PERMIT TO WORK PROCEDURE

Size: px
Start display at page:

Download "PERMIT TO WORK PROCEDURE"

Transcription

1 KING S COLLEGE LONDON Directorate of Estates & Facilities PERMIT TO WORK PROCEDURE Document No: EF-ASU-02-PR01 Version No: E-Controlled Prepared By: Nicola Barrett Issue Date: Nov 2016 Review Date: Nov 2017 Approved By: David Lissah Table of Contents 1. Introduction Scope Definitions Requirements Listing a Company KCL Contractor Inductions Contractor Asbestos Awareness Training Assessing the Task/s Permission to Access Permits Permits to Work Permit Requests Permission to Access Permits Permits to Work Permit Process Issuing Permit Acceptance Permit Handback - Contractor Permit Handback KCL (Final Sign Off) Re-issue Emergency Callouts... 9 Document No: EF-ASU-02-PR01 1

2 9. Record Keeping Permits Risk Assessments and Method Statements (RAMS) Organisation and Contractor Information Competency for Permit Issuers and Authorisers Key Performance Indicators (KPIs) & Inspections Key Performance Indicators Issued Permit Inspection Criteria Site Inspection Criteria... Error! Bookmark not defined. 12. Document Review Appendix A: Definition of Construction Work Appendix B: Competency Matrix Appendix C: Work Flow Appendix D: Permit Guidance Note Version Date Details Name V3 Nov 2016 Clarification on roles David Lissah Document No: EF-ASU-02-PR01 2

3 1. Introduction This procedure reflects the requirements contained within HSG159 (HSE Management of Contractors Guidance), the Health and Safety at Work etc Act 1974 and the Management of Health and Safety at Work Regulations The purpose of this procedure is to provide guidance in the use of the Permit to Work Manager (PTWM) system within King s College London (KCL) and covers both the activities of contractors and directly employed labour This document covers in detail the use of the PTWM system which supports the fundamental safety requirements needed to control the vast majority of tasks undertaken by KCL and appointed contractors. 2. Scope This procedure is for all works and activities that are undertaken within KCL owned and occupied areas where KCL are the Landlord/Duty holders. This procedure does not cover spaces that are managed or are under the responsibility of others including, Segregated Project Sites under CDM, Bouygues, Guy s & St Thomas NHS Trust, King s College Hospital NHS Trust and South London & Maudsley NHS Trust. 3. Definitions Contractor means anyone the university employs to do work of any kind who is not an employee and in the course of his or her business may carry out work for the university or a university employee (e.g. maintenance, construction work, cleaning, security etc.). Contract (or) Manager or university representative means anyone managing the contracted works and/or the Contractor. Some examples are Project Managers, Local Estates Managers, Facilities Managers, Site Supervisors and Permit Authorisers etc. Construction Work any works as defined in Appendix A. As defined by the CDM regulations, it does not include: Putting up and taking down marquees and similar tents designed to be re-erected at various locations. General maintenance of fixed plant, except when it is part of other construction work or involves substantial dismantling or alteration of fixed plant large enough to be a structure in its own right, e.g. large boiler. Tree planting and general horticultural work. Positioning and removal of lightweight movable partitions, such as those used to divide open-plan offices or to create exhibition stands and displays. Permit Requestor are persons working on behalf of KCL who are instructing works or contractor activity. Permits cannot be requested by Contractors. Permit Issuer are those persons that are authorised to issue Permission to Access for low risk activities and those which do not require the level of controls necessary for permits to work. Permit Authoriser are those that are deemed competent to issue permits for high risk activities that require additional control measures as provided by Risk Assessments, Method Statements and task specific permits. They will typically be employed by Estates & Facilities Asset Management. 4. Requirements 4.1 Listing a Company University staff or representatives responsible for appointing contractors (including principal contractors) must ensure that those appointed have the skills, knowledge training and experience to carry out the work in a way that secures the health and safety of others including University staff, students and visitors. If those appointed are an organisation, Document No: EF-ASU-02-PR01 3

4 they must also have the appropriate organisational capability. Those making the appointments must establish that those they appoint have these qualities before appointing them. Before a contractor can be issued a Permit to Work (PTW) or Permission to Access Permit (PTA) their company details must be entered onto the PTWM. To add a company, the KCL Responsible Person (person employing/instructing the company) must ask the company to complete forms F003 & FO64 (often combined as one document), the responsible person must then send the complete forms to assurance-estates@kcl.ac.uk This information will be reviewed and uploaded to the PTWM system within 48 hours if satisfactory 1. The company s Insurance documents must also be supplied, they will include: Employers Liability 5million Public Liability 5million 2 Professional Indemnity insurance of 5million may also be required (e.g. for those undertaking work which includes advising, designing or specifying products/equipment). 4.2 KCL Contractor Inductions Each attending contractor must complete the KCL Directorate s Site Induction Presentation, sign & date the induction acknowledgement form. Click Here for Link. There is a separate induction for each geographical campus/outlier, all inductions relevant to the activity must be completed. Each contractor must complete an induction every 12 months. At least 48 hours must be allowed for the upload of contactors information onto the permit to work system prior to requesting a permit. Contractors must send their completed inductions to assurance-estates@kcl.ac.uk. No works can be conducted by an individual who does not have a valid induction recorded on PTWM. 4.3 Contractor Asbestos Awareness Training Evidence to confirm the provision of asbestos awareness training of contractors whose work could foreseeably disturb the fabric of a building and expose them to asbestos or to those who supervise or influence the work may be requested following submission of inductions. This includes, but is not limited to: demolition workers; construction workers; general maintenance staff; electricians; plumbers; gas fitters; painters and decorators; joiners; shop fitters; plasterers; roofers; heating and ventilation engineers; 1 Please note that this review does not trigger the addition of the company on other College systems including as KCeP 2 A basic review of insurance coverage is completed for compliance to the College s minimum standards ( It is the responsibility of the KCL Responsible Person to ensure that coverage and exclusions of policies are appropriate for the work which is being instructed. Document No: EF-ASU-02-PR01 4

5 telecommunication engineers; computer and data installers; fire and burglar alarm installers; Architects, building surveyors and other such professionals. All contractors working at KCL are mandated to receive and acknowledge the F064 form notifying of the presence of asbestos across the Estate and the requirement for asbestos awareness training to be provided to employees on an annual basis. 5. Assessing the Task/s The Permit to Work system has been designed to assist in the management of contractors and contractor activities by issuing and recording Permission to Access Permits or Permits to Work. The permits available are: Type Permission to Access Permits General Work Permit Hot Works Permit Fire Alarm Isolation Permit LOTO/Isolation and Line Breaking Permit Working at Heights Permit Max Duration 5 working days 5 working days 1 working day 1 working day Comments Final Authorisation Notice Non-intrusive Works, Quotations or Visual Inspections, PAT testing, works involving no tools, plant, equipment or chemicals Works involving accessing the fabric of the building including ceiling voids, all intrusive works (external and internal). General building/maintenance works, asbestos or structural surveys or works Hot works may require additional control measures including fire alarm detector isolations. See below Special arrangements must be made with KCL Asset Management, H&SS and College Insurers if isolation is beyond 1 shift 31 days Must be formally reviewed and re-issued every 31 days if the isolation persists beyond this validity period 5 working days Daily pre-use checks to be recorded separated by the person in control of the works or their nominated deputy. Nominated Permit Issuers Nominated Permit Authorisers Asset Management Nominated Permit Authorisers Asset Management Nominated Permit Authorisers Asset Management Nominated Permit Authorisers Asset Management Nominated Permit Authorisers 5 working days 5 working days 5 working days 5 working days 5 working days 5 working days Before Permission to Access or Permits to Work can be raised, the task must be assessed by the Permit Requestor to ensure that the appropriate permit is applied for. The Permit Issuer or Permit Authoriser/s is to verify that the appropriate permit is being requested. With the exception Permission to Access Permits and General Work Permits, all permits must be issued by the Estates & Facilities Asset Management Team The asbestos register must be checked by the Permit Requestor before a permit is requested. If there is insufficient evidence on the asbestos register then an appropriate asbestos survey must be performed and the report received prior to the permit request being submitted. Please see E&F Procedure for Asbestos Management. Asbestos information must be issued to the relevant contractor by the Permit Requestor. The Permit Issuer or Permit Authoriser/s (as applicable) will perform a final check of the asbestos register as part of the permit issuing process and confirm that the contractor has been issued with the relevant asbestos information. Document No: EF-ASU-02-PR01 5

