Capacity Expansion in Competitive Electricity Markets

Size: px
Start display at page:

Download "Capacity Expansion in Competitive Electricity Markets"

Transcription

1 Capacity Expansion in Competitive Electricity Markets Efthymios Karangelos University of Liege November 2013

2 In the past... Vertical Integration A single utility owned & operated all power system infrastructure. Least cost capacity related decisions: 1. Investment & Retirement of Generating Units. 2. Network Reinforcement.

3 Nowadays... Competition Several actors own & operate parts of the system infrastucture. Decentralized, profit seeking capacity related decisions.

4 Overview Part I: Generation capacity expansion from the generators perspective 1. Discounted cash flow method. 2. Real options analysis. Part II: Generation capacity expansion from the consumers perspective 1. Long-term supply security in competitive markets. 2. Capacity reward mechanisms. Part III: Transmission capacity expansion 1. Cost-based model. 2. Merchant model.

5 Part I Generation Capacity Expansion The Generators Perspective

6 GenCo Long-term Perspective Generators need to invest in order to participate in the short-term electricity market.

7 Investment Life Cycle Construction Projected Lifetime Retirement 1. Construction Period (1 5yr) Planning & Permitting. Construction. 2. Projected Lifetime (1 30yr) Production & Sales. Maintenance. 3. Retirement Period Asset Liquidation.

8 Investment Cash Flows Decision Cost & Revenue Realization Construction Projected Lifetime Retirement Decision Making Problem The investor needs to compare in advance costs and revenues to be realized at different points in the future.

9 Discounted Cash Flow Method Principle Refer all cost and revenue cash flows to the decision making point by discounting the future according to: 1. The time value of money... Any amount of money has a greater worth the sooner it is collected (due to the potential to earn an interest). 2. The value of certainty... Any future amount of money has a greater worth if it is to be collected with a greater certainty.

10 Discounted Cash Flow Method Concepts Present Value (PV ) of a cash flow (CF) to be collected at a future year t is the discounted worth of this amount at the present point: PV (F, t) = CF (1 + ρ) t Risk-free Discount Rate (ρ), i.e. interest rate, is the annual percentage change in the value of money. Risk-adjusted Discount Rate (ˆρ) is the risk-free interest rate plus a security premium, increasing with the level of the cash flow uncertainty (ˆρ = ρ + ρ s ).

11 Discounted Cash Flow Method Concepts Net Present Value (NPV ) of an investment opportunity (i) is the difference between the present value of the associated revenues (R i,t ) and costs (C i,t ): t=t c+t L NPV (i, T c, T L ) = C i,0 t=tc+1 R i,t C i,t (1 + ρ) t Message V TL + (1 + ρ) T C+T L NPV shows the value of an opportunity over it s life cycle, referred at the decision making point.

12 Discounted Cash Flow Method Concepts Net Present Value (NPV ) of an investment opportunity (i) is the difference between the present value of the associated revenues (R i,t ) and costs (C i,t ): Rule t=t c+t L NPV (i, T c, T L ) = C i,0 t=tc+1 V TL + (1 + ρ) T C+T L R i,t C i,t (1 + ρ) t Investment opportunity i is profitable if NPV (i, T c, T L ) > 0

13 Discounted Cash Flow Method Example Investment in a new coal-fired power plant Technical Characteristics G i = 500MW ui,g = 0.8

14 Discounted Cash Flow Method Example Investment in a new coal-fired power plant Technical Characteristics G i = 500MW ui,g = 0.8 Construction Data (year 0) ci,0 = 1021$/kW Lifetime Data (years 1 30) c i,g = 11.77$/MWh π = 32$/MWh ρ = 8% Retirement Value Vi = 5 million $

15 Discounted Cash Flow Method Example Investment in a new coal-fired power plant Technical Characteristics G i = 500MW ui,g = 0.8 Construction Data (year 0) ci,0 = 1021$/kW Lifetime Data (years 1 30) c i,g = 11.77$/MWh π = 32$/MWh ρ = 8% Retirement Value Vi = 5 million $ Investment Cost C i,0 = c i,0 G i 1000 = $

16 Discounted Cash Flow Method Example Investment in a new coal-fired power plant Technical Characteristics G i = 500MW ui,g = 0.8 Construction Data (year 0) ci,0 = 1021$/kW Lifetime Data (years 1 30) c i,g = 11.77$/MWh π = 32$/MWh ρ = 8% Retirement Value Vi = 5 million $ Investment Cost C i,0 = c i,0 G i 1000 Annual Cost = $ C i,t = u i,g G i c i,g 8760h/y = $ /y

17 Discounted Cash Flow Method Example Investment in a new coal-fired power plant Technical Characteristics G i = 500MW ui,g = 0.8 Construction Data (year 0) ci,0 = 1021$/kW Lifetime Data (years 1 30) c i,g = 11.77$/MWh π = 32$/MWh ρ = 8% Investment Cost C i,0 = c i,0 G i 1000 Annual Cost = $ C i,t = u i,g G i c i,g 8760h/y = $ /y Annual Revenue Retirement Value Vi = 5 million $ R i,t = u i,g G i π 8760h/y = $ /y

18 Discounted Cash Flow Method Example Investment in a new coal-fired power plant t C i,t ($) R i,t ($) PV {R i,t C i,t } ($) NPV = millions of $

19 Discounted Cash Flow Method Example Investment in a new coal-fired power plant Should we invest? NPV = millions of $

20 Discounted Cash Flow Method Example Investment in a new coal-fired power plant Should we invest? NPV = millions of $ Or... keep our initial capital (510.5 millions of $) in the bank? invest on a different opportunity?

21 Discounted Cash Flow Method Internal Rate of Return (IRR) of an investment opportunity (i) is the discount rate that equates the present value of the future costs and revenues to the initial investment costs: IRR = ρ : NPV (i, T c, T L ) = 0 Message IRR shows the rate of growth the investment opportunity is expected to generate over it s lifecycle. IRR allows the relative evaluation of alternatives.

22 Discounted Cash Flow Method Example Investment in a new coal-fired power plant vs money in the bank ρ (%) NPV ( millions of $)

23 Discounted Cash Flow Method Example Investment in a new coal-fired power plant vs money in the bank ρ (%) NPV ( millions of $) Keeping the initial capital in the bank is more profitable if the banks offers an interest greater than %

24 Discounted Cash Flow Method Example Investment in a new coal-fired power plant vs money in the bank ρ (%) NPV ( millions of $) Keeping the initial capital in the bank is more profitable if the banks offers an interest greater than % Minimum Acceptable Rate of Return (MARR) A firm will decide to invest in a project if it yields an IRR greater than the firm s MARR (e.g. interest on bank deposit).

25 Discounted Cash Flow Method Example Investment in a new coal-fired power plant vs combined cycle gas turbine Technical Characteristics G1 = 500MW u 1,g = 0.8 Construction Data (year 0) c1,0 = 1021$/kW Lifetime Data (years 1 30) c1,g = 11.77$/MWh π = 32$/MWh ρ = 8% Technical Characteristics G2 = 500MW u 2,g = 0.8 Construction Data (year 0) c2,0 = 533$/kW Lifetime Data (years 1 30) c2,g = 20.78$/MWh π = 32$/MWh ρ = 8% Retirement Value V 1 = 5 million $ Retirement Value V 2 = 5 million $

26 Discounted Cash Flow Method Example Investment in a new coal-fired power plant vs combined cycle gas turbine ρ (%) NPV 1 ( millions of $) NPV 2 ( millions of $) < 0 0 At the assumed risk-free discount rate the coal-fired plant has a greater NPV! The combined cycle gas turbine has a greater IRR!

27 Effect of Cyclical Demand So far, we have been thinking that... The plant will run on a given utilization factor throughout it s lifetime. The investor will collect a constant price of electricity throughout the lifetime of the plant. What about seasonal variations in the demand and price of electricity?

28 Effect of Cyclical Demand Load Duration Curve (Annual) x-axis refers to a percentage of time. y-axis refers to a demand level. A point on the curve shows the percentage of periods in a year that the demand is greater than a certain level.

29 Effect of Cyclical Demand MWh 100 time (%) Wh /MW MWh

30 Effect of Cyclical Demand MWh MWh 100 time (%) MWh /MW Wh MWh

31 Effect of Cyclical Demand MWh MWh 100 time (%) MWh /MW Wh /MW Wh 100 time (%) MWh

32 Effect of Cyclical Demand MWh MWh 100 time (%) MWh /MW Wh /MW Wh 100 time (%) MWh

33 Effect of Cyclical Demand A point on the annual price duration curve shows the percentage of periods in a year that the demand is greater than a certain level. Projection of short-run cost determines the plant utilization factor. The integral of area R g is the annual net revenue from the operation of the plant.

34 Effect of Uncertainty So far, we have been thinking that... The plant will run on a constant marginal cost throughout it s lifetime. What if the fuel price is not known with certainty?

35 Effect of Uncertainty So far, we have been thinking that... The plant will run on a constant marginal cost throughout it s lifetime. What if the fuel price is not known with certainty? Sensitivity Analysis Calculation of NPV & IRR for different values of the marginal cost within the uncertainty range.

36 Sensitivity Analysis - Example Investment in a new coal-fired power plant for different fuel cost values Sensitivity plots for NPV & IRR. A steeper NPV curve shows a riskier project. A more variable IRR curve shows a riskier project.

