2 SAPARD Overview. 2.1 SAPARD in Central and Eastern Europe

Size: px
Start display at page:

Download "2 SAPARD Overview. 2.1 SAPARD in Central and Eastern Europe"

Transcription

1 Final Report 2 SAPARD Overview 2.1 SAPARD in Central and Eastern Europe This chapter provides a short overview of SAPARD describing the rural development context on which the programme is inscribed; its genesis; the rationale among needs, objectives, priorities and measures; its system of implementation, as well as the financial allocation and spending and the regulatory framework Rural Development in Central and Eastern European Countries Unlike in Northern and Western Europe, the countries in Central and Eastern Europe (CEE) have significantly larger rural populations and have traditionally had far higher number of people engaged in agriculture and food production. For some time, the longer-term changes were similar to those in western parts of Europe, namely a decrease in the importance of the agricultural sector, an increase in part-time farming, the expansion of the non-farm rural economy, as well as a significant amount of ruralurban commuting. However, the political changes in the 1990s had a profound impact on the agricultural sector and the longer-term development of rural areas. State farms and collective farms were broken up and the land was re-distributed between former owners, their heirs and others deemed entitled to land. In some countries, this process helped bring about a reversal in the drift to the cities, as the newly unemployed took advantage of the land reforms to secure small plots that helped them supplement income from other sources. In the early 1990s, but to very differing degrees, reforms opened up the markets to new actors, reducing the formal role of the state in running the economy. It was well known that the socio-economic transition in the rural areas was much more protracted than in the urban areas. For some areas, the problem was the lack of economic opportunities, whether in farming or in other industries; for others it was the collapse in local public services, which had a severe impact of the quality of rural life and encouraged those more able to move out; a third and related problem was the supposed mismatch between the actual needs for economic revival and the lower levels of human, social and financial capital available in the countryside SAPARD Principles and cornerstones Taking into account the scale of these problems SAPARD was set up within the framework of programmes for accession, namely ISPA (Instrument for Structural Policies for Pre-Accession) 1 and PHARE (Poland and Hungary: Assistance for Restructuring their Economies) 2. SAPARD was specifically devoted to rural development. 1 ISPA was the instrument aimed to provide assistance to large-scale infrastructure projects in the fields of environment and transport. It was implemented initially in the ten applicant countries of Central and Eastern Europe. Croatia started benefiting from the 1 January PHARE aimed to strengthen the public administrations and institutions to function effectively after the accession. Although when it was originally created in 1989 was implemented only in Poland and Hungary, it was later expanded to cover the ten applicant countries of Central and Eastern Europe and until 2000 the countries of the Western Balkans as well. page 23

2 SAPARD was introduced in 1999 by Council Regulation (EC) No 1268/ providing assistance for restructuring the agriculture and rural sectors of candidate countries leading up to accession. Map 1. Acceding countries eligible for SAPARD SAPARD Countries: Bulgaria, Czech Republic, Estonia, Hungary, Latvia, Lithuania, Poland, Romania, Slovakia, Slovenia and Croatia 4. 3 Council Regulation (EC) No 1268/1999 of 21June 1999, on Community Support for pre-accession measures for agriculture and rural development in the applicant countries of Central and Eastern Europe in the pre-accession period 4 As it could be seen from the map, although SAPARD covered 11 applicant countries, the present report covers only three of them, namely: Bulgaria, Romania and Croatia. The report, therefore, constitutes the completion of the previous Synthesis report delivered in November 2010, covering the other applicant countries. page 24

3 Final Report SAPARD was designed in order to address strategic needs and problems of the rural areas of the beneficiary countries, namely: The need of implementation of the acquis communautaire in candidate countries and the need to gain experience in its application and the need to face specific structural drawbacks and inequalities in the agricultural sector and the economy of rural areas in these countries. Box 1. Objectives of SAPARD Accordingly, the two corresponding overall objectives of SAPARD were formulated 5 : - Contributing to the implementation of the acquis communautaire concerning the Common Agricultural Policy (CAP) and related policy; - Solving priorities and specific problems for the sustainable adaptation of the agricultural sector and rural areas in the applicant countries. The pre-amble of the regulation explains the scope of what was intended with SAPARD: Whereas pre-accession aid for agriculture should follow the priorities of the reformed CAP; whereas such aid should be applied to priority areas to be defined for each country, such as the improvement of structures for processing agricultural and fishery products, distribution, quality control of food as well as veterinary and plant-health controls and the setting-up of producer groups; whereas it should also be possible to finance integrated rural development projects to support local initiatives and agrienvironmental measures, to improve the efficiency of farms, to adapt infrastructure as well as measures which will accelerate structural reconversion; This paragraph sets out the main aims for programmes to be supported. It also gives working definitions for the development of agriculture and for 'integrated rural development'. Concerning agriculture the scope of the regulation is clearly stated and restricted to agricultural structural policies 6. In particular, it should contribute to the preparation of the agri-food sector for their participation in the common market and the application of Community health, hygiene and quality standards. Concerning rural development the statement is more tentative ( it should be possible ). It also contributed to the development of economic activities in rural areas through investments in small businesses and rural infrastructures. In order to achieve these goals, SAPARD provided the applicant countries with a series of measures based on the following guiding principles: 1. Improving market efficiency, quality and health standards; 2. Maintaining and creating jobs and 3. Environmental protection. Accordingly, the countries were encouraged to select measures from a list of 15 eligible measures (Table 1) based on their needs and priorities. Following the principle 5 Council Regulation EC No 1268/1999, art. 1 6 At the time of the publication of this document (1999), these countries were excluded from the direct payments system - the major part of the First Pillar of the CAP. They were only to be prepared for the Second Pillar of the CAP (Rural Development) which constituted the smaller part of the CAP budget. page 25

4 of subsidiarity, the list only offered a basic menu, from which the applicant countries could create their own programme. Countries were also allowed to reallocate the original budget of SAPARD between measures based on trends of socioeconomic development, relevant new information and the results observed from the implementation of the measures, utilising the results from monitoring and evaluation. Table 1. Eligible SAPARD Measures Measure Short title of measure Full title of measure Measure I Agri-investment Investments in agricultural holdings Measure II Processing investment Improving the processing and marketing of agricultural and fishery products Measure III Vet & plant health Improving the structures for quality, veterinary and plant-health controls, for the quality of foodstuffs and for consumer protection Measure IV Agri-environment Agriculturally production methods designed to protect the environment and maintain the countryside Measure V Diversification Development and diversification of economic activities providing for multiple activities and alternative income Measure VI Farm relief Setting up farm relief and farm management services Measure VII Producer groups Setting up producer groups Measure VIII Village renewal Renovation and development of villages and protection and conservation of the rural heritage Measure IX Land improvement Land improvement and re-parcelling Measure X Land register Establishment and updating of land registers Measure XI Vocational training Improvement of vocational training Measure XII Rural infrastructure Development and improvement of rural infrastructure Measure XIII Water resources Agricultural water resources management Measure XIV Forestry Forestry, including afforestation of agricultural areas, investments in forest holdings owned by private forest owners and processing and marketing of forestry products Measure XV Technical assistance Source: Council Regulation EC No 1268/1999, art. 2 Technical assistance for the measures covered by SAPARD including studies to assist with the preparation and monitoring of the programme, information and publicity campaigns page 26

5 Final Report Box 2. Eligible measures in SAPARD and in Rural Development Programmes of EU-15 SAPARD measures are very similar to those for Rural Development Programmes (RDP) of the Member States. However, there are also differences: The scope of SAPARD is narrower, some RDP-measures are not replicated in SAPARD and others are less pronounced or less defined. On the other hand, there are measures in the field of agriculture and administration, specifically designed for the problems of Candidate Countries. Also, some measures in the field of rural development provide a larger scope for integrating non-agricultural measures. SAPARD measures are defined on Art 2 of Council Regulation (EC) No 1268/1999. The main differences between SAPARD and the RDP measures are: - Two measures, being only part of SAPARD (and not in RDP), are designed for special CEE problems and they are to support the restructuring of administration and the production system inside agriculture. Without the establishment and updating of land registers (which were missing or otherwise inadequate in many CEE countries) it would be almost impossible to apply any central, administrative control over agricultural policies. Also, the support for setting up producer groups is essential to restructure CEE production systems in a more Euro-compliant way; - In the field of human resource management only vocational training can be supported by SAPARD. Neither early retirement nor the setting up of young farmers can be subsidised. However, contrary to the CAP, vocational training is not restricted to agriculture by the legislation. - SAPARD does not include measures for Less Favoured Areas (LFA), - Environmental protection is less pronounced in SAPARD (in relation to the proportion of the budget and the range of measures). SAPARD does not include a wide range of agri-environmental measures and measures specifically targeted at environmental protection in agricultural rural areas; - A few RDP-measures mainly targeted at endogenous development are not part of SAPARD (marketing of quality agricultural products; basic services for rural economies and populations; promotion of tourism and crafts); thus nonagricultural economic activities are supported in SAPARD to a lesser degree than in the RDP. The most important intended impact of these projects, in line with the overall objectives of SAPARD, can be concluded as follow: The agricultural sector is better prepared for accession (i.e. better compliance with EU standards and acquis communautaire, improved competitiveness on the EU market); Rural economies are better prepared for accession (i.e. improvement in solving priority and specific rural problems); Countries are better prepared for the implementation and utilisation of postaccession rural development programmes. page 27

