IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48660) ON A LOAN IN THE AMOUNT OF US$ MILLION TO THE ISTANBUL METROPOLITAN MUNICIPALITY

Size: px
Start display at page:

Download "IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48660) ON A LOAN IN THE AMOUNT OF US$ MILLION TO THE ISTANBUL METROPOLITAN MUNICIPALITY"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48660) ON A LOAN IN THE AMOUNT OF US$ MILLION TO THE ISTANBUL METROPOLITAN MUNICIPALITY FOR AN ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT Sustainable Development Department Turkey Country Unit Europe and Central Asia Region November 28, 2013

2 CURRENCY EQUIVALENTS (Exchange Rate Effective November 28, 2013) Currency Unit = Turkish Lira 1.00 = US$ 0.50 US$ 1.00 = 2.02 FISCAL YEAR ABBREVIATIONS AND ACRONYMS CAS DMs EA EMF FI FM GDP ICR IMM ISDS ISMEP LARP MSP M&E OP PAD PAPs PCU PDO PP RAP SPO WB Country Assistance Strategy District Municipalities Environmental Assessment Environmental Framework Financial Intermediary Financial Management Gross Domestic Product Implementation Completion Report Istanbul Metropolitan Municipality Integrated Safeguards Datasheet Istanbul Seismic Risk Mitigation and Emergency Preparedness Project Land Acquisition and Resettlement Policy Framework Municipal Services Project Monitoring and Evaluation Operational Policy Project Appraisal Document Project-affected Persons Project Coordination Unit Program Development Objectives Project Paper Resettlement Action Plan State Planning Organization World Bank Vice President: Laura Tuck Country Director: Martin Raiser Sector Manager: Sumila Gulyani Project Team Leader: Mara Warwick ICR Team Leader: Stephen Karam ii

3 TURKEY Istanbul Municipal Infrastructure Project CONTENTS Data Sheet A. Basic Information iv B. Key Dates iv C. Ratings Summary iv D. Sector and Theme Codes v E. Bank Staff v F. Results Framework Analysis v G. Ratings of Project Performance in ISRs vii H. Restructuring vii I. Disbursement Graph viii 1. Project Context, Development Objectives and Design Key Factors Affecting Implementation and Outcomes Assessment of Outcomes Assessment of Risk to Development Outcome Assessment of Bank and Borrower Performance Lessons Learned Comments on Issues Raised by Borrower/Implementing Agencies/Partners Annex 1. Project Costs and Financing Annex 2. Outputs by Component Annex 3. Economic and Financial Analysis Annex 4. Bank Lending and Implementation Support/Supervision Processes Annex 5. Beneficiary Survey Results Annex 6. Stakeholder Workshop Report and Results Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders Annex 9. List of Supporting Documents MAP 43 iii

4

5 A. Basic Information Country: Turkey Project Name: Istanbul Municipal Infrastructure Project Project ID: P L/C/TF Number(s): IBRD ICR Date: 05/08/2012 ICR Type: Core ICR Lending Instrument: SIL Borrower: Original Total Commitment: Revised Amount: USD 22.44M Environmental Category: FI Istanbul Metropolitan Municipality USD M Disbursed Amount: USD 22.44M Implementing Agencies: Istanbul Metropolitan Municipality Cofinanciers and Other External Partners: None B. Key Dates Process Date Process Original Date Revised / Actual Date(s) Concept Review: 04/03/2006 Effectiveness: 09/14/ /23/2009 Appraisal: 04/04/2007 Restructuring(s): 09/09/2009 Approval: 06/28/2007 Mid-term Review: 4/23/2011 Closing: 12/31/ /30/2013 C. Ratings Summary C.1 Performance Rating by ICR Outcomes: Risk to Development Outcome: Bank Performance: Borrower Performance: Highly Unsatisfactory High Unsatisfactory Unsatisfactory C.2 Detailed Ratings of Bank and Borrower Performance (by ICR) Bank Ratings Borrower Ratings Moderately Quality at Entry: Highly Unsatisfactory Government: Unsatisfactory Implementing Quality of Supervision: Unsatisfactory Unsatisfactory Agency/Agencies: Overall Bank Overall Borrower Unsatisfactory Unsatisfactory Performance: Performance: iv

6 C.3 Quality at Entry and Implementation Performance Indicators Implementation QAG Assessments Indicators Performance (if any) Potential Problem Project No at any time (Yes/No): Problem Project at any time (Yes/No): DO rating before Closing/Inactive status: Yes Unsatisfactory Quality at Entry (QEA): Quality of Supervision (QSA): None None Rating D. Sector and Theme Codes Original Actual Sector Code (as % of total Bank financing) General transportation sector 23 General water, sanitation and flood protection sector Housing construction 11 Solid waste management 30 Sub-national government administration 23 Theme Code (as % of total Bank financing) Natural disaster management Other urban development Pollution management and environmental health 20 E. Bank Staff Positions At ICR At Approval Vice President: Laura Tuck Shigeo Katsu Country Director: Martin Raiser Ulrich Zachau Sector Manager: Sumila Gulyani Sumter Lee Travers Project Team Leader: Mara K. Warwick Seema Manghee ICR Team Leader: Stephen Karam ICR Primary Author: Sonia Hammam F. Results Framework Analysis Project Development Objectives (from Project Appraisal Document) The objectives of the project are to assist the Istanbul Metropolitan Municipality in: (a) improving its solid waste management; and (b) improving its capacity to mitigate v

7 earthquakes by retrofitting key facilities and infrastructure and upgrading the institutions and their procedures to help them respond to emergencies. Revised Project Development Objectives (as approved by original approving authority) The objectives of the project are to contribute to: (i) the rehabilitation and cleanup of unauthorized waste disposal sites and creeks; and, (ii) the strengthening of the capacity of the Istanbul Metropolitan Municipality (IMM) to mitigate the impact of earthquakes by retrofitting infrastructure and providing training to respond to emergencies more effectively. (a) PDO Indicator(s) Indicator Indicator 1 : Value quantitative or Qualitative) Baseline Value Original Target Values (from approval documents) Formally Revised Target Values Actual Value Achieved at Completion or Target Years Percentage decrease in water pollution in the nearest body of water to the dumps and creeks rehabilitated. No baseline specified in No target specified Not reported by September 2009 in September 2009 Borrower. restructuring. restructuring. Date achieved 09/09/ /09/ /15/2011 Comments (incl. % No achievement on PDO indicators. achievement) Indicator 2 : The Istanbul Municipality is able to ensure safe and accessible infrastructure during and in the aftermath of an earthquake. Value No baseline specified in No target specified Not reported by quantitative or September 2009 in September 2009 Borrower. Qualitative) restructuring. restructuring. Date achieved 09/09/ /09/ /15/2011 Comments (incl. % PDO indicators not achieved. achievement) (b) Intermediate Outcome Indicator(s) Indicator Indicator 1 : Value (quantitative or Qualitative) Baseline Value Original Target Values (from approval documents) Formally Revised Target Values Actual Value Achieved at Completion or Target Years Rehabilitation and stabilization of creeks: Number and percent of creeks rehabilitated. No baseline specified No target specified. Creek rehabilitation started on nine of the 14 sections, and partially completed on six of the vi

8 sections for which contracts had been awarded by project closing. Date achieved 09/09/ /09/ /15/2011 Comments (incl. % achievement) Creek rehabilitation contracts were awarded for 14 creek sections. Rehabilitation works commenced on 9 sections and were partially completed on 6 creek sections. G. Ratings of Project Performance in ISRs No. Actual Date ISR DO IP Disbursements Archived (USD millions) 1 02/07/2008 Satisfactory Satisfactory /01/2009 Satisfactory Moderately Unsatisfactory /21/2009 Satisfactory Moderately Unsatisfactory /11/2010 Unsatisfactory Moderately Unsatisfactory /27/2010 Unsatisfactory Moderately Unsatisfactory /29/2011 Unsatisfactory Unsatisfactory H. Restructuring (if any) Restructuring Date(s) Board Approved PDO Change ISR Ratings at Restructuring DO IP Amount Disbursed at Restructuring in USD millions 09/09/2009 Y S MU 0.00 Reason for Restructuring & Key Changes Made Restructuring approved to: a) revise the PDO and project components; b) extend the closing date until June 30, 2013; and, c) revise the project results framework. If PDO and/or Key Outcome Targets were formally revised (approved by the original approving body) enter ratings below: Outcome Ratings Against Original PDO/Targets Highly Unsatisfactory Against Formally Revised PDO/Targets Highly Unsatisfactory Overall (weighted) rating Highly Unsatisfactory vii

9 I. Disbursement Profile Original ---- Formally Revised -- Actual 300 ~ c $ i... "' :::> N N N N N N N ~ <1 ~ <1 ~ <1 ~ <1 ~ <1 & <1 ~ <1 ~ N N '<t '<t "'.. "' "' "' N N N N N N N N N N N N N N N " viii

10

11 1. Project Context, Development Objectives and Design 1.1 Context at Appraisal 1. Background. In 2007 when the project was approved, Istanbul s population was estimated at 12.5 million. Istanbul is the largest city in Turkey and the country s main center of industrial, financial, service and other economic activities. Administratively, Istanbul is both a metropolitan municipality and a province, contributing 23% of Turkey s Gross Domestic Product (GDP) in An extremely rapid six-fold population increase over the past three decades - largely a result of the attraction that Istanbul s expanding labor market exerted on Turkey s internal migration - has taxed the capacity of the Istanbul Metropolitan Municipality (IMM) to provide services to its population. New and often illegal settlements and industrial plants expanded into environmentally fragile areas such as creek watercourses that should have been protected as natural resources. Inefficiencies in collection and safe disposal of solid waste, including industrial waste, have created potential public health hazards. Istanbul s problems are exacerbated by its location in one of the world's most active earthquake zones adjacent to the North Anatolian fault line. Strong earthquakes are a periodic occurrence and throughout recorded history have struck the city repeatedly, causing severe damage and loss of life. 3. Istanbul s future challenges are even more daunting with the city expected to double in size over the next 25 years and reach a population of million by the year Accommodating such growth, while maintaining and/or improving the living conditions of the city s inhabitants, requires strong coordination and control of urban development and public service delivery. 4. The governance structure in Istanbul is complex: as a province, Istanbul is administered by a Governor who is appointed as the representative of the national government. Responsibilities of the Governor include provision of nationally administered services such as education, health, and disaster management. As a municipality, governed by the Metropolitan Municipality Law of 2004, Istanbul is administered through a two-tier local government system that consists of IMM at the top level and 32 District Municipalities (DMs) at the lower level. The head of IMM is an elected mayor. IMM is responsible for management of all citywide municipal services and infrastructure. 5. The Metropolitan Municipality Law expanded the geographical area of IMM from 1,830 km 2 to 5,349 km 2, dramatically increasing the investment needs and service delivery challenges for IMM. The Law also required IMM to prepare both a Metropolitan Strategic Development Plan and an Environmental Plan to reflect the demands of the expanded area, identify the corresponding investment needs, and explore possible sources of financing. The Strategic and Environmental Plans were completed and approved by the Municipal Council of IMM in To address its multiple needs and prepare for future challenges, in 2006 IMM requested the World Bank to assist in 1

12 financing a first investment program under its strategic plans, focusing on environmental management and disaster risk reduction. 6. Rationale for Bank involvement. The project was included in the 2003 Country Assistance Strategy (CAS) for Turkey (Report No TU) which pursued four major objectives: (i) supporting sound macroeconomic management and governance; (ii) promoting equitable human and social development; (iii) creating a more attractive business climate; and (iv) strengthening environmental management, and disaster preparedness and mitigation capacity. 7. The project aimed to support these CAS objectives by focusing on: (i) critical environmental problems by upgrading solid waste disposal facilities and safe disposal of waste; and (ii) strengthening disaster mitigation by improving key infrastructure and infrastructure services whose continuing operation would be critical in the event of an earthquake. The project was intended to complement the Istanbul Seismic Risk Mitigation and Emergency Preparedness Project (ISMEP) approved in 2005, implemented by the Istanbul Special Provincial Directorate, which focused on strengthening Istanbul s disaster response capabilities, and reducing risk through seismic mitigation of public facilities. The project was also intended to work in parallel with the Municipal Services Project (MSP), approved in 2005 and implemented by Iller Bank, which supports the provision of infrastructure to medium and small municipalities in Turkey. It is worth noting that both of the other related municipal projects are progressing satisfactorily and have been extended with Additional Financing, and, in the case of ISMEP, with considerable co-financing from other IFIs. 1.2 Original Project Development Objectives (PDO) and Key Indicators 8. The objectives of the project at Board approval were to assist the Istanbul Metropolitan Municipality in: (a) improving its solid waste management; and (b) improving its capacity to mitigate earthquakes by retrofitting key facilities and infrastructure and upgrading the institutions and their procedures to help them respond to emergencies. 9. Project Outcome Indicators were: (a) reduced negative impact of solid waste collection and disposal operations on environment and population; and (b) reduced risk of breakdown of key municipal services during earthquakes. There were no baseline values or targets developed for these indicators at Board approval. 1.3 Revised PDO (as approved by original approving authority) and Key Indicators, and reasons/justification 10. For reasons explained in detail below, the project content presented to and approved by the Bank s Board of Directors in June 2007 had not been included in the 2

13 approved investment program for 2007 by the State Planning Organization (SPO) 1, the national authority responsible for domestic approval of internationally financed projects in Turkey. Given the mandatory requirement that SPO confirm externally-financed investments, the project could not proceed with implementation as appraised. After SPO provided its confirmation of components to be included in the project, a Level I restructuring was necessary to align the project components with SPO s approved allocations and components before implementation could begin. This Level I restructuring, approved by the Board on September 9, 2009, was used to: (a) revise the PDO and project components; (b) extend the closing date until June 30, 2013; and, (c) revise the project results framework. 11. The revised objectives of the project were to contribute to: (a) the rehabilitation and cleanup of unauthorized waste disposal sites and creeks; and (b) the strengthening of the capacity of the Istanbul Metropolitan Municipality (IMM) to mitigate the impact of earthquakes by retrofitting infrastructure and providing training to respond to emergencies more effectively. 12. The PDO indicators after restructuring were: (a) percentage decrease in water pollution in the nearest body of water to the dumps and creeks rehabilitated; and, (b) the ability of the Istanbul Municipality to ensure safe and accessible infrastructure during and in the aftermath of an earthquake measured by the number of road viaducts retrofitted according to Turkish seismic standards. However, no baseline values or targets were developed for these indicators. 1.4 Main Beneficiaries 13. The main beneficiaries of the project were intended to be the population of Istanbul Metropolitan Municipality, which was expected to benefit directly from improved environmental quality of creeks and watercourses, and from increased resilience of key municipal infrastructure to earthquake risks. Although unstated in the original project design or project restructuring of September 2009, the final project design, whose creek rehabilitation component included civil works for flood mitigation purposes, would have provided additional flood risk mitigation benefits to populations living along Istanbul s many creeks and watercourses. 1.5 Original Components 14. At Board approval, the project consisted of the following four components: Component A: Improvements in environmental management: closure of existing illegal landfills and rehabilitation of creeks; preparation of annual business plans that include operating performance, investment program and financial targets and results; and, financing waste collection equipment. 1 Under a Government-wide restructuring of ministries and public agencies in 2011, the State Planning Organization was renamed the Ministry of Development. 3