37 Risk-adjusted Discount Rate Principle Risk-free interest rate plus a security premium: ˆρ = ρ + ρ s ρ s (%) NPV ( millions of $) Practical Challenge How to calculate the correct security premium for each uncertainty?

38 Effect of Uncertainty So far, we have been thinking that... The price of electricity throughout the lifetime of the plant is known with certainty. What if there is more than one future scenario?

39 Effect of Uncertainty So far, we have been thinking that... The price of electricity throughout the lifetime of the plant is known with certainty. What if there is more than one future scenario? Real Option Analysis Investment opportunity as an option which can be used now (under uncertainty) OR in the future (with better information).

40 Real Options Analysis Example Investment under uncertainty in a new coal-fired power plant Technical Characteristics G i = 500MW ui,g = 0.8 Construction Data (year 0) ci,0 = 1021$/kW Retirement Value Vi = 5 million $ Lifetime Data ci,g = 11.77$/MWh ρ = 8% (years 1 2) π = 32$/MWh (years 3 30) p 1 = 40% π 1 = 32$/MWh p 2 = 60% π 2 = 20$/MWh

41 Real Options Analysis Example Investment under uncertainty in a new coal-fired power plant Scenario 1 (p 1 = 40%) t C i,t ($) R i,t ($) PV {R i,t C i,t } ($) NPV = millions of $

42 Real Options Analysis Example Investment under uncertainty in a new coal-fired power plant Scenario 2 (p 2 = 60%) t C i,t ($) R i,t ($) PV {R i,t C i,t } ($) NPV = millions of $

43 Real Options Analysis Example Investment under uncertainty in a new coal-fired power plant R i,t = p 1 R 1 i,t + p2 R 2 i,t t C i,t ($) R i,t ($) PV {R i,t C i,t } ($) Expected NPV = 48.6 millions of $

44 Real Options Analysis Example Investment under uncertainty in a new coal-fired power plant Should we invest? Expected NPV = 48.6 millions of $

45 Real Options Analysis Example Investment under uncertainty in a new coal-fired power plant Should we invest? Expected NPV = 48.6 millions of $ Real Option Analysis What if we keep the opportunity to invest and decide after year 3? Is it better to invest after year 3, only if the electricity price stays at 32$/MWh?

46 Real Options Analysis Example Investment under uncertainty in a new coal-fired power plant Investment at year 3 if scenario 1 becomes true... t C i,t ($) R i,t ($) PV {R i,t C i,t } ($) Expected NPV = 86.5 millions of $

47 Real Options Analysis Example Investment under uncertainty in a new coal-fired power plant Investment NPV (millions of year 0 without uncertainty year 0 under uncertainty year 3 if scenario 1 is true 86.5 Option Value (The opportunity to invest is worth... ) V O =max{48.6, 86.5, 0} = 86.5 millions of $ Value of Waiting to Invest (Not investing now is worth... ) V W =max{ , 0} = 37.9 millions of $ Cost of Uncertainty (Not knowing the future costs... ) NPV p 1 =100% V O = millions of $

48 Real Options Analysis Extension Principle An investment opportunity can be evaluated as a financial call option. Financial Call Option The holder has the right to buy a commodity in the future at a given price. Option Fee: The cost of getting the right to buy. Exercise Fee: The price at which the commodity can be bought in the future. The option value is the difference between the expected future value of the commodity and the option + exercise fees.

49 Real Options Analysis Extension Financial Call Option Evaluation Model the dynamics of the commodity value in detail: 1. Optimal option capturing strategy (time, option & exercise fees). 2. Optimal time to exercise an option. Application to the GenCo s Problems Model the dynamics of the costs and revenues within the life cycle of a plant in detail: 1. Optimal investment strategy (type & capacity of plant, time, location.) 2. Optimal retirement strategy for an existing plant. Analytical focus on uncertainty origins and impacts.

50 Summary Decision Making Criteria Value of an investment over its life cycle. Risk on investment profitability. Net Present Value Analysis Projection of future cash flows at the decision making point. Qualitative consideration of investment risks. Real Options Analysis Detailed modeling of the cash flow evolution. Quantitative consideration of investment risks.

51 Part I Questions?

52 Part II Generation Capacity Expansion The Consumers Perspective

53 The Consumers Perspective The consumers demand capacity for a secure & reliable supply of electricity.

54 The Regulator s Perspective Objective The regulator must ensure that the market framework encourages the generators to invest & meet the consumers expectations. In theory... The operation a short-term competitive market should result in optimal investment decisions. In practice... Will the generators invest to secure the supply of electricity on a long-term basis?

55 A Theoretical Result When there is excess supply... The price of the short-term market is set at the marginal cost of the most expensive generating unit. Infra-marginal generators receive a premium in addition to their marginal costs (scarcity rent).

56 A Theoretical Result When there is excess demand... The price of the short-term market is set at the value of lost load. Every generator receives a scarcity rent.

57 A Theoretical Result In the long term... The marginal costs of every generating unit are completely recovered through the electricity market price. A rational investor should invest up to the point where the net revenues (area R g ) are equal to the investment and fixed operational costs.

58 A Theoretical Result In the long term... /MWh voll peaking mid merit base load 100 time (%) If an existing generator is not needed, it will be non-profitable and its owner should decide to retire it. If a new generator is needed, there will be a profitable investment opportunity. The system capacity should converge to an optimal mix.

59 What could go wrong? 1. Demand-side Participation Most electricity consumers do not participate in the short-term market. Voll is not common for different consumers, times of the day etc... The system capacity mix relies strongly on a statistical estimation of the average voll.

60 What could go wrong? 1. Demand-side Participation Most electricity consumers do not participate in the short-term market. Generators have opportunities for capacity withholding and strategic bidding (e.g. California Crisis).

61 Capacity Withholding If a generator reduces the capacity it makes available in the short-term market...

62 Capacity Withholding If a generator reduces the capacity it makes available in the market, it may increase its profit through pushing the price to the level of the voll.

63 Strategic Bidding The most expensive generator can only be outplaced by the voll.

64 Strategic Bidding The most expensive generator can only be outplaced by the voll. As long as it remains below the voll, it can increase its bid price above its marginal cost.

65 What could go wrong? 1. Demand-side Participation Most electricity consumers do not participate in the short-term market. Generators have opportunities for capacity withholding and strategic bidding (e.g. California Crisis). A regulator needs to apply a price cap on the short-term market to protect the consumers.

66 What could go wrong? 2. Regulatory Price Caps /MWh voll price cap cap peaking mid merit base load The price cap applies even when there is an actual capacity shortage. The market price never reaches the voll. 100 time (%) Investors face a missing money problem.

67 What could go wrong? 3. Ancillary & Balancing Services System operators procure ancillary & balancing services through out-of-market arrangements. System operators use these services according to technical rules. While the system is stressed the market price does not indicate the need for more capacity.

68 What could go wrong? 4. Investment Uncertainty /MWh Price variation due to wind - January 6 strategic firms Hour Maximum 90th percentile 75th percentile Median 25th percentile 10th percentile Minimum The profitability of generation capacity is uncertain as it depends on rare & extreme price levels. Missing an investment opportunity is better than risking to suffer a loss. Risk-averse investors tend to under-invest in generation capacity.

69 What could go wrong? 5. Power Plant Capacity Standardization Power plant can be built on standard capacity ratings. The optimal capacity expansion may not be a technically feasible option. Less than the optimal capacity risks the security of the supply. More than the optimal capacity risks the profitability of the investment.

70 The Regulator s Solution In the interest of the long-term supply security... Wh MW Security Margin A net generation capacity surplus should be maintained. Investment decisions should remain private but also become coordinated. 100 time (%) Generators should be encouraged to maintain a net capacity surplus through a capacity reward mechanism.

71 Capacity Reward Principle Electricity Consumers Energy Supply Risk Financial Security Security of Supply Investor Financial Risk A regulator should reward investors according to the value the consumers place on the firm commitment to develop a project.

72 Capacity Reward Mechanisms 1. Strategic Reserve e.g. Finland, Norway 2. Capacity Payment e.g. Argentina, Italy, Spain (past) 3. Capacity Market e.g. New England, PJM, Brazil, Colombia

73 Strategic Reserve Wh MW Strategic Reserve 100 time (%) Principle The system operator (on behalf of the regulator) reserves in advance & controls a part of the system s generation capacity.

74 Strategic Reserve In the long-term... The system operator centrally controls the system security margin (MW). The generators that engage in this scheme receive an additional certain revenue (euro/mw).

75 Strategic Reserve In the long-term... The system operator centrally controls the system security margin (MW). The generators that engage in this scheme receive an additional certain revenue (euro/mw). In the short-term... The system operator can make the reserved capacity available in the electricity market, or... The system operator can decide to use the reserved capacity in the case of an emergency. The consumers pay for the additional cost of the reserved capacity (euro/mwh).

76 Strategic Reserve Main Benefits The system operator can contract for the resources that are needed to protect the supply. The withdrawal of the reserved capacity from the market enhances investment profitability without endangering the supply. Criticism The use of the reserved capacity by the system operator may distort the operation of the short-term market. The capacity reward is only available to the generators that engage in the reserve procurement.

77 Capacity Payment Wh MW Security Margin 100 time (%) Principle The regulator offers a payment per MW of installed generation capacity to make investments more attractive and thus stimulate the development of a security margin.

