1 Subject: GUIDANCE ON THE COMPLETION OF REVISED REVENUE BUSINESS CASE TEMPLATES AND POST PROJECT EVALUATION For Action by: Chief Executive of HSC Bodies and NIFRS Directors of Finance of HSC Bodies and NIFRS Summary of Contents: This circular provides guidance on the completion of revised revenue business case templates and PPE for the Arms Length Bodies of DHSSPS. Circular Reference: HSC (F) 34/2013 Date of Issue: 6 th June 2013 Related documents: DAO(DFP) 06/12 FD(DFP) 20/09 - Northern Ireland Guide to Economic Appraisal and Evaluation (NIGEAE) Superseded Documents: Enquiries: Any enquiries about the contents of this Circular should be addressed to: Catriona O Connor Finance Policy, Accountability & Counter Fraud Unit DHSSPS Room D3 Castle Buildings Stormont Estate Belfast BT4 3SQ Status of Contents: Action Implementation: Immediate Tel: Fax: Catriona.O Connor@dhsspsni.gov.uk
2 GUIDANCE ON THE COMPLETION OF REVISED REVENUE BUSINESS CASE TEMPLATES AND POST PROJECT EVALUATION Introduction 1. The purpose of this circular is to draw the attention of Department s Arm s Length Bodies (i.e. Health and Social Care (HSC) bodies and NIFRS) to the following revised templates: Revenue Business Cases; and Post Project Evaluation (PPE) Economic Appraisal 2. FD(DFP)20/09 draws departments attention to the Northern Ireland Guide to Expenditure Appraisal and Evaluation (NIGEAE), which contains DFP s core guidance on the appraisal, evaluation, approval and management of policies, programmes and projects. 3. The principles of appraisal should be applied, with proportionate effort, to every proposal for spending or saving public money, or proportionate changes in the use of public sector resources. For example, appraisal must be applied irrespective of whether the relevant public expenditure or resources: involve capital or current spending, or both; are large or small; are above or below delegated limits. 4. Appraisal is a systematic process for examining alternative uses of resources. It is designed to assist in defining problems and finding the solutions which offer the best value for money. It is a way of thinking expenditure proposals through, right from the emergence of the need for a project through its implementation, to postproject evaluation. It is the established vehicle for planning and approving
3 projects and other expenditures. Good appraisal leads to better decisions and use of resources. It facilitates good project management and project evaluation. 5. Appraisal is not optional; it is an essential part of good financial management, which is vital to decision-making and crucial to accountability. But it must also be proportionate. 6. It is important to begin applying appraisal early in the gestation of any proposal which has expenditure or resource implications. The justification for incurring any expenditure at all should be considered. Appraisal should be applied from the emergence of a need right through to the recommendation of the most costeffective course of action. It should not be regarded merely as the means to refine the details of a predetermined option. Revenue Business Case Templates 7. A working group consisting of senior finance representatives from across the Department and HSC was set up to examine the processes in place for the preparation and approval of business cases. The group developed a new set of business case templates for revenue expenditure and these were agreed with DFP. 8. The revised templates have different thresholds for expenditure, and have been developed in line with the requirements of NIGEAE, with proportionality in mind. 9. The revised templates, together with guidance on when and how to complete a business case, are attached as follows: Revenue Business Case Proforma (Annex A) Revenue expenditure up to 50k (Annex B) Revenue expenditure greater than 50k up to 250k (Annex C); and Revenue expenditure greater than 250k up to 1m (Annex D).
4 10. The attached templates should be completed for the following types of expenditure for the total life of the project/service: Policy and Programme Development; Significant Expansion to Existing Services; and New Expenditure. 11. NB for normal recurrent / maintaining existing services expenditure, a brief justification is required and template does not need to be completed; although recurrent expenditure does not warrant the perpetual production of business cases, appraisals are required for all new procurements/ contracts in line with procurement practice. There must, however, for any expenditure, always be evidence available to justify that options have been considered and the spend can be justified as representing the most optimum solution that provides value for money. When it comes to small scale and/or simple decisions in the main all that is required would be small scale and simple documentation. You may find it helpful to refer to the NIGEAE guidance on The Appraisal and Evaluation of Small Expenditure at: Post Project Evaluations 12. FD(DFP)20/09 sets out the requirement for the completion of Post Project Evaluations (PPEs). DFP is placing a greater emphasis on the completion of PPEs, and expects all projects to be subject to proper monitoring and control measures including PPEs for all projects, both above and below delegated limits. Such measures can help ensure good VFM by identifying difficulties, preventing the repetition of mistakes, revealing positive points and in particular it is an essential part of PPEs that lessons which may be of use in other projects and/or other Departments are identified and shared.
5 13. Every appraisal (or business case) of any substance should indicate how the proposals concerned will be evaluated after completion and how the results of the evaluation will be disseminated (i.e. shared with colleagues and CoPE). 14. In general, evaluation reports should summarise whether, and if so, why the outturn differed from that foreseen in the appraisal; how effective the activity was in achieving its objectives, and why; the cost-effectiveness of the activity; and what the results imply for future management or policy decisions 15. A revised PPE template has also been developed by the working group at Annex E. Revenue Business Case Database 16. A further recommendation made by the Working Group was that all HSC bodies and Core Department should develop an internal database to record all revenue expenditure business cases submitted each year. It is therefore suggested that you maintain a list of all revenue expenditure appraisals within your business area and this will be used as a sample base for test drilling 2013/14 onwards. Action 17. Against this background, it is therefore recommended that bring this circular to the attention of the appropriate staff within your organisation, noting all action points and documents included within Annexes A E. 18. The revised templates at Annexes A-E should be adopted with immediate effect.
6 Enquiries 19. Should you have any queries please contact Catriona O Connor on or Catriona.O Connor@dhsspsni.gov.uk. PAULA SHEARER Finance Policy, Accountability and Counter Fraud Unit
7 Annex A REVENUE BUSINESS CASE PROFORMA COVER (To be submitted with every business case) Name of organisation Project Title Total Cost Start date Completion date Complete this section if bid is for new funding BID FOR NEW FUNDING Is this bid for new funding (Y/N) How much total funding required? How much funding required per year? Is this funding to be made recurrent? Complete this section if funding available within existing allocation Funding available within existing allocation (Y/N) Total cost of proposal Cost of proposal per year Is this cost within recurrent allocation? Is this business case (a) Standard (b) Novel Contentious (d) Setting a precedent If yes to (b) or (c) or (d), requires Departmental & DFP approval Is Departmental / DFP approval required Y/N
8 Approvals & submissions Prepared by Name Printed (signed) Grade/ Title Date Approved by Name printed (signed) Grade / Title Date Insert more boxes if further approvals are required by officials Complete this section if Department / DFP approval required Date submitted to Department Department/ DFP approval (y/n) Date approved
9 Annex B BUSINESS CASE TEMPLATE REVENUE FUNDING up to 50,000 GUIDANCE NOTES This template should be completed for the following types of expenditure for the total life of the project/service: Policy and Programme Development; Significant Expansion to Existing Services; and New Expenditure. NB for normal recurrent/ maintaining existing services expenditure, a brief justification is required and template does not need to be completed; Although recurrent expenditure does not warrant the perpetual production of business cases, appraisals are required for all new procurements/ contracts in line with procurement practice. There must, however for any expenditure always be evidence available to justify that options have been considered and the spend can be justified as representing the most optimum solution that provides value for money. When it comes to small scale and/or simple decisions in the main all that is required would be small scale and simple documentation. You may find it helpful to refer to the NIGEAE guidance on The Appraisal and Evaluation of Small Expenditure on GUIDANCE NOTES This investment proposal template should be prepared in line with NIGEAE Guidance - see Template is to be used for all revenue expenditures up to 50k. Please complete this template with proportional effort, i.e. detail provided should be commensurate with the size of the bid. This is a general template and that the boxes and tables may be enlarged or modified to suit the particulars of the case in hand. When necessary, refer to the NIGEAE website Section 1: Strategic Context and Need: Briefly explain the background to the proposal including its relevance to your organisation/ Gov /or Departmental strategic aims and policy objectives. Identify the key stakeholders and explain their commitment and any outstanding issues. Explain the nature of the needs or demands that are to be addressed, and detail any deficiencies in existing service provision.
