1 Subject: GUIDANCE ON THE COMPLETION OF REVISED REVENUE BUSINESS CASE TEMPLATES AND POST PROJECT EVALUATION For Action by: Chief Executive of HSC Bodies and NIFRS Directors of Finance of HSC Bodies and NIFRS Summary of Contents: This circular provides guidance on the completion of revised revenue business case templates and PPE for the Arms Length Bodies of DHSSPS. Circular Reference: HSC (F) 34/2013 Date of Issue: 6 th June 2013 Related documents: DAO(DFP) 06/12 FD(DFP) 20/09 - Northern Ireland Guide to Economic Appraisal and Evaluation (NIGEAE) Superseded Documents: Enquiries: Any enquiries about the contents of this Circular should be addressed to: Catriona O Connor Finance Policy, Accountability & Counter Fraud Unit DHSSPS Room D3 Castle Buildings Stormont Estate Belfast BT4 3SQ Status of Contents: Action Implementation: Immediate Tel: Fax: Catriona.O Connor@dhsspsni.gov.uk

2 GUIDANCE ON THE COMPLETION OF REVISED REVENUE BUSINESS CASE TEMPLATES AND POST PROJECT EVALUATION Introduction 1. The purpose of this circular is to draw the attention of Department s Arm s Length Bodies (i.e. Health and Social Care (HSC) bodies and NIFRS) to the following revised templates: Revenue Business Cases; and Post Project Evaluation (PPE) Economic Appraisal 2. FD(DFP)20/09 draws departments attention to the Northern Ireland Guide to Expenditure Appraisal and Evaluation (NIGEAE), which contains DFP s core guidance on the appraisal, evaluation, approval and management of policies, programmes and projects. 3. The principles of appraisal should be applied, with proportionate effort, to every proposal for spending or saving public money, or proportionate changes in the use of public sector resources. For example, appraisal must be applied irrespective of whether the relevant public expenditure or resources: involve capital or current spending, or both; are large or small; are above or below delegated limits. 4. Appraisal is a systematic process for examining alternative uses of resources. It is designed to assist in defining problems and finding the solutions which offer the best value for money. It is a way of thinking expenditure proposals through, right from the emergence of the need for a project through its implementation, to postproject evaluation. It is the established vehicle for planning and approving

3 projects and other expenditures. Good appraisal leads to better decisions and use of resources. It facilitates good project management and project evaluation. 5. Appraisal is not optional; it is an essential part of good financial management, which is vital to decision-making and crucial to accountability. But it must also be proportionate. 6. It is important to begin applying appraisal early in the gestation of any proposal which has expenditure or resource implications. The justification for incurring any expenditure at all should be considered. Appraisal should be applied from the emergence of a need right through to the recommendation of the most costeffective course of action. It should not be regarded merely as the means to refine the details of a predetermined option. Revenue Business Case Templates 7. A working group consisting of senior finance representatives from across the Department and HSC was set up to examine the processes in place for the preparation and approval of business cases. The group developed a new set of business case templates for revenue expenditure and these were agreed with DFP. 8. The revised templates have different thresholds for expenditure, and have been developed in line with the requirements of NIGEAE, with proportionality in mind. 9. The revised templates, together with guidance on when and how to complete a business case, are attached as follows: Revenue Business Case Proforma (Annex A) Revenue expenditure up to 50k (Annex B) Revenue expenditure greater than 50k up to 250k (Annex C); and Revenue expenditure greater than 250k up to 1m (Annex D).

4 10. The attached templates should be completed for the following types of expenditure for the total life of the project/service: Policy and Programme Development; Significant Expansion to Existing Services; and New Expenditure. 11. NB for normal recurrent / maintaining existing services expenditure, a brief justification is required and template does not need to be completed; although recurrent expenditure does not warrant the perpetual production of business cases, appraisals are required for all new procurements/ contracts in line with procurement practice. There must, however, for any expenditure, always be evidence available to justify that options have been considered and the spend can be justified as representing the most optimum solution that provides value for money. When it comes to small scale and/or simple decisions in the main all that is required would be small scale and simple documentation. You may find it helpful to refer to the NIGEAE guidance on The Appraisal and Evaluation of Small Expenditure at: Post Project Evaluations 12. FD(DFP)20/09 sets out the requirement for the completion of Post Project Evaluations (PPEs). DFP is placing a greater emphasis on the completion of PPEs, and expects all projects to be subject to proper monitoring and control measures including PPEs for all projects, both above and below delegated limits. Such measures can help ensure good VFM by identifying difficulties, preventing the repetition of mistakes, revealing positive points and in particular it is an essential part of PPEs that lessons which may be of use in other projects and/or other Departments are identified and shared.

5 13. Every appraisal (or business case) of any substance should indicate how the proposals concerned will be evaluated after completion and how the results of the evaluation will be disseminated (i.e. shared with colleagues and CoPE). 14. In general, evaluation reports should summarise whether, and if so, why the outturn differed from that foreseen in the appraisal; how effective the activity was in achieving its objectives, and why; the cost-effectiveness of the activity; and what the results imply for future management or policy decisions 15. A revised PPE template has also been developed by the working group at Annex E. Revenue Business Case Database 16. A further recommendation made by the Working Group was that all HSC bodies and Core Department should develop an internal database to record all revenue expenditure business cases submitted each year. It is therefore suggested that you maintain a list of all revenue expenditure appraisals within your business area and this will be used as a sample base for test drilling 2013/14 onwards. Action 17. Against this background, it is therefore recommended that bring this circular to the attention of the appropriate staff within your organisation, noting all action points and documents included within Annexes A E. 18. The revised templates at Annexes A-E should be adopted with immediate effect.

6 Enquiries 19. Should you have any queries please contact Catriona O Connor on or Catriona.O Connor@dhsspsni.gov.uk. PAULA SHEARER Finance Policy, Accountability and Counter Fraud Unit

7 Annex A REVENUE BUSINESS CASE PROFORMA COVER (To be submitted with every business case) Name of organisation Project Title Total Cost Start date Completion date Complete this section if bid is for new funding BID FOR NEW FUNDING Is this bid for new funding (Y/N) How much total funding required? How much funding required per year? Is this funding to be made recurrent? Complete this section if funding available within existing allocation Funding available within existing allocation (Y/N) Total cost of proposal Cost of proposal per year Is this cost within recurrent allocation? Is this business case (a) Standard (b) Novel Contentious (d) Setting a precedent If yes to (b) or (c) or (d), requires Departmental & DFP approval Is Departmental / DFP approval required Y/N

8 Approvals & submissions Prepared by Name Printed (signed) Grade/ Title Date Approved by Name printed (signed) Grade / Title Date Insert more boxes if further approvals are required by officials Complete this section if Department / DFP approval required Date submitted to Department Department/ DFP approval (y/n) Date approved

9 Annex B BUSINESS CASE TEMPLATE REVENUE FUNDING up to 50,000 GUIDANCE NOTES This template should be completed for the following types of expenditure for the total life of the project/service: Policy and Programme Development; Significant Expansion to Existing Services; and New Expenditure. NB for normal recurrent/ maintaining existing services expenditure, a brief justification is required and template does not need to be completed; Although recurrent expenditure does not warrant the perpetual production of business cases, appraisals are required for all new procurements/ contracts in line with procurement practice. There must, however for any expenditure always be evidence available to justify that options have been considered and the spend can be justified as representing the most optimum solution that provides value for money. When it comes to small scale and/or simple decisions in the main all that is required would be small scale and simple documentation. You may find it helpful to refer to the NIGEAE guidance on The Appraisal and Evaluation of Small Expenditure on GUIDANCE NOTES This investment proposal template should be prepared in line with NIGEAE Guidance - see Template is to be used for all revenue expenditures up to 50k. Please complete this template with proportional effort, i.e. detail provided should be commensurate with the size of the bid. This is a general template and that the boxes and tables may be enlarged or modified to suit the particulars of the case in hand. When necessary, refer to the NIGEAE website Section 1: Strategic Context and Need: Briefly explain the background to the proposal including its relevance to your organisation/ Gov /or Departmental strategic aims and policy objectives. Identify the key stakeholders and explain their commitment and any outstanding issues. Explain the nature of the needs or demands that are to be addressed, and detail any deficiencies in existing service provision.

