TIE2140 / IE2140e Engineering Economy Tutorial 6 (Lab 2) Engineering-Economic Decision Making Process using EXCEL

Size: px
Start display at page:

Download "TIE2140 / IE2140e Engineering Economy Tutorial 6 (Lab 2) Engineering-Economic Decision Making Process using EXCEL"

Transcription

1 TIE2140 / IE2140e Engineering Economy Tutorial 6 (Lab 2) Engineering-Economic Decision Making Process using EXCEL Solutions Guide by Wang Xin, Hong Lanqing & Mei Wenjie 1. Learning Objectives In this lab-based tutorial, you will learn how to: 1. Develop a basic deterministic financial after-tax cash flow model using Excel 2. Perform One-Way Range Sensitivity Analysis using Sensit (Tornado and Spider Diagrams) 3. Perform Break-Even Analysis using Rainbow Diagrams (and Goal Seek) 4. Perform Probabilistic Risk Analysis using Monte Carlo Simulation 5. Interpret Risk Profile and determine risk measures. 2. Problem Description A company plans to invest in a flexible manufacturing system (FMS) to mass produce a new product for the market. The relevant information including base estimates for production quantity, price, fixed & variable costs, direct & indirect costs, etc are given in the table below: Variables Base Value 1 Number of pieces produced/year 550,000 2 Selling Price $ Variable labor cost/part $ Variable material cost/part $ Annual overhead $ 2,250,000 6 Annual tooling costs $ 450,000 7 Annual inventory costs $ 150,000 8 Investment Cost $ 7,500,000 9 Useful system life 10 years 10 Salvage value $ 500, Depreciation scheme 3-Year Capital Allowance 12 Corporate tax rate 17% 13 MARR 15% The company is not sure what to do, and you have been engaged as a consultant to help and advice the company on the feasibility and risk of investing in this project. soln-tut6-lab-2-1

2 3. Hand-on Exercises and Solutions 3.1 Base Model Development & Analysis a. Using Excel, perform ATCF analysis to determine the After-Tax PW for the proposed investment based on the base estimates and a study period of 10 years. You may use the Excel template provided. b. Is the project economically feasible based on the base estimates? First, open the ie tut-06-lab2-templates and go to the Base Model sheet. The uncertain variables, fixed parameters and their base values are already inputted in the Excel sheet. Then, conduct the After-Tax Cash Flow Analysis. First, input the investment cost of Year 0, which equals to B12, the investment cost. Then we move on to the first year: Annual revenue = number of pieces produced/year selling price, i.e., -$B$5*$B$6, here, we press F4 to fix the values. Labor cost = number of pieces produced/year variable labor cost/part, i.e., -$B$5*$B$7. Material cost = number of pieces produced/year variable material cost/part, i.e., -$B$5*$B$8. Overheads = - annual overheads, i.e., -$B$9. Tooling cost = - annual tooling costs, i.e., -$B$10. Inventory cost = - annual inventory costs, i.e., -$B$11. After input all the related values of Year 1, we select all of them, put the mouse on the lower right corner where there is a + sign, and then drag to the right side and obtain values from Year 2 to Year 10. Investment Cost of Year 0, -B12 drag to the right side Then we input the investment cost of Year 10, B13. Investment Cost of Year 10, B13 Then we move to the depreciation. In this project, the 3-year CA is used, so the depreciation is investment cost divided by 3, i.e., $B$12/3. After inputting all the related values, we go to FORMULAS Calculate now, all other numbers are updated accordingly. soln-tut6-lab-2-2

3 Or you could click Calculate Options Automatic, then next time Excel would update the calculation automatically. In the after tax cash flow (ATCF), we could see that there are two cash flow in Year 10, so we need to add them up to be the total cash flow in Year 10, L42 + M42. Then we use the NPV function to calculate the after-tax PW, where After-tax PW = Year 0 cash flow + NPV (after tax MARR, cash flow from Year 1 to Year 10) Then, we get the after-tax PW = $716, Since the after-tax PW is greater than zero, the project is feasible. We can also obtain after-tax IRR of the project using IRR function. As the IRR function does not allow separate entries of cash flows, we need to develop a compacted ATCF array that has a single cash flow in Year 10 equal to L42+M42. The After-Tax IRR can be obtained using IRR function, which is 17.60%. The project is feasible as it is larger than MARR. soln-tut6-lab-2-3

4 3.2 One-Way Range Sensitivity Analysis The management is not very comfortable with the results as the company does not have any previous experience in operating an FMS, and there are uncertainties in the many of the variables base values. It is proposed that sensitivity analyses be performed on the base model to raise the company s confidence. Expert s estimates of the possible range of values for each of the uncertain input variables are given in the table below: Uncertain Variables Low Value Base Value High Value 1 Number of pieces produced/year 500, , ,000 2 Selling Price $ $ $ Variable labor cost/part $ 2.10 $ 2.20 $ Variable material cost/part $ 1.25 $ 1.50 $ Annual overhead $ 2,000,000 $ 2,250,000 $ 2,500,000 6 Annual tooling costs $ 425,000 $ 450,000 $ 475,000 7 Annual inventory costs $ 130,000 $ 150,000 $ 170,000 8 Investment Cost $ 7,400,000 $ 7,500,000 $ 7,600,000 9 Salvage value $ 475,000 $ 500,000 $ 525,000 a. Perform one-way range sensitivity analysis by generating Tornado and Spider Diagrams using the Sensit software. Interpret the results. b. Which are the sensitive variables? c. Which are the insensitive variables? In the second part, instead of having just one base value, each variable now has its low value and high value. To perform one-way range sensitivity analysis, we need to add in macros. We go back to the folder of templets, double click the Sensit-XXX-Trial-Addin-XXXX, and add the macro into Excel. Then we could find ADD-INS in the menu bar. soln-tut6-lab-2-4