10 Section 2: Objectives: Objectives must be stated so that it is clear what proposals are intended to achieve Explain and list the project objectives in specific measureable terms. Specify targets that are SMART i.e. Specific,Measureable, Achievable, Relevant and Time dependent Include implementation targets/ outcomes/ outputs if possible e.g. dates, milestones, etc e.g. Achieve X outputs by 31 March 20XX, XX staff in place by 31 March 20XX etc. Section 3: Identify and Describe Options: Identify and briefly describe all options, including status quo. Status quo means to continue with existing arrangements or maintain services as close as possible to existing levels. Requirement is that at least 2 options considered including status quo. Identify and evaluate the benefits of all the options considered. Section 4: Project Costs: Provide details of total cost of project over total life of the project for all options. Provide details of any assumptions made in formulating costs. State if funding is recurrent funding going forward or is this a one-off project with a life of XX years? Section 5: Non-Monetary Benefits Briefly list and describe the benefits of preferred option (benefits will relate closely to the objectives) Section 6: Project Risks Identify and describe the risks that the project may face. Section 7: Preferred option and Explanation for Selection Identify which option is preferred and why, in terms of assumptions, costs, non monetary benefits, risks, constraints and other factors etc Section 8: Monitoring and Evaluation Indicate how the proposed option will be monitored during and after implementation. Indicate factors to be evaluated, when, how and by whom. The following additional information is required for Trusts submitting business cases to HSCB only. Section 9: Changes to SBA activity for the preferred option The purpose of this section is to record the current baseline activity in appropriate currencies and to specify the additional activity that will be provided for this investment, and the new SBA volumes. If approved the additional activity will be added to the volumes in the organisation s SBA.
11 The associated baseline costs and additional costs must be shown in the financial appendix. Examples: Approval of a stationary budget is deemed suitable justification for expenditure on a stationary order and therefore you would not be required to complete this template. This is considered to be business as usual and therefore you would not be required to complete a business case for such items that are covered within approved budgets. The need for a business case would arise only if there was a change in policy or a contract was coming to an end. For example a move from oil to gas heating or something to that effect then there would be a need to examine the options.
12 BUSINESS CASE TEMPLATE REVENUE FUNDING up to 50,000 SECTION 1: STRATEGIC CONTEXT AND NEED SECTION 2: OBJECTIVES SECTION 3: LIST AND DESCRIBE AT LEAST 2 OPTIONS (INCLUDING STATUS QUO) OPTION NO. BRIEF DESCRIPTION OF OPTION 1 ( Status quo) 2 3 (if applicable) SECTION 4: PROJECT COSTS Option Year 1 ( 000) 1 Status Quo continue with existing arrangements 2 Year 2 ( 000) Year 3 ( 000) Total ( 000) 3
13 [Cost Assumptions - expand as appropriate] SECTION 5: NON-MONETARY BENEFITS SECTION 6: PROJECT RISKS SECTION 7: PREFERRED OPTION AND EXPLANATION FOR SELECTION SECTION 8: MONITORING AND EVALUATION Who will manage the implementation? Who will monitor and evaluate the outcomes? When will this take place?
14 SECTION 9: ACTIVITY OUTCOMES (TRUSTS ONLY) Baseline Additional activity New Baseline Activity Specifiy activity, e.g. IP, DC OPN, OPR, Contacts etc IP DC OPN OPR
15 Annex C BUSINESS CASE TEMPLATE REVENUE FUNDING 50k - 250k GUIDANCE NOTES This template should be completed for the following types of expenditure for the total life of the project/service: Policy and Programme Development; Significant Expansion to Existing Services; and New Expenditure. NB for normal recurrent / maintaining existing services expenditure, a brief justification is required and template does not need to be completed; Although recurrent expenditure does not warrant the perpetual production of business cases, appraisals are required for all new procurements/ contracts in line with procurement practice. There must, however for any expenditure always be evidence available to justify that options have been considered and the spend can be justified as representing the most optimum solution that provides value for money. When it comes to small scale and/or simple decisions in the main all that is required would be small scale and simple documentation. You may find it helpful to refer to the NIGEAE guidance on The Appraisal and Evaluation of Small Expenditure on GUIDANCE NOTES This investment proposal template should be prepared in line with NIGEAE Guidance - see Template is to be used for all revenue expenditures greater than 50k up to 250k. Please complete this template with proportional effort, i.e. detail provided should be commensurate with the size of the bid. This is a general template and that the boxes and tables may be enlarged or modified to suit the particulars of the case in hand. When necessary, refer to the NIGEAE website Section 1: Strategic Context and Need: Briefly explain the background to the proposal including its relevance to your organisation/ Gov /or Departmental strategic aims and policy objectives. Identify the key stakeholders and explain their commitment and any outstanding issues. As specifically as possible, explain the nature of the needs or demands that are to be addressed, and detail any deficiencies in existing service provision. Include suitable quantification of needs/demands/deficiencies where possible.
16 Section 2 (a): Objectives: Objectives must be stated so that it is clear what proposals are intended to achieve Explain and list the project objectives in specific measureable terms. Specify targets that are SMART i.e. Specific, Measureable, Achievable, Relevant and Time dependent. It is particularly important that objectives are measurable - otherwise it will not be possible to gauge whether or how well they have been achieved. Include implementation targets / outcomes/ outputs if possible e.g. dates, milestones, etc e.g. Achieve X outputs by 31 March 20XX, XX staff in place by 31 March 20XX etc. Section 2 (b): Constraints: State the key constraints on the project, e.g. technical issues, timing issues, legal requirements, professional standards, planning constraints, policy commitments and so on. Section 3: Identify and Describe Options: Identify and briefly describe all options, including status quo. Status quo means to continue with existing arrangements or maintain services as close as possible to existing levels. Requirement is that at least 2 options considered including status quo, giving reasons if only 1 alternative option other than status quo considered. Identify and evaluate the benefits of all the options considered. Section 4: Project Costs: Provide details of total cost of project over total life of the project for all options. Provide details of any assumptions made in formulating costs. State if funding is recurrent funding going forward or is this a one-off project with a life of XX years? NPV analysis should be included for revenue projects spanning more than 5 years, or those revenue projects that have differing cash flows over the time period. Decision to include should be made on a case by case basis. If NPV required use table per template for larger business cases. Sensitivity - should be included for projects spanning more than 5 years, or where a change in a variant would significantly change the outcome. Decision to include should be made on a case by case basis. Section 5: Non-Monetary Benefits: Briefly list and describe the benefits of preferred option (benefits will relate closely to the objectives) Section 6: Project Risks & Uncertainities Identify and describe the risks that the project may face. Explain how these compare under the various options.
17 Section 7: Preferred option and Explanation for Selection: Identify which option is preferred and why, in terms of assumptions, costs, non monetary benefits, risks, constraints and other factors etc Section 8: Affordability and Funding Requirements: Detail what funding is available / how it will be funded and whether it will be recurrent funding. Section 9: Management Arrangements: Describe from start to finish of project who will be responsible at each stage eg planning timetable, obtaining finance, procurement, legal issues, accommodation staff, consultancy, TUC issues, security, training, documentation of project progress etc. Section 10: Monitoring and Evaluation: Indicate how the proposed option will be monitored during and after implementation. Indicate factors to be evaluated, when, how and by whom. The following additional information is required for Trusts submitting business cases to HSCB only. Section 11: Changes to SBA activity for the preferred option The purpose of this section is to record the current baseline activity in appropriate currencies and to specify the additional activity that will be provided for this investment, and the new SBA volumes. If approved the additional activity will be added to the volumes in the organisation s SBA. The associated baseline costs and additional costs must be shown in the financial appendix. Section 12: Benchmarking evidence to support preferred option. The purpose of this section is to provide evidence that the preferred option compares favourably to Trust specialty costs, Trust HRGs, Reference costs, PbR tariffs, Best practise tariffs, Community indicators or other recognised benchmarks Examples: Approval of a stationary budget is deemed suitable justification for expenditure on a stationary order and therefore you would not be required to complete this template. This is
18 considered to be business as usual and therefore you would not be required to complete a business case for such items that are covered within approved budgets. The need for a business case would arise only if there was a change in policy or a contract was coming to an end. For example a move from oil to gas heating or something to that effect then there would be a need to examine the options.