10 Section 2: Objectives: Objectives must be stated so that it is clear what proposals are intended to achieve Explain and list the project objectives in specific measureable terms. Specify targets that are SMART i.e. Specific,Measureable, Achievable, Relevant and Time dependent Include implementation targets/ outcomes/ outputs if possible e.g. dates, milestones, etc e.g. Achieve X outputs by 31 March 20XX, XX staff in place by 31 March 20XX etc. Section 3: Identify and Describe Options: Identify and briefly describe all options, including status quo. Status quo means to continue with existing arrangements or maintain services as close as possible to existing levels. Requirement is that at least 2 options considered including status quo. Identify and evaluate the benefits of all the options considered. Section 4: Project Costs: Provide details of total cost of project over total life of the project for all options. Provide details of any assumptions made in formulating costs. State if funding is recurrent funding going forward or is this a one-off project with a life of XX years? Section 5: Non-Monetary Benefits Briefly list and describe the benefits of preferred option (benefits will relate closely to the objectives) Section 6: Project Risks Identify and describe the risks that the project may face. Section 7: Preferred option and Explanation for Selection Identify which option is preferred and why, in terms of assumptions, costs, non monetary benefits, risks, constraints and other factors etc Section 8: Monitoring and Evaluation Indicate how the proposed option will be monitored during and after implementation. Indicate factors to be evaluated, when, how and by whom. The following additional information is required for Trusts submitting business cases to HSCB only. Section 9: Changes to SBA activity for the preferred option The purpose of this section is to record the current baseline activity in appropriate currencies and to specify the additional activity that will be provided for this investment, and the new SBA volumes. If approved the additional activity will be added to the volumes in the organisation s SBA.

11 The associated baseline costs and additional costs must be shown in the financial appendix. Examples: Approval of a stationary budget is deemed suitable justification for expenditure on a stationary order and therefore you would not be required to complete this template. This is considered to be business as usual and therefore you would not be required to complete a business case for such items that are covered within approved budgets. The need for a business case would arise only if there was a change in policy or a contract was coming to an end. For example a move from oil to gas heating or something to that effect then there would be a need to examine the options.

12 BUSINESS CASE TEMPLATE REVENUE FUNDING up to 50,000 SECTION 1: STRATEGIC CONTEXT AND NEED SECTION 2: OBJECTIVES SECTION 3: LIST AND DESCRIBE AT LEAST 2 OPTIONS (INCLUDING STATUS QUO) OPTION NO. BRIEF DESCRIPTION OF OPTION 1 ( Status quo) 2 3 (if applicable) SECTION 4: PROJECT COSTS Option Year 1 ( 000) 1 Status Quo continue with existing arrangements 2 Year 2 ( 000) Year 3 ( 000) Total ( 000) 3

13 [Cost Assumptions - expand as appropriate] SECTION 5: NON-MONETARY BENEFITS SECTION 6: PROJECT RISKS SECTION 7: PREFERRED OPTION AND EXPLANATION FOR SELECTION SECTION 8: MONITORING AND EVALUATION Who will manage the implementation? Who will monitor and evaluate the outcomes? When will this take place?

14 SECTION 9: ACTIVITY OUTCOMES (TRUSTS ONLY) Baseline Additional activity New Baseline Activity Specifiy activity, e.g. IP, DC OPN, OPR, Contacts etc IP DC OPN OPR

15 Annex C BUSINESS CASE TEMPLATE REVENUE FUNDING 50k - 250k GUIDANCE NOTES This template should be completed for the following types of expenditure for the total life of the project/service: Policy and Programme Development; Significant Expansion to Existing Services; and New Expenditure. NB for normal recurrent / maintaining existing services expenditure, a brief justification is required and template does not need to be completed; Although recurrent expenditure does not warrant the perpetual production of business cases, appraisals are required for all new procurements/ contracts in line with procurement practice. There must, however for any expenditure always be evidence available to justify that options have been considered and the spend can be justified as representing the most optimum solution that provides value for money. When it comes to small scale and/or simple decisions in the main all that is required would be small scale and simple documentation. You may find it helpful to refer to the NIGEAE guidance on The Appraisal and Evaluation of Small Expenditure on GUIDANCE NOTES This investment proposal template should be prepared in line with NIGEAE Guidance - see Template is to be used for all revenue expenditures greater than 50k up to 250k. Please complete this template with proportional effort, i.e. detail provided should be commensurate with the size of the bid. This is a general template and that the boxes and tables may be enlarged or modified to suit the particulars of the case in hand. When necessary, refer to the NIGEAE website Section 1: Strategic Context and Need: Briefly explain the background to the proposal including its relevance to your organisation/ Gov /or Departmental strategic aims and policy objectives. Identify the key stakeholders and explain their commitment and any outstanding issues. As specifically as possible, explain the nature of the needs or demands that are to be addressed, and detail any deficiencies in existing service provision. Include suitable quantification of needs/demands/deficiencies where possible.

16 Section 2 (a): Objectives: Objectives must be stated so that it is clear what proposals are intended to achieve Explain and list the project objectives in specific measureable terms. Specify targets that are SMART i.e. Specific, Measureable, Achievable, Relevant and Time dependent. It is particularly important that objectives are measurable - otherwise it will not be possible to gauge whether or how well they have been achieved. Include implementation targets / outcomes/ outputs if possible e.g. dates, milestones, etc e.g. Achieve X outputs by 31 March 20XX, XX staff in place by 31 March 20XX etc. Section 2 (b): Constraints: State the key constraints on the project, e.g. technical issues, timing issues, legal requirements, professional standards, planning constraints, policy commitments and so on. Section 3: Identify and Describe Options: Identify and briefly describe all options, including status quo. Status quo means to continue with existing arrangements or maintain services as close as possible to existing levels. Requirement is that at least 2 options considered including status quo, giving reasons if only 1 alternative option other than status quo considered. Identify and evaluate the benefits of all the options considered. Section 4: Project Costs: Provide details of total cost of project over total life of the project for all options. Provide details of any assumptions made in formulating costs. State if funding is recurrent funding going forward or is this a one-off project with a life of XX years? NPV analysis should be included for revenue projects spanning more than 5 years, or those revenue projects that have differing cash flows over the time period. Decision to include should be made on a case by case basis. If NPV required use table per template for larger business cases. Sensitivity - should be included for projects spanning more than 5 years, or where a change in a variant would significantly change the outcome. Decision to include should be made on a case by case basis. Section 5: Non-Monetary Benefits: Briefly list and describe the benefits of preferred option (benefits will relate closely to the objectives) Section 6: Project Risks & Uncertainities Identify and describe the risks that the project may face. Explain how these compare under the various options.

17 Section 7: Preferred option and Explanation for Selection: Identify which option is preferred and why, in terms of assumptions, costs, non monetary benefits, risks, constraints and other factors etc Section 8: Affordability and Funding Requirements: Detail what funding is available / how it will be funded and whether it will be recurrent funding. Section 9: Management Arrangements: Describe from start to finish of project who will be responsible at each stage eg planning timetable, obtaining finance, procurement, legal issues, accommodation staff, consultancy, TUC issues, security, training, documentation of project progress etc. Section 10: Monitoring and Evaluation: Indicate how the proposed option will be monitored during and after implementation. Indicate factors to be evaluated, when, how and by whom. The following additional information is required for Trusts submitting business cases to HSCB only. Section 11: Changes to SBA activity for the preferred option The purpose of this section is to record the current baseline activity in appropriate currencies and to specify the additional activity that will be provided for this investment, and the new SBA volumes. If approved the additional activity will be added to the volumes in the organisation s SBA. The associated baseline costs and additional costs must be shown in the financial appendix. Section 12: Benchmarking evidence to support preferred option. The purpose of this section is to provide evidence that the preferred option compares favourably to Trust specialty costs, Trust HRGs, Reference costs, PbR tariffs, Best practise tariffs, Community indicators or other recognised benchmarks Examples: Approval of a stationary budget is deemed suitable justification for expenditure on a stationary order and therefore you would not be required to complete this template. This is

18 considered to be business as usual and therefore you would not be required to complete a business case for such items that are covered within approved budgets. The need for a business case would arise only if there was a change in policy or a contract was coming to an end. For example a move from oil to gas heating or something to that effect then there would be a need to examine the options.

19 BUSINESS CASE TEMPLATE REVENUE FUNDING 50k - 250k SECTION 1: PROJECT BACKGROUND, STRATEGIC CONTEXT & NEED SECTION 2 (a): OBJECTIVES 1. Project Objectives Measurable Targets [add more objectives as appropriate] SECTION 2 (b) : CONSTRAINTS SECTION 3: IDENTIFY AND DESCRIBE OPTIONS OPTION NO. BRIEF DESCRIPTION OF OPTION 1 Status Quo - continue with existing arrangements 2 3 (if applicable)

20 SECTION 4: PROJECT COSTS 1 Option Year 1 ( 000) Year 2 ( 000) Year 3 ( 000) Total ( 000) 2 3 COST ASSUMPTIONS: SECTION 5: NON-MONETARY BENEFITS SECTION 6: PROJECT RISKS & UNCERTAINITIES SECTION 7: PREFERRED OPTION AND EXPLANATION FOR SELECTION

21 SECTION 8: AFFORDABILITY AND FUNDING REQUIREMENTS AFFORDABILITY STATEMENT Required Capital required Revenue required Existing budget : Capital Revenue Additional Allocation Required: Capital Revenue Yr s Yr s Yr s Yr s Totals 000 s AFFORDABILITY ASSUMPTIONS SECTION 9: MANAGEMENT ARRANGEMENTS SECTION 10: MONITORING AND EVALUATION Who will manage the implementation? Who will monitor and evaluate the outcomes? What other factors will be monitored and evaluated? When will this take place?