5 To conduct the sensitivity analysis, we move to the Sensitivity Model. Here we can also find the correct answer of the first question. First, we click the Senslt Trial Tornado-Spider option, and click OK. Here, to input the input variables, we click the drop-down list, and select all the names of uncertain variables, $A$5 to $A$13. click soln-tut6-lab-2-5

6 Then, click the right side and back to the main menu. click to go back By the same procedure, we input the value of the input variables, $B$5 to $B$13. In the right side, One Extreme is the low value, so we select $D$5 to $D$13. The Base Case is the middle column, $E$5 to $E$13, and Other Extreme is all the high values, $F$5 to $F$13. As for the Cells for Output Variable, it is the After-Tax PW, $A$45, whose value is $B$45. After select all the related variables, we click both the Tornado Chart and Spider Chart, then click on OK. After running the macros, we obtain the Tornado Chart and Spider Chart. In the Tornado Chart, it has a summary table of all the relevant information. soln-tut6-lab-2-6

7 For each of the variables, we have the low, base and high values. Excel calculates the corresponding PW, and then draws the Tornado Chart. It is shown that the Selling Price is the most sensitive, we define the first five variables as the sensitive variables. The Salvage value is the least sensitive. soln-tut6-lab-2-7

8 The Spider PW output file contains a summary table and the spider diagram. All variables were sorted in descending order of sensitivity. As shown in the table and figure, the Selling Price is the most sensitive. We define the first five variables as the sensitive variables. The Salvage value is the least sensitive. 3.3 Break-Even Analysis a. Plot a Rainbow Diagram to determine the break-even the number of pieces produced and sold for the project to be feasible. What is the break-even value? How will the change in the production will affect our decision? b. Plot a Rainbow Diagram to determine the break-even the price of product for the project to be feasible. What is the break-even value? Now we go back to the sensitivity model, and click the Sensit Trial One-Input Plot. In case a, the only variable that is changing is the number of pieces produced/year, so we input the corresponding label $A$5 and value $B$5. For the range of the input value, the Start is the lower bound, which is 500,000. The Stop is the upper bound, $600,000. The maximum step (number of calculation point) in Excel is 32,000. In each point, Excel calculates the corresponding After-Tax PW. soln-tut6-lab-2-8

9 the number of pieces produced/year After-Tax PW After click OK, we obtain the rainbow diagram. To find the break-even point which PW = 0, we choose DESIGN Add Chart Element Gridlines to add Gridlines to add major and minor gridline into the diagram. soln-tut6-lab-2-9

10 We can see that the break-even point is about $530,000. In case b, we perform the rainbow diagram to determine the break-even the price of product for the project to be feasible. The procedure is the same as case a. We get the rainbow diagram as below, and the breakeven point is about $ The exact break-even values of the number of pieces produced and the price of product are 529,264 and 11.69, which can be obtained using the Goal Seek function. soln-tut6-lab-2-10

11 soln-tut6-lab-2-11

12 3.4 Probabilistic Risk Analysis using Monte Carlo Simulation a. Risk Profile Generation: For each of the sensitive variables identified in the previous step, access their respective probability distribution, and perform Monte Carlo simulations on them (while keeping the non-sensitive variables at their base values) to generate the risk profile for the project s after-tax PW. Hint: You may assume the followings distributions if needed: Variable Distribution Parameters 1 Number of pieces produced/year Uniform Integer (500,000, 600,000) 2 Selling Price Normal (Truncated) µ = $12.00 σ = $ Variable labor cost/part Normal (Truncated) µ = $2.20 σ = $ Variable material cost/part Normal (Truncated) µ = $1.50 σ = $ Annual overhead Uniform ($2,000,000, $2,500,000) You may assume that although the above variables are currently uncertain, each of them has the same value over the 10 years study period. b. Risk Profile: What are the mean and standard deviation of the After-tax PW of the project? c. Downside Risk: What is the probability that the project will be economically infeasible based on aftertax PW? d. Upside Potentials: i. What is the probability that project will achieve after-tax PW $3 million? ii. What is the probability that project will achieve after-tax PW $4 million? e. Project Value-at-Risk: Value-at-Risk (VaR) is a popular measure for investment risk. It indicates the maximum loss an investment may incur at a certain level of confidence (e.g. 90%, 95%). i. What is the project s present-value-at-risk at 90% confidence? ii. What is the project s present-value-at-risk at 95% confidence? Optional Homework f. Perform Monte Carlo Simulation using After-Tax IRR as the output measure and interpret the risk profile generated. In this question, we move to the Probabilistic Model. The distribution of variables are already inputted in the Excel sheet. We will to do the probabilistic analysis. Simply in your computer. Double click the icon. Click Close when you see the following dialog. soln-tut6-lab-2-12

13 is successfully loaded, you will in the menu bar. In the probabilistic analysis, each uncertain variable has a distribution. So we need to use Excel to generate random numbers for each variable according to its distribution. To define a uniform integer distribution for the number of pieces produced per year, we first click cell B5. Then click Define Distributions. The uniform integer function can be found in the Discrete group of functions. Click IntUniform and click Select Distribution. soln-tut6-lab-2-13

14 We then input parameter references by clicking the small data icon shown below. Min and Max should contain cell I5 and J5, respectively. Then click the icon in the upper right corner to go back and then click Ok. soln-tut6-lab-2-14

15 Most of distributions can be input in a similar way while the truncated normal distribution requires more effort. To define a truncated normal distribution for the selling price, we first find a normal distribution and then specify limits. Click B6. Go to Define Distributions. Find normal distribution under Common or Continuous and then click Select Distribution. Click small arrow next to Parameter and select Truncation Limits and Values. Click OK. soln-tut6-lab-2-15

16 Besides mu and sigma, you will see there are two more entries (Trunc. Min and Trunc.Max) to specify. Again, click the icon at the bottom right corner. soln-tut6-lab-2-16