19 BUSINESS CASE TEMPLATE REVENUE FUNDING 50k - 250k SECTION 1: PROJECT BACKGROUND, STRATEGIC CONTEXT & NEED SECTION 2 (a): OBJECTIVES 1. Project Objectives Measurable Targets [add more objectives as appropriate] SECTION 2 (b) : CONSTRAINTS SECTION 3: IDENTIFY AND DESCRIBE OPTIONS OPTION NO. BRIEF DESCRIPTION OF OPTION 1 Status Quo - continue with existing arrangements 2 3 (if applicable)
20 SECTION 4: PROJECT COSTS 1 Option Year 1 ( 000) Year 2 ( 000) Year 3 ( 000) Total ( 000) 2 3 COST ASSUMPTIONS: SECTION 5: NON-MONETARY BENEFITS SECTION 6: PROJECT RISKS & UNCERTAINITIES SECTION 7: PREFERRED OPTION AND EXPLANATION FOR SELECTION
21 SECTION 8: AFFORDABILITY AND FUNDING REQUIREMENTS AFFORDABILITY STATEMENT Required Capital required Revenue required Existing budget : Capital Revenue Additional Allocation Required: Capital Revenue Yr s Yr s Yr s Yr s Totals 000 s AFFORDABILITY ASSUMPTIONS SECTION 9: MANAGEMENT ARRANGEMENTS SECTION 10: MONITORING AND EVALUATION Who will manage the implementation? Who will monitor and evaluate the outcomes? What other factors will be monitored and evaluated? When will this take place?
22 SECTION 9: ACTIVITY OUTCOMES (TRUSTS ONLY) Baseline Additional activity New Baseline Activity Specifiy activity, e.g. IP, DC OPN, OPR, Contacts etc IP DC OPN OPR SECTION 12: BENCHMARKING EVIDENCE TO SUPPORT PREFERRED OPTION [expand as necessary]
23 Annex D BUSINESS CASE TEMPLATE REVENUE FUNDING 250k - 1m GUIDANCE NOTES This template should be completed for the following types of expenditure for the total life of the project/service: Policy and Programme Development; Significant Expansion to Existing Services; and New Expenditure. NB for normal recurrent/ maintaining existing services expenditure, a brief justification is required and template does not need to be completed; Although recurrent expenditure does not warrant the perpetual production of business cases, appraisals are required for all new procurements/ contracts in line with procurement practice. There must, however for any expenditure always be evidence available to justify that options have been considered and the spend can be justified as representing the most optimum solution that provides value for money. When it comes to small scale and/or simple decisions in the main all that is required would be small scale and simple documentation. You may find it helpful to refer to the NIGEAE guidance on The Appraisal and Evaluation of Small Expenditure on GUIDANCE NOTES This investment proposal template should be prepared in line with the NIGEAE Guidance - see Template is to be used for all revenue expenditures > 250k up to 1m. It can be used as a basis for expenditures > 1m, but more detail/ analysis will be required commensurate with the size of the bid. Please refer to NIGEAE when completing business case > 1m Please complete this template with proportional effort, i.e. detail provided should be commensurate with the size of the bid. This is a general template and that the boxes and tables may be enlarged or modified to suit the particulars of the case in hand. When necessary, refer to the NIGEAE website Section 1 (a) : Project Background and Strategic Context Explain the background to the proposal including its relevance to your organisation/ NI Government or Departmental strategic aims and policy objectives. Identify the key stakeholders and explain their commitment and any outstanding issues.
24 Section 1 (b): Need As specifically as possible, explain the nature of the needs or demands that are to be addressed, and detail any deficiencies in existing service provision. Include suitable quantification of needs/demands/deficiencies where possible. Provide historical service activity (previous years), for eg, hospital caseload, evidence of service/equipment failure, service risk rating etc., along with service projections for the next 3 years where appropriate. Section 2 (a) : State Objectives Objectives must be stated so that it is clear what proposals are intended to achieve. These should be consistent with statements of government policy, departmental or agency objectives, departmental Public Service Agreements Specify targets that are SMART i.e. Specific Measureable Achievable, Relevant and Time dependent. It is particularly important that objectives are measurable - otherwise it will not be possible to gauge whether or how well they have been achieved. Include quantifiable targets/ outcomes/ outputs where possible e.g. Achieve X outputs by 31 March 20XX, XX staff in place by 31 March 20XX etc. Where there are numerous objectives, or there is a potential conflict between objectives, it is helpful to indicate their relative priority, both to inform option assessment and to assist in post project evaluation. Section 2 (b) : State Constraints Identify any likely constraints to the project e.g. technical issues, timing issues, legal requirements, professional standards, planning constraints, policy commitments and so on. Section 3: Identify and Shortlist the Options Consider alternative ways to meet the objectives e.g. variations in scale, quality, technique, location, timing etc. Start with an initial long list of options and sift them to provide a shortlist. Record all the options considered and the reasons for rejecting those not shortlisted. The shortlist of options should include a baseline Status Quo or Do Minimum option and a suitable number of alternative Do Something options (usually at least two). The status quo should normally be short-listed and appraised even where it is not considered to be a realistic option Its function is to provide a benchmark so that the VFM of the alternative 'do something' options may be judged by reference to current service provision. The exception to this requirement is where the appraisal concerns the introduction of a wholly new service, that is, where there is no existing provision to appraise.