22 SECTION 9: ACTIVITY OUTCOMES (TRUSTS ONLY) Baseline Additional activity New Baseline Activity Specifiy activity, e.g. IP, DC OPN, OPR, Contacts etc IP DC OPN OPR SECTION 12: BENCHMARKING EVIDENCE TO SUPPORT PREFERRED OPTION [expand as necessary]

23 Annex D BUSINESS CASE TEMPLATE REVENUE FUNDING 250k - 1m GUIDANCE NOTES This template should be completed for the following types of expenditure for the total life of the project/service: Policy and Programme Development; Significant Expansion to Existing Services; and New Expenditure. NB for normal recurrent/ maintaining existing services expenditure, a brief justification is required and template does not need to be completed; Although recurrent expenditure does not warrant the perpetual production of business cases, appraisals are required for all new procurements/ contracts in line with procurement practice. There must, however for any expenditure always be evidence available to justify that options have been considered and the spend can be justified as representing the most optimum solution that provides value for money. When it comes to small scale and/or simple decisions in the main all that is required would be small scale and simple documentation. You may find it helpful to refer to the NIGEAE guidance on The Appraisal and Evaluation of Small Expenditure on GUIDANCE NOTES This investment proposal template should be prepared in line with the NIGEAE Guidance - see Template is to be used for all revenue expenditures > 250k up to 1m. It can be used as a basis for expenditures > 1m, but more detail/ analysis will be required commensurate with the size of the bid. Please refer to NIGEAE when completing business case > 1m Please complete this template with proportional effort, i.e. detail provided should be commensurate with the size of the bid. This is a general template and that the boxes and tables may be enlarged or modified to suit the particulars of the case in hand. When necessary, refer to the NIGEAE website Section 1 (a) : Project Background and Strategic Context Explain the background to the proposal including its relevance to your organisation/ NI Government or Departmental strategic aims and policy objectives. Identify the key stakeholders and explain their commitment and any outstanding issues.

24 Section 1 (b): Need As specifically as possible, explain the nature of the needs or demands that are to be addressed, and detail any deficiencies in existing service provision. Include suitable quantification of needs/demands/deficiencies where possible. Provide historical service activity (previous years), for eg, hospital caseload, evidence of service/equipment failure, service risk rating etc., along with service projections for the next 3 years where appropriate. Section 2 (a) : State Objectives Objectives must be stated so that it is clear what proposals are intended to achieve. These should be consistent with statements of government policy, departmental or agency objectives, departmental Public Service Agreements Specify targets that are SMART i.e. Specific Measureable Achievable, Relevant and Time dependent. It is particularly important that objectives are measurable - otherwise it will not be possible to gauge whether or how well they have been achieved. Include quantifiable targets/ outcomes/ outputs where possible e.g. Achieve X outputs by 31 March 20XX, XX staff in place by 31 March 20XX etc. Where there are numerous objectives, or there is a potential conflict between objectives, it is helpful to indicate their relative priority, both to inform option assessment and to assist in post project evaluation. Section 2 (b) : State Constraints Identify any likely constraints to the project e.g. technical issues, timing issues, legal requirements, professional standards, planning constraints, policy commitments and so on. Section 3: Identify and Shortlist the Options Consider alternative ways to meet the objectives e.g. variations in scale, quality, technique, location, timing etc. Start with an initial long list of options and sift them to provide a shortlist. Record all the options considered and the reasons for rejecting those not shortlisted. The shortlist of options should include a baseline Status Quo or Do Minimum option and a suitable number of alternative Do Something options (usually at least two). The status quo should normally be short-listed and appraised even where it is not considered to be a realistic option Its function is to provide a benchmark so that the VFM of the alternative 'do something' options may be judged by reference to current service provision. The exception to this requirement is where the appraisal concerns the introduction of a wholly new service, that is, where there is no existing provision to appraise.

25 Section 4: Monetary Costs and Benefits of Options Appraisals should include all the costs and benefits to Northern Ireland arising from the project, not just those to a particular organisation or sector e.g. all costs and benefits to the public, private and third sectors should be included. Costs and benefits should be valued in economic cost terms, which are generally reflected by using current market prices. All the assets and other resources employed by each option should be costed, even if they have already been purchased. This is because they have an opportunity cost value i.e. if not used in this project they could be put to an alternative use. Calculate the Net Present Value (NPV) for each option where cash flows of options differ over the time period or when a project spans greater than 5 years. However decision whether or not include NPV should be considered on a case by case basis. Use the NPC spreadsheet at the NIGEAE website and append the NPC calculation for each option to the pro forma. In the simplest cases, the table in Section 4 may be used instead. Create a table for each option, adjusting the no. of columns to reflect the years of the project s life. Treat the current financial year as Year 0. Set out the expected annual revenue costs for each option. Express the figures in real terms i.e. held constant at today s prices. The checklist of typical costs at the NIGEAE website should help identify relevant costs. Financial savings arising from an option will be reflected in its lower costs compared to the Status Quo. Do not double count by also including them separately as benefits. Other monetised benefits may be taken into account but are likely to be rare in small expenditure cases. Most benefits will be covered in the non-monetary Section 5 below. For particularly uncertain cost assumptions, consider using sensitivity analysis to illustrate how NPCs and option rankings are affected by varying these assumptions. For more in-depth guidance, see Step 5 and Step 8 of NIGEAE. Section 5: Non-Monetary Costs and Benefits List and describe the benefits of each option (benefits will relate closely to the objectives), Either the weighted scoring method can be used or impact assessment, depending on which is appropriate. The weighted scoring method. This involves assigning numerical weights to each factor to reflect its comparative importance; scoring the performance of each option against each factor on a numerical scale; and calculating a 'weighted score' for each option. Detailed guidance on the use of this approach is given in The Weighting and Scoring Method. Impact Assessment. This method tabulates the impact of each option upon each non-monetary factor in an impact statement or performance matrix. It involves

26 assessing the impact of each option upon each relevant objective or assessment criterion. The presentation is often in tabular form, with the cells of the table containing suitable quantitative impact measures or indicators; and/or qualitative impact analysis. An accompanying commentary summarising the main trade-offs and other features of the analysis should generally be provided. Explain rationale for weighting and scoring. Section 6: Assess Risks and Uncertainties Identify and describe the risks that the project may face. Explain how these compare under the various options using the table below. Identify measures to ensure that each risk is appropriately managed and mitigated. Explain any contingency allowances included for risks in the option costings.. For further guidance see Step 6 of NIGEAE. Section 7: Preferred Option and explanation for selection Summarise the main differences between the options e.g. in terms of key assumptions, NPCs, non-monetary impacts, risks and other factors. Identify which option is preferred and explain why. Section 8: Assess Affordability and Funding Arrangements Set out the annual capital and resource requirements for the preferred option. Figures should allow for inflation, contingencies and (where relevant) optimism bias. Resource figures should include appropriate allowance for depreciation/impairment. Identify expected sources of funding and the degree to which each funder is committed. Section 9: Project Management Explain the proposed project management structure (e.g. use of PRINCE2), key management personnel and project timetable. Where relevant, indicate the proposed approach to procurement. Consider provision for benefits management and realisation, including e.g. documentation of Benefit Profiles using the templates at the Successful Delivery NI website. A benefits profile is attached at Annex B Identify any significant management issues e.g. legal, contractual, accommodation, staff or TUS issues. Is any external consultancy support required? If so, it must be supported by a separate business case as per FD(DFP)07/12 and section 5 of the accompanying guidance note. Section 10: Monitoring, and Evaluation Arrangements Indicate arrangements for regular monitoring of the project s progress.