17 Mu, Sigma, Trunc.Min, Trunc.Max should correspond to cell I6, J6, K6, and L6, respectively. Then click the icon in the upper right corner to go back and then click OK. Distributions for variable labor cost and material cost per part can be defined similarly as selling price. Or you can click cell B6, move mouse to the bottom right corner until a cross sign appears. Then drag all the way down to cell B8. In this way, you copy the formula in B6 to B7 and B8. The uniform distribution for the annual overhead is defined as below. soln-tut6-lab-2-17

18 Note that we have provided formula for all variables so that you can check whether your input is correct or not. As we would like to see the risk profile for the project s after-tax PW, we next add After-Tax PW as the output. Click cell B45, click Add Output in the menu, and click OK. soln-tut6-lab-2-18

19 Note that you can add After-Tax IRR as the output simultaneously to see its risk profile. Before running the simulation, it is highly suggested checking model inputs and outputs carefully. You can do this by clicking Model Window. As can be seen, there are five inputs corresponding to five random variables and two outputs of interest. soln-tut6-lab-2-19

20 Then click Start Simulation to run the simulation. Simulation results will be shown in a separate window and you can always view the results by clicking Browse Results in the menu. The expected value and standard deviation of the After-tax PW of the project are $716, and $2,340, soln-tut6-lab-2-20

21 Downside Risk: The probability that the project will be economically infeasible based on after-tax PW is about 39.2%. soln-tut6-lab-2-21

22 Upside Potentials: The probability that project will achieve after-tax PW $3 million is 17.3%. The probability that project will achieve after-tax PW $4 million is 8.7%. soln-tut6-lab-2-22

23 Project Value-at-Risk: The project s equivalent present value-at-risk at 90% confidence is million dollars. The project s equivalent present value-at-risk at 95% confidence is million dollars. soln-tut6-lab-2-23

24 To generate excel report, you can click Excel Reports in the menu bar or the icon at bottom left of the result window. soln-tut6-lab-2-24

IE2140 Engineering Economy Tutorial 3 (Lab 1) Using Excel Financial Functions for Project Evaluation

IE2140 Engineering Economy Tutorial 3 (Lab 1) Using Excel Financial Functions for Project Evaluation IE2140 Engineering Economy Tutorial 3 (Lab 1) Using Excel Financial Functions for Project Evaluation 1. Objectives and Overview Solutions Guide by Hong Lanqing, Wang Xin and Mei Wenjie The objective of

More information

Acritical aspect of any capital budgeting decision. Using Excel to Perform Monte Carlo Simulations TECHNOLOGY

Acritical aspect of any capital budgeting decision. Using Excel to Perform Monte Carlo Simulations TECHNOLOGY Using Excel to Perform Monte Carlo Simulations By Thomas E. McKee, CMA, CPA, and Linda J.B. McKee, CPA Acritical aspect of any capital budgeting decision is evaluating the risk surrounding key variables

More information

ExcelSim 2003 Documentation

ExcelSim 2003 Documentation ExcelSim 2003 Documentation Note: The ExcelSim 2003 add-in program is copyright 2001-2003 by Timothy R. Mayes, Ph.D. It is free to use, but it is meant for educational use only. If you wish to perform

More information

Simulation. Decision Models

Simulation. Decision Models Lecture 9 Decision Models Decision Models: Lecture 9 2 Simulation What is Monte Carlo simulation? A model that mimics the behavior of a (stochastic) system Mathematically described the system using a set

More information

Monte Carlo Simulation (General Simulation Models)

Monte Carlo Simulation (General Simulation Models) Monte Carlo Simulation (General Simulation Models) Revised: 10/11/2017 Summary... 1 Example #1... 1 Example #2... 10 Summary Monte Carlo simulation is used to estimate the distribution of variables when

More information

INTRODUCING RISK MODELING IN CORPORATE FINANCE

INTRODUCING RISK MODELING IN CORPORATE FINANCE INTRODUCING RISK MODELING IN CORPORATE FINANCE Domingo Castelo Joaquin*, Han Bin Kang** Abstract This paper aims to introduce a simulation modeling in the context of a simplified capital budgeting problem.

More information

DECISION SUPPORT Risk handout. Simulating Spreadsheet models

DECISION SUPPORT Risk handout. Simulating Spreadsheet models DECISION SUPPORT MODELS @ Risk handout Simulating Spreadsheet models using @RISK 1. Step 1 1.1. Open Excel and @RISK enabling any macros if prompted 1.2. There are four on-line help options available.

More information

What's new in Invest for Excel 3.6

What's new in Invest for Excel 3.6 What's new in Invest for Excel 3.6 Microsoft Excel versions supported... 2 Russian user manual... 2 Digitally signed program code... 2 Template folders... 2 Goodwill depreciation tax-deductibility option...

More information

Descriptive Statistics

Descriptive Statistics Chapter 3 Descriptive Statistics Chapter 2 presented graphical techniques for organizing and displaying data. Even though such graphical techniques allow the researcher to make some general observations

More information

LAB 2 INSTRUCTIONS PROBABILITY DISTRIBUTIONS IN EXCEL

LAB 2 INSTRUCTIONS PROBABILITY DISTRIBUTIONS IN EXCEL LAB 2 INSTRUCTIONS PROBABILITY DISTRIBUTIONS IN EXCEL There is a wide range of probability distributions (both discrete and continuous) available in Excel. They can be accessed through the Insert Function

More information

GL Budgets. Account Budget and Forecast. Account Budgets and Forecasts Menu

GL Budgets. Account Budget and Forecast. Account Budgets and Forecasts Menu Account Budget and Forecast The Account Budget and Forecast function allows you to enter and maintain an unlimited number of budgets and/or forecasts values and types. When setting up the account budgets