78 Capacity Payment Cost-based Payment Method Payment level is defined as a portion of the investment & fixes operational costs of a power plant. Reliability-based Payment Method Payment level is defined hourly as the difference between the voll and the short-term market price, weighted by the outage probability. π r = lolp t (voll µ t )

79 Capacity Payment Main Benefit Profitability of generation capacity becomes controllable/ more certain when needed. Criticism No obligation on the generators to provide energy via the rewarded capacity. No association between the cost-based payment & the generator s contribution to the supply security. Generators have an opportunity to increase the level of the reliability-based payment through capacity withholding.

80 Capacity Market Wh MW Security Margin 100 time (%) Principle The regulator defines the desired security margin and creates a long-term forward market where generators compete to collect capacity revenues.

81 Capacity Market At the forward point... (e.g today, for ) The regulator awards a capacity credit per MW to every generator that is expected to be operational (existing & in construction today). Generators can sell these credits through a centralized market in exchange for: 1. a direct payment, 2. the responsibility to provide energy or reserve when instructed, 3. a cap on the future short-term market revenues.

82 Capacity Market The Capacity Demand Curve MW /M target Security Margin (%) The reward at the targeted margin is the expected net cost of a reference new power plant. The credit value gradually decreases (increases) above (below) the targeted security margin. Generators do not have an opportunity to manipulate the level of the capacity reward.

83 Capacity Market In the long-term... Generators receive the capacity value (euro/mw) through the forward auction. The consumers pay the regulator ex-post. In the short-term... The market revenue of the generators that receive a capacity reward is capped. The generators that receive a capacity reward face a penalty charge for failing to deliver energy or reserve when instructed.

84 Capacity Market /MWh voll price cap cap Capacity Value + Market Revenue Unavailability Penalty The GenCo s Perspective 100 time (%) In spite of the price cap cost recovery is guaranteed for a generator that is available when needed. A generator has an incentive to avoid the unavailability penalties.

85 Capacity Market Main Benefit Generators are rewarded for actually securing the supply. Consumers pay for the security level they receive. Criticism More suitable for centralized (pool) short-term markets. Complexity of availability measurement.

86 Summary Long-term Security of Supply Question The regulator should implicitly coordinate investment decisions through the electricity market rules. Capacity Reward Mechanisms Provide additional investment incentives to enhance the long-term security of the electricity supply. All mechanisms have different advantages & disadvantages. The forward capacity market appears more favorable.

87 Part II Questions?

88 Part III Transmission Capacity Expansion

89 In the past... Vertical Integration Transmission capacity expansion followed the evolution of the supply & demand.

90 Nowadays... Competition Transmission capacity expansion is an independent process.

91 The Transmission Business A service The delivery of electrical energy with certain quality & security from the point of production to the point of consumption. A natural monopoly No rationale for the existence of competing transmission lines along the same route. An impartial role Focus on the global economic welfare of the market actors (equitable treatment of generators and consumers).

92 Investing on the Transmission System Capital Intensive Assets Lines of long distance. Transformers & switchgear. Control & communication infrastructure. Life Time & Irreversibility Expected life time in the order of years. Insignificant value of retiring/reselling assets.

93 Investing on the Transmission System Standardized Assets Voltage & capacity of transmission equipment comes in standard ratings. Utilization should be expected to evolve throughout the asset life time. Economies of Scale Main cost component is line length rather than line rating. A line of greater capacity has a smaller investment cost per MW.

94 Models of Transmission Expansion Cost-based The transmission company invests under the approval of the regulator and receives a regulated, risk-free return on investment. Merchant (market-driven) The transmission company invests in expectation of the future market value of transmission capacity. The transmission company undertakes the risk of not recovering its investment costs.

95 Cost-based Expansion 1. Network expansion is planned by the transmission company according to the projected future needs.

96 Cost-based Expansion 1. Network expansion is planned by the transmission company according to the projected future needs. 2. The transmission company submits an expansion plan to the regulator.

97 Cost-based Expansion 1. Network expansion is planned by the transmission company according to the projected future needs. 2. The transmission company submits an expansion plan to the regulator. 3. The regulator reviews & possibly accepts the submitted plan.

98 Cost-based Expansion 1. Network expansion is planned by the transmission company according to the projected future needs. 2. The transmission company submits an expansion plan to the regulator. 3. The regulator reviews & possibly accepts the submitted plan. 4. If the plan is accepted, the regulator defines the net profit of the transmission company.

99 Cost-based Expansion 1. Network expansion is planned by the transmission company according to the projected future needs. 2. The transmission company submits an expansion plan to the regulator. 3. The regulator reviews & possibly accepts the submitted plan. 4. If the plan is accepted, the regulator defines the net profit of the transmission company. 5. The transmission company undertakes the accepted expansion plan.

100 Cost-based Expansion 1. Network expansion is planned by the transmission company according to the projected future needs. 2. The transmission company submits an expansion plan to the regulator. 3. The regulator reviews & possibly accepts the submitted plan. 4. If the plan is accepted, the regulator defines the net profit of the transmission company. 5. The transmission company undertakes the accepted expansion plan. 6. The transmission company collects its revenue via regulated use-of-network charges.

101 Use-of-network charges Scope Allocate the cost of the transmission infrastructure to the network users (producers & consumers). Ensure that the transmission company collects the regulated return on investment. Cost Allocation Alternatives 1. Postage Stamp Method 2. Contract Path Method 3. MW-mile Method

102 Postage Stamp Method Principle Charge network users according to their average use of the whole network. e.g. Allocate the regulated revenue of the transmission company to the generators (consumers) according to the annual energy produced (consumed). Charges do not depend on the location of connection.

103 Postage Stamp Method Advantages Simplicity. Disadvantages Allocation does not reflect differences in the actual network use. Remote transmission costs passed on to central network users. Allocation can only reflect transmission costs at a regional level.

104 Contract Path Method Principles Define an assumed route of the electricity flow between the points of production and consumption (contract path) for every transaction. Apply a per MW charge to every transaction for the use of a contract path. Charge generators and consumers according to the cost of the transmission infrastructure along the respective contract path.

105 Contract Path Method Advantages Allocation is more reflective of the use of the network. Locational differences are taken into consideration. Disadvantages Relevance between the contract path and the actual electrical path (according to Kirchoff s laws) is questionable. Allocation more suitable for long-term bilateral agreements.

106 MW-mile Method Principles Define a per MW-mile cost of the transmission network. Determine the actual electrical path of every transaction via power flow calculation methods. Charge generators and consumers according to the energy volume and the electrical path corresponding to every transaction.

107 MW-mile Method Advantages Allocation is based on Kirchoff s laws for the use of a network. Disadvantages Complexity (power flow is non-linear). Electrical paths are not independent, calculation relies on the adopted transaction sequence.

108 Merchant Expansion The transmission company... Invests in expectation of the future market value of transmission capacity. Undertakes the risk of not recovering its investment costs.

109 The Market Value of Transmission Capacity INVESTING IN TRANSMISSION 20 $/MWh A B 1000 MW 45 $/MWh G 1 G 2 Figure MW Simple example illustrating the value of transmission A transmission line in a competitive setting... on its own. Finally, we assume that the capacity of the transmission line is sufficient to support any power transmission that may be required. The consumers at bus B can either buy energy at 45 $/MWh from the local generator G 2 or buy energy at 20 $/MWh from the remote generator G 1 and pay for the transmission of generator this energy. If rather cost of than this transmissiona local, more is less than expensive 25 $/MWh, one. consumers will choose to buy their energy from G 1 because the overall cost would be less than Allows the 45 $/MWh a remote that theycheaper would havegenerator pay buy energy to compete from generator withg 2 a. local, It is thusmore not in expensive the best interestone. of the owner of the transmission line to charge more than 25 $/MWh because such a charge would discourage consumers from making use of the transmission system. In this example, the value of the transmission service is thus 25 $/MWh because, at that price, consumers are indifferent between using and not using transmission. The value of transmission is thus a function of the short-run marginal cost of generation. In this case, this function is very simple because there is Allows consumers to buy electricity from a remote, cheaper

110 Example (Borduria - Syldavia interconnection) 8.4 VALUE-BASED TRANSMISSION EXPANSION 235 Borduria P B Syldavia P S D B = 500 MW D S = 1500 MW Figure 8.2 Model of the Borduria/Syldavia interconnection Borduria The demands in Borduria and Syldavia are respectively 500 MW and 1500 MW. We continue to assume that these demands do not vary with time and are perfectly inelastic. In the absence of an interconnection, the two national electricity markets operate independently and the prices in Borduria and Syldavia are respectively 15 $/MWh and 43 $/MWh. The value of transporting the first megawatt-hour from Borduria to Syldavia is thus equal to the difference in price between the two countries, that is, 28 $/MWh. We saw in Chapter 6 that when the flow through the interconnection is 400 MW, generators in Borduria produce 900 MW. 500 MW of this production is for the local load, while the remaining 400 MW is sold to consumers in Syldavia. The remaining 1100 MW of Syldavian load is produced locally. Under these conditions, the prices in Borduria and Syldavia are 19 $/MWh and 35 $/MWh respectively. The value of transporting one additional megawatt-hour from Borduria to Syldavia is thus only 16 $/MWh. This is also the maximum price that consumers in Syldavia would agree to pay for the transport of a megawatt-hour that they have bought in Borduria for π 19 $/MWh. If the price of transmission S π B = 28 $/MWh were any higher, they would prefer to buy this megawatt-hour from local generators. When the flow on the interconnection reaches MW, the prices in Borduria D B = 500MW π B = P B $/MWh = 15 $/MWh Syldavia D S = 1500MW π S = P S $/MWh = 43 $/MWh The marginal value of transmission capacity is...