27 State proposed evaluation arrangements e.g. when it will happen, who will do it, what factors will be evaluated? For further guidance see para at Step 9 of NIGEAE Appendix A: Benefits Profile Benefit Owner: This is the name of the actual benefit owner, not the person responsible for reporting on it. This might be the SRO, but could also be someone else senior in the organisation; Baseline Value: The Baseline value can be estimated at OBC stage (This should be firmed up and accurate by the time the business case reaches FBC if applicable); Target Value: Insert the target value you hope to attain for the benefit Measurement: Explain how and when you hope to measure and report on the benefit; Timing: Details of how often you intend to report on the realisation of the benefits; Responsibility: Who has responsibility for measuring and reporting on the benefit. For large expenditure decisions were FBC is required, i.e. > 1m, please complete the benefit profile as detailed at the following link:

28 BUSINESS CASE TEMPLATE REVENUE FUNDING 250k - 1m SECTION 1(a): PROJECT BACKGROUND AND STRATEGIC CONTEXT SECTION 1(b): DEMONSTRATE THE NEED FOR THE PROJECT

29 SECTION 2(a): OBJECTIVES Project Objectives Measurable Targets [add more objectives as appropriate] SECTION 2(b): CONSTRAINTS Constraints 1. Measures to address constraints [add more constraints as appropriate] SECTION 3: IDENTIFY AND SHORTLIST OPTIONS Option Number/ Description Shortlisted (S) or Rejected (R) Reason for Rejection 1. Status Quo - continue with existing arrangements S (if applicable)

30 SECTION 4: MONETARY COSTS AND BENEFITS OF OPTIONS Option 1: Status Quo Yr 0 Yr 1 Yr 2 Yr 3 Yr 4 Yr 5.. Totals Capital Costs (a) Total Capital Cost Revenue Costs Include details (b) Total Revenue Cost (c) Total Cost = (a) + (b) (d) Disc 3.5%pa (e) NPC = (c) x (d) COST ASSUMPTIONS: (Expand as appropriate) SECTION 5: NON MONETARY COSTS AND BENEFITS Weighting method Non-Monetary Factor etc Weighting (%) Score Option 1 Score Option 2 Score Option 3 Total 100%

31 Or Impact assessment Non-Monetary Factor Option 1 Option 2 Option etc Rationale for weighting and scoring SECTION 6: ASSESS RISKS AND UNCERTAINTIES Risk Description Likely impact of Risk H/M/L Opt 1 Opt 2 Opt 3 Opt 4 State how the options compare and identify relevant risk management / mitigation measures Overall Risk (H/M/L):

32 SECTION 7: PREFERRED OPTION AND EXPLANATION FOR SELECTION SECTION 8: ASSESS AFFORDABILITY AND FUNDING ARRANGEMENTS Required: Capital Resource Existing Budget: Capital Resource Additional budget Required: Capital Resource Yr s Yr s Yr s Yr s Totals 000 s Affordability narrative [expand as necessary] SECTION 9: PROJECT MANAGEMENT (Please see Benefits Realisation Plan in Annex B) [expand as necessary]

33 SECTION 10: MONITORING AND EVALUATION [expand as necessary]

34 Revenue Expenditure 250k - 1m - APPENDIX A Benefit Profile (Small Projects) Signed off by: Date: Benefit Owner Benefit Baseline value Target Value Measurement Timing Responsibility

35 Annex E POST PROJECT EVALUATION GUIDANCE NOTES This Post-Project Evaluation (PPE) template should be prepared in line with NIGEAE Guidance see To be completed for all Revenue Business Cases Please complete this template with proportionate effort, i.e. detail provided should be commensurate with the size of the bid. This is a general template and the boxes and tables may be enlarged or modified to suit the particulars of the case in hand. When necessary, refer to the NIGEAE website The purpose of a PPE is to: Evaluate the effectiveness of a project in realising the proposed benefits as outlined in the Business Case; Compare planned costs and benefits with actual costs and benefits to allow an assessment of the project's overall value for money to be made; Identify particular aspects of the project which have affected benefits either positively or negatively; recommendations for future projects can then be derived; and Reveal opportunities for increasing the project's yield of benefits, whether they were planned or became apparent during or after implementation, and to recommend the actions required to achieve their maximisation. 1.0 Background Please provide a brief description of the project, its objectives, and an outline of its progress, identifying those who played major roles, e.g. SRO, Project Manager, Senior User. Please provide details of how the PPE has been carried out (i.e. methodology used to ascertain if objectives have been met) and record any constraints that were met in carrying out the PPE. Please provide details of when the project started, giving explanations for any lag. 2.0 Achievement of Objectives Please list objectives as set out in business case and advise how they have been achieved. Look at project outcomes and state how and why outcome(s) differed (if at all) from those set out in the business case and project plan.

36 3.0 Benefits and Outcomes Include a summary of how fully the claimed benefits/outcomes were realised. Any benefits which have emerged from the use of the system which were not predicted in the Business Case should be outlined. Include comment on whether the costing assumptions and estimates of targeted benefits made at the project's inception proved realistic; a comparison of estimated and actual cost savings and efficiency improvements. Any dis-benefits, expected or unexpected, should be outlined, along with an estimate of their impact on the business. 4.0 Value for Money Provide an assessment (based on achievement of objectives and any variances noted as per above) of whether the project represented good value for money. 5.0 Recommendations and Lessons Learned This section should include lessons to be learned, covering all aspects of the project which relate to the realisation of benefits. Lessons may refer to the identification, quantification or planning of benefits, to project management, to user monitoring and control of benefit onset etc. PPEs should be used to promote good practice and the results should be shared to ensure that key lessons are identified and disseminated; It should also identify actions which have the potential to increase the benefits to be reaped from the project. These recommendations should be based on consideration of how to enhance both expected and unexpected benefits, how to minimise the effects of dis-benefits, and how to develop further, if possible, the beneficial use of systems or services delivered. Any broader lessons which may be learnt from the project should be outlined, including problems encountered and how they were mitigated. If they are felt to be necessary, further monitoring, specific benefit reviews or full PPEs should be recommended. Recommendations for the circulation of the PPE report should be made. 6.0 Timeframe for completion PPE should be planned before project closure; It should be conducted 4 to 12 months after project closure, led by an individual independent of the Project Board and Project Team. Any reasons for delay in submission of a completed PPE should be clearly specified.

37 POST PROJECT EVALUATION Name of organisation Project Title Total Cost Start date Completion date PPE Due Date SECTION 1: INTRODUCTION Background (a brief description of the project and its objectives) Please give details of commencement of scheme, when staff were appointed and when full capacity was achieved. SECTION 2: ACHEIVEMENT OF OBJECTIVES Did this Investment meet objectives given in IPT? Please give details. How they were achieved? Objectives [add more objectives as appropriate]

38 SECTION 3: BENEFITS AND OUTCOMES Outcomes planned in original Business Case Actual Outcomes (Please comment on variances or delays etc.) [add more outcomes as appropriate] How were benefits and outcomes evidenced? Please give details of such. SECTION 4: VALUE FOR MONEY What methodology was used to assess quality and value for money of service provided? What were the conclusions? SECTION 5: RECOMMENDATIONS AND LESSONS LEARNED What problems were encountered during implementation of the project, and how where such resolved? What was learned, how has this been disseminated, and to whom? Please provide supporting evidence.

39

Public Private Partnerships in the National Health Service: The Private Finance Initiative

Public Private Partnerships in the National Health Service: The Private Finance Initiative Public Private Partnerships in the National Health Service: The Private Finance Initiative Good Practice Section 3: Technical Issues Contents 1. Introduction 3 2. Risk analysis 4 3. The Public Sector Comparator

More information

COMMON APPRAISAL FRAMEWORK FOR TRANSPORT PROJECTS AND PROGRAMMES

COMMON APPRAISAL FRAMEWORK FOR TRANSPORT PROJECTS AND PROGRAMMES COMMON APPRAISAL FRAMEWORK FOR TRANSPORT PROJECTS AND PROGRAMMES March 2016 OVERVIEW OF 2016 COMMON APPRAISAL FRAMEWORK This guidance document replaces the 2009 Guidelines on a Common Appraisal Framework

More information

Lisburn Primary and Community Care Project

Lisburn Primary and Community Care Project Lisburn Primary and Community Care Project Appointment Business Case DRAFT v0.2 Section 1 Executive Summary 0 Contents 1 Executive Summary... 1 Introduction... 1 Project Background... 1 Section 2: Update

More information

Section 1 OVERVIEW OF PROJECT DEVELOPMENT PROCESS

Section 1 OVERVIEW OF PROJECT DEVELOPMENT PROCESS Section 1 OVERVIEW OF PROJECT DEVELOPMENT PROCESS 1.1 Introduction Before the Sanctioning Authority can consider approving expenditure proposals, certain analysis needs to be carried out and presented