More information

Getting started with WinBUGS

Getting started with WinBUGS 1 Getting started with WinBUGS James B. Elsner and Thomas H. Jagger Department of Geography, Florida State University Some material for this tutorial was taken from http://www.unt.edu/rss/class/rich/5840/session1.doc

More information

Investit Software Inc. INVESTMENT ANALYSIS MONTHLY EXAMPLE WITH REVENUE & EXPENSES PROJECTIONS

Investit Software Inc.   INVESTMENT ANALYSIS MONTHLY EXAMPLE WITH REVENUE & EXPENSES PROJECTIONS INVESTMENT ANALYSIS MONTHLY EXAMPLE WITH REVENUE & EXPENSES PROJECTIONS Canadian Example Including application of Incremental Cash Flow Analysis INTRODUCTION This is an investment analysis example where

More information

Investit Software Inc. INVESTMENT ANALYSIS YEARLY EXAMPLE WITH EXPENSES ONLY COMPARISON Canadian Example

Investit Software Inc.   INVESTMENT ANALYSIS YEARLY EXAMPLE WITH EXPENSES ONLY COMPARISON Canadian Example INVESTMENT ANALYSIS YEARLY EXAMPLE WITH EXPENSES ONLY COMPARISON Canadian Example INTRODUCTION This example shows how to compare two investments that; 1. Involves an investment in equipment 2. Incurs operating

More information

Confidence Intervals for the Difference Between Two Means with Tolerance Probability

Confidence Intervals for the Difference Between Two Means with Tolerance Probability Chapter 47 Confidence Intervals for the Difference Between Two Means with Tolerance Probability Introduction This procedure calculates the sample size necessary to achieve a specified distance from the

More information

Value of Information in Spreadsheet Monte Carlo Simulation Models

Value of Information in Spreadsheet Monte Carlo Simulation Models Value of Information in Spreadsheet Monte Carlo Simulation Models INFORMS 010 Austin Michael R. Middleton, Ph.D. Decision Toolworks Mike@DecisionToolworks.com 15.10.7190 Background Spreadsheet models are

More information

GETTING STARTED. To OPEN MINITAB: Click Start>Programs>Minitab14>Minitab14 or Click Minitab 14 on your Desktop

GETTING STARTED. To OPEN MINITAB: Click Start>Programs>Minitab14>Minitab14 or Click Minitab 14 on your Desktop Minitab 14 1 GETTING STARTED To OPEN MINITAB: Click Start>Programs>Minitab14>Minitab14 or Click Minitab 14 on your Desktop The Minitab session will come up like this 2 To SAVE FILE 1. Click File>Save Project

More information

You should already have a worksheet with the Basic Plus Plan details in it as well as another plan you have chosen from ehealthinsurance.com.

You should already have a worksheet with the Basic Plus Plan details in it as well as another plan you have chosen from ehealthinsurance.com. In earlier technology assignments, you identified several details of a health plan and created a table of total cost. In this technology assignment, you ll create a worksheet which calculates the total

More information

Form 162. Form 194. Form 239

Form 162. Form 194. Form 239 Below is a list of topics that we receive calls about each year with the solutions to them detailed. New features and funds have also been added. Note: Some of the topics have more than one question so

More information

Importing Fundamental Data

Importing Fundamental Data Chapter V Importing Fundamental Data Includes Clearing Fundamental Data In this chapter 1. Retrieve fundamental data from a data service 726 2. Import Telescan/ProSearch Scan File (for Telescan users)

More information

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

Full Monte. Looking at your project through rose-colored glasses? Let s get real. Realistic plans for project success. Looking at your project through rose-colored glasses? Let s get real. Full Monte Cost and schedule risk analysis add-in for Microsoft Project that graphically displays

More information

Notes for CHEE 332 Report

Notes for CHEE 332 Report Notes for CHEE 332 Report - binary VLE data should be from a reputable source (ex. not from somerandomwebsite.com) and if you are using Perry's Handbook then recognize that the data is not originally from

More information

Central Budget Entry Munis - Financials: Central Budget Entry

Central Budget Entry Munis - Financials: Central Budget Entry MU-FN-8-F, MU-FN-14-C Central Budget Entry Munis - Financials: Central Budget Entry CLASS DESCRIPTION This class will provide an overview of the Central Budget Entry program that is new to Munis version

More information

Workshop 1. Descriptive Statistics, Distributions, Sampling and Monte Carlo Simulation. Part I: The Firestone Case 1

Workshop 1. Descriptive Statistics, Distributions, Sampling and Monte Carlo Simulation. Part I: The Firestone Case 1 Sami Najafi Asadolahi Statistics for Managers Workshop 1 Descriptive Statistics, Distributions, Sampling and Monte Carlo Simulation The purpose of the workshops is to give you hands-on experience with

More information

Lecture 10. Ski Jacket Case Profit calculation Spreadsheet simulation Analysis of results Summary and Preparation for next class

Lecture 10. Ski Jacket Case Profit calculation Spreadsheet simulation Analysis of results Summary and Preparation for next class Decision Models Lecture 10 1 Lecture 10 Ski Jacket Case Profit calculation Spreadsheet simulation Analysis of results Summary and Preparation for next class Yield Management Decision Models Lecture 10

More information

Learning The Expert Allocator by Investment Technologies

Learning The Expert Allocator by Investment Technologies Learning The Expert Allocator by Investment Technologies Telephone 212/724-7535 Fax 212/208-4384 228 West 71st Street, Suite Support 7I, New Telephone York, NY 203703 203/364-9915 Fax 203/547-6164 Technical

More information

Real Options Valuation, Inc. Software Technical Support

Real Options Valuation, Inc. Software Technical Support Real Options Valuation, Inc. Software Technical Support HELPFUL TIPS AND TECHNIQUES Johnathan Mun, Ph.D., MBA, MS, CFC, CRM, FRM, MIFC 1 P a g e Helpful Tips and Techniques The following are some quick