6 A permit request will be refused if no asbestos information has been provided by the Permit Requestor to the contractor. DOES THE TASK INVOLVE: Access to ceiling voids High level access equipment (scaffold, MEWPs, mobile towers) Dusts & vapours Hot works and flammables Fire alarm isolation Isolation of electrical or mechanical systems Drilling or breaking out Other complex tasks e.g. roof work, confined spaces etc NO YES PERMISION TO ACCESS PERMIT PERMIT TO WORK 5.1 Permission to Access Permits Permission to Access Permits are used for allowing contractors access to college premises and carry out low risk activities which do not include works such as those listed above. Permission to Access Permits must not be used where a Permit to Work is required. Permission to Access Permits does not require the level of controls for works involving the above but still gives College Campus and Security Teams visibility as to which contractors are on site, when and where. At least 5 days notice must be given for all Permission to Access requests. There must be a clear understanding of where contractors are allowed to access and must identify restricted areas. Permission to Access Permits are managed locally and can be provided by Permit Issuers. Document No: EF-ASU-02-PR01 6

7 5.2 Permits to Work A Permit to Work is issued when contractor or directly employed labour (including the Asset Management (including Asset Maintenance and Asset Improvement Teams and other departments) tasks involve higher risk activities such as those detailed in Section 5 above. Additional controls will be required and these may include permits for isolations, inspections, hot works or specialist training and equipment. Works must be properly planned and sufficient time must be allocated to prepare for the task. Before issuing a Work Permit, the Permit Requestor must ensure that the contractor has completed a Risk Assessment and Method Statement (RAMS) suitable and sufficient for the task at hand. RAMS must be checked and accepted by the permit requestor and passed to and relevant Asset Management Team at least 5 working days prior to the activity starting. RAMS MUST be agreed prior to the works taking place and must be provided in electronic format. Permits to work can only be issued by Permit Authorisers. Permit Authorisers are those that are deemed competent to issue permits for high risk activities that require additional control measures as provided by Risk Assessments, Method Statements and task specific permits. Permission to Access must not be issued for intrusive or complex works such as those listed in section 5 above. 6. Permit Requests Requests for all permit types must be made by the Permit Requestor at least 5 working days prior to the activity starting. The permit requestor is accountable for ensuring that the correct permit has been applied for and for ensuring that the RAMS supplied are fully developed for the task to be undertaken. The asbestos register must be checked by the Permit Requestor prior to the submission of RAMS, and if required a management, refurbishment or demolition asbestos survey must be performed and actioned as necessary. Relevant asbestos information must be included as part of the permit request application. The permit requestor is responsible for ensuring that the relevant building users, Security and Operations Teams have been suitably notified of the planned activity and the necessary approvals have been sought before a permit is applied for. 6.1 Permission to Access Permits Any permission to access permit request submitted which is found to require a permit to work will be refused and will require re-submitting by the permit requestor via the appropriate channel and with the appropriate timescale. Permit Requestor Example Permit Issuer Asset Management, Service visit, Water Asset Management (Maintenance & Improvement) Sustainability & Assurance sampling, Quotation/Scoping visit Operations/Facilities Pest control visit Campus Operations Capital Projects King s Venues/King s Food Faculty/Departmental Visual inspection, noise survey Filming, catering repair Equipment servicing, exhibitions Capital Projects Campus Operations Asset Management Campus Operations Asset Management (back-up) Campus Operations Asset Management Document No: EF-ASU-02-PR01 7

8 Permit Requestor Example Permit Issuer Restricted/Controlled Spaces Any access within a lab (may be used in conjunction with PTW depending on activity) PTWM Authorised Lab Manager Asset Management with written authority from responsible Lab Manager. 6.2 Permits to Work RAMS must be prepared by contractors for all Permit to Work Requests and must be checked and accepted by the Permit Requestor to ensure that they are suitable and sufficient for the task by the KCL employee instructing the works prior to submission to the Permit Authoriser. RAMS submitted by sub-contractors cannot be accepted. Principal contractors must prepare RAMS which cover off sub-contractor activity and include sub-contractor RAMS as an addendum in order to confirm their acceptance. These must be issued to the relevant Asset Management Team at least 5 working days before the activity is due to start. Group address for the three teams have been produced to simplify the submission process: - Denmark Hill (Including Champion Hill & Sports Grounds) - denmarkhillplanner@kcl.ac.uk - Guy s Campus (Including Great Dover Street Apartments, Wolfson House & St Thomas ) - guysplanner@kcl.ac.uk - Strand Campus (Including Waterloo & Stamford Street apartments) - strandplanner@kcl.ac.uk All risk assessments, method statements/plan of works must be submitted electronically and agreed prior to any activity starting. All permits to work must include pre-work asbestos register checks (made by the Permit Requestor, confirmed by Permit Issuer), arrangements for suitable and sufficient supervision of work & post work review commensurate with the activity covered by the permit. 7. Permit Process 7.1 Issuing Once the permit details and RAMS, asbestos register and conditions have been agreed, the permit shall be authorised and issued. Contractors will be issued with a system notification to confirm permit approval by the relevant Permit Requestor 24hrs prior to the works. RAMS must be uploaded to each permit to work issued. Contractors must adhere to the conditions within the permit and must not deviate from the method statement, any deviation must be recorded and agreed prior to the deviation occurring. 7.2 Permit Acceptance Before a contractor may commence any activity, the permit must be accepted by the contractor in charge of the work. This is completed using the "Contractors Zone" tab. For out of hours works, this can be completed by the relevant Security Teams. This is a legal declaration stating that the contractor responsible for the permit accepts the conditions within the permit itself and any associated documentation/arrangements. The contractor is then able to commence with the work covered by the permit using the named persons on the permit. A permit is not valid until the contractor acceptance has been completed. Document No: EF-ASU-02-PR01 8

9 7.3 Permit Handback - Contractor Once the work/activity is complete or when the permit expires (whichever is first), the permit must be handed back (either electronically (preferred) or manually). Handing back provides an opportunity for the work/activity to be reviewed by the contractor as well as confirmation that the work/activity has been completed and confirmation that site has been handed back in a safe condition. Any issues with the work area that need to be addressed should be recorded by this process. Failure of a contractor to return permits to the applicable issuing Permit Office will be reviewed and may result in corrective action being taken including suspension from works for individuals or companies with multiple non-returns. 7.4 Permit Handback KCL (Final Sign Off) Upon completion of the permit acceptance and handback, the permit must be formally closed off electronically by the permit issuer. For all permits to work (except General Permit to Work) this must include a visual check of the work area. 7.5 Re-issue A permit must be reviewed and re-issued by a Permit Issuer or Permit Approver in the following situations: Any change to or re-issue of the RAMS Change to the work start and finish time. Change to the work group Prior to the extension of any permit due to expire in line with the maximum validity periods e.g. line breaking/isolation. If a permit is re-issued, the original permit must be handed back and signed off as per sections 7.3 and 7.4 above. 8. Emergency Callouts Dispensation for the timescales detailed above can be gained in the event of an unplanned emergency such as Laboratory or Catering freezer repairs, Gas emergencies etc, lift breakdowns. It is advised that contractors utilised for emergency attendances prepare a series of generic risk assessments and method statements for the scope of their contract appointment for rapid submission in the event of a call-out. These would then require on-site review by the nominated contractor engineer at the time of the attendance. A stock of engineers should be maintained with valid inductions on the PTWM system to ensure site familiarity in the event of an emergency call-out. Suitable and sufficient arrangements must be put in place to ensure the monitoring and supervision of all contractors attending on an emergency basis. Where emergency call-outs occur during the College s normal working hours, the PTWM system must be used. 9. Record Keeping 9.1 Permits Once the contractors task has been completed and the permit is formerly closed, it will be archived and stored electronically for a period of 5 years. Permits raised for activities which involve working with asbestos shall be kept indefinitely. During this time, permits can be recalled for the purposes of auditing, the system will not allow authorised or closed permits to be altered or amended. Document No: EF-ASU-02-PR01 9

