1 CONTRACTOR WHS SYSTEM STANDARD HIGH RISK CONSTRUCTION WORK EXTERNAL USE ONLY

2 Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition WHS hazard areas are a key consideration in the selection of the appropriate procurement channel. PROCUREMENT CHANNEL SELECTION SPECIFICATION EVALUATION APPROVAL AND RELEASE Specification Hazard areas and Optus expectations in relation to these are communicated to potential providers in relevant project / task requirements (e.g. tenders, statement of works, purchase orders). Appropriate WHS specifications are included in the tender / statement of work conditions / purchase order (if required) and are reflective of Optus role (e.g. principal contractor). Evaluation The contractor submission suggests they are competent to manage the task and WHS risks of their workplace. ENGAGEMENT Engagement All parties have a consistent understanding of their mutual accountabilities as they relate to WHS risk management. Appropriate WHS specifications and obligations are included in the relevant contracts negotiated and signed by Optus. MONITORING Monitoring Relevant WHS controls are implemented and monitored at the workplace to manage the specific conditions and WHS risks of that workplace. SATISFACTORY PERFORMANCE? HANDOVER CLOSE AND REVIEW Handover Customers (internal and external) are made aware of potential risk areas and legislative expectations at handover. Close and review Contractor WHS performance is assessed and considered when using the contractor in future. Project feedback is captured and used to enhance the contractor WHS management process.

3 IMPORTANT NOTE THIS CONTRACTOR WORKPLACE HEALTH SAFETY (WHS) STANDARD HAS BEEN DEVELOPED TO ASSIST OPTUS CONTRACTORS IN THE EXECUTION OF OPTUS CONTRACTED WORKS. THE STANDARD MUST BE ENACTED IN CONJUNCTION WITH OTHER APPLICABLE OPTUS CONTRACT CONDITIONS REGARDING WHS AND THE GOVERNING LEGAL REQUIREMENTS. WHILE THIS STANDARD HAS BEEN DEVELOPED IN CONSIDERATION OF THE LEGAL REQUIREMENTS IT IS NOTED THAT WHERE ANY LEGAL REQUIREMENT EXCEEDS THIS STANDARD THE LEGAL REQUIREMENT SHALL TAKE PRECEDENCE. Purpose and scope This Contractor WHS Standard (Standard) High Risk Construction Work aims to establish minimum WHS requirements for Optus Contractors when undertaking high risk construction works. In addition, this Standard supports the Commonwealth WHS Act 2011 (Act) where a duty is imposed (under the Act) on a person to ensure health and safety, it requires the person to eliminate so far as is reasonably practicable, and if it is not reasonably practicable to eliminate risks to health and safety, to minimise those risks so far as is reasonably practicable to workers. The Commonwealth WHS Regulations 2011 (Regulations) defines high risk construction work (and as applied to the type of works Optus Contractors typically undertake) as: a risk of a person falling more than 2 metres; work carried out on telecommunication towers; demolition of an element of a structure that is load bearing or otherwise related to the physical integrity of the structure; or is likely to involve, the disturbance of asbestos; structural alterations or repairs that require temporary support to prevent collapse; work carried out in or near a confined space; work carried out in or near a shaft or trench with an excavated depth greater than 1.5 metres or a tunnel; work carried out on or near pressurised gas distribution mains or piping; work carried out on or near chemical, fuel or refrigerant lines; work carried out on or near energised electrical installations or services; work carried out in an area that may have a contaminated or flammable atmosphere; work carried out on, in or adjacent to a road, railway or other traffic corridor that is in use by traffic other than pedestrians; work carried out in an area at a workplace in which there is any movement of powered mobile plant; work carried out in an area in which there are artificial extremes of temperature; and work carried out in or near water or other liquid that involves a risk of drowning. The Act and Regulations, are further supported by the provisions of the Commonwealth Code of Practice (CoP) How to Manage Work Health and Safety Risks This Standard applies to entities contracted to Optus where high risk construction work is undertaken and these activities are a part of their scope of works. Roles and responsibilities Optus Contractors, so far as is reasonably practicable, are generally responsible for: Complying with all contractual obligations for ensuring workplace health and safety. Reviewing Optus risk management processes such as Risk Register(s) and this Standard and factor this information into their safe systems of work.

4 Establishing accountability and authorities for risk management and ensuring a competent person undertakes the risk assessment and is provided with all the necessary information to enable the works to be carried out in safe manner. Conducting risk management Hazard Identification Risk Assessment & Control (HIRAC) and documenting the outcome(s) as a Safe Work Method Statement (SWMS) or similar, and in accordance with applicable legislative and industry standards including legal provisions for high risk construction work. Providing communication and consultation to workers and their representatives, as related to high risk construction work. Keeping and maintaining a SWMS until the completion of work or where a notifiable incident occurs, a copy of the SWMS for a period of 2 years. Developing emergency preparedness and response provisions for works, this may include plans and procedures, rescue plans, external notifications and response hardware. Investigating and reporting incidents, accidents, dangerous occurrences and illness within the required contractual reporting period to Optus and where required to the applicable Regulator. In addition to the above, Optus Contractors, so far as is reasonably practicable, are specifically responsible for: Documenting the outcomes of the risk assessment such as a SWMS or similar and in consideration of: The type of high risk construction work, its risk profile, hazards and controls. The planned arrangements for any WHS information, training, instruction or supervision. The manner in which it is expressed, communicated and its accessibility. The Workplace Health Safety Management Plan (if the high risk construction work is carried out in connection with a construction project as defined by the WHS Regulations 2011). The planned arrangements to ensure the works are carried out in accordance with the SWMS. The planned arrangements for monitoring and reviewing of the controls as specified in the SWMS. The planned arrangements for the revision of the SWMS when changes to the workplace are made, new or used plant and equipment is purchased or hired, design changes, new hazards are identified, new information is secured, WHS issues are raised by workers, when using hazardous substances or where required by the regulator. The planned arrangements for emergency preparedness response provisions specifically developed for the high risk work activities being undertaking. Work planning Work planning includes, but is not limited to: Identifying a risk management process in order to manage the hazards and risks associated with high risk construction work. Ensuring the risk management process associated with high risk construction work is carried out by a competent person(s). Identifying the required licences, certification, training and / or competencies for persons undertaking high risk construction work. Identifying relevant Commonwealth, State, Territory and local statutory requirements for high risk construction work.