More information

PROJECT BUSINESS PLAN RURAL DEVELOPMENT PROGRAMME PRIORITY 6: SOCIAL INCLUSION, POVERTY REDUCTION AND RURAL DEVELOPMENT

PROJECT BUSINESS PLAN RURAL DEVELOPMENT PROGRAMME PRIORITY 6: SOCIAL INCLUSION, POVERTY REDUCTION AND RURAL DEVELOPMENT Appendix 6E PROJECT BUSINESS PLAN RURAL DEVELOPMENT PROGRAMME 2014-2020 PRIORITY 6: SOCIAL INCLUSION, POVERTY REDUCTION AND RURAL DEVELOPMENT SCHEMES BASIC SERVICES, VILLAGE RENEWAL AND RURAL BROADBAND

More information

NEPAD/Spanish Fund for African Women s empowerment

NEPAD/Spanish Fund for African Women s empowerment NEPAD/Spanish Fund for African Women s empowerment Project Proposal Format Annex 0 1 P age Proposal Format Proposal Cover Page: PROPOSAL TO THE NEPAD- SPANISH FUND FOR AFRICAN WOMEN s EMPOWERMENT Organization

More information

Page Paragraph Content Introduction 4 DEL 5 Expenditure not proposed in the budget 6-7 Procurement

Page Paragraph Content Introduction 4 DEL 5 Expenditure not proposed in the budget 6-7 Procurement Page Paragraph Content 3 1-3 Introduction 4 DEL 5 Expenditure not proposed in the budget 6-7 Procurement 4 8-10 Competition 11 Best value for money 12 Timeliness in paying bills 13 Novel, contentious or

More information

Finance Committee. Inquiry into methods of funding capital investment projects. Submission from Audit Scotland

Finance Committee. Inquiry into methods of funding capital investment projects. Submission from Audit Scotland Finance Committee Inquiry into methods of funding capital investment projects Submission from Introduction is the public sector audit agency covering the external audit of the majority of public sector

More information

BASE CAPEX PROPOSAL - QUALITATIVE INFORMATION

BASE CAPEX PROPOSAL - QUALITATIVE INFORMATION SCHEDULE F BASE CAPEX PROPOSAL - QUALITATIVE INFORMATION cl. 7.3.1, 9.1.1 F1 Qualitative information required in a base capex proposal For the purpose of clause 7.3.1 (1) a base capex proposal must, in

More information

RESERVE BANK OF MALAWI

RESERVE BANK OF MALAWI RESERVE BANK OF MALAWI GUIDELINES ON INTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS (ICAAP) Bank Supervision Department March 2013 Table of Contents 1.0 INTRODUCTION... 2 2.0 MANDATE... 2 3.0 RATIONALE...

More information

PRINCE2 - Business Case

PRINCE2 - Business Case Created/updated 05/11/17 PRINCE2 - Business Case Downloaded from stakeholdermap.com. Visit Prince2 Templates for more Prince2 downloads. Get a Business Case Mind Map Project Name:

More information

UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DECISION MAKING PROCESS

UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DECISION MAKING PROCESS UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DECISION MAKING PROCESS Document Status: Approving Body: Last Update: Author: Approved Information Services Committee

More information

Integrated Capital Planning Manual

Integrated Capital Planning Manual 0 Integrated Capital Planning Manual August 2017 0 Contents Introduction... 1 Annual Integrated Capital Planning Cycle... 3 Integrated Capital Plan Submission... 8 Business Case Guide and Template... 11

More information

Solvency II Detailed guidance notes for dry run process. March 2010

Solvency II Detailed guidance notes for dry run process. March 2010 Solvency II Detailed guidance notes for dry run process March 2010 Introduction The successful implementation of Solvency II at Lloyd s is critical to maintain the competitive position and capital advantages

More information

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS

SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS Incorporating amendments by Scottish Futures Trust (Proposals for Decision Points 2 5 Only) Executive summary... 1 Section 1: Introduction

More information

INTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS GUIDELINE. Nepal Rastra Bank Bank Supervision Department. August 2012 (updated July 2013)

INTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS GUIDELINE. Nepal Rastra Bank Bank Supervision Department. August 2012 (updated July 2013) INTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS GUIDELINE Nepal Rastra Bank Bank Supervision Department August 2012 (updated July 2013) Table of Contents Page No. 1. Introduction 1 2. Internal Capital Adequacy

More information

OVERVIEW OF DETAILED APPRAISAL PROCESS

OVERVIEW OF DETAILED APPRAISAL PROCESS Section 3 OVERVIEW OF DETAILED APPRAISAL PROCESS 3.1 Introduction The detailed appraisal stage aims to provide a basis for a decision on whether to proceed with a project in principle or not. It includes

More information

PRINCE2-PRINCE2-Foundation.150q

PRINCE2-PRINCE2-Foundation.150q PRINCE2-PRINCE2-Foundation.150q Number: PRINCE2-Foundation Passing Score: 800 Time Limit: 120 min File Version: 6.0 Exam PRINCE2-Foundation Version: 6.0 Exam A QUESTION 1 What process ensures focus on

More information

PRINCE2 Sample Papers

PRINCE2 Sample Papers PRINCE2 Sample Papers The Official PRINCE2 Accreditor Sample Examination Papers Terms of use Please note that by downloading and/or using this document, you agree to comply with the terms of use outlined

More information

Implementing IFRS 15 Revenue from Contracts with Customers A practical guide to implementation issues for the aerospace and defence industry

Implementing IFRS 15 Revenue from Contracts with Customers A practical guide to implementation issues for the aerospace and defence industry Implementing IFRS 15 Revenue from Contracts with Customers A practical guide to implementation issues for the aerospace and defence industry Contents About this guide 1 Overview 2 Scope and core principle

More information

Prince2 Foundation.exam.160q

Prince2 Foundation.exam.160q Prince2 Foundation.exam.160q Number: Prince2 Foundation Passing Score: 800 Time Limit: 120 min PRINCE2 Foundation PRINCE2 Foundation written Exam Sections 1. Volume A 2. Volume B Exam A QUESTION 1 Which

More information

South East Local Enterprise Partnership Business Case Review Pro-Forma: Strategic Case

South East Local Enterprise Partnership Business Case Review Pro-Forma: Strategic Case INDEPENDENT TECHNICAL EVALUATION (GATE 1 & 2) Scheme Name: Date Completed: Completed By: South East Local Enterprise Partnership Business Case Review Pro-Forma: Strategic Case Question Value / Source R/A/G

More information

2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias

2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias 2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias 2.6.1 In appraisals, there is always likely to be some difference between what is expected and what eventually happens, because of biases unwittingly

More information

Project Sponsor Group Handbook

Project Sponsor Group Handbook VERSION 6 UNIVERSITY OF OXFORD Project Sponsor Group Handbook May 2015 Project Sponsor Group Handbook, Version 6, 01/05/15 CONTENTS 1. INTRODUCTION... 3 2. CONTEXT... 4 3. PROJECT SPONSOR GROUP MEMBERSHIP...

More information

HSC Business Services Organisation Board

HSC Business Services Organisation Board Paper BSO 25/2009 HSC Business Services Organisation Board Risk Management 1. Purpose of this report The purpose of this report is to brief the Board on the BSO Risk Management process. 2. Background HSC

More information

Braindumps.PRINCE2-Foundation.150.QA

Braindumps.PRINCE2-Foundation.150.QA Braindumps.PRINCE2-Foundation.150.QA Number: PRINCE2-Foundation Passing Score: 800 Time Limit: 120 min File Version: 29.1 http://www.gratisexam.com/ I was a little apprehensive at first about an online

More information

Project Administration Instructions

Project Administration Instructions Project Administration Instructions PAI 6.07A Page 1 of 4 PROJECT COMPLETION REPORT FOR SOVEREIGN OPERATIONS 1 A. Objective and Scope 1. The main objective of a project completion report (PCR) 1 is to

More information

UN-Habitat Policy For Implementing Partners. UN-Habitat. Policy For. Partners

UN-Habitat Policy For Implementing Partners. UN-Habitat. Policy For. Partners UN-Habitat Policy For Implementing Partners 01 Version Date Author/Reviewer Status V1 06.12.2016 Mohamed Robleh Circulated for SMB comments V2 27.01.2017 Andrew Cox Approved For further information, please

More information

Appendix 2 CLAIMS MANAGEMENT POSITIONAL STATEMENT. Introduction

Appendix 2 CLAIMS MANAGEMENT POSITIONAL STATEMENT. Introduction CLAIMS MANAGEMENT POSITIONAL STATEMENT Appendix 2 Introduction 1 This report provides the Board with a statement of current ongoing claims, both personal injury and clinical negligence brought against

More information

Module. Governor Training Materials. Financial management.

