Annual Report. Utilities Business Operations University of Saskatchewan Facilities Management Division.

Size: px
Start display at page:

Download "Annual Report. Utilities Business Operations University of Saskatchewan Facilities Management Division."

Transcription

1 Annual Report Utilities Business Operations November 5, 2012 University of Saskatchewan Facilities Management Division

2 Executive Summary The 2011/12 total utility costs were under budget by $642,600 (96% of the total budget of $15,291,240) and down by approximately $74,000 from 2010/11. This represents a 0.5% decrease from 2010/11 and is 7% higher than the campus five year average. The outlook for the fiscal period 2012/13 is estimated to be consistent with past years. Consumption levels of all commodities are expected to continue with the same trends as in the last five years. Prices for electricity and water increased by 1% and 6% respectively in 2011/12. The average natural gas price for 2012/13 is booked at $7.15 per Gigajoule (Gj), as compared to $7.52 per Gj in 2011/12. In 2012/13, the university s metering needs will be reviewed and various models of allocating utility costs will be assessed in support of the Transparent Activity-Based Budget System (TABBS) review and the Energy Management Program under development. Also new for 2012/13 will be the launch of monthly information based utility invoices sent to various contact people on campus. The purpose of these invoices is to make campus users more aware of the consumption totals and costs associated with the day to day operations of their campus building. Purpose of Annual Report The purpose of this document is to provide an overview of the utilities business operations for the past fiscal period, including trending information to give context, as well as provide an update on some of the key activities carried out during the year. In addition, information is provided regarding expectations for the utilities business operations in the 2012/ /2012 Fiscal Period Analysis In 2011/12 the total utility costs to the university were down 0.5% from 2010/11 and 7% higher than the five year average, for a total of $14,650,000 (see Figure 1 below), under budget by approximately $642,600 (96% of budget amount of $15,291,240) and down $74,000 from 2010/11. University of Saskatchewan, Facilities Management Division Utilities Business Operations Annual Report Page 1

3 Millions $20.0 $16.0 U of S Total Utility Costs $12.0 $8.0 $4.0 $0.0 Total Utility Costs Total Utility Budgets (Figure 1) The surplus this year was due to maintenance and wage costs ending the year $1,450,000 under budget, offset by net commodity purchases going over budget by $800,000. These variances were due to a change in cost distributions which resulted in $1,100,000 being reclassified as consumption costs and reducing the overall maintenance costs in the utilities operation. This redistribution was undertaken with the objective of increasing the overall accuracy of the university s financial statements. The remaining $350,000 maintenance variance was mainly due to the postponement of the replacement of one of the main electrical transformers located in the Agriculture Building. This transformer is expected to be replaced in the 2012/13 fiscal period. Commodity Cost Breakdown In 2011/12 the campus spent $11,109,250 for its electricity, natural gas, and water consumptions up 3% from 2010/11. The individual breakdowns are shown in Figure 2 below. Electricity made up 52% of the total commodity costs with expenditures of $5,797,450; natural gas was next with expenditures of $4,311,545 (39%); and water made up the remainder with expenditures of $1,000,255 (9%). These breakdowns are very comparable to the five year average where electricity represents 52%, natural gas accounts for 40%, and water represents 8% (see Figure 3). University of Saskatchewan, Facilities Management Division Utilities Business Operations Annual Report Page 2

4 $1,000,255 9% Commodity Cost Breakdown 2011/2012 Commodity Cost Breakdown Five Year Average 8% $4,311,545 39% $5,797,451 52% 40% 52% Electricity Natural Gas Water Electricity Natural Gas Water (Figure 2) (Figure 3) Analysis by Commodity An analysis of the electricity, natural gas and water commodities are provided below to give a better sense of reasons for budget to actual variances, how prices per unit have trended, and the proportion of commodities that are used to service our external and ancillary customers. Electricity The cost of electricity for the campus (i.e. excluding customers) in 2011/12 was $5,797,450 under budget by $3,000 with consumption being 93.6 Million kwh (see Figures 4 and 5). The electricity costs for 2011/12 represent a 2% increase over the 2010/11 period and a 9% increase over the five year average. Millions $6.0 $5.0 $4.0 $3.0 $2.0 $1.0 $0.0 Campus Electricity Costs Millions Campus Electricity Consumption (kwh) (Figure 4) (Figure 5) University of Saskatchewan, Facilities Management Division Utilities Business Operations Annual Report Page 3

5 The variance was made up of a combination of price and consumption variances as shown. Variance Budget Actual Variance F, (U) Calculation $ Variance Price $ $0.062 (U) ($ $0.062) x 94,014,500 ($28,000) Consumption (kwh) 94,014,500 93,568,314 F (94,014,500 93, ) x $0.062 $31,000 Total Variance $3,000 The 2011/12 fiscal period saw no increase in power rates from SaskPower. In the 2011/12 fiscal year the campus consumed 93,568,000 kwh of electricity, an increase of 2% over 2010/11 and up 2% over the five year average consumptions. In 2011/12 our average electricity rates were $.062 per kwh. This is an increase of 1% over 2010/11 and a 7% increase over the average costs of the last five years (Figure 6). $0.07 $0.06 $0.05 $0.04 $0.03 $0.02 $0.01 Electricty Cost Per Unit (kwh) $ / / / / /12 (Figure 6) The university purchases power at our Preston substation from SaskPower at 72 kilo volts and distributes this power to the campus as well as external and ancillary customers. In 2011/12 customers consumed 48% of the distributed power with the campus consuming the remaining 52%. Royal University Hospital and CLS are the largest external customers consuming a total of 59% of the total customer consumptions. The customer consumption is up slightly from 2010/11 and up slightly by 1% from the last five year average (Figure 7). University of Saskatchewan, Facilities Management Division Utilities Business Operations Annual Report Page 4

6 60% Electricity Consumption 50% 40% 30% 20% 10% 0% 2007/ / / / /12 External % Ancillary % Campus % (Figure 7) Natural Gas Final results for the 2011/12 fiscal period showed campus (i.e. excluding customers) consumption of 573,330 Gj of natural gas for a total of $4,311,545 (Figures 8 and 9), under budget by $734,357. The natural gas costs for 2011/12 represent a 5% decrease over the 2010/11 period and a 3% increase over the five year average. Millions $5.0 $4.0 $3.0 $2.0 $1.0 $0.0 Campus Natural Gas Costs 700, , , , , , ,000 0 Campus Natural Gas Consumption (Figure 8) (Figure 9) University of Saskatchewan, Facilities Management Division Utilities Business Operations Annual Report Page 5