111 Example (Borduria - Syldavia interconnection) 8.4 VALUE-BASED TRANSMISSION EXPANSION 235 Borduria P B Syldavia P S D B = 500 MW D S = 1500 MW Figure 8.2 Model of the Borduria/Syldavia interconnection The demands in Borduria and Syldavia are respectively 500 MW and 1500 MW. We continue to assume that these demands do not vary with time and are perfectly inelastic. In the absence of an interconnection, the two national electricity markets operate independently and the prices in Borduria and Syldavia are respectively 15 $/MWh and 43 $/MWh. The value of transporting the first megawatt-hour from Borduria to π Syldavia is thus equal to the difference B = π in price S between the two countries, that is, 28 $/MWh. We saw in Chapter 6 that when the flow through the interconnection is 400 MW, generators in Borduria produce 900 MW. 500 MW of this production is for the local load, while the remaining 400 MW is sold to consumers in Syldavia. The remaining 1100 MW of Syldavian load is produced locally. Under these conditions, the prices in Borduria and Syldavia are 19 $/MWh and 35 $/MWh respectively. The value of transporting one additional megawatt-hour from Borduria to Syldavia is thus only F = MW 16 $/MWh. This is also the maximum price that consumers in Syldavia would agree to pay for the transport of a megawatt-hour that they have bought in Borduria for 19 $/MWh. If the price of transmission were any higher, they would prefer to buy this megawatt-hour from local generators. When the flow on the interconnection reaches MW, the prices in Borduria and Syldavia are equal: If we had a line of sufficiently large capacity (D B + F) = (D S F ) { πb = π S = 24.3$/MWh The marginal value of transmission capacity would be zero!

112 Example (Borduria - Syldavia interconnection) 8.4 VALUE-BASED TRANSMISSION EXPANSION 235 Borduria P B Syldavia P S D B = 500 MW D S = 1500 MW Figure 8.2 Model of the Borduria/Syldavia interconnection The demands in Borduria and Syldavia are respectively 500 MW and 1500 MW. We continue to assume that these demands do not vary with time and are perfectly inelastic. In the absence of an interconnection, the two national electricity markets operate independently and the prices in Borduria and Syldavia are respectively 15 $/MWh and 43 $/MWh. The value of transporting the first megawatt-hour from Borduria to Syldavia is thus equal to the difference in price between the two countries, that is, 28 $/MWh. We saw in Chapter 6 that when the flow through the interconnection is 400 MW, generators in Borduria produce 900 MW. 500 MW of this production is for the local load, while the remaining 400 MW is sold to consumers in Syldavia. The remaining 1100 MW of Syldavian load is produced locally. Under these conditions, the prices in Borduria and Syldavia are 19 $/MWh and 35 $/MWh respectively. The value of transporting one additional megawatt-hour from Borduria to Syldavia is thus only 16 $/MWh. This is also the maximum price that consumers in Syldavia would agree to pay for the transport of a megawatt-hour that they have bought in Borduria for 19 $/MWh. If the price of transmission were any higher, they would prefer to buy this megawatt-hour from localπgenerators. S π B = 16 $/MWh When the flow on the interconnection reaches MW, the prices in Borduria and Syldavia are equal: If we had a line of limited capacity (e.g. F max = 400MW ) π B = (D B + F max ) = 19$/MWh π S = (D S F max ) = 35$/MWh The marginal value of transmission capacity would be...

113 The Market Value of Transmission Capacity Transmission Demand Function π T (F) Expresses the marginal value of transmission as a function of the flow. e.g. Borduria - Syldavia interconnection π T (F) = π S (F) π B (F) = = (D S F) [ (D B + F)] = = F $/MWh

114 The Market Value of Transmission Capacity Transmission Revenue Function R T (F) Expresses the revenue of the transmission company as a function of the flow. e.g. Borduria - Syldavia interconnection R T (F ) = π T (F) F = = ( F) F $

115 The Market Value of Transmission Capacity Annuitized Transmission Cost Function C T (F) C T (F) = C 0 + k l F where C 0 : Annuitized fixed transmission capacity cost ($ per year) k: Annutized marginal transmission capacity cost ($/MW km year) l: Line length (km)

116 Optimal Transmission Capacity Annuitized Transmission Capacity Value V T (F) V T (F) = R T (F) 8760 (hr/year) C T (F) Optimal Transmission Capacity (F ) F {R T (F) 8760 C T (F)} : = 0 ( F πt (F ) ) 8760 F + π T (F ) = k l F F

117 Example (Borduria - Syldavia interconnection) Optimal Transmission Capacity { k = 35 } $/(MW km year) l = 100 km F = 800 πb = 23 πs = 27 MW $/MWh $/MWh Annual Cost & Revenue R T (F ) = (π S (F ) π B (F )) F = 28 millions of $/year C T (F ) = C 0 + k l F = C millions of $/year At the optimal capacity the investor would not recover its fixed transmission capacity costs!

118 The Regulator s Solution Transmission Capacity Uplift (π u ) R T (F ) = (π T (F) + π u ) F Principle Support Recover the fixed investment costs of merchant capacity expansion through an additional regulated charge. Transmission capacity expansion increases the net welfare of the electricity system stakeholders.

119 Transmission Constraints & Welfare Losses Merit Order Dispatch The lowest net electricity cost (maximum global welfare) solution to the electricity supply problem. e.g. Borduria - Syldavia interconnection {F MW P B = MW, P S = 566.6MW } C(P B ) = 10 P B P2 B $/h C(P S ) = 13 P S P2 S $/h C M = $/h Can only happen in a transmission network with infinite capacity!

120 Transmission Constraints & Welfare Losses Out of Merit Generation Cost (Cost of Constraints) The difference between the constrained optimal solution and the unconstrained merit order dispatch. e.g. Borduria - Syldavia interconnection {F = 800MW P B = 1300MW, P S = 700MW } C = $/h Hourly cost: C = C M C = 267 $/h

121 Example (Borduria - Syldavia interconnection) 8.4 VALUE-BASED TRANSMISSION EXPANSION Cost ($/h) 8000 Total cost 4000 Investment cost Cost of constraints Transmission capacity (MW) Figure 8.6 Evolution of the cost of constraints, the investment cost and the total transmission cost for the Borduria Syldavia interconnection At the optimal solution the total cost of transmission is minimized. The total cost of transmission is the sum of the cost of building the transmission system and the cost of constraints. As Figure 8.6 shows, the cost of building the transmission system increases with the transmission capacity while the cost of constraints

122 Capacity Expansion & Welfare Gain Gain of Capacity Expansion The difference between the constrained optimal solution and the case where the additional transmission capacity is not built. e.g. Borduria - Syldavia interconnection { F N = 0MW P B = 500MW, P S = 1500MW } Hourly gain: C N = $/h C N = C N C = $/h

123 Effect of Cyclical Demand MWh 100 time (%) Generalization Optimal transmission capacity must be calculated considering the duration of different load levels. Optimal transmission capacity would impose constraints only on a limited period of time.

124 Effect of Cyclical Demand Annuitized Transmission Capacity Value V T (F) N t V T (F) = RT t (F) Ht C T (F) t=1 Optimal Transmission Capacity (F ) F : { N t t=1 Rt T (F) Ht C T (F)} = 0 F N t ( π H t t T (F ) ) F + πt t F (F ) = k l F t=1 where: t: Type of period (e.g. peak/off-peak) H t : Duration of period t (hr/year)

125 Duration Example (BorduriaFigure - Syldavia 8.8 Simplified load-duration interconnection) curve 2700 D B (MW) 900 D S (MW) Figure Duration (h) Optimal Transmission Capacity { k = 140 $/(MW km yr) l = 100 km Duration (h) Load-duration curves for (a) Borduria and (b) Syldavia Table 8.1 Unconstrained economic dispatch for the peak and off-peak load conditions in the Borduria Syldavia system Load Generation } Generation FTotal hourly (MW) in Borduria in Syldavia = 400 generation π,p (MW) (MW) cost B ($/h) π ,p S π,o B = π,o S MW = 23 $/MWh = 27 $/MWh = 23 $/MWh Revenue only collected during peak hours!

126 optimization procedure has been applied to the IEEE 24 bus reliability test sys- RTS) Indepicted a network in Figure Forwith the detailsmore of this network, than see IEEE 2(1979). nodes... e 8.15 shows that, except for a small number of lines, line flows are well below BUS 17 BUS 18 BUS 21 BUS 22 BUS 23 BUS 16 BUS 19 BUS 20 BUS 14 BUS 15 BUS 13 BUS 11 BUS 24 BUS 12 BUS 3 BUS 9 BUS 10 BUS 6 BUS 5 BUS 4 BUS 8 Power flow accross all lines follows Kirchoff s current & voltage laws. Transmission demand function cannot be defined intuitively! Optimal transmission capacity expansion becomes a complex optimization problem! BUS 1 BUS 2 BUS 7 Figure 8.14 One-line diagram of the IEEE Reliability Test System

127 The Reference Network Concept A network with a set of given nodes (e.g. existing connection points) and transmission lines of optimal capacity. Defined through the solution of a transmission investment & operation cost minimization problem. Purpose Sets a basis for identifying transmission capacity value. Existing network suboptimality? Welfare gains of capacity expansion?

