executive Mayor s Report Council Resolutions Executive Summary Operating Expenditure Framework Capital Expenditure 22 TABLE OF CONTENTS 2 PART 1 ANNUAL BUDGET Page 1.1 Executive Mayor s Report 5 1.2 Council Resolutions 7 1.3 Executive Summary 8 1.4 Operating Revenue Framework 10 1.5 Operating 18 1.6 Capital Expenditure

More information

DOING BUSINESS IN BULGARIA

DOING BUSINESS IN BULGARIA COMPANY FORMATION IN MAIN FORMS OF COMPANY/BUSINESS IN Entities in Bulgaria fall under the following categories: resident and non-resident. Resident entities can be registered as branches or subsidiaries,

More information

South Africa s Platinum Mining Crisis

South Africa s Platinum Mining Crisis South Africa s Platinum Mining Crisis Presentation to the Parliamentary Portfolio Committee: Minerals 20 th February 2013. Roger Baxter Senior Executive: Economics & Strategy 1 2 Presentation Outline The

More information

Solar PV where the sun doesn t shine: Estimating the economic impacts of support schemes for residential PV with detailed net demand profiling

Solar PV where the sun doesn t shine: Estimating the economic impacts of support schemes for residential PV with detailed net demand profiling Sources: www.engineersjournal.ie; www.investopedia.com; www.theguardian.com Solar PV where the sun doesn t shine: Estimating the economic impacts of support schemes for residential PV with detailed net

More information

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB TILLSONBURG HYDRO INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB TILLSONBURG HYDRO INC. Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER TILLSONBURG HYDRO INC. Application for an order approving just and reasonable rates and other charges for electricity distribution

More information

Notice of Public Hearing for Proposed Change to a Water Budget Rate Structure to be Held at Murrieta City Hall

Notice of Public Hearing for Proposed Change to a Water Budget Rate Structure to be Held at Murrieta City Hall May 20, 2011 Notice of Public Hearing for Proposed Change to a Water Budget Rate Structure to be Held at Murrieta City Hall Dear Western Municipal Water District customer, Every Western Municipal Water

More information

Financial Highlights Q May 3, 2018

Financial Highlights Q May 3, 2018 Financial Highlights Q1 2018 May 3, 2018 1 COPYRIGHT RUBICON PROJECT 2018 SAFE HARBOR FORWARD-LOOKING STATEMENTS This presentation and management's prepared remarks during the conference call referred

More information

Pre-Budget Consultation Submission to the Ministry of Finance

Pre-Budget Consultation Submission to the Ministry of Finance Kitchener, January 31 st, 2014 The Honorable Charles Sousa Minister of Finance Government of Ontario c/o Budget Secretariat Submitted by email: submissions@ontario.ca Pre-Budget Consultation Submission

More information

The Truth About How To Create A Secure Retirement Income For Life

The Truth About How To Create A Secure Retirement Income For Life The Truth About How To Create A Secure Retirement Income For Life By Mark Kennedy, www.kennedywealthmgmt.com There is so much conflicting information out in the media world about what to do with your money

More information

Title of presentation

Title of presentation Tariffs versus Return on Investment Title of presentation Cornelis van der Waal Industry Manager Africa Energy and Power Systems Power Indaba 2008, Cape Town, South Africa TOC Current State of the Electricity

More information

ESKOM S DEMAND EXEMPTION POLICY. This document may be updated from time to time, please refer to for the latest version.

ESKOM S DEMAND EXEMPTION POLICY. This document may be updated from time to time, please refer to   for the latest version. ESKOM S DEMAND EXEMPTION POLICY This document may be updated from time to time, please refer to www.eskom.co.za/tariffs for the latest version. Eskom s Demand Exemption Policy Page 2 of 15 1. Introduction...