More information

Decision Trees Using TreePlan

Decision Trees Using TreePlan Decision Trees Using TreePlan 6 6. TREEPLAN OVERVIEW TreePlan is a decision tree add-in for Microsoft Excel 7 & & & 6 (Windows) and Microsoft Excel & 6 (Macintosh). TreePlan helps you build a decision

More information

Discrete Probability Distributions

Discrete Probability Distributions 5 Discrete Probability Distributions 5-3 Binomial Probability Distributions 5-5 Poisson Probability Distributions 52 Chapter 5: Discrete Probability Distributions 5-3 Binomial Probability Distributions

More information

HandDA program instructions

HandDA program instructions HandDA program instructions All materials referenced in these instructions can be downloaded from: http://www.umass.edu/resec/faculty/murphy/handda/handda.html Background The HandDA program is another

More information

IE5203 Decision Analysis Case Study 1: Exxoff New Product Research & Development Problem Solutions Guide using DPL9

IE5203 Decision Analysis Case Study 1: Exxoff New Product Research & Development Problem Solutions Guide using DPL9 IE5203 Decision Analysis Case Study 1: Exxoff New Product Research & Development Problem Solutions Guide using DPL9 Luo Chunling Jiang Weiwei Teaching Assistants 1. Creating Value models Create value node:

More information

FxCraft Trade Manager User Manual (version 1_01)

FxCraft Trade Manager User Manual (version 1_01) FxCraft Trade Manager User Manual (version 1_01) 1 Table of contents FxCraft Trade Manager... 1 User Manual... 1 Introduction... 3 Short description of the product... 4 Installation... 5 Main Window...

More information

Introduction to Basic Excel Functions and Formulae Note: Basic Functions Note: Function Key(s)/Input Description 1. Sum 2. Product

Introduction to Basic Excel Functions and Formulae Note: Basic Functions Note: Function Key(s)/Input Description 1. Sum 2. Product Introduction to Basic Excel Functions and Formulae Excel has some very useful functions that you can use when working with formulae. This worksheet has been designed using Excel 2010 however the basic

More information

Creating and Assigning Targets

Creating and Assigning Targets Creating and Assigning Targets Targets are a powerful reporting tool in PortfolioCenter that allow you to mix index returns for several indexes, based on the portfolio s asset class allocation. For example,

More information

Yield Management. Decision Models

Yield Management. Decision Models Decision Models: Lecture 10 2 Decision Models Yield Management Yield management is the process of allocating different types of capacity to different customers at different prices in order to maximize

More information

DazStat. Introduction. Installation. DazStat is an Excel add-in for Excel 2003 and Excel 2007.

DazStat. Introduction. Installation. DazStat is an Excel add-in for Excel 2003 and Excel 2007. DazStat Introduction DazStat is an Excel add-in for Excel 2003 and Excel 2007. DazStat is one of a series of Daz add-ins that are planned to provide increasingly sophisticated analytical functions particularly

More information

7. Portfolio Simulation and Pick of the Day

7. Portfolio Simulation and Pick of the Day 7. Portfolio Simulation and Pick of the Day Overview Two special functions are incorporated into the AIQ Portfolio Manager for users who base their trading selections on Expert Design Studio (EDS) analysis.

More information

Insurance Tracking with Advisors Assistant

Insurance Tracking with Advisors Assistant Insurance Tracking with Advisors Assistant Client Marketing Systems, Inc. 880 Price Street Pismo Beach, CA 93449 800 643-4488 805 773-7985 fax www.advisorsassistant.com support@climark.com 2015 Client

More information

ESD.70J Engineering Economy

ESD.70J Engineering Economy ESD.70J Engineering Economy Fall 2010 Session One Xin Zhang xinzhang@mit.edu Prof. Richard de Neufville ardent@mit.edu http://ardent.mit.edu/real_options/rocse_excel_latest/excel_class.html ESD.70J Engineering

More information

Decision Trees: Booths

Decision Trees: Booths DECISION ANALYSIS Decision Trees: Booths Terri Donovan recorded: January, 2010 Hi. Tony has given you a challenge of setting up a spreadsheet, so you can really understand whether it s wiser to play in

More information

FMS View Expense Budget Information

FMS View Expense Budget Information FMS View Expense Budget Information Budget Information Queries To view your operating expense budget (Fund 110) in the Financial Management System (FMS), you create a budget query with specific criteria;

More information

Form 155. Form 162. Form 194. Form 239

Form 155. Form 162. Form 194. Form 239 Below is a list of topics that we receive calls about each year with the solutions to them detailed. New features and funds have also been added. Note: Some of the topics have more than one question so

More information

Two-Sample Z-Tests Assuming Equal Variance

Two-Sample Z-Tests Assuming Equal Variance Chapter 426 Two-Sample Z-Tests Assuming Equal Variance Introduction This procedure provides sample size and power calculations for one- or two-sided two-sample z-tests when the variances of the two groups

More information

Lesson Plan for Simulation with Spreadsheets (8/31/11 & 9/7/11)

Lesson Plan for Simulation with Spreadsheets (8/31/11 & 9/7/11) Jeremy Tejada ISE 441 - Introduction to Simulation Learning Outcomes: Lesson Plan for Simulation with Spreadsheets (8/31/11 & 9/7/11) 1. Students will be able to list and define the different components

More information

PSCM_ Data Analytics

PSCM_ Data Analytics PSCM_7217.1.1 Data Analytics Excel Functions and Simulation Sang Jo Kim July 4, 2015 * Reference - Business Analytics: Methods, Models, and Decisions (1 st edition, James R. Evans, Pearson) Contents Excel

More information

Personal Finance Amortization Table. Name: Period:

Personal Finance Amortization Table. Name: Period: Personal Finance Amortization Table Name: Period: Ch 8 Project using Excel In this project you will complete a loan amortization table (payment schedule) for the purchase of a home with a $235,500 loan

More information

5.- RISK ANALYSIS. Business Plan

5.- RISK ANALYSIS. Business Plan 5.- RISK ANALYSIS The Risk Analysis module is an educational tool for management that allows the user to identify, analyze and quantify the risks involved in a business project on a specific industry basis

More information

Data Sheet for Trendline Trader Pro

Data Sheet for Trendline Trader Pro Data Sheet for Trendline Trader Pro Introduction Trendline Trader Pro is a hybrid software application which used a JavaFX based interface to communicate with an underlying MetaTrader MT4 Expert Advisor.