6 Table 2 below summarises the overall rationale and Intervention Logic of SAPARD Table 2. Overall rationale and Intervention Logic of SAPARD Needs Overall objectives Eligible measures Intended overall impacts Need for the implementation of the acquis communautaire in candidate countries Need to gain experience in its application Need to address specific structural drawbacks and inequalities in the agricultural sector and the economy of rural areas Contributing to the implementation of the acquis communautaire concerning the common agricultural policy and related policies Solving priority and specific problems for the sustainable adaptation of the agricultural sector and rural areas in the applicant countries I. Agri-investment II. Processing investment III. Vet & plant health IV. Agri-environment V. Diversification VI. Farm relief VII. Producer groups VIII. Village renewal IX. Land improvement X. Land register XI. Vocational training XII. Rural infrastructure XIII. Water resources Agricultural sectors are better prepared for accession (compliance with EU standards, competitiveness on EU markets) Rural economies are better prepared for accession; i.e. improvement in solving priority and specific rural problems Countries are better prepared for the implementation and utilisation of post-accession rural development programmes XIV. Forestry XV. Technical assistance page28

7 Final Report Regulatory framework SAPARD constituted the first time in the history of the EU that the management of external aid was conferred on applicant countries on a fully decentralised basis. This required an enormous legislative and administrative effort both on the side of the Commission and of the applicant countries. Together with the main legislative act of SAPARD, namely Council Regulation (EC) No 1268/1999 setting up the basis rules governing the programme, several acts were delivered over the years amending or clarifying certain aspects regarding the implementation of the Programme. The most important are: the mentioned Council Regulation (EC) No 1268/1999 of 21 June 1999 on Community support for pre-accession measures for agriculture and rural development in the applicant countries of central and eastern Europe in the preaccession period; Commission Regulation (EC) No 2759/1999 of 22 December 1999 laying down rules for the application of Council Regulation (EC) No 1268/1999 on Community support for pre-accession measures for agriculture and rural development in the applicant countries of central and eastern Europe in the preaccession period and Commission Regulation (EC) No 2222/2000 of 7 June 2000 laying down financial rules for the application of Council Regulation (EC) No 1268/1999 on Community support for pre-accession measures for agriculture and rural development in the applicant countries of Central and Eastern Europe in the preaccession period. Amended by Regulation (EC) No 2252/2001 and following. Finally, as set out in the Council Regulation (EC) No 1268/1999, the Commission prepared ten annual reports from2000 to 2009 on the implementation of SAPARD in the applicant countries. The reports covered the support granted and progress made towards achieving the objectives of the programme System of implementation Unlike the other pre-accession instruments (PHARE and ISPA), SAPARD was based on a decentralised management of aid; management was conferred to designated agencies in the beneficiary countries. The SAPARD agencies, consisting of an Implementing and a Paying Agency - usually either located in the National Ministry of Agriculture 7 or established as separate yet supervised entities - were responsible for project selection, management, arranging finance and carrying out controls. This approach was similar to the one developed for the Managing and Paying Authorities in Programmes under the Community legislation for Member States implementing the European Agricultural Guidance and Guarantee Fund (EAGGF) 8. Ideally the SAPARD agencies would become the later Authorities for the Common Agricultural Policy. This decentralised structure offered a first practical opportunity for Candidate Countries to develop the structures and build the capacity to manage and administer EU rural development funds as actual Member States, therefore assessing whether they were mature for accession. 7 Political reforms and restructuring have often caused (and continue to do so) the names of the responsible ministries to change. For ease of reading they are generically called Ministry of Agriculture in this report. 8 See also Council Regulation (EC) No 1257/1999of 17 May 1999on support for rural development from the European Agricultural Guidance and Guarantee Fund (EAGGF) Page 29

8 The Set-up and implementation of SAPARD was based on the following steps: Design and approval of the National Agriculture and Rural Development Plan (NARDP 9 ): The competent country authorities drew the National Agriculture and Rural Development Plan identifying the needs of the agricultural sector, the strategy proposed, its quantified objectives, the geographical scope and the selected SAPARD measures. The Plan, after compulsory consultations with the socio-economic partners at the national level (in line with the principle of partnership 10 ), was adopted by the countries andreviewed by the Commission services. Finally the Plan, after positive review by the STAR Committee, was finally approved by the EC as a SAPARD Programme. Approval of the accreditation of the SAPARD agencies: SAPARD agencies were responsible for project selection, management, arranging finance, carrying out controls and disbursing payments based on expenditures really incurred by beneficiaries. They were subject to independent audits by the Commission. Each SAPARD implementation system consisted of two branches : the Managing Authority responsible for drawing up and monitoring the SAPARD Programme (checking applications, carrying out on the spot-checks, issuing approval for works to commence and monitoring the progress of the projects) and the SAPARD Paying Agency responsible for all financial procedures, including checking payment claims and authorising payments. Accreditation of the national SAPARD agencies by the national competent authority and confirmed by the National Authorising Officer had finally to be approved by the Commission in its conferral of management decision to ensure that it met the accreditation criteria and that the national structures involved in the management of the programme were satisfactory) so that allocated funds could start to flow. Signature and conclusion of the Multi-Annual Financial Agreement (MAFA): Prior to accession no Community legislation was applicable in the candidate countries.consequently, a bilateral agreement - the MAFA - was signed between the EC and the beneficiary countries laying down the main requirements for the management and control of the SAPARD funds throughout the programming period. In accordance with the Commission s communication, MAFA consisted of the following parts: - Financial management, laying down the detailed provisions for the execution of SAPARD on a decentralised basis in each applicant country; - Management, Monitoring and Evaluation of the Programme,: describing the monitoring and evaluation requirements necessary to determine the effectiveness and efficiency of the programmes. - General Provisions on issues such as co-ordination with other instruments (for example, PHARE and ISPA), taxation and customs, import and export rules; - Rules on Quarterly and Annual Declarations of expenditure defining the forms to be completed and the rules to be respected in the declaration of expenditure; 9 The full title is NARPD over period under SAPARD. In this report it will be referred as the SAPARD Programme. 10 The principle of partnership implies that any appropriate organizations representing the civil society, environmental or non-governmental organizations, can participate in the negotiations concerning the use of structural funds. Page 30

9 Final Report - Guidelines for Certifying Body, setting out the form, scope and contents of the certificate and report of the body performing the certification of the accounts of the SAPARD Agency and National Fund. - Community legislation referred to in Regulation (EC) No. 2222/2000 on financial rules for SAPARD adapted for the specific MAFA and - Dispute settlement provisions describing the procedure to be followed in the event of a dispute. The MAFA was based, among others, on the following criteria: - Full decentralisation of management of aid by an agency established under the responsibility of each country; - Financial allocations to the programmes based on differentiated appropriations with commitment and payment entitlements following the rules of rural development assistance for Member States (RD); - Application of Clearance of Accounts procedures in line with the Financial Regulation of the EU. Based on those elements the MAFA introduced a system of Programme Management and Payment procedures, which are comparable to those of the Structural Funds and Rural Development systems Financial allocations and spending SAPARD had an initial annual budget for the year 2000 of 529 Million EUR (1999 prices) or about 24% of the total allocation to pre-accession activities under the three instruments (PHARE having Million EUR and ISPA Million EUR per year). The allocation of funds in the countries - as set up by the art. 7(3) of the Council Regulation EC No 1268/ was decided upon a formula attributing different weights at the following objective criteria: GDP per capita in purchasing power; Farming population; Agricultural area; Specific territorial situation. 90% of funding was allocated to the territories with 65% or more of areas for agriculture and with the share of the agricultural workforce equal to or greater than 35%. The remaining 10% of the funds were allocated on the basis of specific territorial situations. Additionally the final amount could be slightly modified according to the contribution of agriculture to GDP 11. As can be seen in Table 3, this led to a significant variation in the actual amounts of funds available for the different countries. Indeed, 80% of SAPARD funds were allocated to Poland, Bulgaria and Romania. 11 Europe Institute Foundation (2005) SAPARD REVIEW in Bulgaria, Czech Republic, Estonia, Hungary, Latvia, Poland and Romania, Impact Analysis of The Agriculture And Rural Development, Bulgaria. Page 31

10 Table 3. Annual Indicative budget allocated by the EU per country (in Million EUR, at constant 1999 prices) for the year BG CZ EE HR HU LT LV PL RO SI SK n.a Source: EC (2000) SAPARD questions and answers However, the financing mentioned in the table was not the final one available per candidate country. In fact, the concrete annual country allocation was based on the Annual Financing Agreements (AFA), an accord between the EU and the candidate country lying down the final financial provisions. Indeed, in pursuance of the principle of additionality, AFA was constituted by EU co-financing, covering up to 75% of the total cost for the investment, and financing from national funds 13. For comparison, the total payments made by the Commission by are depicted in the following table: Table 4. Final accumulated budget spent by the EU per country (in Million EUR, at constant 1999 prices) at the end of year BG CZ EE HR HU LT LV PL RO SI SK Finally, SAPARD Programmes did not foresee advance payments, but only reimbursements of the expenses already made 16. In other words, the beneficiaries had to cover the expenses of the investment ex-ante for being reimbursed by the programme once the expenditures have occurred and were verified. 2.2 SAPARD in Bulgaria, Croatia and Romania The present chapter offers an overview of the SAPARD Design and Implementation in Bulgaria, Croatia and Romania. It is structured along the Rationale and objectives of the three Programmes, The selected Measures; The allocated funds, The number of targeted and implemented projects and A summary of common issues encountered. 12 These amounts are for comparison only. Final Figures were slightly different. 13 In this regard, Regulation 696/2003 introduced certain amendments for which, in case of natural disaster in the SAPARD applicant countries, the share of EU assistance may reach the 85%, if applied with projects/measures for affected regions. 14 SAPARD Annual Report 2009, ANNEX A, Financial Execution These amounts are for comparison only. Final Figures were slightly different. 16 The reimbursements are made on the basis of a payment request accompanied by the justifying documentations. Page 32