7 The variance was made up of a combination of price and consumption variances as shown. Variance Budget Actual Variance F, (U) Calculation $ Variance Price $7.17 $7.52 (U) ($ $7.52) x 703,752 ($246,300) Consumption (Gj) 703, ,330 F (703, ,330) x $7.52 $980,700 Total Variance $734,400 The university forward contracts our natural gas purchases to manage fluctuations in pricing from year to year, as well as to minimize our natural gas costs to the extent possible. The amounts and timelines that can be forward contracted are governed by guidelines that have been established under the authority of the University s Derivatives Policy. When the budget was prepared 100% of the natural gas needs were booked. Increases in administration, transportation and storage costs accounted for the unfavorable price variance. This natural gas consumption level was 8% lower than in 2010/11 and 4% lower than the five year campus average. This can be attributed to the warmer than average heating season in the 2011/12 fiscal period. The heating season (October to April) in 2011/12 was 17% warmer than average and 19% warmer than the same period in 2010/11. In 2011/12 our average natural gas costs were $7.52 per Gj, a 4% increase from 2010/11 and a 7% increase from the five year average of $7.04 (see Figure 10). $8.00 $7.00 $6.00 $5.00 $4.00 $3.00 $2.00 $1.00 Natural Gas Consumption Cost Per Unit (GJ) $ / / / / /12 (Figure 10) The university purchases natural gas and uses this commodity to produce steam. We then sell a portion of this steam to external and ancillary customers. In 2011/12 customers consumed 37% of the overall steam produced with the campus consuming the remaining 63%. Royal University Hospital is by far the largest external customer consuming 55% of the total customer consumptions. The customer consumption represents a 1% decrease over the previous period and a 2% decrease over the last five year average (Figure 11). University of Saskatchewan, Facilities Management Division Utilities Business Operations Annual Report Page 6

8 70% 60% 50% 40% 30% 20% 10% 0% Natural Gas Consumption 2007/ / / / /12 External % Internal % Campus % (Figure 11) In order to even out the campus monthly gas costs, natural gas is purchased in equal amounts every day throughout the year (2011/12 purchased 2,700 Gj per day). During the summer months excess Gj s are purchased and stored with TransGas in caverns located outside of the city. During the winter months the campus consumption exceeds the daily purchase amounts. This difference is made up by drawing the summer excess out of storage. The university s total storage capacity in these caverns is 350,000 Gj. On April 30, 2012 the university had 127,932 Gj in storage valued at $922,610. Water The final results of the 2011/12 year showed the campus (i.e. excluding customers) consuming 243, cu ft of water for a total cost of $1,000,255 (Figures 12 and 13), under budget by $234,370. The water costs for 2011/12 represent a 46% increase over the 2010/11 period and a 19% increase over the five year average. Millions $1.2 $1.0 $0.8 $0.6 $0.4 $0.2 $0.0 Campus Water Costs 350, , , , , ,000 50,000 0 Campus Water Consumption (100 CuFt) (Figure 12) (Figure 13) University of Saskatchewan, Facilities Management Division Utilities Business Operations Annual Report Page 7

9 The variance was made up of a combination of price and consumption variances as shown. Variance Budget Actual Variance F, U Calculation $ Variance Price (100 Cu Ft) $4.15 $4.12 F ($ $4.12) x 297,500 $9,000 Consumption (100 Cu Ft) 297, ,024 F (297, ,024) x $4.12 $225,000 Total Variance $234,000 The actual price of water was very close to that budgeted, resulting in a minimal favourable variance of $9,000. Campus water consumption trends have been investigated to understand the reduced consumption over the past three years and no definitive explanation has been determined. It appears that that the two periods 2009/10 and 2010/11 were anomalies and that the more normal trend has resumed for 2011/12. In 2011/12 our average water costs were $4.12 per 100 cu ft, an increase of 6% over 2010/11 and an increase of 16% over the five year average (Figure 14). $4.50 $4.00 $3.50 $3.00 $2.50 $2.00 $1.50 $1.00 $0.50 $0.00 Water Cost Per Unit (100 CuFt) (Figure 14) The university purchases its water from the City of Saskatoon and distributes it to the campus as well as external and ancillary customers. In 2011/12, customers consumed 38% of water, with the remaining 62% being consumed by the campus. Agriculture Canada is the largest customer consuming 25% of the total customer consumptions. The customer consumption represents a 1% increase over 2010/11 and a 1% decrease over the last five year average (Figure 15). University of Saskatchewan, Facilities Management Division Utilities Business Operations Annual Report Page 8

10 80% 70% 60% 50% 40% 30% 20% 10% 0% Water Consumption 2007/ / / / /12 External % Ancillary % Campus % (Figure 15) Natural Gas Contracting The university forward contracts natural gas needs which follow the natural gas year November 1 to October 31. The amounts and timelines in forward contracting are governed by the University s Derivative Policy. As of April 30, 2012 percentages booked, average prices and compliance with the policy were as follows: Target Range % Booked per Derivatives Policy Approximate Consumption Needs Booked % Weighted Average Price /Gj $ Year Gas Year 0 Nov 11 / Oct Nov 12 / Oct Nov 13 / Oct Nov 14 / Oct Nov 15 / Oct Nov 16 / Oct Nov 17 / Oct Nov 18 / Oct Nov 19 / Oct Nov 20 / Oct Nov 21/ Oct The value of the commitments as of April 30, 2012 was $33,820,000. In the past we have hedged all of our purchases with Nexen Energy using forward fixed price contracts. In 2010 we signed an agreement with the Royal Bank, and are in the process of signing an agreement with CIBC, to enable the university to undertake commodity trading with these institutions. This allows for more competitive pricing. Nexen Energy will continue to be the main supplier of the university s natural gas needs in accordance with a ten year supply contract with Nexen at $.05 above the Alberta monthly index NG price, plus the University of Saskatchewan, Facilities Management Division Utilities Business Operations Annual Report Page 9

11 transportation costs that are determined before the start of each gas year. This arrangement positions the university well to ensure our natural gas supply needs are met into the future. Energy Management Initiatives in 2011/12 As part of the university s commitment to sustainability a number of energy management initiatives are undertaken each year. The following are a few of the highlights and accomplishments that were started or completed in the last fiscal period. Heating plant boiler feedwater project - A $10 million dollar replacement and upgrading project to the campus central heating plant. The end result was increased capacity to the plant coupled with increased efficiencies in operations. Campus lighting retrofit program- Ongoing campus wide upgrade to lighting fixtures replacing old T12 lighting with more efficient T8 s. Agriculture phytotron lighting retrofit Replacement of approximately 4,000 incandescent bulbs and magnetic ballast fixtures with more efficient electronic ballasts and T5 fluorescent lamps. Health Sciences D-wing construction Construction of Health Sciences D wing was completed in 11/12 making it the first campus building fitted extensively with lighting control systems. Education building VFD replacements As part of the LEED: EBOM project the three main fans are slated for replacement with high efficiency variable frequency drives. Total project cost is approximately $220,000 with a three year payback in reduced electrical energy costs Education building water fixture upgrades All the high water consuming fixtures in the Education building were replaced. Sensors and controls were added to the urinals to limit the consumption of water when not in use. These replacements were part of the LEED: EBOM project costing $95,000 with a three year payback period. LED street light pilot project - A pilot project was started on campus last fiscal retrofitting two roadway lights and two walkway lights with an LED conversion kit. If lighting is deemed adequate for campus use the energy savings could be anywhere from 55% to 75% of the current streetlight consumptions. Infrastructure Funding Mechanisms The utilities business operations support the funding needs for infrastructure through the management of the Infrastructure Renewal Fund and the Infrastructure Development Fund. Infrastructure Renewal Fund (IRF) The IRF was established in 1997 and provides a mechanism for accumulating funding sources for infrastructure renewal projects and programs. The key source of funding for the IRF is the net revenues from utility sales to the university s external and ancillary utility customers. In 2011/12 the net revenues accumulated in the IRF amounted to $2,229,140 down 1% from the previous year and up 2% from the five year average. University of Saskatchewan, Facilities Management Division Utilities Business Operations Annual Report Page 10