5 Identify the contractual relationships between the parties (e.g. client, Principal Contractor, Construction Manager, Constructor, Project Manager, Engineer, Contractor, etc.) to ensure the roles and responsibilities for high risk construction work are clearly communicated and catered for. Identifying the type of works to be undertaken and the appropriate high risk construction work risk controls to be applied. Planning for high risk construction works that have hazards with exposure standards, such as noise and airborne contaminants, and the specific types of risk controls to be engaged. Planning for all potential emergency preparedness and response procedures appropriate for the particular circumstance. Document control Uncontrolled when Printed. Control Source: Optus Document System: Document CWHSS_S_St04_OM38061_V1F_15 th September Authorised / Owner: Optus WHS Team. Implement work planning In order to establish a safe workplace, the implementation of the above Work Planning, may include, but not be limited to the following: No SAMPLE - WORK PLANNING CHECKLIST YES NO NA Ensuring any residual design risk emanating from the Design Plan, Safety Report or similar is managed during construction, operation and/or maintenance and in accordance with the hierarchy of controls. Approving, communicating, consulting and implementing the risk assessment once the residual design risk emanating from the Design Plan, Safety Report or similar has been transferred into the workplace risk assessment. Ensuring the Principal Contractor is in receipt of a copy of the risk assessment such as a SWMS for high risk construction work. Conducting workplace inspections to identify high risk construction work hazards and risks and apply the necessary WHS control(s) and in accordance with the hierarchy of controls. Analysing any information and advice concerning high risk construction work hazards and risks and consider this information and advice when framing and documenting workplace risk assessment such as a SWMS. Providing access to information, training and instruction for workers having regards to the nature of the high risk construction work, the type of hazards and risks and the control measures. Securing necessary certificates and competencies required for undertaking high risk construction works including licencing, certificates and competencies requirements. Revising the risk assessment where changes to the workplace affect worker health and safety (e.g. when design is revised, altered or updated, when new or used plant and equipment is purchased or hired, new hazard is identified, when new information is secured, where WHS issues are raised by workers and when using hazardous chemicals and substances). Providing the necessary plant and equipment including personal protective equipment where the workplace risk assessment so determines. Ensuring the provision to cease unsafe work is upheld, where a worker or their health and safety representative, has a reasonable concern that to carry out the works would expose the worker to a serious risk to the worker s health and safety. Ensuring where the work is not in accordance with the risk assessment the work is stopped immediately or as soon as is reasonably practicably, and that the works recommence only

6 when in compliance with the risk assessment. Ensuring the workplace risk assessment is verified and audited at specified intervals, detailing any non-conformance, corrective actions and documented control. Ensuring emergency preparedness and response provisions such as plans, procedures, communications (internal and external) and hardware such as fire extinguishers are in place for the works and they are scheduled for testing at regular intervals.

linked to the Australian National University s Work health and safety policy and is one of the procedures within the WHS Management System.

linked to the Australian National University s Work health and safety policy and is one of the procedures within the WHS Management System. Purpose This procedure describes how the Australian National University evaluates and monitors contractors work health and safety for all activities performed at the University. This procedure ensures

More information

Contractor Safety Plan

Contractor Safety Plan Contractor Safety Plan INSTRUCTIONS Scope This form is to be completed by the contractor that has been identified as a major contract. This Plan expires at the completion of the contract work or 12 months

More information

Work Health and Safety Conditions

Work Health and Safety Conditions Work Health and Safety Conditions Table of Contents PURPOSE AND SCOPE... 1 RESPONSIBILITIES... 1 DEFINITIONS, ABBREVIATIONS AND ACRONYMS... 1 GENERAL WH&S & ELECTRICAL SAFETY REQUIREMENTS... 1 Compliance...

More information

WORK HEALTH AND SAFETY REFRESHER

WORK HEALTH AND SAFETY REFRESHER WORK HEALTH AND SAFETY REFRESHER LEARNING OUTCOMES Advice regarding legislative duties, rights and obligations WHSMS implementation and maintenance Identifying hazards; assessing risks; and developing,

More information

Contractor Management Procedure

Contractor Management Procedure Contractor Management Procedure Purpose Skillset Limited ( Skillset ) has a duty under the NSW Work Health and Safety Act and Regulations 2011 (the Legislation ) to prevent and/or to minimise risk in the

More information

This policy aims to ensure the health, safety and welfare of contractors working on UEL premises and those affected by their work.

This policy aims to ensure the health, safety and welfare of contractors working on UEL premises and those affected by their work. HR Services UEL Health and Safety Handbook Contractor Health and Safety Management Policy This policy is a sub-policy of the main University Health and Safety Policy Statement Introduction The University

More information

Vend Engineering Pty Ltd. Residential & Commercial construction Site Safety Pack For subcontractors

Vend Engineering Pty Ltd. Residential & Commercial construction Site Safety Pack For subcontractors Vend Engineering Pty Ltd Residential & Commercial construction Site Safety Pack For subcontractors Version 3 2015 Disclaimer The authors of the VEND Engineering Site Safety Pack (the Site Safety Pack)

More information

CAMBRIDGESHIRE GUIDED BUSWAY OPERATIONS POLICY

CAMBRIDGESHIRE GUIDED BUSWAY OPERATIONS POLICY CAMBRIDGESHIRE GUIDED BUSWAY OPERATIONS POLICY Page 1 of 7 CGB OPERATIONS POLICY Contents: 1. Introduction 2. Contents 3. General Policy 4. Safety Inductions 5. Access 6. Requirements and Restrictions

More information

Policy for Occupational Health, Safety and Environment Requirements for Contracted Construction and Maintenance Work

Policy for Occupational Health, Safety and Environment Requirements for Contracted Construction and Maintenance Work Policy for Occupational Health, Safety and Environment Requirements for Contracted Construction and Maintenance Work Policy Statement Rationale Construction and Maintenance work undertaken by contracted

More information

WHS Terminology. . where the person is engaged solely as a worker in, or as an officer of, that business or undertaking.