25 Section 4: Monetary Costs and Benefits of Options Appraisals should include all the costs and benefits to Northern Ireland arising from the project, not just those to a particular organisation or sector e.g. all costs and benefits to the public, private and third sectors should be included. Costs and benefits should be valued in economic cost terms, which are generally reflected by using current market prices. All the assets and other resources employed by each option should be costed, even if they have already been purchased. This is because they have an opportunity cost value i.e. if not used in this project they could be put to an alternative use. Calculate the Net Present Value (NPV) for each option where cash flows of options differ over the time period or when a project spans greater than 5 years. However decision whether or not include NPV should be considered on a case by case basis. Use the NPC spreadsheet at the NIGEAE website and append the NPC calculation for each option to the pro forma. In the simplest cases, the table in Section 4 may be used instead. Create a table for each option, adjusting the no. of columns to reflect the years of the project s life. Treat the current financial year as Year 0. Set out the expected annual revenue costs for each option. Express the figures in real terms i.e. held constant at today s prices. The checklist of typical costs at the NIGEAE website should help identify relevant costs. Financial savings arising from an option will be reflected in its lower costs compared to the Status Quo. Do not double count by also including them separately as benefits. Other monetised benefits may be taken into account but are likely to be rare in small expenditure cases. Most benefits will be covered in the non-monetary Section 5 below. For particularly uncertain cost assumptions, consider using sensitivity analysis to illustrate how NPCs and option rankings are affected by varying these assumptions. For more in-depth guidance, see Step 5 and Step 8 of NIGEAE. Section 5: Non-Monetary Costs and Benefits List and describe the benefits of each option (benefits will relate closely to the objectives), Either the weighted scoring method can be used or impact assessment, depending on which is appropriate. The weighted scoring method. This involves assigning numerical weights to each factor to reflect its comparative importance; scoring the performance of each option against each factor on a numerical scale; and calculating a 'weighted score' for each option. Detailed guidance on the use of this approach is given in The Weighting and Scoring Method. Impact Assessment. This method tabulates the impact of each option upon each non-monetary factor in an impact statement or performance matrix. It involves
26 assessing the impact of each option upon each relevant objective or assessment criterion. The presentation is often in tabular form, with the cells of the table containing suitable quantitative impact measures or indicators; and/or qualitative impact analysis. An accompanying commentary summarising the main trade-offs and other features of the analysis should generally be provided. Explain rationale for weighting and scoring. Section 6: Assess Risks and Uncertainties Identify and describe the risks that the project may face. Explain how these compare under the various options using the table below. Identify measures to ensure that each risk is appropriately managed and mitigated. Explain any contingency allowances included for risks in the option costings.. For further guidance see Step 6 of NIGEAE. Section 7: Preferred Option and explanation for selection Summarise the main differences between the options e.g. in terms of key assumptions, NPCs, non-monetary impacts, risks and other factors. Identify which option is preferred and explain why. Section 8: Assess Affordability and Funding Arrangements Set out the annual capital and resource requirements for the preferred option. Figures should allow for inflation, contingencies and (where relevant) optimism bias. Resource figures should include appropriate allowance for depreciation/impairment. Identify expected sources of funding and the degree to which each funder is committed. Section 9: Project Management Explain the proposed project management structure (e.g. use of PRINCE2), key management personnel and project timetable. Where relevant, indicate the proposed approach to procurement. Consider provision for benefits management and realisation, including e.g. documentation of Benefit Profiles using the templates at the Successful Delivery NI website. A benefits profile is attached at Annex B Identify any significant management issues e.g. legal, contractual, accommodation, staff or TUS issues. Is any external consultancy support required? If so, it must be supported by a separate business case as per FD(DFP)07/12 and section 5 of the accompanying guidance note. Section 10: Monitoring, and Evaluation Arrangements Indicate arrangements for regular monitoring of the project s progress.
27 State proposed evaluation arrangements e.g. when it will happen, who will do it, what factors will be evaluated? For further guidance see para at Step 9 of NIGEAE Appendix A: Benefits Profile Benefit Owner: This is the name of the actual benefit owner, not the person responsible for reporting on it. This might be the SRO, but could also be someone else senior in the organisation; Baseline Value: The Baseline value can be estimated at OBC stage (This should be firmed up and accurate by the time the business case reaches FBC if applicable); Target Value: Insert the target value you hope to attain for the benefit Measurement: Explain how and when you hope to measure and report on the benefit; Timing: Details of how often you intend to report on the realisation of the benefits; Responsibility: Who has responsibility for measuring and reporting on the benefit. For large expenditure decisions were FBC is required, i.e. > 1m, please complete the benefit profile as detailed at the following link:
28 BUSINESS CASE TEMPLATE REVENUE FUNDING 250k - 1m SECTION 1(a): PROJECT BACKGROUND AND STRATEGIC CONTEXT SECTION 1(b): DEMONSTRATE THE NEED FOR THE PROJECT
29 SECTION 2(a): OBJECTIVES Project Objectives Measurable Targets [add more objectives as appropriate] SECTION 2(b): CONSTRAINTS Constraints 1. Measures to address constraints [add more constraints as appropriate] SECTION 3: IDENTIFY AND SHORTLIST OPTIONS Option Number/ Description Shortlisted (S) or Rejected (R) Reason for Rejection 1. Status Quo - continue with existing arrangements S (if applicable)
30 SECTION 4: MONETARY COSTS AND BENEFITS OF OPTIONS Option 1: Status Quo Yr 0 Yr 1 Yr 2 Yr 3 Yr 4 Yr 5.. Totals Capital Costs (a) Total Capital Cost Revenue Costs Include details (b) Total Revenue Cost (c) Total Cost = (a) + (b) (d) Disc 3.5%pa (e) NPC = (c) x (d) COST ASSUMPTIONS: (Expand as appropriate) SECTION 5: NON MONETARY COSTS AND BENEFITS Weighting method Non-Monetary Factor etc Weighting (%) Score Option 1 Score Option 2 Score Option 3 Total 100%
31 Or Impact assessment Non-Monetary Factor Option 1 Option 2 Option etc Rationale for weighting and scoring SECTION 6: ASSESS RISKS AND UNCERTAINTIES Risk Description Likely impact of Risk H/M/L Opt 1 Opt 2 Opt 3 Opt 4 State how the options compare and identify relevant risk management / mitigation measures Overall Risk (H/M/L):
32 SECTION 7: PREFERRED OPTION AND EXPLANATION FOR SELECTION SECTION 8: ASSESS AFFORDABILITY AND FUNDING ARRANGEMENTS Required: Capital Resource Existing Budget: Capital Resource Additional budget Required: Capital Resource Yr s Yr s Yr s Yr s Totals 000 s Affordability narrative [expand as necessary] SECTION 9: PROJECT MANAGEMENT (Please see Benefits Realisation Plan in Annex B) [expand as necessary]
33 SECTION 10: MONITORING AND EVALUATION [expand as necessary]
34 Revenue Expenditure 250k - 1m - APPENDIX A Benefit Profile (Small Projects) Signed off by: Date: Benefit Owner Benefit Baseline value Target Value Measurement Timing Responsibility
35 Annex E POST PROJECT EVALUATION GUIDANCE NOTES This Post-Project Evaluation (PPE) template should be prepared in line with NIGEAE Guidance see To be completed for all Revenue Business Cases Please complete this template with proportionate effort, i.e. detail provided should be commensurate with the size of the bid. This is a general template and the boxes and tables may be enlarged or modified to suit the particulars of the case in hand. When necessary, refer to the NIGEAE website The purpose of a PPE is to: Evaluate the effectiveness of a project in realising the proposed benefits as outlined in the Business Case; Compare planned costs and benefits with actual costs and benefits to allow an assessment of the project's overall value for money to be made; Identify particular aspects of the project which have affected benefits either positively or negatively; recommendations for future projects can then be derived; and Reveal opportunities for increasing the project's yield of benefits, whether they were planned or became apparent during or after implementation, and to recommend the actions required to achieve their maximisation. 1.0 Background Please provide a brief description of the project, its objectives, and an outline of its progress, identifying those who played major roles, e.g. SRO, Project Manager, Senior User. Please provide details of how the PPE has been carried out (i.e. methodology used to ascertain if objectives have been met) and record any constraints that were met in carrying out the PPE. Please provide details of when the project started, giving explanations for any lag. 2.0 Achievement of Objectives Please list objectives as set out in business case and advise how they have been achieved. Look at project outcomes and state how and why outcome(s) differed (if at all) from those set out in the business case and project plan.
36 3.0 Benefits and Outcomes Include a summary of how fully the claimed benefits/outcomes were realised. Any benefits which have emerged from the use of the system which were not predicted in the Business Case should be outlined. Include comment on whether the costing assumptions and estimates of targeted benefits made at the project's inception proved realistic; a comparison of estimated and actual cost savings and efficiency improvements. Any dis-benefits, expected or unexpected, should be outlined, along with an estimate of their impact on the business. 4.0 Value for Money Provide an assessment (based on achievement of objectives and any variances noted as per above) of whether the project represented good value for money. 5.0 Recommendations and Lessons Learned This section should include lessons to be learned, covering all aspects of the project which relate to the realisation of benefits. Lessons may refer to the identification, quantification or planning of benefits, to project management, to user monitoring and control of benefit onset etc. PPEs should be used to promote good practice and the results should be shared to ensure that key lessons are identified and disseminated; It should also identify actions which have the potential to increase the benefits to be reaped from the project. These recommendations should be based on consideration of how to enhance both expected and unexpected benefits, how to minimise the effects of dis-benefits, and how to develop further, if possible, the beneficial use of systems or services delivered. Any broader lessons which may be learnt from the project should be outlined, including problems encountered and how they were mitigated. If they are felt to be necessary, further monitoring, specific benefit reviews or full PPEs should be recommended. Recommendations for the circulation of the PPE report should be made. 6.0 Timeframe for completion PPE should be planned before project closure; It should be conducted 4 to 12 months after project closure, led by an individual independent of the Project Board and Project Team. Any reasons for delay in submission of a completed PPE should be clearly specified.