12 The balance of the IRF at April 30, 2012 was a deficit of $854,338 due to the commitment made in 2006 to finance the $9.2 Million replacement of the Heating Plant chiller addition (IRF is expected to move into surplus position in 2012/13). The net revenues and expenditure projections for the IRF for the next five years are as follows (new commitments to expenditures will be identified in the later years as needs are determined): Fiscal Period 2012/ / / / /2017 Beginning Balance $(854,338) $778,500 $1,133,959 $849,627 $1,236,709 Net Revenues $2,971,838 $3,010,460 $3,070,669 $3,132,082 $3,194,724 Expenditures $(1,339,000) $(2,655,000) $(3,355,000) $(2,745,000) $(2,585,000) Forecast Balance $778,500 $1,133,959 $849,627 $1,236,709 $1,846,432 Infrastructure Development Fund (IDF) The IDF was established in 2008 and provides a mechanism for accumulating funding sources for infrastructure expansion projects. The key source of funding for the IDF is from a fee called the Infrastructure Development Charge, a flat 1% charge applied to any capital project that results in new space. In 2011/12, the IDF fund collected charges for a total of $663,300 and $1,541,000 was distributed to infrastructure expansion projects. The IDF balance on April 30, 2012 was $1,856,160. Forecasts of yearly contributions are based on current active projects that have Board 1 or 2 approval. The contributions and expenditure projections for the IDF for the next five years are as follows (forecasts of yearly contributions are based on current active projects that have Board 1 or 2 approval and new commitments to expenditures will be identified in the later years as needs are determined): Fiscal Period 2012/ / / / /2017 Beginning Balance $1,856,160 $1,807,160 $1,218,160 $778,160 $778,160 Yearly Contributions $551,000 $161,000 $10,000 $0 $0 Expenditures $(600,000) $(750,000) $(450,000) $0 $0 Forecast Balance $1,807,160 $1,218,160 $778,160 $778,160 $778, /13 Outlook The outlook for the 2012/13 fiscal period can be best described as consistent with the past. Consumption levels of all utilities are expected to follow the trends of the last five years plus additional levels due to the addition of Health Sciences D Wing. Electricity consumption is expected to increase by 3%, natural gas consumption is weather related and, as such, difficult to predict, and water consumptions are expected to return to normal. Pricing levels are, for the most part, expected to continue the trends seen over the last five years. Electricity rates are expected to increase by 4.9% effective January 1, 2012, water rates are estimated to increase by 7.5% effective January 1, 2012, and the average natural gas price will be slightly lower at $7.15 per Gj, as compared to $7.52 per Gj in 2011/12. Maintenance costs in 2012/13 are estimated to be on budget as we aggressively pursue some of the deferred maintenance issues that have been postponed in the past. On August 21, 2012 the University of Saskatchewan signed a contract with Twin Eagle Resource Management to be the supplier of the natural gas to our small meter accounts. The contract starts November 1, 2012 and runs through to October 31, These accounts are currently being supplied by Sask Energy. Given the current consumption rates on these meters this contract has the potential of saving the university approximately $50,000. University of Saskatchewan, Facilities Management Division Utilities Business Operations Annual Report Page 11

13 We will focus on several initiatives in 2012/13: Utility Metering The university s metering needs are being reviewed within the context of Transparent Activity-Based Budget System (TABBS) as well as the Energy Management Program under development. A Meter Replacement Program has been developed and will be put into action during the 2012/13 fiscal period. Campus Building Energy Contact Initiative An energy management initiative was started in 2011/12 identifying key energy individuals for each building on campus. These individuals will be sent monthly energy consumption figures for their respective buildings to increase the awareness and importance of energy conservation moving forward. This list of people will also serve as a source for troubleshooting not only consumption variances, but also any operations and maintenance issues that may come forward. Information based invoices with information on consumption and associated cost to the university have been developed and sent out to a few select individuals for feedback. Response has been very good. After completing a few small changes to the format, invoices will be sent out monthly for all buildings. University of Saskatchewan, Facilities Management Division Utilities Business Operations Annual Report Page 12

SASKENERGY INCORPORATED

SASKENERGY INCORPORATED SASKENERGY INCORPORATED THIRD QUARTER REPORT September 30, 2015 OF CONTENTS TABLE OF CONTENTS Corporate Profile 2 Vision, Mission and Values 3 Financial and Operating Highlights 4 Management s Discussion

More information

SASKENERGY INCORPORATED

SASKENERGY INCORPORATED SASKENERGY INCORPORATED THIRD QUARTER REPORT, 2017 TABLE OF CONTENTS VISION, MISSION AND VALUES As a Crown corporation, SaskEnergy is committed to ensuring that all corporate activities align with the

More information

BUSINESS INCENTIVE PROGRAM APPLICATION

BUSINESS INCENTIVE PROGRAM APPLICATION BUSINESS INCENTIVE PROGRAM APPLICATION PART A APPLICANT INFORMATION (Financial incentive payment will be made to Applicant ONLY.) 1. Applicant: Legal Name of Business (the "Applicant"): Address: City:

More information

SASKENERGY INCORPORATED

SASKENERGY INCORPORATED SASKENERGY INCORPORATED FIRST QUARTER REPORT June 30, 2018 TABLE OF CONTENTS VISION, MISSION AND VALUES As a Crown corporation, SaskEnergy is committed to ensuring that all corporate activities align with

More information

2017 Distribution Rates and Charges Q&A s

2017 Distribution Rates and Charges Q&A s 2017 Distribution Rates and Charges Q&A s Overview Distribution rates and charges for all rate classes are reviewed and set on an annual basis and as such, Enbridge Gas New Brunswick submitted an application

More information

MANITOBA Order No. 15/01. THE PUBLIC UTILITIES BOARD ACT February 1, G. D. Forrest, Chair M. Girouard, Member M.