WHS Terminology. . where the person is engaged solely as a worker in, or as an officer of, that business or undertaking. WHS Terminology A person conducts a business or undertaking: (a) whether the person conducts the business or undertaking alone or with others; and (b) whether or not the business or undertaking is conducted

More information

Contractor Health and Safety Code of Practice. Updated June 4, 2018

Contractor Health and Safety Code of Practice. Updated June 4, 2018 Contractor Health and Safety Code of Practice 2018 Updated June 4, 2018 Updated June 4, 2018 TABLE OF CONTENTS A. DEFINITIONS...3 B. PURPOSE...7 C. STRATEGIC ALIGNMENT...7 D. REGULATORY CONSIDERATIONS...7

More information

Contractor Guidelines

Contractor Guidelines Contractor Guidelines This Guideline has been written to detail the minimum expectations with regards to contractor safety at Sodexo business units. It is the responsibility of the contractor to understand

More information

2016 CDM Smith All Rights Reserved July 2016 SECTION SAFETY, HEALTH, AND EMERGENCY RESPONSE

2016 CDM Smith All Rights Reserved July 2016 SECTION SAFETY, HEALTH, AND EMERGENCY RESPONSE PART 1 GENERAL 1.01 SCOPE OF WORK SECTION 01 11 01 SAFETY, HEALTH, AND EMERGENCY RESPONSE A. Pursuant to Section 107 of the Contract Work Hours and Safety Standards Act and DOL Regulations set forth in

More information

Occupational Safety & Health Policy & Guidelines for Contractors

Occupational Safety & Health Policy & Guidelines for Contractors Occupational Safety & Health Policy & Guidelines for Contractors Occupational Safety & Health Policy & Guidelines for Contractors Table of Contents Forward..1 Introduction... 1 Policy.1 City of Kalamunda

More information

Environmental Impairment Liability

Environmental Impairment Liability PROPOSAL FORM Environmental Impairment Liability Goods in Transit Pollution Liability (road) Underwritten by The Hollard Insurance Co. Ltd, an authorised Financial Services Provider www.itoo.co.za @itooexpert

More information

New Work Health & Safety Legislation What does it mean for you as a Business Owner, Director or Executive?

New Work Health & Safety Legislation What does it mean for you as a Business Owner, Director or Executive? New Work Health & Safety Legislation What does it mean for you as a Business Owner, Director or Executive? Session Overview The WHS Act 2011 became law in January 2012. This presentation outlines some

More information

SAFETY MANAGEMENT PLAN. WassonMoyCreativeCompliance

SAFETY MANAGEMENT PLAN. WassonMoyCreativeCompliance SAFETY MANAGEMENT PLAN WassonMoyCreativeCompliance TABLE OF CONTENTS FOREWORD... 3 LEGAL NOTICE... 3 1. INTRODUCTION TO THE PRODUCTION SAFETY MANAGEMENT PLAN... 4 1.1 SETTING OBJECTIVES AND TARGETS FOR

More information

Accident and Incident Reporting Policy and Procedure (including Notifiable Incidents Procedure)

Accident and Incident Reporting Policy and Procedure (including Notifiable Incidents Procedure) Purpose YPCT recognises the important role of accident and incident reporting, and investigation in ensuring the health, safety and welfare of all persons within the workplace. YPCT will ensure all accidents

More information

Memorandum of Understanding Victorian WorkCover Authority and Energy Safe Victoria

Memorandum of Understanding Victorian WorkCover Authority and Energy Safe Victoria Memorandum of Understanding Victorian WorkCover Authority and Energy Safe Victoria PARTIES Victorian WorkCover Authority ABN 90 296 467 627 ( WorkSafe Victoria ) the statutory authority responsible for

More information

Risk Assessment Procedure

Risk Assessment Procedure 1. Introduction Risk Assessment Procedure 1.1 The Management of Health and Safety at Work Regulations 1999 set out general duties which apply to employers and are aimed at improving health and safety management.

More information

MAIN CIVIL WORKS CONTRACT SCHEDULE 10 SAFETY TABLE OF CONTENTS

MAIN CIVIL WORKS CONTRACT SCHEDULE 10 SAFETY TABLE OF CONTENTS MAIN CIVIL WORKS CONTRACT SCHEDULE 10 SAFETY TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 GENERAL OCCUPATIONAL HEALTH AND SAFETY REQUIREMENTS... 2 2.1 Safety Areas... 2 2.2 General Duties

More information

SUB CONTRACTOR INDUCTION PACK

SUB CONTRACTOR INDUCTION PACK REQUIREMENTS FOR WORKING ON ROYAL MAIL PREMISES 1. INTRODUCTION AND PURPOSE This document sets out the arrangements that Royal Mail Property & Facilities Solutions Limited and Royal Mail [hereinafter jointly

More information

CORPORATE POLICY MANUAL

CORPORATE POLICY MANUAL Name of Policy: Contractor Safety Policy Policy Number: CPM-10-91 (replaces MPM-10-91) Responsibility: Health, Safety and Environment Department Approval: Chief Executive Officer Approval Date: March 13,

