Risk Management Plan for the Ocean Observatories Initiative

Size: px
Start display at page:

Download "Risk Management Plan for the Ocean Observatories Initiative"

Transcription

1 Risk Management Plan for the Ocean Observatories Initiative Version 1.0 Issued by the ORION Program Office July 2006 Joint Oceanographic Institutions, Inc New York Ave NW, Suite 400, Washington, D.C

2 Document Control Sheet Record of Issue Issue Date Document Status Version 1.0 July 2006 Initial Release Revisions Date Description of Change 2

3 TABLE OF CONTENTS SECTION PAGE TABLE OF CONTENTS...3 LIST OF FIGURES...4 LIST OF TABLES...4 LIST OF ACRONYMS AND ABBREVIATIONS OOI PROGRAM PROGRAM GOALS PROGRAM RISK MANAGEMENT OBJECTIVES APPROACH TO RISK MANAGEMENT RISK CATEGORIES Technical Risk Schedule Risk Cost Risk RISK MANAGEMENT STRUCTURE Risk Planning Risk Assessment Risk Handling Risk Monitoring ORGANIZATION MANAGEMENT OVERVIEW RISK MANAGER RISK MANAGEMENT DEFINITIONS RISK MANAGEMENT PROCESS RISK ASSESSMENT Risk Rating System RISK HANDLING Risk Control Risk Avoidance Risk Assumption Risk Transfer RISK MONITORING Watch List Reports RISK DOCUMENTATION...10 APPENDIX A RISK INFORMATION FORM INSTRUCTIONS FOR COMPLETING THE RISK INFORMATION FORM

4 LIST OF FIGURES FIGURE PAGE Figure 2-1. OOI Risk Management Structure...3 Figure 3-1. OOI Risk Management Organization...5 Figure 4-1. OOI Risk Management Process...10 Figure 4-2. Risk Rating Matrix...11 LIST OF TABLES TABLE PAGE Table 4-1. Likelihood Criteria Table 4-2. Consequence Criteria LIST OF ACRONYMS AND ABBREVIATIONS IO JOI NSF OOI WBS RMT Implementing Organization Joint Oceanographic Institutions National Science Foundation Ocean Observatories Initiative Work Breakdown Structure Risk Management Team 4

5 1. OOI PROGRAM The OOI program is responsible for implementing the U.S. scientific community's requirements for an a networked observatory for conducting basic oceanography using cabled, buoyed and mobile platforms and using funds from the National Science Foundation (NSF). The program is managed by the Joint Oceanographic Institutions (JOI) and a group of academic institutions called Implementing Organizations (IO's) The OOI will provide the infrastructure to allow a wide range of spatial scales, from local coastal phenomena to global scale. This observatory will allow transformational science to be conducted to better understand: (1) The deep biosphere and the seafloor ocean (2) Environmental change, processes, and effects (3) Solid Earth cycles and geodynamics 1.1 Program Goals The primary goal of the OOI program is to develop an ocean observatory meeting the science plan and within budgetary and schedule constraints. The budget has been fixed at $309.5M over six years. The OOI design relies heavily upon creative, efficient, and effective use of proven but relatively recent technologies. Mitigation of risk in this environment must be concerned with equipment development, cyberinfrastructure and program management. 1.2 Program Risk Management Objectives Risk management is defined as a systematic approach to identifying, analyzing, and controlling areas or events with a potential for causing unwanted change. It is through risk management that risks to the program are assessed and systematically managed to reduce risk to an acceptable level. The OOI program has established the following risk management objectives: a. To develop and implement a risk management process with risk assessment, handling, and monitoring functions; to define and generate risk watch lists; and to apply metrics to assess the implementation of alternative concepts. b. To establish quantified acceptable risk levels to be achieved and to define the risks and proposed risk mitigation steps to be addressed during design and construction. 1

6 2. APPROACH TO RISK MANAGEMENT Risk is an undesirable situation or circumstance, generally associated with uncertainties, that has both a likelihood of occurring and a potential consequence to the program. Risk management is an organized process to effectively reduce such risks to achieve program goals. The process includes identification, assessment and analysis of potential risks, implementation of risk-handling options, and a monitoring effort to track the effectiveness of the risk management program. The goal of risk management is to define methods or identify alternatives that mitigate or minimize risks to an acceptable level. 2.1 Risk Categories Four types of risk could affect the OOI Program: Technical Risk Schedule Risk Cost Risk Operational Risk? Programmatic Risk Technical Risk Technical risk is risk associated with a new design that provides an increased level of performance relative to existing system. This category also includes the supportability risks associated with fielding and maintaining new OOI subsystems Schedule Risk Schedule risks are risks whose occurrences could delay program schedules Cost Risk Cost risk is the risk to a program associated with overrunning program budget. As stated in section 1.1, the budget has been fixed at $309.5M over six years Operational Risk Operational risks are risks that may make the OOI more expensive to operate and maintain but have minimal or no risk to the OOI development program Programmatic Risk Programmatic risks are risks associated with circumstances outside the program management s control but which could affect the program s direction (e.g., budget cuts, labor disputes, concurrent development and manufacturing, etc) 2

7 2.2 Risk Management Structure Risk management consists of four separate but interrelated activities: Risk Planning Risk Assessment Risk Handling Risk Monitoring These are shown in perspective in Figure 2-1. To ensure success, all activities in the risk management process should be documented. Execution Phase Risk Planning Risk Assessment Risk Handling Risk Monitoring Requirements Responsibilities Definitions Resources Procedures Risk Events Analysis Update Assessments Document Findings Mitigation Tasks Metrics Report Metrics Track Status Report Documentation Figure 2-1. OOI Risk Management Structure Risk Planning The first stage of risk management is to plan the activity. Risk planning is the umbrella term for the systematic process of reducing or eliminating the undesirable occurrences inherent in programs. Effective risk planning ensures that risk is identified and minimized, alternatives are developed and time and/or money is identified to cover the risks that cannot be avoided. Risk planning is an integral part of the routine Program Office functions. It becomes especially important as major scheduled events approach. This Risk Management Plan is to be used to identify the risk management process and provide the framework for executing the process Risk Assessment Risk assessment consists of identification and quantification of program risks. Risk identification is the process of exposing the risks that have a realistic potential of harming the program. Risk identification is not intended to uncover every possible unfortunate incident that could happen. There are various techniques used to identify risk. In general, the OOI program will identify risk by analogy comparisons with prototype systems and by discussion at program documentation reviews. After the risks are identified, a quantification method is used to organize and stratify the risks. This process does not need to be complicated. The goal is to prioritize the list of risks and identify those that require the most management attention. Ratings of Low, Medium and High are sufficient. A risk 3