11 Final Report Short profiles of the three countries Bulgaria The Republic of Bulgaria is situated in the south-eastern part of Europe with a total territory of 110,994 km 2 and with a population of 7.97 million people. Although its economy experienced a stable growth before and during the year of implementation of SAPARD, its agricultural sector, employing about the 9,6% of the total work force of the country, has been declining (13,9% in 2000 and 12,5% in 2002), mainly on account of the slow growth experienced by the sector. In order to solve these deficiencies and in particular to prepare the country for the accession in the EU, the SAPARD Programme was adopted by the Council of Ministers in November 1999 and was approved by the EC in October The Minister of Agriculture and Forestry was assigned to implement the Programme, the State Fund Agriculture (SFA) performed the functions of a SAPARD Agency. The bodies responsible were the Monitoring Committee, the Managing Authority and the SAPARD Agency. The Monitoring Committee included representatives of other ministries, a representative of the EC, local authorities, NGOs and socio-economic partners in the relevant sector and rural areas. The administrative and organizational structure of the SAPARD Agency included a Management Board, a Chief Executive Director and two Deputies, as well as Selection Committee, Operational Department, Financial Department, Internal Audit Department, Legal Department (and Anti-Fraud unit) and an IT Department. The Financial Department performed the functions of the Paying Agency. Three measures namely Measures I, II, and V had the allocation of the 80% of the available funding. Bulgaria joined the EU on 1 January The contracting to final beneficiaries under SAPARD stopped on 31 October Croatia The Republic of Croatia is located in the south-western part of Europe and has a total land area of 56,594 km 2 with 4,290,612 inhabitants. It submitted the request to become EU Member State on 21 st March 2003, and was granted candidate status on 18 th June Its accession to the EU was completed on 1 st of July 2013, therefore, unlike the other SAPARD beneficiaries, Croatia was the only granted candidate which did not became Member State neither during the SAPARD Programme implementation, nor after its full execution. As a whole country, Croatia is characterized by a high degree of rurality (91,6% of the territory could be classified as rural 17 ), which makes the role of agriculture and food industry strategic for the country. However, during the last decades there has been a constant decrease in the share of rural population. Accordingly, to solve these deficiencies, the Plan for agriculture and rural development was approved by the EC on 8 th February 2006 as a SAPARD programme covering only one financial allocation, 2006, in conjunction with the signing of the Multi- 17 OECD definition of rural areas (150 inhabitants/km 2 ) Page 33

12 Annual Financing Agreement (MAFA) on 29 th December 2005, between the Government of Croatia and the EC, on behalf of the EU. The Ministry of Agriculture, Forestry and Water Management was responsible for the SAPARD Programme in the Republic of Croatia, supported by the National Authorisation Officer, which was in charge of financial management of Community preaccession funds. The Directorate for Sustainable Development of Rural Areas acted as Managing Authority, while the Directorate for Market and Structural Support in Agriculture (both belonging to the aforementioned Ministry) acted as the SAPARD Agency. The Department for Internal Audit took over the role of the Paying Agency. Unlike the other accessing countries, only one annual allocation for 2006 was implemented under SAPARD in Croatia from April 2006 (when MAFA came into force) to Croatia stopped contracting to final beneficiaries under SAPARD in August Romania Romania is located at the intersection of Central and South-eastern Europe with a surface of 238,391 Km 2 and with 19 million inhabitants. Due to several reasons such as low income, low number of local jobs and unsatisfactory living conditions, the main demographic trends characterising the Romanian rural population are population decline (e.g. a decrease of 4.47% from 2000 to 2010) and aging, combined with a measurable increase of women's participation in the agricultural sector. In 2000, Romania started a decade of integration, a period characterised by reforms designed to improve the Romania s living conditions and to prepare Romania s admission into the EU. In the framework of agriculture, the National Plan for Agriculture and Rural Development (NPARD), approved by the EC in December 2000, was the reference document. Responsibility in Romania was initially within the Ministry of European Integration (from 2000 until 2004), then for a short period of time transferred to the Ministry of Finances and finally to the Ministry of Agriculture, Forestry and Rural Development acting as the Managing Authority. The Monitoring Committee composed of members representing governmental and non-governmental institutions/bodies, as well as representatives of the European Commission was also hosted by the responsible Ministry. The National Fund from the Ministry of Finances was in charge of the control and verification of the implementation procedures applied by the SAPARD Agency. The Certification Body functions were fulfilled by the Romanian Court of Auditors. The SAPARD Agency in charge with the operational and financial implementation of the Programme was in September 2000 as an independent body, subordinated to the Ministry of Agriculture, consisting of eight Regional Offices and of the Delegated Technical Services, namely the County Departments for Agriculture and the specialized services from the Ministry of Transport, Building and Tourism. Each of the regional offices contained two departments: Programme Implementation Division; and Payments Pre-authorisation Division. Page 34

13 Final Report In 2006, following the dissolution of the Agency, the role and the duties entrusted to it were transferred to the Agency of Payments for Rural Development and Fishery, which was represented on territorial level by 8 Regional Centres and 42 County Offices. Romania joined the EU on 1 January The contracting to final beneficiaries under SAPARD stopped on the 31 July Rationale and objectives of the three Programmes The accessing countries, in order to be eligible for co-financing from SAPARD, had to design and obtain from the EC approval for its SAPARD Programme. The SAPARD Programmes for Bulgaria, Croatia and Romania all developed an extensive SWOT analysis of the condition of the agriculture and rural areas, each of which contains the weaknesses and threats upon which the programme objectives and strategies were built. The major problems identified by the three SAPARD Programmes, could be summarized as follows 18 : The major presence of family agricultural holdings, inducing a low development of agricultural market, as well as low qualification of the labour workforce; Certain demographic trends, such as aging and migrations to urban settlements, bringing to a high rate of fragmentation of the agricultural working force; Low use of mechanisation and therefore very low level of agricultural labour productivity; Lack of distribution channels, as well as inefficient marketing capacity; Limited institutional capacity of the public and private institutions dealing with agriculture, forestry and fishery; Pollution in general, erosion and land-sliding processes, combined with low awareness of issues related to environmental protection; Fragmented land ownership and lack of legislative solutions for it. In summary, the condition of agriculture in Bulgaria, Croatia and Romania, were quite similar to the conditions of the other eight accessing countries: significantly underdeveloped conditions in agriculture and rural areas compared to the EU-15 countries, mainly on account of lack of basic requirement in agriculture. Based on the deficiencies identified and in line with the objectives set up by SAPARD, each of the NARDPs established their own objectives to be pursued through several priorities of interventions. 18 NARDPs Reports for the countries of Romania, Croatia and Bulgaria. Page 35

14 Table 5. SAPARD Programme Objectives in Bulgaria, Croatia and Romania Topic Bulgaria Croatia Romania Overall Goal...achieving sustainable lowinflationary economic growth as a major precondition for the generation of higher income and improvement of living conditions and standard with a view to Bulgaria s future integration into the EU social and economic area. -Improved competitiveness and efficiency of agricultural, forestry and fishery production, processing and marketing of products; -Improved quality, hygiene, environmental and animal welfare standards, -Additional employment opportunities and income...in rural areas.. -Achieving sustainable rural development....contribute to the accession of Romania to the European Union and allowing that Romanian agriculture shall be reinforced in order to be able to cope with the Community market competition s pressure and at the same time improve the life conditions of the economic agents of rural areas... SAPARD Objectives - Development of efficient and sustainable agricultural production and competitive food processing sector through improved market and technological infrastructure and strategic investment policies, ultimately aimed at reaching EU standards. - Sustainable rural development, consistent with the best international environmental practices by providing alternative employment opportunities, economic diversification, development and rehabilitation of infrastructure - The implementation of the Acquis Communautaire concerning the Common Agricultural Policy (CAP) and related policies; - Finding sustainable solutions for pressing adaptation problems in specific priority fields of the agricultural sector and Croatia s rural areas. - The implementation of the Acquis Communautaire concerning the CAP, the environment protection and related policies in the field of food and consumer protection regulations, public health, well been and good health condition of the animals and plants health - Engaging for the environment protection, the transposition in the national legislation and implementation of the [EU Environmental] Directives -Solving priorities and specific problems for the sustainable adaptation of theagricultural sector and rural areas of Romania Page 36

15 Final Report Topic Bulgaria Croatia Romania Priority 1: Improved market efficiency Priority 2: Quality and Health Standards Priority 3: Create new employment in rural areas Priority 1: Development of the rural economy; Priority 2: Improving the access to markets; Priority 3: Development of rural infrastructures; Priority 1: Improving the access to markets and of the competitiveness of agricultural processed products; Priority 2: Improving infrastructures for rural development and agriculture; Priorities Priority 3: Development of rural economy; Priority 4: Development of human resources. Source: NARDP Documents for Bulgaria, Croatia and Romania As it can be seen in the table above Bulgaria and Romania followed a similar approach in the formulation of the narrative to their Intervention Logic addressing the preparation for EU accession and for the adaptation steps needed as an overall goal. Croatia followed a more operational approach. The specific SAPARD objectives of all three countries were closely modelled to the Objectives of Article 1 of the Regulation 1268/1999, the implementation of the acquis communautaire being omnipresent. Priorities were also formulated in a similar manner, addressing the rural economy, improving infrastructures and creating employment opportunities. The three countries selected out of the menu of eligible measures the following: Table 6. Selected SAPARD eligible measures per Country Measures ( ) Bulgaria Croatia Romania Measure I Investments in Agricultural holdings Measure II Measure III Measure IV Measure V Measure VI Improving the processing and marketing of agricultural and fishery products Improving the structures for quality, veterinary and plant-health controls for the quality of the foodstuffs and for consumer protection Agricultural production methods designed to protect the environment and maintain the countryside Development and diversification of economic activities, providing for multiple activities and alternative income Setting up farm relief and farm management services Page 37