MANITOBA Order No. 15/01. THE PUBLIC UTILITIES BOARD ACT February 1, G. D. Forrest, Chair M. Girouard, Member M. MANITOBA Order No. 15/01 THE PUBLIC UTILITIES BOARD ACT February 1, 2001 Before: G. D. Forrest, Chair M. Girouard, Member M. Santos, Member AN APPLICATION BY CENTRA GAS MANITOBA INC. FOR AN ORDER APPROVING

More information

Additional Agenda. City of Mississauga. General Committee. Date June 27, 2018 Time 9:00 A.M. Location Council Chamber 2 nd Floor 300 City Centre Drive

Additional Agenda. City of Mississauga. General Committee. Date June 27, 2018 Time 9:00 A.M. Location Council Chamber 2 nd Floor 300 City Centre Drive City of Mississauga Additional Agenda General Committee Date June 27, 2018 Time 9:00 A.M. Location Council Chamber 2 nd Floor 300 City Centre Drive REMOVAL OF DEPUTATION 5.5 Kevin Sherwin, Chair of the

More information

SaskEnergy Commodity Rate 2011 Review and Natural Gas Market Update

SaskEnergy Commodity Rate 2011 Review and Natural Gas Market Update SaskEnergy Commodity Rate 2011 Review and Natural Gas Market Update The following is a discussion of how SaskEnergy sets its commodity rate, the status of the natural gas marketplace and the Corporation

More information

SASKENERGY INCORPORATED

SASKENERGY INCORPORATED SASKENERGY INCORPORATED FIRST QUARTER REPORT June 30, 2016 TABLE OF CONTENTS TABLE OF CONTENTS Corporate Profile 2 Vision, Mission and Values 3 Financial and Operating Highlights 4 Management s Discussion

More information

DTE Energy Multifamily Program

DTE Energy Multifamily Program DTE Energy Multifamily Program 2016 Policies and Procedures Manual The DTE Energy Multifamily Program provides incentives for Multifamily property owners who upgrade their facilities with energy efficient

More information

M A N I T O B A ) Order No. 148/08 ) THE PUBLIC UTILITIES BOARD ACT ) October 30, 2008

M A N I T O B A ) Order No. 148/08 ) THE PUBLIC UTILITIES BOARD ACT ) October 30, 2008 M A N I T O B A ) ) THE PUBLIC UTILITIES BOARD ACT ) October 30, 2008 BEFORE: Graham Lane, C.A., Chairman Leonard Evans, LL.D., Member Monica Girouard, CGA, Member SWAN VALLEY GAS CORPORATION: NATURAL

More information

Executive Director s Summary Report

Executive Director s Summary Report Executive Director s Summary Report to the Board of Trustees of the Efficiency Maine Trust November 19, 2014 I. Communications a. Awareness and Press Staff has scheduled the Annual Event for Thursday January

More information

DTE Energy s Energy Efficiency Program for Business Policies and Procedures Manual

DTE Energy s Energy Efficiency Program for Business Policies and Procedures Manual DTE Energy s Energy Efficiency Program for Business 2015 Policies and Procedures Manual DTE Energy s Energy Efficiency Program for Business provides incentives for business customers who upgrade their

More information

Management s discussion and analysis ( MD&A ) May 17, 2017

Management s discussion and analysis ( MD&A ) May 17, 2017 Management s discussion and analysis ( MD&A ) May 17, 2017 The following discussion and analysis is a review of the financial condition and operating results of Just Energy Group Inc. ( JE or Just Energy

More information

TCDSB GAS PURCHASING STRATEGY

TCDSB GAS PURCHASING STRATEGY PUBLIC REPORT TO CORPORATE AFFAIRS, STRATEGIC PLANNING AND PROPERTY COMMITTEE TCDSB GAS PURCHASING STRATEGY 2014-2015 I can do all this through Him who gives me strength. Philippians 4:13 (NIV) Created,

More information

Pacific Gas and Electric Company. Statement of Estimated Cash Flows April 20, 2001

Pacific Gas and Electric Company. Statement of Estimated Cash Flows April 20, 2001 Pacific Gas and Electric Company Statement of Estimated Cash Flows April 20, 2001 This document provides the latest forecast of cash flows for Pacific Gas and Electric Company (the Company ). The purpose

More information

Executive Director s Summary Report

Executive Director s Summary Report Executive Director s Summary Report to the Board of Trustees of the Efficiency Maine Trust July 18, 2018 1. Communications A) Awareness and Press Press o Events o The Trust s Electric Vehicle Supply Equipment

More information

M A N I T O B A ) Order No. 81/10 ) THE PUBLIC UTILITIES BOARD ACT ) July 28, 2010

M A N I T O B A ) Order No. 81/10 ) THE PUBLIC UTILITIES BOARD ACT ) July 28, 2010 M A N I T O B A ) ) THE PUBLIC UTILITIES BOARD ACT ) BEFORE: Graham Lane, CA, Chairman Leonard Evans, LLD, Member Monica Girouard, CGA, Member CENTRA GAS MANITOBA INC.: PRIMARY GAS RATES, EFFECTIVE AUGUST

More information

Facility Condition Assessment. Facility Condition Assessment 8/13/2013 AGENDA

Facility Condition Assessment. Facility Condition Assessment 8/13/2013 AGENDA AGENDA benefits & limitations Rod Moore, RA, LEED AP, PMP Georgia Tech Benjamin Dutton, FFB, MCIOB, MRICS Faithful+Gould GT Facilities GT Program What is GT FCA Deliverables How GT uses FCA Information

More information

November 30, 2018 Index MANITOBA HYDRO 2019/20 ELECTRIC RATE APPLICATION

November 30, 2018 Index MANITOBA HYDRO 2019/20 ELECTRIC RATE APPLICATION MANITOBA HYDRO 0/0 ELECTRIC RATE APPLICATION November 0, 0 Index 0 0 0 INDEX.0 Overview and Reasons for the Requested Rate Increase....0 Manitoba Hydro s Financial Position and Outlook.... 0/ Actual Financial

More information

Quarterly Report for the three months ended June 30, 2017

Quarterly Report for the three months ended June 30, 2017 The Manitoba Hydro-Electric Board Quarterly Report for the three months ended, 2017 Comments by The Chair of the Board and by The President and Chief Executive Officer Financial Overview Manitoba Hydro

More information

M A N I T O B A ) Order No. 147/09 ) THE PUBLIC UTILITIES BOARD ACT ) October 29, 2009

M A N I T O B A ) Order No. 147/09 ) THE PUBLIC UTILITIES BOARD ACT ) October 29, 2009 M A N I T O B A ) ) THE PUBLIC UTILITIES BOARD ACT ) BEFORE: Graham Lane, CA, Chairman Leonard Evans, LLD, Member Monica Girouard, CGA, Member CENTRA GAS MANITOBA INC.: PRIMARY GAS RATES, EFFECTIVE NOVEMBER

More information

TECHNICAL GUIDE A GUIDE TO FINANCING ENERGY MANAGEMENT

TECHNICAL GUIDE A GUIDE TO FINANCING ENERGY MANAGEMENT TECHNICAL GUIDE A GUIDE TO FINANCING ENERGY MANAGEMENT Table of Contents 1. Introduction 1 2. What is Energy Management Financing? 2 3. Barriers to Investing in Energy Management 3 1. Initial Costs 3 2.