8 assessment (rating) mechanism is required to consistently apply a quantitative rating to risk items as they are identified. This rating system is discussed in detail in section Risk Handling Risk Handling is the action (or inaction) taken in response to an identified risk, after it has been identified and assessed. There are four basic actions that can be taken in response to handling a risk item. These actions are avoidance, control, assumption, and transfer. Avoidance is the act of not accepting an option because of the unfavorable aspects. Selecting a lower risk approach is an example of risk avoidance. Control is the process of applying management attention to a situation by continually monitoring and correcting a series of events or processes. Risk assumption is the conscious decision to accept the consequences of a particular risk. Simply stated, it s the I ll take the chance approach. Transfer is the process of sharing a risk with another party (normally the contractor) and may take the form of program compromises or cost sharing Risk Monitoring The last step in the risk management process is risk monitoring. The monitoring process systematically tracks and evaluates the effectiveness of risk handling actions against established metrics. Monitoring results also provide a basis for developing additional handling options and identifying new risks. The key to the monitoring process is to establish a cost, schedule, and performance management indicator system over the entire program. The JOI OOI Director uses this indicator system to evaluate the status of the program. The indicator system is designed to provide early warning of potential problems so that management can take action. Risk monitoring is not a problem-solving technique, but rather, a proactive technique to observe the results of risk handling and to identify new risks. Risk monitoring will be accomplished by periodic Risk Management Team (RMT) review of the risk register considering approved program documentation. The risks will be discussed in relation to the contractual capabilities desired by NSF and the program baseline. Results of monitoring activities will be captured in the watch list and cost/performance reports. 4

9 3. ORGANIZATION In one sense, everyone involved in the OOI conversion program contributes to risk management; i.e., all program participants are responsible for exposing risk items within their purview so that the negative impact of such risks can be minimized. But the organization that deals with risk on a regular basis is the Risk Management Team (RMT). (Figure 3-1) Risk Management Team Risk Manager CI IO JOI Acting Risk Director Risk Manager CSO IO SAC Rep Risk Manager RCO IO Risk Manager GSO IO Figure 3-1. OOI Risk Management Organization The RMT is comprised of the Risk Managers from each of the IO's and the lead for risk on the JOI Project Office Team. Also, there will be occasions when technical experts may be asked to attend RMT meetings to effectively evaluate or address risk issues. 3.1 Management Overview The JOI Director of OOI is ultimately accountable for execution of the OOI program and for managing the risks associated with delivering the modified OOI to the NSF. But the Director is responsible for many tasks in addition to risk management. Because of the broad demands of this position, the Director has delegated much of the OOI risk management functions to the Risk Manager. 3.2 Risk Manager The Risk Manager is responsible for all routine risk management activities and reports directly to the Director on significant risk issues. The Risk Manager generally adjudicates (i.e., approves or disapproves) risk handling and monitoring actions. In cases where high profile items are involved, the Risk Manager will defer approval to the Director, providing complete details and background information for the proposed action. Rosie Lunde, Senior Project Engineer for OOI has been designated as the acting Risk Manager. 5

10 4. RISK MANAGEMENT Risk management is a process whereby technical, schedule, cost, and programmatic risks to the program are identified, analyzed, and reduced or eliminated. For the OOI, the risk management process will engage all disciplines of the program and provide management with a systematic, decision-making tool for addressing potential risk issues. Through the risk management process, the OOI risk team: Identifies the risks to the program Analyzes the impact these risks could have should they materialize Prioritizes the risks so that program-threatening risks are given top management attention Makes adjustments to mitigate (eliminate or acceptably reduce) these risks Monitors actions to ensure adjustments were adequate Tracks the risk status of the program to determine if additional risk management procedures are needed This process enables the OOI Director to effectively manage risk and determine the potential effect risk will have on the program schedule and budget. 4.1 Definitions These definitions facilitate an understanding of OOI risk management. Risk the Likelihood of an undesirable event occurring and the significance of the consequence of the occurrence. Note that risk has two components Likelihood and consequence. Risk Management an organized, systematic, decision-making process that efficiently identifies risks, analyses risks, and effectively reduces or eliminates risks for the purpose of achieving program goals. Risk Event any event that has a realistic Likelihood of creating an undesirable effect on the technical, schedule, cost or programmatic aspects of the program. Risk Assessment the process of identifying and analyzing program risks. Risk Identification investigating all aspects of the program with the goal of identifying areas of risk and their corresponding potential impacts. Risk Analysis examining each identified risk event to refine the description of the risk, isolating the cause and determining effects should the risk event occur. Mitigation Analysis the process of examining the impact to the program of each individual risk and considering potential consequences if risk inputs are revised. Risk Handling the action (or inaction) taken in response to an identified risk after it has been quantified and analyzed. Risk Monitoring the process that systematically tracks and evaluates the performance of riskhandling actions against established metrics throughout the acquisition process and develops further riskhandling options, as appropriate. Program Risk the Likelihood of not achieving a defined goal in the following risk categories (see section 2.1 for further discussion): Technical Schedule Cost Operational 6

11 Programmatic 4.2 Risk Management Process The risk management process (Figure 4-1) is a closed-loop course of action used to identify, analyze, and manage risk items. The tools and techniques used within this process are described in the following sections. Risk items are maintained and tracked within the OOI risk database. The status of the risk program and active risk handling activities are presented as needed during RMT meetings and all program reviews. In addition, selected reports are available in the document management system. Analogy Comparison Program Documentation Review Identify Risk Issue Enter Risk Issue in Risk database Conduct Risk Assessment and Update database Update Risk Database No Is Risk Issue Data Complete? Yes Plan Mitigation High Moderate Calculate Risk Values for Likelihood and Consequence Publish periodic Watch List to Key Team Members Feedback Monitor Risk Mitigation Actions Address Risk Issues at Program Reviews/RMT Meetings Feedback Figure 4-1. OOI Risk Management Process 7

12 4.3 Risk Assessment Risk management begins with identification of a potential risk item. As described above, risk assessment has two components identification and analysis. All personnel can enter new risk items into the risk management process using the risk identification form (RIF), which is provided as Appendix A. The RMT will evaluate all new items and ensure the items are properly identified if further processing is warranted Risk Rating System In order to assess risk items in a meaningful way, a risk rating system is required. The RMT is comprised of experts familiar with each risk area (e.g., design, engineering, construction, science, cost, software, schedule and management). This team of experts determines risk ratings for the OOI program. The rating system establishes levels of Likelihood and consequences and provides a range of possibilities large enough to distinguish differences in risk ratings. At the program level, Consequences are expressed in terms of impact on cost, schedule and performance. Table 4-1 and Table 4-2 show the criteria for Likelihood and Consequence. Table 4-1. Likelihood Criteria Level What is the likelihood the risk event will happen? 1 Remote 2 Unlikely 3 Possible 4 Probable 5 Near Certainty Table 4-2. Consequence Criteria Level Technical Program Schedule Program End Cost Operational Programmatic 1 Minimal Impact Minimal impact Minimal impact Minimal Impact Minimal Impact 2 Acceptable with some reduction in capability Additional resources required; able to meet need dates < 1% Small increase in operational costs Small impact on cost, schedule or technical baselines 3 Acceptable with significant reduction in capability Moderate slip in key milestones; not able to meet need dates 1-5% Moderate increase in operational costs Moderate impact on cost, schedule or technical baselines 4 Marginally Acceptable, barely able to perform needed science Major slip in key milestone or critical path impacted 5-10% Significant increase in operational costs Significant impact on cost, schedule or technical baselines 5 Unacceptable Cannot achieve key team or major program milestone >10% Unacceptable increase in operational costs Unacceptable impact on cost, schedule or technical baselines Figure 4-2 shows the simple method that the OOI program uses for rating risk events. The matrix shows how the Risk Manager has defined levels as high, moderate, and low for the various combinations of likelihood and consequences. A high (H) rating means that a major disruption to the program is likely. A moderate (M) rating means that some disruption will likely occur. A low (L) rating means that the risk, if realized, will have a minimum impact on the program. 8