16 Measures ( ) Bulgaria Croatia Romania Measure VII Setting up producer groups Measure VIII Measure IX Measure X Renovation and development of villages and the protection and conservation of the rural heritage Land improvement and re-parcelling, Establishment and updating of land registers Measure XI Improvement of vocational training Measure XII Development and improvement of rural infrastructure * Measure XIII Measure XIV Measure XV Agricultural water resources management Forestry, including afforestation of agricultural areas, investments in forest holdings owned by private forest owners and processing and marketing of forestry products Technical assistance for the measures covered by this Regulation, including studies to assist with the preparation and monitoring of the programme, information and publicity campaigns * Total Budget (initial total public expenditure, allocations as provided in the SAPARD Programmes) *measure selected but no conferral of management conducted Source: Ex-post evaluation Reports As can be inferred from the table, Romania and Bulgaria selected the same number of measures, while Croatia, although it planned to implement four, it ultimately ended up implementing only two within the tight frame of its single annual allocation of It must be mentioned that the measures for each country were not implemented concurrently, but some measures had conferral of management at early stage, while other measures had conferral of management even two or three years later (see Figure 1). It is the opinion of this report, based on the review of the programme documents and the evaluation reports and the field research that the link between intended impacts and planned measures was not always consistent, since the implemented measures were not always matching the identified needs; a characteristic example is the Measure XI on vocational training. Moreover, although the monitoring system assumed greater relevance compared to the past, it did not reach the level where the causal chain between measures implemented and result or impact achieved could be followed save be used for corrective interventions. In summary, with regard to the intervention logic, it could be argued that, similarly to the EU8, the objectives were not obvious consequences of the identified needs and Page 38

17 Final Report problems, and moreover, the strategic choices on eligible measures were not always underpinned by programme objectives Administrative Timeline This part comprises a timeline representing the different steps through which SAPARD was implemented in the three countries. It illustrates when the SAPARD Programmewas approved, when the SAPARD Agency was accredited,when the MAFA was signed and subsequently when the countries had conferral of management, the different stages of signing of AFAs, the last approved project, the last payment and finally the closure of the programme. The Bulgarian programme envisaged 10 measures, three of which (I, II, V) had conferral of financial management in May 2001,six measures (VII, VIII, XI, XII, XIV, XV and II.1) had conferral in August 2003, while Measure IV started in October Croatia instead had conferral of financial management for measures I and II in October Measure XII on rural infrastructure did not receive conferral due to the low level of preparedness at the local level, while conferral for measure XV on technical assistance was not requested due to the short time for implementation and the coverage of related tasks by other funding sources (PHARE and World Bank). Romania experienced a more lengthy conferral period with some measures (II, XII, XV) receiving conferral in July 2002, a second batch (I, V, XI) following in December 2004 and another four (III, IV, VII and XIV) coming as late as March Page 39

18 Figure 1. Administrative implementation timeline Although the expected date for paying the contracts was initially established for the end of 2008, in December 2008 the Commission extended the deadline by one year to n+3 in order to increase the absorption of funds Financial Performance Out of the set of selected measures, the financial supports allocated were like in EU 8 concentrated on rural infrastructures (36%) and on processing investments (27%). These two measures absorbed almost two thirds of the funds. Another 22% were allocated to Agri-investments. Thus, 85% of the funds were allocated to three measures, which is also the overall SAPARD benchmark in the period (See Table 7 below). Moreover, it should be noted that SAPARD in the three countries experienced a reallocation of funds within measures, determined by the late implementation of the programme or by the problems for the Commission to confer management(e.g. Croatia). The initial allocation of funds proved to be inefficient. Delays and the risk of decommitment have led to the reallocation of funds to measures with higher absorption capacity (e.g. Measure I: Agri-investment or Measure II: Processing investment), mainly in order to absorb in a short time the high amount of financing available. High absorption capacity can be attributed to intense needs, but also to administrative reasons, standardisation potential for applications (e.g. the purchase of mechanical equipment can be easier replicated rather than agri-environmental measures), lower Page 40

19 Final Report interest on the beneficiaries sides etc. Concurrently, measures with low absorption capacity (either due to administrative reasons or) faced a reduced budget. Table 7. Initial allocated EU contribution per measure (in EUR) Measure Bulgaria Romania Croatia I Agri-investment 145,669, ,418,480 8,474,576 II Processing investment 149,007, ,868,434 16,525,424 III Vet & plant health 28,343, IV Agri-environment 9,501,731 1,.387, V Diversification 56,382,685 63,255, VI Farm relief VII Producer groups 389, , VIII Village renewal 45,795, IX Land improvement X Land register XI Vocational training 336,411 2,961, XII Rural infrastructures 33,222, ,809, XIII Water resources XIV Forestry 3,057,828 55,838, XV Technical assistance 433,495 1,153, Total 443, ,159,785,692 25,000,000 Source: Ex-post evaluation reports & Final Annual Implementation Report As evident from Table 8, the country with the highest allocation of funding is Romania, followed by Bulgaria and Croatia. Interestingly, considering all the SAPARD countries beneficiaries, after Poland, Romania was the country with the highest EU allocated resources 19. Table 8. Total Commission payments of SAPARD in Bulgaria, Croatia, Romania by Initially total approved budget (MEUR) Total utilised budget (MEUR) at end of 2009 Budget absorption Bulgaria ,6% Croatia ,8% Romania ,9% Source: SAPARD Annual Report 2009, Annex A 19 Council Regulation EC No 1268/1999, art The total amount for Bulgaria was subject to de-commitments. Out of the original 444 million EUR, the amount was finally reduced to 371 million EUR. Page 41

20 Comparing those numbers to 2006, the figures for Bulgaria and Romania were at appr. 46% of the committed funds being actually paid by the Commission. It enhanced in the two following years to 62% in 2007 and to almost 70% in 2008; payment interruptions and recovery of funds by the Commission reduced the final figure. Considering these delays, the payment rate for all three countries at the end of 2009 was a considerable improvement. However, it is still low if compared to the rate of the EU 8 Member States, which reached almost 100% (the Latvian programme being an exception with a rate of 95%). At this point it should also be pointed out that the Croatian Programme poses an exception in its size, magnitude (37 projects) and formally one year of implementation; thus comparisons are reasonable between Bulgaria, Romania and the rest of the 2004 Enlargement wave. The major difficulties that the countries faced were the late and slow start and a slowdown in implementation in 2008, due to control issues in Bulgaria and Romania. EC missions carried out in 2008 to Bulgaria and Romania led to a request to the national authorities to draw up an action plan to remedy the identified control deficiencies and to inform the Commission of the implementation. The Commission interrupted reimbursements of declared expenditure with regard to three important measures in the case of Bulgaria, and for all measures of Romania, until proper implementation of their action plans. It should be mentioned here that the overall absorption might be finally even lower since at least for Bulgaria there might be additional claims for funds recovery 21. In the case of Croatia overall absorption was low due to the tight time-plan and more attractive national programmes implemented in the same period Projects implemented The table below gives an overview of the total numbers of projects targeted in the SAPARD Programme, approved by the SAPARD agency and finally implemented and paid out. In line with the budget available, Romania implemented the highest number of projects (4,374), and Bulgaria 2,595. Only 37 projects were paid in Croatia. Moreover, it is evident that the number of paid projects is very low compared to the initially targeted projects. This table should be compared to Table 8 on Budget absorption. It is notable that will the range of achievement of the output targets in terms of number of projects ranged from 10% in Romania to 22% in Croatia and 27% in Bulgaria, the overall budget absorption was much higher. This is an indication that as a general rule, larger, more expenditure-heavy projects were implemented. The reasons for that are discussed in the Chapters 4 and Information provided during the third Monitoring Group Meeting for this report. Page 42

21 Final Report I II III IV V Measure Proces. investment Vet & plant health Reimbursed Agriinvestment Agrienvironment Diversificatio n Table 9. Number of approved and implemented/reimbursed projects per measure Bulgaria Romania Croatia Targeted Approved Reimbursed Targeted Approv ed Targeted Approved Reimbursed n.a VI Farm relief VII VIII IX Producer groups Village renewal Land improvement n.a n.a X Land register XI XII XIII Vocational training Rural infrastructure s Water resources n.a n.a XIV Forestry n.a XV TA n.a n.a Total Source: Ex-post evaluation reports Common features among the three Programmes While the three SAPARD programmes were delivered under different settings, yet some common issues arose: Page 43

22 While the three programmes fared differently in total financial performance (ranging from 48 to 89%), the deviation among targeted and implemented projects was overall high (achievements between 10 and 27%); Ratio of approved to submitted projects was very low; beneficiaries were unable to prepare projects meeting the eligibility criteria established by the programme; Demanding eligibility and implementation criteria, which could not have been met by the majority of the holdings, have influenced the type of projects and beneficiaries being successful. For example it is mentioned that in the case of Bulgaria for...simple project for the purchase of a combine harvester and a plough, the number of pages in the application file was and for the file with the payment request 601 pages 22. Similar remarks are contained in the Croatian (p.70f) and the Romanian Ex-post reports (p.180f). The low level of beneficiaries capacity in dealing with the requirements of the SAPARD Programme was paired by the inexperience of the administration especially considering ineffective decentralised structures, the lack of adequate consultancy and the long idle times between the submission of the application for financing and the receipt of contribution mainly due to the preference of the Paying Agency to exhaust all possibilities of covering her position in case of irregularities; As a consequence of the slow progress made by the administration, late conferral of certain measures has influenced the overall performance (this was less the case for Croatia, where the whole programme was implemented under a tight timetable and covering only Measure I and II in the final version, hence not implemented Measures XII and XV did not influence the overall picture); On the positive side the whole procedure of transposition, planning, accreditation and conferral of management has improved the capacity of the administration synchronisation of national legislation and the familiarisation with EU practices and the acquis communautaire and the functioning of the EC. This capacity can be utilised also in the Rural Development Programmes as a Member State; Last but not least, those beneficiaries supported have improved the situation of their holdings, improved productivity and competitiveness and have complied with EU standards. 22 Court of Auditors (2004), Special Report No 2/2004 concerning pre-accession aid, 2004/C295/01 Page 44