14 Component B: strengthening of municipal services and infrastructure: preparing a detailed risk assessment for all major municipal systems; preparing a Municipal Infrastructure Risk Mitigation Plan; retrofitting of municipal infrastructure (under-passes, pipelines, viaducts, etc.); and, providing emergency fire department equipment. Component C: Pilot urban transformation program: pilot urban transformation feasibility studies; and, retrofitting and construction of buildings, fire stations and emergency housing associated with urban transformation in the most seismically vulnerable areas. Component D: Project Management and audits: design studies, surveys and technical training for project implementation; and, external audits of project accounts. 1.6 Revised Components 15. At restructuring, revisions were made to the project components to align them with SPO s approved investment allocations. The components of the restructured project were as follows: Component A: Improvements in solid waste management and rehabilitation and cleanup of creeks: (a) closure and rehabilitation of existing unauthorized disposal sites for municipal solid waste (landfills) and rehabilitation of creeks through creek bed and canal cleaning, protection of stream banks to control erosion and loss of bank materials, and rehabilitation and replacement of existing rainwater and wastewater pipelines; (b) preparation of annual Business Plans for IMM that include operating performance, investment program and financial targets and results; and (c) financing waste collection equipment. Component B: Strengthening of municipal services and infrastructure: (a) preparing a detailed risk assessment for all major municipal systems; (b) preparing a Municipal Infrastructure Risk Mitigation Plan; (c) retrofitting of municipal infrastructure; and, (d) providing emergency fire department equipment. Component C: Pilot urban transformation program: (a) pilot urban transformation feasibility studies and preparation of microzonation studies. Component D: Project Management and audits: (a) design studies, surveys and technical training for project implementation; and, (b) external audits of project accounts. 16. The most significant changes were made in Component A, where funding for the creek rehabilitation subcomponent was expanded substantially to $161.4 million to give 4

15 more importance to the mitigation of flood-related hazard risks in Istanbul, while funding for activities related to the solid waste subcomponent was considerably reduced to only $4.1 million. The other major change was the elimination of the investment activities for retrofitting and construction of buildings and housing under Component C, which SPO determined should be funded separately by IMM and not included in the externally financed project. Most of the increased funding for the creek rehabilitation subcomponent came through the savings that resulted from the exclusion of these activities. The other two components were unchanged although funding for Component B was reduced in line with the SPO allocations. 1.7 Other significant changes 17. There was insufficient agreement with the Government s domestic approval authorities on the content of the project prior to Board approval. In contrast to the expected practice for investment lending in Turkey, the project content as described in the Board package had not been confirmed in SPO s approved Annual Investment Plan prior to Board presentation. However, the Bank still sought clearance of the negotiated documents in order to proceed with Board presentation, even though it was aware that SPO s confirmation of project components would not occur before January 2008 when its Annual Investment Plans are published. The Guarantor s clearance was conditional with a caveat that the signing of both the Loan and Guarantee agreements could not proceed without SPO s confirmation of the project components. 18. SPO s eventual confirmation of project investments in February 2008, introduced important modifications to the content and allocations of various project components, which had to be reflected in a subsequent project restructuring before implementation could begin. As previously indicated, there was a significant increase in allocations for the creek rehabilitation subcomponent of Component A. While this subcomponent for creek rehabilitation was included in the approved 2007 Board package, it had been added during in the context of negotiations, and its preparation and appraisal took place as part of the preparation of the restructured project. 19. After the SPO confirmation was in place, and internal procedures for clearance completed, the Loan Agreement was signed with IMM on July 25, However, the signing of the Guarantee Agreement was made a condition of loan effectiveness because the project could not be accommodated in the Government s sovereign guarantee envelope for Once the 2009 guaranty authority was available, the Guaranty Agreement was signed on January 13, 2009 and effectiveness was finally declared in February The project then had to undergo a Level 1 Restructuring in September 2009 to align it with the SPO-approved components and allocations, before implementation could begin. 20. Prior to the restructuring of September 2009, a subcomponent intended to purchase solid waste cleanup vessels and vessels for firefighting was dropped. While this component had the support of SPO, the Guarantor and IMM, the Bank deemed that it could not be included in the restructured project without triggering the International Waterways Policy (OP/BP 7.50). The Bank and the Government discussed this issue at 5

16 some length, and Bank management and regional safeguards staff sought options to resolve the issue both internally and with the Government. However, the Government objected to the Bank s interpretation that this policy should be triggered and riparians notified for a component that covered the purchase of sea vessels that would be used by IMM to clean up oil spills on the Bosphorus. 2. Key Factors Affecting Implementation and Outcomes 2.1 Project Preparation, Design and Quality at Entry 21. The project, as prepared, was intended to support investments based on Istanbul s strategic plan related to environmental management and disaster risk mitigation. Some flexibility was built in by design for selected physical subprojects, many of which were to be identified during implementation. This programmatic approach to design encompassing a broad range of municipal investments was appropriate for a large municipality with Istanbul s capacity and large investment program, and has been successfully applied in other contexts. It, however, proved ambitious for a first engagement in the absence of carefully defined implementation arrangements and procedures and clearly established criteria for prioritization of strategic investments, 2 including selection and preparation of a first year set of investments. Moreover, the flexibility afforded by a programmatic approach was limited in a context which entailed lengthy procedures to obtain prior confirmation of externally-financed activities. 22. The choice of a multi-sector approach was justified on the grounds that it would provide IMM with a broader capability to address environmental and disaster mitigation issues. However, given that this was IMM s first Bank project, and the Bank s first municipal project in Turkey, there was a learning curve for both IMM and the Bank. In the end, much of the implementation focused on ensuring procedural compliance with Bank rules and procedures rather than institutional strengthening in the management of IMM s strategic investment projects. 23. In analyzing project preparation, design and quality at entry, three features stand out which reflect the Bank s shortcomings in its assessment of risks, the adequacy of mitigation measures, and of project readiness: (a) consensus on project components appears to have been in flux for a considerable amount of time before and after Board approval; (b) the absence of a realistic appraisal by the Bank of IMM s capacity to manage implementation in compliance with Bank processes, including coordination of a diverse group of municipal departments, and (c) Safeguards instruments developed for management of land acquisition and resettlement were not sufficiently robust to guide implementation, nor were they adapted to actual project components. 2 A sector note was undertaken concurrently with project preparation that, according to the concept note, was intended to analyze the strategic plan investments, and establish priorities. However, much of the analysis in the note which was completed in June 2008, focused on the finances of the municipality and its associated enterprises, and did not address the original objective. 6

17 24. Lack of agreement on project components. The absence of SPO approval of project components prior to presentation of the Board package represented a substantial risk to both project design and implementation, which was not adequately recognized and addressed. In addition, project preparation and readiness for implementation were compromised by the lack of internal agreement on project components, which were still in a state of flux at the time of Board presentation, as evidenced by the late addition of the creek rehabilitation component during negotiations. The lack of agreement on project components ultimately led to design changes, which had to be subsequently reflected through a restructuring, further delaying the start of implementation. 25. The Bank was aware that SPO s confirmation of project components was a domestic mandatory requirement for all externally financed investments, and that project effectiveness and implementation would be delayed until the confirmation was in place. It was also aware of the complex relationships between central and municipal government, and that their lack of agreement still needed to be resolved. Under these circumstances, the more prudent course would have been to work out these outstanding issues as part of project design and preparation, in advance of Board presentation. In fact, the PAD flagged the absence of SPO confirmation of the project investments as a high risk for FM, and proposed that SPO confirmation be sought by Board date. This was not done due to lending pressures, despite the substantial FM risk rating even after mitigation. 26. Incomplete assessment of IMM s implementation capacity. The Bank and the Borrower agreed to embed the project within IMM with a light coordination function established within the office of the Deputy General Secretary responsible for Finance. The strategic choice of embedding project management within IMM was considered good practice, in contrast to establishing a project-specific implementation unit. Nonetheless, the project decision meeting acknowledged the inherent risk of this management model for project disbursement and procurement, given that this was IMM s first project with the Bank. To mitigate this risk, completion of an Operations Manual, acceptable to the Bank, was made a condition of Board presentation at the decision meeting. Additional mitigation measures identified in the PAD were: training of IMM staff in Bank procedures, field presence of the supervision team, and assistance from the ISMEP team, which had a well-established IPCU. 27. The mitigating measures proved insufficient in a number of respects. Most notably, the Operations Manual, provided a very summary description of the project responsibilities of IMM s departments, their staff and the project coordinator, contrary to what had been anticipated at the project decision meeting. While it covered procurement and financial management processes adequately, it did not identify specific areas requiring support and strengthening, leaving such issues to be identified at a later date. Nor did it describe implementation and coordination procedures, reporting requirements and implementation responsibilities for various components. In hindsight, many of the subsequent implementation problems resulted from this lack of clarity and specificity about roles and responsibilities, and the inadequate assessment by the Bank of IMM s capacity to incorporate Bank requirements in its internal processes. 7

18 28. While the original appraisal had focused on the solid waste component, the responsibilities, procedures and reporting requirements of different departments for its implementation are not described in the 2007 Operations Manual. Reportedly IMM updated the Operations Manual to reflect subsequent project changes. However, it is not clear from available project documentation that it was provided with adequate guidance to ensure that the institutional responsibilities and implementation procedures for the creek rehabilitation component were covered in sufficient detail, and roles and procedures clarified for the different implementing departments. 29. After Board approval, the Bank strengthened its field presence with the posting of the task manager in the field and some training sessions on project-related issues, such as safeguards, procurement and financial management to IMM. 3 However, the frequent changes in staff within IMM implementing departments meant that continuity and institutional knowledge was difficult to maintain. There was further loss of continuity with the changes in key Bank staff who had been engaged in project preparation but who did not remain during the implementation phase, including some who were never replaced. 30. Inadequacy of supporting social safeguards instruments. The project was classified as FI in November 2006 at the project concept stage, based on the understanding that the specific subprojects, which could cover the range of environmental classifications, would only be identified during implementation. In keeping with the FI classification, an Environmental Management Framework (EMF) and Land Acquisition and Resettlement Policy Framework (LARP) were prepared. At the time of restructuring, the appropriateness of the FI classification for a non-financial intermediary project was raised. However, the PP notes that the classification was retained for the sake of continuity as the EMF was already in place and IMM staff had been trained accordingly. 31. The problems that arose during implementation were not caused by the classification. Both the EMF and environmental safeguards were adequately treated in project preparation and restructuring. Instead, the problems centered on land acquisition and resettlement (OP4.12). In part, they reflected weaknesses in the original preparation of the LARP, which had been approved by the Bank in 2007, as it did not provide sufficient guidance for planning and preparing resettlement action plans (RAPs). More importantly, it was not strengthened or adapted to reflect the challenges of creek rehabilitation at restructuring, which was a critical oversight. 32. Implementation could have proceeded more smoothly, if, during project preparation and restructuring, social safeguards had received the same level of attention and guidance given to developing and testing instruments for environmental safeguards. This would have required greater emphasis on developing a LARP that covered potential situations, set out clear principles, criteria and procedural steps, and reached a consensus 3 Training in social safeguards was provided in November 2008, as part of an overall training session on safeguards, with the regional social safeguards coordinator making the presentation. Several training sessions on procurement and financial management are reported to have taken place. 8

19 on measures to bridge the gaps between Turkish law and Bank policy requirements. Instead, these instruments had to be developed during the course of implementation, or applied retroactively as described in more detail in Section The project documentation for both the original and restructured project indicated that the LARP had been prepared as a precautionary measure intended to provide flexibility in the event that subprojects were presented that might require public land to be cleared or private land to be acquired. Yet, despite having allowed for this flexibility, there was little effort to ensure that the instruments were robust enough to treat potential cases of resettlement should they arise. The general expectation was that resettlement would not be required, as activities would be undertaken on public land and within existing rights of way. This proved to be a serious oversight in the absence of specific criteria for the selection of creeks to be rehabilitated under the project. Moreover, given that flooding is a significant disaster risk in Istanbul, limiting creek rehabilitation activities to cleaning up existing systems for environmental purposes did not reflect IMM s interest in mitigating the risk of devastating floods and associated loss of life. 34. A further complicating factor was the extension of a clause in the 2007 Board approved Loan Agreement that had precluded resettlement under Component C pilot urban transformation to cover all components in the restructured project. This overall ban was inconsistent with the claim in both the original and restructured project that the LARP was intended to allow flexibility. Moreover, the notion that urban transformation could take place without resettlement was naïve at best. For this provision to be applied, it would unnecessarily restrict dealing with a large creek rehabilitation program where resettlement is, at times, unavoidable to ensure the safety of residents, and mitigate the severity of the flooding problems caused by encroachment. This was underscored in the 2008 feasibility study for the creek rehabilitation component, which identified encroachment on Istanbul s creeks as one of the major causes of flooding, and suggested that the design of an effective creek rehabilitation program might entail land acquisition and resettlement. 2.2 Implementation 35. The project was in unsatisfactory implementation status from January 2009 until its closure in July At that time, fourteen contracts had been signed under the creek rehabilitation component, with disbursements of US$ 22 million (7% of total project financing). The considerable procedural delays in the start of implementation, the changes in priorities and the lack of attention by the Bank and the Borrower in ensuring the adequacy of the project s systems and procedures and their consistency with evolving priorities and activities significantly affected project implementation and outcomes. 36. Implementation was essentially put on hold from Board approval in 2007 until the project was restructured in late During that period, project activities were effectively an extension of the preparation and design phase and its restructuring, including: resolving procedural issues, confirmation of project components, design and preparation of the creek rehabilitation component, including an EMF and EMPs, and 9