10 9.2 Risk Assessments and Method Statements (RAMS) All risk assessments and method statements electronically attached to a permit will be available for viewing and auditing until such time the permit archive period expires. All RAMS must be checked to ensure that they are suitable and sufficient for the task by those instructing the works prior to submission to the Permit Authoriser. RAMS submitted by sub-contractors cannot be accepted. Principal contractors must prepare RAMS which cover off sub-contractor activity and include sub-contractor RAMS as an addendum in order to confirm their acceptance. Whilst the permit remains on the system so will all associated control and management documents. Risk Assessments & Method statements for permit to work requests must be submitted by the Permit Requestor at least 5 working days prior to works starting. 9.3 Organisation and Contractor Information Organisation and contractors details shall remain on the Permit to Work system for the duration of their employment by KCL. Organisations or contractors which have not been employed by KCL for a period of more than 18 months may be archived on the system. Archived organisations will be required to complete the initial registration process as outlined in section 4.1 if reappointed by KCL. This promotes good housekeeping and will ensure that KCL have the latest company and contractor information when employing their services. 10. Competency for Permit Issuers and Authorisers The matrix within Appendix B details the documented training and experience required in order to be considered as a permit issuer or permit authoriser. Document No: EF-ASU-02-PR01 10

11 11. Key Performance Indicators (KPIs) & Inspections 11.1 Key Performance Indicators Permit to work system KPIs will be reported on a monthly basis by the Permit Co-ordinator. PTWM KEY PERFORMANCE INDICATORS FROM: DD/MM/YYYY TO: DD/MM/YYYY Total Number of LIVE Companies listed Live Companies with no Contractor Rules and Regulations submission 3 Live Companies with no public liability and/or employers liability insurance held 3 Live Companies with expired insurance documentation 3 Live Companies with insurance due to expire in 1 month 3 Total Number of permits raised Total PTA PTW Hot Works Fire Alarm LOTO WAH Number of expired permits at month close Denmark Hill Guy s & St Thomas Strand & Waterloo Residences Sports Grounds Number of expired high risk permits at month close Hot Works Fire Alarm LOTO WAH 3 This number excludes PFI (Bouygues) and NHS Partners as well as enforcing authorities such as Thames Water and internal departments (such as KCL IT) Document No: EF-ASU-02-PR01 11

12 11.2 Issued Permit Inspection Criteria Each month a number of permits issued for the previous month will be reviewed against the below criteria by the Operational Assurance and Planning & Compliance Teams. Permits raised by each permit authoriser will be audited at least every three months. PTWM DESKTOP PERMIT INSPECTION CRITERIA Building Person Completing Inspection Permit Number Permit Issuer/Authoriser What type of permit does this inspection relate to: Circle all that apply PTA PTW Is the work location specified and correct? Please check the RAMS If applicable, has a room number been detailed? Provide details of the room number/s where the work is taking place Is the Description of Work sufficient for the tasks being undertaken? Have the type of work questions been completed correctly based on the activity being undertaken? Is there a record that asbestos information has been passed to the contractor? Has a risk assessment and method statement been uploaded to the permit? Has the potential hazards section been completed? Have the precautions to be taken been recorded N/a Has the who is at risk and severity and likelihood matrix been completed? N/a Has the permit been accepted electronically by the contractor? If No, is the paper copy readily available and accepted by the contractor? N/a Has the permit been handed back electronically by the contractor? If No, is the paper copy readily available and handed back by the contractor? N/a Has the permit been sign off on the system? Post inspection checks Check the Asbestos Register for the room number/s where the work is taking place and provide detail of findings. Is the asbestos register information sufficient for the works? Further Actions Required Hot works Details: Details: Fire Alarm LOTO WAH 1. Sign Off Inspection Completed By (Name and Signature) Date Document No: EF-ASU-02-PR01 12

13 11.3 Site Inspection Criteria Random site safety inspections on contractor activities will be conducted throughout the academic year. The permit site inspection criteria look at the completion and application of the permit only. PTWM ON-SITE PERMIT INSPECTION CRITERIA Is the contractor in possession of a KCL permit? Permit Number: If Yes, what type? Circle all that apply Hot Fire PTA PTW works Alarm Is the contractor company name correct? Contractor Name: Is the building correct? Building: Is the work location specified and correct? If applicable, has a room number been detailed? Give details of the room number/s where the work is taking place Is the Description of Work sufficient for the tasks Details: being undertaken? Have the type of work questions been completed correctly based on the activity being undertaken? Is there a record that asbestos information has been passed to the contractor? Are all members of the work group (including subcontractors) listed? Provide details of any person present not listed on the permit. Is the permit within its validity period? Has a risk assessment and method statement been uploaded to the permit? Has the potential hazards section been completed? Have the precautions to be taken been recorded N/a Has the who is at risk and severity and likelihood matrix been completed? N/a Name of permit authoriser? Has the permit been accepted electronically by the contractor? Hot Works Review permit criteria against observed site practices and provide detail on inconsistencies? Fire Alarm Isolation Review permit criteria against observed site practices and provide detail below on inconsistencies? Isolation and Line Breaking Review permit criteria against observed site practices and provide detail below on inconsistencies? Working at Heights/Roof works Review permit criteria against observed site practices and provide detail below on inconsistencies? Further Actions Required (itemise) 1. LOTO WAH Sign Off Inspection Completed By (Name and Signature) Contractor Representative (Name and Signature) Date and Time Document No: EF-ASU-02-PR01 13

14 12. Document Review PERMIT TO WORK PROCEDURE This procedure shall be reviewed at least on an annual basis or more frequently as required. This included, but is not limited to: Audit results New information or associated processes System changes Changes to key personnel Document No: EF-ASU-02-PR01 14

15 Appendix A: Definition of Construction Work Preparation for a structure: Work activities on a structure Prefabricated elements of a structure Removal of a structure Site clearance Exploration Construction Alteration Decommissioning Assembly Conversion Fitting out Commissioning Investigations Demolition Renovation Excavation including earthwork, trench, well, shaft, tunnel or underground working Repair Upkeep Redecoration Maintenance Disassembly Dismantling Clearance or preparation of the site or structure for use or occupation at its conclusion Cleaning with water or abrasive at high pressure or using corrosive or toxic substances Removal of any waste or product resulting from structure during the above Any waste or product resulting from structure during the above Document No: EF-ASU-02-PR01 15 Installation, commissioning, maintenance, repair and removal of: Mechanical Electrical Gas Compressed air Hydraulic Telecommunications Computer or similar services which are normally fixed within or to a structure.