COMMISSION OF THE EUROPEAN COMMUNITIES

COMMISSION OF THE EUROPEAN COMMUNITIES COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 28.10.2005 COM(2005) 537 final REPORT FROM THE COMMISSION TO THE COUNCIL, THE EUROPEAN PARLIAMENT, THE EUROPEAN ECONOMIC AND SOCIAL COMMITTEE AND THE COMMITTEE

More information

Access to EU-Funding. Ulrich Daldrup Riga, 19th February 2002

Access to EU-Funding. Ulrich Daldrup Riga, 19th February 2002 Regional Development in the EU Regional Development in the EU and Access to EU-Funding presented by Ulrich Daldrup Riga, 19th February 2002 1 Regional Development in the EU Programmes Funding is available

More information

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 02.05.2005 COM(2005) 178 final REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL GENERAL REPORT ON PRE-ACCESSION ASSISTANCE (PHARE ISPA

More information

CHAPTER 4. Overview of the EU Rural Development Policy

CHAPTER 4. Overview of the EU Rural Development Policy CHAPTER 4. Overview of the EU Rural Development Policy 2007-2013 Council Regulation (EC) No 1698/2005 of 20 September 2005 on support for rural development by the European Agricultural Fund for Rural Development

More information

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL EUROPEAN COMMISSION Brussels, 27.9.2017 COM(2017) 554 final REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL 10th FINANCIAL REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND

More information

THE STRUCTURAL FUNDS' IMPLEMENTATION IN POLAND CHALLENGES FOR

THE STRUCTURAL FUNDS' IMPLEMENTATION IN POLAND CHALLENGES FOR STUDY Budgetary Support Unit THE STRUCTURAL FUNDS' IMPLEMENTATION IN POLAND CHALLENGES FOR 2007-2013 BUDGETARY AFFAIRS 4/9/2007 JANUARY 2004 EN This study was requested by the European Parliament's Committee

More information

EU Funds in Central and Eastern Europe 2011 kpmg.com/cee

EU Funds in Central and Eastern Europe 2011 kpmg.com/cee PUBLIC SECTOR EU Funds in Central and Eastern Europe 2011 kpmg.com/cee 2 Section or Brochure name EU Funds in Central and Eastern Europe 2011 3 Table of contents Introduction Foreword 4 EU Funds covered

More information

FINANCIAL MANAGEMENT OF THE EUROPEAN AGRICULTURAL FUNDS

FINANCIAL MANAGEMENT OF THE EUROPEAN AGRICULTURAL FUNDS FINANCIAL MANAGEMENT OF THE EUROPEAN AGRICULTURAL FUNDS Agenda Introduction (slides 3-7) Principles of shared financial management (slides 8-17) Financial management of EAGF (slides 18-22) Financial management

More information

Challenges Of The Indirect Management Of Eu Funds In Albania

Challenges Of The Indirect Management Of Eu Funds In Albania Challenges Of The Indirect Management Of Eu Funds In Albania Neritan Totozani, Msc Central Financing & Contracting Unit, Ministry of Finance, Albania doi: 10.19044/esj.2016.v12n7p170 URL:http://dx.doi.org/10.19044/esj.2016.v12n7p170

More information

FINAL REPORT ON SAPARD PROGRAMME IMPLEMENTATION IN ROMANIA

FINAL REPORT ON SAPARD PROGRAMME IMPLEMENTATION IN ROMANIA MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT MANAGING AUTHORITY FOR SAPARD PROGRAMME FINAL REPORT ON SAPARD PROGRAMME IMPLEMENTATION IN ROMANIA Consolidated version ROMANIA June, 2011 CONTENT CHAPTER

More information

The Future of CAP: Community led local development based on Leader approach

The Future of CAP: Community led local development based on Leader approach The Future of CAP: Community led local development based on Leader approach Mihail Dumitru, Director E European Commission DG Agriculture and Rural development Raise the stake" conference, Siret, Romania

More information

The Reform of the Common Agricultural Policy Implementation. Catherine Combette DG Agriculture and Rural Development European Commission

The Reform of the Common Agricultural Policy Implementation. Catherine Combette DG Agriculture and Rural Development European Commission The Reform of the Common Agricultural Policy 2014-2020 Implementation Catherine Combette DG Agriculture and Rural Development European Commission catherine.combette@ec.europa.eu Agriculture and Rural Development

More information

LATVIA. Programme Complement Latvia Objective 1 Programme

LATVIA. Programme Complement Latvia Objective 1 Programme LATVIA Programme Complement Latvia Objective 1 Programme 2004-2006 2007-11-6 Riga Table of content Introduction... 4 The Socio-Economic Context and the Strategy... 5 Structural Funds and Priority Areas...

More information

National Agriculture and Rural Development Plan

National Agriculture and Rural Development Plan MEASURE 2.3. DEVELOPMENT AND IMPROVEMENT OF THE RURAL INFRASTRUCTURE Rationale The development of the private economic activities and the improvement of the living conditions for the population in the

More information

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL EUROPEAN COMMISSION Brussels, 17.9.2018 COM(2018) 629 final REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL 11th FINANCIAL REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND

More information

EU Funds investments and projections, preparation for the period December, 2014

EU Funds investments and projections, preparation for the period December, 2014 EU Funds investments and projections, preparation for the 2014-2020 period December, 2014 Content 1.Implementation progress 2.Risks 3.Progress of EU funds planning documents 2014-2020 4.Preparation for

More information

COMMISSION DECISION. C(2007)6121 of 12/12/2007

COMMISSION DECISION. C(2007)6121 of 12/12/2007 EN EN EN COMMISSION DECISION C(2007)6121 of 12/12/2007 adopting a Programme on financing the participation of Croatia in the ERDF European Territorial Co operation transnational programmes "South East

More information

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION ANNUAL REPORT ON THE COHESION FUND (2003) (SEC(2004) 1470)

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION ANNUAL REPORT ON THE COHESION FUND (2003) (SEC(2004) 1470) COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 15.12.2004 COM(2004) 766 final. REPORT FROM THE COMMISSION ANNUAL REPORT ON THE COHESION FUND (2003) (SEC(2004) 1470) EN EN TABLE OF CONTENTS 1. Budget

More information

Report on the distribution of direct payments to agricultural producers (financial year 2016)

Report on the distribution of direct payments to agricultural producers (financial year 2016) Report on the distribution of direct payments to agricultural producers (financial year 2016) Every year, the Commission publishes the distribution of direct payments to farmers by Member State. Figures

More information

Instrument for Pre-accession Assistance (IPA): the Rural Development Component IPARD

Instrument for Pre-accession Assistance (IPA): the Rural Development Component IPARD Instrument for Pre-accession Assistance (IPA): the Rural Development Component IPARD Elitsa Yanakieva European Commission, DG AGRI, Unit for Pre-accession assistance 5th meeting of EU-the former Yugoslav

More information

04.02 EAGGF EAGGF - p.1

04.02 EAGGF EAGGF - p.1 04.02 EAGGF 1. Basic information 1.1. CRIS Number : 2002/000-605-04.02 Twinning number: PL02-AG-05 1.2. Title: EAGGF 1.3. Sector: Agriculture 1.4. Location: Poland 2. Objectives: 2.1. Overall objective:

More information

Briefing May EIB Group Operational Plan

Briefing May EIB Group Operational Plan Briefing May 17 The winners and losers of climate action at the European Investment Bank The European Investment Bank has committed to support the EU s transition to a low-carbon and climate-resilient

More information

LIMITE EN CONFERENCE ON ACCESSION TO THE EUROPEAN UNION CROATIA. Brussels, 15 April 2011 AD 13/11 LIMITE CONF-HR 8

LIMITE EN CONFERENCE ON ACCESSION TO THE EUROPEAN UNION CROATIA. Brussels, 15 April 2011 AD 13/11 LIMITE CONF-HR 8 CONFERENCE ON ACCESSION TO THE EUROPEAN UNION CROATIA Brussels, 15 April 2011 AD 13/11 LIMITE DOCUMENT PARTIALLY ACCESSIBLE TO THE PUBLIC (12.09.2011) CONF-HR 8 ACCESSION DOCUMENT Subject: EUROPEAN UNION

More information

PHARE 2003 STANDARD SUMMARY PROJECT FICHE

PHARE 2003 STANDARD SUMMARY PROJECT FICHE PHARE 2003/005-551.06.03 version of 16.06.2003 PHARE 2003 STANDARD SUMMARY PROJECT FICHE 1. Basic information 1.1 CRIS Number: PHARE 2003/005-551.06.03 1.2 Title: Support for improving the participation

More information

PHARE 2005 PROJECT FICHE. 1.2 Title: Institutional Capacity Building and Support for Implementation of SAPARD/IPA-RD Programme

PHARE 2005 PROJECT FICHE. 1.2 Title: Institutional Capacity Building and Support for Implementation of SAPARD/IPA-RD Programme 1 BASIC INFORMATION 1.1 CRIS Number: HR2005/5/1 PHARE 2005 PROJECT FICHE 1.2 Title: Institutional Capacity Building and Support for Implementation of SAPARD/IPA-RD Programme 1.3 Sector: 43010 1.4 Location:

More information

TWINNING: A TESTED EXPERIENCE IN A BROADER EUROPEAN CONTEXT

TWINNING: A TESTED EXPERIENCE IN A BROADER EUROPEAN CONTEXT TWINNING: A TESTED EXPERIENCE IN A BROADER EUROPEAN CONTEXT European Commission Directorate General Enlargement Institution Building Unit INTRODUCTION The Twinning programme was established in 1998 to

More information

Ispa will have until 2006 an annual budget of about 1,040m (expressed in 1999 price).