20 preparation of an initial set of procurement packages for the microzonation, fire-fighting equipment and creek components. 37. After the restructuring, the Bank engaged IMM on ways and means to move implementation forward. Progress was made on initiating works on the creek rehabilitation component, but was very slow on other components. It was intended that a second Level I restructuring would take place by the end of 2010 to address the implementation deficiencies, cancel activities that had been included in the September 2009 restructuring that IMM no longer intended to undertake, and to scale back the project to a more manageable size through partial cancellation of the IBRD loan. 38. A restructuring proposal was submitted by IMM in April However, the restructuring and mid-term review mission later that month revealed serious shortcomings in project implementation, particularly with respect to IMM s handling of land acquisition and resettlement under the creek rehabilitation component, which made it difficult to proceed with restructuring, and ultimately led to the decision to cancel the project. 39. The senior management of IMM played a very active role in communicating with the Bank and assessing project implementation during the period from March to June IMM management spent considerable time and effort in evaluating alternative implementation arrangements for the project. Finally, they concluded that due to internal limitations and the differences between local regulations and World Bank policies, the implementation problems could not be easily overcome, nor could implementation arrangements be quickly revised. Therefore, in close consultation with the Bank and the Guarantor, and in recognition of the risks faced by all three parties of continuing with a non-performing project, IMM requested cancellation of the remaining loan funds and closure of the project. 40. As a result of IMM s request, which was supported by the Bank and the Guarantor, implementation was stopped on July 13, 2011 and all remaining loan funds were cancelled, resulting in a total disbursement of US$ million of the original US$ million over the life of the project. Aside from the creek rehabilitation component, the two other activities (microzonation and fire safety) under implementation at the time of cancellation, were not subject to the same implementation issues and had been expected to be completed. However, upon cancellation of the entire project, these activities were also stopped. 41. Factors affecting Implementation 42. Shortly after the 2009 restructuring, the Bank s Quality Assurance Group (QAG) undertook a disbursement learning review of the project, which identified major issues affecting project implementation. It took note of the lack of project readiness at the time of approval, the effectiveness delay caused by the delay in providing guarantee authority, and the lengthy process for achieving internal consensus on project design changes, which were ultimately reflected in restructuring. 10

21 43. The review identified the following factors on the part of the government: (i) the difficulties in obtaining timely clearances and approvals for both the loan guarantee and components to be included in the project; and (ii) Istanbul s relatively strong financial position which allowed it to finance activities with its own funds when it deemed Bank policies/requirements to be either too burdensome or too slow. The issues identified on the part of the Bank were: (i) the decision to opt for a first order restructuring, (ii) stringent interpretation of the application of OP7.50 requirements for notifying riparians before Istanbul could purchase sea vessels to clean up the Bosphorous; and (iii) inadequate procurement planning, which led to delays in reviews and approvals. The review s conclusion that the changes in design appeared to require a simple reallocation among components overlooks the fact that the creek rehabilitation component had not been defined and appraised at the time of Board approval. 44. The key issues that are indicative of, and contributed to implementation difficulties reflect many of the weaknesses in project preparation that were identified earlier. They include: (a) the long lag time between Board approval and effectiveness, (which has been discussed previously); (b) the incomplete restructuring and revision of instruments; (c) changing priorities during implementation; (d) IMM s inability to incorporate necessary systems for successful implementation; and (e) inadequacies in project management and coordination. 45. Incomplete Restructuring and Revision of Instruments. The restructuring was justified in the Project Paper (PP as being necessary to align the project components with the evolving priorities of the IMM within the framework of the national investment budget approved by the Turkish State Planning Organization. The creek rehabilitation sub-component, took on greater significance in its own right, as an important measure to mitigate the risks of flooding, and accounted for half of total project financing. The PP indicated that the main rationale for the increased importance of activities under this component was IMM s request to expand funding for creek rehabilitation due to the urgent need to mitigate risks against flooding. Yet, the revised objectives and indicators did not reflect this rationale. Instead, the objectives focused on the environmental aspects of cleaning up creeks. Similarly, the indicators made no reference to mitigation of flood risks, but were measured by the decline in pollutants. 46. The restructuring PP defined the activities to be financed under the creek rehabilitation subcomponent as cleaning creek bed and canals, protection of stream banks and rehabilitation and replacement of existing rainwater and wastewater pipelines. The very large addition of resources for these activities warranted review and modification of the appraisal analysis, and a separate analysis of its benefits and risks, since it had not been an integral part of the original appraisal. However, the PPP effectively treated the restructuring as though it was a matter of reallocation of resources from one component (pilot urban transformation) to another (creek rehabilitation). 47. Implementation was adversely affected by the failure to fully analyze the additional risks and benefits that this subcomponent might entail, or to establish criteria for the selection of creeks to be rehabilitated. The general assumption appears to have been that the significant expansion of the creek rehabilitation activities would not affect 11

22 the institutional arrangements and associated implementation processes, or the identified risks and benefits of the project as appraised. As a result project implementation processes and tools, such as the Operations Manual and LARP, were not adapted to reflect the requirements of the largest component of the restructured project. 48. Changing Priorities During Implementation. While the restructuring allowed the creek rehabilitation component to move forward, progress on implementation of other components was quite slow as a result of lengthy procurement processes, and was affected by changes in IMM priorities. The degree to which these changes were influenced by the significant lag in the start of implementation, and the heavy emphasis on procedural compliance, is difficult to ascertain based on existing documentation. However, at least in the case of the solid waste component, for which preparation of consultant procurement packages was started in late 2009, IMM later made it clear that it had found other means of dealing with the issue of unauthorized dumps, and would not need to use Bank financing for this component. 49. In October 2010, IMM reported in a letter to the Bank that it no longer intended to carry out many of the activities listed in the September 2009 Project Paper, including the rehabilitation of illegal waste dumps and most of the technical assistance. Its stated priorities were: (i) the rehabilitation of creeks for flood control purposes, under Component A, (ii) providing emergency vehicles to the fire department, and limiting seismic strengthening of city bridges and viaducts, under component B and (iii) microzonation studies under Component C. In short, within a year from the start of implementation, IMM decided to largely limit project components to the activities that were already underway. The changes in priorities implied that a second first order restructuring would be necessary to align objectives and components with the actual project activities and priorities of IMM, and reduce the size of the loan. 50. Inability to Develop Necessary Systems for Successful Implementation. A critical deficiency was related to IMM s implementation of safeguards policies, in particular OP4.12. No system was developed for IMM to plan, prepare, implement and report on land acquisition and resettlement under the project. As Section below describes in detail, it was not possible to remedy this deficiency before project closure. Similarly, project monitoring and reporting systems were not sufficiently developed prior to the start of implementation, and remained inadequate throughout the implementation period, with only one progress report produced by IMM. 51. Weaknesses in Project Management and coordination capacity. Implementation was adversely affected by weaknesses in the project management structure, which was characterized by: Insufficient authority of the project coordinator to coordinate the actions of diverse implementing departments and ensure compliance with project requirements; Insufficient capacity to carry out the project functions in line with Bank implementation requirements; and Inadequacy of overall project monitoring and reporting. 12

23 52. Despite IMM s appointment of a full time coordinator in July 2010, coordination authority to ensure compliance by the staff in implementing departments remained weak. Staffing of key implementation functions was subject to frequent changes in some instances, or was insufficient in others. At the same time, the inadequacy of the reporting and monitoring systems and ambiguity regarding associated roles and responsibilities made the task of coordination and ensuring compliance even more difficult. The project implementation management issues finally came to a head at the time of the midterm/restructuring mission in late April At that point, the continued lack of progress in resolving safeguards compliance and other implementation issues led the Bank to conclude that the decentralized implementation arrangements were unworkable and needed to be replaced with a designated unit with qualified staff. 2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization 53. The design of project monitoring during project preparation was inadequate as the results framework in the PAD provided few baselines and targets and the indicators were not measurable. During the September 2009 restructuring, the indicators were improved significantly, although the two PDO indicators were still vague and the indicators for the first objective did not reflect the importance of creek rehabilitation as a flood control measure. In the absence of significant data collection, indicators could not be measured, and no baselines and targets were developed for the restructured project. 2.4 Safeguard and Fiduciary Compliance Safeguards Compliance / Social: 54. A central issue that led to IMM s decision to cancel the project in July 2011 was non-compliance with the World Bank social safeguard policy on Involuntary Resettlement (OP4.12) as it related to land acquisition and resettlement under the creek rehabilitation component. Due diligence on land acquisition and resettlement aspects was recorded in the initial 2007 (Board approval version) ISDS and elsewhere in the project files: The project is expected to take place on public land or within existing rights of way and it is not expected that any project activities will entail any land acquisition, relocation of population, or result in restricting the access of individuals or communities to economic resources. However, as a precautionary measure to enable a quick response in case the final design of any activities should unexpectedly call for the expropriation of private land or relocation of people or businesses, the IMM has prepared a Resettlement Policy Framework satisfactory to the Bank that will ensure compliance with OP 4.12, and hence the safeguard is triggered as a precautionary measure. 55. During the 2009 restructuring process, the ISDS was revised and re-dated. The same policies were triggered: OP 4.01, Environmental Assessment; OP4.11, Cultural Property, and OP 4.12, Involuntary Resettlement. The section on OP 4.12 was unchanged from the above-cited text, indicating that land acquisition and resettlement impacts were still seen as likely to be quite minor. Accordingly, the LARP accepted Turkish 13

24 legislation on expropriation and treatment of informal settlers, while also requiring that IMM prepare and submit land acquisition plans for Bank approval, and ensure public consultation. 56. While the supervision missions in late 2009 until March 2010 also did not foresee major resettlement requirements, the team was conscious from the start of the potential risks and provided guidance to help IMM establish adequate planning, monitoring and reporting on resettlement and land acquisition. Initially, the primary concern of supervision missions, starting in late 2009, was to ensure adequate documentation and reporting by IMM on land acquisition as required by the LARP. The reporting problems were attributed to: a) the lack of adequate guidance in the LARP as to IMM s planning, monitoring and reporting obligations, and b) the weak inter-departmental collaboration and communications on expropriation matters. 57. Over the course of implementation, it became clear that the effective rehabilitation of creeks for the purposes of flood control was likely to entail more significant requirements for land acquisition and resettlement than had originally been anticipated in the social safeguards due diligence documentation. In addition to their vulnerability to being used as wild dumpsites, Istanbul s creeks are crucial for protecting the city from flooding by providing storm water drainage along their natural contours. In light of the frequency of severe flood events, it is understandable and even desirable that IMM sought to augment the capacity of the creeks. In fact, the reports on creek rehabilitation, submitted by IMM to the Bank, as part of the preparation of the restructured project, specifically stated that due to the damage and associated loss of life caused by frequent flooding, IMM intended to expand the capacity of those creeks that it deemed risky. This should have alerted the project restructuring team of the need to review the consequences of such works for land acquisition and potentially resettlement, and the adequacy of the existing LARP in addressing these requirements. 58. In view of the emerging significance of land acquisition and resettlement during implementation, it became clear to the supervision team that the LARP that had been established would need to be revised and considerably strengthened to provide policycompliant resettlement plans and actions. The Bank worked intensively with IMM to develop adequate systems for managing resettlement and land acquisition issues. The intention was to establish acceptable policy- compliant procedures, (including a complete revision and strengthening of the LARP, and RAPs), and have the system in place prior to the proposed second restructuring, at which time the clause banning resettlement could be lifted. However, the difficulties of correcting existing deficiencies in social safeguards systems, and applying ex post remedial actions soon became evident, as the cases of Beykoz and Kurbagalidere creeks, described below, illustrate. 59. To develop more robust systems for handling and reporting on resettlement and land acquisition issues, a consultant was hired by IMM in October 2010 to undertake a social assessment of Beykoz Creek, where rehabilitation of the lower creek sections had already been completed by IMM, and World Bank funding was sought to complete the upper section. It was known that resettlement had already taken place at the site, and that more resettlement would be needed in the future. It was expected that the social 14

25 assessment would lead to a final, Bank-compliant report that would facilitate immediate progress on Beykoz Creek and serve as a prototype report for future creek rehabilitation. 60. The report produced in November 2010 revealed that, on the positive side, IMM had taken solid steps to minimize land-related and resettlement impacts, and that land acquisition processes were generally applied in a fair manner and consistent with domestic policy requirements. However, it also indicated that the actions taken in Beykoz with respect to some of the 12 households that had been relocated some time before the signing of the contracts, did not comply with OP4.12 due to gaps between domestic and Bank requirements, or special circumstances surrounding individual cases. 4 While the report could not be considered a full RAP and did not provide specific recommendations on remedial actions, the Bank requested that IMM indicate whether it would, in principle, be willing and able to provide remedial assistance to affected households. 61. In late March 2011, IMM responded in writing, indicating that the actions it had already taken at Beykoz were in line with Turkish laws and regulations and that such legislation did not allow retroactive remedial actions once legal processes were completed. It, however, indicated that it would take on board the issues raised by the report in future rehabilitation activities to ensure compliance with OP4.12. The noncompliance with the World Bank resettlement policy and the legal agreement made it impossible for the Bank to provide a no-objection to the bid evaluation report for civil works at Beykoz Creek. 62. During the mid-term-restructuring mission in late April 2011, visits were made to all creeks that had either been proposed by IMM or were already under implementation. Key features of each creek, including land acquisition and access aspects, were assessed by order of difficulty with respect to resettlement impacts. At that time, the mission observed that IMM had made significant design changes at Kadikoy Kurbagalidere Creek E-5 section after the signing of the creek rehabilitation contract, without obtaining a noobjection from the Bank. These changes had resulted in cases of physical resettlement, without aid of a RAP, and in spite of the Loan Agreement s preclusion of such resettlement. 63. Beyond, the issues at this site, the mission also found additional problems related to implementation of resettlement, which rendered restructuring very difficult: (1) Bidding on two creek rehabilitation contracts had started without site-specific drawings and without the World Bank s review and clearances for EMPs and RAPs; and (2) Reports provided to the Bank on resettlement and expropriation were often inconsistent, 4 The Beykoz contract was signed in 2010 and the inclusion of this creek in the project was finalized at the time of restructuring in While the 2010 consultant report does not indicate the actual date that houses were demolished, and households relocated, it makes reference to the 2006 floods as the main cause of the expropriation under emergency measures, and resettlement of the 12 households who had already had their houses demolished. It also indicates that these households had spent about two years as tenants until they could rebuild or relocate to more permanent housing in the same area. 15

26 and did not accurately reflect reality on the ground, particularly with regard to the presence of informal structures which were not taken into account. The overall deficiencies in reporting resettlement and the weaknesses in the procurement practices and implementation arrangements led the Bank to request that IMM take actions beyond remedying the specific violations that had been observed at Kurbagalidere Creek. 64. In a letter to IMM, Bank Management on April 27, 2011, requested that IMM : a) confer the creek rehabilitation component to experienced personnel or entities; b) suspend civil works on all contracts where resettlement had occurred, or was expected to occur, until a full review had been completed; c) suspend bidding and contract signing on creek rehabilitation until completion of remedial actions on all creeks; and d) ensure that no further land acquisition and resettlement take place until the project is restructured and the Loan Agreement amended to allow for resettlement. 65. In addition, to remedy the deficiencies in the instruments and institutional arrangements for social safeguards, IMM was asked to: Establish a project coordination unit through assignment of full time qualified personnel for key project management functions, such as procurement and safeguards; Revise the LARP to produce a resettlement policy-compliant framework that includes provisions related to all project-affected persons, (PAPs), social surveys of and consultation with PAPs, and for the preparation of RAPs where surveys indicate that resettlement may be required; Carry out RAPs as a routine part of subproject planning, and prior to the bidding of contracts; and Hire a social expert to carry out a full social survey of all creek sections to provide a full and complete assessment of current status. 66. Discussions continued between IMM and Bank management throughout May and June 2011, with IMM responding positively indicating its willingness to address most of these issues. It did, in fact, report that it had suspended construction on the Kurbagalidere contract. It also suspended bidding and contract signing, and confirmed that no future resettlement would take place. However, as the pending issues with respect to revisions in implementation arrangements and instruments could not be satisfactorily resolved in a reasonably short time frame, and in light of the residual risks to the Borrower, Guarantor and the Bank, the project, as previously noted, was cancelled in July 2011, at IMM s request Safeguard Compliance / Environmental: 67. Compliance with environmental safeguards was generally satisfactory. Safeguards issues were adequately addressed during the original project preparation in An environmental assessment framework was prepared in January 2007 by IMM. In addition, a general environmental assessment report and Environmental Management 16