13 5 L M H H H Likelihood 4 L M M H H 3 L L M M H 2 L L L M M 1 L L L L M CONSEQUENCE Figure 4-2. Risk Rating Matrix. Based on the ratings determined by the RMT, the Risk Manager identifies risk items requiring priority management. The OOI program risk information is recorded in the risk database. 4.4 Risk Handling This section describes how the OOI program will deal with risk, when it should be accomplished, who is responsible, and the cost and schedule impact. As described in section 2, there are four risk-handling techniques, or options. Risk avoidance eliminates the sources of high risk and replaces them with lower-risk solutions. Risk transfer is the reallocation of risk from one part of the system to another or the reallocation of risks between the Government, the prime contractor or subcontractors. Risk control manages the risk in a manner that reduces the likelihood of its occurrence and/or minimizes the risk s effect on the program. Risk assumption is the acknowledgment of the existence of a particular risk situation and a conscious decision to accept the associated level of risk without engaging in any special efforts to control it. Many programs select control as the risk-handling option without seriously evaluating assumption, avoidance, and transfer. This is unwise, since control may not be the best option, or even appropriate option in some cases. The OOI program applies an unbiased assessment of risk-handling options to determine the most appropriate option. The RMT deliberate on each risk item to determine what risk-handling technique is appropriate for incorporation into the program baseline. As necessary, the Director forwards the action to the NSF Program Officer for approval Risk Control Using risk control, the RMT takes active steps to reduce the likelihood of a risk event occurring and to reduce the potential impact on the program. Most risk-control steps share two features: they require a commitment of program resources and they require additional time for accomplishment. Thus, the selection of risk-control actions undoubtedly requires some tradeoff between resources and the expected benefit of the actions Risk Avoidance Risk avoidance reduces risk through the modification or elimination of operational requirements, processes or activities that cause the risks. When risk avoidance is used, a risk-handling plan is developed to ensure a close coordination with the users so that the eliminated requirements do not adversely affect operations Risk Assumption The OOI will use risk assumption where appropriate, but will insure that the new technologies being employed must prove very reliable due to the inaccessibility of many of the components once they are installed on the seafloor. 9

14 4.4.4 Risk Transfer Risk transfer involves the reduction of risk exposure by the reallocation of risk from one part of the observatory to another or the reallocation of risks between the Government and the prime contractor, or between the prime contractor and its subcontractors. In reallocating risk, design requirements that are risk drivers are transferred to other system elements, with the intention of lowering system risk while still meeting system requirements. The effectiveness of reallocating requirements depends on good system engineering and design techniques. In fact, efficient allocation of those requirements that are risk drivers is an integral part of the systems engineering process. 4.5 Risk Monitoring Risk monitoring is a continuous process to systematically track and evaluate the performance of risk-handling actions against established metrics throughout the acquisition process. Risk monitoring includes results of periodic reassessments of program risk to evaluate both known and new risks to the program. When necessary, the risk manager re-examines the risk-handling approaches for effectiveness while conducting assessments. As the program progresses, the monitoring process will identify the need for additional risk-handling options. An effective monitoring effort will provide information to show if handling actions are not working and which risks are on their way to becoming actual problems. The information should be available in sufficient time for the Project Office to take corrective action. A key to risk monitoring is the establishment of a management indicator system that provides accurate, timely, and relevant risk information in a clear, easily understood manner Watch List A watch list is a straightforward listing of critical areas requiring special management attention during program execution. For the OOI program, the watch list is a subset of the top ten (or so) risks in the risk register which is published in the Monthly Reports to NSF. It includes the priority of the risk, how long it has been on the watch list, handling actions, planned and actual completion dates for the handling actions, and explanations for any differences Reports Reports are used to convey information to decision-makers and program participants on the status of risks and the effectiveness of risk-handling actions. The OOI risk database is a comprehensive reservoir of risk related information. Standard risk reports can be derived from this database. A report of mitigation options and actions will be a part of the risk package presented at all program management reviews. 4.6 Risk Documentation A primary criterion for successful risk management is formally documenting the ongoing risk management process. This is important because: It provides the basis for program assessments and updates as the program progresses. Formal documentation tends to ensure more comprehensive risk assessments than if it is not documented. It provides a basis for monitoring risk-handling actions and verifying the results. It provides program background material for new personnel. It is a management tool for the execution of the program. It provides the rationale for program decisions. 10

15 The JOI Risk Manager, with the cooperation of the RMT, ensures that risk documentation is complete and up-to-date. Examples of risk management documents and reports provided for the OOI program are: Risk Management Plan Risk Information Form Risk register Risk assessment report Risk monitoring documentation (program baseline, contract capabilities, watch list, cost/performance report) 11

16 APPENDIX A RISK INFORMATION FORM A - 12

17 Risk Information Form (RIF) Risk Submission Form for OOI Risk ID: Submitter of Risk Name: Title: Organization: Risk Title: Impact type: Description:. Phone: Submission Date: Estimated Cost: Consequence: Likelihood: Assessment: Mitigation Options: Risk Handling: Mitigation Action: Resolution: Closed Date: Comments: A - 13

18 INSTRUCTIONS FOR COMPLETING THE RISK INFORMATION FORM Risk Information Forms are to be downloaded from the JOI Program Office database, completed using the instructions that follow, and submitted electronically to Complete as much as possible of the form. 1. Risk ID No: To be assigned by the Risk Manager. 2. Submitter of Risk Item a. Name: Name of the individual submitting the risk. b. Title: The job title of the individual submitting the risk. c. Work Phone: Work phone of the individual creating the risk. d. Organization Name: Activity/company of the individual submitting the risk. e. The address of the individual submitting the risk. f. Submission Date: The date when the risk was submitted. 3. Risk Title: Denotes a short title to also uniquely identify each risk issue. 4. Impact: Identifies the impact of the risk as a technical/performance, cost or schedule or a combination of any or all these. 5. Estimated Cost: Best guess estimate of the actual cost to the program if the risk were to be realized. 6. Description of Risk: A complete and through description of the risk and its impacts should be entered in this block. If possible, make into an If.., Then statement. Identify the cause of the risk and its potential adverse cost, schedule, performance impacts. 7. Consequences Criteria: In each applicable category (performance, program schedule or procurement end cost) in Table RIF-1 (see page A-5), choose the block corresponding to the magnitude of the consequence should the risk be realized: level 1-5 for technical, cost, or schedule, whichever has the most potential impact. 8. Likelihood of Failure: Use Table RIF-2 (see page A-5), choose the block that best corresponds to the Likelihood that your risk will actually occur: level Assessment: Using Table RIF-3 (see page A-5) to determine the overall risk rating low, moderate or high by determining the intersection of the plotted consequence rating on the X axis and the Likelihood rating on the Y axis of the table. 10. Mitigation Options: Recommended actions that would allow the program to reduce or eliminate the risk you have identified. 11. Risk Handling: One of the four (4) handling options (Avoidance, Control/Mitigation, Assumption, or Transfer) should be identified that will be used on the risk. Avoidance eliminates the source of high risk and replaces it with a lower risk solution. For example, eliminating a requirement that is unachievable at cost. Control/Mitigation manages the risk in a manner that reduces the Likelihood/likelihood of its occurrence and/or minimizes and mitigates the risk s effect on the program. For example, using modeling to reduce the risk of a system. Assumption is the acknowledgement of the existence of a particular risk situation and a conscious decision to accept the associated level of risk without engaging in any special efforts to control it. This decision must always be accompanied by monitoring techniques, a fallback plan should the monitoring indicate a situation tending toward the risk occurring, and an allocation of resources/budget for the fall back plan. A - 14