37 POST PROJECT EVALUATION Name of organisation Project Title Total Cost Start date Completion date PPE Due Date SECTION 1: INTRODUCTION Background (a brief description of the project and its objectives) Please give details of commencement of scheme, when staff were appointed and when full capacity was achieved. SECTION 2: ACHEIVEMENT OF OBJECTIVES Did this Investment meet objectives given in IPT? Please give details. How they were achieved? Objectives [add more objectives as appropriate]
38 SECTION 3: BENEFITS AND OUTCOMES Outcomes planned in original Business Case Actual Outcomes (Please comment on variances or delays etc.) [add more outcomes as appropriate] How were benefits and outcomes evidenced? Please give details of such. SECTION 4: VALUE FOR MONEY What methodology was used to assess quality and value for money of service provided? What were the conclusions? SECTION 5: RECOMMENDATIONS AND LESSONS LEARNED What problems were encountered during implementation of the project, and how where such resolved? What was learned, how has this been disseminated, and to whom? Please provide supporting evidence.
39
Public Private Partnerships in the National Health Service: The Private Finance Initiative
Public Private Partnerships in the National Health Service: The Private Finance Initiative Good Practice Section 3: Technical Issues Contents 1. Introduction 3 2. Risk analysis 4 3. The Public Sector Comparator
More informationCOMMON APPRAISAL FRAMEWORK FOR TRANSPORT PROJECTS AND PROGRAMMES
COMMON APPRAISAL FRAMEWORK FOR TRANSPORT PROJECTS AND PROGRAMMES March 2016 OVERVIEW OF 2016 COMMON APPRAISAL FRAMEWORK This guidance document replaces the 2009 Guidelines on a Common Appraisal Framework
More informationLisburn Primary and Community Care Project
Lisburn Primary and Community Care Project Appointment Business Case DRAFT v0.2 Section 1 Executive Summary 0 Contents 1 Executive Summary... 1 Introduction... 1 Project Background... 1 Section 2: Update
More informationSection 1 OVERVIEW OF PROJECT DEVELOPMENT PROCESS
Section 1 OVERVIEW OF PROJECT DEVELOPMENT PROCESS 1.1 Introduction Before the Sanctioning Authority can consider approving expenditure proposals, certain analysis needs to be carried out and presented
More informationPROJECT BUSINESS PLAN RURAL DEVELOPMENT PROGRAMME PRIORITY 6: SOCIAL INCLUSION, POVERTY REDUCTION AND RURAL DEVELOPMENT
Appendix 6E PROJECT BUSINESS PLAN RURAL DEVELOPMENT PROGRAMME 2014-2020 PRIORITY 6: SOCIAL INCLUSION, POVERTY REDUCTION AND RURAL DEVELOPMENT SCHEMES BASIC SERVICES, VILLAGE RENEWAL AND RURAL BROADBAND
More informationNEPAD/Spanish Fund for African Women s empowerment
NEPAD/Spanish Fund for African Women s empowerment Project Proposal Format Annex 0 1 P age Proposal Format Proposal Cover Page: PROPOSAL TO THE NEPAD- SPANISH FUND FOR AFRICAN WOMEN s EMPOWERMENT Organization
More informationPage Paragraph Content Introduction 4 DEL 5 Expenditure not proposed in the budget 6-7 Procurement
Page Paragraph Content 3 1-3 Introduction 4 DEL 5 Expenditure not proposed in the budget 6-7 Procurement 4 8-10 Competition 11 Best value for money 12 Timeliness in paying bills 13 Novel, contentious or
More informationFinance Committee. Inquiry into methods of funding capital investment projects. Submission from Audit Scotland
Finance Committee Inquiry into methods of funding capital investment projects Submission from Introduction is the public sector audit agency covering the external audit of the majority of public sector
More informationBASE CAPEX PROPOSAL - QUALITATIVE INFORMATION
SCHEDULE F BASE CAPEX PROPOSAL - QUALITATIVE INFORMATION cl. 7.3.1, 9.1.1 F1 Qualitative information required in a base capex proposal For the purpose of clause 7.3.1 (1) a base capex proposal must, in
More informationRESERVE BANK OF MALAWI
RESERVE BANK OF MALAWI GUIDELINES ON INTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS (ICAAP) Bank Supervision Department March 2013 Table of Contents 1.0 INTRODUCTION... 2 2.0 MANDATE... 2 3.0 RATIONALE...
More informationPRINCE2 - Business Case
Created/updated 05/11/17 PRINCE2 - Business Case Downloaded from stakeholdermap.com. Visit Prince2 Templates for more Prince2 downloads. Get a Business Case Mind Map Project Name:
More informationUNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DECISION MAKING PROCESS
UNIVERSITY OF CAMBRIDGE INFORMATION SERVICES COMMITTEE PROJECT AND PROGRAMME GOVERNANCE: DECISION MAKING PROCESS Document Status: Approving Body: Last Update: Author: Approved Information Services Committee
More informationIntegrated Capital Planning Manual
0 Integrated Capital Planning Manual August 2017 0 Contents Introduction... 1 Annual Integrated Capital Planning Cycle... 3 Integrated Capital Plan Submission... 8 Business Case Guide and Template... 11
More informationSolvency II Detailed guidance notes for dry run process. March 2010
Solvency II Detailed guidance notes for dry run process March 2010 Introduction The successful implementation of Solvency II at Lloyd s is critical to maintain the competitive position and capital advantages
More informationSCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS
SCOTTISH FUNDING COUNCIL CAPITAL PROJECTS DECISION POINT PROCESS Incorporating amendments by Scottish Futures Trust (Proposals for Decision Points 2 5 Only) Executive summary... 1 Section 1: Introduction
More informationINTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS GUIDELINE. Nepal Rastra Bank Bank Supervision Department. August 2012 (updated July 2013)
INTERNAL CAPITAL ADEQUACY ASSESSMENT PROCESS GUIDELINE Nepal Rastra Bank Bank Supervision Department August 2012 (updated July 2013) Table of Contents Page No. 1. Introduction 1 2. Internal Capital Adequacy
More informationOVERVIEW OF DETAILED APPRAISAL PROCESS
Section 3 OVERVIEW OF DETAILED APPRAISAL PROCESS 3.1 Introduction The detailed appraisal stage aims to provide a basis for a decision on whether to proceed with a project in principle or not. It includes
More informationPRINCE2-PRINCE2-Foundation.150q
PRINCE2-PRINCE2-Foundation.150q Number: PRINCE2-Foundation Passing Score: 800 Time Limit: 120 min File Version: 6.0 Exam PRINCE2-Foundation Version: 6.0 Exam A QUESTION 1 What process ensures focus on
More informationPRINCE2 Sample Papers
PRINCE2 Sample Papers The Official PRINCE2 Accreditor Sample Examination Papers Terms of use Please note that by downloading and/or using this document, you agree to comply with the terms of use outlined
More informationImplementing IFRS 15 Revenue from Contracts with Customers A practical guide to implementation issues for the aerospace and defence industry
Implementing IFRS 15 Revenue from Contracts with Customers A practical guide to implementation issues for the aerospace and defence industry Contents About this guide 1 Overview 2 Scope and core principle
More informationPrince2 Foundation.exam.160q
Prince2 Foundation.exam.160q Number: Prince2 Foundation Passing Score: 800 Time Limit: 120 min PRINCE2 Foundation PRINCE2 Foundation written Exam Sections 1. Volume A 2. Volume B Exam A QUESTION 1 Which
More informationSouth East Local Enterprise Partnership Business Case Review Pro-Forma: Strategic Case
INDEPENDENT TECHNICAL EVALUATION (GATE 1 & 2) Scheme Name: Date Completed: Completed By: South East Local Enterprise Partnership Business Case Review Pro-Forma: Strategic Case Question Value / Source R/A/G
More information2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias
2.6 STEP SIX: Assess Risks and Adjust for Optimism Bias 2.6.1 In appraisals, there is always likely to be some difference between what is expected and what eventually happens, because of biases unwittingly
More informationProject Sponsor Group Handbook
VERSION 6 UNIVERSITY OF OXFORD Project Sponsor Group Handbook May 2015 Project Sponsor Group Handbook, Version 6, 01/05/15 CONTENTS 1. INTRODUCTION... 3 2. CONTEXT... 4 3. PROJECT SPONSOR GROUP MEMBERSHIP...