More information

Board of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019

Board of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019 Board of Trustees Budget, Finance and Facilities Committee Meeting January 24, 2019 PRESENTED BY Finance and Administration Florida Agricultural and Mechanical University 1 ACTION ITEM IV: Approval of

More information

ENMAX Corporation 2017 Q2 INTERIM REPORT CAUTION TO READER

ENMAX Corporation 2017 Q2 INTERIM REPORT CAUTION TO READER ENMAX Corporation 2017 Q2 INTERIM REPORT ENMAX Corporation CAUTION TO READER This document contains statements about future events and financial and operating results of ENMAX Corporation and its subsidiaries

More information

M A N I T O B A ) Order No. 108/10 ) THE PUBLIC UTILITIES BOARD ACT ) October 29, 2010

M A N I T O B A ) Order No. 108/10 ) THE PUBLIC UTILITIES BOARD ACT ) October 29, 2010 M A N I T O B A ) Order No. 108/10 ) THE PUBLIC UTILITIES BOARD ACT ) October 29, 2010 BEFORE: Graham Lane, C.A., Chairman Leonard Evans, LL.D., Member Monica Girouard, CGA, Member SWAN VALLEY GAS CORPORATION:

More information

Canadian Oil Sands Trust announces 2009 second quarter results

Canadian Oil Sands Trust announces 2009 second quarter results Canadian Oil Sands Trust announces 2009 second quarter results All financial figures are unaudited and in Canadian dollars unless otherwise noted. TSX - COS.UN Calgary, Alberta (July 27, 2009) Canadian

More information

TFS Energy CC Lighting Energy Efficiency Consultants

TFS Energy CC Lighting Energy Efficiency Consultants Lighting Audit Report Company: Lufil Packaging 170 Units Only Version 2 Actual Electricity 27 h October 2016 Dear Sir, Thank you for the opportunity to do a Lighting Energy Efficiency Audit of your company

More information

M A N I T O B A ) Order No. 140/07 ) THE PUBLIC UTILITIES BOARD ACT ) October 29, 2007

M A N I T O B A ) Order No. 140/07 ) THE PUBLIC UTILITIES BOARD ACT ) October 29, 2007 M A N I T O B A ) ) THE PUBLIC UTILITIES BOARD ACT ) October 29, 2007 BEFORE: Graham Lane, B.A., C.A., Chairman Leonard Evans, LL.D., Member Monica Girouard, C.G.A., Member CENTRA GAS MANITOBA INC. PRIMARY

More information

2009 ENERGY EFFICIENCY INDICATOR

2009 ENERGY EFFICIENCY INDICATOR Johnson Controls, Inc. International Facility Management Association 2009 ENERGY EFFICIENCY INDICATOR SUMMARY REPORT www.ifma.org International Facility Management Association International Facility Management

More information

2017 Mid-Year Financial Report

2017 Mid-Year Financial Report 2017 Mid-Year Financial Report BACKGROUND The mid-year report provides information regarding the City of Regina s (City) financial performance. This report provides a high level summary on how the City

More information

STANDARD AND CUSTOM INCENTIVES PRE-APPROVAL AND FINAL APPLICATION FORM

STANDARD AND CUSTOM INCENTIVES PRE-APPROVAL AND FINAL APPLICATION FORM PRE-APPROVAL AND FINAL APPLICATION FORM The ComEd Energy Efficiency Program offers incentives to help facilities save money by improving the efficiency of their equipment. Receive standard cash incentives

More information

Subsidiary Crown Policy Manual

Subsidiary Crown Policy Manual Subsidiary Crown Policy Manual Public Reporting Guidelines Issue Date: January 1, 2003 Revised Date: May 31, 2017 Authority: The Crown Corporations Act, 1993 CIC Board Minute Number # 31/2004 Applicability:

More information

Richmond Building Energy Challenge

Richmond Building Energy Challenge Richmond Building Energy Challenge Robert Greenwald, P.Eng., MBA, President (Principal) Robert Greenwald has 25 years of energy management experience including developing energy plans, determining opportunities,

More information

Canadian Oil Sands Trust announces 2009 third quarter results

Canadian Oil Sands Trust announces 2009 third quarter results Canadian Oil Sands Trust announces 2009 third quarter results All financial figures are unaudited and in Canadian dollars unless otherwise noted. TSX - COS.UN Calgary, Alberta (October 28, 2009) Canadian

More information

SCHOOL DISTRICT OF BOROUGH OF MORRISVILLE

SCHOOL DISTRICT OF BOROUGH OF MORRISVILLE FEBRUARY 8, 2019 INVESTMENT GRADE AUDIT SUMMARY REPORT SCHOOL DISTRICT OF BOROUGH OF MORRISVILLE in support of Act 77/39 Guaranteed Energy Savings Agreement (GESA) Reynolds Energy Services, Inc. 3300 North

More information

A Portfolio Approach to Securing Internal Financing for Energy Efficiency

A Portfolio Approach to Securing Internal Financing for Energy Efficiency A Portfolio Approach to Securing Internal Financing for Energy Efficiency Evelyn Lundhild, IESO Ian Shaw, ArcelorMittal Dofasco ABSTRACT The Ontario Independent Electricity System Operator (IESO), formerly

More information

5 YEARS. CASE STUDY with Utility Bills

5 YEARS. CASE STUDY with Utility Bills CASE STUDY with Utility Bills 5 YEARS Performance Review: The First Independent Retailer in the US to Retrofit with LED Tubes. In 2009, a third generation family business took the initiative to invest

More information

ONTARIO ENERGY REPORT Q3 2018

ONTARIO ENERGY REPORT Q3 2018 ONTARIO ENERGY REPORT Q3 JULY SEPTEMBER OIL AND NATURAL GAS Regular Gasoline and Diesel Provincial Retail Prices ($/L) Regular Gasoline $1.3 Diesel $1.9 Source: Ministry of Energy, Northern Development

More information

BC HYDRO S RATE DESIGN APPLICATION FARM AND IRRIGATION CUSTOMER ISSUES. Presentation to the BC Cranberry Marketing Commission (BCCMC) June 15, 2015

BC HYDRO S RATE DESIGN APPLICATION FARM AND IRRIGATION CUSTOMER ISSUES. Presentation to the BC Cranberry Marketing Commission (BCCMC) June 15, 2015 BC HYDRO S RATE DESIGN APPLICATION FARM AND IRRIGATION CUSTOMER ISSUES Presentation to the BC Cranberry Marketing Commission (BCCMC) June 15, 2015 AGENDA Background on BC Hydro s 2015 Rate Design Application

More information

Multifamily Energy Efficiency Program

Multifamily Energy Efficiency Program Multifamily Energy Efficiency Program Rebate Reservation Request To reserve incentives from the PNM Multifamily Energy Efficiency Program, please complete this form and return to multifamily@pnm.com or

More information

Q INTERIM REPORT

Q INTERIM REPORT ENMAX CORPORATION Q2 2018 INTERIM REPORT CAUTION TO READER This document contains statements about future events and financial and operating results of ENMAX Corporation and its subsidiaries (ENMAX or

More information

NEWS RELEASE Bonterra Energy Corp. Announces Third Quarter 2018 Financial and Operational Results

NEWS RELEASE Bonterra Energy Corp. Announces Third Quarter 2018 Financial and Operational Results NEWS RELEASE Bonterra Energy Corp. Announces Third Quarter 2018 Financial and Operational Results November 7, 2018 CALGARY, ALBERTA - Bonterra Energy Corp. (www.bonterraenergy.com) (TSX: BNE) ( Bonterra

More information

LIGHTING MAINTENANCE PLAN

LIGHTING MAINTENANCE PLAN LIGHTING MAINTENANCE PLAN THE FIRST AND LAST LED YOU'LL EVER NEED. THE FIRST AND LAST LED YOU'LL EVER NEED. ABOUT WHY BENEFITS? SAFE Fast-Lite product is third party tested by either of the two industry