19 Transfer is the reallocation of risk from one part of the system to another or the reallocation of risks between the Government, the prime contractor or subcontractors. For example, contract incentives for the contractor to reduce production time. 12. Mitigation Action: A list of mitigation actions to be taken by the Action Officer to attempt to avoid the risk. This section may also include a description of industry s fallback option, i.e., contingency plan, if applicable. Include cost, schedule, and performance impacts of the fallback option. Assess and if acceptable, provide a rationale statement and recommend possible program actions, i.e., risk handling options, as appropriate. 13. Resolution: An event or activity (such as testing) that effectively retired the risk. 14. Closed Date: The date the risk was closed. 15. Comments: Use this block to enter any additional comments you wish to provide to help the Risk Manager evaluate your risk. A - 15

20 Table RIF-1. Consequence Criteria Level Technical Program Schedule Program End Cost Operational Programmatic 1 Minimal Impact Minimal impact Minimal impact Minimal Impact Minimal Impact 2 Acceptable with some reduction in capability Additional resources required; able to meet need dates < 1% Small increase in operational costs Small impact on cost, schedule or technical baselines 3 Acceptable with significant reduction in capability Moderate slip in key milestones; not able to meet need dates 1-5% Moderate increase in operational costs Moderate impact on cost, schedule or technical baselines 4 Marginally Acceptable, barely able to perform needed science Major slip in key milestone or critical path impacted 5-10% Significant increase in operational costs Significant impact on cost, schedule or technical baselines 5 Unacceptable Cannot achieve key team or major program milestone >10% Unacceptable increase in operational costs Unacceptable impact on cost, schedule or technical baselines Table RIF-2. Likelihood Criteria TableRIF-3. Risk Rating Matrix Level Probability 5 L M H H H 1 Remote 4 L M M H H 2 Unlikely 3 L L M M H 3 Possible 2 L L L M M 4 Probable 1 L L L L M PROBABILITY 5 Near Certainty CONSEQUENCE A - 16

12 GeV CEBAF Upgrade. Risk Management Plan

12 GeV CEBAF Upgrade. Risk Management Plan 12 GeV CEBAF Upgrade Risk Management Plan May 29, 2007 12 GeV CEBAF Upgrade Risk Management Plan 1 Apr 05 ISSUE DATE PAGES AFFECTED DESCRIPTION Original CD-2 4/01/05 5/29/07 All All General update to maintain

More information

Crowe, Dana, et al "EvaluatingProduct Risks" Design For Reliability Edited by Crowe, Dana et al Boca Raton: CRC Press LLC,2001

Crowe, Dana, et al EvaluatingProduct Risks Design For Reliability Edited by Crowe, Dana et al Boca Raton: CRC Press LLC,2001 Crowe, Dana, et al "EvaluatingProduct Risks" Design For Reliability Edited by Crowe, Dana et al Boca Raton: CRC Press LLC,2001 CHAPTER 13 Evaluating Product Risks 13.1 Introduction This chapter addresses

More information

RISK MANAGEMENT GUIDE FOR DOD ACQUISITION

RISK MANAGEMENT GUIDE FOR DOD ACQUISITION RISK MANAGEMENT GUIDE FOR DOD ACQUISITION Sixth Edition (Version 1.0) August, 2006 Department of Defense Table of Contents. Key Activity - Risk Analysis... 11.1. Purpose... 11.2. Risk Reporting Matrix...

More information

Helioseismic and Magnetic Imager for Solar Dynamics Observatory

Helioseismic and Magnetic Imager for Solar Dynamics Observatory Helioseismic and Magnetic Imager for Solar Dynamics Observatory Concept Study Report Appendix G Risk Management Plan LMSAL-2H00075 1 July 2003 Stanford University Hansen Experimental Physics Laboratory

More information

Introduction to Risk for Project Controls

Introduction to Risk for Project Controls Introduction to Risk for Project Controls By Eukeni Urrechaga, PE Quick view at Project Controls Project Controls, like project management, is much an art as it is a science. The secret of good project

More information

0470_022817_03_chap01.fm Page 11 Wednesday, September 8, :29 PM. Part I The basics of project risk management

0470_022817_03_chap01.fm Page 11 Wednesday, September 8, :29 PM. Part I The basics of project risk management 0470_022817_03_chap01.fm Page 11 Wednesday, September 8, 2004 3:29 PM Part I The basics of project risk management 0470_022817_03_chap01.fm Page 12 Wednesday, September 8, 2004 3:29 PM 0470_022817_03_chap01.fm

More information

Managing Project Risk DHY

Managing Project Risk DHY Managing Project Risk DHY01 0407 Copyright ESI International April 2007 All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or

More information

Unit 9: Risk Management (PMBOK Guide, Chapter 11)

Unit 9: Risk Management (PMBOK Guide, Chapter 11) (PMBOK Guide, Chapter 11) Some exam takers may be unfamiliar with the basic concepts of probability, expected monetary value, and decision trees. This unit will review all these concepts so that you should

More information

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA RISK MANAGEMENT 11.1 Plan Risk Management: The process of DEFINING HOW to conduct risk management activities for a project. In Plan Risk Management, the remaining FIVE risk management processes are PLANNED

More information

Risk Management Guidelines

Risk Management Guidelines Risk Management Guidelines Guideline as defined for this manual is a detailed minimum requirement to implement Risk Management 10/19/2011 Risk Management Guidelines for the Capital Program PD-QA-05-019,

More information

Case Study. IR-SIP Risk Management Plan Outline

Case Study. IR-SIP Risk Management Plan Outline Case Study IR-SIP Risk Management Plan Outline Baselined: Last Modified: Owner: Purpose: Section 1. Introduction 1.1 Purpose and Scope 1.2 Assumptions, Constraints, and Policies 1.3 Related Documents and

More information

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS N A T I O N A L C O N C E S S I O N C O U N C I L RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS PREPARED BY: ENGINEER ÁLVARO BORBON M. PRIVATE INITIATIVE PROGRAM DECEMBER 2008 INDEX Guide Purpose...