More information

AGREEMENT ON OCCUPATIONAL HEALTH AND SAFETY IN TERMS OF SECTION 37(2) OF THE OCCUPATIONAL HEALTH AND SAFETY ACT 85 OF 1993 (AS AMENDED) between

AGREEMENT ON OCCUPATIONAL HEALTH AND SAFETY IN TERMS OF SECTION 37(2) OF THE OCCUPATIONAL HEALTH AND SAFETY ACT 85 OF 1993 (AS AMENDED) between AGREEMENT ON OCCUPATIONAL HEALTH AND SAFETY IN TERMS OF SECTION 37(2) OF THE OCCUPATIONAL HEALTH AND SAFETY ACT 85 OF 1993 (AS AMENDED) between TELKOM SA SOC LIMITED (Registration number: 1991/005476/07)

More information

PEOP-048 OCCUPATIONAL HEALTH AND SAFETY MANAGEMENT SYSTEM FOR ENZED FRANCHISES

PEOP-048 OCCUPATIONAL HEALTH AND SAFETY MANAGEMENT SYSTEM FOR ENZED FRANCHISES OCCUPATIONAL HEALTH AND SAFETY MANAGEMENT SYSTEM FOR ENZED FRANCHISES 01 November This Occupational Health & Safety Management System (OHSMS) is a guide only to managing occupational health and safety

More information

Guideline for external contractors working on the premise of MANN+HUMMEL

Guideline for external contractors working on the premise of MANN+HUMMEL Guideline for external contractors working on the premise of MANN+HUMMEL 1 Purpose MHG-HS-I-0011 describes the regulations for health, safety and environment for external contractors working on the premise

More information

Environmental Impairment Liability

Environmental Impairment Liability PROPOSAL FORM Environmental Impairment Liability Fixed Facilities, Pipelines & Storage Tanks & Goods in Transit Pollution Liability (road) Underwritten by The Hollard Insurance Co. Ltd, an authorised Financial

More information

Contractor Safety Management Element November 2018

Contractor Safety Management Element November 2018 Contractor Safety Management Element November 2018 Table of Contents 1.0 Purpose... 1 2.0 Scope... 1 3.0 Definitions... 1 4.0 Roles and Responsibilities... 2 4.1 Project Management Team... 2 4.2 Contractors...

More information

National OHS Harmonisation

National OHS Harmonisation National OHS Harmonisation Your Questions Answered.. What are the new laws? Safe Work Australia is developing model work health and safety laws as part of an initiative of the Council of Australian Governments.

More information

Auckland Transport HS03-01 Risk and Hazard Management

Auckland Transport HS03-01 Risk and Hazard Management Auckland Transport HS03-01 Risk and Hazard Management (Procedure uncontrolled when printing) Relating to Standard: HS03 Risk and Hazard Management Standard December 2016 Health and Safety-Procedure-HS03-01

More information

Contractor Information

Contractor Information Contractor Information Contractor Induction Program Table of Contents Introduction... 1 Contractor Occupational Safety and Health Management Systems... 2 Safety Orientation Sessions for Contractors Employees...

More information

Appendix L Safety Notifiable Incident Flowchart

Appendix L Safety Notifiable Incident Flowchart Appendix L Safety Notifiable Incident Flowchart See the following pages for: Safety Notifiable Incident Flowchart Victoria; and Safety Notifiable Incident Flowchart - Tasmania June 2016 Version 4 1 of

More information

OHS RISK MANAGEMENT GUIDELINES

OHS RISK MANAGEMENT GUIDELINES OHS RISK MANAGEMENT GUIDELINES Contents 1 Introduction...2 2 Related UOW Documents...2 3 References and Applicable Legislation...2 4 Definitions...2 5 Responsibilities...3 5.1 Employees...3 5.2 Supervisors...3

More information

NGC1 - Element 4 - Health and safety management systems 3 - planning January RMS Publishing. Issued to: Single Licence Licence No:

NGC1 - Element 4 - Health and safety management systems 3 - planning January RMS Publishing. Issued to: Single Licence Licence No: Licence details NEBOSH National General Certificate RMS Publishing Victoria House, Lower High Street, Stourbridge DY8 1TA RMS Publishing. Sixth Edition January 2011. All rights reserved. No part of this

More information

Health & Safety Policy HSP 06 Asbestos Management Version Status Date Title of Reviewer Purpose/Outcome

Health & Safety Policy HSP 06 Asbestos Management Version Status Date Title of Reviewer Purpose/Outcome Health & Safety Policy HSP 06 Asbestos Management Version Status Date Title of Reviewer Purpose/Outcome 1.0 Draft 07.03.2016 David Maine 1 st Draft for consultation/review 1.1 Approved 22.12.2016 David

More information

WORKING WITH CONTRACTORS POLICY AND PROCEDURE

WORKING WITH CONTRACTORS POLICY AND PROCEDURE WORKING WITH CONTRACTORS POLICY AND PROCEDURE CROWN SECURITY CONTRACTORS & OSH (i) Preface Contract work is becoming increasingly common in the modern workplace management culture, and has been a feature

More information

RISK ASSESSMENT POLICY 2018

RISK ASSESSMENT POLICY 2018 RISK ASSESSMENT POLICY 2018 INTRODUCTION A risk assessment is an important tool in protecting employees, parents, children and visitors by analysing hazards and identifying risk reduction measures. The

More information

Aide Memoire for Fieldwork

Aide Memoire for Fieldwork Aide Memoire for Fieldwork Description of Fieldwork Full Itinerary Dates Name of Work Organiser Name of Travel Organiser This Aid Memoire can be used by Work Organisers, Travel Organisers and Authorising

More information

ANSI A10.1 Pre-Project/Pre-Task Safety & Health Planning

ANSI A10.1 Pre-Project/Pre-Task Safety & Health Planning ANSI A10.1 Pre-Project/Pre-Task Safety & Health Planning Presenter: Pete Chaney May -2012 ANSI A10 Construction & Demolition Operations Committee Employer Employee Technical Membership 1 CII Zero Injury

More information

Health and Safety Procedure: Risk Assessment. 1. Introduction

Health and Safety Procedure: Risk Assessment. 1. Introduction Health and Safety Procedure: Risk Assessment 1. Introduction 1.1. The purpose of this Procedure is to set out the London School of Economics (hereafter the School or LSE) arrangements for undertaking risk

More information

Submission to. WorkSafe Victoria Proposed Occupational Health and Safety Regulations 2017

Submission to. WorkSafe Victoria Proposed Occupational Health and Safety Regulations 2017 Submission to WorkSafe Victoria Proposed Occupational Health and Safety Regulations 2017 09 September 2016 1. INTRODUCTION...3 2. RESPONSE TO SPECIFIC REGULATIONS...3 DRAFT REGULATION 5 - DEFINITIONS...