More information

Application Terms & Conditions and Final Payment Agreement

Application Terms & Conditions and Final Payment Agreement Prescriptive, Self-Direct Custom Program & Self-Direct Application Terms & Conditions and Final Payment Agreement Version: January 1, 2015 January 2017 TERMS AND CONDITIONS AEP Ohio offers Efficient Products

More information

Executive Director s Summary Report

Executive Director s Summary Report Executive Director s Summary Report to the Board of Trustees of the Efficiency Maine Trust November 14, 2018 1. Communications A) Awareness and Press Press o Ductless heat pumps were the topic of an article

More information

R E Q U E S T F O R P R O P O S A L O N Q U A L I F I C A T I O N S F O R A C A M P U S W I D E E N E R G Y S E R V I C E S P R O G R A M

R E Q U E S T F O R P R O P O S A L O N Q U A L I F I C A T I O N S F O R A C A M P U S W I D E E N E R G Y S E R V I C E S P R O G R A M U N I V E R S I T Y O F N O R T H A L A B A M A R E Q U E S T F O R P R O P O S A L O N Q U A L I F I C A T I O N S F O R A C A M P U S W I D E E N E R G Y S E R V I C E S P R O G R A M R F P 2 0 1 7-23

More information

2008 Second Quarter Results

2008 Second Quarter Results 20 Second Quarter Results August 8, 20 Power to Perform Forward-Looking Statements This presentation contains forward-looking statements that may be identified by words like forecast, estimated, expected

More information

Natural Gas Demand Side Management Evaluation, Measurement, and Verification (EM&V) Plan

Natural Gas Demand Side Management Evaluation, Measurement, and Verification (EM&V) Plan 2016-2018 Natural Gas Demand Side Management Evaluation, Measurement, and Verification (EM&V) Plan submitted to the Ontario Energy Board Date: November 10, 2016 DNV GL - Energy www.dnvgl.com/energy Table

More information

BOARD OF PUBLIC UTILITIES KANSAS CITY, KANSAS

BOARD OF PUBLIC UTILITIES KANSAS CITY, KANSAS BOARD OF PUBLIC UTILITIES KANSAS CITY, KANSAS Electric Utility Revenues, Revenue Requirements, Cost of Service, And Rates Draft Final Report (As Updated) February 2010 February 1, 2010 Kansas City Board

More information

Executive Director s Summary Report

Executive Director s Summary Report Executive Director s Summary Report to the Board of Trustees of the Efficiency Maine Trust July 20, 2016 1. Communications A.) Awareness and Press Outreach Events o Save the date for the Trust s Combined

More information

Lunch and Learn: Energy Efficient Dairy Production

Lunch and Learn: Energy Efficient Dairy Production Lunch and Learn: Energy Efficient Dairy Production People s Energy Cooperative December 11, 2014 Agenda Welcome Introductions Clicker Trial Run Farmer Feedback on Energy Efficient Dairy Production Technologies

More information

Schedule of Revenues, Expenses, and Changes in Net Position (Income Statement) Page 4

Schedule of Revenues, Expenses, and Changes in Net Position (Income Statement) Page 4 M E M O R A N D U M EUGENE WATER & ELECTRIC BOARD TO: Commissioners Simpson, Helgeson, Manning, Mital and Brown FROM: Sue Fahey, Chief Financial Officer; Susan Eicher, Accounting & Treasury Supervisor

More information

Statement of Revenues, Expenses, and Changes in Net Position (Income Statement) Page 4

Statement of Revenues, Expenses, and Changes in Net Position (Income Statement) Page 4 M E M O R A N D U M EUGENE WATER & ELECTRIC BOARD TO: FROM: DATE: August 26, 2016 SUBJECT: OBJECTIVE: Commissioners Simpson, Helgeson, Manning, Mital and Brown Sue Fahey, CFO; Susan Eicher, Accounting

More information

FIVE YEAR PLAN FOR ENERGY EFFICIENCY

FIVE YEAR PLAN FOR ENERGY EFFICIENCY FIVE YEAR PLAN FOR ENERGY EFFICIENCY Executive Summary Prepared for: Holy Cross Energy Navigant Consulting, Inc. 1375 Walnut Street Suite 200 Boulder, CO 80302 303.728.2500 www.navigant.com July 15, 2011

More information

SECOND QUARTER REPORT 2010

SECOND QUARTER REPORT 2010 SECOND QUARTER REPORT 2010 Q2 FORMERLY ENERGY SAVINGS INCOME FUND HIGHLIGHTS FOR THE THREE MONTHS ENDED SEPTEMBER 30, 2009, INCLUDED: Sales (seasonally adjusted) of 562.1 million, up 46% year over year.

More information

TAME Express Guidebook

TAME Express Guidebook TAME Express Guidebook This Guidebook provides an overview of the eligibility requirements, available funding, and process for municipalities to participate in the Taking Action to Manage Energy Express

More information

Quarterly Report to the Pennsylvania Public Utility Commission

Quarterly Report to the Pennsylvania Public Utility Commission Quarterly Report to the Pennsylvania Public Utility Commission For the Period November 05 through February 06 Program Year 7, Quarter For Pennsylvania Act 9 of 008 Energy Efficiency and Conservation Plan

More information

Saskatchewan Lotteries Trust Fund for Sport, Culture, and Recreation

Saskatchewan Lotteries Trust Fund for Sport, Culture, and Recreation Saskatchewan Lotteries Trust Fund for Sport, Culture, and Recreation Performance Plan 2016-2017 Board Approved: 15:71 Who We Are The Saskatchewan Lotteries Trust Fund for Sport, Culture and Recreation

More information

Canadian Oil Sands announces second quarter 2012 financial results

Canadian Oil Sands announces second quarter 2012 financial results July 27, 2012 TSX: COS Canadian Oil Sands announces second quarter 2012 financial results All financial figures are unaudited and in Canadian dollars unless otherwise noted. Highlights for the three and

More information

Comprehensive Review of BC Hydro: Phase 1 Final Report

Comprehensive Review of BC Hydro: Phase 1 Final Report Comprehensive Review of BC Hydro: Phase 1 Final Report ii Table of Contents 1. Executive Summary 1 1.1 Enhancing Regulatory Oversight of BC Hydro 1 1.2 New Rates Forecast 3 1.3 Next Steps 5 2. Strategic

More information

Orlando Utilities Commission

Orlando Utilities Commission THREE MONTHS ENDED December 2016 1 Orlando Utilities Commission Table of Contents Management s Discussion and Analysis 3 Quarterly Report Capital Project Approval 6 Statements of Revenues, Expenses and

More information

Executive Director s Summary Report

Executive Director s Summary Report Executive Director s Summary Report to the Board of Trustees of the Efficiency Maine Trust August 22, 2018 1. Communications A) Awareness and Press Press o The Residential Manager was interviewed for a

More information

CHESAPEAKE UTILITIES CORPORATION REPORTS SEVENTH CONSECUTIVE YEAR OF RECORD EARNINGS

CHESAPEAKE UTILITIES CORPORATION REPORTS SEVENTH CONSECUTIVE YEAR OF RECORD EARNINGS FOR IMMEDIATE RELEASE March 6, 2014 NYSE Symbol: CPK CHESAPEAKE UTILITIES CORPORATION REPORTS SEVENTH CONSECUTIVE YEAR OF RECORD EARNINGS Net income increased to $32.8 million, or $3.39 per share Growth

More information

Contents. Financial Decisions Simple Payback Time Value of Money Net Present Value Internal Rate of Return Life-Cycle Cost Analysis

Contents. Financial Decisions Simple Payback Time Value of Money Net Present Value Internal Rate of Return Life-Cycle Cost Analysis March 28, 2017 2 Mike Carter Contents Financial Decisions Simple Payback Time Value of Money Net Present Value Internal Rate of Return Life-Cycle Cost Analysis Source: Svilen Milev at www.sxc.hu Combining

More information

MANITOBA Order No. 170/01. THE PUBLIC UTILITIES BOARD ACT October 31, G. D. Forrest, Chairman M. Girouard, Member M.