Module. Governor Training Materials. Financial management. Governor Training Materials Module Financial management Further Education Funding Council June 2000 www.fefc.ac.uk/documents/othercouncilpublications Financial management Module For suggestions on how

More information

3Ts Hospital Redevelopment Programme Full Business Case

3Ts Hospital Redevelopment Programme Full Business Case 3Ts Hospital Redevelopment Programme Full Business Case Economic Case February 2016, v13 Contents Introduction... 4 The FBC Economic Case - Requirements... 4 The OBC Economic Case Conclusion... 4 Changes

More information

Doing the right projects how the five case model can help

Doing the right projects how the five case model can help Doing the right projects how the five case model can help 1 Agenda JL 1. Characteristics of the right projects. 2. The five case model and the development of the business case. 3. Identifying the right

More information

Strategic Business Case. Estates Guidance and Activity DataBase

Strategic Business Case. Estates Guidance and Activity DataBase Strategic Business Case Estates Guidance and Activity DataBase November 2016 You may re-use the text of this document (not including logos) free of charge in any format or medium, under the terms of the

More information

IPP TRANSACTION ADVISOR TERMS OF REFERENCE

IPP TRANSACTION ADVISOR TERMS OF REFERENCE IPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services to the Government of [ ] for the [insert description of the project] (the Project ). Contents 1. Introduction

More information

Policy and Procedures

Policy and Procedures Procurement Policy and Procedures Page 1 of 23 Document Version Control Version Description Date Approval Number 0.1 for Discussion to P&R 01/04/2003 P&R noted 0.2 for Discussion to P&R 30/04/2003 P&R

More information

POLICY AND GUIDELINES ON THE ACCEPTANCE OF, AND EXPENDITURE ON, GIFTS AND HOSPITALITY

POLICY AND GUIDELINES ON THE ACCEPTANCE OF, AND EXPENDITURE ON, GIFTS AND HOSPITALITY POLICY AND GUIDELINES ON THE ACCEPTANCE OF, AND EXPENDITURE ON, GIFTS AND HOSPITALITY Revised March 2016 D110316 POLICY AND GUIDELINES ON THE ACCEPTANCE OF, AND EXPENDITURE ON, GIFTS AND HOSPITALITY POLICY

More information

Actualtests.PRINCE2Foundation.120questions

Actualtests.PRINCE2Foundation.120questions Actualtests.PRINCE2Foundation.120questions Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version: 4.8 http://www.gratisexam.com/ PRINCE2 Foundation PRINCE2 Foundation written Exam 1. Dump

More information

Risk Management Procedure. Version Number: 6.0 Controlled Document Sponsor: Controlled Document Lead:

Risk Management Procedure. Version Number: 6.0 Controlled Document Sponsor: Controlled Document Lead: Risk Management Procedure CONTROLLED DOCUMENT CATEGORY: CLASSIFICATION: PURPOSE Controlled Document Number: Procedure Governance To detail the procedure for the management of risk 419 Version Number: 6.0

More information

UNIVERSITY OF ABERDEEN RISK MANAGEMENT FRAMEWORK

UNIVERSITY OF ABERDEEN RISK MANAGEMENT FRAMEWORK UNIVERSITY OF ABERDEEN RISK MANAGEMENT FRAMEWORK 1 TABLE OF CONTENTS FIGURES AND TABLES... 3 1. INTRODUCTION... 4 2. KEY TERMS AND DEFINITIONS... 5 2.1 Risk... 5 2.2 Risk Management... 5 2.3 Risk Management

More information

The University of Leeds Guidelines on Investment Decision Making: Building and Refurbishment Projects

The University of Leeds Guidelines on Investment Decision Making: Building and Refurbishment Projects The University of Leeds Guidelines on Investment Decision Making: Building and Refurbishment Projects Advice may be obtained from Clive Smith (Treasury Manager) E-mail: c.r.smith@adm.leeds.ac.uk Introduction

More information

Greater Bristol Bus Network Major Scheme Business Case. Chapter 1. Developing the Full Approval Major Scheme Business Case

Greater Bristol Bus Network Major Scheme Business Case. Chapter 1. Developing the Full Approval Major Scheme Business Case Greater Bristol Bus Network Major Scheme Business Case Chapter 1 Developing the Full Approval Major Scheme Business Case i ii 1. The Case for Full Approval INTRODUCTION 1.1.1 Bath and North East Somerset,

More information

Decommissioning Basis of Estimate Template

Decommissioning Basis of Estimate Template Decommissioning Basis of Estimate Template Cost certainty and cost reduction June 2017, Rev 1.0 2 Contents Introduction... 4 Cost Basis of Estimate... 5 What is a Basis of Estimate?... 5 When to prepare

More information

The PRINCE2 Practitioner Examination. Sample Paper TR. Answers and rationales

The PRINCE2 Practitioner Examination. Sample Paper TR. Answers and rationales The PRINCE2 Practitioner Examination Sample Paper TR Answers and rationales For exam paper: EN_P2_PRAC_2017_SampleTR_QuestionBk_v1.0 Qu Correct Syll Rationale answer topic 1 A 1.1a a) Correct. PRINCE2

More information

Fundamentals of Project Risk Management

Fundamentals of Project Risk Management Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on

More information

Section 6 IMPLEMENTATION, MONITORING AND EVALUATION

Section 6 IMPLEMENTATION, MONITORING AND EVALUATION Section 6 IMPLEMENTATION, MONITORING AND EVALUATION This section seeks to explain the responsibilities that the Department, Agencies and other public bodies have once a proposal has been appraised. It

More information

Contents INTRODUCTION...4 THE STEPS IN MANAGING RISKS ESTABLISH GOALS AND CONTEXT IDENTIFY THE RISKS...8

Contents INTRODUCTION...4 THE STEPS IN MANAGING RISKS ESTABLISH GOALS AND CONTEXT IDENTIFY THE RISKS...8 Contents INTRODUCTION...4 THE STEPS IN MANAGING RISKS...4 1. ESTABLISH GOALS AND CONTEXT...5 2. IDENTIFY THE RISKS...8 Identifying the risks... 8 Identify the sources of the risks... 8 Identify the impact

More information

(Notices) COURT OF AUDITORS

(Notices) COURT OF AUDITORS 9.2.2010 Official Journal of the European Union C 32/1 IV (Notices) NOTICES FROM EUROPEAN UNION INSTITUTIONS, BODIES, OFFICES AND AGENCIES COURT OF AUDITORS Report on the audit of the operational efficiency

More information

Risk Management Strategy

Risk Management Strategy Risk Management Strategy 2016 2019 Version: 6 Policy Lead/Author & Deputy Director of Quality position: Ward / Department: Nursing Directorate Replacing Document: Version 5 Approving Committee Quality

More information

Illustrative IPSAS Entity Financial Statements Public Sector Entity (PSE) Year ended 31 December [January 2016]

Illustrative IPSAS Entity Financial Statements Public Sector Entity (PSE) Year ended 31 December [January 2016] Illustrative IPSAS Entity Financial Statements Public Sector Entity (PSE) Year ended 31 December [January 2016] Introduction A cornerstone of accountability is fair and transparent reporting of transactions

More information

The Society of Actuaries in Ireland. Actuarial Standard of Practice INS-1, Actuarial Function Report

The Society of Actuaries in Ireland. Actuarial Standard of Practice INS-1, Actuarial Function Report The Society of Actuaries in Ireland Actuarial Standard of Practice INS-1, Actuarial Function Report Classification Mandatory MEMBERS ARE REMINDED THAT THEY MUST ALWAYS COMPLY WITH THE CODE OF PROFESSIONAL

More information

PRINCE2. Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version:

PRINCE2. Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version: PRINCE2 Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version: 1.0 Exam M QUESTION 1 Identify the missing word(s) from the following sentence. A project is a temporary organization that is

More information

IMPORTANT NOTICE TO READERS

IMPORTANT NOTICE TO READERS IMPORTANT NOTICE TO READERS Please read below for the terms and conditions on which you may read this report. In reading this report you will be deemed to have agreed to the terms and conditions set out

More information

A CEPR / DFID Research Initiative MAJOR RESEARCH GRANT BUDGET GUIDELINES

A CEPR / DFID Research Initiative MAJOR RESEARCH GRANT BUDGET GUIDELINES Coordinated by: In partnership with: A CEPR / DFID Research Initiative MAJOR RESEARCH GRANT BUDGET GUIDELINES 2017-2020 Contents 1 Introduction... 2 2 General rules... 2 3 Definition of Costs... 2 3.1

More information

A simplifi ed approach to documentation and risk assessment for small to medium businesses