More informationHSC Business Services Organisation Board
Paper BSO 25/2009 HSC Business Services Organisation Board Risk Management 1. Purpose of this report The purpose of this report is to brief the Board on the BSO Risk Management process. 2. Background HSC
More informationBraindumps.PRINCE2-Foundation.150.QA
Braindumps.PRINCE2-Foundation.150.QA Number: PRINCE2-Foundation Passing Score: 800 Time Limit: 120 min File Version: 29.1 http://www.gratisexam.com/ I was a little apprehensive at first about an online
More informationProject Administration Instructions
Project Administration Instructions PAI 6.07A Page 1 of 4 PROJECT COMPLETION REPORT FOR SOVEREIGN OPERATIONS 1 A. Objective and Scope 1. The main objective of a project completion report (PCR) 1 is to
More informationUN-Habitat Policy For Implementing Partners. UN-Habitat. Policy For. Partners
UN-Habitat Policy For Implementing Partners 01 Version Date Author/Reviewer Status V1 06.12.2016 Mohamed Robleh Circulated for SMB comments V2 27.01.2017 Andrew Cox Approved For further information, please
More informationAppendix 2 CLAIMS MANAGEMENT POSITIONAL STATEMENT. Introduction
CLAIMS MANAGEMENT POSITIONAL STATEMENT Appendix 2 Introduction 1 This report provides the Board with a statement of current ongoing claims, both personal injury and clinical negligence brought against
More informationModule. Governor Training Materials. Financial management.
Governor Training Materials Module Financial management Further Education Funding Council June 2000 www.fefc.ac.uk/documents/othercouncilpublications Financial management Module For suggestions on how
More information3Ts Hospital Redevelopment Programme Full Business Case
3Ts Hospital Redevelopment Programme Full Business Case Economic Case February 2016, v13 Contents Introduction... 4 The FBC Economic Case - Requirements... 4 The OBC Economic Case Conclusion... 4 Changes
More informationDoing the right projects how the five case model can help
Doing the right projects how the five case model can help 1 Agenda JL 1. Characteristics of the right projects. 2. The five case model and the development of the business case. 3. Identifying the right
More informationStrategic Business Case. Estates Guidance and Activity DataBase
Strategic Business Case Estates Guidance and Activity DataBase November 2016 You may re-use the text of this document (not including logos) free of charge in any format or medium, under the terms of the
More informationIPP TRANSACTION ADVISOR TERMS OF REFERENCE
IPP TRANSACTION ADVISOR TERMS OF REFERENCE Terms of reference for transaction advisor services to the Government of [ ] for the [insert description of the project] (the Project ). Contents 1. Introduction
More informationPolicy and Procedures
Procurement Policy and Procedures Page 1 of 23 Document Version Control Version Description Date Approval Number 0.1 for Discussion to P&R 01/04/2003 P&R noted 0.2 for Discussion to P&R 30/04/2003 P&R
More informationPOLICY AND GUIDELINES ON THE ACCEPTANCE OF, AND EXPENDITURE ON, GIFTS AND HOSPITALITY
POLICY AND GUIDELINES ON THE ACCEPTANCE OF, AND EXPENDITURE ON, GIFTS AND HOSPITALITY Revised March 2016 D110316 POLICY AND GUIDELINES ON THE ACCEPTANCE OF, AND EXPENDITURE ON, GIFTS AND HOSPITALITY POLICY
More informationActualtests.PRINCE2Foundation.120questions
Actualtests.PRINCE2Foundation.120questions Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version: 4.8 http://www.gratisexam.com/ PRINCE2 Foundation PRINCE2 Foundation written Exam 1. Dump
More informationRisk Management Procedure. Version Number: 6.0 Controlled Document Sponsor: Controlled Document Lead:
Risk Management Procedure CONTROLLED DOCUMENT CATEGORY: CLASSIFICATION: PURPOSE Controlled Document Number: Procedure Governance To detail the procedure for the management of risk 419 Version Number: 6.0
More informationUNIVERSITY OF ABERDEEN RISK MANAGEMENT FRAMEWORK
UNIVERSITY OF ABERDEEN RISK MANAGEMENT FRAMEWORK 1 TABLE OF CONTENTS FIGURES AND TABLES... 3 1. INTRODUCTION... 4 2. KEY TERMS AND DEFINITIONS... 5 2.1 Risk... 5 2.2 Risk Management... 5 2.3 Risk Management
More informationThe University of Leeds Guidelines on Investment Decision Making: Building and Refurbishment Projects
The University of Leeds Guidelines on Investment Decision Making: Building and Refurbishment Projects Advice may be obtained from Clive Smith (Treasury Manager) E-mail: c.r.smith@adm.leeds.ac.uk Introduction
More informationGreater Bristol Bus Network Major Scheme Business Case. Chapter 1. Developing the Full Approval Major Scheme Business Case
Greater Bristol Bus Network Major Scheme Business Case Chapter 1 Developing the Full Approval Major Scheme Business Case i ii 1. The Case for Full Approval INTRODUCTION 1.1.1 Bath and North East Somerset,
More informationDecommissioning Basis of Estimate Template
Decommissioning Basis of Estimate Template Cost certainty and cost reduction June 2017, Rev 1.0 2 Contents Introduction... 4 Cost Basis of Estimate... 5 What is a Basis of Estimate?... 5 When to prepare
More informationThe PRINCE2 Practitioner Examination. Sample Paper TR. Answers and rationales
The PRINCE2 Practitioner Examination Sample Paper TR Answers and rationales For exam paper: EN_P2_PRAC_2017_SampleTR_QuestionBk_v1.0 Qu Correct Syll Rationale answer topic 1 A 1.1a a) Correct. PRINCE2
More informationFundamentals of Project Risk Management
Fundamentals of Project Risk Management Introduction Change is a reality of projects and their environment. Uncertainty and Risk are two elements of the changing environment and due to their impact on
More informationSection 6 IMPLEMENTATION, MONITORING AND EVALUATION
Section 6 IMPLEMENTATION, MONITORING AND EVALUATION This section seeks to explain the responsibilities that the Department, Agencies and other public bodies have once a proposal has been appraised. It
More informationContents INTRODUCTION...4 THE STEPS IN MANAGING RISKS ESTABLISH GOALS AND CONTEXT IDENTIFY THE RISKS...8
Contents INTRODUCTION...4 THE STEPS IN MANAGING RISKS...4 1. ESTABLISH GOALS AND CONTEXT...5 2. IDENTIFY THE RISKS...8 Identifying the risks... 8 Identify the sources of the risks... 8 Identify the impact
More information(Notices) COURT OF AUDITORS
9.2.2010 Official Journal of the European Union C 32/1 IV (Notices) NOTICES FROM EUROPEAN UNION INSTITUTIONS, BODIES, OFFICES AND AGENCIES COURT OF AUDITORS Report on the audit of the operational efficiency
More informationRisk Management Strategy
Risk Management Strategy 2016 2019 Version: 6 Policy Lead/Author & Deputy Director of Quality position: Ward / Department: Nursing Directorate Replacing Document: Version 5 Approving Committee Quality
More informationIllustrative IPSAS Entity Financial Statements Public Sector Entity (PSE) Year ended 31 December [January 2016]
Illustrative IPSAS Entity Financial Statements Public Sector Entity (PSE) Year ended 31 December [January 2016] Introduction A cornerstone of accountability is fair and transparent reporting of transactions
More informationThe Society of Actuaries in Ireland. Actuarial Standard of Practice INS-1, Actuarial Function Report
The Society of Actuaries in Ireland Actuarial Standard of Practice INS-1, Actuarial Function Report Classification Mandatory MEMBERS ARE REMINDED THAT THEY MUST ALWAYS COMPLY WITH THE CODE OF PROFESSIONAL