Ispa will have until 2006 an annual budget of about 1,040m (expressed in 1999 price). 15 June 2000 The Instrument for Structural Policies for Pre-accession (Ispa) is the European Commission s instrument to help the ten Central European candidate countries to adapt to the environmental and

More information

Flash Eurobarometer 408 EUROPEAN YOUTH REPORT

Flash Eurobarometer 408 EUROPEAN YOUTH REPORT Flash Eurobarometer EUROPEAN YOUTH REPORT Fieldwork: December 2014 Publication: April 2015 This survey has been requested by the European Commission, Directorate-General for Education and Culture and co-ordinated

More information

EU Funds in Central and Eastern Europe

EU Funds in Central and Eastern Europe PUBLIC SECTOR EU Funds in Central and Eastern Europe Progress report 2007 08 ADVISORY EU Funds in Central and Eastern Europe 3 Contents Foreword 4 1 Introduction 5 2 CEE overview 8 3 Country overviews

More information

STANDARD PROJECT FICHE

STANDARD PROJECT FICHE STANDARD PROJECT FICHE 1. Basic Information 1.1 CRIS Number : 2004-016-919.04 1.2 Title: Preparation for Extended Decentralized Implementation System (EDIS) in the management of pre-accession funds in

More information

PART 1: DANUBE TRANSNATIONAL PROGRAMME

PART 1: DANUBE TRANSNATIONAL PROGRAMME Applicants Manual for the period 2014-2020 Version 1 PART 1: DANUBE TRANSNATIONAL PROGRAMME edited by the Managing Authority/Joint Secretariat Budapest, Hungary, 2015 Applicants Manual Part 1 1 PART 1:

More information

COMMISSION DECISION. C(2007)6376 on 18/12/2007

COMMISSION DECISION. C(2007)6376 on 18/12/2007 COMMISSION DECISION C(2007)6376 on 18/12/2007 adopting a horizontal programme on the Energy Efficiency Finance Facility for Albania, Bosnia and Herzegovina, Croatia, Montenegro, Serbia including Kosovo

More information

IMPLEMENTATION OF THE EUROPEAN UNION COHESION POLICY FOR PROGRAMMING PERIOD: EVOLUTIONS, DIFFICULTIES, POSITIVE FACTORS

IMPLEMENTATION OF THE EUROPEAN UNION COHESION POLICY FOR PROGRAMMING PERIOD: EVOLUTIONS, DIFFICULTIES, POSITIVE FACTORS IMPLEMENTATION OF THE EUROPEAN UNION COHESION POLICY FOR 2007-2013 PROGRAMMING PERIOD: EVOLUTIONS, DIFFICULTIES, POSITIVE FACTORS PhD Candidate Ana STĂNICĂ Abstract In an European Union that integrated

More information

Marche Region. Ex Ante Evaluation report. Executive summary. Roma, June 2015

Marche Region. Ex Ante Evaluation report. Executive summary. Roma, June 2015 Marche Region 2014-2020 COMMITTENTE RDP for Marche Ex Ante Evaluation report Roma, June 2015 Executive summary EXECUTIVE SUMMARY Introduction The Ex Ante Evaluation (EAE) of the Rural Development Programme

More information

COMMISSION OF THE EUROPEAN COMMUNITIES

COMMISSION OF THE EUROPEAN COMMUNITIES COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 14.12.1998 COM(1998) 750 final 98/0352 (CNS) Proposal for a COUNCIL DECISION concerning the Community position within the Association Council on the participation

More information

The INTERREG III Community Initiative

The INTERREG III Community Initiative Version: 14 March 2003 The INTERREG III Community Initiative How to prepare programmes A practical guide for preparing new, and amending existing, INTERREG III Community Initiative Programmes as a result

More information

REPORT FROM THE COMMISSION TO THE EUROPEAN COURT OF AUDITORS, THE COUNCIL AND THE EUROPEAN PARLIAMENT

REPORT FROM THE COMMISSION TO THE EUROPEAN COURT OF AUDITORS, THE COUNCIL AND THE EUROPEAN PARLIAMENT EUROPEAN COMMISSION Brussels, 27.2.2017 COM(2017) 120 final REPORT FROM THE COMMISSION TO THE EUROPEAN COURT OF AUDITORS, THE COUNCIL AND THE EUROPEAN PARLIAMENT Member States' Replies to the European

More information

COUNCIL OF THE EUROPEAN UNION. Brussels, 19 October /05 Interinstitutional File: 2004/0163 (AVC) LIMITE

COUNCIL OF THE EUROPEAN UNION. Brussels, 19 October /05 Interinstitutional File: 2004/0163 (AVC) LIMITE COUNCIL OF THE EUROPEAN UNION Brussels, 9 October 005 05/05 Interinstitutional File: 004/06 (AVC) LIMITE FSTR 57 FC 4 REGIO 50 SOC 68 CADREFIN 9 NOTE from : Presidency to : Structural Actions Working Party

More information

Official Journal of the European Union

Official Journal of the European Union L 210/82 31.7.2006 COUNCIL REGULATION (EC) No 1085/2006 of 17 July 2006 establishing an Instrument for Pre-Accession Assistance (IPA) THE COUNCIL OF THE EUROPEAN UNION, Having regard to the Treaty establishing

More information

LIMITE EN CONFERENCE ON ACCESSION TO THE EUROPEAN UNION CROATIA. Brussels, 30 September 2009 AD 13/09 LIMITE CONF-HR 8

LIMITE EN CONFERENCE ON ACCESSION TO THE EUROPEAN UNION CROATIA. Brussels, 30 September 2009 AD 13/09 LIMITE CONF-HR 8 CONFERENCE ON ACCESSION TO THE EUROPEAN UNION CROATIA Brussels, 30 September 2009 AD 13/09 LIMITE DOCUMENT PARTIALLY ACCESSIBLE TO THE PUBLIC (12.09.2011) CONF-HR 8 ACCESSION DOCUMENT Subject : EUROPEAN

More information

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents 2006R1083 EN 25.06.2010 004.001 1 This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents B COUNCIL REGULATION (EC) No 1083/2006 of 11 July

More information

IMPACT ASSESSMENT OF THE DRAFT EU STRUCTURAL FUNDS REGULATIONS

IMPACT ASSESSMENT OF THE DRAFT EU STRUCTURAL FUNDS REGULATIONS This research was performed by a group of authors lead by H. Brožaitis from the public non-profit organisation Public Policy and Management Institute on the order of the Prime Minister Office of the Republic

More information

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof,

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof, L 244/12 COMMISSION IMPLEMTING REGULATION (EU) No 897/2014 of 18 August 2014 laying down specific provisions for the implementation of cross-border cooperation programmes financed under Regulation (EU)

More information

Delegation of the European Commission to Turkey

Delegation of the European Commission to Turkey Regional Development in the EU and Turkey REGIONAL DEVELOPMENT IN THE EU AND TURKEY* Teresa Reeves Delegation of the European Commission to Turkey Abstract This text examines the fundamental concepts of

More information

Cross Border Co-operation between Bulgaria & Romania Multi-annual Programme Project Fiche for Programme Support

Cross Border Co-operation between Bulgaria & Romania Multi-annual Programme Project Fiche for Programme Support Cross Border Co-operation between Bulgaria & Romania Multi-annual Programme 2003 2006 2005 Project Fiche for Programme Support 1. Basic Information 1.1 CRIS Number: BG 2005/017-455.01;04 1.2 1.2 Title:

More information

ANNEX ICELAND NATIONAL PROGRAMME IDENTIFICATION. Iceland CRIS decision number 2012/ Year 2012 EU contribution.

ANNEX ICELAND NATIONAL PROGRAMME IDENTIFICATION. Iceland CRIS decision number 2012/ Year 2012 EU contribution. ANNEX ICELAND NATIONAL PROGRAMME 2012 1 IDENTIFICATION Beneficiary Iceland CRIS decision number 2012/023-648 Year 2012 EU contribution 11,997,400 EUR Implementing Authority European Commission Final date

More information

EUROPEAN COMMISSION DIRECTORATE-GENERAL TAXATION AND CUSTOMS UNION Customs Policy, Legislation, Tariff Customs Processes and Project Management

EUROPEAN COMMISSION DIRECTORATE-GENERAL TAXATION AND CUSTOMS UNION Customs Policy, Legislation, Tariff Customs Processes and Project Management EUROPEAN COMMISSION DIRECTORATE-GENERAL TAXATION AND CUSTOMS UNION Customs Policy, Legislation, Tariff Customs Processes and Project Management Brussels, 01/06/2016 taxud.a.3(2016)2380286 FINAL Report

More information

Preparing Romania for EU Membership: A Commission perspective. Presentation by Martijn Quinn European Commission DG Enlargement

Preparing Romania for EU Membership: A Commission perspective. Presentation by Martijn Quinn European Commission DG Enlargement Preparing Romania for EU Membership: A Commission perspective Presentation by Martijn Quinn European Commission DG Enlargement Preparing Romania for EU Membership EU-Romania: a developing relationship

More information

COMMISSION STAFF WORKING DOCUMENT Accompanying the document

COMMISSION STAFF WORKING DOCUMENT Accompanying the document EUROPEAN COMMISSION Brussels, 9.10.2017 SWD(2017) 330 final PART 13/13 COMMISSION STAFF WORKING DOCUMENT Accompanying the document REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT, THE COUNCIL, THE

More information

Reforming Policies for Regional Development: The European Perspective

Reforming Policies for Regional Development: The European Perspective Business & Entrepreneurship Journal, vol.3, no.1, 2014, 57-62 ISSN: 2241-3022 (print version), 2241-312X (online) Scienpress Ltd, 2014 Reforming Policies for Regional Development: The European Perspective

More information

Axis 4 (Leader) Implementing Local Development Strategies

Axis 4 (Leader) Implementing Local Development Strategies Axis 4 (Leader) Implementing Local Development Strategies Basic Information: Axis 4 Leader: Implementing local development strategies with a view to achieving the objectives of one or more of the axes

More information

COMMISSION DECISION. C(2007)5980 of 10/12/2007

COMMISSION DECISION. C(2007)5980 of 10/12/2007 EN EN EN COMMISSION DECISION C(2007)5980 of 10/12/2007 adopting the Cross border programme between Serbia and Montenegro under the IPA- Cross border Co operation component, for the year 2007 THE COMMISSION