More information

MARKET OH&S PLAN 1 INTRODUCTION 2 OH&S RESPONSIBILITIES

MARKET OH&S PLAN 1 INTRODUCTION 2 OH&S RESPONSIBILITIES 1 INTRODUCTION Melbourne Market Authority (MMA) is committed to a safety culture and practices that provide for a healthy and safe working environment. The health and safety of all those who work for us

More information

Appendix 4 :Contractors Health and Safety Questionnaire (Form CCHSQ1) 1. DETAILS OF CONTRACTOR / SUB-CONTRACTOR Name of Company:

Appendix 4 :Contractors Health and Safety Questionnaire (Form CCHSQ1) 1. DETAILS OF CONTRACTOR / SUB-CONTRACTOR Name of Company: Appendix 4 :Contractors Health and Safety Questionnaire (Form CCHSQ1) 1. DETAILS OF CONTRACTOR / SUB-CONTRACTOR Name of Company: Address: Telephone Number: Contact for Further Information: Email Address:

More information

Risk Assessment Policy

Risk Assessment Policy Risk Assessment Policy Updated: April 2018 Date of next Review: April 2019 Policy Lead: Bursar Checked by: Middle Leadership Team 1. INTRODUCTION Beachborough School will have hazards which if not controlled

More information

Contractor Compliance Review Procedure

Contractor Compliance Review Procedure Contractor Compliance Review Procedure 2. Amendments and Distribution Notes on Document Control This document is the property of Edinburgh Airport Limited (EAL) and its contents are confidential. It must

More information

HAZARD IDENTIFICATION AND ASSESSMENT

HAZARD IDENTIFICATION AND ASSESSMENT SOP-28 Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 11 Purpose To provide guidelines for identifying, assessing and controlling workplace hazards; To ensure the potential

More information

Policy. Safety risk assessment. 1 Why use risk assessment?

Policy. Safety risk assessment. 1 Why use risk assessment? Safety risk assessment V E R S I O N 1. 1 M A R C H 2 0 0 5 1 Why use risk assessment? 1.1 The principle reason for conducting risk assessments is to comply with our legal duty. The Management of Health

More information

Health and Safety Management System Overview

Health and Safety Management System Overview Health and Safety Management System Overview 24 January 2018 DOCUMENT CONTROL Document Identifier HS007 (previously HS1001) Version 1 Date of Issue 24/01/2018 Version History Version Date Nature of Amendment

More information

SUPPLY OF PEST CONTROL SERVICES

SUPPLY OF PEST CONTROL SERVICES . SUPPLY OF PEST CONTROL SERVICES TENDER DETAILS: DURATION: Tenders should be prepared on the basis of a twelve (12) month arrangement commencing 1 st July 2018. CLOSING DATE: Monday 28th May 2018. TENDER

More information

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd. TRANSNET LIMITED (Registration no. 1990/000900/06) PRIEVIEW COPY ONLY

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd. TRANSNET LIMITED (Registration no. 1990/000900/06) PRIEVIEW COPY ONLY TRANSNET LIMITED (Registration no. 1990/000900/06) SAFETY ARRANGEMENTS AND PROCEDURAL COMPLIANCE WITH THE OCCUPATIONAL HEALTH AND SAFETY ACT (ACT 85 OF 1993) AND APPLICABLE REGULATIONS 1. General 1.1 The

More information

CN Course Exercise. c. Ensure all employees have received the required training for their work.

CN Course Exercise. c. Ensure all employees have received the required training for their work. CN Course Exercise First Name Last Name If you facilitated this course and persons other than you went through this course, please fill out their names below. Each student must be individually regis tered

More information

Combined Liability Proposal Form

Combined Liability Proposal Form Combined Liability Proposal Form 1. Full name of the Insured (including the name of all subsidiary companies): 2. Date Business established: 3. Period of Insurance 4. Business Address (if more than one

More information

Asbestos Management. Date of Approval: Date for Next Scheduled Review: Review Body: Equality Impact Assessment Complete: Policy Published on Web:

Asbestos Management. Date of Approval: Date for Next Scheduled Review: Review Body: Equality Impact Assessment Complete: Policy Published on Web: Asbestos Management Policy Title: Policy Author: Date of Approval: Date for Next Scheduled Review: Review Body: Asbestos Management Diane Hendry MC Equality Impact Assessment Complete: Policy Published

More information

Between the Western Sydney Parklands Trust (the Trust) (LAND OWNER) and

Between the Western Sydney Parklands Trust (the Trust) (LAND OWNER) and PERMIT TO ENTER Between the Western Sydney Parklands Trust (the Trust) (LAND OWNER) and (ENTRANT) DEED made the day of, over land at / known as: Address Western Sydney Parklands Certificate of Title LAND

More information

UC DAVIS. Plant Biology INJURY AND ILLNESS PREVENTION PROGRAM

UC DAVIS. Plant Biology INJURY AND ILLNESS PREVENTION PROGRAM Plant Biology UC DAVIS Plant Biology INJURY AND ILLNESS PREVENTION PROGRAM This Injury and Illness Prevention Program has been prepared by the University of California, Plant Biology department in accordance