27 Plan (EMP) was prepared and disclosed in February 2007, reflecting the solid waste subcomponent that was originally the principal activity under Component A. 68. During the restructuring in September 2009, the ISDS was revised to include provisions for the creek rehabilitation. The safeguard policies triggered remained the same, and again a general EMP was prepared for the creek rehabilitation component. Sub-project specific EMPs were prepared, and were included in the bidding documents and shared with the contractors. While there was general compliance with the site specific EMPs, the mid-term review mission found that there were problems with the mitigation measures and Bank reporting requirements related to physical and cultural property on three sites. These issues were brought to the attention of IMM, in the April 27, 2011 management letter, and IMM was asked to update the EMPs of the three affected creek contracts to reflect the authorizations received and actions needed in and around the cultural property. Authorization was obtained or sought on two of the sites, but the EMPs were not updated at the time of project closure. However, there was no adverse impact since construction did not start at any of the sites by project closure Fiduciary Compliance: 69. IMM s procurement performance remained weak until the cancellation of the project. Accordingly, the procurement risk rating prior to project cancellation was substantial. 70. The management and implementation of procurement, was hampered by the fragmented implementation arrangements, the lack of central coordinating and control mechanisms, understaffing of the procurement function and frequent changes in personnel. As a result, procurement planning and contract management were weak on the creek rehabilitation component, with delays in contract execution, and significant design changes, which were not reported to the Bank for a no-objection. 71. In general, procurement under the microzonation and fire safety components was less problematic in terms of the process, but proceeded quite slowly without reaching the contract award stage before closure. The preparation of both packages was quite lengthy, having started even before the restructuring, with significant back and forth between the Bank and the IMM. While the procurement of the microzonation package was finally bid in 2011, contract award was cancelled due to project closure. Preparation of the fire equipment package was ultimately completed, but the procurement process was not started due to the project closure. 72. In contrast, IMM took steps to enhance the financial management procedures relating to the project once the project was declared effective. It integrated the project accounting into its main financial management system and generated the Interim Unaudited Financial Reports automatically from the system. 73. The marginally unsatisfactory rating for financial management at the time the project was cancelled was due to weaknesses that had been identified in the last FM supervision, for which actions were pending, and had not been reviewed by the Bank prior to closing. 17

28 2.5 Post Completion Operation/Next Phase 74. Not applicable as the assets intended to be financed under the project have not been completed. 3. Assessment of Outcomes 3.1 Relevance of Objectives, Design and Implementation 75. The relevance of the PDO as defined in the PAD remains high. Improving environmental management and reducing vulnerability to disasters was and still is a high priority for Istanbul Metropolitan Municipality. The PDO fit well with the Bank s strategy in Turkey at the time, and complemented other ongoing Bank-financed projects in Istanbul and other municipalities in Turkey. 76. The relevance of the project design was weak insofar as the relative priority of various components and their alignment with stated objectives changed over the course of project preparation, restructuring and implementation. Moreover, implementation arrangements and procedures proved to be inadequate to the task of ensuring effective implementation in line with Bank procedural requirements and achievement of PDOs. 3.2 Achievement of Project Development Objectives 77. The project did not make any progress towards achieving its development objectives, given the limited implementation of planned activities. 3.3 Efficiency Not Applicable. 3.4 Justification of Overall Outcome Rating Rating: Highly Unsatisfactory 78. Although the project was relevant at appraisal and remains relevant in terms of Istanbul s priorities for infrastructure development and disaster risk reduction, its outcome is rated as highly unsatisfactory given its failure to achieve all of its intended PDOs. 3.5 Overarching Themes, Other Outcomes and Impacts (a) Poverty Impacts, Gender Aspects, and Social Development 79. Not Applicable. (b) Institutional Change/Strengthening 80. Not applicable, since none of the institutional strengthening activities and studies, which were intended to improve IMM s capacity to plan for urban environmental management and disaster risk reduction were carried out. 18

29 (c) Other Unintended Outcomes and Impacts (positive or negative) 81. Not applicable. 3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops 82. Not applicable 4. Assessment of Risk to Development Outcome Rating: High 83. The risk to development outcome is rated High, as most key activities under the project were not implemented. 5. Assessment of Bank and Borrower Performance 5.1 Bank Performance a. Bank Performance in Ensuring Quality at Entry Rating: Highly Unsatisfactory 84. Bank inputs and processes during project preparation were inadequate. Adjustments to the project appraisal were not made as project components changed to ensure readiness of the project, prior to Board submission. Project preparation did not consider major details for effective implementation by ensuring that there was a wellstructured Operations Manual that created a framework for successful implementation of the Project with clearly spelled out coordination, reporting and monitoring responsibilities and functions. The Bank also did not adequately assess the Borrower s capacity to comply with the Bank s safeguards and fiduciary procedures and identify relevant technical assistance to strengthen these functions, beyond training sessions. 85. During project preparation the issue of land acquisition and resettlement was not addressed satisfactorily, nor was this deficiency addressed at the time of restructuring when the creek rehabilitation component was better defined. While the project documentation allowed some flexibility to respond to situations where resettlement might be necessary, the legal agreement on the restructured project banned resettlement. Instead of addressing the land acquisition and resettlement requirements of the creek rehabilitation program, the assumption seems to have been that the project would not require resettlement, or could exclude works on creeks where resettlement might be necessary. These deficiencies should have been better addressed by the project team, but were also overlooked by the sector and country management units that could have proposed corrective actions and other means of addressing these important gaps. 19

30 (b) Quality of Supervision Rating: Unsatisfactory 86. During the period between Board approval and restructuring, the supervision activities were essentially a continuation of the preparation phase. The field-based team worked to resolve procedural issues of clearances, as well as reach agreement on project components, the restructuring of the project, and preparation of the creek component, including an initial procurement package, so it could be initiated shortly after restructuring. The Bank also provided guidance on IMM s preparation of procurement packages for both the microzonation and fire-fighting equipment during this period. 87. Many of the weaknesses that affected the original preparation were carried through the restructuring. Specifically, these included a weak focus on implementation processes, reporting requirements, roles and responsibilities for different components, and the inadequacy and ambiguity with respect to social safeguards instruments. While there was continuity in the staffing of the environmental function throughout the period, social safeguards did not receive adequate attention beyond a training session in November Nor was there adequate staffing of the social safeguards function to review the implications of the creek rehabilitation component at the time of restructuring, despite requests for assignment of staff. 88. The Bank s supervision activity during this period was not recorded in formal detailed reporting by the field-based team in the form of aide memoires or management letters. Moreover, only a limited number of Back to Office reports were issued during this period to record findings of missions. The lack of a formal written record of communications on critical issues and understandings, as emphasized by IMM management, affected the level of attention given to project implementation issues and required actions. It also impacted the transition to a new team that took on supervision when project implementation started shortly after the restructuring in late Surprisingly, there was no supervision handover mission on what was a complex project that had already experienced significant procedural delays, and a restructuring. 89. After the restructuring, (i.e., when actual implementation started), supervision reporting was significantly intensified in late 2009 by the Bank s new team. More formal and frequent short missions were undertaken, with five aide memoires and management letters issued, and timely responses from IMM. Notably, safeguards supervision was strengthened and included three social safeguard specialists (including the Lead Social Specialist in the ECA Regional Safeguards compliance unit who participated in 3 missions in 2010). An intensive mid-term/project restructuring mission was undertaken that made significant recommendations for remedying project deficiencies. However, as evidenced by the final outcome, even such intensified supervision, could not ensure successful implementation. 20

31 (c) Justification of Rating for Overall Bank Performance Rating: Unsatisfactory. The overall unsatisfactory rating is based on the highly unsatisfactory performance at entry, unsatisfactory performance during supervision, and the final project outcome. 5.2 Borrower Performance (a) Government Performance Rating: Moderately Unsatisfactory 90. The Government s performance under the project is rated as moderately unsatisfactory. During preparation, the domestic project preparation and approval process was not handled efficiently, particularly the delay in issuing the sovereign guarantee 19 months after Board approval, which substantially delayed project effectiveness. The rating of moderately unsatisfactory, however, reflects the Government s positive contribution at the final stages of the project to facilitate project closure. (b) Implementing Agency or Agencies Performance Rating: Unsatisfactory 91. IMM s performance under the Project is rated unsatisfactory. Despite substantial efforts made during the preparation phase and the diligence of IMM staff in trying to address problems that arose on the creek rehabilitation sub-projects, these were not sufficient to overcome earlier weaknesses in project implementation, particularly regarding adherence to some procurement and safeguard procedures. Given IMM s unfamiliarity with World Bank financing procedures and guidelines, it is understandable that it did not fully appreciate the challenges of managing the project through its internal departments, while incorporating Bank requirements and meeting its obligations under the Project. 92. During the period after Board approval through restructuring, IMM was engaged in preparation of the creek rehabilitation component, maintaining a steady dialogue with the Bank on the restructuring documentation and preparation of the initial procurement documents. However, during implementation, IMM was not able to satisfactorily address deficiencies in project coordination, procurement, safeguards compliance, and progress reporting. To its credit, its management took on a proactive and collaborative approach to resolve the issues raised in the mid-term restructuring mission, and when it became clear that the implementation deficiencies could not be resolved, it sought cancellation of the project. (c) Justification of Rating for Overall Borrower Performance Rating: Unsatisfactory 93. The overall rating of Borrower performance as Unsatisfactory is based on a combined assessment of the Moderately Unsatisfactory Government performance, 21

32 Unsatisfactory Implementing Agency performance, and the Highly Unsatisfactory project outcome. 6. Lessons Learned 94. Early closure of project. The proactive and consultative approach taken by the Borrower, the Guarantor and the Bank in closing the project when their joint assessment showed that the problems hindering implementation could not be easily resolved is a positive lesson from this project. This proactive approach allowed all parties to manage risk and minimize the cost of an unsuccessful project. 95. Resettlement as part of urban development. The project s assumption that effective creek rehabilitation and flood control works could be undertaken without the need for land acquisition and/or resettlement was flawed. In projects of this type, the need for land acquisition and resettlement is often necessary to ensure safe development and provide social benefits. Treatment of OP4.12 should be integrated into project design, such that social impact can be proactively understood, minimized, and mitigated ex ante. 96. Moreover in a country, such as Turkey, where there is a highly developed set of rules for social protection, the emphasis should be on consistency of outcomes, and agreement upfront on specific measures to bridge the gap between local requirements and Bank policy and procedures. In this respect, the recent report by the ECA Operational Services and Quality department, which compares Turkey s policies with those of the World Bank is an important contribution. It provides a good guide for how differences could be addressed in future projects. The report tackles the question of which procedural differences are really significant, making it important to ensure full adherence to WB requirements, and when it is desirable to exercise some flexibility as long as the outcomes are acceptable and consistent with WB policies. This focus on outcomes rather than a rigid imposition of procedures for compliance requires an understanding on the part of Bank teams of local practices and results, and of the legislative constraints facing the client. 97. Ownership for project preparation and implementation. It was clear that the Borrower wanted to engage with the Bank, but together they were not able to find the best way to do so. IMM continued to demonstrate its interest in engaging with the Bank, with its move to sign the Loan Agreement once it had obtained SPO approval. However, given what was known about the level of preparation, and the lack of ownership of the original project components at the central level, it would have been prudent for Bank management to have taken a more conservative approach with respect to the Board approval timeline, and not present the project to the Board until it was fully ready. At restructuring, there was a chance to adjust the project to more fully reflect the priority of the creek rehabilitation program for flood control purposes, which appears to have had full ownership by the Borrower. 98. Quality control during restructuring. The outcome of this project indicates that in the case of a major reallocation of resources or significant changes in the priority of 22

33 components through restructuring, a greater use of the Bank s internal quality control mechanisms, such as a full decision-meeting, and peer reviews would likely improve the outcome of the restructuring. 99. Implementation Capacity Assessment. While the decentralized management of the project proved to be problematic in this instance, it is not evident that a dedicated stand-alone PIU structure would have necessarily produced a more satisfactory outcome. Resolution of many of the issues that arose during implementation required engagement of IMM departmental staff and decisions by the IMM management. While a PIU management structure might have simplified the process of Bank supervision, its effectiveness in achieving PDO s and ensuring smooth implementation would still have required adequate processes and authority for the PIU to interface and coordinate with various implementing departments and entities To manage the risks of a decentralized management model, more rigor is needed in the assessment of implementation capacity, even when the implementing agency responsible for a project is generally perceived to be of high capacity. Istanbul s ability to undertake a large infrastructure program was not at issue. However, its ability to incorporate Bank processes and comply with the project-related requirements was untested. A sound understanding of the implementing agency s own procedures and practices is required to determine how project-specific requirements will be incorporated into the agency s regular work flow. Any gaps and/or procedural differences should be carefully analyzed and agreements on how these gaps would be bridged should be put in place at appraisal through the Operations Manual and project documentation. Where such an assessment identifies gaps in capacity to carry out project implementation functions, organizational strengthening should be provided in a timely and targeted manner Flexible project design. Projects that support a large number of different investments, not all of which may be fully identified before appraisal, require careful project design. Successful projects of this type take significant care before appraisal to clarify the project components, and establish, through the project s legal agreements, specific and rigorous eligibility criteria for investments under each component. Most importantly, they identify the first year s investments, which are fully prepared through feasibility study, EA and RAP stage prior to project appraisal. Alternatively, if such projects are intended to provide flexibility in support of a priority investment program, the overall program along with criteria for selection of investments, capacity for implementation and internal implementation procedures are appraised and projectspecific adjustments to internal processes are identified, and agreed to. In both instances procedures and requirements for the project are established, appraised and agreed prior to Board approval of the project. 7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners (a) Borrower/implementing agencies Comments of the Guarantor, Borrower and Implementing Agency reflect the findings of the ICR with regard to: (i) the ambitious timetable for project preparation that didn t 23