More information

User Guide to the Budget Process

User Guide to the Budget Process User Guide to the Budget Process 2/22/2018 Contents 1. Adaptive Insights... 2 2. Browsers... 2 3. Nomenclature... 2 4. User Security - Roles and Levels... 2 5. Logging into Adaptive Insights... 3 6. Budget

More information

Uncertainty in Economic Analysis

Uncertainty in Economic Analysis Risk and Uncertainty Uncertainty in Economic Analysis CE 215 28, Richard J. Nielsen We ve already mentioned that interest rates reflect the risk involved in an investment. Risk and uncertainty can affect

More information

Maintaining Budget Change Requests

Maintaining Budget Change Requests Maintaining Budget Change Requests This document describes the functions used in TEAMS to enter and approve requests to move funds from one General Ledger account to another. In this document: Request

More information

Two-Sample T-Tests using Effect Size

Two-Sample T-Tests using Effect Size Chapter 419 Two-Sample T-Tests using Effect Size Introduction This procedure provides sample size and power calculations for one- or two-sided two-sample t-tests when the effect size is specified rather

More information

Tests for Two ROC Curves

Tests for Two ROC Curves Chapter 65 Tests for Two ROC Curves Introduction Receiver operating characteristic (ROC) curves are used to summarize the accuracy of diagnostic tests. The technique is used when a criterion variable is

More information

Real-time Strategy Scanner User Guide

Real-time Strategy Scanner User Guide Real-time Strategy Scanner User Guide Real-time Strategy Scanner service is a professional tool for scanning equity option universe for profit opportunities. It covers the most popular strategies, from

More information

Importing Historical Returns into Morningstar Office

Importing Historical Returns into Morningstar Office Importing Historical Returns into Morningstar Office Overview - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1 What are historical returns? - - - - - - - - - - - - - - - -

More information

Using the Clients & Portfolios Module in Advisor Workstation

Using the Clients & Portfolios Module in Advisor Workstation Using the Clients & Portfolios Module in Advisor Workstation Disclaimer - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1 Overview - - - - - - - - - - - - - - - - - - - - - -

More information

Non-Inferiority Tests for the Ratio of Two Means

Non-Inferiority Tests for the Ratio of Two Means Chapter 455 Non-Inferiority Tests for the Ratio of Two Means Introduction This procedure calculates power and sample size for non-inferiority t-tests from a parallel-groups design in which the logarithm

More information

Pertmaster - Risk Register Module

Pertmaster - Risk Register Module Pertmaster - Risk Register Module 1 Pertmaster - Risk Register Module Pertmaster Risk Register Module This document is an extract from the Pertmaster help file version h2.62. Pertmaster - Risk Register

More information

How to Use Fundamental Data in TradingExpert Pro

How to Use Fundamental Data in TradingExpert Pro Chapter VII How to Use Fundamental Data in TradingExpert Pro In this chapter 1. Viewing fundamental data on the Fundamental Report 752 2. Viewing fundamental data for individual stocks 755 3. Building

More information

Principia Research Mode Online Basics Training Manual

Principia Research Mode Online Basics Training Manual Principia Research Mode Online Basics Training Manual Welcome to Principia Research Mode Basics Course, designed to give you an overview of Principia's Research Mode capabilities. The goal of this guide

More information

3. Entering transactions

3. Entering transactions 3. Entering transactions Overview of Transactions functions When you place an order to buy or short sell, you should immediately enter the transaction into the appropriate portfolio account so that the

More information

SENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL. Petter Gokstad 1

SENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL. Petter Gokstad 1 SENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL Petter Gokstad 1 Graduate Assistant, Department of Finance, University of North Dakota Box 7096 Grand Forks, ND 58202-7096, USA Nancy Beneda

More information

University of Texas at Dallas School of Management. Investment Management Spring Estimation of Systematic and Factor Risks (Due April 1)

University of Texas at Dallas School of Management. Investment Management Spring Estimation of Systematic and Factor Risks (Due April 1) University of Texas at Dallas School of Management Finance 6310 Professor Day Investment Management Spring 2008 Estimation of Systematic and Factor Risks (Due April 1) This assignment requires you to perform

More information

USERGUIDE MT4+ MINI TERMINAL

USERGUIDE MT4+ MINI TERMINAL TABLE OF CONTENTS. INSTALLATION OF PAGE 03. INTRODUCTION TO PAGE 06 3. PLACING BUY/SELL ORDERS PAGE 08 4. PLACING PENDING ORDERS PAGE 5. OCO ORDERS PAGE 3 6. ORDER TEMPLATES PAGE 4 7. SETTINGS PAGE 5 8.