128 Optimal Transmission Capacity Problem Formulation Objective Function min P g(t),α j,f j N t N g N j H t c g P g (t) + t=1 g=1 N t : Set of periods in a year N g : Set of generators N j : Set of transmission lines H t : Duration of period t j=1 (hr/year) [ ] αj C 0 + k j l j F j

129 Optimal Transmission Capacity Problem Formulation Subject to... Power Flow Constraints ( t [1, N t ], j [1, N j ] ) ( h j Pg (t), P d (t) ) = 0 Line Flow Constraints ( t [1, N t ], j [1, N j ] ) f j ( Pg (t), P d (t), F j ) = 0 0 F j α j M Generation Constraints ( t [1, N t ], g [1, N g ] ) y g ( Pg (t) ) 0

130 Summary Investments on the Transmission Network Lumpy, capital intensive, economies of scale are critical. Cost-based Capacity Expansion Is the obvious solution for a natural monopoly providing an essential service. Merchant Capacity Expansion Driven by differences in short-term locational marginal prices. Cost recovery may need to be controlled by the regulator.

131 Part III Questions?

Electricity market reform to enhance the energy and reserve pricing mechanism: Observations from PJM

Electricity market reform to enhance the energy and reserve pricing mechanism: Observations from PJM Flexible operation and advanced control for energy systems Electricity market reform to enhance the energy and reserve pricing mechanism: Observations from PJM January 7, 2019 Isaac Newton Institute Cambridge

More information

ASSESSMENT OF TRANSMISSION CONGESTION IMPACTS ON ELECTRICITY MARKETS

ASSESSMENT OF TRANSMISSION CONGESTION IMPACTS ON ELECTRICITY MARKETS ASSESSMENT OF TRANSMISSION CONGESTION IMPACTS ON ELECTRICITY MARKETS presentation by George Gross Department of Electrical and Computer Engineering University of Illinois at Urbana-Champaign University

More information

Economic Dispatch. Quantitative Energy Economics. Anthony Papavasiliou 1 / 21

Economic Dispatch. Quantitative Energy Economics. Anthony Papavasiliou 1 / 21 1 / 21 Economic Dispatch Quantitative Energy Economics Anthony Papavasiliou Economic Dispatch 2 / 21 1 Optimization Model of Economic Dispatch 2 Equilibrium Model of Economic Dispatch Outline 3 / 21 1

More information

Crediting Wind and Solar Renewables in Electricity Capacity Markets: The Effects of Alternative Definitions upon Market Efficiency. The Energy Journal

Crediting Wind and Solar Renewables in Electricity Capacity Markets: The Effects of Alternative Definitions upon Market Efficiency. The Energy Journal Crediting Wind and Solar Renewables in Electricity Capacity Markets: The Effects of Alternative Definitions upon Market Efficiency The Energy Journal On-Line Appendix A: Supporting proofs of social cost

More information

ICAP Demand Curve. Zachary T. Smith Supervisor, ICAP Market Operations, NYISO. Intermediate ICAP Course. November 7-8, 2017 Rensselaer, NY 12144

ICAP Demand Curve. Zachary T. Smith Supervisor, ICAP Market Operations, NYISO. Intermediate ICAP Course. November 7-8, 2017 Rensselaer, NY 12144 ICAP Demand Curve Zachary T. Smith Supervisor, ICAP Market Operations, NYISO Intermediate ICAP Course November 7-8, 2017 Rensselaer, NY 12144 1 Objectives Upon the completion of this module, trainees should

More information

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing Ross Baldick Copyright c 2016 Ross Baldick www.ece.utexas.edu/ baldick/classes/394v/ee394v.html Title Page 1 of 33

More information

Resource Planning with Uncertainty for NorthWestern Energy

Resource Planning with Uncertainty for NorthWestern Energy Resource Planning with Uncertainty for NorthWestern Energy Selection of Optimal Resource Plan for 213 Resource Procurement Plan August 28, 213 Gary Dorris, Ph.D. Ascend Analytics, LLC gdorris@ascendanalytics.com

More information

Comparison of Performance-Based Capacity Models in ISO-NE and PJM June 2, 2016

Comparison of Performance-Based Capacity Models in ISO-NE and PJM June 2, 2016 Comparison of Performance-Based Capacity Models in ISO-NE and PJM June 2, 2016 Michael Borgatti, Director, RTO Services Gabel Associates, Inc. Michael.Borgatti@gabelassociates.com 732.296.0770 1 Goals

More information

In April 2013, the UK government brought into force a tax on carbon

In April 2013, the UK government brought into force a tax on carbon The UK carbon floor and power plant hedging Due to the carbon floor, the price of carbon emissions has become a highly significant part of the generation costs for UK power producers. Vytautas Jurenas

More information

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing Ross Baldick Copyright c 2017 Ross Baldick www.ece.utexas.edu/ baldick/classes/394v/ee394v.html Title Page 1 of 205

More information

Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing

Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing Organization of MISO States Response to the Midwest ISO October Hot Topic on Pricing I. Day Ahead and Real Time Energy and Ancillary Services Pricing Prices that Accurately Reflect the Marginal Cost of

More information

Supply function equilibrium, price caps, and investment 1

Supply function equilibrium, price caps, and investment 1 Supply function equilibrium, price caps, and investment 1 Andy Philpott EPOC University of Auckland. 1 EPOC Winter Workshop, July 6, 2012 Motivation Some recent discussion on Energy News about undesirable

More information

THE operators of power transmission networks are

THE operators of power transmission networks are ECONOMIC EVALUATION OF CONTROLLABLE DEVICES IN THE SLOVENIAN ELECTRIC POWER SYSTEM A CASE STUDY Christian Schaffner Swiss Federal Institute of Technology Zurich, Switzerland schaffner@eeh.ee.ethz.ch Rafael

More information

Pricing Transmission

Pricing Transmission 1 / 47 Pricing Transmission Quantitative Energy Economics Anthony Papavasiliou 2 / 47 Pricing Transmission 1 Locational Marginal Pricing 2 Congestion Rent and Congestion Cost 3 Competitive Market Model

More information

An Analysis of Long Run Power-Emissions Markets Interactions Under Alternative Emissions Allocation Rules. Benjamin F. Hobbs

An Analysis of Long Run Power-Emissions Markets Interactions Under Alternative Emissions Allocation Rules. Benjamin F. Hobbs An Analysis of Long Run Power-Emissions Markets Interactions Under Alternative Emissions Allocation Rules Benjamin F. Hobbs The Johns Hopkins University Jinye Zhao and Jong-Shi Pang Rennselaer Polytechnic

More information

Electricity Markets. Prof. Dr. G. Erdmann Fachgebiet Energiesysteme / TU Berlin Einsteinufer 25 / TA 8 (Room TA 033) D Berlin

Electricity Markets. Prof. Dr. G. Erdmann Fachgebiet Energiesysteme / TU Berlin Einsteinufer 25 / TA 8 (Room TA 033) D Berlin 1 Energy Economics: Electricity Markets Prof. Dr. G. Erdmann Fachgebiet Energiesysteme / TU Berlin Einsteinufer 25 / TA 8 (Room TA 033) D-10587 Berlin georg.erdmann@tu-berlin.de Internet: http://www.ensys.tu-berlin.de

More information

BASICS OF COMPETITIVE MARKETS FOR ELECTRICITY AUCTIONS - INTENT AUCTIONS - COMPONENTS. Basic Definitions Transactions Futures

BASICS OF COMPETITIVE MARKETS FOR ELECTRICITY AUCTIONS - INTENT AUCTIONS - COMPONENTS. Basic Definitions Transactions Futures BASICS OF COMPETITIVE MARKETS FOR ELECTRICITY Basic Definitions Transactions Futures 3/6/2003 copyright 1996 Gerald B. Sheble' 1 AUCTIONS - INTENT Open Exchange on a Common Product Open Knowledge on Price

More information

Congestion Revenue Rights Settlement Rule

Congestion Revenue Rights Settlement Rule California Independent System Operator Corporation Congestion Revenue Rights Settlement Rule Department of Market Monitoring August 18, 2009 I. Background Under nodal convergence bidding, the California

More information

Demand Curve Definitions

Demand Curve Definitions Demand Curve Definitions Presented by Andrew P. Hartshorn Market Structures Working Group Albany, NY August 27, 2003 Capacity $10,000 Capacity Price Energy+Reserves Energy Quantity 1 WHY A DEMAND CURVE?

More information

Overview of the Forward Capacity Market ( FCM ) ISO New England Inc.