16 Appendix B: Competency Matrix Working at Heights /Roof Work/Restricted Access Permit Isolation and Line Breaking Permit - Mechanical (Permit authoriser Isolation and Line Breaking Permit - Electrical (Permit authoriser) Fire Alarm Isolation Permit (Permit authoriser) Permit to Work (Permit authoriser) Permission to Access Permit (Permit issuer) Periodicity (months) MANDATORY REQUIREMENTS 36 ü ü ü ü ü ü College General Risk Assessment Training or equivalent (IOSH Managing Safely, NEBOSH) ü ü ü ü ü ü As required Safe System of Work Training ü ü ü ü ü ü As required PTWM Software Training (1-2-1) Asbestos Register Induction 36 ü ü ü ü ü ü Documented familiarity with the property and systems within N/a ü ü ü ü ü ü Fire Panel Training provided by term fire alarm contractor 24 ü JOB ROLES Subject to the above requirements, those appointed in the below positions can be considered to be a permit issuer or permit authoriser Head of Asset Maintenance & Head of Asset Improvement N/a ü Asset Maintenance Managers, Compliance Support Managers N/a ü ü ü ü ü ü Asset Improvement Managers & Campus Operations Project Managers N/a ü ü Asset Maintenance Team Leaders and (Senior) Maintenance Technicians Electrical Engineers N/a ü ü ü ü * 4 ü Asset Maintenance Team Leaders and (Senior) Maintenance Technicians Mechanical Engineers N/a ü ü ü * ü ü Other KCL Staff N/a ü 4 To be considered on a case by case basis based on qualifications, training and experience for the individuals concerned. Document No: EF-ASU-02-PR01 16

17 Appendix C: Work Flow WORKS WHICH REQUIRE A PERMIT UNDER THE SSOW PM to ensure completion of F003 and F064 by contractor and return to Permit Coordinator Not listed or out of date Project Manager (PM) to check that the company is listed and documentation is up to date on PTWM ask the Permit Coordinator Responsible Person for Work Project Manager (PM) Documentation unsatisfactory Permit co-ordinator reviews and adds documents to PTWM Documentation satisfactory Inductions completed by contractor PM to pass updated inductions to Permit Coordinator PM to ask Permit Co-ordinator to check that all of the declared work group on the system and pass updated inductions Academics King s Venues King s Food Professional Services Capital Projects (Exc CDM) Campus Operations (inc Campus Projects) Inductions required Individual Inductions for all members at least 48 hours before start date PM to consult with building users, Campus Operations and other key parties regarding work dates and request contractor to develop RAMS Contractor to revise RAMS until accepted by PM Submission refused RAMS refused RAMS re-submitted PM to review RAMS and when satisfactory request PTW or PTA at least 5 working days prior to work start date using on-line form. Submission refused Submission refused Permission to Access for restricted areas Permission to Access for general areas Permit to Work (General, Isolation, Hot Works, LOTO, WAH or Fire Alarn Permit issuer to part raise Permission to access permit Nominated permit issuers review submission Asset Management inc Asset Maintenance & Asset Improvement review permit submission Permit to access (PTA) for authorised 3rd parties. Eg Lab Managers Submit for secondary approval by authorised third party Authorise Permission to Access permit Authorise Permit to Work Authorise Permission to access permit Permit accepted by contractor and works start Handed back permit reviewed by staff plus Authorised person on system Permit handed back by contractor / staff in paper / system Document No: EF-ASU-02-PR01 17

18 Appendix D: Permit Guidance Note Document No: EF-ASU-02-PR01 18 PERMIT TO WORK PROCEDURE Company Location Location Details Work Group Validity Documentation Authorisation Acceptance Company to which the permit has been issued will be entered here Campus and the building where the permit is valid. Permits are only valid for one property. All floors of the building where the contractor needs access must be listed here. A reference number for the works, this should be the risk assessment and method statement unique number, or the Planon works number. A brief description of the work, including rooms to be accessed where possible, should be entered. If the permit is valid over multiple days, the agreed shift start and finish times must be specified. The names of all persons with permission for work must be detailed. Any persons not listed must be covered by a separate valid permit, or, access will be refused. The date and time range where the permit is valid must be entered. If this is exceeded a new permit for the work must be issued to the work group. Risk Assessments and Method Statements must be uploaded to the permit. Details the name of the KCL person who is in control of the works. Provides a contact number for all queries or concerns. A permit is only valid if this section has been completed - this can be either hand signed or electronically signed. Access will be refused by Security if this is not completed.

19 Document No: EF-ASU-02-PR01 19 PERMIT TO WORK PROCEDURE Hand-back - Contractor To be completed at the end of the job or upon expiry of the permit (whichever is first). The questions about completion of the work, fire watch, clean and tidy and isolations must be answered. Completed by hand or electronically. Hand-back - KCL Completed by Permit Issuer upon receipt of handed back permit. Must be completed electronically Work area to be checked for all permits to work (except General Permit to Work)

This policy aims to ensure the health, safety and welfare of contractors working on UEL premises and those affected by their work.

This policy aims to ensure the health, safety and welfare of contractors working on UEL premises and those affected by their work. HR Services UEL Health and Safety Handbook Contractor Health and Safety Management Policy This policy is a sub-policy of the main University Health and Safety Policy Statement Introduction The University

More information

Alcumus Health and safety assessment standards

Alcumus Health and safety assessment standards Alcumus Health and safety assessment standards Comply with your assessment duties as a client Gain greater visibility of the anticipated risks throughout your supply chain Document Code: TG-S-01 Version:

More information

Contractor Policy and Procedures. Contractor. Policy and Procedures. Working Together. November Borders College 4/12/ Working Together

Contractor Policy and Procedures. Contractor. Policy and Procedures. Working Together. November Borders College 4/12/ Working Together Contractor Working Together Policy and Procedures November 2017 Borders College 4/12/2017 1 Working Together History of Changes Version Description of Change Authored by Date 1.1 This document combines

More information

linked to the Australian National University s Work health and safety policy and is one of the procedures within the WHS Management System.

linked to the Australian National University s Work health and safety policy and is one of the procedures within the WHS Management System. Purpose This procedure describes how the Australian National University evaluates and monitors contractors work health and safety for all activities performed at the University. This procedure ensures

More information

Asbestos Management. Date of Approval: Date for Next Scheduled Review: Review Body: Equality Impact Assessment Complete: Policy Published on Web:

Asbestos Management. Date of Approval: Date for Next Scheduled Review: Review Body: Equality Impact Assessment Complete: Policy Published on Web: Asbestos Management Policy Title: Policy Author: Date of Approval: Date for Next Scheduled Review: Review Body: Asbestos Management Diane Hendry MC Equality Impact Assessment Complete: Policy Published

More information

Asbestos. When it feels irreplaceable, trust

Asbestos. When it feels irreplaceable, trust Asbestos Asbestos is a naturally occurring, fibrous material which if inhaled can cause serious diseases. These include cancers of the lungs and chest linings which can take many years to develop following

More information

Policy & Procedures for the management of Asbestos Containing Materials

Policy & Procedures for the management of Asbestos Containing Materials Limited Policy & Procedures for the management of Asbestos Containing Materials Housing Management/Maintenance Sub- Committee submission: 20 February 2018 Approved: 20 February 2018 Review date: February

More information

ASBESTOS POLICY. November 2015 November 2018 Chair Person/Office Bearers Signature:

ASBESTOS POLICY. November 2015 November 2018 Chair Person/Office Bearers Signature: ASBESTOS POLICY Date Approved Proposed Review Date November 2015 November 2018 Chair Person/Office Bearers Signature: CASSILTOUN HOUSING ASSOCIATION LIMITED CASTLEMILK STABLES, 59 MACHRIE ROAD, GLASGOW

More information

Asbestos Management Policy

Asbestos Management Policy Asbestos Management Policy Originator: Executive Management Team Approval Date: Policy and Strategy Policy 18 July 2017 Review date: July 2018 1 Introduction 1.1 1.2 1.3 1.4 The scope of this Policy sets

More information

Contractor Safety Plan

Contractor Safety Plan Contractor Safety Plan INSTRUCTIONS Scope This form is to be completed by the contractor that has been identified as a major contract. This Plan expires at the completion of the contract work or 12 months

More information

Asbestos Management Policy

Asbestos Management Policy Asbestos Management Policy Reviews and Revisions Date Reason Reviewer Next review date Approved by 28/07/2015 New members of working group L Salkeld 28/07/16 L Salkeld 10/02/2016 Following an incident

More information

HIGH RISK CONSTRUCTION WORK

HIGH RISK CONSTRUCTION WORK CONTRACTOR WHS SYSTEM STANDARD HIGH RISK CONSTRUCTION WORK EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION

More information

PROJECT NAME. Risk Management Log

PROJECT NAME. Risk Management Log Risk Management Log Document Number:JobNo/001 Revision:0 Revision date:dd/mm/yyyy Document Owner: Levitt Bernstein QMS/SF/3-07-04/08.06.11 PAGE 1 OF 9 Purpose: The Risk Management Log is a record of each

More information

Roofers and Scaffolders Enquiry Form

Roofers and Scaffolders Enquiry Form Broker: Address inc Pcode: Contact Name: Telephone No: Proposer Details Name of Client: Full Address: Post Code: Website: Current Insurer: Current Broker: Expiring Premium: + Insurance Premium Tax Work

More information

Control of Contractors Policy

Control of Contractors Policy Reference Number: UHB 163 Version Number: 2 Date of Next Review: 19/07/2019 Previous Trust/LHB Reference Number: Control of Contractors Policy Policy Statement To ensure the Health Board delivers its aims,

More information

Work Health and Safety Conditions

Work Health and Safety Conditions Work Health and Safety Conditions Table of Contents PURPOSE AND SCOPE... 1 RESPONSIBILITIES... 1 DEFINITIONS, ABBREVIATIONS AND ACRONYMS... 1 GENERAL WH&S & ELECTRICAL SAFETY REQUIREMENTS... 1 Compliance...