More information

Project Title: INFRASTRUCTURE AND INTEGRATED TOOLS FOR PERSONALIZED LEARNING OF READING SKILL

Project Title: INFRASTRUCTURE AND INTEGRATED TOOLS FOR PERSONALIZED LEARNING OF READING SKILL Project Title: INFRASTRUCTURE AND INTEGRATED TOOLS FOR PERSONALIZED LEARNING OF READING SKILL Project Acronym: Grant Agreement number: 731724 iread H2020-ICT-2016-2017/H2020-ICT-2016-1 Subject: Dissemination

More information

Earned Value Management. Danielle Kellogg. Hodges University

Earned Value Management. Danielle Kellogg. Hodges University Earned Value Management 1 EARNED VALUE MANAGEMENT Earned Value Management Danielle Kellogg Hodges University Earned Value Management 2 Abstract Earned Value Management has been used with enterprise-level

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management INSE 6230 Total Quality Project Management Lecture 6 Project Risk Management Project risk management is the art and science of identifying, analyzing, and responding to risk throughout the life of a project

More information

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone:   Last revised: for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:

More information

Procedures for Management of Risk

Procedures for Management of Risk Procedures for Management of Policy Sponsor: Name of Parent Policy: Policy Contact: Procedure Contact: Vice President Finance and Administration Enterprise Management Policy Vice President Finance and

More information

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS Advanced Project Management MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS 06 07 November 2018 Facilitator: Mr Mondli Mbambo Module Purpose Project Risk & Procurement Managment Knowledge Risk

More information

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. For the PMP Exam using PMBOK Guide 5 th Edition PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc. 1 Contacts Name: Khaled El-Nakib, MSc, PMP, PMI-RMP URL: http://www.khaledelnakib.com

More information

2. 5 of the 75 questions are under trial and will not contribute to your overall score. There is no indication of which questions are under trial.

2. 5 of the 75 questions are under trial and will not contribute to your overall score. There is no indication of which questions are under trial. The Foundation Examination Sample Paper 3 Question Booklet Multiple Choice Exam Duration: 60 minutes Instructions 1. You should attempt all 75 questions. 2. 5 of the 75 questions are under trial and will

More information

Conference Paper A New Cost Management Policy for Your Organization: An Integrated Approach Woomi Chase Ken Odom Tom Dauber

Conference Paper A New Cost Management Policy for Your Organization: An Integrated Approach Woomi Chase Ken Odom Tom Dauber Conference Paper A New Cost Management Policy for Your Organization: An Integrated Approach Woomi Chase Ken Odom Tom Dauber Denver, CO June 2014 1 Table Of Contents Introduction Program/Project Structure

More information

Fundamentals of Project Risk Management

Fundamentals of Project Risk Management Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on

More information

Chapter 7: Risk. Incorporating risk management. What is risk and risk management?

Chapter 7: Risk. Incorporating risk management. What is risk and risk management? Chapter 7: Risk Incorporating risk management A key element that agencies must consider and seamlessly integrate into the TAM framework is risk management. Risk is defined as the positive or negative effects

More information

Intermediate Systems Acquisition Course. Integrated Baseline Reviews (IBRs)

Intermediate Systems Acquisition Course. Integrated Baseline Reviews (IBRs) Integrated Baseline Reviews (IBRs) Holding an IBR is a best practice for all programs, and it supports the implementation of an earned value management system (EVMS). EVM can be a valuable tool for controlling

More information

Project Risk Management

Project Risk Management Project Risk Management Introduction Unit 1 Unit 2 Unit 3 PMP Exam Preparation Project Integration Management Project Scope Management Project Time Management Unit 4 Unit 5 Unit 6 Unit 7 Project Cost Management

More information

LIFE CYCLE ASSET MANAGEMENT. Project Management Overview. Good Practice Guide GPG-FM-001. March 1996

LIFE CYCLE ASSET MANAGEMENT. Project Management Overview. Good Practice Guide GPG-FM-001. March 1996 LIFE YLE Good Practice Guide ASSET MANAGEMENT Project Management Overview March 1996 Department of Energy Office of Field Management Office of Project and Fixed Asset Management ontents 1. INTRODUTION...1

More information

MEMORANDUM. To: From: Metrolinx Board of Directors Robert Siddall Chief Financial Officer Date: September 14, 2017 ERM Policy and Framework

MEMORANDUM. To: From: Metrolinx Board of Directors Robert Siddall Chief Financial Officer Date: September 14, 2017 ERM Policy and Framework MEMORANDUM To: From: Metrolinx Board of Directors Robert Siddall Chief Financial Officer Date: September 14, 2017 Re: ERM Policy and Framework Executive Summary Attached are the draft Enterprise Risk Management

More information

Job Safety Analysis Preparation And Risk Assessment

Job Safety Analysis Preparation And Risk Assessment Job Safety Analysis Preparation And Risk Assessment Sample Only Reference CPL_PCR_JSA_Risk_Assessment Revision Number SAMPLE ONLY Document Owner Sample Date 2015 File Location Procedure Revision Date Major

More information

Tangible Assets Threats and Hazards: Risk Assessment and Management in the Port Domain

Tangible Assets Threats and Hazards: Risk Assessment and Management in the Port Domain Journal of Traffic and Transportation Engineering 5 (2017) 271-278 doi: 10.17265/2328-2142/2017.05.004 D DAVID PUBLISHING Tangible Assets Threats and Hazards: Risk Assessment and Management in the Port

More information

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich Project Risk Management Prof. Dr. Daning Hu Department of Informatics University of Zurich Learning Objectives Understand what risk is and the importance of good project risk management Discuss the elements

More information

Project Theft Management,

Project Theft Management, Project Theft Management, by applying best practises of Project Risk Management Philip Rosslee, BEng. PrEng. MBA PMP PMO Projects South Africa PMO Projects Group www.pmo-projects.co.za philip.rosslee@pmo-projects.com

More information

The Proactive Quality Guide to. Embracing Risk

The Proactive Quality Guide to. Embracing Risk The Proactive Quality Guide to Embracing Risk Today s Business Uncertainties Are Driving Risk Beyond the Control of Every Business. Best Practice in Risk Management Can Mitigate these Threats The Proactive

More information

Risk Management User Guide. Prepared By: Neville Turbit Version Feb /01/2009 Risk Management User Guide Page 1 of 36

Risk Management User Guide. Prepared By: Neville Turbit Version Feb /01/2009 Risk Management User Guide Page 1 of 36 Risk Management User Guide Prepared By: Neville Turbit Version 1.0 1 Feb 09 22/01/2009 Risk Management User Guide Page 1 of 36 Table of Contents Document Origin...2 Change History...2 Risk Guidelines...