More informationPRINCE2. Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version:
PRINCE2 Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version: 1.0 Exam M QUESTION 1 Identify the missing word(s) from the following sentence. A project is a temporary organization that is
More informationIMPORTANT NOTICE TO READERS
IMPORTANT NOTICE TO READERS Please read below for the terms and conditions on which you may read this report. In reading this report you will be deemed to have agreed to the terms and conditions set out
More informationA CEPR / DFID Research Initiative MAJOR RESEARCH GRANT BUDGET GUIDELINES
Coordinated by: In partnership with: A CEPR / DFID Research Initiative MAJOR RESEARCH GRANT BUDGET GUIDELINES 2017-2020 Contents 1 Introduction... 2 2 General rules... 2 3 Definition of Costs... 2 3.1
More informationA simplifi ed approach to documentation and risk assessment for small to medium businesses
BUSINESS SEGMENT SMALL TO MEDIUM BUSINESSES AUDIENCE GUIDE FORMAT NAT 12032-03.2005 PRODUCT ID INTERNATIONAL TRANSFER PRICING A simplifi ed approach to documentation and risk assessment for small to medium
More informationIntro Public-Private Partnership (P3) Finance Course
Intro Public-Private Partnership (P3) Finance Course Identifying P3 Projects and Knowing the Atmosphere Kylee Anastasi Director, Capital Projects and Infrastructure Advisory PricewaterhouseCoopers LLP
More informationOutline Business Case for Ballymena Health & Care Centre VERSION 3 SEPT 2009
Outline Business Case for Ballymena Health & Care Centre VERSION 3 SEPT 2009 1 CHAPTER 1 EXECUTIVE SUMMARY 1.1 Introduction 1.1.1 This document sets out the Strategic content and Outline Business Case
More informationRisk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:
for the Prepared by: Title: Address: Phone: E-mail: Last revised: Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date:
More informationUCISA TOOLKIT. Major Project Governance Assessment. version 1.0
UCISA TOOLKIT Major Project Governance Assessment version 1.0 Contents Introduction 1 Roles and responsibilities 2 Definition of a Major Project 3 Guidance for using the Toolkit 4 Governance elements 4
More informationProject Sponsor Group Handbook
VERSION 3 UNIVERSITY OF OXFORD Project Sponsor Group Handbook April 2013 Authorship Friends and colleagues would like to remember with affection Bárbara Galanes-Álvarez who passed away after a sudden and
More information3. Minutes of Governance and Audit Committee Meeting held on 15 January 2013 GAC 17/2013
NORTHERN IRELAND HEALTH AND SOCIAL CARE BUSINESS SERVICES ORGANISATION GOVERNANCE AND AUDIT COMMITTEE Minutes of the Governance and Audit Committee (GAC) which took place on Tuesday, 16 April 2013 at 11:00am
More informationTopic RISK MANAGEMENT Procedure Category Risk Management Updated 07/2011
Topic RISK MANAGEMENT Procedure 07.01 Category Risk Management Updated 07/2011 RELATED POLICIES, PROCEDURES AND FORMS Policies Procedures Forms Risk Management Policy Code of Conduct Public Interest Disclosure
More informationDevelopment Cooperation Development Education Partnership Fair. Writing a successful co financing application
Development Cooperation Development Education Partnership Fair Writing a successful co financing application 3 sessions to guide project preparation Session 1: Deciding on stakeholders and defining problems/issues.
More informationRisk Management. Webinar - July 2017
Risk Management Webinar - July 2017 Compiled by: Raaghieb Najjaar, Yaeesh Yasseen & Rashied Small Adapted and Facilitated by: Professor Enslin J. van Rooyen Risk Management - June 2017 2 Defining Risk
More informationMPA/MPS Capital Strategy
Appendix 1 MPA/MPS Capital Strategy 2005 2010 July 2004 Draft Page 1 of 13 Contents Section 1 Context sheet Page General 3 Capital and Revenue Budgets 3 Section 2 Capital Strategy Introduction 5 Strategic
More informationChapter 2 Department of Supply and Services Public-Private Partnership: Eleanor W. Graham Middle School and Moncton North School
Department of Supply and Services - Public-Private Partnership: Chapter 2 Department of Supply and Services Public-Private Partnership: Eleanor W. Graham Middle School and Moncton North School Contents
More informationRisk Management. Seminar June Compiled by: Raaghieb Najjaar, Yaeesh Yasseen & Rashied Small
Risk Management Seminar June 2017 Compiled by: Raaghieb Najjaar, Yaeesh Yasseen & Rashied Small Defining Risk Risk reflects the chance that the actual event may be different than the planned / expected
More informationFinancial planning handbook
Financial planning handbook This financial planning handbook sets out the framework for completing financial plans for sixth form colleges and other further education colleges for 2016 to 2018. April 2016
More informationRISK MANAGEMENT FRAMEWORK
RISK MANAGEMENT FRAMEWORK Approving authority Approval date University Council 5 August 2013 (3/2013 meeting) Advisor Vice President (Corporate Services) vpcorporateservices@griffith.edu.au (07) 373 57343
More informationPRINCE2 Sample Papers
PRINCE2 Sample Papers The Official PRINCE2 Accreditor Sample Examination Papers Terms of use Please note that by downloading and/or using this document, you agree to comply with the terms of use outlined
More informationPlanning Construction Procurement. A guide to risk and value management
Planning Construction Procurement A guide to risk and value management ISBN: 978-1-98-851708-7 (online) First published October 2015 Revised October 2016 New Zealand Government Procurement PO Box 1473
More informationMINI GUIDE. Project risk analysis and management
MINI GUIDE Project risk analysis and management Association for Project Management January 2018 Contents Page 3 Introduction What is PRAM? Page 4 Page 7 Page 9 What is involved? Why is it used? When should
More informationRedevelopment of MOD Main Building
Ministry of Defence Redevelopment of MOD Main Building REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 748 Session 2001-2002: 18 April 2002 LONDON: The Stationery Office 0.00 Ordered by the House of Commons
More informationNIRS 2: Contract extension. REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session : 14 November 2001
NIRS 2: Contract extension REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 355 Session 2001-2002: 14 November 2001 The National Audit Office scrutinises public spending on behalf of Parliament. The Comptroller
More informationMODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS
Advanced Project Management MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS 06 07 November 2018 Facilitator: Mr Mondli Mbambo Module Purpose Project Risk & Procurement Managment Knowledge Risk
More informationScouting Ireland Risk Management Framework
No. SID 124A/15 Gasóga na héireann/scouting Ireland Issued Amended 20 th June 2015 Deleted Source: National Management Committee Scouting Ireland Risk Management Framework Revision Date Description # 20/06/2015
More informationProject Integration Management
Project Integration Management The Key to Overall Project Success: Good Project Integration Management Project managers must coordinate all of the other knowledge areas throughout a project s life cycle.