34 allow sufficient time for preparing and appraising several elements of the project and ensuring full ownership by project stakeholders; (ii) the inadequacy of the project at design stage in taking full cognizance of the likely need for resettlement and land acquisition and associated safeguard measures; (iii) a breakdown in communications during implementation due to a weak documentary record of understandings reached during missions as typically reflected in mission Aide Memoires; and (iv) a lack of familiarity on the part of the Bank of the Government of Turkey s procedures for committing external financing. (b) Cofinanciers Not applicable. (c) Other partners and stakeholders Not applicable. 24

35 Annex 1. Project Costs and Financing (a) Project Cost by Component (in USD Million equivalent) Components Appraisal Estimate (USD millions) Actual/Latest Estimate (USD millions) Percentage of Appraisal Contingencies Total Baseline Cost % N/A 0.00 Total Project Costs % Front-end fee IBRD Total Financing Required % (b) Financing Source of Funds Type of Cofinancing Appraisal Estimate (USD millions) Actual/Late st Estimate Percentage (USD of Appraisal millions) Borrower % International Bank for Reconstruction and Development % 25

36 Annex 2. Outputs by Component Project component as per September 2009 Implementation status and outputs at time of Restructuring Paper project closure in July 2011 Component 1. Improvements in Solid Waste Management and Rehabilitation and Cleanup of Creeks (Cost $165.5 million) a. Closure and rehabilitation of existing Closure and rehabilitation of municipal solid unauthorized disposal sites for municipal solid waste landfills did not commence. waste (landfills) and rehabilitation of creeks as well as replacement existing rainwater and Creek rehabilitation contracts signed on 14 wastewater pipelines; sections; works commenced on 9 creek sections, which were partially financed as per table below. None of the contracts were b. Preparation of annual Business Plans for IMM that include operating performance, investment program and financial targets and results; finalized prior to project closure. Did not commence. c. Financing waste collection equipment. Did not commence. Component 2. Strengthening of Municipal Services and Infrastructure (Cost: $98.5M) a. Preparing a detailed risk assessment for all Did not commence. major municipal systems; b. Preparing a Municipal Infrastructure Risk Did not commence. Mitigation Plan; c. Retrofitting of municipal infrastructure Did not commence. (under-passes, viaducts, etc.); d. Providing emergency fire department Procurement preparation completed but equipment. procurement process not started. Component 3. Pilot Urban Transformation Program (Cost $40M; Loan:$40M) Preparation of pilot urban transformation Pilot urban transformation feasibility study not feasibility studies and preparation of commenced. microzonation studies. These are necessary in Microzonation study procurement started, but the analysis of seismic risk and the contract award cancelled due to project closure. development of land use plans. Component 4. Project Management and Audit (Cost: $14.15M) a. Design studies, surveys and technical Did not commence. training for project implementation; b. External audits of project accounts. Did not commence. 26

37 Contracts awarded under project prior to cancellation (all within Component A - Creek Rehabilitation) including physical progress achieved on each contract and total disbursements made prior to project cancellation Description of Works Çekmeköy Kemerderesi Rehabilitation Project 1st Stage Küçükçekmece Nakkaşderesi Rehabilitation Project 1st Stage Çekmeköy Kemerderesi Rehabilitation Project 2nd Stage Küçükçekmece Nakkaşderesi Rehabilitation Project 2nd Stage Beykoz (Akbaba, Dereseki) Creek Rehabilitation Project 2nd Stage Date of Contract Signing Contract Amount ( VAT included) (TRY) Total Payment (TRY) Progress (Total Payment / Contract Amount) Total length of the creek to be rehabilitated in meters (1) Total length of rehabilitation works at the last payment certificate in meters (2) Physical progress (2)/(1) 5/7/2010 7,339, ,040, % 1,480 1,450 98% 5/7/2010 9,187, ,166, % 1, % 6/14/2010 6,405, ,951, % % 6/15/2010 8,099, ,817, % % 6/29/2010 9,899, ,167, % 2,545 2,180 86% 6 Kadıköy Kurbağalıdere Rehabilitation Project 8/6/2010 5,107, ,855, % % 7 Üsküdar Bekar Creek Rehabilitation Project 8/9/2010 5,899, % % 8 Beylikdüzü, Kavaklıderesi Rehabilitation Project 1st Stage 10/6/2010 6,017, % 2, % 9 Beylikdüzü, Kavaklıderesi Rehabilitation Project 2nd Stage 10/6/2010 8,258, % 3, % 10 Haramidere Rehabilitation Project 1st Stage 2/25/ ,270, , % 1, % 11 Haramidere Rehabilitation Project 2 nd Stage 2/25/2011 9,690, , % 1, % 12 Haramidere Rehabilitation Prıoject 3rd Stage 2/25/ ,731, , % 1, % 13 Esenyurt Haramidere Rehabilitation Project 4/19/ ,438, % 1, % 14 Küçükçekmece Hasanoğlu Creek Rehabilitation Project 4/18/2011 9,752, % 1, % Total 119,096, ,342, ,231 6,385 27

38 Annex 3. Economic and Financial Analysis Not Applicable 28

39 Annex 4. Bank Lending and Implementation Support/Supervision Processes (a) Task Team members Names Title Unit Responsibility/ Specialty Lending Seema Manghee Sr Water & Sanitation Spec. TWIWA TTL Sana Kh.H. Agha Al Nimer Sr Water & Sanitation Spec. MNSWA Engineer Zeynep Zerrin Koclar Technical Specialist ECSSD Engineer Jolanta Kryspin-Watson Operations Officer ECSS6 Technical Frank Van Woerden Senior Environmental Engineer ECSS3 Solid Waste Specialist Ibrahim Sirer Senior Procurement Specialist ECSO2 Procurement Zeynep Lalik Sr Financial Management Specialist ECSO3 Financial Management Supervision (June October 2009) Seema Manghee Sr Water & Sanitation Spec. TWIWA TTL Sana Kh.H. Agha Al Nimer Sr Water & Sanitation Spec. MNSWA Engineer Zeynep Zerrin Koclar Technical Specialist ECSSD Engineer Ibrahim Sirer Senior Procurement Specialist ECSO2 Procurement Zeynep Lalik Sr Financial Management Financial ECSO3 Specialist Management Supervision/ICR (October 2009 July 2011) Mara Warwick Country Sector Coordinator ECSSD TTL Elif Ayhan Urban Specialist ECSS6 Engineer Daniel R. Gibson Lead Social Development Specialist ECSOQ Social Safeguards Frederick E. Brusberg Lead Social Development Specialist ECSS4 Social Safeguards Chukwudi H. Okafor Sr Social Development Specialist ECSS4 Social Safeguards Ayse Seda Aroymak Sr Financial Management Financial ECSO3 Specialist Management Ibrahim Sirer Sr Procurement Specialist ECSO2 Procurement Salih Erdurmus Procurement Specialist ECSO2 Procurement Esra Arikan Environmental Specialist ECSS3 Environmental Safeguards Xiaoke Zhai Transport Specialist EASCS Engineer 29

40 (b) Staff Time and Cost Staff Time and Cost (Bank Budget Only) USD Thousands Stage of Project Cycle No. of staff weeks (including travel and consultant costs) Lending FY FY FY Total: Supervision/ICR FY FY FY FY FY Total:

41 Annex 5. Beneficiary Survey Results Not Applicable Annex 6. Stakeholder Workshop Report and Results Not Applicable 31

42 Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR RePUBLIC Of rurkey PRii'viE viinistry 1'111: Cndcrsccretariur c;ftrc-aslu"y Ref: 1195-! Ankara, i\ lr. Flori:m Fichtl L~ad Opcr:1tions Ot"tic.::r Europe and Ct:ntralt\sia Region The World Bani.. Ankara Ofticc Rei": Your lcll..:r dated June I J regarding btanhul ~vlunit:ipal lnli":!struc!un: Project Impleme-ntation Completion and Results RcpJrt-Rrquests for Conllllt:nts Dear Mr. Fichtl. R.:gan.ling l:;tunbul Municipul lnlbstructure Project Implementation C<lmplction and Results Report, please lind altach.:d the comments of Undersecrata riat of Treasury, Ministry of Development and Istanbul,vktropo!itan Municipality. Yours si ncen.:ly. ~~Y/1. '..... ' ' J, w.. l'l 1,.. ;,.,\Llin;.: Dcpu:_, I li r~cto; Ci-.:nt.:r:ll Ji.n F. t..:ign EconomiL Rc!:llton~ ,.., 1 :\ AY S :AN.'tfD f.e p '.5 '~'..-ll.etq.~,., ILNC:tOR/11I'ESWCcn\:J,o,o.,.,.,_ j,~ ~nll lluhnr, \\1. J(, l; llll:"- 1)(,5 1(1,\~,KAR :\ ~ :N d,:!:ukd intiliio<hion; ~. A Yl)r\.~ i:\j)ci1 lei: 104 'i.l!,1.1~' : ~(I~ 7Jft7 ~.:-pn-i;a : il!.!..1!1s:iihmirw!.!l)v~ 32

43 COMMENTS OF THE UNDERSECRETARIAT OF TREASURY ON THE ICR OF ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT Implementation Completion and Results Report (ICRR) of Istanbul Municipal Infrastructure Project has some evaluations on government performance. Our comments on these evaluat ions are as follows; 1) Regula r Project Financing There are regular steps that need to be followed for loans provided for project financing guaranteed by the Turkish Treasury. a- Concept Note needs to be finalized by incorporating the comments of relevant institutions b- According to Law on Regulating Public Finance and Debt Management, Undersecratariat of Treasury asks Ministry of Development whether the project is in the annual investment program and has priority, in order to get their view on the total project amount and appropriations at the stage of obtaining foreign financing for such projects. The Project cannot be externally financed if it is not in the investment program and loan amount cannot exceed the external financing amount envisaged in the investment program c- Following affirmation of Ministry of Development, technical discussions or negotiations can take place between the implementing agen cy together with the Undersecratariat of Treasury and the Bank d- After signing the agreed minutes as a result of the negotiiltions World Bank Board 'lpproves the Project r!- Luiln :111d ~udrjntee,1greemen ts take their fin.ll ver~ions to be sigrwd f- Effectiwness orocess starts to le~alize the ln'ln For this project, our regular project financing procedures could not be followed because of the ambitious timeline and as a result of this; problems have been occurred for the w hole project cycle. 2) Inefficient project preparation Timeline was set for the project at the beginning. The preparations of the project were not mature enough to start negot iations. Therefore, technical discussions have been held in order to discuss the project with all re levant parties (namely, Ministry of Development, Treasury and istanbul Metropolitan Municipality). However, technical discussions were upgraded to negotiations although the problems were not completely solved and the Project was not completely included in the Investment Program. Presenting the Project for the Board approval before solving the problems ca used long delays and implementation problems. 33

44 The reasons for the delay in process are twofold: - Although the project was not in the 2007 Investment Program, and this fact is known by the Bank it was submitted to the Board for approval. -Project was included in 2008 Investment Program. However, the components of this project as in the Project Paper were not aligned with the 2008 Investment Program. Therefore, project was amended by the Bank in Guarantee agreement was signed with the Bank 19 months after the Board approval since sovereign guarantee statutory limits were 2 billion dollars in 2008 and the limit was already reached when the istanbul Metropolitan Municipality Project Loan and Guarantee Agreement were ready to sign. The refore, the Guarantee Agreement could not be signed before The Bank knew that situation but preferred signing the agreement. Lessons from the Project: One the most outstanding lessons to be taken from this project was the importance of the preparation and the design stage of the project. It is essential to note that rushing at the preparedness stage weakens t he project and affects the development objectives. Technical discussions or negotiations should not be started unless the project is included or is about to be included in the Annual Investment Program as envisaged in the Concept Note and Project Paper. 34

45 T.C. istanbul B0Y0K$EHiR BELEDiYE BA$KANLIGJ Mali Hi:t:metler Daire Ba~kanhg1 Finansman Mildilrlilgil ' Say1 : h "\' -! :; ~...; :... Konu: istanbul Beledi yesi Altyap1 Projesi "."""r.u:. <.\'lof!ooe#a OUNYII KGLT~HX~02~1l t ~ "1 ;.. ~~~~ ::n /20 13 T.C. BA~BAKANLIK HAZiNE MUSTE$ARLIGI (Dl$ EKONOMiK ili$kiler MUDURL0GU'NE) ANKARA 11gi : tarih ve I 0196 sayll1 yazrmz. Bilindigi Uzerc, istanbul Bilyilk~ehir Belediyesi, Milste~arhgmJZ garantorltigunde Otinya Bankas1 kaynaklan ile finanse edilen belediyemizin altyap1 yat:mmlan finansmanmda kullanllmak ilzere faiz ve diger masraflar hari~ ABO Dolan ilzerinden kredi sozle~mes i imzalanrm~ ve bahse konu krediden USD kullarum yapilmi~ttr. Bunun ilzerine, Belediyemiz tarih ve sayllt yaz1 ile bahse konu kredi kapsammda kullantlmayan yaki~lk 299,6 mil yon ABD Dolarmm iptal edildigini ve soz konusu projenin 3 I Arahk 2011 tarihi itibari ile kapandjglm belirterek, Miiste~arhgm1za bildirmi~tir. tlgi yazmtz ilt:, Bartka tarafmdan Projeye ili~kin haz1rlanan "Uygulama Tamamlama ve Sonu~ Raporu (Implementation Completion and Results Report - ICR)" ile kurumumuzun diizeltme ve gtiril!?leri talep edilmektedir. Bu dogrultuda, Kurumumuz, Rapor ile ilgili degerlendirme ve goril~ lerimizi tamamlam1~ olup; ektc Miistc~arh gmi za ekte tarafm1za gundcrilmcktedir. ' " silcrini;i rz ::!.:rim. I'' 'i. 'I Ekler: 1-Rapora lli~kin Goril~lerimiz ( lngilizceffork~e) 2-Dere 1slahlan Odeme listesi ( lngilizcerrork~e) t 1a"bul RO)Ok.jthir B<led y.:so Mall Ho<meUer Oaore B~kanhA FinammOll MOdariUAU Me.hmtr Nezohi 6m~tn Mahalle." KaSlm Sok fl ill" ~ Kar Mencr-<OOng.oreniiS1 ANBUL "II f / Faks. 0-ll ~ 35