Overview of the Forward Capacity Market ( FCM ) ISO New England Inc. Overview of the Forward Capacity Market ( FCM ) ISO New England Inc. Objectives of this Presentation 1. Introduce the ISO Presentation Series on the Forward Capacity Market 2. Present an OVERVIEW of the

More information

INVESTMENT OPPORTUNITIES AND TECHNOLOGY SELECTION: IPP VALUE PROPOSITION FOR ERCOT A WHITE PAPER BY WÄRTSILÄ

INVESTMENT OPPORTUNITIES AND TECHNOLOGY SELECTION: IPP VALUE PROPOSITION FOR ERCOT A WHITE PAPER BY WÄRTSILÄ INVESTMENT OPPORTUNITIES AND TECHNOLOGY SELECTION: IPP VALUE PROPOSITION FOR ERCOT A WHITE PAPER BY WÄRTSILÄ INVESTMENT OPPORTUNITIES AND TECHNOLOGY SELECTION: IPP VALUE PROPOSITION FOR ERCOT INDEX Executive

More information

Transactional Energy Market Information Exchange (TeMIX)

Transactional Energy Market Information Exchange (TeMIX) An OASIS Energy Market Information Exchange Technical Committee White Paper Transactional Energy Market Information Exchange (TeMIX) An Information Model for Energy Transactions in the Smart Grid By Edward

More information

Generation Adequacy through Call Option Obligations: Safe Passage to the Promised Land

Generation Adequacy through Call Option Obligations: Safe Passage to the Promised Land Generation Adequacy through Call Option Obligations: Safe Passage to the Promised Land Shmuel S. Oren University of California at Berkeley PSERC Research Tele-Seminar February 7, 2006 The Promised Land

More information

ISG206-SPAR REPORTING ON MAY 2018 SYSTEM PRICE ANALYSIS REPORT 1 SYSTEM PRICES AND LENGTH

ISG206-SPAR REPORTING ON MAY 2018 SYSTEM PRICE ANALYSIS REPORT 1 SYSTEM PRICES AND LENGTH Count of Settlement Periods -1+ -1 - -9-9 - -8-8 - -7-7 - -6-6 - -5-5 - -4-4 - -3-3 - -2-2 - -1-1 - - 1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-1 1 + PUBLIC ISG26-SPAR REPORTING ON MAY 218 ISSUE 31 PUBLISHED

More information

No-Load Definition: Educational Document

No-Load Definition: Educational Document No-Load: Past and Present PJM began as a power pool where generating companies agreed to centralized dispatch of their generation. PJM originally dispatched the pool using incremental cost curves developed

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent Of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions For The Imposition Of Mitigation Measures... 2 39.2.1

More information

Optimal Bidding Strategies in Electricity Markets*

Optimal Bidding Strategies in Electricity Markets* Optimal Bidding Strategies in Electricity Markets* R. Rajaraman December 14, 2004 (*) New PSERC report co-authored with Prof. Fernando Alvarado slated for release in early 2005 PSERC December 2004 1 Opening

More information

Hedging Risk. Quantitative Energy Economics. Anthony Papavasiliou 1 / 47

Hedging Risk. Quantitative Energy Economics. Anthony Papavasiliou 1 / 47 1 / 47 Hedging Risk Quantitative Energy Economics Anthony Papavasiliou 2 / 47 Contents 1 Forward Contracts The Price of Forward Contracts The Virtues of Forward Contracts Contracts for Differences 2 Financial

More information

Alberta Capacity Market

Alberta Capacity Market Alberta Capacity Market Comprehensive Market Design (CMD 1) Design Proposal Document Section 8: Supply Obligations and Performance Assessments Prepared by: Alberta Electric System Operator Date: January

More information

Resource Adequacy and Managing Unilateral Market Power in Wholesale Electricity Markets

Resource Adequacy and Managing Unilateral Market Power in Wholesale Electricity Markets Resource Adequacy and Managing Unilateral Market Power in Wholesale Electricity Markets Frank A. Wolak Department of Economics Stanford University Stanford, CA 94305-6072 wolak@zia.stanford.edu http://www.stanford.edu/~wolak

More information

Scarcity Pricing Market Design Considerations

Scarcity Pricing Market Design Considerations 1 / 49 Scarcity Pricing Market Design Considerations Anthony Papavasiliou, Yves Smeers Center for Operations Research and Econometrics Université catholique de Louvain CORE Energy Day April 16, 2018 Outline

More information

ISG202-SPAR REPORTING ON JANUARY 2018 SYSTEM PRICE ANALYSIS REPORT 1 SYSTEM PRICES AND LENGTH

ISG202-SPAR REPORTING ON JANUARY 2018 SYSTEM PRICE ANALYSIS REPORT 1 SYSTEM PRICES AND LENGTH Count of Settlement Periods -8 - -7-7 - -6-6 - -5-5 - -4-4 - -3-3 - -2-2 - -1-1 - - 1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9-1 1 + PUBLIC ISG22-SPAR REPORTING ON JANUARY 218 ISSUE 27 PUBLISHED 2 FEBRUARY 218

More information

Chapter 7 A Multi-Market Approach to Multi-User Allocation

Chapter 7 A Multi-Market Approach to Multi-User Allocation 9 Chapter 7 A Multi-Market Approach to Multi-User Allocation A primary limitation of the spot market approach (described in chapter 6) for multi-user allocation is the inability to provide resource guarantees.

More information

PJM Reliability Pricing Model

PJM Reliability Pricing Model Note: Presentation by B. Hobbs et al. on the dynamic analysis of the RPM is attached PJM Reliability Pricing Model Murty P. Bhavaraju PJM Interconnection IEEE/PES General Meeting Tampa, FL June 27, 2007

More information

California ISO October 1, 2002 Market Design Elements

California ISO October 1, 2002 Market Design Elements California October 1, 2002 Market Design Elements California Board of Governors Meeting April 25, 2002 Presented by Keith Casey Manager of Market Analysis and Mitigation Department of Market Analysis 1

More information

Valuation of Transmission Assets and Projects. Transmission Investment: Opportunities in Asset Sales, Recapitalization and Enhancements

Valuation of Transmission Assets and Projects. Transmission Investment: Opportunities in Asset Sales, Recapitalization and Enhancements Valuation of Transmission Assets and Projects Assef Zobian Cambridge Energy Solutions Alex Rudkevich Tabors Caramanis and Associates Transmission Investment: Opportunities in Asset Sales, Recapitalization

More information

Scarcity Pricing using ORDC for reserves and Pricing Run for Out- Of-Market Actions

Scarcity Pricing using ORDC for reserves and Pricing Run for Out- Of-Market Actions Scarcity Pricing using ORDC for reserves and Pricing Run for Out- Of-Market Actions David Maggio, Sai Moorty, Pamela Shaw ERCOT Public Agenda 1. History of the Operating Reserve Demand Curves (ORDC) at

More information

Southern California Edison Stakeholder Comments. Energy Imbalance Market 2 nd Revised Straw Proposal issued July 2, 2013

Southern California Edison Stakeholder Comments. Energy Imbalance Market 2 nd Revised Straw Proposal issued July 2, 2013 Southern California Edison Stakeholder Comments Energy Imbalance Market 2 nd Revised Straw Proposal issued July 2, 2013 Submitted by Company Date Submitted Paul Nelson (626) 302-4814 Jeff Nelson (626)

More information

83C Questions and Answers

83C Questions and Answers 83C Questions and Answers (1) Section 1.10 Could the Evaluation Team elaborate on what types of changes constitute a new project, including listing additional examples? For example, we have assumed that

More information

Policies to Mitigate Electric Price Increases PAPUC M June 2006 Comments of David M. Boonin, TBG Consulting,

Policies to Mitigate Electric Price Increases PAPUC M June 2006 Comments of David M. Boonin, TBG Consulting, Policies to Mitigate Electric Price Increases - Docket # M-00061957 Comments of David Magnus Boonin Before the Pennsylvania Public Utility Commission - Submitted June 15, 2006 I submit these comments as

More information

Financial Transmission and Auction Revenue Rights

Financial Transmission and Auction Revenue Rights Section 13 FTRs and ARRs Financial Transmission and Auction Revenue Rights In an LMP market, the lowest cost generation is dispatched to meet the load, subject to the ability of the transmission system

More information

Ramsey s Growth Model (Solution Ex. 2.1 (f) and (g))

Ramsey s Growth Model (Solution Ex. 2.1 (f) and (g)) Problem Set 2: Ramsey s Growth Model (Solution Ex. 2.1 (f) and (g)) Exercise 2.1: An infinite horizon problem with perfect foresight In this exercise we will study at a discrete-time version of Ramsey

More information

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Seventh Northwest Conservation and Electric Power Plan APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST Contents Introduction... 3 Key Findings... 3 Background... 5 Methodology... 7 Inputs and Assumptions...

More information

Forward Contracts and Capacity Markets: High Powered Incentives or Assets to be Stranded?

Forward Contracts and Capacity Markets: High Powered Incentives or Assets to be Stranded? Forward Contracts and Capacity Markets: High Powered Incentives or Assets to be Stranded? March 2, 2006 Jim Sheffield Vice President James.Sheffield@MorganStanley.com 404-949-4263 Overview Morgan Stanley

More information

Proposed Reserve Market Enhancements

Proposed Reserve Market Enhancements Proposed Reserve Market Enhancements Energy Price Formation Senior Task Force December 14, 2018 Comprehensive Reserve Pricing Reform The PJM Board has determined that a comprehensive package inclusive

More information

Flexible Ramping Product. Draft Final Technical Appendix

Flexible Ramping Product. Draft Final Technical Appendix Flexible Ramping Product Draft Final Technical Appendix January 25, 2016 Table of Contents 1. Introduction... 3 2. Generalized flexible ramping capacity model... 3 3. Flexible ramping product summary...