More information

A Study on Risk Analysis in Construction Project

A Study on Risk Analysis in Construction Project A Study on Risk Analysis in Construction Project V. Rathna Devi M.E. Student, Department of civil engineering, Velammal Engineering College, Tamil Nadu, India ---------------------------------------------------------------------***--------------------------------------------------------------------

More information

Presented at the 2010 ISPA/SCEA Joint Annual Conference and Training Workshop -

Presented at the 2010 ISPA/SCEA Joint Annual Conference and Training Workshop - Abstract Risk Identification and Visualization in a Concurrent Engineering Team Environment Jairus Hihn 1, Debarati Chattopadhyay, Robert Shishko Mission Systems Concepts Section Jet Propulsion Laboratory/California

More information

RISK MANAGEMENT POLICY

RISK MANAGEMENT POLICY RISK MANAGEMENT POLICY CIN: L51505KL1989PLC005478 1. BACKGROUND ARTECH POWER & TRADING LIMITED Risk Management Policy Business Risk Management is an ongoing process within the organization. The Company

More information

Earning Value From Risk

Earning Value From Risk Earning Value From Risk Ron Higuera March 1999 rph@cise.cmu.edu Agenda Overview Earned Value Overview Risk Management Investment Strategy Summary 2 Presentation Objective Relate risk management and earned

More information

Using data mining to detect insurance fraud

Using data mining to detect insurance fraud IBM SPSS Modeler Using data mining to detect insurance fraud Improve accuracy and minimize loss Highlights: combines powerful analytical techniques with existing fraud detection and prevention efforts

More information

Risk Management Policy

Risk Management Policy Risk Management Policy BACK GROUND & LEGAL FRAMEWORK Risk Management is a key aspect of the Corporate Governance Principles and Code of Conduct which aims to improvise the governance practices across the

More information

RISK EVALUATIONS FOR THE CLASSIFICATION OF MARINE-RELATED FACILITIES

RISK EVALUATIONS FOR THE CLASSIFICATION OF MARINE-RELATED FACILITIES GUIDE FOR RISK EVALUATIONS FOR THE CLASSIFICATION OF MARINE-RELATED FACILITIES JUNE 2003 American Bureau of Shipping Incorporated by Act of Legislature of the State of New York 1862 Copyright 2003 American

More information

Contract Performance Report

Contract Performance Report Contract Performance Report Description This report consists of five formats containing cost and related data for measuring contractors' cost and schedule performance on Department of Defense (DOD) acquisition

More information

An Introduction to Risk

An Introduction to Risk CHAPTER 1 An Introduction to Risk Risk and risk management are two terms that comprise a central component of organizations, yet they have no universal definition. In this chapter we discuss these terms,

More information

Information Technology Project Management, Sixth Edition

Information Technology Project Management, Sixth Edition Management, Sixth Edition Prepared By: Izzeddin Matar. Note: See the text itself for full citations. Understand what risk is and the importance of good project risk management Discuss the elements involved

More information

Ahsan Jamal. Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS

Ahsan Jamal. Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS Ahsan Jamal Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS Introduction For the last couple of years, we have seen enormous growth in the construction industry of Pakistan due to

More information

machine design, Vol.7(2015) No.4, ISSN pp

machine design, Vol.7(2015) No.4, ISSN pp machine design, Vol.7(205) No.4, ISSN 82-259 pp. 9-24 Research paper ANALYSIS AND RISK ASSESSMENT OF IMPLEMENTATION OF THE AUTOMATED CAR PARKING SYSTEM PROJECT Radoslav TOMOVIĆ, * - Rade GRUJIČIĆ University

More information

Solvency Assessment and Management: Stress Testing Task Group Discussion Document 96 (v 3) General Stress Testing Guidance for Insurance Companies

Solvency Assessment and Management: Stress Testing Task Group Discussion Document 96 (v 3) General Stress Testing Guidance for Insurance Companies Solvency Assessment and Management: Stress Testing Task Group Discussion Document 96 (v 3) General Stress Testing Guidance for Insurance Companies 1 INTRODUCTION AND PURPOSE The business of insurance is

More information

Remediation Risk Management: A Comprehensive Approach for Reducing Remediation Uncertainties

Remediation Risk Management: A Comprehensive Approach for Reducing Remediation Uncertainties 1 Welcome Remediation Risk Management: A Comprehensive Approach for Reducing Remediation Uncertainties Environment, Energy & Sustainability Symposium & Exhibition May 6, 2009 Denver, CO Mr. Ning-Wu Chang,

More information

Project Risk Management

Project Risk Management Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-986-4 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-986-4 The material contained within

More information

Risk Management. CITS5501 Software Testing and Quality Assurance

Risk Management. CITS5501 Software Testing and Quality Assurance Risk Management CITS5501 Software Testing and Quality Assurance (Source: Pressman, R. Software Engineering: A Practitioner s Approach. McGraw-Hill, 2005) 2017, Semester 1 Definition of Risk A risk is a

More information

Kidsafe NSW Risk Management Plan. August 2014

Kidsafe NSW Risk Management Plan. August 2014 Kidsafe NSW Risk Management Plan August 2014 Document Control Document Approval Name & Position Signature Date Document Version Control Version Status Date Prepared By Comments Document Reviewers Name

More information

PRINCE2 Sample Papers

PRINCE2 Sample Papers PRINCE2 Sample Papers The Official PRINCE2 Accreditor Sample Examination Papers Terms of use Please note that by downloading and/or using this document, you agree to comply with the terms of use outlined

More information

A Project Management Guide for Researchers

A Project Management Guide for Researchers A Project Management Guide for Researchers Prepared by: Research Grant and Contract Services January 2018 Copyright 2018 Memorial University of Newfoundland Table of Contents 1.0 Introduction... 4 2.0

More information

Risk Management Policies and Procedures

Risk Management Policies and Procedures Risk Management Policies and Procedures As at May 5 2017 Masters Swimming Australia ABN 24 694 633 156 Level 2, Sports House, 375 Albert Road, Albert Park 3206 t: (03) 9682 5666 e: gm@mastersswimming.org.au

More information

Presenting and Understanding Risk Management

Presenting and Understanding Risk Management The best source of information and training on Aboriginal finance and management The Aboriginal Finance and Management Capacity Development Series Presenting and Understanding Risk Management A Practical

More information

To P3 or Not to P3 By JohN Gross

To P3 or Not to P3 By JohN Gross To P3 or Not to P3 By John Gross Public-private partnerships (P3s) can bring substantial benefits and value to the procurement, delivery, operation, and maintenance of public infrastructure although care

More information

Risk Management Process-02. Lecture 06 By: Kanchan Damithendra

Risk Management Process-02. Lecture 06 By: Kanchan Damithendra Risk Management Process-02 Lecture 06 By: Kanchan Damithendra Risk Analysis Risk Register The main output of the risk identification process is a list of identified risks and other information needed to

More information

Guidance Note System of Governance - Insurance Transition to Governance Requirements established under the Solvency II Directive

Guidance Note System of Governance - Insurance Transition to Governance Requirements established under the Solvency II Directive Guidance Note Transition to Governance Requirements established under the Solvency II Directive Issued : 31 December 2013 Table of Contents 1.Introduction... 4 2. Detailed Guidelines... 4 General governance

More information

Risk Management Strategy

Risk Management Strategy Risk Management Strategy 2016 2019 Version: 6 Policy Lead/Author & Deputy Director of Quality position: Ward / Department: Nursing Directorate Replacing Document: Version 5 Approving Committee Quality