46 COMMENTS ON THE COMPLETION OF THE implementation AND THE RESULT REPORT OF WORLD BANK INFRASTRUCTURE PROJECT As is known, Istanbul Metropolitan Municipality signed a loan a!:,'tt:ement with the World Bank on with an amount of USD under the guarantee of the Undersecretariat of Treasury. After a Guarantee Protocol was s igned with the Undersccretariat of Treasury on , the loan went into effect and the Undersecretariat of Treasury gave 100% guarantee for this loan agreement. T he aforementioned loan agreement was amended on and the validation of the loan was extended until The loan agreement was signed for funding the following: I. Stream rehabilitation 2. Bridge and Viaduct Reinforcement 3. Rehabilitation of Fire Brigade Services 4. Mapping and Microzoning of European Side Southwest Region 5. Rehabilitation of the former landfill 6. Service procurement for sea pollution and environmental cleaning Regarding the Stream Rehabilitation Constituent of the loan with the amount of USD, tenders were made for 14 streams and USD was spent for the construction of 9 s1ream rehabilitation which are quoted below: 1- Construction of the I st Section of <;:ckmekoy Kemerderesi Stream Rchahil itation l.- t.:onstruction of the 2nd Section of <;:ekmcki:iy Kemerdercsi Stream Rehabilitation > l.-ullmru<.uon u1 tile o,,.;c~.ollull.,,,,u.,:uj...,:..:koucc.: o' l ai-.!<a~ticn:~ i :1r::am ;{,_habilitation 4- Construction of the 2nd Section of Kiioyiiko;:ekmece Nakka~de res i Stream Rehabilitation 5- Construction of the 2nd Section of Beykoz (Akbaba, Dereseki) Stream Rehabilitation 6- Construction ofkad1kiiy Kurbagahdere Stream Rehabilitation 7- Construction of the I st Section of Haram idere Stream Rehabilitation 8- Construction of the 2nd Section of Haramidere Stream Rehabilitation 9- Construction of the 3rd Section ofharamidere Stream Rehabilitation The unused amount of the loan which is ljsd ( USD ljsd = USO) was terminated on with the approval of the World Bank and the assent of the Undersecretariat oftreasury. Our Comment~ Regarding the Negative Points io the Report As in all loans receiv~d for the projects of our municipality, the municipality b~:gan working eageoly and with excitement for this loan so that constiwents of it can be realized immediately. Including, the 36

47 positive approach of the employees of World Bank Ankara Office, necessary work conducted by responsible units of our municipality on the coustituents of the loan, all employees put efforts to bring this project to tender phase as soon as possible. Due to the fact that the guarantee of the Undersccretariat of Treasury was granted 19 months later than Board's approval, there has been a major delay in the project. However, this delay is not directly a result of our municipal work. Istanbul Metropolitan Municipality (IMM) cannot affect the decision process of an independent authority. IMM cannot be claimed to be unfamiliar with international financing. After the Undersecretariat of Treasury, IMM has the most efficient management system of taking and using external debt. Until this agreement was signed, our municipality took loans for countless projects. Moreover after this project, externals loans were taken and used for 5 more projects. The amount of this loan is not even the I 0% of total external financing oflmm. Relevant work for micro-zoning and mapping of Southwest Region in European side started at the beginning of Due to the fact that appropriate purchase document did not exist in the Bank, the preparation of a new purchase document based on examples sent to Directorate of Earthquake and Ground Analysis and its translation was a significant progress. As the bank provided wrong documents, documents had to be changed twice. Moreover, although all requests of the Bank were met by our directorate on short notice, the approval of final purchase document and return of it took a long time. The Bank continued sending feedback for different and new requests every time. In addition to this, the fact that fo r the negotiation of requested technical changes, the Bank Jid not have any compt:tcnl -., ~ "<"nncl md t;lr that onntler :1 o:on~uhant was ~ou ~ht a lter fnr the technical i~~ucs. \~ hich c::mscd important delays. Concerning another constituent, Rehabilitation of Fire Brigade Services, working on tender documents with the World Bank took some time and the Project has been brought to tender stage. However, as the credit was cancelled, the project could not be finalized. One of the goals set by our Municipa lity is to prevent spates caused by heavy rain at specific periods in the year and casualties resulting from these incidents. Jn this respect, it is necessary to note that stream rehabilitation must be taken into consideration. This constituent is the most difficult to coordinate among other constituents. It does not only include construction work. In addition, it includes social evaluation reporting topics. socialization processes and cadastral sheets. This constituent requires many departments -within our Municipality to work closely together in coordinatiou and simultaneously. 37

48 Our Municipality paid strict attention in order not to aggrieve citizens during expropriation and repositioning activities as a pan o f tht: implication of stream rehabilitation constituent. As some of stream beds are expropriated and some arc occupied, stream beds are carefully selected, nevertheless some problems occurred. The expropriation of Beyroz (Akbaba, Dereseki) stream connections project that is projected to be funded via World Bank loan was initiated in 20 I ,86 m 2 of land was included io the expropriation program. So far, a total sum of tl. was paid in return for expropriation of ,50 m 2 of land. The expropriation of28.646, 18m' treasury revenue, 4.992,00 m 2 forest land, ,34 m 2 land was cancelled. The legal process for the remaining 6.918,84 m' is still continuing. Failure to complete applications on time resulted from the extension oflegal process. Land in tbe Project (m') ,86 Treasury Revenue ,18 Forest Laud (m 2 ) 4.992,00 Cancelled Land (m') ,34 Completed Laud (m') ,50 Paid Sum (fl.) Remaining Sum (m') 6.918,84 b propriution of Silivri Bogluca :-itrt:arn, Jllother expropriation projc~.: t, was initiated in I he ;;rojccl CIIClHIIpa"c>.111 J I j /..i.. oil" i.111j Ull.i.).) :noduings wuh 2J 7 inclcp c llllciil. ~Cli ijiis Ill l<lwi ;, ithin the expropriation project. So far, a total of TL has been paid to expropriate 8.058,68 m 2 of land and 272 independent sections in total. Lega.l process on the expropriation oftht: remaining 103,66 m 2 and 15 independent sections on top of it is in progress. Area in project (m 2 ) 8157,34 Number of buildings 55 (287 independent sections) Completed area (mz) 8053,68 (272 independent sections) Price paid (TL.) I Remaining area (m 1 ) 1103,66 Istanbul Metropolitan Municipality Dire<:toratc of Domiciies cart) out wcrk to designate and assess in ~:trcam Rehabilitation projects to evacuate slums on stream bt:ds. 38

49 In other words. for instance, within the context of the rehabilitation of Uzundere (located in the Sultanbeyli District) and its branch Naldoken Stream, 29 buildings were evacuated and TL was paid as price of debris and 23 houses were allocated in return. Prices of debris were appropriated to the prices of houses and installment plans up to 20 years were designed for the remaining debts. Prices of debris were paid to those who did not receive any housing in return. That way, no rightful party was put in disadvantage and they were granted healthy housing and livable environments in all the stream rehabilitation projects. During meetings between the World Bank and Directorates of lnfrastructural Services, Expropriation arrd Domiciles, these issues were tabled in detail. Within the context of the World Bank credit, Istanbul Metropolitan Municipality commissioned an independent firm to come up with reports that were submitted to the World Bank on the expropriation, social and economic activities for the Beykoz and Silivri (Bogluca) Streams which require expropriation or resettlement. Within the scope of Stream Rehabilitation constituent, while Istanbul Metropolitan Municipality has used ,86 TL of the loan granted by the World Bank for 14 streams, Istanbul Metropolitan Municipality used TL from equity capital to complete the rehabilitation process of the remainmg steams and realized 94% of the tender price although the loan agreement haj been cancelled. For the remaining part, studies are continuing. Apart from that, as a consequence of the protocol with our subsidiary iski in 2007, 2008, 2009 and 20 I 0, an amount of3 I TL was paid to iski for the rehabilitated streams and the construction of rain channels. Stream rehabilitation has not entered the agenda of Istanbul :~ fter the loans granted by the World Bank; there had already ' ::.:11 l i::::m ;::h:rhilitation act iv ir ic~ hd r,re the nroiect md 1 h<:se rchahilitntions v il1 1 1kc place dh:r the project a~ well. Apparelllly, the claim in the report that ' Istanbul Metropolitan Municipality is not interested in the minimization of the destructive risks and casualties of tlood disasters" fails to reflect the truth. Istanbul Metropolitan Municipality could never adopt such a point of view. Despite all the activities and endeavors, the settlement of the increasing disputes has not been feasible as the procedure, regulations and rules between o ur municipality and the World Bank differ especially on Stream rehabilitation constituent. The aforementioned lending agreement has therefore been cancelled with the joint resolution of the World Bank, Undersecretariat oftreasury and Istanbul Metropolitan Municipality, resulting in the abolishment of the loan agreement. Kindly submitted to your infom1ation. 39

50 Progress To tal (Total Total Stream rehabilitation Signing Da~, Total Payment Total Payment Paymet/ Length to be length at the PhySical of tho '"'hreement Total (TLJ ( World Bank [TL) Agreement rehabilitated( las t payment Progrrss Job Description Agreeme. (I AT mcluded) (TL) Loan) ( Equity Capital) Total)% m)(l) zone (m) (2) ((2) 1 (1).% ~ekmckoy Kemerdercst Stream 1 Reha bilita tion Project Phase l u 7,339, ,0<10, ~.. l~ll.771,6 '.' 69 1,48 1,45 98 Kil~iik~ekmece Nakka~deresi 2 Stre"m Rch3billtation Project Phase ~ekmekiiy Kemerderesl Stream 3 Rehahilltotlon Project Phase lu 9.1a , o.4i15,632 uo 6, ~z:~.:-:u<; zn ioo 40 Kii~k~ekmece Nakka~deresi 4 Stream Rehahilitation Project Phase 2 Beykoz (Akbaba, Deresekl) Stream 5 Rehabilitation Project Phase 2 Kad1koy Kurbagahdere Stream 6 Rehabilitation Project Osktldot llekar Stream 7 Rchab11ita t1on Project Oeyllkdfiztl, Kavakhderul Stream n RehabilitatiOn ProJect Phase 1 Bcyllkduzu, Kavakhderesi Stream 9 Rehabilitation Project Phase 2 llaramidere Stream Rehabilitation io Project Pha<e 1 Haramidcre Stream Rehabilitation II Project Phase 2 Haramidcre Rehabilitation Project 12 Phase G,U'J ,817, "?.1 Ht :" t, 3'~ ~.~~ ,167, , i 9.Z5 62 2,54 5 2, CJ.. 5,107, ,055, ; 1!),1_297,[; "! Z \.20;.. 5.d ~.u5:,_1: J"'' tt u u,ul7, o.~33s6~.'?~ 0 2, u 8,250, ~.4%.~57,10 0 3, , , ! >ll,7<, 4 1, c~J 234.H 410, d.jh.799,79 4 1, 'l). ~ b4 45., \2.l';,l.c: ;2 li} 4 1,3 0 0 Esenyurt Haramidere Stream ' 13 Rehabilitation Project 19.0 ; & St>B.24 ~ ,20 0 1,5 0 0 Kurukrekmecc Hasanoglu Stream 14 Rehabilltotion ProJect Equity Capital Totai :1~ ~.2 i ?3,7il 0 1, Total t- 119,096, , :107,R5 12,231 6,305 - "---

51 ~ -.,.._ --~ fl \ A T.C. K<\LKINMA BA.KAJ'ILIGI Sosyal Sektorlct ve Koordinasyon Gene! MUdUriUgti Say1 Konu Istanbul Belediyesi Altyap1l"tojesi 16/08/2013 HAZ~ MOS~ARLICINA ilgi: Hazinc Mils~hgmm tarib ve /10196 say1h yaz1s1. llgi'de kay1tlt yaz1 ile, DUnya Bankas1 tarafmdan finanse edilen ve istanbul BUytl~ehi r Belediyesi tarafmdan ytlrllttilen Istanbul Belediyesi Altyap1 Projesinin 31 Arollk tarihi itibanyla kapand1g1 bildirilerek Dllnya Bankas1 taraf1odan projeye ili~kin hazjrlanan "Uygulama Tamamlama ve Sonus: Raporu" gonderilmekte ve taslak ltapora ili~kin gtl~le rimiz talep edilmektedir. Bilindigi Uzere, Bakanhgmnz beledlyelerin talebi Uzerine d1~ kredi ile yap1lmas1 planlanan projeleri degerlendirmekte ve uygun goriilenltri Yatmm Program1 ile ili~kilendirmektedir. D~ kredi ilt: finanse edilecek projelerin iyi ettid edilmesi, proje ihtiyac1 ile proje yonetim sure9lerinin iyi tasarlwu11as1 Bakanhg1m1Zm projeleri degerlil!dirirken ancelik verdigi hususlard1r. Bununla birlikte, Bakanlt 1m1z taraftndan_?nwanan proj.,lerde uygulama safhastnda meydana selebilecek deg1~1 1 ertn. 1 1m1Z 1 e ~aitere~@.!tmas1 onem arz etmektedtr.!ju kap.sa~... ::h!illili.l!!l!efeaiyc.f]... cy~w.uu.~'tt\tjme5.l~tciiicrey~aruii }oi5!!!1f~j!r~~ ir9jci~fl~::..,_ ~e~5.~ e.~~~esh~l!l... ~~z kon~s,!!_cj!!gerfelid~ll)e ran9@g~c.r ~~"iiiigll~fell)ier l~tgmda s;1kiiqla~ak ~. 'aersler,,ol1emh gontlmek:te ve!iul)d~o sonra )<redi altnmast ongoriilen projebde de yukanc!a.belirtilej\ hususlara dikkat edilm~:si g~relnigi de~erlendirifmel<re<lir: - -. ~ -..,.,... ~ _ ~~: ~1 'o DilgileriniLe v~ gcrc~ini rica edcrim. o ~ l i K:-,..... I H tln>,,,.,, \ \drcs: Ncc:>tlb.:y Cad.~:.,: 11 0/A O~ IOQ YUccttpc.. f'.nka!'.a T~kton:+90(3 l 'ZJ ~ Fa~,:,9(1 t31 1) f.ld<tronik.~c: hup:l/wv.w.kulkinmn.gol tr 1arli@dp,;o~.t r ~!l:'v s.. y1b El,..,_uomk ~m~" K!! nll:'ll ' ur~ 11) 0\IH liar,\o.. \juvcnll tleklf.:mi"' lm1a :1c {Jr(tilmt$tir. E.PI Io.. t.:yidl bu ~u :/l dpttb. dtl '.fo V.t r.'~orku ad:csmdcll Tl l''}l UI.IJP 30'l(J kodu tic yapll lliltr i_. 41

52 Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders Not Applicable Annex 9. List of Supporting Documents 1. Istanbul Municipal Infrastructure Project (IMIP), Project Appraisal Document (PAD) 2. IMIP World Bank Implementation Supervision Reports 3. IMIP World Bank Aide Memoires and Back to Office Reports 4. Istanbul Metropolitan Municipality Project Progress Reports 5. Correspondence between the Istanbul Metropolitan Municipality, Undersecretariat of the Treasury and the World Bank 6. Consultant studies and reports relating to the creek rehabilitation activities 42