A simplifi ed approach to documentation and risk assessment for small to medium businesses BUSINESS SEGMENT SMALL TO MEDIUM BUSINESSES AUDIENCE GUIDE FORMAT NAT 12032-03.2005 PRODUCT ID INTERNATIONAL TRANSFER PRICING A simplifi ed approach to documentation and risk assessment for small to medium

More information

Intro Public-Private Partnership (P3) Finance Course

Intro Public-Private Partnership (P3) Finance Course Intro Public-Private Partnership (P3) Finance Course Identifying P3 Projects and Knowing the Atmosphere Kylee Anastasi Director, Capital Projects and Infrastructure Advisory PricewaterhouseCoopers LLP

More information

Outline Business Case for Ballymena Health & Care Centre VERSION 3 SEPT 2009

Outline Business Case for Ballymena Health & Care Centre VERSION 3 SEPT 2009 Outline Business Case for Ballymena Health & Care Centre VERSION 3 SEPT 2009 1 CHAPTER 1 EXECUTIVE SUMMARY 1.1 Introduction 1.1.1 This document sets out the Strategic content and Outline Business Case

More information

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone:   Last revised: for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:

More information

UCISA TOOLKIT. Major Project Governance Assessment. version 1.0

UCISA TOOLKIT. Major Project Governance Assessment. version 1.0 UCISA TOOLKIT Major Project Governance Assessment version 1.0 Contents Introduction 1 Roles and responsibilities 2 Definition of a Major Project 3 Guidance for using the Toolkit 4 Governance elements 4

More information

Project Sponsor Group Handbook

Project Sponsor Group Handbook VERSION 3 UNIVERSITY OF OXFORD Project Sponsor Group Handbook April 2013 Authorship Friends and colleagues would like to remember with affection Bárbara Galanes-Álvarez who passed away after a sudden and

More information

3. Minutes of Governance and Audit Committee Meeting held on 15 January 2013 GAC 17/2013

3. Minutes of Governance and Audit Committee Meeting held on 15 January 2013 GAC 17/2013 NORTHERN IRELAND HEALTH AND SOCIAL CARE BUSINESS SERVICES ORGANISATION GOVERNANCE AND AUDIT COMMITTEE Minutes of the Governance and Audit Committee (GAC) which took place on Tuesday, 16 April 2013 at 11:00am

More information

Topic RISK MANAGEMENT Procedure Category Risk Management Updated 07/2011

Topic RISK MANAGEMENT Procedure Category Risk Management Updated 07/2011 Topic RISK MANAGEMENT Procedure 07.01 Category Risk Management Updated 07/2011 RELATED POLICIES, PROCEDURES AND FORMS Policies Procedures Forms Risk Management Policy Code of Conduct Public Interest Disclosure

More information

Development Cooperation Development Education Partnership Fair. Writing a successful co financing application

Development Cooperation Development Education Partnership Fair. Writing a successful co financing application Development Cooperation Development Education Partnership Fair Writing a successful co financing application 3 sessions to guide project preparation Session 1: Deciding on stakeholders and defining problems/issues.

More information

Risk Management. Webinar - July 2017

Risk Management. Webinar - July 2017 Risk Management Webinar - July 2017 Compiled by: Raaghieb Najjaar, Yaeesh Yasseen & Rashied Small Adapted and Facilitated by: Professor Enslin J. van Rooyen Risk Management - June 2017 2 Defining Risk

More information

MPA/MPS Capital Strategy

MPA/MPS Capital Strategy Appendix 1 MPA/MPS Capital Strategy 2005 2010 July 2004 Draft Page 1 of 13 Contents Section 1 Context sheet Page General 3 Capital and Revenue Budgets 3 Section 2 Capital Strategy Introduction 5 Strategic

More information

Chapter 2 Department of Supply and Services Public-Private Partnership: Eleanor W. Graham Middle School and Moncton North School

Chapter 2 Department of Supply and Services Public-Private Partnership: Eleanor W. Graham Middle School and Moncton North School Department of Supply and Services - Public-Private Partnership: Chapter 2 Department of Supply and Services Public-Private Partnership: Eleanor W. Graham Middle School and Moncton North School Contents

More information

Risk Management. Seminar June Compiled by: Raaghieb Najjaar, Yaeesh Yasseen & Rashied Small

Risk Management. Seminar June Compiled by: Raaghieb Najjaar, Yaeesh Yasseen & Rashied Small Risk Management Seminar June 2017 Compiled by: Raaghieb Najjaar, Yaeesh Yasseen & Rashied Small Defining Risk Risk reflects the chance that the actual event may be different than the planned / expected

More information

Financial planning handbook

Financial planning handbook Financial planning handbook This financial planning handbook sets out the framework for completing financial plans for sixth form colleges and other further education colleges for 2016 to 2018. April 2016

More information

RISK MANAGEMENT FRAMEWORK

RISK MANAGEMENT FRAMEWORK RISK MANAGEMENT FRAMEWORK Approving authority Approval date University Council 5 August 2013 (3/2013 meeting) Advisor Vice President (Corporate Services) vpcorporateservices@griffith.edu.au (07) 373 57343

More information

PRINCE2 Sample Papers

PRINCE2 Sample Papers PRINCE2 Sample Papers The Official PRINCE2 Accreditor Sample Examination Papers Terms of use Please note that by downloading and/or using this document, you agree to comply with the terms of use outlined

More information

Planning Construction Procurement. A guide to risk and value management

Planning Construction Procurement. A guide to risk and value management Planning Construction Procurement A guide to risk and value management ISBN: 978-1-98-851708-7 (online) First published October 2015 Revised October 2016 New Zealand Government Procurement PO Box 1473

More information

MINI GUIDE. Project risk analysis and management

MINI GUIDE. Project risk analysis and management MINI GUIDE Project risk analysis and management Association for Project Management January 2018 Contents Page 3 Introduction What is PRAM? Page 4 Page 7 Page 9 What is involved? Why is it used? When should

More information

Redevelopment of MOD Main Building

Redevelopment of MOD Main Building Ministry of Defence Redevelopment of MOD Main Building REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 748 Session 2001-2002: 18 April 2002 LONDON: The Stationery Office 0.00 Ordered by the House of Commons

More information

NIRS 2: Contract extension. REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session : 14 November 2001

NIRS 2: Contract extension. REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session : 14 November 2001 NIRS 2: Contract extension REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session 2001-2002: 14 November 2001 The National Audit Office scrutinises public spending on behalf of Parliament. The Comptroller

More information

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS Advanced Project Management MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS 06 07 November 2018 Facilitator: Mr Mondli Mbambo Module Purpose Project Risk & Procurement Managment Knowledge Risk

More information

Scouting Ireland Risk Management Framework

Scouting Ireland Risk Management Framework No. SID 124A/15 Gasóga na héireann/scouting Ireland Issued Amended 20 th June 2015 Deleted Source: National Management Committee Scouting Ireland Risk Management Framework Revision Date Description # 20/06/2015

More information

Project Integration Management

Project Integration Management Project Integration Management The Key to Overall Project Success: Good Project Integration Management Project managers must coordinate all of the other knowledge areas throughout a project s life cycle.

More information

Control activities that are part of the process are detailed in the riskcontrol

Control activities that are part of the process are detailed in the riskcontrol Policy Title Previous title (if any) Cash Transfers to Implementing Partners N/A Policy objective Target audience Risk control matrix Checklist The policy and procedures outline the process for management

More information

Follow-Up on VFM Section 3.05, 2014 Annual Report RECOMMENDATION STATUS OVERVIEW

Follow-Up on VFM Section 3.05, 2014 Annual Report RECOMMENDATION STATUS OVERVIEW Chapter 1 Section 1.05 Ministry of Infrastructure (formerly the Ministry of Economic Development, Employment and Infrastructure) Infrastructure Ontario Alternative Financing and Procurement Follow-Up on

More information

George Eliot Hospital NHS Trust - Securing a sustainable future Project. Annex A

George Eliot Hospital NHS Trust - Securing a sustainable future Project. Annex A Annex A ISOS financial submission requirements Historical financial performance NHS Foundation Trusts 1. Please provide a copy of the Annual Plan that you submitted to Monitor for 2013/14. If a revised

More information

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS Guidance Paper No. 2.2.6 INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS GUIDANCE PAPER ON ENTERPRISE RISK MANAGEMENT FOR CAPITAL ADEQUACY AND SOLVENCY PURPOSES OCTOBER 2007 This document was prepared

More information

COWENS RISK SOLUTIONS REVIEWING FIRE RISK ASSESSMENTS

COWENS RISK SOLUTIONS REVIEWING FIRE RISK ASSESSMENTS COWENS RISK SOLUTIONS REVIEWING FIRE RISK ASSESSMENTS October 2014 WHEN TO REVIEW A FIRE RISK ASSESSMENT?: The Regulatory Reform (Fire Safety) Order, (FSO) and equivalent legislation in Scotland and Northern

More information

Audit Committee Annual Report to the Board

Audit Committee Annual Report to the Board Audit Committee Annual Report to the Board Report to: Board Date: 28 September 2017 Report by: Report No: Mike Cairns, Convener of the Audit Committee Agenda Item: 13.3 PURPOSE OF REPORT This report represents

More information

Submission on NZX Listing Rule Review Discussion Paper dated 27 September November 2017

Submission on NZX Listing Rule Review Discussion Paper dated 27 September November 2017 Submission on NZX Listing Rule Review Discussion Paper dated 27 September 2017 17 November 2017 INTRODUCTION & EXECUTIVE SUMMARY 1 We welcome the opportunity to participate in the NZX listing rule review.