MANITOBA Order No. 170/01. THE PUBLIC UTILITIES BOARD ACT October 31, G. D. Forrest, Chairman M. Girouard, Member M. MANITOBA Order No. 170/01 THE PUBLIC UTILITIES BOARD ACT October 31, 2001 BEFORE: G. D. Forrest, Chairman M. Girouard, Member M. Santos, Member AN APPLICATION BY CENTRA GAS MANITOBA INC. FOR AN ORDER APPROVING

More information

WGL Holdings, Inc. Reports Second Quarter Fiscal Year 2014 Financial Results; Raises Fiscal Year 2014 Non-GAAP Guidance

WGL Holdings, Inc. Reports Second Quarter Fiscal Year 2014 Financial Results; Raises Fiscal Year 2014 Non-GAAP Guidance May 7, 2014 WGL Holdings, Inc. Reports Second Quarter Fiscal Year 2014 Financial Results; Raises Fiscal Year 2014 Non-GAAP Guidance Consolidated earnings per share $1.18 per share vs. $1.73 per share for

More information

Graham F.J. Lane, B. A., C.A., Chairman Monica Girouard, C.G.A., Member Mario J. Santos, B.A., LL.B., Member

Graham F.J. Lane, B. A., C.A., Chairman Monica Girouard, C.G.A., Member Mario J. Santos, B.A., LL.B., Member MANITOBA THE PUBLIC UTILITIES BOARD ACT January 31, 2006 Before: Graham F.J. Lane, B. A., C.A., Chairman Monica Girouard, C.G.A., Member Mario J. Santos, B.A., LL.B., Member AN APPLICATION BY CENTRA GAS

More information

TOWNSHIP OF LOWER MERION. PUBLIC WORKS COMMITTEE Wednesday, September 12, :00 PM ( Approximately)

TOWNSHIP OF LOWER MERION. PUBLIC WORKS COMMITTEE Wednesday, September 12, :00 PM ( Approximately) TOWNSHIP OF LOWER MERION PUBLIC WORKS COMMITTEE Wednesday, September 12, 2018 7:00 PM ( Approximately) Chairpersons: Vice Chairperson: Rick Churchill Cheryl B. Gelber, Anthony C. Stevenson a a AGENDA 1.

More information

Delivering Efficiency as a Service: The Metrus ESA

Delivering Efficiency as a Service: The Metrus ESA Delivering Efficiency as a Service: The Metrus ESA May 22, 2018 Overview Metrus develops, finances, owns, and operates large-scale efficiency projects for Fortune 500 companies and major industrial customers.

More information

Bill Assistance Report. I. Key Components of Bill Assistance Programs

Bill Assistance Report. I. Key Components of Bill Assistance Programs Bill Assistance Report Through Order 116/08, Manitoba Public Utilities Board issued a directive to propose for Board approval a low-income bill assistance program. Manitoba Hydro is in the process of reviewing

More information

The University of Alberta Budget

The University of Alberta Budget The University of Alberta Budget The University of Alberta Budget We ll be looking at: The Province and PSE Budgets at the U of A Student Fees Tuition MNIFS Quality of Education A Note on Student Finances

More information

Executive Director s Summary Report

Executive Director s Summary Report Executive Director s Summary Report to the Board of Trustees of the Efficiency Maine Trust December 19, 2018 1. Communications A) Awareness and Press Press o The Executive Director was interviewed on the

More information

Natural Gas & Electricity Procurement Program

Natural Gas & Electricity Procurement Program Reported to the Board of Trustees May 31, 2012 Natural Gas & Electricity Procurement Program Status Report to the Board of Trustees May 31, 2012 PROGRESS TO DATE The procurement activity under the Board

More information

Plant Organization and Operations. Operations. Overview of Session. Responsibilities 8/19/2015

Plant Organization and Operations. Operations. Overview of Session. Responsibilities 8/19/2015 Plant Organization and Operations Jeff Zumwalt and Larry Schuster University of New Mexico Overview of Session Performance Measurement Customer Connections Environment Human Resources Budgeting Emergency

More information

November 22, British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3

November 22, British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 Diane Roy Director, Regulatory Affairs - Gas FortisBC Energy Inc. November 22, 2012 British Columbia Utilities Commission 6 th Floor, 900 Howe Street Vancouver, BC V6Z 2N3 16705 Fraser Highway Surrey,

More information

New natural gas rates approved in 2018.

New natural gas rates approved in 2018. New natural gas rates approved in 2018. Who is CenterPoint Energy? CenterPoint Energy, Inc., headquartered in Houston, Texas, is a domestic energy delivery company that includes electric transmission &

More information

Economics of Distributed Resources

Economics of Distributed Resources ELG4126- Sustainable Electrical Power Systems- DGD Economics of Distributed Resources Maryam Parsa DGD 04-31 Jan, 2013 Winter 2013 REVIEW from DGD 02- Jan 14 th Simple Payback Period Initial (Simple) Rate-Of-Return

More information

ESSENTIAL ENERGY SERVICES TRUST RELEASES FOURTH QUARTER AND YEAR END RESULTS

ESSENTIAL ENERGY SERVICES TRUST RELEASES FOURTH QUARTER AND YEAR END RESULTS For Immediate Release: March 17, 2008 ESSENTIAL ENERGY SERVICES TRUST RELEASES FOURTH QUARTER AND YEAR END RESULTS Calgary, Alberta (TSX: ESN.UN) ( Essential, or the Trust ) releases the operational and

More information

Executive Director s Summary Report

Executive Director s Summary Report Executive Director s Summary Report to the Board of Trustees of the Efficiency Maine Trust July 26, 2017 1. Communications A) Awareness and Press Outreach Events: o Staff presented at the Education Facility

More information

Spire Reports 2017 Results

Spire Reports 2017 Results For Immediate Release Spire Reports 2017 Results Raises dividend 7.1 percent ST. LOUIS (November 15, 2017) - Spire Inc. (NYSE: SR) today reported results for its fiscal 2017 full year and fourth quarter

More information

The Company's resource management effort is a continuous process. used by the Company to manage its portfolio in order to: (i) maximize the use of

The Company's resource management effort is a continuous process. used by the Company to manage its portfolio in order to: (i) maximize the use of V. MANAGEMENT OF THE RESOURCE PORTFOLIO A. Introduction The Company's resource management effort is a continuous process used by the Company to manage its portfolio in order to: (i) maximize the use of

More information

ENMAX Corporation FINANCIAL REVIEW ENMAX 2016

ENMAX Corporation FINANCIAL REVIEW ENMAX 2016 ENMAX Corporation FINANCIAL REVIEW ENMAX 2016 CAUTION TO READER This document contains statements about future events and financial and operating results of ENMAX Corporation and its subsidiaries (ENMAX

More information

Cash & Liquidity The chart below highlights CTA s cash position at March 2018 compared to March 2017.