More information

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION ANNUAL REPORT OF THE COHESION FUND (2004) {SEC(2005)1396}

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION ANNUAL REPORT OF THE COHESION FUND (2004) {SEC(2005)1396} COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 7.11.2005 COM(2005) 544 final REPORT FROM THE COMMISSION ANNUAL REPORT OF THE COHESION FUND (2004) {SEC(2005)1396} EN EN TABLE OF CONTENTS REPORT FROM THE

More information

Pension Policy: Reversals of Funded Schemes

Pension Policy: Reversals of Funded Schemes Public Disclosure Authorized Public Disclosure Authorized Pension Policy: Reversals of Funded Schemes Public Disclosure Authorized Agnieszka Chłoń-Domińczak, Ph. D. Warsaw School of Economics Washington

More information

Themes Income and wages in Europe Wages, productivity and the wage share Working poverty and minimum wage The gender pay gap

Themes Income and wages in Europe Wages, productivity and the wage share Working poverty and minimum wage The gender pay gap 5. W A G E D E V E L O P M E N T S At the ETUC Congress in Seville in 27, wage developments in Europe were among the most debated issues. One of the key problems highlighted in this respect was the need

More information

Preparations for IPA II - EU State Enlargement. Iwona Lisztwan European Commission Directorate General Agriculture and Rural development

Preparations for IPA II - EU State Enlargement. Iwona Lisztwan European Commission Directorate General Agriculture and Rural development Preparations for IPA II - EU State Enlargement of play Iwona Lisztwan European Commission Directorate General Agriculture and Rural development A new set of instruments for external action for the period

More information

Official Journal of the European Union

Official Journal of the European Union 13.5.2014 L 138/5 COMMISSION DELEGATED REGULATION (EU) No 480/2014 of 3 March 2014 supplementing Regulation (EU) No 1303/2013 of the European Parliament and of the Council laying down common provisions

More information

COMMISSION DECISION. of on technical provisions necessary for the operation of the transition facility in the Republic of Croatia

COMMISSION DECISION. of on technical provisions necessary for the operation of the transition facility in the Republic of Croatia EUROPEAN COMMISSION Brussels, 13.6.2013 C(2013) 3463 final COMMISSION DECISION of 13.6.2013 on technical provisions necessary for the operation of the transition facility in the Republic of Croatia EN

More information

Leader approach and local development strategies in Slovenia

Leader approach and local development strategies in Slovenia Matej Bedrac, Tomaž Cunder 245 1 Agricultural Institute of Slovenia, Department of Agricultural Economics, Hacquetova 17, Ljubljana matej.bedrac@kis.si; tomaz.cunder@kis.si Leader approach and local development

More information

FOCUS AREA 2A: Improving economic performance of all farms, farm restructuring and modernisation

FOCUS AREA 2A: Improving economic performance of all farms, farm restructuring and modernisation Rural Development Programmes 2014-2020: Key facts & figures FOCUS AREA 2A: Improving economic performance of all farms, farm restructuring and modernisation 1. Introduction Focus Area (FA) 2A is designed

More information

DECREE No 104 OF 17 MAY 2008 ON ORGANIZATION AND COORDINATION OF MANAGEMENT OF RESOURCES FROM THE FUNDS OF THE EUROPEAN UNION

DECREE No 104 OF 17 MAY 2008 ON ORGANIZATION AND COORDINATION OF MANAGEMENT OF RESOURCES FROM THE FUNDS OF THE EUROPEAN UNION DECREE No 104 OF 17 MAY 2008 ON ORGANIZATION AND COORDINATION OF MANAGEMENT OF RESOURCES FROM THE FUNDS OF THE EUROPEAN UNION Effective as of 20 May 2008 Promulgated, SG No 47 of 20 May 2008, as amended,

More information

US$M): US$M): (US$M. Cofinancing (US$M US$M):

US$M): US$M): (US$M. Cofinancing (US$M US$M): Public Disclosure Authorized IEG ICR Review Independent Evaluation Group Report Number : ICRR14162 1. Project Data: Date Posted : 05/20/2014 Public Disclosure Authorized Public Disclosure Authorized Public

More information

HOW RECESSION REFLECTS IN THE LABOUR MARKET INDICATORS

HOW RECESSION REFLECTS IN THE LABOUR MARKET INDICATORS REPUBLIC OF SLOVENIA HOW RECESSION REFLECTS IN THE LABOUR MARKET INDICATORS Matej Divjak, Irena Svetin, Darjan Petek, Miran Žavbi, Nuška Brnot ??? What is recession?? Why in Europe???? Why in Slovenia?

More information

COMMISSION OF THE EUROPEAN COMMUNITIES. Proposal for a COUNCIL REGULATION

COMMISSION OF THE EUROPEAN COMMUNITIES. Proposal for a COUNCIL REGULATION COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 14.7.2004 COM(2004)490 final 2004/0161(CNS) Proposal for a COUNCIL REGULATION on support for rural development by the European Agricultural Fund for Rural

More information

Official Journal of the European Communities. (Acts whose publication is obligatory) COUNCIL REGULATION (EC) No 1260/1999.

Official Journal of the European Communities. (Acts whose publication is obligatory) COUNCIL REGULATION (EC) No 1260/1999. 26.6.1999 L 161/1 I (Acts whose publication is obligatory) COUNCIL REGULATION (EC) No 1260/1999 of 21 June 1999 laying down general provisions on the Structural Funds THE COUNCIL OF THE EUROPEAN UNION,

More information

Riding the global growth wave. Richard Grieveson. Press conference, 13 March New wiiw forecast for Central, East and Southeast Europe,

Riding the global growth wave. Richard Grieveson. Press conference, 13 March New wiiw forecast for Central, East and Southeast Europe, Wiener Institut für Internationale Wirtschaftsvergleiche The Vienna Institute for International Economic Studies wiiw.ac.at Press conference, 13 March 2018 New wiiw forecast for Central, East and Southeast

More information

Standard Summary Project Fiche IPA centralised programmes Project Fiche: 18

Standard Summary Project Fiche IPA centralised programmes Project Fiche: 18 Standard Summary Project Fiche IPA centralised programmes Project Fiche: 18 1. Basic information 1.1. CRIS Number: 2010/022-154 1.2. Title: Technical Assistance and Project Preparation Facility (TA&PPF)

More information

Committee on Agriculture and Rural Development

Committee on Agriculture and Rural Development EUROPEAN PARLIAMT 2009-2014 Committee on Agriculture and Rural Development 24.7.2013 2013/0117(COD) ***I DRAFT REPORT on the proposal for a regulation of the European Parliament and of the Council laying

More information

Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL

Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL EUROPEAN COMMISSION Brussels, 5.10.2017 COM(2017) 565 final 2017/0247 (COD) Proposal for a REGULATION OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL amending Regulation (EU) No 1303/2013 as regards the

More information

COMMISSION STAFF WORKING DOCUMENT Accompanying the document. Report form the Commission to the Council and the European Parliament

COMMISSION STAFF WORKING DOCUMENT Accompanying the document. Report form the Commission to the Council and the European Parliament EUROPEAN COMMISSION Brussels, 4.5.2018 SWD(2018) 246 final PART 5/9 COMMISSION STAFF WORKING DOCUMENT Accompanying the document Report form the Commission to the Council and the European Parliament on

More information

Index. Executive Summary 1. Introduction 3. Audit Findings 11 MANDATE 1 AUDIT PLAN 1 GENERAL OBSERVATION AND MAIN CONCLUSIONS 1 RECOMMENDATIONS 2

Index. Executive Summary 1. Introduction 3. Audit Findings 11 MANDATE 1 AUDIT PLAN 1 GENERAL OBSERVATION AND MAIN CONCLUSIONS 1 RECOMMENDATIONS 2 Report to the Contact Commiittee of the heads of the Supreme Audit Institutions of the Member States of the European Union and the European Court of Auditors On the Parallel Audit on the Costs of controlls

More information

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION TO THE COUNCIL

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION TO THE COUNCIL EN EN EN COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 10.12.2009 COM(2009) 682 final REPORT FROM THE COMMISSION TO THE COUNCIL on the follow-up to 2007 Discharge Decisions (Summary) - Council Recommendations

More information

COMMISSION OF THE EUROPEAN COMMUNITIES COMMUNICATION FROM THE COMMISSION TO THE COUNCIL AND THE EUROPEAN PARLIAMENT. Roadmaps for Bulgaria and Romania

COMMISSION OF THE EUROPEAN COMMUNITIES COMMUNICATION FROM THE COMMISSION TO THE COUNCIL AND THE EUROPEAN PARLIAMENT. Roadmaps for Bulgaria and Romania COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 13.11.2002 COM(2002) 624 final COMMUNICATION FROM THE COMMISSION TO THE COUNCIL AND THE EUROPEAN PARLIAMENT Roadmaps for Bulgaria and Romania COMMUNICATION

More information

Poverty Profile Executive Summary. Azerbaijan Republic

Poverty Profile Executive Summary. Azerbaijan Republic Poverty Profile Executive Summary Azerbaijan Republic December 2001 Japan Bank for International Cooperation 1. POVERTY AND INEQUALITY IN AZERBAIJAN 1.1. Poverty and Inequality Measurement Poverty Line

More information

Guidance for Member States on the Drawing of Management Declaration and Annual Summary

Guidance for Member States on the Drawing of Management Declaration and Annual Summary EGESIF_15-0008-02 19/08/2015 EUROPEAN COMMISSION European Structural and Investment Funds Guidance for Member States on the Drawing of Management Declaration and Annual Summary Programming period 2014-2020

More information

OUTCOME OF THE COUNCIL MEETING. 3607th Council meeting. Agriculture and Fisheries. Brussels, 19 March 2018 P R E S S