More information

METHODOLOGY For Risk Assessment and Management of PPP Projects

METHODOLOGY For Risk Assessment and Management of PPP Projects METHODOLOGY For Risk Assessment and Management of PPP Projects December 26, 2013 The publication was produced for review by the United States Agency for International Development. It was prepared by Environmental

More information

MINDA INDUSTRIES LIMITED RISK MANAGEMENT POLICY

MINDA INDUSTRIES LIMITED RISK MANAGEMENT POLICY ` MINDA INDUSTRIES LIMITED RISK MANAGEMENT POLICY MINDA INDUSTRIES LIMITED RISK MANAGEMENT POLICY 1. Vision To develop organizational wide capabilities in Risk Management so as to ensure a consistent,

More information

Delay Expert practical tips for making delay claims

Delay Expert practical tips for making delay claims Octavian Dan Delay Expert practical tips for making delay claims Identification of clauses in the FIDIC Contract useful for consideration when making delay claims: FIDIC 2017 edition a short summary of

More information

We will begin the web conference shortly. When you arrive, please type the phone number from which you are calling into the chat field.

We will begin the web conference shortly. When you arrive, please type the phone number from which you are calling into the chat field. Welcome We will begin the web conference shortly. When you arrive, please type the phone number from which you are calling into the chat field. To login to the audio portion of the web conference, dial

More information

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7 Jefferson Science Associates, LLC 900 Glossary Project Control System Manual Revision 7 900 Glossary Actual Cost of Work Performed (ACWP) The direct costs incurred in accomplishing the project work activities,

More information

ENTERPRISE RISK MANAGEMENT POLICY FRAMEWORK

ENTERPRISE RISK MANAGEMENT POLICY FRAMEWORK ANNEXURE A ENTERPRISE RISK MANAGEMENT POLICY FRAMEWORK CONTENTS 1. Enterprise Risk Management Policy Commitment 3 2. Introduction 4 3. Reporting requirements 5 3.1 Internal reporting processes for risk

More information

Chapter-8 Risk Management

Chapter-8 Risk Management Chapter-8 Risk Management 8.1 Concept of Risk Management Risk management is a proactive process that focuses on identifying risk events and developing strategies to respond and control risks. It is not

More information

Risk Management Strategy January NHS Education for Scotland RISK MANAGEMENT STRATEGY

Risk Management Strategy January NHS Education for Scotland RISK MANAGEMENT STRATEGY NHS Education for Scotland RISK MANAGEMENT STRATEGY January 2016 1 Contents 1. NES STATEMENT ON RISK MANAGEMENT 2 RISK MANAGEMENT STRATEGY 3 RISK MANAGEMENT STRUCTURES 4 RISK MANAGEMENT PROCESSES 5 RISK

More information

Risk Management at Central Bank of Nepal

Risk Management at Central Bank of Nepal Risk Management at Central Bank of Nepal A. Introduction to Supervisory Risk Management Framework in Banks Nepal Rastra Bank(NRB) Act, 2058, section 35 (a) requires the NRB management is to design and

More information

RESERVE BANK OF MALAWI

RESERVE BANK OF MALAWI RESERVE BANK OF MALAWI GUIDELINES ON INTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS (ICAAP) Bank Supervision Department March 2013 Table of Contents 1.0 INTRODUCTION... 2 2.0 MANDATE... 2 3.0 RATIONALE...

More information

Mitigating Delay Claims and Scheduling Best Practices

Mitigating Delay Claims and Scheduling Best Practices Mitigating Delay Claims and Scheduling Best Practices Prepared and Presented by: Raquel Speers Shohet, EI, PSP Hill International, Inc. Claims and Consulting Group 10801 W. Charleston Blvd. Suite 650 Las

More information

An Update On Association Policies, Health Checks & Guidelines To A Safer Hockey Association. Lauren Woods Member Engagement & Operations

An Update On Association Policies, Health Checks & Guidelines To A Safer Hockey Association. Lauren Woods Member Engagement & Operations An Update On Association Policies, Health Checks & Guidelines To A Safer Hockey Association Lauren Woods Member Engagement & Operations Association Health Checks Issues arising from the health check: 3/27

More information

Bournemouth Primary MAT Risk Management Policy

Bournemouth Primary MAT Risk Management Policy Bournemouth Primary MAT Risk Management Policy 1. Introduction The Bournemouth Primary Multi-Academy Trust (the Trust) operates a risk management system in order to identify and manage key exposures and

More information

Council. International Seabed Authority ISBA/16/C/6

Council. International Seabed Authority ISBA/16/C/6 International Seabed Authority Council Distr.: General 5 March 2010 Original: English Sixteenth session Kingston, Jamaica 26 April-7 May 2010 Proposal to seek an advisory opinion from the Seabed Disputes

More information

RISK MANAGEMENT STANDARDS FOR P5M

RISK MANAGEMENT STANDARDS FOR P5M Journal of Engineering Science and Technology Vol. 13, No. 1 (2018) 011-034 School of Engineering, Taylor s University RISK MANAGEMENT STANDARDS FOR P5M PETR ŘEHÁČEK Department of Systems Engineering,

More information

Appendix B: Glossary of Project Management Terms

Appendix B: Glossary of Project Management Terms Appendix B: Glossary of Project Management Terms Assumption - There may be external circumstances or events that must occur for the project to be successful (or that should happen to increase your chances

More information

NYISO Capital Budgeting Process. Draft 01/13/03

NYISO Capital Budgeting Process. Draft 01/13/03 NYISO Capital Budgeting Process Draft 01/13/03 1 1.0 INTRODUCTION An effective, capital budgeting process is essential to ensure sound capital investment decisions. This report details a recommended approach

More information

Earned Value Management (EVM) and the Acquisition Program

Earned Value Management (EVM) and the Acquisition Program American Society of Military Comptrollers Professional Development Institute May 31 June 2, 2017 Earned Value Management (EVM) and the Acquisition Program Workshop #102 R o b e r t L. G u s t a v u s.