Cash & Liquidity The chart below highlights CTA s cash position at March 2018 compared to March 2017. To: Chicago Transit Authority Board From: Jeremy Fine, Chief Financial Officer Re: Financial Results for March 2018 Date: May 9, 2018 I. Summary CTA s financial results are $0.9 million favorable to budget

More information

Year end fiscal Earnings conference call. November 15, 2017

Year end fiscal Earnings conference call. November 15, 2017 Year end fiscal 2017 Earnings conference call November 15, 2017 Participants on today s call Suzanne Sitherwood President and Chief Executive Officer Steven L. Lindsey Executive Vice President and Chief

More information

Canadian Oil Sands Trust second quarter funds from operations increase 14 per cent with higher crude oil prices and production

Canadian Oil Sands Trust second quarter funds from operations increase 14 per cent with higher crude oil prices and production Canadian Oil Sands Trust second quarter funds from operations increase 14 per cent with higher crude oil prices and production All financial figures are unaudited and in Canadian dollars unless otherwise

More information

ORCAS POWER AND LIGHT COOPERATIVE 2018 Q3 FINANCIALS Q3 Financial Report Page 1 of 20

ORCAS POWER AND LIGHT COOPERATIVE 2018 Q3 FINANCIALS Q3 Financial Report Page 1 of 20 ORCAS POWER AND LIGHT COOPERATIVE 2018 Q3 FINANCIALS Page 1 of 20 MEMORANDUM November 09, 2018 To: Board of Directors From: Foster Hildreth, General Manager Re: OPALCO 2018 Third Quarter Financial Report

More information

PRESS RELEASE. Just Energy Reports Second Quarter Fiscal 2018 Results

PRESS RELEASE. Just Energy Reports Second Quarter Fiscal 2018 Results PRESS RELEASE Just Energy Reports Second Quarter Fiscal 2018 Results Numerous Headwinds, Mostly Non-Recurring, Negatively Impacted Quarterly Performance Positive net customer additions achieved with higher

More information

SECOND QUARTER REPORT JUNE 30, 2015

SECOND QUARTER REPORT JUNE 30, 2015 SECOND QUARTER REPORT JUNE 30, 2015 TORONTO HYDRO CORPORATION TABLE OF CONTENTS Glossary 3 Management s Discussion and Analysis 4 Executive Summary 5 Introduction 5 Business of Toronto Hydro Corporation

More information

FortisBC Inc. (FBC) Application for Approval of Demand Side Management (DSM) Expenditures for 2015 and 2016 FBC Final Submission

FortisBC Inc. (FBC) Application for Approval of Demand Side Management (DSM) Expenditures for 2015 and 2016 FBC Final Submission Dennis Swanson Director, Regulatory Affairs FortisBC Inc. Suite 100 1975 Springfield Road Kelowna, BC V1Y 7V7 Tel: (250) 717-0890 Fax: 1-866-335-6295 www.fortisbc.com Regulatory Affairs Correspondence

More information

Energy Efficiency & Utility Allowances MAHMA Regional Affordable Housing Conference Detroit, Michigan June 4 th, 2014

Energy Efficiency & Utility Allowances MAHMA Regional Affordable Housing Conference Detroit, Michigan June 4 th, 2014 Energy Efficiency & Utility Allowances 2014 MAHMA Regional Affordable Housing Conference Detroit, Michigan June 4 th, 2014 Portfolio Statistics # of properties in US and Puerto Rico 340 # of states with

More information

PRESS RELEASE. Just Energy Reports First Quarter 2019 Results

PRESS RELEASE. Just Energy Reports First Quarter 2019 Results PRESS RELEASE Just Energy Reports First Quarter 2019 Results Positive customer addition trends continue Continued execution of multi-channel expansion strategy Reaffirms fiscal 2019 Base EBITDA guidance

More information

General Fund Revenue

General Fund Revenue Millions Percent of Kathy Steinert, Director of Fiscal Services Phone: 541.923.8927 145 SE Salmon Ave Redmond, OR 97756 kathy.steinert@redmond.k12.or.us Date: May 23, 2014 To: Redmond School District Board

More information

Commercial Refrigeration Incentive Application for Business Customers

Commercial Refrigeration Incentive Application for Business Customers 2019 Commercial Refrigeration Incentive Application for Business Customers A Cash Incentive Energy Efficiency Program brought to you by: IMPORTANT INSTRUCTIONS: Step 1: Determine Eligibility: Pre-approval

More information

Southern Company. 3rd Quarter 2003 Earnings. September 30, 2003

Southern Company. 3rd Quarter 2003 Earnings. September 30, 2003 Southern Company 3rd Quarter 2003 Earnings September 30, 2003 Contents Press Release 1 Business Outlook 4 Financial Highlights 8 Factors Affecting Earnings 8 Analysis of Consolidated Earnings 9 Kilowatt

More information

Managing your profits using temperature and commodity price protection

Managing your profits using temperature and commodity price protection Managing your profits using temperature and commodity price protection What affects my business? Your earnings volatility Temperature Commodity Prices Dec13 Feb14-1981-2010 anomaly European Climate Assessment

More information

2009 FINANCIAL REPORT. Customer focused, Results driven

2009 FINANCIAL REPORT. Customer focused, Results driven 2009 FINANCIAL REPORT Customer focused, Results driven KEYERA 2009 FINANCIAL REPORT Corporate Profile As one of the largest midstream operators in Canada, Keyera provides key services and products to oil

More information

The Real Meaning of Total Cost of Ownership (TCO)

The Real Meaning of Total Cost of Ownership (TCO) The Real Meaning of Total Cost of Ownership (TCO) Presented by David Patnaude Director of Plant and Sustainability Riverdale Country School Lawrence Eighmy Managing Principle 1 The Real Meaning of Total

More information

Executive Director s Summary Report

Executive Director s Summary Report Executive Director s Summary Report to the Board of Trustees of the Efficiency Maine Trust January 23, 2019 1. Communications A) Awareness and Press Press o Efficiency Maine s electric vehicle charging

More information

CONSOLIDATED FINANCIAL STATEMENTS MARCH 31, 2013

CONSOLIDATED FINANCIAL STATEMENTS MARCH 31, 2013 Toronto Hydro Corporation First Quarter of 2009 - Report to the Shareholder For the Three Months Ended March 31, 2009 CONSOLIDATED FINANCIAL STATEMENTS MARCH 31, 2013 INTERIM CONSOLIDATED BALANCE SHEETS

More information