More information

CAMBRIDGESHIRE GUIDED BUSWAY OPERATIONS POLICY

CAMBRIDGESHIRE GUIDED BUSWAY OPERATIONS POLICY CAMBRIDGESHIRE GUIDED BUSWAY OPERATIONS POLICY Page 1 of 7 CGB OPERATIONS POLICY Contents: 1. Introduction 2. Contents 3. General Policy 4. Safety Inductions 5. Access 6. Requirements and Restrictions

More information

1.3 All employees are equally responsible for complying with the Ontario Occupational Health & Safety Act and its Regulations.

1.3 All employees are equally responsible for complying with the Ontario Occupational Health & Safety Act and its Regulations. Revision No: 1 Page: 1 of 14 1.0 PURPOSE 1.1 The purpose of this policy is to establish guidelines for contractors in order to provide and maintain a safe work environment for all employees. Advance planning

More information

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd. TRANSNET LIMITED (Registration no. 1990/000900/06) PRIEVIEW COPY ONLY

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd. TRANSNET LIMITED (Registration no. 1990/000900/06) PRIEVIEW COPY ONLY TRANSNET LIMITED (Registration no. 1990/000900/06) SAFETY ARRANGEMENTS AND PROCEDURAL COMPLIANCE WITH THE OCCUPATIONAL HEALTH AND SAFETY ACT (ACT 85 OF 1993) AND APPLICABLE REGULATIONS 1. General 1.1 The

More information

Policy for Occupational Health, Safety and Environment Requirements for Contracted Construction and Maintenance Work

Policy for Occupational Health, Safety and Environment Requirements for Contracted Construction and Maintenance Work Policy for Occupational Health, Safety and Environment Requirements for Contracted Construction and Maintenance Work Policy Statement Rationale Construction and Maintenance work undertaken by contracted

More information

PREQUALIFICATION QUESTIONNAIRE

PREQUALIFICATION QUESTIONNAIRE PREUALIFICATION UESTIONNAIRE 1.0 COMPANY DETAILS 1.1 Please complete the company details below: Company: Post Code: Tel: E-mail Contact: Title: CRN: Fax: Website: 1.2 Does this Company have a Parent Company

More information

Policy A6 Health & Safety Appendix 4 - Control of Asbestos

Policy A6 Health & Safety Appendix 4 - Control of Asbestos Policy A6 Health & Safety Appendix 4 - Control of Asbestos Contents 1. Policy Statement 2. Introduction 3. Objectives 4. Statutory Requirements 5. Roles and Responsibilities 5.1 The Trust 5.2 Local Governing

More information

SUB CONTRACTOR INDUCTION PACK

SUB CONTRACTOR INDUCTION PACK REQUIREMENTS FOR WORKING ON ROYAL MAIL PREMISES 1. INTRODUCTION AND PURPOSE This document sets out the arrangements that Royal Mail Property & Facilities Solutions Limited and Royal Mail [hereinafter jointly

More information

WORKING WITH CONTRACTORS POLICY AND PROCEDURE

WORKING WITH CONTRACTORS POLICY AND PROCEDURE WORKING WITH CONTRACTORS POLICY AND PROCEDURE CROWN SECURITY CONTRACTORS & OSH (i) Preface Contract work is becoming increasingly common in the modern workplace management culture, and has been a feature

More information

HEALTH AND SAFETY AT WORK (CONSTRUCTION) (PERSONAL PROTECTIVE EQUIPMENT) (JERSEY) REGULATIONS 2002

HEALTH AND SAFETY AT WORK (CONSTRUCTION) (PERSONAL PROTECTIVE EQUIPMENT) (JERSEY) REGULATIONS 2002 HEALTH AND SAFETY AT WORK (CONSTRUCTION) (PERSONAL PROTECTIVE EQUIPMENT) (JERSEY) REGULATIONS 2002 Revised Edition Showing the law as at 1 January 2006 This is a revised edition of the law Health and

More information

Contractors Induction Booklet. Contractor s Name:

Contractors Induction Booklet. Contractor s Name: Contractors Induction Booklet Date Contractor s Name: Business Name: The following information relates to Work Health & Safety and has been designed and implemented by the Owner s Corporation (OC) and

More information

Risk Assessment Procedure

Risk Assessment Procedure 1. Introduction Risk Assessment Procedure 1.1 The Management of Health and Safety at Work Regulations 1999 set out general duties which apply to employers and are aimed at improving health and safety management.

More information

Risk Management Guidelines

Risk Management Guidelines Management of Asbestos in Buildings - Occupiers General Guidance Introduction Asbestos continues to be a major occupational health issue in the UK. It currently causes about 3,000 fatalities a year and

More information

ASBESTOS POLICY (2017)

ASBESTOS POLICY (2017) ASBESTOS POLICY (2017) 1.0 INTRODUCTION The Association has stated its commitment, through its Health & Safety Policy Statement, to take all reasonable steps to ensure the health, safety and welfare at

More information

Contractor Guidelines

Contractor Guidelines Contractor Guidelines This Guideline has been written to detail the minimum expectations with regards to contractor safety at Sodexo business units. It is the responsibility of the contractor to understand

More information

Risk assessment Policy and Procedures

Risk assessment Policy and Procedures Risk assessment Policy and Procedures 1. Introduction The purpose of risk assessment is to identify hazards and evaluate any associated risks to health and safety arising from Youth Works activities, enabling

More information

COMPANY POLICY FOR HEALTH AND SAFETY

COMPANY POLICY FOR HEALTH AND SAFETY Breakfire Ltd, Unit 2 Woodview Business Centre, Lockwood Close, Nottingham, NG5 9JN COMPANY POLICY FOR HEALTH AND SAFETY January 2018 TABLE OF CONTENTS SECTION 1 TITLE NUMBER REVISION Policy & Administration

More information

SHOPPING & CRAFT BOOKING FORM (Closing Date 31 st July 2018)

SHOPPING & CRAFT BOOKING FORM (Closing Date 31 st July 2018) Saturday 8th September 2018 FOR OFFICE USE ONLY Confirm App. Received On SMACS STAND NO. Paid () Receipt Sent Paid by: SHOPPING & CRAFT BOOKING FORM (Closing Date 31 st July 2018) Trading Name: Contact

More information

SUPPLY OF PEST CONTROL SERVICES

SUPPLY OF PEST CONTROL SERVICES . SUPPLY OF PEST CONTROL SERVICES TENDER DETAILS: DURATION: Tenders should be prepared on the basis of a twelve (12) month arrangement commencing 1 st July 2018. CLOSING DATE: Monday 28th May 2018. TENDER

More information

POWER CONSTRUCTION COMPANY CCIP PROGRAM SAFETY REQUIREMENTS

POWER CONSTRUCTION COMPANY CCIP PROGRAM SAFETY REQUIREMENTS POWER CONSTRUCTION COMPANY CCIP PROGRAM SAFETY REQUIREMENTS The following requirements apply to all subcontractors including tier subcontractors, vendors, deliveries, visitors and the like (herein known