More informationControl activities that are part of the process are detailed in the riskcontrol
Policy Title Previous title (if any) Cash Transfers to Implementing Partners N/A Policy objective Target audience Risk control matrix Checklist The policy and procedures outline the process for management
More informationFollow-Up on VFM Section 3.05, 2014 Annual Report RECOMMENDATION STATUS OVERVIEW
Chapter 1 Section 1.05 Ministry of Infrastructure (formerly the Ministry of Economic Development, Employment and Infrastructure) Infrastructure Ontario Alternative Financing and Procurement Follow-Up on
More informationGeorge Eliot Hospital NHS Trust - Securing a sustainable future Project. Annex A
Annex A ISOS financial submission requirements Historical financial performance NHS Foundation Trusts 1. Please provide a copy of the Annual Plan that you submitted to Monitor for 2013/14. If a revised
More informationINTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS
Guidance Paper No. 2.2.6 INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS GUIDANCE PAPER ON ENTERPRISE RISK MANAGEMENT FOR CAPITAL ADEQUACY AND SOLVENCY PURPOSES OCTOBER 2007 This document was prepared
More informationCOWENS RISK SOLUTIONS REVIEWING FIRE RISK ASSESSMENTS
COWENS RISK SOLUTIONS REVIEWING FIRE RISK ASSESSMENTS October 2014 WHEN TO REVIEW A FIRE RISK ASSESSMENT?: The Regulatory Reform (Fire Safety) Order, (FSO) and equivalent legislation in Scotland and Northern
More informationAudit Committee Annual Report to the Board
Audit Committee Annual Report to the Board Report to: Board Date: 28 September 2017 Report by: Report No: Mike Cairns, Convener of the Audit Committee Agenda Item: 13.3 PURPOSE OF REPORT This report represents
More informationSubmission on NZX Listing Rule Review Discussion Paper dated 27 September November 2017
Submission on NZX Listing Rule Review Discussion Paper dated 27 September 2017 17 November 2017 INTRODUCTION & EXECUTIVE SUMMARY 1 We welcome the opportunity to participate in the NZX listing rule review.
More information2. 5 of the 75 questions are under trial and will not contribute to your overall score. There is no indication of which questions are under trial.
The Foundation Examination Sample Paper 3 Question Booklet Multiple Choice Exam Duration: 60 minutes Instructions 1. You should attempt all 75 questions. 2. 5 of the 75 questions are under trial and will
More informationGE4. Service Redesign & Clinical Practice. Benchmarking for Locally-Priced Services
GE4 Service Redesign and Clinical Practice Benchmarking for Locally-Priced Services Scheme Code and Full Name GE4. Service Redesign & Clinical Practice Benchmarking for Locally-priced Services Section
More informationTERMS OF REFERENCE (TOR) FOR AUDITS OF UN-WOMEN NGO, GOV T, IGO AND GRANT PROJECTS
TERMS OF REFERENCE (TOR) FOR AUDITS OF UN-WOMEN NGO, GOV T, IGO AND GRANT PROJECTS TABLE OF CONTENTS Introduction... 3 A. Background... 7 B. Project Management... 7 C. Consultations with concerned parties...
More informationReport of the Advisory Committee on Administrative and Budgetary Questions
United Nations General Assembly Distr.: General 3 November 2000 Original: English A/55/543 Fifty-fifth session Agenda item 116 Review of the efficiency of the administrative and financial functioning of
More informationINTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS
Guidance Paper No. 2.2.x INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS GUIDANCE PAPER ON ENTERPRISE RISK MANAGEMENT FOR CAPITAL ADEQUACY AND SOLVENCY PURPOSES DRAFT, MARCH 2008 This document was prepared
More informationEUROPEAN STANDARD OF ACTUARIAL PRACTICE 2 (ESAP 2) ACTUARIAL FUNCTION REPORT UNDER DIRECTIVE 2009/138/EC
ACTUARIAL ASSOCIATION OF EUROPE ASSOCIATION ACTUARIELLE EUROPÉENNE 4 PLACE DU SAMEDI B-1000 BRUSSELS, BELGIUM TEL: (+32) 22 17 01 21 FAX: (+32) 27 92 46 48 E-MAIL: info@actuary.eu WEB: www.actuary.eu EUROPEAN
More informationINVEST NORTHERN IRELAND MANAGEMENT STATEMENT AND FINANCIAL MEMORANDUM
INVEST NORTHERN IRELAND MANAGEMENT STATEMENT AND FINANCIAL MEMORANDUM March 2018 1 INVEST NORTHERN IRELAND: MANAGEMENT STATEMENT Page no: 1. INTRODUCTION 3 1.1 This Document. 3 1.2 Founding Legislation;
More informationSHEFFIELD TEACHING HOSPITALS NHS FOUNDATION TRUST. EXECUTIVE SUMMARY REPORT TO THE BOARD OF DIRECTORS MEETING HELD ON 18 th DECEMBER 2013
SHEFFIELD TEACHING HOSPITALS NHS FOUNDATION TRUST M EXECUTIVE SUMMARY REPORT TO THE BOARD OF DIRECTORS MEETING HELD ON 18 th DECEMBER 2013 Subject Lead Author Status 1 Treasury Management Policy Neil Priestley
More informationEUROPEAN STANDARD OF ACTUARIAL PRACTICE 2 (ESAP 2) ACTUARIAL FUNCTION REPORT UNDER DIRECTIVE 2009/138/EC
ACTUARIAL ASSOCIATION OF EUROPE ASSOCIATION ACTUARIELLE EUROPÉENNE 4 PLACE DU SAMEDI B-1000 BRUSSELS, BELGIUM TEL: (+32) 22 17 01 21 FAX: (+32) 27 92 46 48 E-MAIL: info@actuary.eu WEB: www.actuary.eu EUROPEAN
More informationRailway Housing Association. Value for Money Strategy
Railway Housing Association Value for Money Strategy 2016-21 1 Executive Summary 1.1 Railway Housing Association (RHA) recognises that Value for Money (VFM) is a fundamental consideration for all housing
More informationBUDGETING. After studying this unit you will be able to know: different approaches for the preparation of budgets; 10.
UNIT 10 Structure APPROACHES TO BUDGETING 10.0 Objectives 10.1 Introduction 10.2 Fixed Budgeting 10.3 Flexible Budgeting 10.4 Difference between Fixed and Flexible Budgeting 10.5 Appropriation Budgeting
More informationCapital Project Approval Request
Capital Project Approval Request PMP T07 Project Number MAJ 0000 Project Title Project Description Existing Approvals EC Approval Court Approval Approved Gateway 0 To proceed to GW1 Prepare OBC / Feasibility
More informationFinancial Reporting Consolidation PEMPAL Treasury Community of Practice thematic group on Public Sector Accounting and Reporting
DRAFT 2016 Financial Reporting Consolidation PEMPAL Treasury Community of Practice thematic group on Public Sector Accounting and Reporting Table of Contents 1 Goals and target audience for the Guidance
More informationBasic Introduction to Project Cycle. Management Using the. Logical Framework Approach
Basic Introduction to Project Cycle Management Using the Logical Framework Approach Developed and Presented by: Umhlaba Development Services Umhlaba Development Services Noswal Hall, Braamfontein, Johannesburg,
More informationThe Annual Audit Letter for London Borough of Lewisham
The Annual Audit Letter for London Borough of Lewisham Year ended 31 March 2016 October 2016 Darren Wels Director T 07880 456 152 E darren.j.wells@uk.gt.com Jamie Bewick Senior Manager T 07880 456 144
More informationPEFA Training. Dakar, Senegal January & February 1, #PEFA. PEFA Secretariat
www.pefa.org #PEFA PEFA Training Dakar, Senegal January 30-31 & February 1, 2019 PEFA Secretariat Improving public financial management. Supporting sustainable development. INTRODUCTION Introductions Participant
More informationAttachment C: How capital expenditure is proposed and approved under the capex IM
ISBN no. 978-1-869455-84-2 Project no. 14.09/16274 Public version Attachment C: How capital expenditure is proposed and approved under the capex IM Transpower capex input methodology review - Proposed
More information