More information

2. 5 of the 75 questions are under trial and will not contribute to your overall score. There is no indication of which questions are under trial.

2. 5 of the 75 questions are under trial and will not contribute to your overall score. There is no indication of which questions are under trial. The Foundation Examination Sample Paper 3 Question Booklet Multiple Choice Exam Duration: 60 minutes Instructions 1. You should attempt all 75 questions. 2. 5 of the 75 questions are under trial and will

More information

GE4. Service Redesign & Clinical Practice. Benchmarking for Locally-Priced Services

GE4. Service Redesign & Clinical Practice. Benchmarking for Locally-Priced Services GE4 Service Redesign and Clinical Practice Benchmarking for Locally-Priced Services Scheme Code and Full Name GE4. Service Redesign & Clinical Practice Benchmarking for Locally-priced Services Section

More information

TERMS OF REFERENCE (TOR) FOR AUDITS OF UN-WOMEN NGO, GOV T, IGO AND GRANT PROJECTS

TERMS OF REFERENCE (TOR) FOR AUDITS OF UN-WOMEN NGO, GOV T, IGO AND GRANT PROJECTS TERMS OF REFERENCE (TOR) FOR AUDITS OF UN-WOMEN NGO, GOV T, IGO AND GRANT PROJECTS TABLE OF CONTENTS Introduction... 3 A. Background... 7 B. Project Management... 7 C. Consultations with concerned parties...

More information

Report of the Advisory Committee on Administrative and Budgetary Questions

Report of the Advisory Committee on Administrative and Budgetary Questions United Nations General Assembly Distr.: General 3 November 2000 Original: English A/55/543 Fifty-fifth session Agenda item 116 Review of the efficiency of the administrative and financial functioning of

More information

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS Guidance Paper No. 2.2.x INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS GUIDANCE PAPER ON ENTERPRISE RISK MANAGEMENT FOR CAPITAL ADEQUACY AND SOLVENCY PURPOSES DRAFT, MARCH 2008 This document was prepared

More information

EUROPEAN STANDARD OF ACTUARIAL PRACTICE 2 (ESAP 2) ACTUARIAL FUNCTION REPORT UNDER DIRECTIVE 2009/138/EC

EUROPEAN STANDARD OF ACTUARIAL PRACTICE 2 (ESAP 2) ACTUARIAL FUNCTION REPORT UNDER DIRECTIVE 2009/138/EC ACTUARIAL ASSOCIATION OF EUROPE ASSOCIATION ACTUARIELLE EUROPÉENNE 4 PLACE DU SAMEDI B-1000 BRUSSELS, BELGIUM TEL: (+32) 22 17 01 21 FAX: (+32) 27 92 46 48 E-MAIL: info@actuary.eu WEB: www.actuary.eu EUROPEAN

More information

INVEST NORTHERN IRELAND MANAGEMENT STATEMENT AND FINANCIAL MEMORANDUM

INVEST NORTHERN IRELAND MANAGEMENT STATEMENT AND FINANCIAL MEMORANDUM INVEST NORTHERN IRELAND MANAGEMENT STATEMENT AND FINANCIAL MEMORANDUM March 2018 1 INVEST NORTHERN IRELAND: MANAGEMENT STATEMENT Page no: 1. INTRODUCTION 3 1.1 This Document. 3 1.2 Founding Legislation;

More information

SHEFFIELD TEACHING HOSPITALS NHS FOUNDATION TRUST. EXECUTIVE SUMMARY REPORT TO THE BOARD OF DIRECTORS MEETING HELD ON 18 th DECEMBER 2013

SHEFFIELD TEACHING HOSPITALS NHS FOUNDATION TRUST. EXECUTIVE SUMMARY REPORT TO THE BOARD OF DIRECTORS MEETING HELD ON 18 th DECEMBER 2013 SHEFFIELD TEACHING HOSPITALS NHS FOUNDATION TRUST M EXECUTIVE SUMMARY REPORT TO THE BOARD OF DIRECTORS MEETING HELD ON 18 th DECEMBER 2013 Subject Lead Author Status 1 Treasury Management Policy Neil Priestley

More information

EUROPEAN STANDARD OF ACTUARIAL PRACTICE 2 (ESAP 2) ACTUARIAL FUNCTION REPORT UNDER DIRECTIVE 2009/138/EC

EUROPEAN STANDARD OF ACTUARIAL PRACTICE 2 (ESAP 2) ACTUARIAL FUNCTION REPORT UNDER DIRECTIVE 2009/138/EC ACTUARIAL ASSOCIATION OF EUROPE ASSOCIATION ACTUARIELLE EUROPÉENNE 4 PLACE DU SAMEDI B-1000 BRUSSELS, BELGIUM TEL: (+32) 22 17 01 21 FAX: (+32) 27 92 46 48 E-MAIL: info@actuary.eu WEB: www.actuary.eu EUROPEAN

More information

Railway Housing Association. Value for Money Strategy

Railway Housing Association. Value for Money Strategy Railway Housing Association Value for Money Strategy 2016-21 1 Executive Summary 1.1 Railway Housing Association (RHA) recognises that Value for Money (VFM) is a fundamental consideration for all housing

More information

BUDGETING. After studying this unit you will be able to know: different approaches for the preparation of budgets; 10.

BUDGETING. After studying this unit you will be able to know: different approaches for the preparation of budgets; 10. UNIT 10 Structure APPROACHES TO BUDGETING 10.0 Objectives 10.1 Introduction 10.2 Fixed Budgeting 10.3 Flexible Budgeting 10.4 Difference between Fixed and Flexible Budgeting 10.5 Appropriation Budgeting

More information

Capital Project Approval Request

Capital Project Approval Request Capital Project Approval Request PMP T07 Project Number MAJ 0000 Project Title Project Description Existing Approvals EC Approval Court Approval Approved Gateway 0 To proceed to GW1 Prepare OBC / Feasibility

More information

Financial Reporting Consolidation PEMPAL Treasury Community of Practice thematic group on Public Sector Accounting and Reporting

Financial Reporting Consolidation PEMPAL Treasury Community of Practice thematic group on Public Sector Accounting and Reporting DRAFT 2016 Financial Reporting Consolidation PEMPAL Treasury Community of Practice thematic group on Public Sector Accounting and Reporting Table of Contents 1 Goals and target audience for the Guidance

More information

Basic Introduction to Project Cycle. Management Using the. Logical Framework Approach

Basic Introduction to Project Cycle. Management Using the. Logical Framework Approach Basic Introduction to Project Cycle Management Using the Logical Framework Approach Developed and Presented by: Umhlaba Development Services Umhlaba Development Services Noswal Hall, Braamfontein, Johannesburg,

More information

The Annual Audit Letter for London Borough of Lewisham

The Annual Audit Letter for London Borough of Lewisham The Annual Audit Letter for London Borough of Lewisham Year ended 31 March 2016 October 2016 Darren Wels Director T 07880 456 152 E darren.j.wells@uk.gt.com Jamie Bewick Senior Manager T 07880 456 144

More information

PEFA Training. Dakar, Senegal January & February 1, #PEFA. PEFA Secretariat

PEFA Training. Dakar, Senegal January & February 1, #PEFA. PEFA Secretariat www.pefa.org #PEFA PEFA Training Dakar, Senegal January 30-31 & February 1, 2019 PEFA Secretariat Improving public financial management. Supporting sustainable development. INTRODUCTION Introductions Participant

More information

Attachment C: How capital expenditure is proposed and approved under the capex IM

Attachment C: How capital expenditure is proposed and approved under the capex IM ISBN no. 978-1-869455-84-2 Project no. 14.09/16274 Public version Attachment C: How capital expenditure is proposed and approved under the capex IM Transpower capex input methodology review - Proposed

More information