More information

A UNIQUE AND COMPREHENSIVE INSURANCE SCHEME FOR THE ELECTRICAL INDUSTRY

A UNIQUE AND COMPREHENSIVE INSURANCE SCHEME FOR THE ELECTRICAL INDUSTRY .. A UNIQUE AND COMPREHENSIVE INSURANCE SCHEME FOR THE ELECTRICAL INDUSTRY PROPOSAL FORM Camberford Law plc Innovative Insurance solutions Since 1958 Insurance Brokers Underwriting Agents Authorised and

More information

BROCKWOOD PARK SCHOOL & INWOODS SMALL SCHOOL

BROCKWOOD PARK SCHOOL & INWOODS SMALL SCHOOL BROCKWOOD PARK SCHOOL & INWOODS SMALL SCHOOL RISK ASSESSMENT POLICY Last Review Date August 2018 Policy endorsed by Policy is maintained by ISI reference The Trustees, Principal & Inwoods Head Teacher

More information

Health & Safety Policy HSP 06 Asbestos Management Version Status Date Title of Reviewer Purpose/Outcome

Health & Safety Policy HSP 06 Asbestos Management Version Status Date Title of Reviewer Purpose/Outcome Health & Safety Policy HSP 06 Asbestos Management Version Status Date Title of Reviewer Purpose/Outcome 1.0 Draft 07.03.2016 David Maine 1 st Draft for consultation/review 1.1 Approved 22.12.2016 David

More information

Health & Safety Policy

Health & Safety Policy Health & Safety Policy K4S Security Ltd Imperial Office 2a Heigham Road East Ham London E6 2JG Registered Company Number: 09646212 Policy Date: 12 April 2018 1/14 Contents Page 1.0 General Statement of

More information

Guidance. For Departments on Engaging External Service Providers

Guidance. For Departments on Engaging External Service Providers Guidance For Departments on Engaging External Service Providers Jan 2012 CONTENTS 1 Introduction 1.1 University Policy 1.2 Purpose of this Guidance 2. Main activities of Department Supervising Officers

More information

3 OUR INSTALLERS 4 OUR RESPONSIBILITY

3 OUR INSTALLERS 4 OUR RESPONSIBILITY NPOWER SALE TERMS & CONDITIONS FOR NEST THERMOSTAT 1 OUR CONTRACT These Terms & Conditions apply to the Contract between you and us. Please read them carefully. Words which appear in bold type throughout

More information

COMPREHENSIVE GENERAL LIABILITY INSURANCE

COMPREHENSIVE GENERAL LIABILITY INSURANCE PROPOSAL FORM COMPREHENSIVE GENERAL LIABILITY INSURANCE Important tice 1. Statement pursuant to Section 25(5) of the Insurance Act (Cap 142) or any amendments thereof; you are to disclose in the application,

More information

Contractor Management Procedure

Contractor Management Procedure Contractor Management Procedure Purpose Skillset Limited ( Skillset ) has a duty under the NSW Work Health and Safety Act and Regulations 2011 (the Legislation ) to prevent and/or to minimise risk in the

More information

This document is meant to be a starting point for any company wanting to implement the safety passport scheme for their contractors on site.

This document is meant to be a starting point for any company wanting to implement the safety passport scheme for their contractors on site. Introduction This document is meant to be a starting point for any company wanting to implement the safety passport scheme for their contractors on site. It was put together by members of the Food & Drink

More information

Occupational Safety & Health Policy & Guidelines for Contractors

Occupational Safety & Health Policy & Guidelines for Contractors Occupational Safety & Health Policy & Guidelines for Contractors Occupational Safety & Health Policy & Guidelines for Contractors Table of Contents Forward..1 Introduction... 1 Policy.1 City of Kalamunda

More information

Power Construction Company CCIP Program Safety Requirements

Power Construction Company CCIP Program Safety Requirements Introduction The following safety requirements (herein known as safety requirements) apply to all subcontractors including tier subcontractors, employees, consultants, vendors, deliveries, visitors and

More information

Health and Safety. Version 5. Category: Corporate. Latest Review Date: December Review Frequency: Annual. Owner: Company Secretary

Health and Safety. Version 5. Category: Corporate. Latest Review Date: December Review Frequency: Annual. Owner: Company Secretary Health and Safety Version 5 Category: Corporate Latest Review Date: December 2016 Review Frequency: Annual Owner: Company Secretary Contributors: H&S Facilitator, Facilities Manager, Customer Service Manager,

More information

Contractor Compliance Review Procedure

Contractor Compliance Review Procedure Contractor Compliance Review Procedure 2. Amendments and Distribution Notes on Document Control This document is the property of Edinburgh Airport Limited (EAL) and its contents are confidential. It must

More information

Guideline for external contractors working on the premise of MANN+HUMMEL

Guideline for external contractors working on the premise of MANN+HUMMEL Guideline for external contractors working on the premise of MANN+HUMMEL 1 Purpose MHG-HS-I-0011 describes the regulations for health, safety and environment for external contractors working on the premise

More information

Contractor Health and Safety Code of Practice. Updated June 4, 2018

Contractor Health and Safety Code of Practice. Updated June 4, 2018 Contractor Health and Safety Code of Practice 2018 Updated June 4, 2018 Updated June 4, 2018 TABLE OF CONTENTS A. DEFINITIONS...3 B. PURPOSE...7 C. STRATEGIC ALIGNMENT...7 D. REGULATORY CONSIDERATIONS...7

More information

Professional Indemnity Insurance Architects & Engineers Proposal

Professional Indemnity Insurance Architects & Engineers Proposal NOTES 1. This form does not apply to Practices which also undertake construction, installation or fabrication. These Practices should complete the Design and Construct Proposal. 2. Please answer all questions

More information

Professional Indemnity Insurance Design & Construct Proposal

Professional Indemnity Insurance Design & Construct Proposal NOTES 1. This form should be completed by Practices which, in addition to the provision of engineering consultancy, undertake construction, installation or fabrication. Practices whose services do not

More information

AGREEMENT ON OCCUPATIONAL HEALTH AND SAFETY IN TERMS OF SECTION 37(2) OF THE OCCUPATIONAL HEALTH AND SAFETY ACT 85 OF 1993 (AS AMENDED) between

AGREEMENT ON OCCUPATIONAL HEALTH AND SAFETY IN TERMS OF SECTION 37(2) OF THE OCCUPATIONAL HEALTH AND SAFETY ACT 85 OF 1993 (AS AMENDED) between AGREEMENT ON OCCUPATIONAL HEALTH AND SAFETY IN TERMS OF SECTION 37(2) OF THE OCCUPATIONAL HEALTH AND SAFETY ACT 85 OF 1993 (AS AMENDED) between TELKOM SA SOC LIMITED (Registration number: 1991/005476/07)

More information

Request for Tender The Owners Corporation of Units Plan 2413 Landmark Strata and Building Management Services

Request for Tender The Owners Corporation of Units Plan 2413 Landmark Strata and Building Management Services Request for Tender The Owners Corporation of Units Plan 2413 Landmark Strata and Building Management Services TABLE OF CONTENTS SECTION 1 - INFORMATION ADVICE TO TENDERERS... 2 SECTION 2 - SCOPE OF SERVICES...