OUTCOME OF THE COUNCIL MEETING. 3607th Council meeting. Agriculture and Fisheries. Brussels, 19 March 2018 P R E S S Council of the European Union 7272/18 (OR. en) PRESSE 17 PR CO 17 OUTCOME OF THE COUNCIL MEETING 3607th Council meeting Agriculture and Fisheries Brussels, 19 March 2018 President Rumen Porodzanov Minister

More information

Special Eurobarometer 418 SOCIAL CLIMATE REPORT

Special Eurobarometer 418 SOCIAL CLIMATE REPORT Special Eurobarometer 418 SOCIAL CLIMATE REPORT Fieldwork: June 2014 Publication: November 2014 This survey has been requested by the European Commission, Directorate-General for Employment, Social Affairs

More information

Standard Summary Project Fiche for the Transition Facility

Standard Summary Project Fiche for the Transition Facility Standard Summary Project Fiche for the Transition Facility 1 Basic Information 1.1 CRIS Number: 2006/01/-176.05.01 1.2 Title: Unallocated IB envelope 1.3 Sector: Other IB actions 1.4 Location: Hungary*

More information

Economic Integration and Social Cohesion: the European Union s experience. Vasco Cal Mexico November 2004

Economic Integration and Social Cohesion: the European Union s experience. Vasco Cal Mexico November 2004 Economic Integration and Social Cohesion: the European Union s experience Vasco Cal Mexico November 2004 Structure of this presentation Origins of EU cohesion policy Cohesion policy: value added Main challenges

More information

Rehabilitation and Partial Reconstruction of Road II-19 Razlog Bansko Gotse Delchev Sadovo

Rehabilitation and Partial Reconstruction of Road II-19 Razlog Bansko Gotse Delchev Sadovo STANDARD SUMMARY PROJECT FICHE Rehabilitation and Partial Reconstruction of Road II-19 Razlog Bansko Gotse Delchev Sadovo 1. Basic Information CRIS Number: 2002/000-624-01 Title: Rehabilitation and Partial

More information

Directorate F. Horizontal aspects of rural development; SAPARD F.3. Consistency of rural development

Directorate F. Horizontal aspects of rural development; SAPARD F.3. Consistency of rural development EUROPEAN COMMISSION AGRICULTURE DIRECTORATE-GENERAL Directorate F. Horizontal aspects of rural development; SAPARD F.3. Consistency of rural development Commission Working Document D/761 FINAL: 01.2005

More information

ANNEX CAP evolution and introduction of direct payments

ANNEX CAP evolution and introduction of direct payments ANNEX 2 REPORT ON THE DISTRIBUTION OF DIRECT AIDS TO THE PRODUCERS (FINANCIAL YEAR 2005) 1. FOREWORD The Commission regularly publishes the breakdown of direct payments by Member State and size of payment.

More information

Fiscal sustainability challenges in Romania

Fiscal sustainability challenges in Romania Preliminary Draft For discussion only Fiscal sustainability challenges in Romania Bucharest, May 10, 2011 Ionut Dumitru Anca Paliu Agenda 1. Main fiscal sustainability challenges 2. Tax collection issues

More information

Standard Summary Project Fiche

Standard Summary Project Fiche Standard Summary Project Fiche 1. Basic Information 1.1 CRIS Number: 2003/005-026.07.01 Twinning EE03-IB-AG-02 1.2 Title: Development of an IT System for administration of EAGGF Guarantee section Rural

More information

European Legislation 1. Indicative-Regulation (EU) No 1299/2013 of the European Parliament and of the Council of 17 December 2013 on specific

European Legislation 1. Indicative-Regulation (EU) No 1299/2013 of the European Parliament and of the Council of 17 December 2013 on specific European 1. Indicative-Regulation (EU) No 1299/2013 of the European Parliament and of the Council of 17 December 2013 on specific provisions for the support from the European Regional Development Fund

More information

Welcome and Introduction

Welcome and Introduction Welcome and Introduction Halfway through the programming 2014-2020 halfway through the programme spending? 22 February 2018 I Nice, France Iuliia Kauk, Interact Objectives Get an update on the state of

More information

EEA AGREEMENT - PROTOCOL 38C p. 1 PROTOCOL 38C{ 1 } ON THE EEA FINANCIAL MECHANISM ( ) Article 1

EEA AGREEMENT - PROTOCOL 38C p. 1 PROTOCOL 38C{ 1 } ON THE EEA FINANCIAL MECHANISM ( ) Article 1 1.8.2016 - EEA AGREEMENT - PROTOCOL 38C p. 1 PROTOCOL 38C{ 1 } ON THE EEA FINANCIAL MECHANISM (2014-2021) Article 1 1. Iceland, Liechtenstein and Norway ( the EFTA States ) shall contribute to the reduction

More information

Croatian Science and Technology System

Croatian Science and Technology System Croatian Science and Technology System Tome Antičić, Ph.D. Ministry of Science and Education 1 Strategic documents In 2014 the Croatian parliament adopted the Strategy of Education, Science and Technology

More information

Flash Eurobarometer N o 189a EU communication and the citizens. Analytical Report. Fieldwork: April 2008 Report: May 2008

Flash Eurobarometer N o 189a EU communication and the citizens. Analytical Report. Fieldwork: April 2008 Report: May 2008 Gallup Flash Eurobarometer N o 189a EU communication and the citizens Flash Eurobarometer European Commission Expectations of European citizens regarding the social reality in 20 years time Analytical

More information

Active Ageing. Fieldwork: September November Publication: January 2012

Active Ageing. Fieldwork: September November Publication: January 2012 Special Eurobarometer 378 Active Ageing SUMMARY Special Eurobarometer 378 / Wave EB76.2 TNS opinion & social Fieldwork: September November 2011 Publication: January 2012 This survey has been requested

More information

This note has been prepared by the Directorate-General for Regional Policy.

This note has been prepared by the Directorate-General for Regional Policy. COCOF 08/0006/00-EN EUROPEAN COMMISSION DIRECTORATE-GENERAL REGIONAL POLICY DRAFT INFORMATION NOTE TO THE COCOF MAJOR PROJECTS IN THE PROGRAMMING PERIOD 2007-2013: THRESHOLDS AND CONTENTS OF COMMISSION

More information

Evaluation of results and impact of EU funded investments in the field of employment during the programming period

Evaluation of results and impact of EU funded investments in the field of employment during the programming period Evaluation of results and impact of EU funded investments in the field of employment during the programming period 2004-2006 DEA Baltika Ltd. 24.08.2010.-21.03.2011. SUMMARY The assessment was carried

More information

Cross-border Cooperation Action Programme Montenegro - Albania for the years

Cross-border Cooperation Action Programme Montenegro - Albania for the years ANNEX 1 Cross-border Cooperation Action Programme Montenegro - Albania for the years 2015-2017 1 IDENTIFICATION Beneficiaries CRIS/ABAC Commitment references Union Contribution Budget line Montenegro,

More information

EUROPEAN COMMISSION. Observations on the Partnership Agreement with the Netherlands

EUROPEAN COMMISSION. Observations on the Partnership Agreement with the Netherlands Ref. Ares(2014)1617982-19/05/2014 EUROPEAN COMMISSION Introduction Observations on the Partnership Agreement with the Netherlands The observations set out below have been made within the framework of the

More information

COMMISSION STAFF WORKING DOCUMENT. on the assessment of root causes of errors in the implementation of rural development policy and corrective actions

COMMISSION STAFF WORKING DOCUMENT. on the assessment of root causes of errors in the implementation of rural development policy and corrective actions EUROPEAN COMMISSION Brussels, 27.6.2013 SWD(2013) 244 final COMMISSION STAFF WORKING DOCUMENT on the assessment of root causes of errors in the implementation of rural development policy and corrective

More information

12608/14 IS/sh 1 DG G II A

12608/14 IS/sh 1 DG G II A Council of the European Union Brussels, 2 September 2014 (OR. en) 12608/14 BUDGET 16 EXPLANATORY MEMORANDUM Subject: Draft budget of the European Union for the financial year 2015: Council position of

More information

REPORT ON WORK WITH THE PRE-ACCESSION-COUNTRIES (PACS) - Financial National Accounts, monetary and other financial statistics

REPORT ON WORK WITH THE PRE-ACCESSION-COUNTRIES (PACS) - Financial National Accounts, monetary and other financial statistics REPORT ON WORK WITH THE PRE-ACCESSION-COUNTRIES (PACS) In Spring 1996 Eurostat was requested by the Commission of the European Union to make arrangements, by end 1997, for the provision of adequate macro-economic

More information

PROGRESS TOWARDS THE LISBON OBJECTIVES 2010 IN EDUCATION AND TRAINING

PROGRESS TOWARDS THE LISBON OBJECTIVES 2010 IN EDUCATION AND TRAINING PROGRESS TOWARDS THE LISBON OBJECTIVES IN EDUCATION AND TRAINING In, reaching the benchmarks for continues to pose a serious challenge for education and training systems in Europe, except for the goal

More information

ANNEX PROTOCOL 38 B ON THE EEA FINANCIAL MECHANISM ( ) EU/IS/FL/NO/EEA/Annex/en 1

ANNEX PROTOCOL 38 B ON THE EEA FINANCIAL MECHANISM ( ) EU/IS/FL/NO/EEA/Annex/en 1 ANNEX PROTOCOL 38 B ON THE EEA FINANCIAL MECHANISM (2009-2014) EU/IS/FL/NO/EEA/Annex/en 1 ARTICLE 1 Iceland, Liechtenstein and Norway ("the EFTA States") shall contribute to the reduction of economic and

More information

State of play of CAP measure Setting up of Young Farmers in the European Union

State of play of CAP measure Setting up of Young Farmers in the European Union State of play of CAP measure Setting up of Young Farmers in the European Union Michael Gregory EN RD Contact Point Seminar CEJA 20 th September 2010 Measure 112 rationale: Measure 112 - Setting up of young

More information