53 resi BULGARIA GREECE 40 N 36 N 26 E 30 E 34 E 38 E GSDPM Map Design Unit Sazli Dere Istanbul Ayayorgi Black Sea ANKARA 30 E 34 E TURKEY SYRIAN ARAB REPUBLIC This map was produced by the Map Design Unit of The World Bank. The boundaries, colors, denominations and any other information shown on this map do not imply, on the part of The World Bank Group, any judgment on the legal status of any territory, or any endorsement or acceptance of such boundaries. Yenihan RUSSIAN FEDERATION GEORGIA 42 E AZER- ARMENIA BAIJAN IRAQ AZER. ISLAMIC REP. OF IRAN Kanli Der Alibey TURKEY ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT e Kemerburgaz E N Yenimahalle Yeniköy Sariyer Çubuklu Keçilik Yali Mahallesi Beykoz Rumelifeneri Paşabahce abahce Black Sea Dereseki Köy Kumlu k Riva Köy şa Polonezköy Alibeyköy N Hasanoğlu Deresi Deresi Hamam Küçükçekmece Gölü Büyük Halkali Halkali Der esi Çamurluhan Atişalan Esenler Güngören Deresi CREEKS REHABILITATED UNDER THE PROJECT TOWNS/URBAN AREAS MAIN ROADS SECONDARY ROADS Sey tan Deresi S t r a i (Bosphorus) t Beykoz (Akbaba, Dereseki) Creek Rehabilitation Project 2nd Stage Deresi Kaldirim Riva Deresi Ha Küçüçekmece Nakkaşderesi Rehabilitation Project 1st Stage Rehabilitation Project 2nd Stage Eyup Istanbul Rumellhisari Bebek Arnavutköy l I s t a n b u Anadoluhisari Kandilli Beylerbeyi Kisikli aşli Taşli Dere Dudullu Deresi Çekmeköy Kemerderesi Rehabilitation Project 1st Stage Rehabilitation Project 2nd Stage N DECEMBER 2013 Topsakizlar E Yeşilköy Bakirköy Kadiköy Sea of Marmara E Erenköyu Küçükbakkal Kadiköy Kurbağahdere Rehabilitation Project Kilometers E IBRD 40569

TURKEY ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT (RESTRUCTURING) PROJECT PAPER

TURKEY ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT (RESTRUCTURING) PROJECT PAPER Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized TURKEY ISTANBUL MUNICIPAL INFRASTRUCTURE PROJECT (RESTRUCTURING) PROJECT PAPER Responsible

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48650) ON A LOAN IN THE AMOUNT OF EURO 90.0 MILLION (US$ MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48650) ON A LOAN IN THE AMOUNT OF EURO 90.0 MILLION (US$ MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48650)

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF MUNICIPAL SERVICES PROJECT LOAN 7885-TU

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF MUNICIPAL SERVICES PROJECT LOAN 7885-TU Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Social, Urban Rural and Resilience (GSURR) Europe and Central Asia Region Document of

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-45170) ON A LOAN IN THE AMOUNT OF US$ 294.

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-45170) ON A LOAN IN THE AMOUNT OF US$ 294. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No:ICR0000131 IMPLEMENTATION COMPLETION AND RESULTS

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 24-Feb-2015

More information

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) IBRD Jun ,000,000.00

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) IBRD Jun ,000,000.00 Public Disclosure Authorized 1. Project Data Report Number : ICRR0021272 Public Disclosure Authorized Public Disclosure Authorized Operation ID P159774 Country Fiji Operation Name Fiji Post-Cyclone Winston

More information

Project development objective/outcomes

Project development objective/outcomes Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized THE SAINT VINCENT & THE GRENADINES HIV/AIDS PREVENTION AND CONTROL PROJECT PE-PO76799

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 400,000,

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000, Original Commitment 400,000, Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020001 Public Disclosure Authorized Project ID P100580 Country Ukraine Project Name ROADS & SAFETY IMPROVEMENT

More information

Country Practice Area(Lead) Additional Financing Croatia Finance & Markets P129220

Country Practice Area(Lead) Additional Financing Croatia Finance & Markets P129220 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020731 Public Disclosure Authorized Public Disclosure Authorized Project ID P116080 Project Name EXPORT

More information

RESTRUCTURING PAPER ON A

RESTRUCTURING PAPER ON A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A Report No: 63424-AR PROPOSED PROJECT

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 04/15/2010 1. Basic Project Data Original

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jun ,670,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jun ,670,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020366 Public Disclosure Authorized Public Disclosure Authorized Project ID P107666 Country Peru Project

More information

IBRD: ($m.) support the development of municipal infrastructure to provide quality local services.

IBRD: ($m.) support the development of municipal infrastructure to provide quality local services. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Integrated Safeguards Data Sheet (ISDS) Section I Basic Information Date ISDS Prepared/Updated:

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA IDA-47610) ON A CREDIT

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA IDA-47610) ON A CREDIT Public Disclosure Authorized Document of The World Bank Report No: ICR2482 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-0 IDA-1 IDA-47610) ON A CREDIT Public Disclosure

More information

Actual Project Name : Marmara Earthquake Emergency Reconstruction Project Country: Turkey US$M): Project Costs (US$M

Actual Project Name : Marmara Earthquake Emergency Reconstruction Project Country: Turkey US$M): Project Costs (US$M Public Disclosure Authorized IEG ICR Review Independent Evaluation Group 1. Project Data: Date Posted : 09/06/2007 Report Number : ICRR12684 Public Disclosure Authorized Public Disclosure Authorized Public

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4291 Project Name. Wenchuan Earthquake Recovery Project Region

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4291 Project Name. Wenchuan Earthquake Recovery Project Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4291 Project Name Wenchuan

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 04/27/2010 INTEGRATED SAFEGUARDS DATASHEET

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE Public Disclosure Authorized Document of The World Bank Public Disclosure Authorized RESTRUCTURING PAPER ON A Report No: RES19152 Public Disclosure Authorized Public Disclosure Authorized PROPOSED PROJECT

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 05/06/2010 INTEGRATED SAFEGUARDS DATASHEET

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD TF-53472) ON A LOAN IN THE AMOUNT OF US$150 MILLION

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD TF-53472) ON A LOAN IN THE AMOUNT OF US$150 MILLION Public Disclosure Authorized Document of The World Bank Report No: ICR2384 IMPLEMENTATION COMPLETION AND RESULTS REPORT Public Disclosure Authorized Public Disclosure Authorized (IBRD-47360 TF-53472) ON

More information

The Bank s Emergency Policy

The Bank s Emergency Policy The Bank s Emergency Policy 04/10/2006 1 Emergency Recovery Assistance OP 8.50 Bank emergency assistance may take the form of (a) immediate support in assessing the emergency's impact and developing a

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47910) ON A LOAN

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47910) ON A LOAN Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47910)

More information

INTEGRATED SAFEGUARDS DATA SHEET RESTRUCTURING STAGE Note: This ISDS will be considered effective only upon approval of the project restructuring

INTEGRATED SAFEGUARDS DATA SHEET RESTRUCTURING STAGE Note: This ISDS will be considered effective only upon approval of the project restructuring Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET RESTRUCTURING STAGE te: This ISDS will be considered effective only upon approval of the project restructuring Date ISDS Prepared/Updated:

More information

World Bank Environmental. and Social Policy for Investment Project Financing

World Bank Environmental. and Social Policy for Investment Project Financing World Bank Environmental and Social Policy for Investment Project Financing Purpose 1. This Environmental and Social Policy for Investment Project Financing 1 sets out the mandatory requirements of the

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jul ,330,316.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jul ,330,316.00 Public Disclosure Authorized 1. Project Data Report Number : ICRR0020321 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project ID P107840 Country Macedonia, former

More information

Bank Policy. Investment Project Financing. Bank Access to Information Policy Designation Public. Catalogue Number OPS5.03-POL.110

Bank Policy. Investment Project Financing. Bank Access to Information Policy Designation Public. Catalogue Number OPS5.03-POL.110 Bank Policy Investment Project Financing Bank Access to Information Policy Designation Public Catalogue Number OPS5.03-POL.110 Issued September 30, 2018 Effective October 1, 2018 Content Operational policy

More information

Bank Policy. Investment Project Financing. Bank Access to Information Policy Designation Public. Catalogue Number OPS5.03-POL.109

Bank Policy. Investment Project Financing. Bank Access to Information Policy Designation Public. Catalogue Number OPS5.03-POL.109 Bank Policy Investment Project Financing Bank Access to Information Policy Designation Public Catalogue Number OPS5.03-POL.109 Issued November 10, 2017 Effective November 10, 2017 Content Operational policy

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE THIRD HIGHWAY PROJECT. IBRD 7889-AZ (May25, 2010) AND IDA 4723-AZ (May 25, 2010) TO THE

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE THIRD HIGHWAY PROJECT. IBRD 7889-AZ (May25, 2010) AND IDA 4723-AZ (May 25, 2010) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Transport Sector Unit Europe and Central Asia Region Document of The World Bank RESTRUCTURING

More information

Document of The World Bank

Document of The World Bank Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-44000, TF-99140)

More information

Country Practice Area(Lead) Additional Financing Social, Urban, Rural and Resilience P Indonesia Global Practice

Country Practice Area(Lead) Additional Financing Social, Urban, Rural and Resilience P Indonesia Global Practice Public Disclosure Authorized 1. Project Data Report Number : ICRR0021284 Public Disclosure Authorized Public Disclosure Authorized Project ID P111577 Project Name ID-Local Government and Decentralization

More information

OP Investment Project Financing. Bank Access to Information Policy Designation Public

OP Investment Project Financing. Bank Access to Information Policy Designation Public Bank Policy - Investment Project Financing Bank Access to Information Policy Designation Public Catalogue Number OPSVP5.03-POL.103 Issued Effective July 1, 2014 Last Revised On July 1, 2016 Retired July

More information

Safeguard Policies: A Quick View Tbilisi. The World Bank Europe & Central Asia Region

Safeguard Policies: A Quick View Tbilisi. The World Bank Europe & Central Asia Region Safeguard Policies: A Quick View Tbilisi April 1-3, 1 2008 The World Bank Europe & Central Asia Region 1 Why do we have the World Bank Safeguard Policies? Do no harm: protect people and environment from

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48580) ON A LOAN IN THE AMOUNT OF 92 MILLION EURO (US$ MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48580) ON A LOAN IN THE AMOUNT OF 92 MILLION EURO (US$ MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR2671 IMPLEMENTATION COMPLETION AND RESULTS REPORT

More information

Bank Policy. Investment Project Financing. Bank Access to Information Policy Designation Public. Catalogue Number OPS5.03-POL.108

Bank Policy. Investment Project Financing. Bank Access to Information Policy Designation Public. Catalogue Number OPS5.03-POL.108 Bank Policy Investment Project Financing Bank Access to Information Policy Designation Public Catalogue Number OPS5.03-POL.108 Issued August 18, 2017 Effective August 18, 2017 Retired November 9, 2017

More information

PROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No.: PIDA9857. Project Name. Parent Project Name. Region. Country

PROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No.: PIDA9857. Project Name. Parent Project Name. Region. Country Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized PROJECT INFORMATION DOCUMENT (PID) ADDITIONAL FINANCING Report No.: PIDA9857 Project

More information

The World Bank Third Secondary and Local Roads Project (P148048)

The World Bank Third Secondary and Local Roads Project (P148048) Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THIRD SECONDARY AND LOCAL ROADS PROJECT APPROVED ON JULY 3, 2014 TO GEORGIA REPORT NO.:

More information

Table 1 the Road Network of Mozambique (in kilometers)

Table 1 the Road Network of Mozambique (in kilometers) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB2867 Roads

More information

US$M): Sector Board : Social Development Cofinancing (US$M (US$M US$M): US$M):

US$M): Sector Board : Social Development Cofinancing (US$M (US$M US$M): US$M): Public Disclosure Authorized IEG ICR Review Independent Evaluation Group Report Number : ICRR14437 1. Project Data: Date Posted : 09/22/2014 Public Disclosure Authorized Public Disclosure Authorized Country:

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 05/10/2007 INTEGRATED SAFEGUARDS DATASHEET

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No.

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Report No. Project Name Region Sector Project ID Borrower(s) Report No. PID5794 Lebanon-Municipal Infrastructure Project (@+) Middle East and North Africa Region Other Urban Development LBPE50544 Lebanese Republic

More information

Country Practice Area(Lead) Additional Financing Indonesia Water P161514

Country Practice Area(Lead) Additional Financing Indonesia Water P161514 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020651 Public Disclosure Authorized Public Disclosure Authorized Project ID P096532 Project Name ID:

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) TF-17383,TF Jun ,540,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) TF-17383,TF Jun ,540,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020847 Public Disclosure Authorized Public Disclosure Authorized Project ID P149629 Country Mozambique

More information

Document of The World Bank

Document of The World Bank Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-35380 IDA-35381)

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA TF-92459) ON A CREDIT IN THE AMOUNT OF SDR MILLION (US$30.00 MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA TF-92459) ON A CREDIT IN THE AMOUNT OF SDR MILLION (US$30.00 MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-42570 TF-92459)

More information

Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H4630 TF TF-96083) ON AN

Document of The World Bank FOR OFFICIAL USE ONLY IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H4630 TF TF-96083) ON AN Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: ICR00003680 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H4630 TF-92396 TF-96083)

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE I. Basic Information Date prepared/updated:

More information

Project Information Document/ Integrated Safeguards Data Sheet (PID/ISDS)

Project Information Document/ Integrated Safeguards Data Sheet (PID/ISDS) Project Information Document/ Integrated Safeguards Data Sheet (PID/ISDS) Concept Stage Date Prepared/Updated: 31-Aug-2016 Report : PIDISDSC18959 Public Disclosure Authorized Public Disclosure Authorized

More information

OPERATIONS MANUAL BANK POLICIES (BP)

OPERATIONS MANUAL BANK POLICIES (BP) BANK POLICIES (BP) OM Section F1/BP Page 1 of 2 These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. SAFEGUARD POLICY STATEMENT 1. The Asian Development

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47570) ON A LOAN IN THE AMOUNT OF US$ MILLION ROMANIA FOR A

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47570) ON A LOAN IN THE AMOUNT OF US$ MILLION ROMANIA FOR A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00001475 IMPLEMENTATION COMPLETION AND RESULTS

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Dec ,000,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020665 Public Disclosure Authorized Public Disclosure Authorized Project ID P117440 Country El Salvador

More information

Country Practice Area(Lead) Additional Financing

Country Practice Area(Lead) Additional Financing Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0021281 Public Disclosure Authorized Public Disclosure Authorized Project ID P149884 Project Name CF-

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) TF Dec ,872,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) TF Dec ,872,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020840 Public Disclosure Authorized Public Disclosure Authorized Project ID P103470 Country OECS Countries

More information

RESETTLEMENT POLICY FRAMEWORK

RESETTLEMENT POLICY FRAMEWORK Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized RESETTLEMENT POLICY FRAMEWORK HURRICANE TOMAS EMERGENCY RECOVERY PROJECT Saint Lucia

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 4 11 A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The government has identified the priority areas to be covered under the ensuing loan project and prepared outline technical studies

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48380) ON A LOAN IN THE AMOUNT OF US$ 180 MILLION TO THE

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48380) ON A LOAN IN THE AMOUNT OF US$ 180 MILLION TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48380)

More information

Program-for-Results Financing 1

Program-for-Results Financing 1 Operational Manual BP 9.00 - Program-for-Results Financing These procedures were prepared for use by World Bank staff and are not necessarily a complete treatment of the subject. BP 9.00 February, 2012

More information

Country Practice Area(Lead) Additional Financing Social, Urban, Rural and Resilience P117308,P Bolivia

Country Practice Area(Lead) Additional Financing Social, Urban, Rural and Resilience P117308,P Bolivia Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0021219 Public Disclosure Authorized Public Disclosure Authorized Project ID P083979 Project Name BO

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48420) ON A LOAN IN THE AMOUNT OF US$ MILLION ROMANIA FOR A

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-48420) ON A LOAN IN THE AMOUNT OF US$ MILLION ROMANIA FOR A Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00001476 IMPLEMENTATION COMPLETION AND RESULTS

More information

DRAFT FOR CONSULTATION OCTOBER 7, 2014

DRAFT FOR CONSULTATION OCTOBER 7, 2014 DRAFT FOR CONSULTATION OCTOBER 7, 2014 Information Note 1: Environmental and Social Risk Classification The Board has requested the release of this document for consultation purposes to seek feedback on

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD 7268; IBRD 7974) ON A LOAN IN THE AMOUNT OF USD 200.