More information

Broadform General & Products Liability 2017/06 Proposal. about Broadform General and Products Liability 2016/05 Proposal

Broadform General & Products Liability 2017/06 Proposal. about Broadform General and Products Liability 2016/05 Proposal About Broadform General & Products Liability 2017/06 Proposal about Broadform General and Products Liability 2016/05 Proposal Page 1 of 12 IMPORTANT INFORMATION: PLEASE READ THE FOLLOWING INFORMATION BEFORE

More information

ARRANGED BY ELECTRICAL & HVAC CONTRACTORS PROPOSAL FORM UNDERWRITTEN BY

ARRANGED BY ELECTRICAL & HVAC CONTRACTORS PROPOSAL FORM UNDERWRITTEN BY ARRANGED BY ELECTRICAL & HVAC CONTRACTORS PROPOSAL FORM UNDERWRITTEN BY P1 PROPOSAL PROPOSAL FORM FORM THE FOR ELECTRICAL THE ELECTRICAL CONTRACTING INDUSTRY INDUSTRY DISCLOSURE: In completing In this

More information

EMPLOYER S, PUBLIC & PRODUCTS LIABILITY PROPOSAL FORM

EMPLOYER S, PUBLIC & PRODUCTS LIABILITY PROPOSAL FORM EMPLOYER S, PUBLIC & PRODUCTS LIABILITY PROPOSAL FORM Please complete all details in BLOCK LETTERS. Where applicable indicate YES or NO Insurance will not be in force until proposal form is accepted by

More information

Cyclical & Planned Maintenance Procedure. This procedure relates to the establishment of programmes for cyclical and planned maintenance.

Cyclical & Planned Maintenance Procedure. This procedure relates to the establishment of programmes for cyclical and planned maintenance. Providing Choice Addressing Inequalities Cyclical & Planned Maintenance Procedure This procedure relates to the establishment of programmes for cyclical and planned maintenance. Improving Life Opportunities

More information

London Christian Learning Centre. Risk Assessment

London Christian Learning Centre. Risk Assessment London Christian Learning Centre Risk Assessment RISK ASSESSMENT POLICY INTRODUCTION At London Christian Learning Centre we recognise the importance of the process of risk assessment to enable us to safeguard

More information

Terms and Conditions of Hire for The Aspire Wellbeing Centre

Terms and Conditions of Hire for The Aspire Wellbeing Centre Terms and Conditions of Hire for The Aspire Wellbeing Centre Hereinafter Aspire Wellbeing Centre shall be referred to as Aspire and the Hirer named on the Booking form as The Hirer Aspire is committed

More information

Dear, Your Client: Re: Policy Number

Dear, Your Client: Re: Policy Number Dear, Your Client: Re: Policy Number As you are no doubt aware, the above policy falls due for renewal on.to enable us to calculate renewal terms, please complete and return the attached Declaration, Estimate

More information

Asbestos Management Policy and Plan

Asbestos Management Policy and Plan Asbestos Management Policy and Plan Trust Board Approval Date 29 January 2018 Effective Date 29 January 2018 Planned Review Date September 2018 Web Access Internet Issue 2 Prepared by: Verified by: Date:

More information

RISK ASSESSMENT POLICY

RISK ASSESSMENT POLICY RISK ASSESSMENT POLICY Scope of the Policy The academy s Governors are committed to promoting the safety and welfare of all members of its community. Governors priority lies in ensuring that all operations

More information

OKLAHOMA CITY COMMUNITY COLLEGE HAZARD COMMUNICATION PROGRAM. Environmental Health and Safety

OKLAHOMA CITY COMMUNITY COLLEGE HAZARD COMMUNICATION PROGRAM. Environmental Health and Safety OKLAHOMA CITY COMMUNITY COLLEGE HAZARD COMMUNICATION PROGRAM Environmental Health and Safety Established: December 1994 Revised: December 1998 Revised: January 31, 2008 Reviewed: May 12, 2009 Revised:

More information

Mine Health and Safety Regulation 2007

Mine Health and Safety Regulation 2007 New South Wales Mine Health and Safety Regulation 2007 under the Mine Health and Safety Act 2004 Her Excellency the Governor, with the advice of the Executive Council, has made the following Regulation

More information

00810 Vendor Diversity

00810 Vendor Diversity 00810 Vendor Diversity 1.1 The University of Florida is an equal opportunity institution and, as such, encourages the use of small businesses, woman-owned businesses, and minority-owned businesses in the

More information

Please give a detailed description of services offered: (This must be filled out completely)

Please give a detailed description of services offered: (This must be filled out completely) CONTRACTOR LICENSE APPLICATION City of Douglas-Planning Department P. O. Box 1030/101 N. 4th Street Douglas, Wyoming 82633-1030 (307) 358-2132 or Fax (307) 358-2133 Application for license shall be made

More information

Please ensure you read this document carefully as it sets out the contractual terms and conditions for the booking that you have made with us.

Please ensure you read this document carefully as it sets out the contractual terms and conditions for the booking that you have made with us. Conference Room Hire Terms and Conditions Please ensure you read this document carefully as it sets out the contractual terms and conditions for the booking that you have made with us. 1. Definitions 1.1

More information

CORPORATE POLICY MANUAL

CORPORATE POLICY MANUAL Name of Policy: Contractor Safety Policy Policy Number: CPM-10-91 (replaces MPM-10-91) Responsibility: Health, Safety and Environment Department Approval: Chief Executive Officer Approval Date: March 13,

More information

Safety & Health Manual

Safety & Health Manual Safety & Health Manual Chapter 8 Sub-Contractor Policy 8-1 Sub-Contractor Policy engages the services of sub-contractors and values its relationships with these essential service providers. In the interest

More information

WRITTEN AGREEMENT FOR OCCUPATIONAL HEALTH AND SAFETY

WRITTEN AGREEMENT FOR OCCUPATIONAL HEALTH AND SAFETY WRITTEN AGREEMENT FOR OCCUPATIONAL HEALTH AND SAFETY In accordance with the provisions of Section 37(2) of the Occupational Health and Safety Act No. 85 of 1993 Entered into and between Tongaat Hulett

More information

Newbridge Town Hall Booking Form

Newbridge Town Hall Booking Form Newbridge Town Hall Booking Form BOOKING DETAILS Description of activity (purpose of hire): Organisation: Contact: Responsible Person Mobile phone: Landline phone: Email: Fax: Address: Indicate any other

More information

ATTACHMENT "I" SUBCONTRACTOR SAFETY, HEALTH, AND ENVIRONMENTAL MINIMUM PERFORMANCE STANDARD (MPS)

ATTACHMENT I SUBCONTRACTOR SAFETY, HEALTH, AND ENVIRONMENTAL MINIMUM PERFORMANCE STANDARD (MPS) ATTACHMENT "I" SUBCONTRACTOR SAFETY, HEALTH, AND ENVIRONMENTAL MINIMUM PERFORMANCE STANDARD (MPS) Swinerton Builders, Inc. (SWINERTON) constantly strives to provide a safe and productive work environment.

More information

UNDERGROUND SERVICE STRIKES

UNDERGROUND SERVICE STRIKES UNDERGROUND SERVICE STRIKES GUIDELINES FOR CONSTRUCTION COMPANIES An underground service strike can lead to injury or loss of life and the costs to your business can be substantial. This short guide is

More information

Proposal Form. Design and Construction Professional Indemnity

Proposal Form. Design and Construction Professional Indemnity Proposal Form Design and Construction Professional Indemnity Important Notices Please read these notices before completing the Proposal Form. Your Duty of Disclosure Before you enter into an insurance

More information

Health and Safety Procedure: Risk Assessment. 1. Introduction

Health and Safety Procedure: Risk Assessment. 1. Introduction Health and Safety Procedure: Risk Assessment 1. Introduction 1.1. The purpose of this Procedure is to set out the London School of Economics (hereafter the School or LSE) arrangements for undertaking risk

More information

APPLICATION FOR STANDS IN THE FOOD HALL Please read attached notes. CARTMEL AGRICULTURAL SHOW WEDNESDAY 7 August 2019

APPLICATION FOR STANDS IN THE FOOD HALL Please read attached notes. CARTMEL AGRICULTURAL SHOW WEDNESDAY 7 August 2019 APPLICATION FOR STANDS IN THE FOOD HALL Please read attached notes. CARTMEL AGRICULTURAL SHOW WEDNESDAY 7 August 2019 Name of Company/Applicant: Address:...Postcode:.. Tel : E mail address:..web Site:..