More information

Asbestos Management Policy

Asbestos Management Policy Asbestos Management Policy Originator: Executive Management Team Approval Date: Policy and Strategy Policy 18 July 2017 Review date: July 2018 1 Introduction 1.1 1.2 1.3 1.4 The scope of this Policy sets

More information

Control of Asbestos Regulations 2012 (SI 2012 No. 632)

Control of Asbestos Regulations 2012 (SI 2012 No. 632) Control of Asbestos Regulations 2012 (SI 2012 No. 632) Part 1: Preliminary Part 1 covers commencement, interpretation and application. 2: Interpretation This contains a number of definitions. Of particular

More information

Contractor Pre-qualification Questionnaire

Contractor Pre-qualification Questionnaire Contractor Pre-qualification Questionnaire This document shall be used to determine qualifications of contractors who shall work under Anderson Engineering Co., Inc. (AECI). AECI shall use this document

More information

HULCHER CONTRACTOR SAFETY MANAGEMENT PROCESS

HULCHER CONTRACTOR SAFETY MANAGEMENT PROCESS Hulcher Services is initiating a mission to improve safety for its employees, contractors, subcontractors, visitors, and general public. The Hulcher Contractor Safety Management Process (HCSMP) was developed

More information

Single Contractor Agreement for Occupational Health & Safety Workers Compensation Act

Single Contractor Agreement for Occupational Health & Safety Workers Compensation Act Single Contractor Agreement for Occupational Health & Safety Workers Compensation Act Instructions This is a fillable form. However, you must first save the form before entering information or the data

More information

APPLICATION PACKAGE FOR LISTING AS A PROVIDER FOR WATER SERVICE CONNECTIONS (DRILLERS) TO THE MANAGING NEW DEVELOPMENTS PROCESS

APPLICATION PACKAGE FOR LISTING AS A PROVIDER FOR WATER SERVICE CONNECTIONS (DRILLERS) TO THE MANAGING NEW DEVELOPMENTS PROCESS APPLICATION PACKAGE FOR LISTING AS A PROVIDER FOR WATER SERVICE CONNECTIONS (DRILLERS) TO THE MANAGING NEW DEVELOPMENTS PROCESS For information regarding this package contact: Provider Registrar Urban

More information

1.3 All employees are equally responsible for complying with the Ontario Occupational Health & Safety Act and its Regulations.

1.3 All employees are equally responsible for complying with the Ontario Occupational Health & Safety Act and its Regulations. Revision No: 1 Page: 1 of 14 1.0 PURPOSE 1.1 The purpose of this policy is to establish guidelines for contractors in order to provide and maintain a safe work environment for all employees. Advance planning

More information

Strata Management Agency Agreement

Strata Management Agency Agreement Strata Management Agency Agreement Date Owners Corporation Name The Owners - Strata Plan No. ABN Short form name owners corporation Notice details Address of strata scheme: Facsimile: Attention: E.mail:

More information

PUBLIC COMPANY ORLEN LIETUVA OCCUPATIONAL HEALTH AND SAFETY PROCEDURE FOR CONTRACTORS BDS-40 I. GENERAL. Purpose and Scope of Application

PUBLIC COMPANY ORLEN LIETUVA OCCUPATIONAL HEALTH AND SAFETY PROCEDURE FOR CONTRACTORS BDS-40 I. GENERAL. Purpose and Scope of Application PUBLIC COMPANY ORLEN LIETUVA APPROVED BY Director of Quality, Labour Safety and Environmental Control 12 October 2017 Order No TV1(1.2-1)-348 OCCUPATIONAL HEALTH AND SAFETY PROCEDURE FOR CONTRACTORS BDS-40

More information

Mine Health and Safety Regulation 2007

Mine Health and Safety Regulation 2007 New South Wales Mine Health and Safety Regulation 2007 under the Mine Health and Safety Act 2004 Her Excellency the Governor, with the advice of the Executive Council, has made the following Regulation

More information

Risk assessment Policy and Procedures

Risk assessment Policy and Procedures Risk assessment Policy and Procedures 1. Introduction The purpose of risk assessment is to identify hazards and evaluate any associated risks to health and safety arising from Youth Works activities, enabling

More information

WorkSafe Victoria inspectors

WorkSafe Victoria inspectors WorkSafe Victoria inspectors How inspectors support and enforce health and safety at work April 2012 1 Contents Introduction 3 Health and safety laws 3 Role of WorkSafe Victoria inspectors 3 Information

More information

POWER CONSTRUCTION COMPANY CCIP PROGRAM SAFETY REQUIREMENTS

POWER CONSTRUCTION COMPANY CCIP PROGRAM SAFETY REQUIREMENTS POWER CONSTRUCTION COMPANY CCIP PROGRAM SAFETY REQUIREMENTS The following requirements apply to all subcontractors including tier subcontractors, vendors, deliveries, visitors and the like (herein known

More information

NFF Contract Template Labour Hire

NFF Contract Template Labour Hire NFF Contract Template Labour Hire Initial: Page 1 of 2 This template is for use with contractors who want to supply workers to your business. It is a standard form contract that you can use to help protect

More information

Alcumus Health and safety assessment standards

Alcumus Health and safety assessment standards Alcumus Health and safety assessment standards Comply with your assessment duties as a client Gain greater visibility of the anticipated risks throughout your supply chain Document Code: TG-S-01 Version:

More information

ASBESTOS CONTAINING MATERIALS POLICY

ASBESTOS CONTAINING MATERIALS POLICY ASBESTOS CONTAINING MATERIALS POLICY 1.0 INTRODUCTION 1.1 Almond Housing Association Limited (AHA Ltd.) recognises the risks to the health of those who have to work with materials containing asbestos (ACM