More information

<Partner Name> <Partner Product> RSA ARCHER GRC Platform Implementation Guide. 6.3

<Partner Name> <Partner Product> RSA ARCHER GRC Platform Implementation Guide. 6.3 RSA ARCHER GRC Platform Implementation Guide Palisade Jeffrey Carlson, RSA Partner Engineering Last Modified: 12/21/2016 Solution Summary Palisade @RISK is risk and decision

More information

Group-Sequential Tests for Two Proportions

Group-Sequential Tests for Two Proportions Chapter 220 Group-Sequential Tests for Two Proportions Introduction Clinical trials are longitudinal. They accumulate data sequentially through time. The participants cannot be enrolled and randomized

More information

Confidence Intervals for Paired Means with Tolerance Probability

Confidence Intervals for Paired Means with Tolerance Probability Chapter 497 Confidence Intervals for Paired Means with Tolerance Probability Introduction This routine calculates the sample size necessary to achieve a specified distance from the paired sample mean difference

More information

Tests for Two Variances

Tests for Two Variances Chapter 655 Tests for Two Variances Introduction Occasionally, researchers are interested in comparing the variances (or standard deviations) of two groups rather than their means. This module calculates

More information

Introduction to RELCOST. Carolyn Roos, Ph.D. Northwest CHP Technical Assistance Partnerships Washington State University Energy Program

Introduction to RELCOST. Carolyn Roos, Ph.D. Northwest CHP Technical Assistance Partnerships Washington State University Energy Program Introduction to RELCOST Carolyn Roos, Ph.D. Northwest CHP Technical Assistance Partnerships Washington State University Energy Program 1 Overview of RELCOST Presentation Outline Program use Results A review

More information

Tidemark Budget Data Entry Payroll Budget (2017)

Tidemark Budget Data Entry Payroll Budget (2017) Budget (2017) This document contains information for entering proposed budget amounts into the Tidemark software for Payroll. 1 Tidemark Accessing Budget Tidemark Data Entry Payroll Overview / Tidemark

More information

A Brief Guide to Engineering Management Financial Calculations in ENGM 401 Section B1 Winter 2009

A Brief Guide to Engineering Management Financial Calculations in ENGM 401 Section B1 Winter 2009 A Brief Guide to Engineering Management Financial Calculations in ENGM 401 Section B1 Winter 2009 MG Lipsett 2008 last updated December 8, 2008 Introduction This document provides concise explanations

More information

World Bank Group - LED Streetlight Financing Tool: User s Manual

World Bank Group - LED Streetlight Financing Tool: User s Manual World Bank Group - LED Streetlight Financing Tool: User s Manual The World Bank Group developed the CityLED Streetlight Financing Tool to allow cities to evaluate the financial implications, as well as

More information

BUDGET IMPORT TEMPLATE

BUDGET IMPORT TEMPLATE BUDGET IMPORT TEMPLATE This video will explain and show how to import budget journals in PeopleSoft using the Excel template. Importing will allow you to easily and quickly create budget transfers and

More information

As a function of the stock price on the exercise date, what do the payoffs look like for European calls and puts?

As a function of the stock price on the exercise date, what do the payoffs look like for European calls and puts? Pricing stock options This article was adapted from Microsoft Office Excel 2007 Data Analysis and Business Modeling by Wayne L. Winston. Visit Microsoft Learning to learn more about this book. This classroom-style

More information

Learning TradeStation. Order-Entry Tools and Preferences

Learning TradeStation. Order-Entry Tools and Preferences Learning TradeStation Order-Entry Tools and Preferences Important Information No offer or solicitation to buy or sell securities, securities derivative or futures products of any kind, or any type of trading

More information

Multi-stage Interventions to Promote Persistent Plug-load Energy Savings in Office Buildings

Multi-stage Interventions to Promote Persistent Plug-load Energy Savings in Office Buildings Multi-stage Interventions to Promote Persistent Plug-load Energy Savings in Office Buildings Shuoqi Wang, Ph.D. Dept. of Civil & Environmental Engineering, University of Washington, Seattle WA Amy A. Kim,

More information

Creating a Standard AssetMatch Proposal in Advisor Workstation 2.0

Creating a Standard AssetMatch Proposal in Advisor Workstation 2.0 Creating a Standard AssetMatch Proposal in Advisor Workstation 2.0 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1 What you will learn - - - - - - - - - - - - - - - - - -

More information

ENGINEERING ECONOMY. William G. Sullivan. Fourteenth Edition. Prentice Hall. Virginia Polytechnic institute and State University

ENGINEERING ECONOMY. William G. Sullivan. Fourteenth Edition. Prentice Hall. Virginia Polytechnic institute and State University ENGINEERING ECONOMY Fourteenth Edition William G. Sullivan Virginia Polytechnic Institute and State University, Emeritus Elin M. Wicks Wicks and Associates C. Patrick Koelling Virginia Polytechnic institute

More information

R & R Study. Chapter 254. Introduction. Data Structure

R & R Study. Chapter 254. Introduction. Data Structure Chapter 54 Introduction A repeatability and reproducibility (R & R) study (sometimes called a gauge study) is conducted to determine if a particular measurement procedure is adequate. If the measurement

More information

PI Reports by Month Range Manual Office of Sponsored Programs Training

PI Reports by Month Range Manual Office of Sponsored Programs Training PI Reports by Month Range Manual Office of Sponsored Programs Training 013 Table of Content Table of Contents Access PI Report by Month Range... PI Report by Month Range Initial View & Summary by Fund

More information

MT4 Supreme Edition Trade Terminal

MT4 Supreme Edition Trade Terminal MT4 Supreme Edition Trade Terminal In this manual, you will find installation and usage instructions for MT4 Supreme Edition. Installation process and usage is the same in new MT5 Supreme Edition. Simply

More information

In this chapter: Budgets and Planning Tools. Configure a budget. Report on budget versus actual figures. Export budgets.

In this chapter: Budgets and Planning Tools. Configure a budget. Report on budget versus actual figures. Export budgets. Budgets and Planning Tools In this chapter: Configure a budget Report on budget versus actual figures Export budgets Project cash flow Chapter 23 479 Tuesday, September 18, 2007 4:38:14 PM 480 P A R T

More information

Policy. Chapter 6. Accessing the Policy. Nexsure Training Manual - CRM. In This Chapter

Policy. Chapter 6. Accessing the Policy. Nexsure Training Manual - CRM. In This Chapter Nexsure Training Manual - CRM Policy In This Chapter Accessing the Policy Adding a Thank You Letter Editing the Policy Adding, Editing and Removing Assignments Admitted Carrier Identification Summary of

More information

This document will provide a step-by-step tutorial of the RIT 2.0 Client interface using the Liability Trading 3 Case.