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD 7268; IBRD 7974) ON A LOAN IN THE AMOUNT OF USD 200. Public Disclosure Authorized Document of The World Bank Report No: ICR00003656 Public Disclosure Authorized Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD 7268; IBRD 7974)

More information

Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name Region Project Information Document Report No. PID8416 Turkey-Marmara Earthquake

More information

Environmental Safeguard Monitoring Report. FIJ: Transport Infrastructure Investment Sector Project

Environmental Safeguard Monitoring Report. FIJ: Transport Infrastructure Investment Sector Project Environmental Safeguard Monitoring Report Semi Annual Report July 2016 ADB Project Number: 48141-001 ADB Loan Number: 3210 FIJ: Transport Infrastructure Investment Sector Project Prepared by Fiji Roads

More information

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE INFORMAL SETTLEMENTS IMPROVEMENT PROJECT CREDIT 4873-KE

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE INFORMAL SETTLEMENTS IMPROVEMENT PROJECT CREDIT 4873-KE Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY Report No: 104604 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

Cofinancing (US$M): c. Policy Areas: The policy areas included into the Program Document of the FIRM DPL were the following:

Cofinancing (US$M): c. Policy Areas: The policy areas included into the Program Document of the FIRM DPL were the following: Public Disclosure Authorized IEG ICR Review Independent Evaluation Group 1. Project Data: Date Posted: 03/25/2015 Report Number: ICRR14675 Public Disclosure Authorized Public Disclosure Authorized Public

More information

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE . Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDSPrepared/Updated: Date ISDS Approved/Disclosed I. BASIC INFORMATION 1. Basic

More information

Mongolia: Social Security Sector Development Program

Mongolia: Social Security Sector Development Program Validation Report Reference Number: PVR196 Project Number: 33335 Loan Numbers: 1836 and 1837(SF) November 2012 Mongolia: Social Security Sector Development Program Independent Evaluation Department ABBREVIATIONS

More information

FOR OFFICIAL USE ONLY

FOR OFFICIAL USE ONLY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank FOR OFFICIAL USE ONLY PROJECT PAPER ON A PROPOSED ADDITIONAL

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF URBAN III - PHASE II PROJECT GRANT IDA-H3300 APPROVED ON JULY 9, 2007

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF URBAN III - PHASE II PROJECT GRANT IDA-H3300 APPROVED ON JULY 9, 2007 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF

More information

Country Practice Area(Lead) Additional Financing Uzbekistan Energy & Extractives P133633,P165054

Country Practice Area(Lead) Additional Financing Uzbekistan Energy & Extractives P133633,P165054 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0021115 Public Disclosure Authorized Public Disclosure Authorized Project ID P118737 Project Name ENERGY

More information

SECTOR ASSESSMENT (SUMMARY): FINANCE (DISASTER RISK MANAGEMENT) 1. Sector Performance, Problems, and Opportunities

SECTOR ASSESSMENT (SUMMARY): FINANCE (DISASTER RISK MANAGEMENT) 1. Sector Performance, Problems, and Opportunities National Disaster Risk Management Fund (RRP PAK 50316) SECTOR ASSESSMENT (SUMMARY): FINANCE (DISASTER RISK MANAGEMENT) A. Sector Road Map 1. Sector Performance, Problems, and Opportunities a. Performance

More information

Implementation Status & Results Indonesia Aceh Infrastructure Reconstruction Financing Facility (IRFF) (P101785)

Implementation Status & Results Indonesia Aceh Infrastructure Reconstruction Financing Facility (IRFF) (P101785) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Indonesia Aceh Infrastructure Reconstruction Financing Facility (IRFF) (P101785) Operation Name:

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE SECOND ADDITIONAL FINANCING (CREDIT 4987-CM) BOARD APPROVAL DATE: JUNE 23, 2011

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE SECOND ADDITIONAL FINANCING (CREDIT 4987-CM) BOARD APPROVAL DATE: JUNE 23, 2011 Public Disclosure Authorized Document of The World Bank Report No: 65071-CM Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF THE SECOND

More information

Implementation Status & Results Brazil Second National Environmental Project - Phase II (P099469)

Implementation Status & Results Brazil Second National Environmental Project - Phase II (P099469) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Brazil Second National Environmental Project - Phase II (P099469) Operation Name: Second National

More information

Project Name. PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4283 PH-Social Welfare and Development Reform

Project Name. PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4283 PH-Social Welfare and Development Reform Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB4283 PH-Social

More information

DOCUMENT OF THE WORLD BANK RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING HONDURAS AND NICARAGUA CATASTROPHE RISK INSURANCE PROJECT

DOCUMENT OF THE WORLD BANK RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING HONDURAS AND NICARAGUA CATASTROPHE RISK INSURANCE PROJECT Public Disclosure Authorized The World Bank DOCUMENT OF THE WORLD BANK REPORT NO.: RES24760 Public Disclosure Authorized Public Disclosure Authorized RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

More information

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jun ,560,000.00

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IBRD Jun ,560,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0021075 Public Disclosure Authorized Public Disclosure Authorized Project ID P101716 Country China Project

More information

Practice Area(Lead) Social, Urban, Rural and Resilience Global Practice

Practice Area(Lead) Social, Urban, Rural and Resilience Global Practice Public Disclosure Authorized 1. Project Data Report Number : ICRR0020608 Public Disclosure Authorized Public Disclosure Authorized Project ID P094055 Country Vietnam Project Name VN-Local Development Investment

More information

The World Bank Kenya Infrastructure Finance/PPP project (P121019)

The World Bank Kenya Infrastructure Finance/PPP project (P121019) Public Disclosure Authorized AFRICA Kenya Financial Systems Practice Global Practice IBRD/IDA Adaptable Program Loan FY 2013 Seq No: 4 ARCHIVED on 22-Dec-2014 ISR17114 Implementing Agencies: Public Private

More information

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) TF Dec ,580,000.00

L/C/TF Number(s) Closing Date (Original) Total Financing (USD) TF Dec ,580,000.00 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020620 Public Disclosure Authorized Public Disclosure Authorized Operation ID P147166 Country Haiti

More information

INTERNAL AUDIT DIVISION REPORT 2016/155. Audit of the United Nations Human Settlements Programme project management process

INTERNAL AUDIT DIVISION REPORT 2016/155. Audit of the United Nations Human Settlements Programme project management process INTERNAL AUDIT DIVISION REPORT 2016/155 Audit of the United Nations Human Settlements Programme project management process Established policies and procedures need to be further strengthened, particularly

More information

Seq No: 5 ARCHIVED on 29-May-2018 ISR31357 Created by: Laila Ashraf AbdelKader Ahmed on 23-Jan-2018 Modified by: Laurent Gonnet on 21- May-2018

Seq No: 5 ARCHIVED on 29-May-2018 ISR31357 Created by: Laila Ashraf AbdelKader Ahmed on 23-Jan-2018 Modified by: Laurent Gonnet on 21- May-2018 Public Disclosure Authorized The World Bank MIDDLE EAST AND NORTH AFRICA Egypt, Arab Republic of Finance, Competitiveness and Innovation Global Practice Requesting Unit: MNC03 Responsible Unit: GFCMW IBRD/IDA

More information

OECS Disaster Vulnerability and Climate Risk Reduction Program Region. Latin America and the Caribbean Country

OECS Disaster Vulnerability and Climate Risk Reduction Program Region. Latin America and the Caribbean Country Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Report No.: AB6619 OECS

More information

b) if the sub-project is in the Annex B list of this Operational Manual;

b) if the sub-project is in the Annex B list of this Operational Manual; Environmental Review Procedures 1. Background The Environmental Category of the project is FI, since Ziraat Bank (as an FI) will on-lend the World Bank funds to private commercial banks and leasing companies

More information

US$M): US$M): (US$M. Cofinancing (US$M US$M):

US$M): US$M): (US$M. Cofinancing (US$M US$M): Public Disclosure Authorized IEG ICR Review Independent Evaluation Group Report Number : ICRR14162 1. Project Data: Date Posted : 05/20/2014 Public Disclosure Authorized Public Disclosure Authorized Public

More information

6 Report No.: JSDSC1361 1

6 Report No.: JSDSC1361 1 Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE 6 Report No.: JSDSC1361 1,2 Date ISDS Prepared/Updated: 05-Nov-2015 Date ISDS Approved/Disclosed: 06-Nov-2015 Public Disclosure

More information

Actual Project Name : Social Insurance. US$9.7 US$9.4 Technical Assistance Project (SITAP) Country: Bosnia and US$M): Project Costs (US$M

Actual Project Name : Social Insurance. US$9.7 US$9.4 Technical Assistance Project (SITAP) Country: Bosnia and US$M): Project Costs (US$M IEG ICR Review Independent Evaluation Group 1. Project Data: Date Posted : 10/22/2008 Report Number : ICRR12969 PROJ ID : P071004 Appraisal Actual Project Name : Social Insurance Project Costs (US$M US$M):

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA-3524A IDA TF-26222) ON A CREDIT

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA IDA-3524A IDA TF-26222) ON A CREDIT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-35240 IDA-3524A

More information

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject.

OPERATIONS MANUAL BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. OM Section H5/BP Page 1 of 4 BANK POLICIES (BP) These policies were prepared for use by ADB staff and are not necessarily a complete treatment of the subject. A. Introduction ADDITIONAL FINANCING 1. The

More information

Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved Project Performance

Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved Project Performance Technical Assistance Report Project Number: 47287-001 Capacity Development Technical Assistance (CDTA) December 2013 Republic of Indonesia: Aligning Asian Development Bank and Country Systems for Improved

More information

Country Practice Area(Lead) Additional Financing Pakistan Governance P130941,P130941,P152586

Country Practice Area(Lead) Additional Financing Pakistan Governance P130941,P130941,P152586 Public Disclosure Authorized Independent Evaluation Group (IEG) 1. Project Data Report Number : ICRR0020611 Public Disclosure Authorized Public Disclosure Authorized Project ID P126425 Project Name PK:

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-7230-ME) ON A LOAN IN THE AMOUNT OF US$108 MILLION TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-7230-ME) ON A LOAN IN THE AMOUNT OF US$108 MILLION TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-7230-ME)

More information

Guidelines for Financial Assurance Planning

Guidelines for Financial Assurance Planning For Global Fund Grants Guidelines for Financial Assurance Planning June 2016 Geneva, Switzerland The financial assurance plan provides improvements to the way the Global Fund obtains financial assurance

More information

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47320) ON A LOAN IN THE AMOUNT OF US$ 9.

Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-47320) ON A LOAN IN THE AMOUNT OF US$ 9. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank Report No: ICR00002035 IMPLEMENTATION COMPLETION AND RESULTS

More information

Public Disclosure Copy

Public Disclosure Copy Public Disclosure Authorized EAST ASIA AND PACIFIC Indonesia Social, Urban, Rural and Resilience Global Practice Global Practice IBRD/IDA Investment Project Financing FY 2012 Seq No: 12 ARCHIVED on 08-Dec-2017

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (4410-NE) ON A CREDIT IN THE AMOUNT OF SDR 14.4 MILLION (US$23.7 MILLION EQUIVALENT) TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (4410-NE) ON A CREDIT IN THE AMOUNT OF SDR 14.4 MILLION (US$23.7 MILLION EQUIVALENT) TO THE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank IMPLEMENTATION COMPLETION AND RESULTS REPORT (4410-NE) ON

More information

Public Disclosure Authorized. Report No.:AC634. Project ID: P Project: Health Transition Project. TTL: Enis Baris

Public Disclosure Authorized. Report No.:AC634. Project ID: P Project: Health Transition Project. TTL: Enis Baris Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Integrated Safeguards Data Sheet (ISDS) Section I - Basic Information Date ISDS Prepared/Updated:

More information

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE EMERGENCY SCHOOL CONSTRUCTION AND REHABILITATION PROJECT (ESCRP TF GRANT )

RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING THE EMERGENCY SCHOOL CONSTRUCTION AND REHABILITATION PROJECT (ESCRP TF GRANT ) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Document of The World Bank RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF

More information

World Bank Safeguard Policies: An Overview

World Bank Safeguard Policies: An Overview Forest Carbon Partnership Facility World Bank Safeguard Policies: An Overview Victor Mosoti, Legal Department, World Bank Pan Africa Indigenous Peoples Dialogue Arusha, Tanzania April 19-24, 2012 Overview

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80640) ON A LOAN IN THE AMOUNT OF US$200 MILLION TO THE

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80640) ON A LOAN IN THE AMOUNT OF US$200 MILLION TO THE Public Disclosure Authorized Document of The World Bank Report No: ICR00004191 Public Disclosure Authorized Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IBRD-80640) ON A LOAN

More information

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2770, IDA-H6880, IDA-49520) A GRANT IN THE AMOUNT OF SDR 10 MILLION (US$15.00 MILLION EQUIVALENT),

IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2770, IDA-H6880, IDA-49520) A GRANT IN THE AMOUNT OF SDR 10 MILLION (US$15.00 MILLION EQUIVALENT), Public Disclosure Authorized Document of The World Bank Report No: ICR00003583 Public Disclosure Authorized IMPLEMENTATION COMPLETION AND RESULTS REPORT (IDA-H2770, IDA-H6880, IDA-49520) ON A GRANT IN

More information