More information

Organized Regional Wholesale Markets

Organized Regional Wholesale Markets Organized Regional Wholesale Markets Paul M. Flynn Shareholder Wright & Talisman, P.C. Overview Organized Market Regions Goals of Regional Markets Energy Markets Congestion and Hedges Market Power and

More information

INTRODUCTION - Price volatility is a measure of the dispersion in prices observed over a time period. - Price volatility in the electricity market is

INTRODUCTION - Price volatility is a measure of the dispersion in prices observed over a time period. - Price volatility in the electricity market is Day-ahead market price volatility analysis in deregulated electricity markets. M.Benini, A. Venturini P. Pelacchi, Member, IEEE, M. Marracci CESI - T&D Network Milan, Italy Electric Systems and Automation

More information

Electricity trading and risk management in liberalised market

Electricity trading and risk management in liberalised market www.pwc.com/jp Electricity trading and risk management in liberalised market PricewaterhouseCoopers Agenda Page 1 Current electricity trading in Japan 1 2 Evolution of trading in a deregulated market 5

More information

Evaluating Electricity Generation, Energy Options, and Complex Networks

Evaluating Electricity Generation, Energy Options, and Complex Networks Evaluating Electricity Generation, Energy Options, and Complex Networks John Birge The University of Chicago Graduate School of Business and Quantstar 1 Outline Derivatives Real options and electricity

More information

Clearing Manager. Financial Transmission Rights. Prudential Security Assessment Methodology. 18 September with September 2015 variation

Clearing Manager. Financial Transmission Rights. Prudential Security Assessment Methodology. 18 September with September 2015 variation Clearing Manager Financial Transmission Rights Prudential Security Assessment Methodology with September 2015 variation 18 September 2015 To apply from 9 October 2015 Author: Warwick Small Document owner:

More information

C2-102 COMMON NORDIC BALANCE MANAGEMENT. K.LINDSTRÖM FINGRID (Finland)

C2-102 COMMON NORDIC BALANCE MANAGEMENT. K.LINDSTRÖM FINGRID (Finland) 21, rue d'artois, F-75008 Paris http://www.cigre.org C2-102 Session 2004 CIGRÉ COMMON NORDIC BALANCE MANAGEMENT O.GJERDE* STATNETT (Norway) F.WIBROE ELTRA (Denmark) J-E. FISCHER ELKRAFT (Denmark) K.LINDSTRÖM

More information

Forward Contracts and Generator Market Power: How Externalities Reduce Benefits in Equilibrium

Forward Contracts and Generator Market Power: How Externalities Reduce Benefits in Equilibrium Forward Contracts and Generator Market Power: How Externalities Reduce Benefits in Equilibrium Ian Schneider, Audun Botterud, and Mardavij Roozbehani November 9, 2017 Abstract Research has shown that forward

More information

Organization of Restructured Wholesale Power Markets

Organization of Restructured Wholesale Power Markets Organization of Restructured Wholesale Power Markets Important Acknowledgement: These notes on Kirschen/Strbac (Chapter 3, Power System Economics, 2004) are based on slides prepared by Daniel Kirschen

More information

Wholesale Energy Markets Overview. Jeff Klarer Market Strategist

Wholesale Energy Markets Overview. Jeff Klarer Market Strategist Wholesale Energy Markets Overview Jeff Klarer Market Strategist Wisconsin Electric Utility Fuel Rules (PSC-116) Fuel Cost Components Fuel for generation (coal, natural gas, uranium, etc.) Energy market

More information

Transactional Energy Market Information Exchange (TeMIX)

Transactional Energy Market Information Exchange (TeMIX) An OASIS Energy Market Information Exchange Technical Committee White Paper Transactional Energy Market Information Exchange (TeMIX) An Information Model for Energy Transactions in the Smart Grid By Edward

More information

California ISO. Allocating CRR Revenue Inadequacy by Constraint to CRR Holders. October 6, Prepared by: Department of Market Monitoring

California ISO. Allocating CRR Revenue Inadequacy by Constraint to CRR Holders. October 6, Prepared by: Department of Market Monitoring California Independent System Operator Corporation California ISO Allocating CRR Revenue Inadequacy by Constraint to CRR Holders October 6, 2014 Prepared by: Department of Market Monitoring TABLE OF CONTENTS

More information

Interconnector participation in Capacity Remuneration Mechanisms

Interconnector participation in Capacity Remuneration Mechanisms Interconnector participation in Capacity Remuneration Mechanisms A REPORT PREPARED FOR ENERGY NORWAY January 2014 Frontier Economics Ltd, London. January 2014 Frontier Economics i Interconnector participation

More information

MRTU. CRR Settlements. CRR Educational Class #10

MRTU. CRR Settlements. CRR Educational Class #10 MRTU CRR Settlements CRR Educational Class #10 Contents Why is CRR Settlements process important to understand Definition of LMP and CRR Types of CRRs: Obligation vs Option Point to Point and Multi Point

More information

ALBERTA MARKET RE-DESIGN CAPACITY MARKET DESIGN AND IMPLEMENTATION

ALBERTA MARKET RE-DESIGN CAPACITY MARKET DESIGN AND IMPLEMENTATION ALBERTA MARKET RE-DESIGN CAPACITY MARKET DESIGN AND IMPLEMENTATION November 30, 2016 www.poweradvisoryllc.com To: Power Advisory Clients and Colleagues From: Kris Aksomitis, Jason Chee-Aloy, Brenda Marshall,

More information

Regulatory and Tax Treatment of Electric Resources

Regulatory and Tax Treatment of Electric Resources Regulatory and Tax Treatment of Electric Resources Stan Hadley and Eric Hirst, Oak Ridge National Laboratory Integrated resource planning (IRP) focuses on providing customer energy-service needs at the

More information

THE ELECTRIC HONEYPOT: THE PROFITABILITY OF DEREGULATED ELECTRIC GENERATION COMPANIES By Edward Bodmer

THE ELECTRIC HONEYPOT: THE PROFITABILITY OF DEREGULATED ELECTRIC GENERATION COMPANIES By Edward Bodmer THE ELECTRIC HONEYPOT: THE PROFITABILITY OF DEREGULATED ELECTRIC GENERATION COMPANIES By Edward Bodmer EXECUTIVE SUMMARY Purpose and Conclusions of the Study This report presents the results of an investigative

More information

Working Paper: Cost of Regulatory Error when Establishing a Price Cap

Working Paper: Cost of Regulatory Error when Establishing a Price Cap Working Paper: Cost of Regulatory Error when Establishing a Price Cap January 2016-1 - Europe Economics is registered in England No. 3477100. Registered offices at Chancery House, 53-64 Chancery Lane,

More information

On Investment Decisions in Liberalized Electrcity Markets: The Impact of Spot Market Design

On Investment Decisions in Liberalized Electrcity Markets: The Impact of Spot Market Design On Investment Decisions in Liberalized Electrcity Markets: The Impact of Spot Market Design Gregor Zöttl, University of Munich, Cambridge, November 17, 2008 Wholesale Prices for Electricity, Germany (EEX)

More information

Assessment of the Buyer-Side Mitigation Exemption Test for the Hudson Transmission Partners Project

Assessment of the Buyer-Side Mitigation Exemption Test for the Hudson Transmission Partners Project Assessment of the Buyer-Side Mitigation Exemption Test for the Hudson Transmission Partners Project by: Potomac Economics, Ltd. November 6, 2012, revised January 16, 2014 revised February 21, 2014 Table

More information

Financial Risk Management

Financial Risk Management Financial Risk Management Prof. Leigh Tesfatsion, ISU NOTE: This presentation makes use of materials from N. Yu, A. Somani, and L. Tesfatsion, Financial Risk Management in Restructured Wholesale Power

More information

Regional Transmission Organization Frequently Asked Questions

Regional Transmission Organization Frequently Asked Questions 1. The CRA analysis showed greater trade benefits to the Entergy region from joining SPP rather than joining MISO. Did Entergy re-do the CRA analysis? No. The CRA analysis was a key component of the Entergy

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent Of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions For The Imposition Of Mitigation Measures... 2 39.2.1

More information

The Sharing Economy for the Smart Grid

The Sharing Economy for the Smart Grid The Sharing Economy for the Smart Grid Kameshwar Poolla UC Berkeley PSERC Webinar February 7, 2017 February 7, 2017 0 / 31 Shared Electricity Services The New Sharing Economy cars, homes, services,...

More information

Design of the National Electricity Market. Fundamentals of the Australian Competitive Electricity Industry August 2005 CEEM, 2005

Design of the National Electricity Market. Fundamentals of the Australian Competitive Electricity Industry August 2005 CEEM, 2005 Design of the National Electricity Market Fundamentals of the Australian Competitive Electricity Industry 17-19 August 2005 CEEM, 2005 Electricity market models Gross pool (eg NEM): Temporal & location

More information

Introduction to transmission network assessment methodology: the ENTSO-E CBA methodology and the PCI selection process.

Introduction to transmission network assessment methodology: the ENTSO-E CBA methodology and the PCI selection process. Introduction to transmission network assessment methodology: the ENTSO-E CBA methodology and the PCI selection process Péter Kaderják SEERMAP training March 7, 2017 Athens, Greece Overview The policy context

More information

Authors: George Katsigiannakis; Shanthi Muthiah; Himanshu Pande; Rachel Green; and Josh Ghosh

Authors: George Katsigiannakis; Shanthi Muthiah; Himanshu Pande; Rachel Green; and Josh Ghosh WHITEPAPER How ISO-NE s Pay-for-Performance Initiative Will Shake Up New England Authors: George Katsigiannakis; Shanthi Muthiah; Himanshu Pande; Rachel Green; and Josh Ghosh Executive Summary Regional

More information

Best Practices in Resource Adequacy

Best Practices in Resource Adequacy Best Practices in Resource Adequacy Presented at PJM Long Term Capacity Issues Symposium Johannes Pfeifenberger and Kathleen Spees www.brattle.com January 27, 2010 Copyright 2010 The Brattle Group, Inc.