More information

TERMS AND CONDITIONS OF SALE ACN: ABN:

TERMS AND CONDITIONS OF SALE ACN: ABN: TERMS AND CONDITIONS OF SALE ACN: 169 441 383 ABN: 28 169 441 383 OFFER TO SUPPLY / QUOTATION VALIDITY Our offer is valid for a period of 30 days from the date of quotation. Notwithstanding; the details

More information

Contractor Policy. Contractor. Policy. Working Together. August Borders College 29/8/ Working Together

Contractor Policy. Contractor. Policy. Working Together. August Borders College 29/8/ Working Together Contractor Working Together Policy August 2014 Borders College 29/8/2014 1 Working Together History of Changes Version Description of Change Authored by Date 1.1 K Drum Borders College 29/8/2014 2 Working

More information

HEALTH AND SAFETY POLICY

HEALTH AND SAFETY POLICY HEALTH AND SAFETY POLICY Please be aware that this printed version of the Policy may NOT be the latest version. Staff are reminded that they should always refer to the Intranet for the latest version.

More information

Carson, CA Inland Star Distribution Centers, Inc. PSM/CalARP

Carson, CA Inland Star Distribution Centers, Inc. PSM/CalARP Carson, CA Inland Star Distribution Centers, Inc. PSM/CalARP CONTRACTOR PROGRAM Revision History Rev. # Description of Change Date Revised By 0 Initial Issues July 2016 PSM RMP Solutions Purpose The purpose

More information

Policy. Safety risk assessment. 1 Why use risk assessment?

Policy. Safety risk assessment. 1 Why use risk assessment? Safety risk assessment V E R S I O N 1. 1 M A R C H 2 0 0 5 1 Why use risk assessment? 1.1 The principle reason for conducting risk assessments is to comply with our legal duty. The Management of Health

More information

Nigeria Oil & Gas Trade and Investment Forum October 2013 Onne Oil & Gas Free Zone, Rivers State, Nigeria

Nigeria Oil & Gas Trade and Investment Forum October 2013 Onne Oil & Gas Free Zone, Rivers State, Nigeria Nigeria Oil & Gas Trade and Investment Forum 2014 30-31 2013 Onne Oil & Gas Free Zone, Rivers State, Nigeria Manual The event team warmly welcomes you to Nigeria Oil & Gas Trade and Investment Forum 2014

More information

MARKET OH&S PLAN 1 INTRODUCTION 2 OH&S RESPONSIBILITIES

MARKET OH&S PLAN 1 INTRODUCTION 2 OH&S RESPONSIBILITIES 1 INTRODUCTION Melbourne Market Authority (MMA) is committed to a safety culture and practices that provide for a healthy and safe working environment. The health and safety of all those who work for us

More information

FUNCTIONS AND EVENTS

FUNCTIONS AND EVENTS FUNCTIONS AND EVENTS Contact 021 858 180 functions@dominionbar.co.nz Visit Corner of Dominion and Valley Road Mt Eden, Auckland WWW.DOMINIONBAR.CO.NZ Located on the city fringe in Mt Eden and only a stone

More information

CONTRACTOR AND VISITOR CONTROLS

CONTRACTOR AND VISITOR CONTROLS CONTRACTOR AND VISITOR CONTROLS This guideline is prepared by Willis Australia Limited for risk management purposes. No responsibility is accepted for the use or reliance upon this report, in whole or

More information

PCHA Legionella Control Policy

PCHA Legionella Control Policy PCHA Legionella Control Policy Originator: Policy and Strategy Team Approval Date: 19 July 2016 Review Date: July 2017 1 Introduction 1.1 1.2 1.3 1.4 Pine Court Housing Association (PCHA), treats the health

More information

ACCESS REQUEST AND REGULATIONS FOR CONTRACTORS AND CREW

ACCESS REQUEST AND REGULATIONS FOR CONTRACTORS AND CREW Access Regulations and Arrangements: ACCESS REQUEST AND REGULATIONS FOR CONTRACTORS AND CREW 1. This Access Request document must be completed for each job and must be submitted to SHEQ and Logistics Departments

More information

Event Safety Policy. Contents. 1. Policy statement. 3. Scope of the policy. 4. Key legislative requirements

Event Safety Policy. Contents. 1. Policy statement. 3. Scope of the policy. 4. Key legislative requirements Event Safety Policy Contents 1. Policy statement 2. Key requirements of the policy 3. Scope of the policy 4. Key legislative requirements 5. Risk management of events: roles and responsibilities 6. Approval

More information

Legionella Control Policy

Legionella Control Policy Legionella Control Policy Originator: Executive Management Team Approval Date: Policy and Strategy Team July 2018 Review date: July 2019 1 Introduction 1.1 1.2 1.3 1.4 One Vision Housing (OVH) treats the

More information

Risk Assessment Policy

Risk Assessment Policy Risk Assessment Policy Introduction All independent schools are legally required to have risk assessments in place that cover a great many school activities, including all the many educational visits,

More information

HIRE OF SCHOOL PREMISES POLICY

HIRE OF SCHOOL PREMISES POLICY Founded 1636 HIRE OF SCHOOL PREMISES POLICY Date of Review: May 2016 Member of staff responsible: Mr Andrew Eckford Approval by Full Governing Body: 13 th October 2016 Date of next review: May 2018 Page

More information

Vend Engineering Pty Ltd. Residential & Commercial construction Site Safety Pack For subcontractors

Vend Engineering Pty Ltd. Residential & Commercial construction Site Safety Pack For subcontractors Vend Engineering Pty Ltd Residential & Commercial construction Site Safety Pack For subcontractors Version 3 2015 Disclaimer The authors of the VEND Engineering Site Safety Pack (the Site Safety Pack)

More information

LETTINGS POLICY. Approved by: Finance & Estates Committee * Safeguarding Policy Health, Safety & Environment Policy.

LETTINGS POLICY. Approved by: Finance & Estates Committee * Safeguarding Policy Health, Safety & Environment Policy. LETTINGS POLICY Responsible Senior Manager: Vice Principal Finance & Facilities Approved by: Finance & Estates Committee * Related Policies: Safeguarding Policy Health, Safety & Environment Policy Effective

More information

PLEASE NOTE. For more information concerning the history of this Act, please see the Table of Public Acts.

PLEASE NOTE. For more information concerning the history of this Act, please see the Table of Public Acts. PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this Act, current to January 1, 2009. It is intended for information and reference purposes only. This

More information

Hazard Identification, Risk Assessment and Control Procedure

Hazard Identification, Risk Assessment and Control Procedure Hazard Identification, Risk Assessment and Control Procedure 1. Purpose To ensure that there is a formal process for hazard identification, risk assessment and control to effectively manage workplace and

More information

COMMUNITY. Application for Hire

COMMUNITY. Application for Hire COMMUNITY Application for Hire ACON is New South Wales leading health promotion organisation specialising in HIV and lesbian, gay, bisexual, transgender and intersex (LGBTI) health. Our mission is to enhance

More information

Northern Territory Airports

Northern Territory Airports Northern Territory Airports SITE RULES for CONTRACTORS at ALICE SPRINGS AIRPORT AND TENNANT CREEK AIRPORT Date Approved: Approved by: Date Issued: Date for Review: PRIOR TO ANY WORKS TAKING PLACE. Page

More information

HIRING OF SCHOOL PREMISES

HIRING OF SCHOOL PREMISES HIRING OF SCHOOL PREMISES Conditions of Hire 1. The Hirer and Guarantor, who both must be over the age of 18 years, must sign the application form and will now be referred to jointly throughout the document

More information

PROFESSIONAL INDEMNITY INSURANCE PROPOSAL FORM FOR CONSULTING ENGINEERS

PROFESSIONAL INDEMNITY INSURANCE PROPOSAL FORM FOR CONSULTING ENGINEERS PROFESSIONAL INDEMNITY INSURANCE PROPOSAL FORM FOR CONSULTING ENGINEERS 1 P a g e CONTENTS 1. ADVICE ON COMPLETING THE PROPOSAL FORM 2. PROPOSAL FORM 3. SUPPLEMENTARY ASBESTOS QUESTIONNAIRE 4. SUPPLEMENTARY

More information