More information

SAFETY POLICY PART 1 - GENERAL POLICY

SAFETY POLICY PART 1 - GENERAL POLICY SAFETY POLICY PART 1 - GENERAL POLICY a. The Scope of This Policy This is the Safety Policy of National Game Fair Ltd (the Organiser) as required by Section 2(3) of the Health and Safety at Work Act 1974,

More information

San Antonio Water System PROJECT CONSTRUCTION PROGRAM HEALTH AND SAFETY PROGRAM

San Antonio Water System PROJECT CONSTRUCTION PROGRAM HEALTH AND SAFETY PROGRAM PROJECT CONSTRUCTION PROGRAM HEALTH AND SAFETY PROGRAM SEPTEMBER 2007 TABLE OF CONTENTS INTRODUCTION... 2 SAFETY RESPONSIBILITIES, AUTHORITY AND ACCOUNTABILITY... 3 REGULATORY AGENCIES... 3 SAWS... 4

More information

UNDERGROUND SERVICE STRIKES

UNDERGROUND SERVICE STRIKES UNDERGROUND SERVICE STRIKES GUIDELINES FOR CONSTRUCTION COMPANIES An underground service strike can lead to injury or loss of life and the costs to your business can be substantial. This short guide is

More information

Power Construction Company CCIP Program Safety Requirements

Power Construction Company CCIP Program Safety Requirements Introduction The following safety requirements (herein known as safety requirements) apply to all subcontractors including tier subcontractors, employees, consultants, vendors, deliveries, visitors and

More information

Guidance. For Departments on Engaging External Service Providers

Guidance. For Departments on Engaging External Service Providers Guidance For Departments on Engaging External Service Providers Jan 2012 CONTENTS 1 Introduction 1.1 University Policy 1.2 Purpose of this Guidance 2. Main activities of Department Supervising Officers

More information

Health & Safety Policy

Health & Safety Policy Fairfield Village Hall Health & Safety Policy 1 Contents Part 1 General Statement of Policy... 3 Part 2: Organisation of Health and Safety... 4 Part 3 Arrangements and Procedures... 6 3.1 Licence... 6

More information

Vehicle Policy Organisation and Management. The University of Edinburgh

Vehicle Policy Organisation and Management. The University of Edinburgh The University of Edinburgh Vehicle Policy 2007 Introduction This policy aims to reduce legal, health and safety and financial liability and to control costs of managing University vehicles. The objective

More information

Hazard Identification and Risk Management Element June 2018

Hazard Identification and Risk Management Element June 2018 Hazard Identification and Risk Management Element June 2018 Table of Contents 1.0 Purpose... 1 2.0 Scope... 1 3.0 Definitions... 1 4.0 Roles and Responsibilities... 2 4.1. Senior Executives, Deans and

More information

Contractor s Environmental Health & Safety Disclosure

Contractor s Environmental Health & Safety Disclosure Contractor s Environmental Health & Safety Disclosure Company Name: Application Date: Address: Phone#: Fax #: Email : Company Contacts: Name Position Environmental Health & Safety (EHS) Personnel: Name

More information

Management Commitment. BEST Level 3 Guidance. Actions to Achieve Desired Outcomes

Management Commitment. BEST Level 3 Guidance. Actions to Achieve Desired Outcomes Management Leadership and Employee 1 Involvement Take proactive steps to build on earlier gains to improve the culture, systems, policies, and procedures that support a safe and healthy work environment.

More information

Hazard Assessment, Analysis and Control

Hazard Assessment, Analysis and Control Hazard Assessment, Analysis and Control Page 1 Section 2 Hazard Assessment, Analysis and Control HAZARD ASSESSMENT POLICY Hazard Assessment Policy - Sample 1...4 Hazard Assessment Policy Sample 2...5 HAZARD

More information

San Antonio Water System Standard Specifications for Construction

San Antonio Water System Standard Specifications for Construction ITEM NO. 902 Construction Safety And Health Program 902.1 DESCRIPTION: This item shall govern the preparation and implementation of the contractor s Constuction Safety and Health Program for the specified

More information

Carson, CA Inland Star Distribution Centers, Inc. PSM/CalARP

Carson, CA Inland Star Distribution Centers, Inc. PSM/CalARP Carson, CA Inland Star Distribution Centers, Inc. PSM/CalARP CONTRACTOR PROGRAM Revision History Rev. # Description of Change Date Revised By 0 Initial Issues July 2016 PSM RMP Solutions Purpose The purpose

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan 24-28 Childs Road Chipping Norton NSW 2170 Version 1 Initial Release Date: 2 nd February 2015 PIRMP Barca Metals 24-28 Childs Road, Chipping Norton NSW 2170

More information

GUIDE BUSINESS & INDUSTRY A STEP-BY-STEP APPROACH TO EMERGENCY PLANNING, RESPONSE AND RECOVERY FOR COMPANIES OF ALL SIZES

GUIDE BUSINESS & INDUSTRY A STEP-BY-STEP APPROACH TO EMERGENCY PLANNING, RESPONSE AND RECOVERY FOR COMPANIES OF ALL SIZES GUIDE EMERGENCY MANAGEMENT GUIDE FOR BUSINESS & INDUSTRY A STEP-BY-STEP APPROACH TO EMERGENCY PLANNING, RESPONSE AND RECOVERY FOR COMPANIES OF ALL SIZES Sponsored by a Public-Partnership with the Federal

More information

WHS Risk Assessment and Control Form Science on the Road, CSU Albury-Wodonga Wednesday 2 & Thursday 3 November 2016

WHS Risk Assessment and Control Form Science on the Road, CSU Albury-Wodonga Wednesday 2 & Thursday 3 November 2016 WHS Risk Assessment and Control Form Science on the Road, CSU Albury-Wodonga Wednesday 2 & Thursday 3 November 2016 Step 1: Who has conducted the Risk Assessment Risk Assessment completed by (name): Geoff