More information

D6.2 Risk Assessment Plan

D6.2 Risk Assessment Plan D6.2 Risk Assessment Plan Project number: 730830 Project acronym: Project title: Safe4RAIL Start date of the project: 1 st of October, 2016 Duration: Programme: Safe4RAIL: SAFE architecture for Robust

More information

APPLICATION OF FORMAL SAFETY ASSESSMENT IN THE LEGAL ACTIVITY OF INTERNATIONAL MARITIME

APPLICATION OF FORMAL SAFETY ASSESSMENT IN THE LEGAL ACTIVITY OF INTERNATIONAL MARITIME Journal of KONES Powertrain and Transport, Vol. 21, No. 4 2014 ISSN: 1231-4005 e-issn: 2354-0133 ICID: 1130510 DOI: 10.5604/12314005.1130510 APPLICATION OF FORMAL SAFETY ASSESSMENT IN THE LEGAL ACTIVITY

More information

Risk Evaluation. Chapter Consolidation of Risk Analysis Results

Risk Evaluation. Chapter Consolidation of Risk Analysis Results Chapter 9 Risk Evaluation At this point we have identified the risks and analyzed their likelihood and consequence. From this we can establish the risk level and compare it to the risk evaluation criteria,

More information

Programmatic Risk Management in Space Projects

Programmatic Risk Management in Space Projects r bulletin 103 august 2000 Programmatic Risk Management in Space Projects M. Belingheri, D. von Eckardstein & R. Tosellini ESA Directorate of Manned Space and Microgravity, ESTEC, Noordwijk, The Netherlands

More information

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017 Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017 David T. Hulett, Ph.D., FAACE Hulett & Associates, LLC David.hulett@projectrisk

More information

Revenue for the engineering and construction industry

Revenue for the engineering and construction industry Revenue for the engineering and construction industry The new standard s effective date is coming. US GAAP December 2016 kpmg.com/us/frn b Revenue for the engineering and construction industry Revenue

More information

Management Reserve Defined

Management Reserve Defined Management Reserve Defined Management Reserve (MR) is defined in EIA 748 Earned Value Management Systems, the commercial standard for EVMS, as An amount of the total budget withheld for management control

More information

Main Sections. Corporate Risk Policy Statement and Procedures AR-RMD-CR01. Executive Summary. Anglia Ruskin University Risk Management

Main Sections. Corporate Risk Policy Statement and Procedures AR-RMD-CR01. Executive Summary. Anglia Ruskin University Risk Management Corporate Risk Policy Statement and Procedures AR-RMD-CR01 Executive Summary This document is intended to assist Anglia Ruskin University, its subsidiaries and Joint Ventures in controlling business risks,

More information

Risk Assessment Policy (Trust, Summer, Senior and Prep School & EYFS)

Risk Assessment Policy (Trust, Summer, Senior and Prep School & EYFS) Risk Assessment Policy (Trust, Summer, Senior and Prep School & EYFS) Introduction St Bede s School Trust (hereafter referred to as Bede s) clearly recognises that a failure to take reasonable safety precautions

More information

Performance-Based Agreements: Incorporating Performance-Based Elements into Standard Loan and Grant Agreements

Performance-Based Agreements: Incorporating Performance-Based Elements into Standard Loan and Grant Agreements Performance-Based Agreements: Incorporating Performance-Based Elements into Standard Loan and Grant Agreements A Technical Guide Mayada El-Zoghbi Jasmina Glisovic-Mezieres Alexia Latortue The authors are

More information

Department of Defense INSTRUCTION

Department of Defense INSTRUCTION Department of Defense INSTRUCTION NUMBER 7041.03 September 9, 2015 Incorporating Change 1, October 2, 2017 DCAPE SUBJECT: Economic Analysis for Decision-making References: See Enclosure 1 1. PURPOSE. In

More information

The Project Times and Costs

The Project Times and Costs The Project Times and Costs Not to underestimate the estimate Chapter 5 Defining the Project Step 1: Defining the Scope Step 2: Establishing Priorities Step 3: Creating the Work Breakdown Structure Step

More information

RISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management

RISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management AACE International Recommended Practice No. 44R-08 RISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management Acknowledgments: John K. Hollmann, PE CCE CEP (Author)

More information

INFIBEAM INCORPORATION LIMITED

INFIBEAM INCORPORATION LIMITED INFIBEAM INCORPORATION LIMITED RISK MANAGEMENT POLICY LEGAL FRAMEWORK Risk Management is a key aspect of the Corporate Governance Principles and Code of Conduct which aims to improvise the governance practices

More information

NEGOTIATION REVIEW. Negotiating Risk By Roger Greenfield. thegappartnership.com

NEGOTIATION REVIEW. Negotiating Risk By Roger Greenfield. thegappartnership.com NEGOTIATION REVIEW Negotiating Risk By Roger Greenfield contact@thegappartnership.com thegappartnership.com Negotiating risk Risk: one of the most under valued variables available during contract negotiations.

More information

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon Abstract- Project Cost Management includes the processes involved in planning, estimating, budgeting,

More information

Presented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration.

Presented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration. Project Risk Management Tutorial Presented to: Eastern Idaho Chapter Project Management Institute Presented by: Carl Lovell, PMP Contract and Technical Integration March 2009 Project Risk Definition An

More information

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS Full citation: Connor, A.M., & MacDonell, S.G. (25) Stochastic cost estimation and risk analysis in managing software projects, in Proceedings of the ISCA 14th International Conference on Intelligent and

More information

Budget Analyst GS Career Path Guide

Budget Analyst GS Career Path Guide Budget Analyst GS-0560 Career Path Guide April, 2015 (This page intentionally left blank.) TABLE OF CONTENTS BUDGET ANALYSIS G-0560... 1 Career Path Guide... 1 Your Career as a Budget Analyst SNAP SHOT...

More information

Contents INTRODUCTION...4 THE STEPS IN MANAGING RISKS ESTABLISH GOALS AND CONTEXT IDENTIFY THE RISKS...8

Contents INTRODUCTION...4 THE STEPS IN MANAGING RISKS ESTABLISH GOALS AND CONTEXT IDENTIFY THE RISKS...8 Contents INTRODUCTION...4 THE STEPS IN MANAGING RISKS...4 1. ESTABLISH GOALS AND CONTEXT...5 2. IDENTIFY THE RISKS...8 Identifying the risks... 8 Identify the sources of the risks... 8 Identify the impact

More information

INTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS GUIDELINE. Nepal Rastra Bank Bank Supervision Department. August 2012 (updated July 2013)

INTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS GUIDELINE. Nepal Rastra Bank Bank Supervision Department. August 2012 (updated July 2013) INTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS GUIDELINE Nepal Rastra Bank Bank Supervision Department August 2012 (updated July 2013) Table of Contents Page No. 1. Introduction 1 2. Internal Capital Adequacy

More information

EFFECTIVE TECHNIQUES IN RISK MANAGEMENT. Joseph W. Mayo, PMP, RMP, CRISC September 27, 2011

EFFECTIVE TECHNIQUES IN RISK MANAGEMENT. Joseph W. Mayo, PMP, RMP, CRISC September 27, 2011 EFFECTIVE TECHNIQUES IN RISK MANAGEMENT Joseph W. Mayo, PMP, RMP, CRISC September 27, 2011 Effective Techniques in Risk Management Risk Management Overview Exercise #1 Break Risk IT Exercise #2 Break Risk

More information

Earned Value Management System

Earned Value Management System DEPARTMENT OF VETERANS AFFAIRS Office of Information and Technology Earned Value Management System Description Document VA-DI-MGMT-81466A RECORD OF CHANGES Change Number Date Reference (Page, Section,

More information

Guidance Note: Stress Testing Credit Unions with Assets Greater than $500 million. May Ce document est également disponible en français.

Guidance Note: Stress Testing Credit Unions with Assets Greater than $500 million. May Ce document est également disponible en français. Guidance Note: Stress Testing Credit Unions with Assets Greater than $500 million May 2017 Ce document est également disponible en français. Applicability This Guidance Note is for use by all credit unions

More information