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 39. Market Power Mitigation Procedures... 2 39.1 Intent of CAISO Mitigation Measures; Additional FERC Filings... 2 39.2 Conditions for the Imposition of Mitigation Measures... 2 39.2.1

More information

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing

Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing Course notes for EE394V Restructured Electricity Markets: Locational Marginal Pricing Ross Baldick Copyright c 2018 Ross Baldick www.ece.utexas.edu/ baldick/classes/394v/ee394v.html Title Page 1 of 160

More information

Designing Competitive Energy Markets. Overview. Energy Legislation. Power Industry Evolution

Designing Competitive Energy Markets. Overview. Energy Legislation. Power Industry Evolution Designing Competitive Energy Markets Dr. Judith Cardell Office of Economic Policy Federal Energy Regulatory Commission October 14, 1999 judith.cardell@ferc.fed.us Overview Evolution of US electric power

More information

Stochastic Loss of Load Study for the 2011 Integrated Resource Plan

Stochastic Loss of Load Study for the 2011 Integrated Resource Plan November 18, 2010 Stochastic Loss of Load Study for the 2011 Integrated Resource Plan INTRODUCTION PacifiCorp evaluates the desired level of capacity planning reserves for each integrated resource plan.

More information

10 Economic Uncertainty Analysis Probabilistic Analysis and Sensitivities Chapter Overview... 1

10 Economic Uncertainty Analysis Probabilistic Analysis and Sensitivities Chapter Overview... 1 Table of Contents Economic Uncertainty Analysis....0 Chapter Overview.... Probabilistic Analysis with Scenarios..... Methodology...... Determination of Highest Impact Factors...... Combinations of Highest

More information

Chapter 5 Fiscal Policy and Economic Growth

Chapter 5 Fiscal Policy and Economic Growth George Alogoskoufis, Dynamic Macroeconomic Theory, 2015 Chapter 5 Fiscal Policy and Economic Growth In this chapter we introduce the government into the exogenous growth models we have analyzed so far.

More information

Financial Economics Field Exam August 2011

Financial Economics Field Exam August 2011 Financial Economics Field Exam August 2011 There are two questions on the exam, representing Macroeconomic Finance (234A) and Corporate Finance (234C). Please answer both questions to the best of your

More information

Carbon Markets and Mexico Key Issues for Market Design

Carbon Markets and Mexico Key Issues for Market Design Carbon Markets and Mexico Key Issues for Market Design Mark C. Trexler Director of Climate Strategies and Markets DNV Climate Change Service North America 24 August 2009 Key Points It s All About the Price

More information

For the Efficiency Maine Trust October 15, 2009 Eric Belliveau, Optimal Energy Inc.

For the Efficiency Maine Trust October 15, 2009 Eric Belliveau, Optimal Energy Inc. DSM Economics For the Efficiency Maine Trust October 15, 2009 Eric Belliveau, Optimal Energy Inc. DSM Economics - Overview Why? Basics of Economics Benefits Costs Economic Test Overviews Economics of Sample

More information

Energy markets. Academic year Damien Ernst University of Liège

Energy markets. Academic year Damien Ernst University of Liège Energy markets Academic year 2016-2017 Damien Ernst University of Liège Email: dernst@ulg.ac.be 1 Energy markets Goal of this class: to learn about energy markets. Class every Friday between 2pm and 6pm,

More information

ECON 3020 Intermediate Macroeconomics

ECON 3020 Intermediate Macroeconomics ECON 3020 Intermediate Macroeconomics Chapter 5 A Closed-Economy One-Period Macroeconomic Model Instructor: Xiaohui Huang Department of Economics University of Virginia c Copyright 2014 Xiaohui Huang.

More information

The Economics and Financing of Distributed Generation Investment. Budapest, Hungary November 17, 2016

The Economics and Financing of Distributed Generation Investment. Budapest, Hungary November 17, 2016 The Economics and Financing of Distributed Generation Investment Budapest, Hungary November 17, 2016 Topics to Cover How to Finance Distributed Generation Investments 1 Importance of financial aspects

More information

Generation investment in a liberalised electricity market. 28 March 2008

Generation investment in a liberalised electricity market. 28 March 2008 Generation investment in a liberalised electricity market 28 March 2008 Darryl Biggar Australian Competition and Consumer Commission Australian Energy Regulator Investment in electricity markets Demand

More information

Tom Chamberlin. Tom Chamberlin. Brian DeBruin Forced Outage Risk Solutions, Managing Director Aon Global Power. Marina Nadirova Product Executive

Tom Chamberlin. Tom Chamberlin. Brian DeBruin Forced Outage Risk Solutions, Managing Director Aon Global Power. Marina Nadirova Product Executive NEW CONTINGENT OUTAGE AND CAPACITY PERFORMANCE COVERAGE Tom Chamberlin Manager of Insurance and Member Financial Services Old Dominion Electric Cooperative Brian DeBruin Forced Outage Risk Solutions, Managing

More information

ENSURING ADEQUATE GENERATION SUPPLY IN COMPETITIVE ELECTRICITY MARKETS 1. INTRODUCTION. Dr. Alex Papalexopoulos Fellow, IEEE

ENSURING ADEQUATE GENERATION SUPPLY IN COMPETITIVE ELECTRICITY MARKETS 1. INTRODUCTION. Dr. Alex Papalexopoulos Fellow, IEEE ENSURING ADEQUATE GENERATION SUPPLY IN COMPETITIVE ELECTRICITY MARKETS Dr. Alex Papalexopoulos Fellow, IEEE ECCO International, Inc. San Francisco, CA alexp@eccointl.com 1. INTRODUCTION A key problem policy

More information

Estimating Capacity Benefits of the AC Transmission Public Policy Projects

Estimating Capacity Benefits of the AC Transmission Public Policy Projects Memorandum TO: NYISO Board of Directors FROM: David B. Patton and Pallas LeeVanSchaick DATE: RE: Estimating Capacity Benefits of the AC Transmission Public Policy Projects A. Introduction In the second

More information

Strategic Policy Choice in State-Level Regulation: The EPA s Clean Power Plan (Appendix B)

Strategic Policy Choice in State-Level Regulation: The EPA s Clean Power Plan (Appendix B) Strategic Policy Choice in State-Level Regulation: The EP s Clean Power Plan (ppendix B) James B. Bushnell, Stephen P. Holland, Jonathan E. Hughes, and Christopher R. Knittel December 2014 CEEPR WP 2014-009

More information

Long-Term Reliability Assessment

Long-Term Reliability Assessment Long-Term Reliability Assessment Key Findings and Long-Term Issues John Moura, Director of Reliability Assessment Topics Covered Today Background on NERC s Long-Term Reliability Assessment Emerging and

More information

Determination of Market Clearing Price in Pool Markets with Elastic Demand

Determination of Market Clearing Price in Pool Markets with Elastic Demand Determination of Market Clearing Price in Pool Markets with Elastic Demand ijuna Kunju K and P S Nagendra Rao Department of Electrical Engineering Indian Institute of Science, angalore 560012 kbijuna@gmail.com,

More information

Welfare implications of capacity markets in the electricity sector

Welfare implications of capacity markets in the electricity sector Welfare implications of capacity markets in the electricity sector Raúl Bajo-Buenestado Baker Institute Center for Energy Studies, Rice University Electricity markets: Best practice and restructuring in

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: June 14, 2018 Re: Decision on congestion

More information

Transmission Loss Factor Methodology

Transmission Loss Factor Methodology Transmission Loss Factor Methodology Discussion Paper Operations & Reliability Draft February 9, 2005 Table of Contents 1. Introduction...3 1.1 Legislative Direction.....3 1.2 Goal and Objectives... 3

More information

Stakeholder Comment Matrix Harry Allen-Eldorado 500 kv line project December 12, 2014

Stakeholder Comment Matrix Harry Allen-Eldorado 500 kv line project December 12, 2014 The ISO received comments on the CAISO economic analysis results stakeholder meeting discussion held on November 20, 2014 1 from the following: 1. Bay Area Municipal Transmission group (BAMx) 2. California

More information

Final Exam Solutions

Final Exam Solutions 14.06 Macroeconomics Spring 2003 Final Exam Solutions Part A (True, false or uncertain) 1. Because more capital allows more output to be produced, it is always better for a country to have more capital

More information

Commodity and Energy Markets

Commodity and Energy Markets Lecture 3 - Spread Options p. 1/19 Commodity and Energy Markets (Princeton RTG summer school in financial mathematics) Lecture 3 - Spread Option Pricing Michael Coulon and Glen Swindle June 17th - 28th,

More information

December 9, City of Farmington Integrated Resource Planning (IRP)

December 9, City of Farmington Integrated Resource Planning (IRP) December 9, 2016 City of Farmington Integrated Resource Planning (IRP) Restricted Siemens AG 2013 All rights reserved. Answers for infrastructure and cities. Pace Global Disclaimer This Report was produced

More information

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy 2011 IRP Public Input Meeting October 5, 2010 Pacific Power Rocky Mountain Power PacifiCorp Energy Agenda Morning Session IRP Schedule Update Energy Gateway Transmission Construction Update and Evaluation

More information