More information

Event Name: Smokin Hot Stanley Date of Event: 7 th May 2017 Contact Name: Jade Miles Contact Number: EVENT MANAGEMENT PLAN

Event Name: Smokin Hot Stanley Date of Event: 7 th May 2017 Contact Name: Jade Miles Contact Number: EVENT MANAGEMENT PLAN Event Name: Smokin Hot Stanley Date of Event: 7 th May 2017 Contact Name: Jade Miles Contact Number: 0418520554 EVENT MANAGEMENT PLAN 1. EVENT DETAILS Event place and time Name of event: Smokin Hot Stanley

More information

Site-Specific Health and Safety Agreement

Site-Specific Health and Safety Agreement : Company Site Name Complete pre-start This agreement establishes the basis on which businesses (including trades and other organisations) agree to work on a specific construction site. A Site-Specific

More information

CENTRAL GOLDFIELDS SHIRE COUNCIL TENDER G CIVIL & TRAFFIC ENGINEERING CONSULTANCY SERVICES

CENTRAL GOLDFIELDS SHIRE COUNCIL TENDER G CIVIL & TRAFFIC ENGINEERING CONSULTANCY SERVICES 0 CENTRAL GOLDFIELDS SHIRE COUNCIL TENDER G530-09 CIVIL & TRAFFIC ENGINEERING CONSULTANCY SERVICES 1 TABLE OF CONTENTS Page No. 1. NOTICE TO TENDERERS AND GENERAL CONDITIONS OF TENDERING...3 2. SCHEDULE

More information

CONTRACTOR PRE-QUALIFICATION FORM

CONTRACTOR PRE-QUALIFICATION FORM Doc..: Rev../Date: C 3/28/2017 Page: 1 of 13 GENERAL INFORMATION 1 Person Completing this PQF: Title: Telephone: Fax: E-mail Address: 2 Contact for Requesting Bids: Title: Telephone: Fax: E-mail Address:

More information

Safety Inspector (Railway Safety Inspector) SECTION 2: OCCUPATIONAL PROFILE

Safety Inspector (Railway Safety Inspector) SECTION 2: OCCUPATIONAL PROFILE 325705 Safety Inspector (Railway Safety Inspector) SECTION 2: OCCUPATIONAL PROFILE 1. Occupational Purpose Railway Safety Inspector inspects railway operations, audits railway safety management systems

More information

ATTACHMENT "I" SUBCONTRACTOR SAFETY, HEALTH, AND ENVIRONMENTAL MINIMUM PERFORMANCE STANDARD (MPS)

ATTACHMENT I SUBCONTRACTOR SAFETY, HEALTH, AND ENVIRONMENTAL MINIMUM PERFORMANCE STANDARD (MPS) ATTACHMENT "I" SUBCONTRACTOR SAFETY, HEALTH, AND ENVIRONMENTAL MINIMUM PERFORMANCE STANDARD (MPS) Swinerton Builders, Inc. (SWINERTON) constantly strives to provide a safe and productive work environment.

More information

A UNIQUE AND COMPREHENSIVE INSURANCE SCHEME FOR THE ELECTRICAL INDUSTRY

A UNIQUE AND COMPREHENSIVE INSURANCE SCHEME FOR THE ELECTRICAL INDUSTRY .. A UNIQUE AND COMPREHENSIVE INSURANCE SCHEME FOR THE ELECTRICAL INDUSTRY PROPOSAL FORM Camberford Law plc Innovative Insurance solutions Since 1958 Insurance Brokers Underwriting Agents Authorised and

More information

CASTAIC LAKE WATER AGENCY STANDARD CONTRACT RISK TRANSFER PROVISIONS, GENERAL CONDITIONS and REQUIRED INSURANCE for

CASTAIC LAKE WATER AGENCY STANDARD CONTRACT RISK TRANSFER PROVISIONS, GENERAL CONDITIONS and REQUIRED INSURANCE for CASTAIC LAKE WATER AGENCY STANDARD CONTRACT RISK TRANSFER PROVISIONS, GENERAL CONDITIONS and REQUIRED INSURANCE for SMALL CONSTRUCTION CONTRACT Typical CLWA services that would use Small Contracts with

More information

MERCHANT SHIPPING (HEALTH AND SAFETY AT WORK) REGULATIONS 2003 BR 52/ 2004 MERCHANT SHIPPING ACT : 35

MERCHANT SHIPPING (HEALTH AND SAFETY AT WORK) REGULATIONS 2003 BR 52/ 2004 MERCHANT SHIPPING ACT : 35 BR 52/ 2004 MERCHANT SHIPPING ACT 2002 2002 : 35 MERCHANT SHIPPING (HEALTH AND SAFETY AT WORK) REGULATIONS 2004 ARRANGEMENT OF REGULATIONS 1 Citation PART I General 2 Interpretation 3 Application PART

More information

Between the Parramatta Park Trust (the Trust) (LAND OWNER) and

Between the Parramatta Park Trust (the Trust) (LAND OWNER) and PERMIT TO ENTER Between the Parramatta Park Trust (the Trust) (LAND OWNER) and (ENTRANT) DEED made the day of, over land at / known as: Address Parramatta Park Certificate of Title LAND OWNER Parramatta

More information

PLEASE NOTE. For more information concerning the history of this Act, please see the Table of Public Acts.

PLEASE NOTE. For more information concerning the history of this Act, please see the Table of Public Acts. PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this Act, current to January 1, 2009. It is intended for information and reference purposes only. This

More information

Evolution and Ecology

Evolution and Ecology Evolution and Ecology Reviewed and Revised December 2015 UC DAVIS Evolution and Ecology INJURY AND ILLNESS PREVENTION PROGRAM This Injury and Illness Prevention Program has been prepared by the University

More information

The regulation applies to the actor offering the amusement device to the use of the public.