More information

non-rate-regulated entities; and rate-regulated entities that do not recognise such balances?

non-rate-regulated entities; and rate-regulated entities that do not recognise such balances? Questions for respondents Question 1 What information about the entity s rate-regulated activities and the rate-regulatory environment do you think preparers of financial statements need to include in

More information

Environmental Change Institute. The future of Energy Efficiency Obligation Schemes in the EU Tina Fawcett, Jan Rosenow & Paolo Bertoldi

Environmental Change Institute. The future of Energy Efficiency Obligation Schemes in the EU Tina Fawcett, Jan Rosenow & Paolo Bertoldi Environmental Change Institute The future of Energy Efficiency Obligation Schemes in the EU Tina Fawcett, Jan Rosenow & Paolo Bertoldi Key questions Can established Energy Efficiency Obligation Schemes

More information

CHAPTER I: PRELIMINARY Short title, commencement and interpretation

CHAPTER I: PRELIMINARY Short title, commencement and interpretation Notification dated 20.2.2009 Bhopal: dated 31 st January, 2009 No. 254-MPERC-2009. In exercise of the powers conferred by Section 181 read with Subsection (b) of Section 86 of the Electricity Act 2003

More information

With Compliments. Make The Right Choice HARD LABOUR NEEDED AT THE DEPARTMENT OF LABOUR

With Compliments. Make The Right Choice HARD LABOUR NEEDED AT THE DEPARTMENT OF LABOUR With Compliments Make The Right Choice 1st Floor, Kenilworth Park 202 Brickfield Road OVERPORT 4091 Tel: 031 204 3311 Fax: 031 207 7705 e-mail : dji@dji.co.za Web site : www.dji.co.za Forward email Online

More information

MYPD Methodology Eskom Response to Consultation Paper

MYPD Methodology Eskom Response to Consultation Paper MYPD Methodology Eskom Response to Consultation Paper 2 June 2016 Introduction Eskom is pleased to provide comments Eskom has provided detailed responses to the consultation paper on the review of the

More information

Local Decisions have created Texas cities where people want to

Local Decisions have created Texas cities where people want to Roanoke Local Decisions have created Texas cities where people want to Local Decisions have created Texas cities where people want to Live Local Decisions have created Texas cities where people want to

More information

Minimum compliance and Alignment with MFMA Calendar. Presented by National Treasury 16 March 2016

Minimum compliance and Alignment with MFMA Calendar. Presented by National Treasury 16 March 2016 Minimum compliance and Alignment with MFMA Calendar Presented by National Treasury 16 March 2016 Compliance When: 1 July 2017 Responsible for: Municipal Councils and Boards of Municipal Entities Implementation

More information

Consumer Rights, Responsibilities, and Education

Consumer Rights, Responsibilities, and Education Consumer Rights, Responsibilities, and Education NARUC Energy Regulatory Partnership Program The Public Services Regulatory Commission of Armenia and The Iowa Utilities Board by Joan Conrad Chief of Staff

More information

Uncertainties within South Africa s goal of universal access to electricity by 2012

Uncertainties within South Africa s goal of universal access to electricity by 2012 Uncertainties within South Africa s goal of universal access to electricity by 2012 B Bekker, CT Gaunt Department of Electrical Engineering, University of Cape Town, South Africa A Eberhard Graduate School

More information

The political-economy of power sector reform in South Africa. Prof Anton Eberhard

The political-economy of power sector reform in South Africa. Prof Anton Eberhard The political-economy of power sector reform in South Africa Prof Anton Eberhard Graduate School of Business University of Cape Town & Board of the National Electricity Regulator Overview istorical development

More information

Energy Losses Management Programme

Energy Losses Management Programme AMEU CONVENTION 2010 Energy Losses Management Programme Presentation to AMEU Presenter: Maboe Maphaka Senior Manager Energy Trading / ELP Project Sponsor 28 September 2010 Defining Energy Losses Technical

More information

COSATU CONGRESS OF SOUTH AFRICAN TRADE UNIONS COSATU COMMENT ON ESKOM S MYPD3 FOR THE YEAR 2, 3, 4

COSATU CONGRESS OF SOUTH AFRICAN TRADE UNIONS COSATU COMMENT ON ESKOM S MYPD3 FOR THE YEAR 2, 3, 4 COSATU CONGRESS OF SOUTH AFRICAN TRADE UNIONS Head Office 110 Jorissen Street Braamfontein 2017 JOHANNESBURG P O Box 1019 JOHANNESBURG 2000 Tel: + 27 11 339 4911 Fax: + 27 11 339 5080 Internet: http://www.cosatu.org.

More information

Online Fixed Energy A Guaranteed Deal

Online Fixed Energy A Guaranteed Deal Online Fixed Energy A Guaranteed Deal Online Fixed Price Energy February 2016 Prices effective from 20th January 2015 Subject to availability and may be withdrawn from sale at any time. Online Fixed Price

More information