This document will provide a step-by-step tutorial of the RIT 2.0 Client interface using the Liability Trading 3 Case. RIT User Guide Client Software Feature Guide Rotman School of Management Introduction Welcome to Rotman Interactive Trader 2.0 (RIT 2.0). This document assumes that you have installed the Rotman Interactive

More information

An application program that can quickly handle calculations. A spreadsheet uses numbers like a word processor uses words.

An application program that can quickly handle calculations. A spreadsheet uses numbers like a word processor uses words. An application program that can quickly handle calculations A spreadsheet uses numbers like a word processor uses words. WHAT IF? Columns run vertically & are identified by letters A, B, etc. Rows run

More information

WEB APPENDIX 8A 7.1 ( 8.9)

WEB APPENDIX 8A 7.1 ( 8.9) WEB APPENDIX 8A CALCULATING BETA COEFFICIENTS The CAPM is an ex ante model, which means that all of the variables represent before-the-fact expected values. In particular, the beta coefficient used in

More information

Manual Asset Based Finance Manager

Manual Asset Based Finance Manager Deutsche Bank Global Transaction Banking Manual Asset Based Finance Manager January 2018 Table of Contents 1. Working with Deutsche Bank Asset Based Finance Manager (ABF Manager) 03 2. Before you start

More information

Directions to build Stochastics & EMA Crossover search

Directions to build Stochastics & EMA Crossover search Directions to build Stochastics & EMA Crossover search 1. Click the UniSearch tab at the top of the program. 2. Click the drop down arrow next to the New icon. 3. Click on New Search. 4. Click in the empty

More information

Summary of Statistical Analysis Tools EDAD 5630

Summary of Statistical Analysis Tools EDAD 5630 Summary of Statistical Analysis Tools EDAD 5630 Test Name Program Used Purpose Steps Main Uses/Applications in Schools Principal Component Analysis SPSS Measure Underlying Constructs Reliability SPSS Measure

More information

Using the Principia Suite

Using the Principia Suite Using the Principia Suite Overview - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -1 Generating Research Mode Reports........................................... 2 Overview -

More information

Discrete Probability Distributions

Discrete Probability Distributions 90 Discrete Probability Distributions Discrete Probability Distributions C H A P T E R 6 Section 6.2 4Example 2 (pg. 00) Constructing a Binomial Probability Distribution In this example, 6% of the human

More information

MLC at Boise State Polynomials Activity 2 Week #3

MLC at Boise State Polynomials Activity 2 Week #3 Polynomials Activity 2 Week #3 This activity will discuss rate of change from a graphical prespective. We will be building a t-chart from a function first by hand and then by using Excel. Getting Started

More information

And Training Manual. Version 1.1. P a g e 1 22

And Training Manual. Version 1.1. P a g e 1 22 And Training Manual Version 1.1 P a g e 1 22 Contents 1 Workspaces 3 2 Watchlist.. 5 3 Graphs.. 8 4 Order Entry 11 5 Linking Panels Together 16 6 Blotter (Positions, Trades, Orders, Order Book).. 17 7

More information

Morningstar Office Academy Day 4: Research and Workspace

Morningstar Office Academy Day 4: Research and Workspace Morningstar Office Academy Day 4: Research and Workspace - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 1 Lesson 1: Modifying Research Settings.......................................

More information

Master User Manual. Last Updated: August, Released concurrently with CDM v.1.0

Master User Manual. Last Updated: August, Released concurrently with CDM v.1.0 Master User Manual Last Updated: August, 2010 Released concurrently with CDM v.1.0 All information in this manual referring to individuals or organizations (names, addresses, company names, telephone numbers,

More information

Calculating the Number and Percent of Workers in Your State by Establishment Size

Calculating the Number and Percent of Workers in Your State by Establishment Size March 2009 Calculating the Number and Percent of Workers in Your State by Establishment Size Policy proposals for paid time-off programs often include an exemption for small businesses. (There are notable

More information

Tests for Paired Means using Effect Size

Tests for Paired Means using Effect Size Chapter 417 Tests for Paired Means using Effect Size Introduction This procedure provides sample size and power calculations for a one- or two-sided paired t-test when the effect size is specified rather

More information

PCGENESIS FINANCIAL ACCOUNTING AND REPORTING (FAR) SYSTEM OPERATIONS GUIDE

PCGENESIS FINANCIAL ACCOUNTING AND REPORTING (FAR) SYSTEM OPERATIONS GUIDE PCGENESIS FINANCIAL ACCOUNTING AND REPORTING (FAR) SYSTEM OPERATIONS GUIDE 4/1/2011 Section A: Budget Account Master Processing, V2.1 Revision History Date Version Description Author 04/1/2011 2.1 11.01.00

More information

A Brief Guide to Engineering Management Financial Calculations in ENGM 401 & ENGM 620 Section X1 Fall 2010

A Brief Guide to Engineering Management Financial Calculations in ENGM 401 & ENGM 620 Section X1 Fall 2010 A Brief Guide to Engineering Management Financial Calculations in ENGM 401 & ENGM 620 Section X1 Fall 2010 MG Lipsett last updated October 21, 2010 Introduction This document provides concise explanations

More information

Bidding Decision Example

Bidding Decision Example Bidding Decision Example SUPERTREE EXAMPLE In this chapter, we demonstrate Supertree using the simple bidding problem portrayed by the decision tree in Figure 5.1. The situation: Your company is bidding

More information